PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN
"PROJECT ":"BIR EL MSANA FIELD DEVELOPMENT PROJECT "
"CONTRACT NO. ":"BMS-001 "
"LOCATION ":"BIR EL MSANA, Algeria "
"contracting ":"SONATRACH SPA / HESS (RHOURDE EL ROUNI) LIMITED "
"Authority " "/ PETRONAS CARIGALI OVERSEAS SDN BHD "
" "
" "
"0 "Mar. 14, "Approved for "Y. M. Kim"D.S.Bae "J.W. Lee " "
" "2012 "Design " " " " "
"REV."DATE "DESCRIPTION "PREPARED "CHECKED "APPROVED "APPROVED "
" " " " " " "BY CA "
" "
REVISION LOG
"REV. "REV. DATE "REVISED PAGE"MAJOR CHANGE DESCRIPTION "
"NO. " " " "
"A1 "Nov. 25, "- "Issued for Approval "
" "2011 " " "
"A2 "Jan. 27, "ALL "CA's Comment Incorporated "
" "2012 " " "
"0 "Mar.14.2012" "Approved for Design "
" " " " "
" " " " "
" " " " "
" " " " "
" " " " "
" " " " "
" " " " "
" " " " "
" " " " "
" " " " "
" " " " "
" " " " "
" " " " "
" " " " "
" " " " "
" " " " "
" " " " "
" " " " "
" " " " "
" " " " "
" " " " "
" " " " "
" " " " "
" " " " "
" " " " "
" " " " "
" " " " "
" " " " "
" " " " "
" " " " "
" " " " "
TABLE OF CONTENTS
1. PURPOSE 4
2. SCOPE 4
3. ABBReVIATION AND ACRONYMS 4
4. HSE LEADERSHIP AND ACCOUNTABILITY 4
5. HSE POLICY 5
6. HSE ORGANIZATION AND RESPONSIBILITIES 8
7. SUBCONTRACTOR 12
8. MANAGEment OF CHANGE 14
9. COMPETENCY ASSURANCE 14
10. INTEGRITY ASSURANCE 15
11. RISK EVALUATION AND MANAGEMENT 15
12. CONSTRUCTION SAFETY PLANNING 22
13. COMMISSIONING SAFETY PLANNING 24
14. START-UP PRECAUTIONS SAFETY PLANNING 25
15. HSE DOCUMENTATION 24
16. HSE TRAINING 27
17. PERMIT TO WORK SYSTEM 31
18. PERSONAL PROTECTIVE EQUIPMENT (ppE) 33
19. COMMUNICATION NETWORK 33
20. HSE MEETINGS 35
21. EMERGENCY EVACUATION PROCEDURE 37
22. FIRE PREVENTION AND PROTECTION 37
23. HSE AWARENESS 38
24. MANAGEMENT OF WASTE MATERIALS 38
25. WELFARE 41
26. IMPLEMENTATION AND MONITORING 42
27. AUDIT AND REVIEW 42
PURPOSE
The purpose of this Health, Safety and Environmental Plan is to
outline the scope of services and activities that shall be undertaken
in the Project HSE scope of the Bir El Msana (BMS) Project,
hereinafter referred to as the 'Project'.
This document describes Contracting Authority (herein after referred
to as 'CA') EHS Plan, CA EHS Management Plan, HYUNDAI Engineering
Co., Ltd. (Contractor) HSE Management System, and ensures that all
major hazards that could cause harm to people, environment or assets
have been identified, and suitable controls and risk reduction
measures are implemented so that the risk associated to the work is
as low as reasonably practicable (ALARP).
SCOPE
This Project HSE Plan is developed, based on the CA's requirements,
and is designed to describe how Contractor will manage and coordinate
their HSE operations during the Engineering, Construction,
Commissioning and Start-up Phase for BMS Project of the Contracting
Authority.
ABBREVIATIONS AND ACRONYMS
CA Contracting Authority (Bir El Msana – BMS).
CONTRACTOR Hyundai Engineering Co,. Ltd.
COSHH Control of Substances Hazards to Health.
EPC Engineering, Procurement and Construction.
HSE Health, Safety and Engineering.
HAZOP Hazard and Operations.
SIL Safety Integrity Level.
QRA Quantitative Risk Assessment.
SIMOPs Simultaneous Operations.
HEMP Hazard Effects Management Process.
JSA Job Safety Analysis.
PPE Personnel Protective Equipments.
PTW Permit to Work
HSE LEADERSHIP AND ACCOUNTABILITY
Contractor will ensure that all Contractor's personnel are briefed,
understand and strictly adhere to CA's policies and directives on the
health, safety and the environment.
Contractor will demonstrate leadership and commitment through
actively participating in all aspects of HSE management, supporting
open dialogue and by allocating sufficient resources to ensure that
the HSE requirements are met.
Contractor will ensure that HSE responsibilities, authorities,
accountabilities and competencies are clearly defined, documented,
communicated and exercised at all levels.
Contractor will ensure that individuals and team contributions to HSE
performance are recognized and considered during performance
appraisals.
Contractor will set clear HSE goals, objectives and targets and
ensure that performance is evaluated against them.
HSE POLICY
6 HSE Policy Statement
Contractor is committed to achieving the highest level of Health,
Safety and Environment (HSE) Management in all activities and
services it undertakes.
To comply with these commitments, Contractor will:
Establish and implement the HSE Management System.
Employ proactive measures on risk assessment and environmental
impact assessment, and establish controls across all of its
operations.
Comply with current applicable HSE legislation and welcome the
recommendations from interested parties that will positively
contribute to the safety of the Project, the Environment and the
Workplace.
Establish the HSE objectives and periodically monitor HSE
performance for continual improvement.
Educate employees and relevant Subcontractors' personnel in their
roles and responsibilities and train them to be competent for the
duty in order to achieve conformance to this policy.
Review on an annual basis and revise this policy as necessary to
ensure it remains relevant and appropriate to all requirements.
The HSE policy statement of Contractor is shown below.
7 Project HSE Policy Statement
Contractor will prepare, implement and maintain a Project HSE Policy
which shall contain a written statement of policy describing
Contractor's HSE Philosophy and Project HSE Objective. It shall be
communicated to all personnel and posted at prominent area. These
will be displayed at all contractor and sub-contractor sites.
8 Drug and Alcohol Policy Statement
Contractor shall have the right to prevent entry to the work site of
any persons suspected of being under the influence of drugs and/or
alcohol. The introduction of alcohol or illegal drugs on to the work
site shall be strictly prohibited.
Anyone found under the influence of alcohol or drugs shall be removed
from site.
All personnel will be advised on this Policy at their induction
briefing and that Contractor may carry out random testing on the
personnel on the project.
9 HSE Objectives
Contractor will incorporate the following objectives:
Identify all potential hazards associated with the execution of
the Project, and to develop prevention, control and mitigation
measures to eliminate or minimize harm to people, damage to plant
or equipment, or adverse impact on the environment.
Encourage the adoption of a positive, proactive, committed HSE
culture throughout all phases of the Project.
Achieve a target of zero fatalities and zero lost time injuries.
Minimize any impact on the natural environment.
Implement a management system with clear health, safety and
environmental objectives.
Review the management of HSE throughout the Project duration in
order to continuously improve performance.
Communicate all the above objectives to all personnel in the
Project.
To engineer a safe, reliable, operable and maintainable facility.
To create a work environment that fosters prevention of incidents
and delivers a goal of zero harm to people and property.
To ensure all parties carry out sufficient risk assessments to
cover all activities.
Minimize emissions and waste.
Maximize resources and energy.
Demonstrate no harm to the environment.
To meet host Government Legislation.
Management to conduct weekly site walk around to increase visible
commitment.
Effective HSE training.
Identification of all hazards.
Openness between CA, Contractor, Sub-contractor and workforce.
Effective and frequent HSE meetings.
Effective Reporting of Near Miss and Unsafe Acts.
Incentives for good HSE performance.
Tools equipment and PPE always fit for purpose.
Emergency Response Plans ensuring all incidents are controlled and
have limited impact.
Develop an Environmentally and Socially aware culture.
Effective communication at all levels to promote the ethos of zero
harm to people property and the environment.
Measure HSE Performance relative to continual improvement.
Perform scheduled audits : Internal; External; Corporate;
Technical.
The aim of Contractor is to complete the Project achieving the HSE
target of zero fire and zero fatal accidents.
HSE ORGANIZATION AND RESPONSIBILITIES
11 HSE Organization
Responsibility for HSE permeates to all levels within the
organizational structure of the Project, and the Contractor down to
each subcontractor and supplier. Coordination and cooperation between
and across these levels is aided through the use of a site HSE
committee comprised of Contractor and subcontractor site management,
field supervision and employees.
12 Project Manager
Has the project responsibility and authority for ensuring that the
specific HSE requirements are identified, defined and fulfilled.
These are defined in the project specific HSE plan/process maps/work
methods and procedures. Also he's responsible for ensuring all of his
management team which includes the Construction Manager, Pre-
commissioning Manager and Engineering Manager, Procurement Manager,
is meeting their HSE objectives and for attending on a regular basis
project HSE Committee meetings and recording the findings.
Responsibilities also include:
Ensuring adequate HSE resources are available to implement HSE
on the Project
Chairs HSE meetings
Supporting the application of the HSE Management System
13 Project HSE Manager
The HSE Manager establishes the safety control procedure based on
CA's safety manuals, Governmental and CA's requirements to prevent
possible accidents arising at site. Safety Officers will be assigned
for safety assurance and control.
The HSE Manager and his staffs will take necessary actions to
maintain the facilities in a safe condition and instruct all site
personnel to realize the importance of safety and to observe the
safety rules. The HSE Manager always keeps close working association
with the respective Construction Superintendents and draws their full
attention towards accident prevention and safe working practices. The
followings are the few of the specific responsibilities of the HSE
Manager.
Establishing field safety program.
Adopting and applying standard safety practices, procedures,
techniques and method.
Establishing field security programs and making every possible
arrangement for good implementation according to the program.
Conducting initial orientation and regular safety meetings to
ensure familiarization of all concerned party with safety
requirements and to maintain safety consciousness and accident
prevention measures.
Determining the legal requirements for protecting worker and the
public from accidents and health hazards.
Providing a comprehensive program which will ensure the
protection of life and property and fostering construction
efficiency through selective use of safe work practices and
through the establishment and maintenance of safe working
conditions.
Supervising whether the work is performing in accordance with
recognized safety standards, codes, statutory and/or local
regulations, which may already exists or may come into force at
later stage.
Conducting Accident/Incident investigations using Root Cause
Analysis.
Coordinate with CA and Contractor Medical Teams to ensure
compliance with expectation.
14 Site HSE Manager
Coordinates with the Project HSE Manager and reports to the
Construction Manager. He is responsible for reviewing, monitoring,
auditing and reporting on the performance of the HSE activities and
performs audits directly or through specialists assigned from the
corporate organization at his request. The Site HSE Manager will
coordinate with the Construction Manager, Construction Supervisors,
Quality Assurance and Quality Control to ensure that the work is
being performed as required by the project HSE documents and
procedures. Specifically, he will review and approve method
statements and Permit to Work requests. In addition he is responsible
for:
Ensuring all HSE activities on site are in accordance with this
Construction Safety Plan and the Construction HSE Reference
Manual.
Ensuring all subcontractors/suppliers and visitors on site
comply with project HSE requirements.
Coordinating with the CA Site HSE Representatives to establish
meetings, training, assessments, etc
Ensuring construction activities comply with all Algerian
Legislation.
HSE training/inductions and awareness training and hazard
Identification.
Ensuring Risk Assessments are carried out for all potentially
hazardous activities.
Notifying directly to the Project HSE Manager any HSE concerns
with reporting responsibility to the Construction Manager.
Preparing or amending the necessary work methods and procedures
for working safely at site.
Implementation of the Transportation Policy and Standards
Ensuring all medical resources is in accordance with project
requirements
Ensuring all Emergency Response planning is in accordance with
project requirements and that ER training is carried out.
Develop, maintain and implement site Emergency Response Plan.
Also make planning for emergencies with the Site Manager
Responsible for accident investigation and reporting
Reporting site HSE Inputs and statistics to CONTRACTOR Corporate
HSE Department on a monthly basis
Responsible for site safety, security and labors health
Application of HSE on site on behalf of the Construction Manager
Line management of the HSE Department
Improvement of HSE awareness and culture
Advice to Construction Manager on HSE issues
Administration and application of the safety incentive scheme
Cooperation and coordination with the CA's Safety Audit
Review and implement the approved Safety Audit recommendation
performed by the CA.
Conduct scheduled inspections and HSE audits of all work areas
and advising managers / area supervisors on unsatisfactory
conditions or practices being observed.
Develop, maintain and implement site Traffic Plan in
coordination with Construction Manager.
Shall report administratively to CONTRACTOR HSE Manager and
functionally to Construction Manager
15 Construction Manager
Responsible for ensuring all construction activities are completed in
accordance with the project HSE objectives and that all of his line
management is suitably competent and trained in the same. He is
responsible for ensuring that all managers, supervisors and
designated subcontractor personnel reporting to him attend all
required HSE meetings and training and comply with/support all HSE
activities including:
The Construction Manager will also have the overall responsibility
for constructability and plot plan and layout reviews for
construction safety aspects. Under his authority, the construction
supervisors will implement the CONTRACTOR HSE policy in the daily
activities.
Promoting the implementation of the HSE Plan by personal example
Ensuring that safe construction equipment, tools and personal
protection equipment and sufficient facilities for welfare, first
aid and sanitation are available and used.
Applying for Permits to Work
Instructing the personnel working under their supervision to
establish work methods, to plan the sequence of operations, to
outline potential hazards at each stage, and to indicate
precautions to be adopted.
Checking work methods for newly started and major activities
before work starts.
Creating safety awareness by holding safety meetings and talks
16 Field Engineers and Supervisors
Field Engineers and Supervisors shall generally assist the
Construction Manager/Section Manager in the execution of their
duties. Field engineers and supervisors' general responsibilities
include, but are not limited to:
Being familiar with the requirements and recommendations for Safe
Working Practices and Method Statements etc. applicable to their
work place and ensure that they are enforced.
Incorporating HSE instructions into the routine day to day orders
and make sure they are understood and obeyed.
Preventing site persons from taking unnecessary risks.
Ensuring that all employees and sub-contractor's personnel are
suitably trained for the work in which they will be engaged.
Ensuring that all employees and sub-contractor's personnel adopt
correct HSE precautions.
Checking that all plant and equipment, including power and hand
tools are maintained in a good condition and remove from use any
defective items.
Maintaining organized tidy and safe working areas.
Maintaining all welfare facilities in a clean and safe condition.
Ensuring that all operators/labor are provided with and use
approved personal protective equipment.
Ensuring that instructions are given in the use of any potentially
hazardous materials.
Discouraging horseplay and take actions against those who
consistently fail to take care of their own Health and Safety and
of other persons working with them or in the vicinity.
Stopping any activity on site if there is an immediate risk of
injury to any site personnel, or the possibility of a dangerous
occurrence happening.
Participate in any accident/incident investigation.
17 Worker's Responsibility
Workers shall report to work in a fit and proper condition to perform
their job in a safe and competent manner.
Workers shall observe and follow all established site HSE rules and
safe work practices. They shall adhere to all work directives and
procedures for the tasks assigned (whether provided orally or in
writing).
The use of personal electronic equipment such as hand phone,
radio/tape sets shall be strictly prohibited at the site.
Workers can have 'STOP Work authority' for each worker if the person
observes unsafe situation.
Workers shall report immediately any unsafe act or condition observed
to a supervisor.
SUBCONTRACTOR
19 Subcontractor Selection and Interface Management
Each subcontractor has the primary responsibility for the safety of
the activities of its own employees in conformance with CONTRACTOR
HSE requirements. The subcontractors will be required to
Have in place/adopt HSE, plans and procedures matching project
requirements
Implement the CONTRACTOR HSE Plan for Construction,
Comply with CA/ CONTRACTOR HSE procedures, and
Prepare method statements and Pre-task Planning and Risk Analysis
as required by CA and CONTRACTOR.
Identify the PPE requirement from CONTRACTOR HSE team and comply
with it.
CONTRACTOR will interface and manage subcontractors through pre-
bid/award and kickoff meetings, weekly progress and performance
reviews (including a review and trending of HSE matrix). This will
also be facilitated by establishing a close working relationship
between all Subcontractor HSE personnel and CONTRACTOR HSE personnel
(Site HSE Committees, weekly meetings, assistance with HSE Toolbox
Talk materials, etc) and through involvement of Subcontractor's in
all sites HSE programs, inspections, meetings, and celebrations of
success initiated on site.
CONTRACTOR will when preparing all contracts and purchase orders
attach HSE requirements to ensure HSE requirements are complied with.
20 Managing Subcontractors
All subcontractors involved in the work will submit their own HSE
program before contract with CONTRACTOR.
CONTRACTOR will ensure that each subcontractor understands and
follows the HSE Management System for this Project prior to
mobilizing to site.
CONTRACTOR will ensure that the applicable HSE procedures are
communicated to the CA, subcontractors.
21 Working with Subcontractors
CONTRACTOR will assess the capability of those who work on
Contractor's behalf to operate approved standards and monitor their
performances.
CONTRACTOR will work with subcontractors to encourage a responsible
and effective approach to HSE and security management.
They are to align with Contractor's system wherever practical and
possible.
22 Discipline to subcontractors
All employees in the Project will comply with the HSE and security
management rules and regulation of the Project.
Any employees who violate HSE and security work practices and
procedure repeatedly or seriously will be removed from the
project/worksite.
23 Subcontractor Construction Manager
Subcontractor construction managers will provide their workers with a
safe and healthy working environment. They will be responsible for
promoting safety and health consciousness among their workers at all
times. They will be held accountable for enforcing:
Subcontract requirements for HSE
Provision of adequate and safe construction equipment and tools,
and personal protection equipment for their workers
That construction work is executed in the safest manner and
follows a planned work sequence and procedures.
Inspections of the work area to ensure that the entire work area
is maintained in a safe and healthy condition
Supervisors take immediate corrective actions for any infractions.
The holding of subcontractor safety meetings
Actions required as a HSE Committee member.
24 Subcontractor Safety Officers
The subcontractor safety officers will:
Implement and coordinate with CONTRACTOR HSE requirements within
their respective work groups under CONTRACTOR overall supervision
and direction.
Become familiar with and comply with all Algerian Laws and
regulations, Company, and CONTRACTOR HSE requirements, plans and
procedures, including reporting and work permit procedures.
Inspect construction areas and prepare reports and corrective
action lists.
Organize CONTRACTOR, Company, and subcontractor safety meetings,
training and tool-box meetings.
Subcontractor shall provide a sufficient number of qualified, full-
time and dedicated field safety officers to support the Site HSE
Plan.
25 Subcontractor Supervisory Personnel
It is the responsibility of the subcontractor supervisors and foremen
to ensure that their workers strictly adhere to the HSE procedures in
their specific work and work areas. They shall promptly correct any
unsafe conditions.
They shall attend and actively participate in all required
orientation, training sessions and meetings. They shall be cognizant
of their positions as safety role models for their workforce and act
accordingly.
MANAGEMENT OF CHANGE
The Contractor continuously manages, monitor and assess changes in
designs or procedures that could potentially affect EHS performance.
Of primary concern to the CA is the possibility of changes being
undertaken that impact on hazards and/or their potential effects.
The Contractor's change procedure shall ensure that any change
proposal is reviewed by the Contractor's EHS specialists prior to its
implementation and the Contractor shall provide the Contracting
Authority with a report of each such change insofar as it is
associated with the Contractor's performance of the Contract. Any
change that involves safety critical equipment shall be referred to
the Contracting Authority Representative for review prior to
implementation.
The Contractor shall implement procedures to cover changes to
conditions or processes on each Worksite. Any change that may affect
the health, safety, environment or security at a Worksite shall be
covered by a procedure that ensures that all Personnel at that
Worksite are made aware of the implications for their conduct at the
Worksite.
COMPETENCY ASSURANCE
The Contractor make provision for ensuring that all Contractor's
Personnel are suitably qualified, appropriately trained, experienced
and familiar with the work they are to perform.
Prior to commencing Work at any Worksite, the Contractor shall
demonstrate to the satisfaction of the Contracting Authority that all
of its Personnel have successfully completed essential training to
ensure competence and safe performance of duties appropriate to the
parts of the Work being performed.
Prior to awarding any sub-contract, the Contractor shall have a
process to assess sub-contractor's ability to comply with these EHS
requirements and can demonstrate that all sub-contractors are
suitably qualified, appropriately trained, experienced and familiar
with the Work they are to perform. Upon request by the Contracting
Authority, the Contractor shall provide evidence of such assessment
prior to the bid award. The Contractor is ultimately responsible for
the performance of any sub-contractor and must ensure all sub-
contractors agree in writing to abide by the Contracting Authority's
EHS requirements.
Contractor identifies inexperienced personnel so that others take
precautions in their presence. Any Contractor personnel with less
than six months of service in the same job/position with his/her
present employer will be considered a Short Service Employee (SSE).
The SSE(s) shall have a mentor assigned to the work site to provide
consistent coaching, feedback, and oversight while employees develop
skill sets to conduct their job tasks safely.
INTEGRITY ASSURANCE
The Contractor has responsible for assuring the underlying integrity
of any equipment or systems developed and/or used in the Contractor's
performance of the Contract. The Contracting Authority expects that
integrity will be primarily assured by the Contractor's effective
application of internationally recognized codes and standards and an
appropriate quality management system.
RISK EVALUATION AND MANAGEMENT
Risk Management shall be performed before any work commences by all
relevant project personnel, all subcontractor organizations and on
all worksites where hazards have been identified or potential hazards
are thought to exist.
30 Safety Planning and Coordination
The safety planning will start with the mobilization of the Project
HSE manager and the preparation of the Subcontracts packages.
As members are assigned to the HSE Group, they will familiarize
themselves with the site conditions and analyze the construction
planning and construction equipment and resources, under the
responsibility of the Project HSE Manager.
The Project HSE Manager will identify and list:
The work areas close to the existing facilities and, therefore,
requiring work permits.
Activities requiring a Job Safety Analysis (JSA) and
recommendations on how to carry out the work.
These lists will be issued for review to CA.
The results of the safety planning will be published and discussed
at the safety meetings, pre-construction meetings and kick-off
meetings with the sub-contractors.
31 Hazard Recognition and Control
HEC structured processes to be utilized during the planning and
execution phases of the work to identify, assess, and eliminate /
control potential work site hazards includes the following:
Project HSE Plan
Site HSE Plan
Construction Hazard Analysis
Methods Statements
Job Safety Analysis
The identification and evaluation of hazards and environmental issues
at the various stages of the Project and the development of control
measures is part of the HSE management system.
The Project will use the Site HSE Plan as the basis for site HSE
Planning for identified risks/hazards. The project policy commits all
personnel to ensure that prior to starting any task a risk assessment
is completed. The risk assessment has the prime purpose of
identifying the hazards associated with the task, who can be hurt and
both that the appropriate controls are in place and the risks are
reduced to as low as reasonably practicable.
As an outcome of the hazard analysis, subcontractors shall be
required to prepare JSA that address the tasks to be performed. Then
as part of the two week look ahead, the tasks shall be planned and,
equipment and personnel resources shall be identified and JSA
developed.
Thereafter ongoing risk assessment, minimize residual risk, hazard
identification and elimination are achieved at the task level during
the construction phase through inspections and audits.
32 Engineering
The Safety Design Philosophy has been established as a separate
document (0304-LB-100) to ensure compliance with CA's HSE Management
Systems, Contract requirement and relevant legislation in Algeria
from engineering stage and it provides controls for the managements
of the Project HSE Risk to a level that is As Low As Reasonably
Practicable (ALARP).
1. Risk Assessment
The identification, assessment and management process shall be
regulated by specific procedures, developed based on the plant
characteristics, location, applicable legislation, and CA's
requirements.
Risk identification, assessment and management of Engineering shall
be an integral part of the safety engineering activities. Tools to be
used include:
Review and update of studies conducted during the FEED phase of
the project, such as HAZID and P&ID safety review study
HAZOP, SIL/LOPA Study
Design reviews, such as 3D Model Reviews
Safety reviews, such as QRA, Emergency Events and Consequence
Assessment, Safety Case etc.
Constructability reviews
Check lists
Management of Changes
2. Contractor HSE Management
Contractor is committed to design the plant to meet industry standards
of which HSE is a key element. The relevant Contractor engineering
standards along with the project design criteria (Specifications,
Drawings and documents) will be applied as the minimum HSE engineering
standard for this Project
HSE Manager will be responsible for ensuring that HSE is applied as
per the relevant project specifications, procedures, international
codes and standards. It is the individual Lead Engineers and Engineers
responsibility to apply the HSE standards and design the plant to meet
modern standards.
3. Identification of Hazards and Effect
Early identification, analysis and evaluation of risks are important
to enable Contractor to take preventive measures. The target is to
reduce the exposure to an acceptable level and to execute tasks
according to the applicable norms and regulations.
In the Process Safety Management structure, which provides a framework
of organizational structure, procedures and practices used to manage
and reduce risks in order to prevent the consequences of catastrophic
releases of toxic or explosive materials, Hazard Identification
Reviews are essential tools to conduct organized, systematic and
documented assessments to identify and analyze the potential hazards
associated with the production process.
The following methodologies will be applied in the Project development
phase:
( HAZOP (Hazards & Operability) Review
( SIL (Safety Integrity Level) Study
( QRA (Quantitative Risk Assessment) including Fire and Explosion
Hazard Analysis
( Emergency Events and Consequence Assessment
( RAM study
( Safety Case
( Safety Critical Elements and Performance Standards
( Escape and Evacuation Study
( Alarm Rationalization Review
All procedures used to execute the above methodologies will comply
with CA' Standards.
33 Construction
4. Risk Assessment
As for Engineering, the identification, assessment and management
process shall be regulated by specific procedures, developed based on
the plant characteristics, location, applicable legislation, and CA's
requirements, shall apply.
Risk identification, assessment and management in Construction shall
be an integral part of the construction activities, starting from the
planning at the Home Office. The following tools shall be used
Review of the studies conducted during the engineering phase of
the project
Participation in the 3D Model Reviews and Building Reviews
Constructability reviews
Check lists
Job Risk Analysis
Pre-start check list
Workshops for specific areas of risks or hazards including SIMOPS
Based on the results of this process at the Home Office, the methods
of construction and type of equipment to be used are selected and the
documentation to be prepared, identified.
During construction, risk identification, assessment and control
shall be regularly carried out as part of the pre-job risk analysis,
and the preparation of method statements. Specific construction risk
assessments shall be conducted by HEC with the participation of CA
and Subcontractors for such items as heavy lift, concurrent
construction of different disciplines (e.g., as civil works and
piping) in the same area at different elevations, confined space
work, radiographic examination at the Site, hydrostatic testing and
SIMOPS.
5. HSE Management
HSE management and safe working practices to be considered for
transition phase since activities will be occurring without operating
facility. That is Construction /Commissioning/ Startup activities
will be going on at the same time.
The Site Manager has responsibility for HSE during the construction
phase. He is assisted in the implementation of HSE by the Site HSE
Manager. HSE is everybody's responsibility and the Site Manager will
ensure that all members of the Project understand their duties.
6. Identification of Hazards and Effect
The Contractor shall adopt various HEMP techniques to identify hazards
in construction and completion phases to assess their likelihood and
consequences. The analysis shall be used in implementing control
measures to manage the risk effectively.
Construction site risk will be identified and mitigated in a planned
manner that will be established before commencement of construction
work.
Job Safety Assessment and other industry standard methods will be
implemented to assess the hazards and identify the relevant controls
required to control the risks.
Job Safety Analysis (JSA)
Control of Hazardous Material
Preparation and implementation of relevant site HSE procedure
Implementation and monitoring of effective general workplace
practices
Implementation of Permit to Work (PTW) system given by the CA
Effective site supervision
Preparation of hazardous chemicals and dangerous goods/materials
inventory
7. Job Safety Analysis (JSA)
Contractor will perform JSA to analyze the individual steps of a
particular job and identify the hazards and risks involved in each
step so as to develop ways to minimize or eliminate them as below
sequence.
Select the job to be analyzed with consideration of "Frequency of
Accident", "Severity Potential", "New Work Operation", "New Job"
and "High-rated Job"
Break the job down into a sequence of steps, each describing what
to do.
Identify Hazards and Potential Accidents which are associated with
job step
Decide what control measures or job procedures are necessary to
eliminate or minimize the hazards.
Perform education for involved employees and ensuring the
implementation of control measures.
HEC supervisors or Subcontractors will develop and perform a pre-task
job safety analysis in order to set out clear procedures and safety
requirements for new activities and those hazardous activities listed
by the Site HSE Manager.
The JSA is a step-by-step analysis of the work to ensure that all the
hazards are identified and the necessary precautions are taken into
account to eliminate or isolate the hazards of the work to be
performed.
A standard form will be used for recording the results of the
analysis. Depending on the complexity of the activity analyzed, more
than one sheet, additional information and diagrams or Material Safety
Data Sheets (MSDS) may be attached.
The supervisor will present the JSA to the work crew who will carry
out the work to ensure that they understand the risks involved and the
work methods to be applied.
34 Hazards Effects Management Process (HEMP) (Explain HEMP briefly)
Activities of all personnel having access to the workplace
(including Subcontractor, workers, visitors and CA).
Facilities of the workplace to be provided by Contractor or others.
Contractor will ensure that the results of these full and
systematic assessments and the effects of the control measures are
considered when setting / reviewing/ revise / updating HSE
objectives.
35 Control of Substances Hazardous to Health (COSHH)
The control of substances hazardous to health is recognized as a
critical element of the safety program and will be achieved through a
combination of hazard communication, establishment of HSE systems of
work and controlled handling and disposal of such substances.
All activities within the site will be carefully and systematically
evaluated for potential health hazards to provide comfortable working
circumstance and the preservation of good Health and Hygiene
Practices.
Methods such as systematic inspections, interviews and
questionnaires, and follow up by technical sampling of the employees
on location will assist in identifying and assessing hazards.
A Health Risk Assessment shall be conducted to identify and evaluate
the following health hazards:
Chemical Hazards
Noise Hazards
Radiation Hazards
Illumination Hazards
Vibration Hazards
Temperature Extremes
Ergonomic Hazards
Other surveys will be conducted as necessary.
The health hazard control measures will be established during
planning of Plant / facilities and improved according to necessity
during the construction phase.
The principal health hazard controls are:
Elimination of hazards
Substitution of safer substances and/or devices
Engineering control, such as improvement of operation, providing
safeguards, ventilation, etc.
Administrative control, such as providing proper work procedures,
observation of HSE requirements and rules, etc.
Ensuring all exposed personnel wear and use proper Personal
Protective Equipment
The control system commences at the procurement stage, at which all
vendors and Subcontractor will be required to submit Material Safety
Data Sheets for all hazardous substances that they will be supplying.
Copies of these data sheets (including methods of treatment of
injuries sustained by hazardous substances) will be forwarded to the
Site HSE Manager who will retain a master file.
Subcontractor will be required to carry out assessments in co-
ordination with the Site HSE Manager and Field Supervisors
(Commissioning Engineers) and in compliance with recognized
standards.
Only when all parties are satisfied there are no suitable alternative
safer materials, and, that the control measures are adequate, will
the materials be permitted on the worksite and used.
Such control measures will address transport, storage, labeling,
packaging, handling, disposal, personnel protective equipment and
emergency procedures and training therein.
Persons using such substances will be trained/ informed on acquainted
with the associated hazards and the necessary control measures
through pre-task instruction and ready availability of method
statements and data sheets.
The hazardous substances covered will also include products from
construction processes (such as welding fumes and solvent vapors).
The disposal of waste material will also be considered, e.g. spent
lubricating oil.
Storage of hazardous substances on site will be kept to a minimum, as
agreed by the Contractor.
The requirements of Control Procedure of Substances Hazardous to
Health (to be developed later) will apply.
36 Environmental
The most effective way to manage the environment is to avoid
spillages. Where this is not entirely possible mitigation measures
will be put in place.
The Project HSE Plan contains further details on environmental
management needs and will be read in conjunction with this
Construction HSE Procedure.
The Contractor and its Subcontractor will follow Project soil erosion
control plans that are in place to identify and address appropriate
erosion control measures.
The Contractor and Subcontractors will comply with CA's ESIA and will
adopt the specific procedures.
37 Environmental Requirements and Protection
These reports identified the environmental sensitivities and impacts
relevant to this Project and to protect the environment by a
hierarchy of measures based on firstly prevention, followed by
mitigation or compensation.
These measures define the environmental requirements.
38 Impacts and Environmental Assessments
These assessments will be used in the preparation of permit
applications for the disposal of construction wastes, both solids and
liquids, and permits related to the disposal of excess soil, to
ensure full control of any environmental impacts, during the
construction phase.
39 Air Emissions
Emissions during construction and commissioning will arise from the
vehicles used for transportation and from the diesel generators.
Dust and noise surveys will be carried out in the vicinity of the
construction site. The Contractor will carry out surveys.
Countermeasures for construction emissions are as follows:
All internal combustion engines will be suitably serviced and
maintained to reduce polluting emissions.
Dust control will be accomplished by properly wetting the work
area by water truck, etc., prior to commencing the work and/or
other approved measures.
40 Pre-commissioning and Commissioning
8. Risk Assessment
The identification, assessment and management process for Engineering
and Construction shall be regulated by specifically developed
procedures based on the plant characteristics, location, applicable
legislation, and CA's requirements shall apply.
Risk identification, assessment and management shall be an integral
part of the pre-commissioning and commissioning activities. Based on
the results of this process at the Home Office, the Pre-commissioning
group may propose changes in design (pre-commissioning and
commissioning in, or close to, general construction areas or punch
listing in pre-commissioning and commissioning areas), for example
addition of isolation valves. The following tools shall be used
Review of the studies conducted during the engineering phase of
the project, such as QRA
Participation in the 3D Model Reviews
Constructability reviews
Check lists
Job Risk Analysis
Pre-start check list
Job Task Analysis
Health Risk Assessment
Workshops for specific areas of risks or hazards
At the Site, risk identification, assessment and control shall be
regularly carried out, in particular for the coordination between the
pre-commissioning and commissioning crews and the construction crews
working in, or closed to, areas that have been energized. Specific
risk assessment workshops shall be conducted by HEC with the
participation of CA and Subcontractors for such items as energization
of the facilities and introduction of hydrocarbons. The results of
the workshops carried out before the start of construction, i.e.,
recommendations and action items, shall be regularly reviewed by the
Pre-commissioning Manager to ensure that the assumptions made at the
workshops on the working areas and the construction schedule are
still valid.
CONSTRUCTION SAFETY PLANNING
42 Crane/Lifting Equipment/Lifting Gear
Risks associated with lifting are significant and, coupled with the
considerable scope of such activity, represent a substantial area of
potential loss exposure.
Consequently, the Contractor will utilize stringent control on both
the lifts themselves and the hardware involved.
Therefore, all cranes, Hiabs, piling rigs, etc., will be inspected,
load tested and all certification checked by the Contractor prior to
entry onto the worksite.
The Heavy Lift Supervisor will maintain records of such inspections.
All proposed Subcontractor prior to mobilization would assess
crane/lift operators for competency and ensure that all certification
is valid for the equipment being used.
This will comprise the submission of a valid national operators
license and also the successful completion of a local competency
test.
All lifting equipment to be added to the Contractor's lifting
register and Colour Coded based on 6 month inspections/re-
certifications by a competent person.
If successful, operators will only be permitted to operate the
equipment for which they have been assessed.
43 Temporary Electrics
Contractor will prepare site specific procedures defining electrical
safety requirements and precautions for those employees working near
electrically operated equipment tools, or with cause to work on or
near electrically operated equipment tools, or with cause to work on
the construction power supply system.
9. Electrical Hazards:
The construction site will present a number of potential hazards
from the use of electrical tools and equipment and the electrical
power supply which extends throughout the work site and each of the
working areas.
The hazards from electrical fault or mishap on the construction site
are severe and ever present. They include:
Electrocution or electrical shock which may kill or cause
serious injury.
Overhead electrical conductors may cause burn injury and ignite
flammable materials.
Switching or sparking of ordinary electrical equipment in
flammable atmospheres may cause fires and explosions, even a
small spark from a battery operated appliance may have
sufficient energy as a source of ignition.
Electrical arcing and flashover from improperly operated
switches, etc. may cause burn injuries.
Accordingly, proper care will be exercised when installing,
operating and working around such electrical equipment and systems
on the site.
10. Electrical Safety Measures:
The electrical safety procedures to be applied on site and will
include training/orientation of both Safety Supervisors and the work
force in the hazards that can be encountered and the safe working
measures needed to protect against injury or damage
44 All Vehicles And Traffic Control
Traffic on the worksite will be minimised so as to avoid unnecessary
hazards and congestion at the workplace, with entry onto worksite
being controlled via the issue of vehicle passes.
Speed limits will be enforced by the Contractor Security Department.
Specific accesses and egresses for pedestrians will be maintained at
all times, as will routings for emergency vehicles. Any vehicle
wishing to block roads for any period of time will first obtain a
road closure permit from the Contractor.
Subcontractor will be made aware of all such closures and heavy
equipment routings at Subcontractor daily HSE meeting.
The Contractor and Subcontractor will develop Road Safety Policies to
minimize possibilities of traffic accidents on the public highway,
e.g.:
Driving times
Age
Driving hours
Route and resting plan
45 Welding and Heat Operation
The purpose of this welding and heating operations instruction is to
outline the Safety requirements for managing and controlling
operations involving the use of welding equipment on this Project.
The main hazards likely to be encountered during welding and burning
processes can be identified as follow:
High Temperature causing risk of fire and burns.
Fumes emitted from the process likely to cause injury to health.
Radiation causing 'arc eye' and burns.
Oxygen deficiency or enrichment, particularly within an enclosed
space.
Electric shock
Explosions during the welding and cutting of drums, tanks or
vessels which have contained flammable materials.
These instructions provide general considerations for the control and
use of welding and burning plant and equipment used on site which is
based upon Permit to Work Camps, Offices.
Fire watchers shall be placed whenever welding or cutting is
performed in locations where a risk assessment shows an increased
likelihood.
46 Excavation Procedures
Excavation procedures(0304-ZB-136) will be developed to address soil
classification, benching, shoring, air sampling, and entry and exit
routes, spoils location, and traffic and equipment management.
COMMISSIONING SAFETY PLANNING
Commissioning Group will pay particular attention to identify any
additional flanging, spading or valve isolation requirements to
ensure the integrity of live systems in an area where construction
work is still being carried out.
Development of diesel and water management plans, and waste disposal
procedures will be carried out.
The safety and welfare of the work force and the need to protect
equipment must be considered paramount and highlighted in any work
permit that is issued.
48 Work Permit Control
a) Once a system has been handed over from Construction to
Commissioning and comes under the care and custody of
Commissioning, the Commissioning Manager will be responsible for
issuing work permits that will govern all activities to be
carried out in the areas being commissioned.
b) A Permit Office will be provided to manage the issue regarding
the Work Permits.
49 Prevention of Contact
"Ingestion "Eating and drinking will be only allowed in designated"
" "areas. "
"Skin Contact"Measures must be taken to prevent hazardous materials "
" "from contacting the skin and provide first aid or "
" "medical treatment in the case of accidental contact. "
" "Non-porous gloves and goggles are minimum "
" "requirements. "
"Burns "All process equipment in accessible areas operating at"
" "temperatures above about 70oC is normally insulated to"
" "ensure personnel protection. Lines and equipment in "
" "cryogenic service are also insulated for heat "
" "retention and for protection against cold burns. "
" "General-purpose gloves will be worn. "
"Eye Contact "Eye irritants can cause permanent damage to the eye "
" "very rapidly. All eye injuries will receive immediate "
" "medical attention. Eye wash bottles and water coolers "
" "will be located on plant against recognized approved "
" "standards where materials such as acids, alkalis, "
" "amines can be encountered. Safety glasses must be worn"
" "and goggles must be worn on the helmet in all "
" "commissioning areas. "
50 Maintenance of Safety Equipment
All safety equipment will be checked on a monthly basis and must be
maintained in a condition ready for use.
Fire extinguishers must be checked at monthly intervals and recharged
or replaced immediately after use. All air and water hose equipment
must be returned to their original place after use. Access to such
equipment must not be obstructed. When a fire extinguisher is used
the occurrence of a fire will be reported in an incident report.
No work on any live equipment will be done without a properly
authorized permit to work issued by the Commissioning Manager or his
designees.
51 Housekeeping
Loose materials etc., will never are left in a manner causing a
tripping hazard on platforms, access ways, etc.
Access to ladders and fire escapes must be kept accessible at all
times. Waste and refuse must be put in proper designated areas or
containers.
START-UP PRECAUTIONS SAFETY PLANNING
53 Work Permit Control
All work will have a Work Permit issued by the CA operations. All
conditions on the work permit will be strictly adhered to such as
fire extinguishers to be in place and drainage systems covered.
54 Emission to Atmosphere
Hot liquids or vapours must never be discharged directly to the
atmosphere. All measures must be taken to prevent or control
emissions. Where temporary noise pollution exceeds 85 dBA, temporary
silencers will be used.
55 Toxic Gases
Vessels may contain highly toxic gases. Inert gases such as nitrogen
pose a particular hazard of asphyxiation. Extreme care must be taken
in the venting purging, cooling and opening of such equipment.
56 Working Practices
1) No burning, welding, cutting, grinding, or other hot work will be
allowed in live areas unless properly authorized by a permit to
work issued by the CA Operation representatives.
2) No person will be permitted to work within a flammable
atmosphere. Where appropriate proof tested flammable gas detector
of calibrated will be employed to minimize the risks from any
leakage by providing adequate warning.
3) Authorized personnel in compliance with a permit to work will
only work electrical equipment on.
4) Do not use hydrocarbons to clean machinery or for any other
cleaning purposes. Use a permitted cleaning agent instead.
5) When pressurized systems are to be worked on a procedure with a
method statement must accompany the work permit.
6) Environmental requirements for collection of cleaning agents to
be determined
7) Guards around moving shafts or couplings, which have been removed
must be replaced when repair work is completed and before
equipment is energized.
8) During flushing or air blowing, areas where liquids or gases are
exiting must be barricaded off and warning signs, written in
English and local languages displayed.
HSE DOCUMENTATION
58 General
The HSE documentation consists of the following:
Project HSE Plan, this document
Confined Space Entry Procedure (0304-ZB-118)
Site Health, Safety and Environment Plan (0304-ZB-124)
Emergency Response Plan (0304-ZB-128)
Environmental Management Plan (0304-ZB-132)
Work at Height Procedure (0304-ZB-134)
Incident Reporting and Investigation (0304-ZB-135)
Occupational Health Policy and Procedure (0304-ZB-137)
Health Risk Assessment (0304-ZB-138)
HSE Schedule and Indices (0304-ZB-139)
Safety Management Plan (0304-ZB-142)
Project HSE Audit Procedure and Plan (0304-ZB-143)
CA Procedures and Requirements. These procedures shall be
followed by HEC as per contract agreement with CA
59 Documentation Hierarchy
. The hierarchy of the HSE Documentation is as follows:
Laws and Regulations of Algeria
Contract between CA and Contractor
CA Project Specifications and Mandatory Procedures
Contractor HSE documentation, plans and procedure
Project Management Directives
Internationally recognized standards for items that are not
adequately covered by regulations or project requirements
HSE TRAINING
61 General Information
Contractor will establish and provide the essential resources
(human, technical and economic) to ensure the implementation,
control and improvement of the HSE system.
The CA is the main reference for Contractor and subcontractor HSE
training requirement.
Therefore, Contractor will establish the necessary means are taken
to ensure that any person working for the Project has, but are not
limited to:
Their HSE functions and responsibilities clearly defined.
The necessary experience and information to carry out his
functions.
The necessary means and resources to carry out the work.
Awareness of the policy and the requirements of the system, the
preventive aspects of his work and consequences of non
compliance with procedures.
62 HEC, Subcontractor and Supplier Personnel
All HSE training for construction personnel will be conducted
through the following:
Work-site admission orientation sessions
Pre-construction meetings for critical activities
Training and awareness sessions
Safety meetings
63 HSE Induction Training for New Entrants
It is mandatory for all managers and employees of the Contractor and
Subcontractor to attend HSE Induction Training prior to starting
their fieldwork.
Without taking this training course, they cannot receive an
Identification (ID) card for entry to work on the construction site.
Prior to the HSE Induction Training, all managerial personnel and
employees will submit their "Personal Information" using the
designated form (name, age, gender, profession, physical status,
experience, license or certification, etc.).
For the training of safe work practices, "Safe Work Practices and
Equipment Standards", which will be developed including the
requirements of CA legislations and standards, is available for
trainer's use.
Any Contractor personnel with less than six months of service in the
same job/position with his/her present employer will be considered a
Short Service Employee (SSE). The SSE(s) shall have a mentor assigned
to the work site to provide consistent coaching, feedback, and
oversight while employees develop skill sets to conduct their job
tasks safely.
The Induction Training includes individual instruction given to new
entrants workers and their supervisors according to their work
categories, as described below, but not be limited to:
64 General Orientation
All personnel assigned to or visiting the construction site will be
given a site induction course and badge/sticker the first day of work
by HEC. This course is mandatory and no entry to the Construction
Site or work will be allowed prior to participation in the Safety
Induction.
Outline of the work and the work procedures.
Working Rules:
Duty hours
Overtime work
Transportation
Prohibition of smoking
Drugs and alcohol
Possession of firearms, etc.
Participation in the Tool Box Meetings,
Security rules, including Gate Control,
Confirmation and registration of worker's craft certificates or
other form of qualification,
Traffic rules and regulations,
Outline of Emergency Procedure,
Work Permit System
Fire Prevention
Personal Protective Equipment Requirements and abuse /ineffective
use
Personal Health and Hygiene
Anticipated environmental problems and their countermeasures,
Housekeeping requirements
Avoidance of spillage/contamination, use of drip trays, oil pans,
65 HSE Training for Managers and Supervisors
In addition to the Induction Training for new entrants, specific HSE
training is given to Contractor and Subcontractor Managers (Two times
per year) and Supervisors (Three times per year) by the Site HSE
Manager or competent persons assigned by Site HSE Manager, the
training will cover, but not be limited to:
Individual's roles and responsibilities for HSE management
Enhancement of HSE awareness (emphasize Line Responsibilities)
Regular safety activities
HSE Committee Meeting and other HSE meetings
Incident Reporting and Investigation
Environmental Awareness & issues
Hazard Awareness and Communication
Light and Heavy Vehicle Daily Check
Method Statement, Risk Analysis Job Safety Analysis, for permanent
and temporary works
HSE Management System
66 HSE Training for Specific Hazardous Work
Special training will be given by competent persons
designated/approved by the Site HSE Manager, to supervisors, foremen
and workers involved in specific hazardous or harmful work, the
training will cover, but not be limited to:
Handling organic solvents, and toxic and hazardous chemicals
Handling and storage of radioactive materials
Work under, over on or near water
Deep excavation and trenching
Work in confined areas or narrow spaces
Rigging, lifting and crane operation
Erection and dismantling of scaffolds
Work in or near an existing plant (regardless of whether operating
or not)
Removal of Grating
Working at Heights
Hot works
Stored Energy
67 Fire, Evacuation and First-Aid Training
Fire and First Aid Training, and Evacuation Training will be given to
all employees.
The competent personnel designated by the Site HSE Manager conduct
this training.
68 HSE Training Matrix
"Item "Contents "Attendee "Instructor "
"General "- Risk Assessment Matrix / "All "Site Manger "
"HSE "Results of HSE inspections / " "Supervisor "
"induction "Identification of Risks and " "HSE Manager "
"Training "Hazards from the work " "Site Manger "
" "- Risks and Hazards from the " "from Sub-con. "
" "work " "External "
" "- Safety Work Method " "instructor "
" "- Usage of PPE and Safety " " "
" "equipment " " "
" "- Accident Cases and its safety " " "
" "measures " " "
" "- HSE notices and news " " "
" "- Emergency preparedness and " " "
" "Response " " "
" "(Natural Disasters, Fire and " " "
" "environment Spill) " " "
" "- HEC & Project site's HSE "Supervisor" "
" "Policy and Target "s " "
" "- Implementation of HSE "And " "
" "Management system "Site " "
" "- Identification of HSE "Managers " "
" "Requirement "from " "
" "and applicable law. "Sub-Con. " "
" "- Job Safety Analysis and " " "
" "Results from " " "
" "HSE Meetings and Inspections " " "
" "- Each Job description on HSE " " "
" "area " " "
" "- Emergency preparedness and " " "
" "Response " " "
" "(Natural Disasters, Fire and " " "
" "environment Spill) " " "
" "- Korean Occupational Safety and" " "
" "Health Law " " "
" "(Only for Korean Project) " " "
" "- Legal Obligation for overseas " " "
" "project. " " "
"Initial "- Legal Obligation for each "All "Site Manger "
"HSE "country. " "HSE Manger "
"induction "- Project General Information, " "Site Manger "
"Training "Plot Plan, " "from Sub-con "
" "Process information, Risk Area " " "
" "Classification and Safety " " "
" "Signage on site. " " "
" "- The usage and distribution of " " "
" "PPE " " "
" "- Specific Site Safety Rules " " "
" "(Using safety passages and " " "
" "housekeeping) " " "
" "- Safety matters for heave " " "
" "equipment. " " "
"Specific "- Fire protection/fighting "All "Site Manager "
"HSE "Safety " "Qualified "
"Training "- Emergency response awareness " "Person "
" "- Heat stress " "Third Party "
" "- Working at height safety " " "
" "- Excavations safety " " "
" "- Confined space entry " " "
" "- Incident reporting and " " "
" "investigation " " "
" "- Lifting safety " " "
" "- Rigging/Slinging safety " " "
"Change of "- Heavy equipment for the work "All "Site Manager "
"Work "- Accident cases from similar " "HSE Manager "
" "types of work " "Site Manager "
" "- The usage of PPE " "from Sub-com "
" "- Emergency preparedness and " " "
" "Response " " "
" "(Natural Disasters, Fire and " " "
" "environment Spill) " " "
" "- The specific information on " " "
" "its area. " " "
"TBM "- Implement of TBM activities. "All "Site Manager "
" "- A brief on the HSE Matters " "HSE Manager "
" " " "Site Manager "
" " " "from Sub-com "
" " " "Foremen "
PERMIT TO WORK SYSTEM
A permit to work system will be implemented on the Project, to ensure
that those tasks attracting elements of risk will be subjected to
thorough and systematic planning and preparation prior to their
authorization to proceed.
The Contractor will continually update the precise scope of the
application reflecting the differing needs of the various
construction phases and also the need to interface with the permit to
work systems to be implemented during commissioning and start up.
Notwithstanding this, certain activities mentioned below are required
to obtain a Work Permit issued by Contractor issuers.
Confined Space Entry,
Radiography, pneumatic testing,
Removal of grating and handrails on structures, etc.,
Electrical work require to de-energize or isolate electrical
equipment/components,
Explosive Device, use of cartridge-operated tools,
Pressurized Testing
The underlying philosophy of the Contractor permit to work system is
that Subcontractor task supervisor receives a permit only after it
has been reviewed by The Contractor Discipline Supervisor and
approved by the relevant Area Construction Manager (Commissioning
Manager).
Further, the permit program provides a form of method statement, job
safety analysis that clearly identifies measures to be adopted by
Subcontractor and his employees.
Only persons who have successfully completed the Contractor permit to
work training module will be permitted to initiate, receive, review
or authorise permits.
The system that allows central control and ongoing monitoring of
higher risk activities to ensure that activities are;
1) Authorized by the appropriate site supervisory personnel
responsible for the particular area or for control of hazardous
activities,
1) Carried out by qualified personnel using appropriate safety
precautions
2) Ensures that those activities with potentially hazardous
interactions do not take place at the same time.
70 Cold & Hot Work Permit
Cold Work Permit
2) General construction/commissioning work and maintenance not
involving the breaking of containment of hydrocarbon system
3) Working with radioactive sources: Radiography Certificate also
required
4) Working with nitrogen gas
5) Excavations: Excavation Certificate also required
6) Working with mineral fiber
7) Handling or use of hazardous substances
8) Spray painting/coating
9) Work affecting the availability of fire and gas detection system,
e.g. flammable gas detection, fire detection and Uninterruptible
Power Supplies (UPS)
10) Work affecting the availability of fire protection gaseous system
(CO2)
11) Work affecting the availability of process safety and protection
arrangement, e.g., Emergency Shutdown Valve (ESDV) systems, blow
down and drains systems
12) Work affecting the internal or external communications systems of
the installation/site
13) Working on computer controlled systems
14) Removal of handrails, gratings, hatches and fixed ladders
15) Work at height greater than 1.8 meters
16) Pressure testing of plant and equipment
17) Bleeding down vessels to drains or to atmosphere
18) Use of equipment or work in Non-Hazardous Zones involving:
a) Dry grit/shot blasting
b) Cartridge operated tools
c) Use of torque wrenches in Hazardous Zones
19) Electric work
Hot Work Permit
1) Work involving naked flame
2) Welding
3) Use of portable grinder (electrically and air power)
4) Use of heat shrink blowers and electric power tools in Hazardous
Zones
5) Nitrogen/ Gas leak testing of plant and equipment
71 Confined Spaces Permit
A space that is large enough and so configured that an employee can
bodily enter and perform assigned work.
1) Confined Space permits are required for any confined space entry
operations
2) A confined space is a place, which if substantially (though not
always entirely) enclosed, and where there is a reasonably
foreseeable risk of serious injury form hazardous substances or
conditions within the space or nearby. Examples of confined
spaces are closed tanks, vessels, sewers, open-topped tanks,
vats, pits, and closed and unventilated or inadequately
ventilated rooms
3) Some places fall within the definition of a confined space only
occasionally, perhaps due to the type of work to be undertaken
e.g. spray painting in a room. Spaces may become confined due to
a change in the condition inside or change in the degree of
enclosure or confinement that may occur intermittently.
4) An initial gas test must be recorded on the Confined Space permit
and must be continuous unless special dispensation is granted.
PERSONAL PROTECTIVE EQUIPMENT (PPE)
An effective PPE program is an essential protection against those
hazards, which cannot be engineered out of the construction
environment.
Further, the conformance to the PPE program also provides a valuable
indicator of safety attitudes and behaviour of the workforce.
The Contractor and Subcontractor will ensure that all PPE is "fitted"
correctly to meet individual requirements.
All PPE will conform to either AS, BS, ANSI or DIN standards when
applicable, be suitable for the purpose, and will be maintained by
individuals to ensure that the integrity of such equipment is not
compromised.
In addition, such equipment will be provided free issue to all
Subcontractors, and replaced as required.
Certain items of PPE will be mandatory and worn at all times whilst
on the worksite, these will be:
Safety helmets
Safety footwear with steel toecaps
Safety glasses with side protection
Coveralls (minimum 60% cotton or 100% cotton)
Welders Coverall, Fire retardant
During the Commissioning phase in addition to the mandatory wearing
of P.P.E specified in above other items of appropriate type of
equipment required by/for the work will be in use.
Also, any persons working at an elevation of 1.8 meters or above will
wear a full-body safety harness with dual lanyards that will be
attached to an adequate load bearing anchor point or lifeline
appropriate fall arrest or on an incomplete structure when working
outside handrails.
However, the Contractor stresses that this is a residual form of
protection, the need for which will be avoided wherever practicable
by the use of safe working platforms.
COMMUNICATION NETWORK
Effective communications are vital to the successful implementation
of the health, safety and environmental plan.
Communications take many forms but their common objective is to
improve understanding of health, safety and environmental matters,
thus obtaining the support, co-operation and commitment of all
interested parties.
Contractor will ensure that all of its personnel are able to
communicate in a safe, clear and effective manner. It is imperative
that all personnel are given and understand written, visual and oral
instruction from management and supervisors.
Contractor will provide all resources necessary to ensure that
communications are understood among all personnel on any Worksite.
Contractor will carefully consider and specify the requirements for
communication between multi-national workforces and ensure that each
work crew shall use a common language or have an in-crew interpreter.
[Contractor HSE Site Communication Chain]
The above communication chain will be developed to incorporate
Commissioning team members as Project progresses.
74 Radio Contact
Adequate numbers of intrinsically safe portable radios (walkie
talkies), and chargers will be made available to the Construction and
Commissioning Group. These will all be correctly licensed according
to Algerian regulations and under the Contractor ARPT Radio licensed.
This requirement will extend to all Sub-contractors.
The radios will have channels allocated according to a radio channel
master plan to be developed by the CA and the Contractor.
Commissioning channels will accommodate the following requirements:
Commissioning, Contractor and CA
Emergency services
Subcontractor and vendors
For overlap with construction
HSE MEETINGS
76 Monthly Site HSE Committee Meeting
Contractor Construction Director chairs the HSE Committee Meeting
with members comprising Contractor Construction Managers, each Area
Construction Managers, Site HSE Manager, all the Subcontractor Site
Managers, HSE Managers, and the CA's Project Manager, HSE
Representatives.
The HSE Committee Meeting will be monthly held throughout the
construction and commissioning.
The agenda for the meeting will be structured around the following
guidelines:
Minutes of the last meeting.
Matters arising timely.
Incidents and near misses.
Feedback on incidents.
Publicity/promotion/initiatives.
Monthly look ahead of construction activities.
Anticipated concerns.
Interface between Subcontractor.
Feedback from site personnel.
The minutes of meeting will be prepared by the Contractor HSE staff,
and distributed to relevant personnel of the CA, Contractor and all
Subcontractor, and by so doing, communicating HSE issues and
requirements to the workforce will be achieved.
The major objectives of the HSE Committee Meeting are to:
Ensure that the HSE training programs are implemented and properly
carried out to promote employees' HSE consciousness and knowledge,
Enhance and maintain housekeeping and waste disposal to the
highest standard.
Distribute any information and instructions from CA and/or the
authorities concerned.
Debate and confirm Monthly HSE Objectives and Targets proposed by
the Contractor Construction Director.
Recommend groups and individuals for HSE incentive awards in
accordance with the HSE incentive award scheme.
Announce Forthcoming changes in the type of work as the Project
progress.
77 Weekly HSE Coordination Meeting
Contractor and Subcontractor will hold weekly HSE Coordination
Meeting.
Participants in this meeting will be:
HSE Officers and Supervisors
Subcontractor's HSE Manager
The purpose of this meeting is to review and coordinate the site
activities planned, with the Contractor and Subcontractor, to discuss
general HSE matters, to review and assess HSE inspections outputs, to
discuss the lessons learn from site incident reports and measures
take or to be taken to prevent the recurrence.
HSE requirements and information will be reinforced and reviewed with
Subcontractor in this meeting.
The major objectives of the meeting are to:
Use findings of HSE scoring.
Discuss HSE topics and any problems observed or anticipated.
Have each Subcontractor report on the status and performance of
HSE activities including HSE training.
Report on recent incidents and near misses, and on follow-up
actions.
78 Weekly Discipline Contractor/Subcontractor Meeting
Each construction area will hold a weekly discipline HSE meeting
(more often if required) attended by all relevant Subcontractor
Management and the Contractor supervisor, and chaired by the
Contractor Area Construction Managers responsible for the area.
Its objectives will include review of recent HSE performance, review
of forthcoming key work activities, recent initiatives, Contractor
interfaces, etc.
79 Daily Toolbox Meeting
Daily 'Toolbox Meeting' will be given at start of each shift, and
again just prior to non-routine activities.
Subcontractor supervision will conduct these in a language understood
by all members of the workforce and will address the application of
safety rules and procedures to the hazards of current work. Two-way
discussion will be encouraged.
Duration of the team talk will typically be 5 minutes, but
particularly hazardous operations may require extended team talks,
for example, confined space entry.
Two-way communication will be encouraged (An interpreter must be
present if needed.).
All work crews including supervisors, foremen and workers, will
actively participate. Managers will attend as frequently as possible.
As a continuation of Subcontractor daily talks prior to starting
work, Area Supervisor's (Commissioning Engineer's) must hold daily
commissioning team talks in order to explain details of Commissioning
work to be carried out in that area and ensure the workforce
understands all safety related matters concerning the work.
A record of the date, the ongoing work, the toolbox topic and
attendance will be kept.
The Contractor line management will monitor the meetings on a weekly
basis to check their effectiveness.
Mainly, the working plan and procedures for the day are explained and
confirmed including the following:
Briefing on topics of HSE meetings, CA's information, etc.
Current HSE issues and concerns.
Anticipated potential hazards and suitable countermeasures.
Safety instructions for equipment and tools to be used.
Confirmation whether any Work Permits required for the work have been
obtained.
Use of proper personal protective equipment (PPE) and safety
devices.
Information on other work to be conducted in the vicinity of the
working area.
Visual check of the health condition and proper allocation of
workers.
80 Special Meetings
Additional meetings may be called to address special circumstances,
e.g.:
Work involving novel construction or commissioning techniques.
Work requiring special instructions and precautions.
Visits by HSE or local regulatory authorities.
Poor performance by specific Subcontractor.
Feed back of audit findings.
Reporting the impact on health, safety and environment of any
design work concurrent with the construction phase (i.e.
Identifying potential hazards, which were unknown at the contract
award stage.)
CA interface co-ordination.
Subcontractor interface co-ordination.
EMERGENCY EVACUATION PROCEDURE
All site personnel will be advised of the actions to be followed in
the event of fire, gas/toxic release or any other emergency
situation.
Such advice will be given at site inductions and subsequent ongoing
safety training sessions.
The procedure will be included in the HSE booklet issued to all
employees and will also be published on notice boards, strategically
placed around the site.
Emergency telephone numbers will be listed. A basic map will be
provided which shows evacuation routes and assembly points.
Exercises in each facility shall be conducted at least every
quarterly basis (to be discussed with Company to increase frequency
at site) and the observation shall be recorded. The report should be
forwarded to the HSSE Department and any remedial actions required
shall be identified.
FIRE PREVENTION AND PROTECTION
Whilst the risk of major fire damage in construction, pre-
commissioning and start-up areas is considered by the Contractor to
be reasonably minor, (with key risks presented by compressed gas
cylinders, painting and insulation materials and general debris and
rubbish), the risk in the camp and office areas is considered to be
high.
In order to prevent such hazards materializing, the Contractor will
implement a Project-wide fire prevention/protection strategy that is
characterized by the following general principles:
Minimal bulk storage on site of flammable substances in
appropriate containers
Isolation of flammables from sources of ignition
Training in fire prevention and suppression techniques
Integrity of electrical equipment
Permit to work control
Containment of sparks and flames from Hot Works
Escape route planning
Restricted smoking areas.
The employment and maintenance of fire extinguishers at strategic
locations throughout the worksite and also the deployment of a fire
and emergency response truck, which will remain permanently manned at
a strategic location, will support this approach.
This truck will be mobilized in response to all fires on site and
will be used during emergency response training exercises.
Prior to start of Start up, all operational fire protection equipment
must be in place.
The fire prevention/protection strategy will include all worksite
offices, warehouses, camp, etc., and will be developed to include
commissioning activities.
HSE AWARENESS
84 HSE Incentive Sheme
The purpose of HSE incentive scheme is one kind of motivation
technique for workers at site to promote individual safety
performance, increasing the production and reduce injuries which will
be done by providing individuals with a certain type of awards for
good performance.
85 HSE Awareness Program
Safety and training materials such as booklets, posters, visual aids,
etc. will be suggested by Contractor. Each subcontractor will be
expected to arrange for appropriate materials and should utilize the
materials suggested. Posters of all sizes must be displayed in the
appropriate languages at locations throughout the site.
Site HSE Manager shall maintain the HSE scoreboard and display it at
the key location of the project site facilities. Information of the
HSE scoreboard shall be updated on daily basis
Also Site HSE Manager shall arrange to issue HSE flyer for providing
details of the site accidents/injuries, summarizing details and
comments to avoid re-occurrence on the project site.
Warning signs will be displayed throughout the site, wherever any
hazard warrant their use. Bulletin boards will be used to advantage
in displaying safety posters.
MANAGEMENT OF WASTE MATERIALS
The objectives of waste management activities are to:
Ensure safe and proper segregation, handling, storage, transport
and disposal of waste.
Identify environmental aspects and impacts
Reduce/minimise the volume of waste or utilize as much as possible
for recycle or reuse.
Reduce/minimize the impact of dust, noise, light, odours, working
hours and general disruption on the local community
Assess any relevant task to ensure adequate controls are in place
to minimize the impact of hazardous substances on individuals and
to protect the environment
Reduce/minimize the environmental impact of chemicals through
correct selection, transportation, storage, deployment and
disposal
Manage all waste according to the following hierarchy: eliminate
where possible, reduce at source, re-use, recycle and dispose.
Disposal shall be in accordance with 'duty of care' principles and
disposal records shall be maintained by Contractor and available
for audit by CA
Reduce/minimize any air emission and discharges to water.
All waste management activities will comply with the applicable laws
and regulations and the CA's requirements.
87 Non-hazardous Waste
Subcontractor are responsible for collection, segregation, recording,
transport and disposal of waste to the location, designated by the
CA, where located out of the Contractor asset/boundaries.
88 Hazardous Waste
Hazardous substances will be handled, transported and stored at the
Contractor designated storage on site properly.
89 Sewage Disposal
The Contractor and Subcontractor will ensure that all sewage from
offices, site and camp is treated properly and follow the local laws
and regulations strictly.
The sewage system will consist of sewage underground piping,
manholes, lift station pit with pumps, biological sewage treatment
plant and treated effluent underground piping to facilitate sewage
management a bioreactor will be installed for the construction
period.
90 Worksite Waste
All waste material will be identified and segregated.
Each Subcontractor will be responsible for the provision of such
facilities to segregate waste.
An adequate number of skips and bins will be located at key positions
on the worksite by Subcontractor based on their workload.
These items to be disposed of will be clearly identified according to
the classification of waste, which they will generate. Subcontractor
will be directly responsible for proper storage of waste in these
containers.
Domestic waste from the temporary facilities etc. on the worksite
will be handled in exactly the same manner as at the Labor Camp.
Hazardous waste will be stored in a closed secure container, clearly
marked, with Material Safety Data sheet, as hazardous material and
transported to the Contractor designated on-site storage.
All concrete debris and/or unused concrete will be deposited to an
area being located out of the site designated by the CA.
91 Housekeeping
All areas must be kept free from debris and waste material on an
ongoing basis. At the end of each working day a check will be carried
out by Subcontractor Task Supervisors to make sure that all waste
material has been gathered and deposed of in the allocated area.
All empty containers of hazardous material must be removed from the
work area as soon as is reasonably practicable. All empty gas bottles
must be returned to their storage area and stored in the proper
manner.
All spillages must be cleaned immediately in accordance with the
product manufacturers recommendations and reported to the Site HSE
Manager.
A spillage is an environmental incident and will be reported in the
Project Incident Data Base. An incident report and investigation
report will be generated. The Contractor will keep an overview of
spillages on an O/A Plot Plan. All cleaning materials due to solvent
content etc. will be treated as hazardous waste and disposed of as
such.
Food consumption will not be permitted on the construction site.
92 Waste Collection and Disposal
The Waste Management Plan(0304-ZB-132) will be an integral part of
each subcontract and will be the responsibility of Subcontractor.
This will ensure that good housekeeping is practiced and also that
collection, segregation, storage and disposal of waste is properly
controlled to minimize the environmental impact of the Project.
Regular waste collections will be undertaken by a specified
Subcontractor, who will be approved by the relevant Authority to
carry and dispose of the various types of waste generated.
The waste management co-coordinator of each Subcontractor will
prepare a monthly report detailing the types and quantities of waste
removed from site and/or stored on-site during that period.
The Contractor Waste Management Controller will monitor all
collection points to ensure that there is no over-spill or backlog of
waste removal. In addition, they will spot check the waste control
against its description on the Manifest before it leaves the site by
the appointed transporter.
Disposal by burning will be prohibited without prior permission of
the Contractor/CA.
All copies of permits must be retained by the waste disposal co-
ordinator and must be produced on demand by any authorized authority.
WELFARE
94 Sanitation
The Contractor and Subcontractor will ensure the provision of
adequate sanitation including sufficient WC's, urinals and washing
facilities for all personnel, anti bacterial soaps and will be clean
and maintain them on a daily basis.
95 Medical Facilities
The Contractor believes that the utilization of a single medical
facility ensures both consistency of treatment and accuracy and
openness of injury reporting.
Therefore, construction Subcontractor will be prohibited from
establishing their own medical facilities, (other than immediate
First Aid) with the result that all injuries, irrespective of
seriousness, will be reported to the Project medical facility on an
immediate basis.
Qualified personnel for all hours during which activity is taking
place on the worksite will man this facility.
Detailed records of all such injuries and treatment will be
maintained and will be input into the Incident Statistical analysis
database.
The medical facility will include emergency response equipment such
as Para guard stretchers, resuscitation sets, etc., and will be
supported by a fully equipped ambulance which itself will be manned
by a dedicated driver and paramedic.
In addition, appropriate vaccines and anti-venoms will be available.
96 Occupational Health
In acknowledging the debilitating and chronic effects of occupational
health hazards, the Contractor will operate an occupational health
program that addresses often-neglected areas of construction activity
such as hernia caused by manual handling, and a white finger disease
resulted from continuous excessive exposure to excessive vibration.
Noise will be limited to as low levels as are reasonably practicable,
with personal hearing protection being utilized only as a secondary
option after enclosure, segregation, modification, rotational
assignments, etc.
The risk of inhalation of hazardous substances will be minimized by
the adoption of safe systems of work that include ventilation
systems, enclosure and isolation, respiratory equipment program and
substitution.
All Project personnel will be subject to random testing for such
substances.
Sanitation and hygiene will also be emphasized throughout the Project
and to this end; Subcontractor will be required to maintain all of
their facilities in a clean and hygienic condition.
The dangers of dehydration, sand fly leishmaniasis, sunburn and
frostbite are recognised as areas of risk for which employees will be
exposed.
Training programs will be put in place.
In order to provide a healthy environment for employees who do not
smoke, smoking will not be permitted in any Project office, or
sleeping accommodation. Smoking will only take place in dedicated
areas outside of building.
The Contractor recognizes that good housekeeping is the best form of
pest and vector control.
The Contractor approved Doctor will develop a pest and vector program
to address site conditions. (e.g. mosquitoes: Spraying, no stagnant
well, scorpions, vipers, sandflys etc.).
97 Health Policies and Procedures
The Contractor will provide first aid, primary medical care,
secondary medical, medical evacuation and medical emergency response
for the worksite.
For all employees, the Contractor and Subcontractor will maintain
medical insurance for hospitalization, in-and-out patient physician
examinations, emergency medical coverage, routine examinations and
short-and long-term disability.
Health insurance will be arranged for expatriate employees assigned
to the Project.
The Contractor will develop and manage by the following Policies and
procedures(0304-ZB-137):
Smoking policy
Fitness to Work
health surveillance
IMPLEMENTATION AND MONITORING
99 HSE Performance(General)
The Project HSE-MS shall be assessed and evaluated through
Site Safety Team monthly meetings
Site safety committee regular meetings
Verification and review of Project level documentation by Project
HSE Manager, or discipline and personnel nominated by him, prior
to issuing the documents to CA for their review.
CA audits
100 Lessons Learned
The HEC shall ensure that lessons learned through the HSE monthly
reports, audits and inspections are incorporated in the HSE-MS and
the related documentations are published and explained to the project
personnel and the workforce.
101 Safety Performance and Reporting
The Contractor will report to the CA Representative the HSE status of
the Work via the monthly report. The detail level of monthly HSE
reporting shall be agreed between the CA Representative and the
Contractor Representative before commencement of any part of the
Work.
The Contractor will notify the CA Representative both orally and in
writing immediately after discovering, or receiving a report relating
to, any of the following events that may occur:
The death of any Personnel whilst performing any part of the Work;
The injury of any Personnel whilst performing any part of the Work
where a recordable incident has occurred;
Any high potential near miss or accident which has the potential
for serious injury or serious damage to equipment;
Any release, spill or discharge of a hazardous material associated
with the Contractor's performance of the Work, which either
results in or has potential for significant injury or
environmental damage;
Any proceedings being commenced or threatened, alleging any
failure by the Contractor or any of its Sub-Contractors to comply
with any EHS requirements, irrespective of whether or not it is
associated with the Contractor's performance of the Contract;.
102 Documentation
The following reports, information and documentation shall be
maintained and timely submitted to CA for each requirement:
Daily/Weekly HSE Report.
Safety Training Records including a List of Recipients.
Safety Patrol Report.
Reports of Corrective Actions taken as instructed by HEC.
Equipment Inspection and Maintenance Records.
Accident/Incident/Near-miss Report.
Equipment/Property Damage Report.
Material Safety Data Sheets (MSDS).
Work Permit Record.
Housekeeping and Waste Disposal Records
Monthly Safety Report
Driver performance reports
Action tracking register (ART) summary
103 Incident Investigation and Reporting
Serious incidents and injuries will be immediately reported to the
Site Manager and to CA HSE representative. All incidents in common
areas will be reported to CA as per CA Incident Reporting and
Incident Procedure.
All incidents will be investigated by HEC and in the event of a
serious accident; HEC and CA will establish a Committee of Inquiry.
The cause or the chain of events that led to an incident will be
determined. Investigations will be conducted without prejudice and
will focus on finding the facts, not faults or placing blame.
The Site HSE Manager will set up an incident reporting and
investigation procedure(0304-ZB-135) and ensure that corrective
actions to prevent recurrence of accidents are implemented.
AUDIT AND REVIEW
The Project HSE audit shall be subject to audits under the Project HSE
Audit Procedures and Plan(0304-ZB-143).
Audits at the Site shall be conducted to assess compliance with local
laws and regulations, CA's requirements, (Contractor Management and
HEC HSE plans and procedures). These audits shall be carried out by
the Site HSE Manager with the support of the Corporate HSE Department
at key points during construction and pre-commissioning, e.g., start
of foundations, and structure and equipment erection; working at
heights, heavy lifts, and energizing.
Action items/non-conformances generated by the audits shall be
recorded. An Action Log shall be prepared and maintained in such a way
as to ensure that it is possible to trail from the initial
recommendation to its final implementation. Action items, non-
conformances generated by the audits shall be recorded by
Project HSE Manager
Site HSE Manager
105 Planning the Audit Programme.
106 The entire HSE System of the company which includes all current
projects as well as the organisation shall be audited at least once a
year.
107 The Manager of the Safety & Environment Department, Head Office shall
prepare the annual audit programme.
108 Formation of Audit Team.
109 The Manager of the Safety & Environment Department, Head Office shall
form HSE Audit Teams.
110 The Audit Team Leader shall have a good knowledge on ISO 14001, Health
and Safety requirements and also sound auditing skills and
techniques.
111 Audit Team Members should be selected on the basis of
1) Technical Background.
2) Impartiality
3) Knowledge of Auditing skill and technique.
112 Conducting the Audit.
113 Pre-Audit Meeting.
1) The Auditee should be informed of the Audit schedule at least a
week in advance through a Audit plan in order to eliminate the
element of surprise.
2) The Audit Team member should have a formal opening meeting with
the Auditee's Representative(s) prior to commencement of the
Audit, stating the scope of audit tabulated in the Audit Plan and
explain how the audit will operate. The audit plan shall be
acknowledge by the Auditee.
114 Audit.
1) The Audit Interview shall be intended for fact-finding and not
fault finding on the system. The Audit Team Members should be
objective in questioning the Auditee.
2) The Audit Team Members shall ask the Auditee to briefly run down
the procedure, stop for clarification if necessary.
3) The Audit Team Members should ask for evidence wherever necessary
such as reports, records, minutes, instructions, etc.
4) The Audit Team Members shall selectively question the
staff/workers at that moment, not to interfere with the routine
activities.
115 Post-Audit Meeting.
1) The Audit Team shall hold a meeting with the Auditee's management
to present Audit Findings.
2) At this meeting, the non-conformities found during the actual
audit and response dates shall be agreed.
116 Issue of Report and Corrective Request.
117 Within 2 weeks after the audit, the Audit Team shall issue the 'Audit
Finding Report' to the Auditee, as necessary.
118 The Auditee must take action on the reported non-conformances and
complete by the stipulated dates.
119 All 'Audit Finding Reports' issued shall be recorded and updated in the
'Audit Finding Report Log' by the Audit Team.
120 The Audit Team Leader shall condense facts of the Non-conformances in
the 'Audit Summary Report' and submitt them to the Management
Representative for his review and approval.
121 Close-out of 'Audit Finding Report'
122 The Audit Team shall evaluate the corrective action responses.
123 If the response is acceptable, the Audit Team shall verify the
Corrective Actions taken and close-out the 'Audit Finding Report'.
124 If the response is unacceptable, the 'Audit Finding Report' shall be
returned with comments.
-----------------------
Construction Director
Monthly
Site HSE Committee
CA & Contractor
HSE Strategy Meeting
HSE
CONSTRUCTION
Construction Manager
Fortnightly
Contractor/Subcontractor
HSE Meetings
Contractor/party/Subcontractor
HSE weekly coordination
Meeting
Contractor/party/Subcontractor
HSE Officers/Supervisor
Daily Meeting
Weekly Discipline
Contractor/party/Subcontractor
Co-ordination Meeting
HSE representation
Weekly Progress Meeting
CA, Contractor & Subcontractor:
Senior Line Management
Construction Manager
Discipline Supervisors
HSE Officers
Weekly HSE Scoring
Party/Subcontractor
HSE Officer/Management
Toolbox Talks/Daily