Internal yield and collapse pressure of tubing/casing
Packer-w/out-tailpipe Calculations Determine the following:
Volume of cement slurry and water ahead/behind – – – –
No. of sacks, mixwater & additives Depth to set packer & when to close packer bypass Maximum displacement volume Displacement ,Hydrostatic pressures and MASP at the following stages:
Cement slurry 1 bbl to end of tubing ( start squeeze ) Cement slurry starts to exit tubing All cement slurry out of tubing 1 bbl of cement slurry above T.O.P ( end squeeze )
– Surface pressure vs volume chart – Internal yield & collapse pressure of tbg/csg 25 Initials
Packer with tailpipe Calculations
Determine the following – Volume of cement slurry & water ahead/behind – No. of sacks, mixwater & additives – Plug height with & without drillpipe or tubing – Length of tailpipe – Displacement volume to balance plug – Depth to set packer – Maximum cumulative brine volume – Hydrostatic pressure at start & end of squeeze – MASP – Surface pressure vs volume chart – Internal yield & collapse pressure of tbg/csg