VIET NAM SHIPBUILDING INDUSTRY COrPORATION HA LONG SHIPBUILDING COMPANY
HA LONG SHIPBUILDING COMPANY
QUALITY STANDARD BOOK 1
H¹ LONG 2006 -0-
HALONG SHIP BUILDING Co.
preface
This HLSQS describes the quality standards and the inspection practice which are applied during repair and building ship process in HA LONG SHIPBUILDING Co.
This document is intended to provide standard instructions to Ship Owners, Class Surveyors, QC, inspectors, and the production workers, aiming that proper quality level is maintained during repair and building ship process and eliminating any possible, disputes among them.
The contents of this documents are applied for all kinds of cargo ships, barges, drilling rigs & special purpose etc. unless additional requirement are specified in the contract specifications.
-1-
HALONG SHIP BUILDING Co.
* * contents * *
* * contents * * Part i:
quality standard …………………………… 1 1. hull construction 2. hull out fittings 3. machinery & out fittings 4. piping system 5. painting part 6. electric part
part II: inspection practice …………………………… 155 1. hull inspection 2. out fittings inspection 3. machinery inspection 4. piping inspection 5. electric inspection 6. painting inspection 7. list of inspection/test
part III
N.D.E technique...................................................... 210
part IV
appendix – I .............................................................. 225
part V
appendix - II ............................................................ 256 -2-
HALONG SHIP BUILDING Co.
part I
quality standard
-3-
Halong shipbuilding co.
HALONG SHIP BUILDING Co.
Section 1
Hull construction
1.1 material ........................................................................................... 5 1.2 gas cutting ..................................................................................... 7 1.3 fabrication..................................................................................... 9 1.4 deformation................................................................................... 12 1.5 accuracy of hull form ........................................................... 15 1.6 welding ............................................................................................. 17 1.7 alignment & finishing............................................................... 20 1.8 welding technique ..................................................................... 30
-4-
HALONG SHIP BUILDING Co.
section I
Hull construction
* shipbuilding & repair
1.1 Material 1.1.1 Surface flaw 1) Pit Item
Remarks 1. Grade A: Repair is unnecessary 2. Grade B: 1) Outer surface of shell plates. To be repaired by grinding if necessary. When painting with epoxy can not be done, grinding is to be carried out. 2) Others: Repair unnecessary. 3. Grade C: To be repaired by grinding 4. Grade D: Repair method is to be determined after discussion with owner and class. * Recommended repair method: Grinding followed by welding. Area ratio (%) =
Area of pit x100 Total area of a plate
2) Flaking: Item
Remarks 1. Grade A: Repair is unnecessary 2. Grade B: Repair if necessary. 3. Grade C: Repair is necessary * Repair method (d=depth of defects ) 1) d 0.07t (max 3mm)- Grinding 2) 0.07t < d 0.2t: Welding and grinding ( The welded area should be less than 2% of the total area of a plate ).
-5-
HALONG SHIP BUILDING Co.
Section 1
Hull construction
* shipbuilding & repair
3) Other defects Item
Remarks 1. Grade A: Repair is unnecessary. 2. Grade B: Repair is necessary. * Repair method (d=depth of defects ) 1) d 0.07t (max 3mm): Grinding. 2) 0.07t < d 0.2t: Welding and grinding. ( The welded area should be less than 2% of the total area of a plate ).
1.1.2) Lamination Item
Remarks
Local
In case where the range lamination is
lamination
limited, it can be chipped out and built up by welding as shown in ( a ). In case where the range of lamination is limited, also but is near the plate surface, it is preferable to make the built up welding as shown in ( b ).
Severe
It is recommended to renew the plate
lamination
locally, in case where the range of
requiring a local
lamination is fairly extensive.
renew of a plate
The standard minimum breadth of a plate to be renewed is as below. 1) Shell and strength deck under large constraint : 1600mm 2) Not under large constraint: 800mm 3) Other structural members: 300mm.
-6-
HALONG SHIP BUILDING Co.
Hull construction
Section 1
* shipbuilding
1.2 Gas cutting. 1.2.1 Notches.
Unit: mm Standard range
Item Free edges
Tolerance limits
1) Upper edges of sheer strake. 2) Strength deck within 0.6L
Indentation 0.5
and free
edges of opening of shell plate. 3) Main longitudinal strength members. Indentation 1.0
Longitudinal and transverse strength members.
Indentation 3
Others Weld grooves
Butt welds
Indentation 2
Shell plate and upper deck within 0.6L
Indentation 3
Others
Indentation 3
Fillet welds
Section 1.
Hull construction
* ship repair
1.2.1 Notches for repair ship
Unit: mm
Standard rang
Item
Tolerance limits
1) Upper edges of sheer strake 2) Strength deck within 0.6L Free edges
and
free edges of opening of shell plate.
Indentation 1.0
3) Main longitudinal strength member. Longitudinal transverse strength
Indentation 1.5
Others
Indentation 3 Shell plate and upper deck
Weld grooves
Butt welds
within 0.6L
Indentation 2 Indentation 3
Others.
Indentation 3
Fillet welds
-7-
HALONG SHIP BUILDING Co.
Section 1
Hull construction
* shipbuilding
1.2.2 Dimensions
Standard range
Item
Tolerance limits
L 3d Length of taper ( L)
Depth of grooves General members compared with correct Sizes of members
ones. Depth of floors and girders in double bottom Breadth of face bars
Section 1
0.5d
1.0d
1.5
2.0
3.5
5.0
2.5
4.0
2.0
3.0~4.0
Hull construction
* ship repair
1.2.2 Dimension for repair ship.
Standard range
Item
Tolerance limits
L 3d Length of taper (L)
Depth of grooves
-8-
0.5d
0.1d
2.0
3.0
HALONG SHIP BUILDING Co.
Section 1
Hull construction
* shipbuilding & repair
1.3 Fabrication. 1.3.1 Flange longitudinals
Unit: mm
Standard range
Item Breadth of webs and flanges
Angle between flange and webs
Tolerance limits
3.0
5.0
2.5
4.5
10
25
10
25
Compared with template per 100mm in breadth of flanges
Curvature or straightness in the plane of flanges Per 10m in length Curvature of straightness in the plane of webs. Per 10m in length 1.3.2 Flange brackets.
Standard range
Item
Tolerance limits
Breadth of webs and
3.0
5.0
3.0
5.0
flanges Angle between flanges and webs
Compared with template per 100mm in breadth of flanges. -9-
HALONG SHIP BUILDING Co.
Section 1
Hull construction
* shipbuilding
1.3.3 Built-up plate.
Unit: mm
Standard range
Item
Tolerance limits
Deviation of face plates Frames and
1.5
3.0 per
longitudinals
per 100mm
100mm
b 100
a 5
Distortion of face
a 3
plates
Section 1
Hull construction
b 100
* ship repair
1.3.3 Built – up plates for repair ship
Unit: mm
Standard range
Item
Tolerance limits
Deviation of face plates Fames and
3.0 per
5.0 per
longitudinals
100mm
100mm
Distortion of face
a 3 .5
plates
- 10 -
b 100
a 6
b 100
Section 1
HALONG SHIP BUILDING Co.
Hull construction
* shipbuilding & repair
1.3.4 Line heating method
Standard range
Item Water cooing just after heating
* 50 HT
Air cooling after heating
Tolerance limits
Under 6500C
Under 9000C
* TMCP Type 50HT
Under 9000C
(Ceq>0.38%)
(Starting Air cooling and subsequent water
temperature of
cooling after heating
water cooling to be under 5000C)
* TMCY Type 50HT
Water cooling just after heating or
(Ceq 0.38%)
air cooling
Under 1000C
* AH~DH * TMCP Type 50HT
Water cooling just after heating or
(Ceq 0.38%)
air cooling.
Under 900oC
* EH 1.3.5. Line heat/ cool’ cycles.
Item TMCP Type 50HT (AH - DH) TMCP Type 50HT (EH)
Remark Within 3 cycles as far as practicable Within 2 cycles as far as practicable
Others
Not defined
- 11 -
HALONG SHIP BUILDING Co.
Section 1
Hull construction
* shipbuilding
1.4 Deformation 1.4.1.Unfairness
Unit: mm
Standard Tolerance range limits
Item Shell plates
Parallel part ( side )
4
6
Standard and/or
Parallel part ( bottom )
4
6
tolerance limits
Fore and aft part
5
7
are to be applied
4
6
Double bottom tank top plates Transverse bulkheads, Swash
per each frame, longitudinal and stiffener space
Longitudinal bulkheads, Bulkheads
Remarks
6
8
respectiveily. Where above is
bulkheads. Parallel part within 0.6L
4
6
not applicable , it
Fore and aft part
6
9
is to be applied
Covered part
7
9
per 1.8m in
Bare part
6
8
length.
Covered part
7
9
Forecastle deck,
Bare part
4
6
Poop deck.
Covered part
7
9
Super structure
Bare part
4
6
deck
Covered part
7
9
Lift-able
10
12
Fixed
6
8
8
10
Outside walls
4
6
Inside walls
4
6
Covered part
7
9
Webs of girders, transverses
5
7
6
8
Strength deck
Second deck
Car deck Intermediate deck Deck house wall
Interior members
Floors and girders in double bottom
- 12 -
(Where above space is over 1.8m paragraph 1.4.2 is to be applied)
HALONG SHIP BUILDING Co.
Section 1
Hull construction
* ship repair
1.4.1 Unfairness for repair ship
Standard Tolerance range limits
Item Shell plate
Parallel part side
4
6
Standard and/or
Parallel part bottom
4
6
tolerance limits
Fore and aft part
5
7
are to be applied
6
6
Double bottom tank top plates Bulkheads
Remarks
longitudinal and stiffener space
Longitudinal bulkheads transverse bulkheads, Swash
per each frame,
6
8
respectiveily. Where above is
bulkheads. Paralleled part with in 0.6L
4
6
not applicable , it
Fore and aft part
6
9
is to be applied
Covered part
7
9
per 1.8m in
Bare part
6
8
length.
Covered part
7
9
Forecastle deck,
Bare part
4
6
poop deck
Covered part
7
9
Super structure
Bare part
4
6
deck
Covered part
7
9
Car deck
10
12
Intermediate
8
10
Outside walls
4
6
Inside walls
4
6
Covered part
7
9
5
7
6
8
Strength deck
Second deck
Deck house wall
Interior member
Webs of girders, trans.
Floors and girders in double bottom
- 13 -
(Where above space is over 1.8m paragraph 1.4.2 is to be applied))
HALONG SHIP BUILDING Co.
section I
Hull construction
1.4.2 Deformation per basic length
Unit: mm
Standard Tolerance range limits
Item Shell plates
* shipbuilding & repair
Parallel part Fore and aft part
Decks, Double bottom tank tops
2L/1.000
3L/1.000
3L/1.000
4L/1.000
3L/1.000
4L/1.000
Remarks Deformation per basic length means the deformation measured between one transverse space.
Bulkheads
4L/1.000
5L/1.000
For cabin walls and
Cabin walls
2L/1.000
3L/1.000
curtain plates, the basic
Curtain plates
2L/1.000
3L/1.000
1.4.3 Distortion
Unit: mm
Distortion of girder and transverses at the
Per span
5
8
L 1000
5
8
part of upper edge and flange. Distortion of longitudinals,
1000
3
2L 1000
6
2L 1000
transverses, frames, beams and stiffener at
L 3500
10
13
5
8
1/2t
t ~
the part of flange . Distortion of H type pillars between decks Distortion of tripping brackets and small stiffeners.
length is about 5m.
Distortion at the part of free edges
- 14 -
HALONG SHIP BUILDING Co.
Section 1
Hull construction
* shipbuilding & repair
1.5 Accuracy of hull form 1.5.1 Principal dimension
Item
Standard range
Tolerance limits
L.B.P.
50/100m
Not defined
Breadth ( Moulded )
15
Not defined
Depth ( Moulded )
10
Not defined
1.5.2 Deformation of hull form
Unit: mm
Item Flatness of keel
Deformation for the whole length
Standard range
Tolerance limits
25
Not defined
30
Not defined
20
Not defined
15
Not defined
Cocking-up
Rise of floor amid ships Rise of floor
1.5.3 Others Unit: mm
Item
Standard range
Tolerance limits
Draft marks
1.0
2.0
Free board marks
0.5
1.0
- 15 -
Section 1
HALONG SHIP BUILDING Co.
Hull construction
* shipbuilding & repair
1.5.4 Special sub-assembly Item
Standard Tolerance range
limits
Remarks
Distance between aft
Block sub-assembly stern frame
edge of boss and aft peak
Rudder
10
5
10
4
8
bulkhead ( b). Twist of sub-assembly (c)
Deviation of rudder from shaft center line ( d )
Others
Other
main
Breadth and length of top plate of main engine bed Others
(C)Twist of plane including
Refer to the section of curved plate block 6
Twist of rudder plate
Flatness of top plate of Main engine bed
5
10
Correct or re-assemble partially
Refer to the section of the curved plate block subassembly
5
10
4
6
Refer to the section of the flat plate block sub-assembly
- 16 -
HALONG SHIP BUILDING Co.
Section 1
Hull construction
* shipbuilding & repair
1.6 Welding 1.6.1 Shape of bead Tolerance
Item
limits
Over-lap
Remarks 1. 90 0 : Repair
is unnecessary
Butt
2. In case 90 0 , grinding or welding 90 0
in necessary to make 90 0
Fillet
Undercut
Skin
Butt
To be repaired by
plates
d 0.5
using fine electrode
and face
(over
( Avoid short beads
plates
90mm
for higher tensile
within
continuous) steel )
0.6L Others
d 0.8
Fillet
d 0.8
Leg length
L0: Design leg
and Throat
length
thickness
- 17 -
L
0.9L0
t0: Design throat
t
0.9t0
thickness
HALONG SHIP BUILDING Co.
Hull construction
Section 1
* shipbuilding & Repair
1.6.2 Distortion of welding joints
Unit: mm Tolerance
Item
Remarks
limits
Angular
Skin plates within
distortion of
0.6L
weld joints
Fore and aft shell
In case where it is
6
over tolerance limits, it is to be
7
plating and
repaired by line
transverse strength
heating or re-
Span of frames or
member
welded after
beams
Others
cutting and
8
refitting 1.6.3 Short beads
Unit: mm Item
Tolerance limits 2
Higher tensile steel ( 50kg/mm class )
50
TMCP type 50HT (Ceq 0.36%)
10
Mild steel( including take and repair welding )
Remarks
Not defined
1.6.4 Arc strike
Unit: mm Item
Higher tensile steel ( 50kg/mm2
Tolerance limits Not allowed
Remarks In case where arc strike made
class ) and grade “ E “ of mild
erroneously, one of the following
steel.
repair methods is applied. 1) Weld over 50mm bead on the arc strike. 2) Remove the hardened zone by grinding.
1.6.5 Alternation case Item Short bead & Arc strike of Higher
Acceptable
Remarks
limits
In case of during repair, building up
10
tensile steel.
on surface after discussion with class & owner. 1) To be preheating at fault areas.
- 18 -
Section 1
HALONG SHIP BUILDING Co.
Hull construction
* shipbuilding & repair
1.6.6 Weld profile 1) Concave bead
Unit: Tolerance limits
Remarks
Unacceptable
L=min 0
2) Convex bead Max 1.6 L 8 Max 3.0 8 L 25 Max 4.5 25 L
3) Division of position
Machine
Manual welding Plat H 3.0mm
Vertical &
welding Overhead
horizontal H 4.0mm
H 4mm
H 4.5mm
4) Bead repair It the bead height is over the standard range which shows bad appearance, the bead will be repaired by grinding. - 19 -
HALONG SHIP BUILDING Co.
Section 1
Hull construction
* shipbuilding & repair
1.7 Alignment and finishing 1.7.1 Minimum distance of weld to adjacent weld
Unit: mm Tolerance
Item
limits
Remarks
a 30 Butt weld to butt weld
a 0
a 10
Butt
a 0
weld to filler weld
Smaller distance can be a 5
acceptable in special cases.
- 20 -
HALONG SHIP BUILDING Co.
Section 1
Hull construction
* shipbuilding & repair
1.7.2 Minimum distance between holes and between hole and end of member. Distance ( s)
Description
“A” Space
“B” Space
d1 d 2 2
d1+d2
Remarks
1) Between holes
2) Between hole and plate, and face d 2 S2 d (mi.n.75) S1
S1=d S2=2d (min. 75)
3) Between hole and scallop d1 d 2 2 (min .50)
d+R (min. 50)
4) Between hole and slot
dB 2
s 200 (ABS) d+B
s 180 (LR) s D (NK)
5) Between slots s1 2B s2 2d and s2 2B
- 21 -
HALONG SHIP BUILDING Co.
Hull construction
Section 1
* shipbuilding & repair
1.7.3 Treatment of holes made erroneously. Tolerance
Item D<300
Skin plate
(D: diameter of holes ) Other d 300
Remarks
limits A*
Open the hole to over 100
Or B*
Open the hole to over 300
B*
Open the hole to over 300
or C*
Open the hole to over 100
Skin plate
B*
Others
B* or C*
Scallop, slot
B* or C*
* Method of treatment A: spigot patch 5
400 0
B: Closing by butt welding with back gouging 5
400 0
C: Closing by lapping piece L 50 or L 2t1+25 Whichever is greater
- 22 -
HALONG SHIP BUILDING Co.
Section 1
Hull construction
1.7.4 Gap of joints
* shipbuilding & repair Unit: mm
Item
Tolerance
Remarks
limits
1. Manual welding
1. 5
1) Welding with backing strip or flat type ceramic back material. 2) Welding at reverse side after chipping. 2. 16
1) Build-up edges with backing strip of a 5
flat type ceramic backing material to keep the gap less than 5mm ( make stringer beads )
Butt
2) Welding.
joints
3) Welding at reverse side after shipping 3. a>25
Repair method is to be determined after discussion with owner & class. Normally partial renew by min. size 300mm is applied. 2. Flexible asbestos
a>5
Backing ( F.A.B )
1) First or second pass by FCAW or a 5
GMAW as shown in 1.7.4 item 4. 2) The rest by automatic (SAW)
- 23 -
HALONG SHIP BUILDING Co.
Section 1
Hull construction
1.7.4 Gap of joints
* shipbuilding & repair
Unit: mm Item
Tolerance
Remarks
limits
3. Submerged Arc welding
1. 0.8
(S.A.W)
2. a>5: Refitting
a 8
4. F.C.A.W and G.M.A.W
1. 12< a 25
Butt
1) Build-up on edges with backing
joints
strip of flat type ceramic backing material to keep the gap within 12mm ( to make stringer beads.) Build-up on the edges should not a 12
exceed 1/2t1 . nor 12.5mm whichever is smaller. 2) Welding. 2. a>25
Repair method is to be determined after discussion with owner & class. Normally partial renew by min. size of 300mm is applied. - 24 -
HALONG SHIP BUILDING Co.
Section 1
Hull construction
1.7.4 Gap of joints
* shipbuilding & repair
Unit: mm Tolerance
Item
Remarks
limits
1. Filler joints without
1. 3< a 5
groove
Leg length to be increased: L=L0+(a-3) (L: increased leg length) (L0: Leg length indicated on drawing ) 2. 5< a 16 Welding with bevel preparation
t1
t2 a 3 (1) To make bevel edge of web to 300~450 (2) To attach backing strip or ceramic
Fillet
backing material.
Joints
(3) Welding. (4) To weld at reverse side after chipping. 3. 16< a 25 1) Bevel preparation (300~450) 2) Build-up of each plate edge should not exceed 1/2t1 nor 12.5mm whichever is smaller. Gap after build-up should not exceed 5mm. 4. a>25 Partial renew with a size of min. 300mm
- 25 -
HALONG SHIP BUILDING Co.
Section 1
Hull construction
1.7.4 Gap of joints
* shipbuilding & repair
Unit: mm Item
Tolerance
Remarks
limits
2. Fillet joints with
1. 5< a 16
groove
1) To attach backing strip or ceramic backing material. 2) Welding 3) To weld at reverse side after chipping. Fillet joints
a 5
2. 16< a 25 Build-up of base plate
Gap after build-up should not exceed 5mm. 3. Partial renew with a size of min. 300mm. a 3
1. 3< a 5 Leg length shall be increased by the amount of gap ( indicated leg length gap )
Lap
2. a>5
joints
Refitting.
- 26 -
HALONG SHIP BUILDING Co.
Section 1
Hull construction
* shipbuilding & repair
1.7.5 Alignment Item Butt joints
Tolerance limits Strength
a 0.15t1,
a>0.15t1, or a>3
members
(max.3)
Refitting
a 0.2t1
a>0.2t1, or a>3
(max.3)
Refitting
Others a: Difference t1 t2 Fillet joints
Strength
a 1/3t
members
1. 1/3t1
For “A” & “B”, increase leg length by 10%t1. a: Difference
2. a>1/2t1: Refitting
t1
* For members having small breadth ( i.e.
t2
face plate of built-up member ), doublers or carling can be attached after discussion with owner & class. Others
a 1/2t1
a>1/2t1 Refitting
- 27 -
HALONG SHIP BUILDING Co.
Section 1
Hull construction
* shipbuilding & repair
1.7.5 Alignment Item
Tolerance
Remarks
Flange width s 0.04b
If s 0.08b
max. 8mm
Grind corners to smooth. Taper over
Alignment of butt
distance min.
joints in stiffeners
L=30s If s>0.08b release and adjust over distance min. L=50s
Overlap brackets, gap before manual welding
For weld
If s 5mm
throat
Parts may be pulled
thickness
together and welded
a 4mm
If s>5mm
Gap s 2mm
Release and adjust
for a>4mm s 3mm
- 28 -
HALONG SHIP BUILDING Co.
Section 1
Hull construction
* shipbuilding & repair
1.7.5 Alignment Item Openings for
Tolerance
1. Position of nearest scallop
Remarks If d>75mm
stiffeners passing
The nib between scallop
through girder webs
and opening to be cut, and lug to be welded to d 75mm
2. Gap
plating, see figure
s 5mm. Weld throat thickness to be increased by one weld bead or 2mm. If 5
Chamfer and build up by welding. If s>10mm. Cut off nib and fit lug of same height as nib.
s 3mm
Sufficient for weld access.
- 29 -
HALONG SHIP BUILDING Co.
Section 1
Hull construction
* shipbuilding & repair
1.8 Welding technique 1.8.1 Welding sequence 1. Welding sequence is to be carefully planned for each structural member. So that the parts can be jointed freely without any deformation or residual stress after welding. 2. Welding sequence for each part actually have some varieties depending upon the surrounding circumstances, but in principle, the following sequences are to be kept at every welding stages. 1) Welding is proceeded symmetrically from center of joint both sides. E. G. incase of erection joint. Welding should be done from a mid-ship to stem or stern and from center line of the ship to the direction of side shell. 2) The part where the deformation or residual stress is anticipated to be welded first, and then others to be done secondly. 3. Welding sequence is generally adopted from be assembly stage. 1) Welding of panel.
2) Butt joints are welded prior to welding of seam line.
- 30 -
HALONG SHIP BUILDING Co.
Section 1
Hull construction
* shipbuilding & repair
2) Welding of profiles on panel
Note that a release length of 100mm is provided in the horizontal seams at each corner of the insert plate. 1. Weld framing to within 100mm of un-welded butts and seams. 2. Weld vertical butt
complete
3. Weld vertical butt
complete
4. Weld un-welded framing in way of vertical butts 5. Weld horizontal seam
including release lengths
6. Weld horizontal seam
including release lengths
7. Weld un-welded framing in way of horizontal seams
- 31 -
HALONG SHIP BUILDING Co.
Section 1
Hull construction
3) Welding of insert
- 32 -
* shipbuilding & repair
HALONG SHIP BUILDING Co.
Section 1
Hull construction
4) Penetration parts
- 33 -
* shipbuilding & repair
HALONG SHIP BUILDING Co.
Section 1
Hull construction
* shipbuilding & repair
1.8.2 Slot welding Symbol
Application for thickness
Kind of plate All
t 50.5
w=t t+8 2.25w t<16.0
L<10.0w
Details of weld joints
p>2L
w t/2 vµ w 16 t+8 2.25w t 16.0
L<10.0w p>2L
Beveled angle
Position welding
Application of member
00
All
All
- 34 -
HALONG SHIP BUILDING Co.
Section 1
Hull construction
1.8.3 Bilge keel joint weld Welding detail ( For all type )
- 35 -
* shipbuilding & repair
HALONG SHIP BUILDING Co.
Section 1
Hull construction
* shipbuilding & repair
1.8.4 Stern frame structure 1) Thicker material ( build-up )
Joint Details of Cast Steel Stern Frame 2) Butt joints
Details of butt joints of steel castings/ Forgings and steel plates 3)Lap joints
Details of Lap joints of steel Casting/ Forging and Steel plates
- 36 -
HALONG SHIP BUILDING Co.
Section 1
Hull construction
* shipbuilding & repair
1.8.5 Butt welding on permanent backing - In case where it is method are to be applied, after discussion & approved with class and owner.
Unit: mm Item
Tolerance limits
t 8
3–5
8
5–8
20
t<20
8 – 10
- 37 -
Remarks * Size of backing plates - Normal: 6 - 10
Section 1
HALONG SHIP BUILDING Co.
Hull construction
* shipbuilding & repair
1.8.6 Pre-heating of before welding 1) Environment Proper precaution are to be taken to insure that all welding is done under condition where the welding site is protected against the deleterious effects of moisture, wind and severe cold. 2) Method The use of preheat control are to be considered when higher strength steels, thicker cross section and subject to high restraint. - Range of heating areas: Min.75mm from weld points. - Heating direction: all direction
Item
Control of heat
Which is heat temp’
temp’
Mild steel
-50C
Min 160C
H.T steel
00 C
Min 160C Min 500C
Remarks
- Thicker plate - Restaint structure
TMCP type
-50C
0
Min 20 C
(Ceq 0.36)
- 38 -
HALONG SHIP BUILDING Co.
Section 1
Hull construction
* modification
1.8.7 Bulb plate modification method Existing
L2 Type
* C=15 mm L3 type
* C=15 mm
Joint detail ( L3 type ) Looking down
- 39 -
xcx
HALONG SHIP BUILDING Co.
Hull construction
Section 1
* modification
* Size comparative sheet ID.N
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50
HT
Bulb plate B T
Area
HT
B
L3 Type T1 T2
A
HT
B
L2 Type T1 T2
A
(mm)
(mm)
(mm)
(Cm )
(mm)
(mm)
(mm)
(mm)
(Cm )
(mm)
(mm)
(mm)
(mm
(Cm2)
140 140 140 160 160 160 180 180 180 180 200 200 200 200 220 220 220 240 240 240 260 260 260 280 280 280 300 300 300 300 320 220 320 320 340 340 340 340 370 370 370 370 400 400 400 400 430 430 430 430
19.0 19.0 19.0 22.0 22.0 22.0 25.0 25.0 25.0 25.0 28.0 28.0 23.0 23.0 31.0 31.0 31.0 34.0 34.0 34.0 37.0 37.0 37.0 40.0 40.0 40.0 43.0 43.0 43.0 46.0 46.0 46.0 46.0 49.0 49.0 49.0 49.0 49.0 53.5 53.5 53.5 53.5 58.0 58.0 58.0 58.0 62.5 62.5 62.5 62.5
7 8 9 7 8 9 8 9 10 11 9 10 11 12 10 11 12 10 11 12 11 11 13 11 12 13 11 12 13 14 12 13 14 15 12 13 14 15 13 14 15 16 14 15 16 17 15 17 19 21
12.6 13.8 15.2 14.6 16.2 17.8 18.9 20.7 22.5 24.3 23.8 25.6 27.6 29.6 29.0 31.2 33.4 32.4 34.9 37.3 36.7 36.7 43.9 42.6 45.5 48.2 46.7 49.7 52.8 55.8 54.2 57.4 60.7 63.9 59.8 62.2 65.5 68.9 69.6 73.3 77.0 80.7 81.4 85.4 89.4 93.4 94.1 103.0 111.0 126.0
155 155 155 175 175 175 195 195 195 195 215 215 215 215 235 235 235 255 255 255 275 275 275 295 295 295 315 315 315 315 335 335 335 335 355 355 355 355 385 385 385 385 415 415 415 415 445 445 445 445
20 20 20 25 25 25 25 25 25 25 30 30 30 30 30 30 30 35 35 35 30 40 40 40 40 40 40 40 40 40 45 45 45 45 50 50 50 50 60 60 60 60 65 65 65 65 75 75 75 75
7 8 9 7 8 9 8 9 10 11 9 10 11 12 10 11 12 10 11 12 11 11 13 11 12 13 11 12 13 14 12 13 14 15 12 13 14 15 13 14 15 16 14 15 16 17 15 17 19 21
10 10 10 10 10 10 10 10 10 10 15 15 15 15 15 20 20 20 20 20 20 20 20 25 25 25 30 30 30 30 30 30 30 30 32 32 32 32 32 32 32 32 35 35 35 35 35 35 35 35
12.85 15.6 17.3 15.8 17.7 19.6 19.3 21.4 23.5 25.6 25.2 27.5 29.8 32.1 29.5 33.5 36 34 36.7 39.4 39.9 39.9 45.7 44.1 47.2 50.3 48.3 51.6 54.9 58.2 55.5 59 62.5 66 60.4 64.1 67.8 71.5 71.2 75.2 79.2 83.2 82.95 87.25 91.55 95.85 95.25 104.5 113.7 122.9
140 140 140 160 160 160 180 180 180 180 200 200 200 200 220 220 220 240 240 240 260 260 260 280 280 280 300 300 300 300 320 320 320 320 340 340 340 340 370 370 370 270 400 400 400 400 430 430 430 430
50.0 50.0 50.0 50.0 50.0 50.0 50.0 50.0 50.0 50.0 50.0 50.0 50.0 50.0 60.0 60.0 60.0 60.0 60.0 60.0 60.0 60.0 60.0 62.0 62.0 70.0 75.0 75.0 75.0 80.0 80.0 85.0 85.0 85.0 90.0 90.0 90.0 90.0 90.0 90.0 90.0 90.0 90.0 90.0 90.0 90.0 95.0 95.0 95.0 95.0
7 8 9 7 8 9 8 9 10 11 9 10 11 12 10 11 12 10 11 12 11 11 13 11 12 13 11 12 13 14 12 13 14 15 12 13 14 15 13 14 15 16 14 15 16 17 15 17 19 21
) 10 10 10 10 10 10 10 10 10 10 12 12 12 12 12 12 12 15 15 15 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 25 25 25 25 30 30 30 30 35 35 35 35
14.1 15.4 16.7 15.5 17.0 18.5 18.6 20.3 22.0 23.7 22.9 24.8 26.7 28.3 28.0 30.1 32.2 32.5 33.8 36.0 38.4 38.4 43.2 41.9 48.6 47.8 45.8 48.6 51.4 55.2 52.0 56.0 59.0 62.0 56.4 59.6 62.8 66.0 67.4 70.8 74.3 77.7 78.8 82.5 86.2 89.9 92.5 100.4 108.3 116.2
2
- 40 -
2
HALONG SHIP BUILDING Co.
Section 2
Hull outfitting
2.1 hatch cover ................................................................................. 42 2.2 hatch coaming ........................................................................... 50 2.3 small hatch .................................................................................. 52 2.4 air vent system .......................................................................... 53 2.5 steel inclined ladder……………………………………… 54 2.6 Steel vertical ladder............................................................ 54 2.7 Hand rail........................................................................................ 55 2.8 Storm rail ..................................................................................... 55 2.9 Guard rail ..................................................................................... 55 2.10 anchor chain ............................................................................... 56 2.11 Derrick boom ............................................................................... 58 2.12 derrick boom repair................................................................ 59 2.13 Deck covering ............................................................................. 60 2.14 insulation ..................................................................................... 63
- 41 -
HALONG SHIP BUILDING Co.
Section 2
Hull outfitting
* h/c fabrication
2.1 Hatch cover
Unit: mm Item
Standard
Tolerance
range
limits
1) Hatch cover ( single pull type )
(3
4L ) 10,000
Length ( 1 hatch )
L
5
Length ( 1 panel )
W
3
Breadth
B
3
Height of hatch cover
h
3
4
5 (3
4L ) 10,000
Diagonal difference ( hatch )
(L1-L2)
5
8
Diagonal difference (1 panel)
(L3-L4)
4
6
Vertical deflection
d1
3
4
Transverse deflection
d2
3
4
Deformation of top plate
d3
4
6
Height of packing gutter
d4
1
2
Height of packing gutter
d5
1
2
Breadth of packing gutter
d6
- 42 -
1
2
HALONG SHIP BUILDING Co.
Section 2
Hull outfitting
Item
* H/c fabrication
Standard
Tolerance
range
limits
3
5
Top plate clearance
d7
Top plate difference
(d8)
2
4
Side & end plate difference
(d9)
2
4
Width of packing groove
d10
1
2
Deviation of compression bar centering
d11
3
Compression of packing
d12
3
5
Span ( between centering )
d13
2
3
Installing height
d14
2
3
Installing pitch
d15
2
4
Installing pitch
d16
2
4
Balancing wheel height
d17
2
3
Balancing wheel distance
d18
2
4
Balancing wheel pitch
d19
2
4
- 43 -
t 2
HALONG SHIP BUILDING Co.
Section 2
Hull outfitting
Item
* H/c fabrication
Standard
Tolerance
range
limits
2) Hatch cover ( side rolling type )
(3
4L ) 10,000
Length ( 1 hatch )
L
5
Length ( 1 panel )
W
4
Breadth
B
5
Height of hatch cover
h
3
4
5 (3
4L ) 10,000
Diagonal difference ( 1 hatch )
(L1-L2)
5
10
Diagonal difference ( 1 panel )
(L3-L4)
4
5
Vertical deflection
d1
3
4
Transverse deflection
d2
3
5
Deformation of top plate
(d3)
3
4
Height of packing gutter
D4
1
2
Height of packing gutter
D5
1
2
Breadth of packing gutter
D6
1
2
- 44 -
HALONG SHIP BUILDING Co.
Section 2
Hull outfitting
Item
* H/c fabrication
Standard
Tolerance
range
limits
3
5
Top plate clearance
d7
Top plate difference
(d8)
2
4
Sid & end plate difference
(d9)
2
4
Width of packing groove
d10
1
2
Deviation of compression bar centering
d11
3
Compression of packing
d12
3
5
Span ( between centering )
d13
2
3
Installing height
d14
2
3
Installing pitch
d15
2
3
Installing pitch
d16
2
3
- 45 -
t 2
HALONG SHIP BUILDING Co.
Section 2
Hull outfitting
Item
* H/c fabrication
Standard
Tolerance
range
limits
3) Hatch cover ( folding type )
(3
4L ) 10,000
Length ( 1 hatch )
L
5
Length ( 1 panel )
W
3
Breadth
B
3
Height of hatch cover
h
3
4
5 (3
4L ) 10,000
Diagonal difference ( 1 hatch )
(L1-L2)
5
10
Diagonal difference ( 1 panel )
(L3-L4)
4
5
Vertical deflection
d1
3
4
Transverse deflection
d2
3
5
Deformation of top plate
d3
4
6
Height of packing gutter
d4
1
2
Height of packing gutter
d5
1
2
Breadth of packing gutter
d6
1
2
- 46 -
HALONG SHIP BUILDING Co.
Section 2
Hull outfitting
Item
* H/c fabrication
Standard
Tolerance
range
limits
3
5
Top plate clearance
d7
Top plate difference
(d8)
2
4
Sid & end plate difference
(d9)
2
4
Width of packing groove
d10
1
2
Deviation of compression bar centering
d11
3
Compression of packing
d12
2
3
Span ( between centering )
d13
2
3
Height of wheel
d14
2
3
Distance of wheel & main hinge
d15
2
3
Distance of main hinge & inter hinge
d16
2
3
Distance of wheel & inter hinge
d17
2
3
Gap of main hinge & cylinder pin
d18
3
–
Height of main hinge & cylinder pin
d19
3
–
Height of main hinge
d20
2
3
Height of inter hinge
d21
2
3
- 47 -
t 2
HALONG SHIP BUILDING Co.
Section 2
Hull outfitting
* H/c fabrication
Standard
Item
range
Tolerance limits
4) Hatch cover ( pontoon type )
Length ( 1 panel )
L
5
(3
4L ) 10,000
Breadth
B
5
(3
4L ) 10,000
Height of hatch cover
h
3
4
5
10
Diagonal difference ( 1 hatch )
(L1-L2)
Vertical deflection
d1
3
4
Diagonal difference
d2
3
5
Deformation of top plate
d3
4
6
Height of packing gutter
d4
1
2
Height of packing gutter
d5
1
2
Breadth of packing gutter
d6
1
2
- 48 -
HALONG SHIP BUILDING Co.
Section 2
Hull outfitting
* H/c fabrication
Standard
Item
range
Tolerance limits
4)
Container cone level (20ft)
d7
Container cone level (40ft) Length ( container cone 20ft )
L3
Length ( container cone 40ft ) Breadth (container cone 20ft )
B1
Breadth (container cone 40ft ) Diagonal difference( 20ft )
(L4-L5)
Diagonal difference ( 40ft )
- 49 -
3
4
3
4
3
5
3
5
2
3
2
3
6
8
8
10
HALONG SHIP BUILDING Co.
Section 2
*h/coaming fabrication
Hull outfitting
2.2 Hatch coming 2.2.1 Typical dimension Item
Standard
Tolerance
range
limits
Length
L
5
10
Breadth
B
5
10
Diagonal
(L1-L2)
Straightness of top plate ( side coaming )
d1
3
5
Straightness of top plate ( end coaming )
d2
4
5
Straightness of top plate ( partially/m )
d3
2
3
d4
3
Not
Straightness of hatch coaming ( partially/m)
10
15
defined d5
Straightness of hatch coaming ( all length ) Alignment of wheel & guide rail
d6 - 50 -
(3
–
4L ) 10,000
″ Min.0
HALONG SHIP BUILDING Co.
Section 2
*h/coaming installation
Hull outfitting
2.2.2 Dimension of repair ship Item
Tolerance limits
Length d1 Breadth d2 Diagonal
(L1-L2)
A. H.coaming wall
d1
d2
L1-L2
1) Single pull type
10
10
15
2) Side rolling type
12
12
15
3) Pontoon type
12
12
15
4) Folding type
12
12
15
B. Compression bar fitting Item
Distance
Straight
Level
1) Single pull type
6
7
5
2) Side rolling type
5
5
5
3) Pontoon type
5
5
5
4) Folding type
5
5
5
- 51 -
HALONG SHIP BUILDING Co.
Section 2
Hull outfitting
* small hatch
2.3 Small hatchs
2.3.1 Height ( refer to ILLC code ) 1) Position 1: H=600 mm 2) Position 2: H=450 mm 2.3.2 Dimension & Material. 1)New shipbuilding: As followed design factor. 2) General repair : As followed ship’s drawings. 3) Material: Mild steel ( Normal practice ) 4) Thickness : 10mm or more ( class require ) Item
Standard
Tolerance
a. Width or length d1,2
2
5
b. Difference between diagonal d3
2
-5
c. Straightness/m d4
1
+2
d. Bending/m d5
2
3
* Small steel hatch cover type ( square type )
- 52 -
HALONG SHIP BUILDING Co.
Section 2
Hull outfitting
* Vent/ duct system
2.4 Air vent system 1) Height of air pipe - Position 1: Min 900m - Position 2: Min 760m 2) Height of others. - Refer to design standard or existing ones. 3) Installation/type or size ( shipbuilding ) - Refer to design dwg’ with class and owner requirement representative 4) General repair, when during dry docking for I.L.L Item
Wire net (SUS 304)
Remarks
Float type Air pipe head 2 mesh x # 19 S.W.G Louver and Mushroom vent
10 Mesh x # 31 S.W.G
Insect proof screen
2 Mesh x # 19 S.W.G
Rat proof screen
2 Mesh x # 19 S.W.G
B/fly closing device
- 53 -
HALONG SHIP BUILDING Co.
Section 2
Hull outfitting
* ladder & rail
2.5 Steel inclined ladder 2.5.1 Installation
Unit: mm Degree ( ) 0
Breadth
Pitch
Normal
50 – 55
Min. 600
200 – 280
Tolerance
±50
-
-
Breadth
Pitch
MIN. 600
180 – 230
MIN. 800
250 – 350
2.5.2 Other rule & regulation Authority SBG
( ) 0
45 - 55
0
0
NMD
45
USCG
MAX.450
MIN. 710
-
NSASN
550 – 650
400 – 700
250 – 350
DOT
600
300 – 600
-
Breadth
Pitch ( step )
Depth ( support )
Normal
300
300
150
Tolerance
400
350
180
2.5.3 Clear height
2.6 Steel vertical ladder
- 54 -
HALONG SHIP BUILDING Co.
Section 2
Hull outfitting
2.7 Hand rail
* ladder & rail
Unit: mm Item
Standard
Total height
Min. 1000
Clear lower height
Max 230
Clear middle height
Max 380
Clear upper height
Max 380
Space of stanchion
1200 – 1500
Space of stavs
3600 – 4500
Remarks
2.8 Storm rail
2.9 Guard rail
Gate type guard rail
chain rail type guard rail
DECK
DECK
- 55 -
HALONG SHIP BUILDING Co.
Section 2
Hull outfitting
2.10 Anchor chain cable 2.10.1 Cable measuring
- Measure at 3 links of each shots - Loss limit: B.V = 13.5% Others =12.0% 2.10.2 Stud repair of common link 1) Loose stud: welding ( one side only ) 2) Missing stud: fabrication & welding - Grade U1: SF45 or similar - Grade U2: SF 45 or similar - Grade U3: SF 65 – 70 or similar (T.S: 690 N/mm2) 2.10.3 Shot marking 1) Paint: Kenter shackle : red color : Common links : white color 2) The cotton canvas shall be secured by wire ( sus or copper ) - Detail of cotton canvas
* D: Cable normal diameter
- 56 -
* anchor chain
HALONG SHIP BUILDING Co.
Section 2
Hull outfitting
- 57 -
* anchor chains marking
HALONG SHIP BUILDING Co.
Section 2
Hull outfitting
* derrick boom
2.11 Derrick boom construction Item
Standard
Tolerance limits
l
a. Length d1
7
10
b. Bending d2
5
10
c. Diameter d3
0 - 0.01d
0 + 0.01d
d. Roundness for piece fitting ( At boom seat ) DL- DS
1
0
20
*Boom & piece fitting d
10
20
- 58 -
HALONG SHIP BUILDING Co.
Section 2
Hull outfitting
* derrick boom
2.12 Derrick boom repair 2.12.1 Boom insert repair
- Material: Same as original DWG - Bevel: 45 – 500 - Root gap: 4 – 5mm - Backing: Steel or pipe (Min’ : 5.0t) 2.12.2Boom reinforcement by double plate
- Material : Same as Dwg’ - Thickness: 10t 2.12.3 Test, after repair ( welding ) 1) Butt joint: visual & N.D.T ( P. T or U. T ) 2) Fillet joint: Visual inspection. 2.12.4 Test confirmation of load applied. - Load test: Proof load test with steel weight. * Following I.L.O guidance
- 59 -
HALONG SHIP BUILDING Co.
Section 2
Hull outfitting
* in accommodation
2.13 Deck covering 2.13.1 A- 60 deck covering ( Floating floor type )
STEEL DECK
Vinyl sheet or
7
Finishing material
6
Top coat
Latex + powder
5
Middle coat
Latex + powder
14mm
4
Base coat
Latex + powder
3mm
3
Expanded metal
SS41 (galv’d)
2.3t
2
Mineral wool
40t
d=200kg/m3
1
Silica bond
silica
2mm
No
Description
Material
Size
carpet
- 60 -
1mm or 0.5mm
Q’ty
Remarks
HALONG SHIP BUILDING Co.
Section 2
Hull outfitting
* in accommodation
2.13.2 A-60 deck covering ( Silicate board type )
STEEL DECK
Vinyl sheet or
7
Finishing material
6
Top coat
Latex + powder
5
Middle coat
Latex + powder
10mm
4
Metal lath
SS41 (galv’d)
#22
3
Base coat
Latex + powder
2
Silicate board
1
Silica bond
silica
2mm
No
Description
Material
Size
carper
25mm
- 61 -
Q’ty
Remarks
Section 2
HALONG SHIP BUILDING Co.
Hull outfitting
* in accommodation
2.13.3 Gutter way ( for galley ) (1) SUS type (SUS-304)
(2) Tile type.
2.13.4 Finishing material. (1) Vinyl tile (2) Vinyl sheet (3) Carpet (4) Rubber mat 1) Perforated ( ring ) type: Outside floor 2) Groove type
: inside floor
(5) Tile 1) Non slip quarry tile 2) Mosaic tile 3) Ceramic tile 4) Corner tile 2.13.5 Wooden deck (1) Oregon pine (2) Apiton 3) Red pine (4) Cedar (5) Teak
- 62 -
HALONG SHIP BUILDING Co.
Section 2
Hull outfitting
* in accommodation
2.14 Insulation ( Typical only ) 2.14.1 Deck insulation ( A-60)
2.14.2 Bulkhead insulation ( A-60 ) Vertical section
Horizontal section
- 63 -
HALONG SHIP BUILDING Co.
Section 2
Hull outfitting
* in accommodation
2.14.3 Det. Of insulation bottom
Not sweat gutter way area
Note: finishing material is glass cloth where not covered with lining material
Sweat gutter way area
Note:
1. The A-60 class insulation should be wrapped 380mm to
adjacent deck head and steel bulkhead. 2. Finish material is glass sloth where not covered with lining material. - 64 -
HALONG SHIP BUILDING Co.
Section 2
* in accommodation
Hull outfitting
2.14.4 Pipe insulation method (Typical of prov’ refr’ system )
Sketch
Mark
Name
Material
Pipe
Copper
Insulation mould
Material
Poly ethylene with al-foiled fiber glass cloth
Cable tie Type
Remark
Nylon
P=300(ABT)
Al-foiled fiber glass cloth
0.32mmx8
tape.
100
Application of insulation Piping system
Type of insulation Location Pipe
Flange
Thickness of piping insulation Nom. Dia.
Thickness of insul.
Refrigerant (R-22) pipe (return gas
Provision ref. system
All size
pipe oily)
- 65 -
25mm
Remark
HALONG SHIP BUILDING Co.
3.1
Section 3
Machinery & outfittings
Main engine & shaft line ................................................................ 67
3.2 Rudder arrangement ....................................................................... 69 3.3 steering gear ........................................................................................ 70 3.4 Pintle / bush ............................................................................................ 71 3.5 Rudder repair( structure ) ............................................................ 73 3.6 Rudder repair( jumping ) .................................................................. 73 3.7 Rudder repair ( pintle locking ).................................................. 73 3.8 Rudder repair ( Gudgeon )............................................................... 74 3.9
Rudder repair ( alignment ).......................................................... 75
3.10 Propeller ( iso r4841).......................................................................... 76 3.11 Blade damage repair........................................................................ 79 3.12 Tip preparation for welding........................................................ 80 3.13 Propeller welding............................................................................. 81 3.14 Stern tube............................................................................................... 82 3.15 Tail shaft sleeve limit .................................................................... 82 3.16 Shaft cone ( taper ) part................................................................. 82 3.17 Coupling alignment.......................................................................... 83 3.18 Line shaft alignment ....................................................................... 83 3.19 Aux’ machinery.................................................................................... 84 3.20 D/G engine ................................................................................................ 86 3.21 traveling deck crane ..................................................................... 87 3.22 boiler tube deformation............................................................... 88 3.23 Boiler tube repair.............................................................................. 89 3.24 boiler tube repair.............................................................................. 89 3.25 boiler drum fab’ & welding ......................................................... 90 3.26 Boiler tube joint welding ............................................................. 94
- 66 -
HALONG SHIP BUILDING Co.
Section 3
Machinery & outfittings
* Main machinery
3.1 Main engine & Shaft line
Unit: mm
Item
Standard range
Tolerance limits
1) Seating 8
Flatness of top of main engine bed
12
(before milling) 2) Crank shaft deflection
1 x stroke 10,000
1 xS 10,000
*Note: this range may
* Note: this
be changeable as per
range is repair
maker’s standard
ship practice
3) Installation (1) Contact, ratio - Main engine chock liner
70%
60%
- Bearing chock liner
60%
50%
(2) Clearance between liner and base
0.04
Not defined
(3) Chock fast orange 1. Thickness
t
25-35
2. Metal temperature
Min 12
160C
3. Curing time
130C external heat 210C 12 hour 160C 24 hour 130C 48 hour
- 67 -
HALONG SHIP BUILDING Co.
Machinery & outfittings
Section 3
* Main machinery Unit: mm
Item
Standard range
Tolerance limits
4) Centering ( New shipbuilding ) (1) Diameter of piano wire: d
d=0.7
d=0.7 0.1
(2) Tension of piano wire : t
t=50kg
t=50 5kg
- Dead weight over 100.000 ton: t1
t1 5
t1 8
- Dead weight below 100.000 ton : t2
t2 4
t2 6
(1) Diameter of piano wire : d
d=0.5-0.7
0.1
(2) Tension of piano wire :
t=50kg
10kg
(3) Deviation between rudder center line and shaft center line.
5) Centering ( Repair ship ) t
(3) Deviation between rudder center line and shaft center line.
t1 10 t2 8
- 68 -
HALONG SHIP BUILDING Co.
Section 3
Machinery & outfittings
* rudder
3.2 Rudder arrangement
Unit: mm
Item
Standard range
Tolerance limits
1) Installation (1) Contact ratio
60%
>50%
(2) Clearance between carrier and liner
0.04
<0.05
d<0.3
d 0.5
d<1.0
d<1.5
2) Centering Deviation between center line of rudder carrier and pintle.
3) Centering of repair ship for checking only
- 69 -
HALONG SHIP BUILDING Co.
Section 2
Machinery & outfittings
3.3 Steering gear arrangement
* Steering gear
Unit: mm
Item
Standard range
Tolerance limits
1) Installation (1) Ram cylinder type - Contact ratio - Clearance between liner and base
<0.06
Not defined
(2) Rotary vane type - Contact ratio
Not defined
60%
- Clearance between liner and base 2) Alignment
(d1)
1
(H1-H2)
3) Alignment for general repair
- 70 -
(d1)
0.08
2
(H1-H2)
0.15
d1 1.5
d1 2.0
H1-H2 0.2
H1-H2 0.5
HALONG SHIP BUILDING Co.
Machinery & outfittings
Section 2
* Rudder pintle/ bush
3.4 Pintle/ Bush Item
Standard range
Tolerance limits
1) Contact ratio of cone part
60%
50%
2) Pintle clearance
Builder’s practice
Metal:
3) Material: sleeve
bc/sus, bc/resin
0.8~2.0mm
4) Thickness ( bush/ sleeve)
Non metal: Unit: mm
Dia
<100 100-
150-
200-
150
200
300
1.5~2.5mm >300 Metal:
Sleeve
7.5
9
10
12
15
Bush
10
12
15
20
25
- Sleeve: 6.0 - Bush: 8.0 Non metal
* NK:
- Bush:10.0 - Thickness of pintle sleeve - Thickness of pintle bush
0.03dp+5
- dp<300
0.05dp+5
- dp>300
0.05dp+11
- Thickness of stock sleeve
0.03dp+3
- Thickness of neck bush
0.05dp+2
- dp<300
0.03dp+8
- dp.300 5) Non-Metallic bush material (HMD) * Brand: HFG-LITE CR 510 * Max’ surface pressure: 56kg/cm2 * Class authority: KR, NK, BV, LR, DNV, GL, ABS
- 71 -
Section 2
HALONG SHIP BUILDING Co.
Machinery & outfittings
* Rudder pintle/ bush
3.4.2 Rudder bearing clearance recommended values ● A.B.S guidance Approximately 1% of the pintle diameter to a maximum 6.3mm Other: R/100x3.0 or 0.4 mm/inch ● N.K guidance The limit of wear down of the pintle bush is 5 to 6mm the bearing clearance in diameter, and the neck bearing is 3 to 4mm abnormal wear-down. ● B.V guidance * Pintle diameter 50 to 100 = 5mm * Pintle diameter 100 over = d/100+4 ● Yard guidance * D/100+2= Upper pintle clearance * D/100+3= Lower pintle clearance ● D.N.V guidance I = Renewal necessary II = Renewal recommended III= New/ repaired
● L.R guidance - Recommend: 4.0+0.002 pintle diameter - Renewal: 5.0+0.02 pintle diameter ● K.R guidance - 0.01 Dia’+4mm of pintle - 0.01 Dia’+2mm of neck - 72 -
HALONG SHIP BUILDING Co.
Section 3
Machinery & outfittings
* rudder repair
3.5 Structure welding
Plate thickness
Dimensions ( m)
(mm)
a
b
Up to 6
65
35
7~18
75
40
19
85
45
Kind of fillet weld F1
Slot welding
Aft end construction of rudder 3.6 Jumping stopper
Unit: mm Item
Standard range
The clearance between jumping stopper and
C 2.0
rudder carrier 3.7 Pintle locking Locking device for pintle nut
Locking ring or bar
- 73 -
Tolerance 2.0
HALONG SHIP BUILDING Co.
Section 3
Machinery & outfittings
* rudder repair
3.8 Center of gudgeon Tolerance
1.50mm - Carrier - Upper - Lower
3.8.1 Gudgeon repair ( case 1) 1) Build –up by welding
smaw
2) Re- boring
Machine practice
3) Re- alignment check
Piano wire
3.8.2 Gudgeon repair ( case 2) 1) Boring to oversize
Machine practice
2) Fabricated steel liner
Forged steel
3) Inserted the steel liner
interference 0.005~0.01 T: Min 6.0mm W: 0.35xL
- 74 -
HALONG SHIP BUILDING Co.
Section 3
Machinery & outfittings
* rudder repair
3.9 Rudder alignment Item
Standard range
Tolerance limits
Deviation of height(H)
0.5
1.5
Deviation of center line
0.5
1.5
3.9.1 Adjustment Min thickness
1) Machine-up the palm
0.03 x stock dia 0.04mm
2) Contact ratio
(70%)
3) Distance of bolt hole and flange edge
(50%)
DE: 0.75xF.T
- 75 -
HALONG SHIP BUILDING Co.
Section 3
Machinery & outfittings
* propeller
3.10 Ship Scrw propeller * Refer to ISO 484/1 or 484/2 Ship building manufacture tolerance 1981(E) 3.10.1 Classification Choice of the class should be made by the user: the indications in table 1 below afferent guidance for this choice. Class
Accuracy of manufacturing
Normal use
S
High precision
I and II
Medium precision
For majority of merchant vessels
III
Large tolerances
For vessels without special characteristics
Screw propeller of superior quality for special purposes
Note-class III: Applies in general only to cast iron screw propellers. 3.10.2 Tolerance of pitch Description Local pitch with a minimum of Mean pitch per blade at any radius With a minimum of Mean pitch per blade with a minimum of Total pitch with a minimum of
Class S
I
II
III
1.5%
2%
3%
15mm
20mm
30mm
1%
1.5%
2%
5%
10mm
15mm
20mm
50mm
0.75%
1%
1.5%
4%
7.5mm
10mm
15mm
40mm
0.625%
0.75%
1%
3%
6mm
7.5mm
10mm
30mm
Note: 1. For screw propeller with constant as well as for screw propellers with variable pitch, the pitch of screw propellers according to classes S. I and II should be measured at least on 5 radius ( e.g 0.3R; 0.5R; 0.8R; 0.95R and for class II on 3 radius ( e.g 0.5R; 0.7R; 0.9R ). As far as possible the measurements should be taken on at least 3 point on each radius.
- 76 -
HALONG SHIP BUILDING Co.
Section 3
Machinery & outfittings
* propeller
3.10.3 Surface finish The surface texture of the blades, expressed as an arithmetic mean deviation, R 2 , in micrometers, in accordance with ISO/R 468, shall have a roughness not greater than: - 3 from the hub for propellers of class S; - 6 from the radius 0.3 R for propellers of class I; - 12 from the radius 0.4R for propellers of class II; - 25 from the radius 0.5R for the propellers of class III;
The smoothness of the surface of the propeller blades should be determined by the mean height. Hm of the surface roughness of the blades at least for the radius of the screw propeller over 0.3R.
Hm
1 ( H 1 H 2 ... Hn) n
- 77 -
Machinery & outfittings
Section 3
HALONG SHIP BUILDING Co.
* propeller
3.10.4 Static balancing Unit: mm Item
Standard range
Tolerance limits
Deviation of blade ( maximum )
150
Refer calculation
* Max’ permissible unbalancing mass. ( According to ISO R481/1 1981)
pC
m or Rn2
Km, whichever is the smaller.
P =............................ p=
Km=
x m=
kg
kg
Where : m: propeller weight in (kg) R: propeller radius in meter (m) n: propeller r.p.m C&K: factors of class given. S
I
II
III
C
15
25
40
75
K
0.0005
0.001
0.001
0.001
* Actual unbalancing mass at the blade deviation m: 0.269 =
M .H 0.269 R.Sin kg
Where M: test ( attached) weight in kg H: length of deviation ( Hmax-H min) R: propeller radius in meter Sin : angle of propeller blade (sin 900 : 1.0, 720 : 0.95, 600 : 0.87)
- 78 -
HALONG SHIP BUILDING Co.
Section 3
Machinery & outfittings
* propeller repair
3.11 Damage repair areas 3.11.1 Yard’s practice
R= propeller radius C1= chord length at radius Section
Repair jones of blade
Propeller
A
B
C
D
boss
x
O
O
O
-
Crack part welding
x
O
O
O
O
Partly renew
x
O
O
O
-
Straightening
O
O
O
O
-
Cold straightening
x
O
O
O
-
Grind out
x
x
x
O
-
Kind of repair Damage & cavitation part build up welding
3.11.2 Classification practice * Refer to class permissible rectification range - 79 -
HALONG SHIP BUILDING Co.
Section 3
Machinery & outfittings
3.12 Blade tip repair preparation
- 80 -
* propeller repair
HALONG SHIP BUILDING Co.
Machinery & outfittings
Section 3
* propeller repair
3.13 Propeller welding 3.13.1 Welding process ( refer to W.P.S) 1) minor repair: in use GTAW 2) Major repair: in use GTAW + GMAW 3.13.2 Temperature control 1) Pre heating: propane torch 2) Stress relief: induction PAD/ COIL analysis ( Electric heating element ) 3)Cooling: should be retarded by asbestos blankets. Straightening
Material
Preheat’ Temp 0C
Stress relief Temp 0C
Mn-bronze
150-250
350-550
500-800
NiMn- bronze
150-250
350-550
500-800
NiAl-Bronze
50-150
Kh«ng
700-900
MnAl-bronze
100-250
450-600
700-850
U.T.P
Gricu
Ampco
Temp. 0C
3.13.3 Welding material Material Mn-bronze
A-34
ALBZ-9
Trode 10
Ni-Al-bronze
A-3444
ALBZ-26
Trode 46
Mn-Ni-Al-bronze
A-34N
T-8
Trode 40
AWS SPEC’ = A 5.7 CLASS = ER CU x x x x * Refer to propeller welding procedure
- 81 -
HALONG SHIP BUILDING Co.
Machinery & outfittings
Section 3
* stern tube/ shaft
3.14 Stern tube clearance Item
Standard
Tolerance
Stern tube lignum vitae clearance a. Tail shaft dia < 230mm
4.5mm
6.0mm
b. 230mm
6.5mm
8.0mm
7.5mm
9.5mm
Tail shaft dia < 305mm
c. Tail shaft dia
305
- Builder’s
Stern tube simplex Type clearance
practical Tail shaft dia. ( mm)
400~500 500~600 600~700 700~800 800~900 900~1000
0.7~0.8 0.8~1.0 0.9~1.2 1.0~1.3 1.0~1.4 1.2~1.5
2x Original clearance (builders practice)
3.15 shaft sleeve thickness loss limits N.K.G.L
L.R, DNV
t= 0.03DS+7.5
T=
T1≠3/4T
Remarks
ds 230 32
ds: Shaft dia’ T: Brg’ surface
T1=0.75T
T1: non Brg’ surface
3.16 shaft cone part Item
Standard range
1) Contact ratio of propeller / shaft
90%
2) Shaft crack detection
* Smooth ground
Tolerance limits 70%
* Decide by class / owner for * ABS repair guidance
renewal
- Max’ depth - Max’ length ( total circ’ )
1/4’’(6.35mm) 1/4C(0.25C)
- 82 -
HALONG SHIP BUILDING Co.
Section 3
Machinery & outfittings
* shaft alignment
3.17 Coupling alignment
Unit:
mm Item 1) Simplex ( oil – bath ) type - gap
Standard
Tolerance
range
limits
Builder’s practice
– Sag
0.20 0.30
2) Lignum vitae ( water lub’ ) type
Builder’s
- Gap
practice
- Sag
0.30 0.70
a. Gap = (g1-g2) b. Sag = (s1-s2) 3.18 Line shaft alignment 1) Reaction load on the bearing surface
Builder’s practice
- 83 -
HALONG SHIP BUILDING Co.
Section 3
Machinery & outfittings
3.19Aux’ machinery
* Aux’ machinery
Unit: mm Item
Standard range
Tolerance limits
1) Classification of auxiliary and deck machinery (1) Grade “A” Windlass Diesel generator (2) Grade “B” Turbo generator Mooring winch & turbine Cargo winch (3) Grade “C” Other machineries which are not listed in Grade “A” and “B” 2) Installation (1) Clearance between liner and base Grade “A”
0.04
0.05
Grade “B”
0.08
0.1
Grade “C”
Not defined
Not defined
(2) Liner contact ratio Grade “A”
60%
60%
Grade “B”
50%
50%
Grade “C” (3) Chock fast orange thickness
- 84 -
Not defined
Not defined
25-35t
Min’ 12t
* Other maker
guidance
HALONG SHIP BUILDING Co.
Section 3
Machinery & outfittings
Item
* Aux’ machinery
Standard
Tolerance
range
limits
3) Alignment ( solid type ) Grade “B” only ab 2 Gap b c Sag
S 0.05
Not defined
G 0.07
Not defined
Gap/sag 0.15 Gap/sag 0.18 4) Alignment of deck machinery - Solid type - Shaft type 5) Alignment of pumps ( flexible coupling type )
Gap/sag
- Shaft dia’ <50mm - 50
Shaft dia’<100mm
0.15
- Shaft dia’>100mm
0.20 0.25
- 85 -
HALONG SHIP BUILDING Co.
Section 3
Machinery & outfittings
3.20 Diesel generator
* D/G engine
Unit: mm
Item
Standard range
Tolerance limits
1) Crank shaft deflection - New installation Cold condition
Hot condition
1 x stroke 10,000
2 x stroke 10,000
2 x stroke 10,000
3 x stroke 10,000
2 x stroke 10,000
- General repair ship Cold condition
- 86 -
HALONG SHIP BUILDING Co.
Section 3
Machinery & outfittings
* deck crane
3.21 Traveling deck crane Item
Standard range
Tolerance limits
(1)Installation of rail - Distance between center of rails ( common type )
d1 5
Not defined
- Distance between center of rails ( Gantry type )
Not defined d2 10
- Straightness of rail ( transverse, vertical direction )
Not defined d3 5 (per 10m)
- Difference of height between port and stb’d Not defined d4
8
To be measured at each 5m
- 87 -
HALONG SHIP BUILDING Co.
Section 3
Machinery & outfittings
Item
Standard
*boiler tube damage
Tolerance
* Boilers
3.22 Boiler tube deformation 1. Water tube
d 0.5d
Not defined
d 0.3d
Not defined
* d = tube dia. 2. Smoke tube
* d = tube dia
- 88 -
HALONG SHIP BUILDING Co.
Section 3
Machinery & outfittings
Item
Standard
* boiler tube repair
Tolerance
3.23. Edge preparation of the pipe or tube and cutting of the window patch method A=50 50C
A=50 100
B=1.5 1mm
B= 2 12
3.24 Procedure for effecting a
A=1.5 1mm
A= 1.5 2
permanent repair mono wall tubes.
B=50 50C
B=50 100
C=2 1
C=2 2
( with wedge in place )
- 89 -
HALONG SHIP BUILDING Co.
Section 3
Machinery & outfittings
* boiler repair
3.25 Boiler repair procedure 1. Applicable to aux boiler drum repair ( partly ) 2.Pressure range: 7.0~12.0kg/cm2 3. Material grade: for pressure vessel jis SB410 or similar 4. Working sequence 1) Material confirmation - Same as original maker or similar - Confirmation of the material mill sheet * Class certificate * Chemical composition * Mechanical property 2) Fabrication of the drum shell * To be rolled to circumference( mm in diameter ) 3) Preparation 1) To be made edge shape the end of plate by grinder and machining. 2) Refer to attached joint details. 3) Permissible misalignment at the butt joint - Longitudinal: 1/4t or max’ 3.0mm - Circumferential: 1/4t or max’ 4.0 mm
- 90 -
Section 3
HALONG SHIP BUILDING Co.
Machinery & outfittings
5. Welding 1) Welding is to be performed by approved welders. 2) Preheating : temp: 100-1500C Method: Propane torch. 5-1) Electrodes 1) Manual: S7016-LF (produces by HWMCO ) LB-52 (produce by kobe steel ) 2) TIG : TGS-50 (produce by kobe steel ) 3) MIG: MGS-50 (produce by kobe steel) 5-2) Size of rods 1) Manual: (3.2-5.0 ) 2) TIG & MIG: (1.2-1.6 ) 5-3) Post weld heating ( if necessary ) 1) Temperature: 6250C 250C (According to Class rules ) 2) Holding time : One ( 1 ) Hour/25 t * To be smooth ground to unbeaded weld metal and spatters. 6. Test and inspection 1) Fit –up and Edge – preparation ( Class, Q.C, owner ) 2) Visual inspection after grinding ( Class, Q.C, owner) 3) N.D.T. 3-1) Radiograph test (100%): Drum shell butt & seam joints. 3-2) M.P.I or DYE – check (100%) : Fillet and other joints. 4) Hydro static test: test pressure: D.Px1.5 time 5) Final dimension check if necessary.
- 91 -
* boiler repair
HALONG SHIP BUILDING Co.
Section 3
Machinery & outfittings
Typical joint detail
- 92 -
* boiler repair
HALONG SHIP BUILDING Co.
Section 3
Machinery & outfittings
6.Burner Plate
7. Flue Pipe
- 93 -
* boiler repair
HALONG SHIP BUILDING Co.
Section 3
Machinery & outfittings
3.26 Typical joint of boiler tube within tube nests 1) Plan tube seal welding
2) Stay tube welding
3) Flange connection
- 94 -
* boiler tube joint
HALONG SHIP BUILDING Co.
section 4
piping system
4.1
general .................................................................................................... 96
4.2
Fabrication ............................................................................................ 99
4.3
installation.......................................................................................... 104
4.4
ship side line repair ........................................................................... 106
4.5
Scupper pipe ........................................................................................... 107
4.6 Hull piping in accommodation .................................................... 110 4.7
P.V.C piping in accommodation .................................................... 113
4.8
Pipe support in accommodation ................................................. 114
4.9
hyd-line grade .................................................................................... 115
4.10 piping joints............................................................................................ 116
- 95 -
section 4
HALONG SHIP BUILDING Co.
piping system
* piping grade
4.1 General 1. Grade of pipe The grade specified by each classification society shall be divided as follows (1) LR Grade Service
Class 1 Press.
Class 2 Temp.
Press.
Class 3 Temp.
Press.
Temp.
Steam
P>16.3 or T>300
7.1
P 7.1
T 170
Fuel oil
P>16.3 or T>150
7.1
P 7.1
T 160
Other media
P>40.8 or T>300
16.3
P 16.3
T 200
(2) ABS Grade
Class 1
Service
Press.
Class 2 Temp.
Press.
Temp.
Vapor and gas
P<10.5 or >343
P 10.5
T 343
Water
P<15.8 or T>177
P 15.8
T 177
Lubricating oil
P<15.8 or T>204
P 15.8
T 204
Fuel oil
P<10.5 or T>66
P 10.5
T 66
Hydraulic fluid
P<15.8 or T>204
P 15.8
T 204
Lethal gas & liquids
All
-
-
(3) KR & NK Grade Service
Class 1 Press.
Class 2
Temp.
Class 3
Press.
Temp.
Press.
Temp.
Steam
P>16 or T>300
7
170
P 7
T 170
Fuel oil
P>16 or T>150
7
60
P 7
T 60
Water, lub. oil, comp. air, Hyd.
P>40 or T>300 (Only KR)
oil
16
200
P 16
T 200 (Only KR)
Primary Refrigerant
All
All
-
-
-
-
-
-
-
-
All
All
( ammonia ) Primary refrigerant (R12,R22) - 96 -
HALONG SHIP BUILDING Co.
section 4
piping system
* piping grade
(4) U.S.C.G. Service
Temp (0F)
Class
Pressure ( psig )
I
Any
and
0 and above
Class B&C
I-L
Any
and
<0
poisons
II
(3)
(3)
(3)
II-L
(3)
(3)
(3)
I
>150
or
> 650
Gases and
I-L
>150
and
<0
vapors
II
150
and
0 to 650
II-L
150
and
<0
I
>150
and
0
I-L
>150
and
<0
II
150
and
0
II-L
150
and
<0
or
>330
Liquefied flammable Gasses Molten sulphur Cargo liquids Grades A Through D
I
>225
II
225
I
>225
or
>150
I-L
>225
and
<0
II
225
and
0 to 50
II-L
225
and
<0
and
330
I
>225
or
>400
Cargo liquids
I-L
>225
and
<0
Grade E
II
225
and
0 to 400
II-L
225
and
<0
or
>350
Water Fuel ( bunker diesel, gasoline, etc...) Lubricating oil Asphalt
I
>225
II
225
I
>150
II
150
I
>225
II
225
I
>225
II
225 - 97 -
and or and or and or and
350 >150 150 >400 400 >400 400
section 4
HALONG SHIP BUILDING Co.
piping system
Heat transfer
I
>225
oil
II
225
I
>225
II
225
Hydraulic fluid
* piping grade
or
>400
And
400
Or
>400
And
400
Flammable or combustible dangerous cargoes ..... Refer to specific requirements of Part 40 of this chapter. Other dangerous cargoes .... Refer to specific requirement of part 98 of this chapter. 1. Where doubt exists as to proper classification, refer to the Commandant for resolution. 2. For definitions, see 46 C. F. R Part 30, 151. Note that the category “B” and “C” poison is not used in the rules applying to self Propelled vessels ( 46 CFR Part 153 ). 3. Not permitted except inside cargo tanks approved for Class B and C poison. ( 5 ) D. N. V Piping
Class I
Class II
system
p/bar
0
tC
0
Steam, Fuel
>16
Or >300
16
300
7
170
oil, Other
>16
Or >150
16
150
7
60
media
>40
Or >300
40
300
16
200
p/bar
tC
Class III p/bar
t0C
p: Design pressure, as defined in Sec. 6 A303 t: Design temperature, as defined in Sec.6 A303 1) For Class II and III piping both specified conditions are to be met, for Class I piping one condition only is sufficient. 2) Air, Water, lubricating oil and hydraulic oil. 3) Cargo oil and open ended pipes ( drains, overflows, vents, boiler escape pipes, ... etc ) independently of the pressure and temperature, are pertaining to class III. 4) Thermal oil pipes independently of temperature and pressure are pertaining to class I. 5) Hyd’ oil piping in engine room with design pressure above 40bar are pertaining to class II.
- 98 -
HALONG SHIP BUILDING Co.
section 4
piping system
4.2 Pipe fabrication
* Fabrication
Unit: mm Item
Standard range
Tolerance limits
d= 4
1)Dimension (1) Straight pipe
Not defined
d= 5
(2) Bending pipe
d 10
1 2 2 0
Not defined
(Two dimensional bending )
d= 5 d 10
Not defined
(Three dimensional bending ) (3) Branch pipe
d= 4 d 10
Not defined
(4) Penetration piece
d= 4 d 10 Not defined
- 99 -
HALONG SHIP BUILDING Co.
section 4
piping system
* Fabrication Unit: mm
Item
Standard range
Tolerance limits
2) Attachment of flange to pipe (1) Angle of flange to pipe a 2
Not defined
(2) Distortion of flange face D>200 a 0.5
<1
200 D≤450 a 1
<2
D>450 D: out dia. Of pipe
a 1.5
<2.5
L 5
Not defined
a: max. 1.5
Not defined
(3) Distance between fillet and butt welding bead
(4) Distance between face to flange and welding toe
- 100 -
HALONG SHIP BUILDING Co.
section 4
piping system
* Fabrication Unit: mm
Item 3) Pipe bending
Bending
Pipe
(1) Elliptically (E)
method
material Steek pipe
Cold or
Copper
hot
Dl Ds E x100% D
bending
pipe
D: Out dia of pipe
Al-Br &
R: Bending radius
kunifer
(2) Thickness reduction ratio ( T)
pipe
T
t tr x100% t
t: Original pipe thickness tr: Thickness after bending D: Out dia. of pipe (3) Wrinkle & swelling
H: Height D: Out of pipe
- 101 -
Division
Standard
Tolerance
range
limits
Bending radius 3D R 4D
4D R
E(%)
≤10
≤10
T(%)
≤20
≤15
H
H
E(%)
≤10
≤10
T(%)
≤25
≤20
H
H
E(%)
≤10
≤10
T(%)
≤20
≤15
H
H
1 D 100
1 D 100
1 D 100
HALONG SHIP BUILDING Co.
section 4
piping system
* Fabrication Unit: mm
Item
Standard range
Tolerance limits
4) Sleeve joint (1) Steel a: Min.1.5 l1:
Not defined
Min.10(D≥65A)
″
Min.20(D≤80A)
″
(But max.1 only for U.S.C.G)
(2) Copper , Al-Br
0.05 a 0.15
Not defined
a 1.0
a 1.5
b 0.2
b 0.8
5) Socket joint
- 102 -
HALONG SHIP BUILDING Co.
section 4
piping system
* Fabrication Unit: mm
Item
Standard range
Tolerance limits
6) Welding of steel pipe ( 1 ) Edge Preparation
d
1.6
a = 2.4 ± 0.8
140
0
d1
Not defined
( 2 ) Back bead
d2
( Class I, II pipe )
2
Not defined
0.5
( Other pipe )
( 3 ) Under cut
d
- 103 -
0.3
d
0.8
HALONG SHIP BUILDING Co.
section 4
piping system
* Installation
4.3. installation
Unit: mm Item
Standard range
Tolerance limits
1) Pipe hole cutting & penetration ( 1) Hole cutting
d
D 100
d
D 100
l = 0.1D But min.50
Not defined
T
Not defined
( 2 ) Pipe penetration A-Type
T1
10 ~ 100A
“
b = 30 ± 5
“
125 ~ 500A b = 40 ± 5 “ D- type
550 ~ 700A b = 50 ± 5 “ D1 = D + Max.15
65A & below L = 100
“ Not defined
80a & above L = 150
- 104 -
“
HALONG SHIP BUILDING Co.
section 4
piping system
* Installation Unit: mm
Item
Standard range
2) Alignment
a
Not defined
2
c–b
3) Bolting
Tolerance limits
2
a=0~3
Not defined
a2 + a3 = 0 ~ 3 b1 = 0 ~ 5 threads b2 = 0 ~3 threads H/coil only ( U bolt )
( Flange bolt )
a=1~3 a1 = 0 ~3 a + a1
3
4) Air vent pipe
H = 10
Not defined
5) Sounding pipe
H = 20 ± 5
Not defined
t = 15
6) Dresser coupling
Short type
Not defined
l = 40
d2
5
d1 = ± 5 d2
3
Long type l = 70 d1 = ± 30 d2 - 105 -
6
Not defined
HALONG SHIP BUILDING Co.
section 4
piping system
4.4 Ship side line repair
* Installation
Unit: mm
Item
Standard range
7) Suction mouth ( hull part ) ( 1 ) A – Type Pipe dia. (D)
G
Main suction
80A & below
20
H = ± 10
100A
25
200A
35
Stripping H=±5
( 2 ) B – Type Pipe dia. (D)
G
150A
40
200A
45
250A
55
300A
65
350A
65
400A
75
450A
85
500A
100
550A
110
600A
120
650A
140
- 106 -
Main suction H = ± 10 Stripping ( Including main & stripping ) H=±5
Tolerance limits
HALONG SHIP BUILDING Co.
section 4
piping system
* Installation
4.5 Scupper pipe Tolerance
Item
Limits
For ship side
C
3
Distance
L
15
Piece
D
500 ± 10
C
3
L
15
D
500 ± 10
C
3
L
15
D
500 ± 10
L1
15
L2
15
C
3
D
450 ± 5
For boiler Blow down Distance Piece
For ship side Distance piece
For pad flange
For Echo sound, Pad flange
- 107 -
Remarks
General adapting
Boiler blow down or general adapting
Sea chest on the sea side
BOILER BLOW DOWN ( Soviet Russia Shipyard, but required class surveyor owner )
Style
Standard 10K >SCH’80
Pressure
Remark
thickness
7.0
t(min)
Normal pipe
25A 32
7.5
50 65
9.0
7.6
125
11.0
80
150
12.7
8.6
200
17.4
100
300
1. flange:
remark
1) Existing using
2) Same size use with valve
material
2. Material
component
STPG38 STPT38
flange
pad
SM41, SF45 or S20C
pipe
Note :
1. The carbon content of the
material shall be 0.23% or less.
2. The material of S20C shall be heat treated.
- 108 -
* Installation
piping system section 4 HALONG SHIP BUILDING Co.
Section 4
piping system
HALONG SHIP BUILDING Co.
1) Deck penetration
2) Ship side discharge penetration the hull
3) PCLE deck or weather deck installation
- 109 -
* Scupper piping
HALONG SHIP BUILDING Co.
Section 4
piping system
* hull piping
4.6 Hull piping in accommodation 4.6.1 Detail of welding method 1) Butt weld No.
Methods
Dimension
Application
t 3.2 t=t1 S=2 1 1
1 20 0 S=2 1
Pipe to pipe
2 20 0 B=1.6 0.8
t >3.2 50
1 30 0 00 t=t1 S=2 1 t >3.2
Pipe to fitting ( Elbow,
2 1 10 0 S=2 1
reducer, tee )
50
2 30 0 00 B=1.6 0.8 t = t1 t >3.2 t < t1
S = 2 1
a 1.6 B =1.6 0.8 : Refer to 1 or 2
Specified above. 3
t >3.2
Pipe to pipe or
a>1.6
Pipe to fitting
: Refer to 1 or 2
Specified above t >3.2
- 110 -
HALONG SHIP BUILDING Co.
Section 4
piping system
* hull piping
4.6.2 Weld profiles and tolerance limit for piping ( 1 ) Jointing and welding shall be carried out to have satisfactory weld profiles. ( 2 ) Tolerance limits and repair procedures are as follows. Item
Tolerance
Methods
Limit
Repair procedure When the depth of under
Under cut
D
0.8 mm
cut exceeds the limitation, to be repaired by welding with small dia, electrodes.
All pipes
10
When the tolerance exceeds the limitation, flange to be refitted.
D: Pipe N/D
Alignment
D<200: a
0.1mm
200 D 450: a
2.0mm D>450:
a 2.5mm
L 5mm
Dimension
- 111 -
When the tolerance exceeds the limitation, flange to be renewed.
Section 4
HALONG SHIP BUILDING Co.
piping system
* hull piping
4.6.3 Filet weld ( 1 ) Pipe to flange W: 1.5t but not less than 5mm. C: Maximum 2mm ( not to be tight fit ), but sum of the clearances diametrically opposite is to exceed 5mm. *
t1 : but need not to exceed 0.3T
( 2 ) Pipe to sleeve W : Refer to page 52/86. C : See “ C “ value of pipe to flange weld. * Mark part to be at least 9.5mm
( 3 ) Welding to structure ( for pipe penetration piece ).
- 112 -
Section 4
HALONG SHIP BUILDING Co.
piping system
* hull piping
4.7 PVC A/B class penetration piece type in accommodation * Application : A/B – class steel deck/ bulkhead penetration for PVC pipe.
Pipe
Steel sleeve
H
L
e
50
60
89.1
78.1
6.0
65
76
114.3
102.3
126.6
6.6
75
89
139.8
126.6
151.0
7.1
100
114
165.2
151.0
N.D
O.D
D
d
t
N.D
50
60
89.1
78.1
5.5
65
76
114.3
102.3
75
89
139.8
100
114
165.2
Note : 1) “ PANDA-90” fire sleeve transit device for the penetration of A or B class division for PVC pipe. 2) Noncombustible material certificate of PANDA -90 fire sleeve. LR: SVG/F91/355 DNV: F-11314 ABS: 91-BK-27245-X KR: BU-02901/03 BV: 5031/5042/A1/0 GL: 67951 HH 3 ) *** Mark : PANDA-90 length 180mm, steel sleeve 200mm.
- 113 -
HALONG SHIP BUILDING Co.
Section 4
piping system
* hull piping
4.8 Pipe support for steel and PVC pipe in accommodation 1) Standard distance of steel and PVC pipe ( 1 ) Distance ( interval ) of pipe supports to be based on the flowing table, but may be increased up to the maximum 1.2 times of the standard distance in consideration of hull structure. Steel pipe
PVC pipe
Nom. dia
Out dia.
Distance
Nom. dia.
Out dia.
Distance
(A)
(mm)
(m)
(A)
(mm)
(m)
15
21.7
1.0
20
27.2
1.5
25
34.0
1.5
32
42.7
1.5
40
48.7
2.5
40
48
1.0
50
60.5
2.5
50
60
1.0
65
76.3
2.5
65
76
1.2
80
89.1
3.2
75
89
1.2
100
114.3
3.2
100
114
1.5
125
139.8
3.2
125
140
1.5
150
165.2
3.9
Remark
L=1.2S (L: Maximum allowable distance of pipe supports. S: Standard distance of pipe supports )
Note: Theoretical criteria is guided by a limitation of about 3mm deflection with piping filled fully between pipe supports one another. ( 2 ) Stays for pipe supports to be fitted on or close to stiffening beam as far as possible. ( 3 ) Stays for pipe supports to be sniffed to avoid sharp ends and to be paint finished.
- 114 -
HALONG SHIP BUILDING Co.
Section 4
piping system
* Hyd-line design
4.9 Pipe grade of hyd-line Symbol JIS G 3452
Grade/ name SGP
Range of applicable LOW PRESS SYSTEM * Pump suction pipe MIDDLE PRESS SYSTEM
JIS G 3454
STPG
HIGH PRESS SYSTEM * SEAM LESS PIPE
JIS G 3455
STS
Remark
HIGH PRESS SYSTEM * SEAM LESS PIPE
- W.P≤100kg/cm2 - W.T≤3500 - W.P≥100kg/cm2
HIGH PRESS SYSTEM
JIS G 3459
SUS ( stainless ) (304, 306 TP)
CORROSION RESISTANCE HIGH TEMPERATURE SERVICE SYSTEM
- 115 -
SPECIAL REQUEST ONLY BY OWNER
HALONG SHIP BUILDING Co.
Section 4
piping system
* Hyd-line design
4.10 PIPING JOINTS KIND OF JOINTS Socket welding and threaded fitting
MATERIAL
PIPE DIA. (mm)
WORK PRESS (kg/cm )
SF45 S25C
6A~100A
Max.500
6A~50A
Max.210
15A~80A
Max.210
SUS BsTF4
Sliver brazing fitting
BsBF CNTF1
Square flange
SF45 S25C
Tween ferrule compression fitting
SUS
Max.210 6A~25A
Brass
Max.20
S25C Multi bite type fitting
SUS
Max.250 6A~25A
Brass
Max.100
S25C Flared fitting
SUS
Max.210 6A~25A
Brass
Quick coupling
MATERIAL
2
Max.20
RANGE * STEEL OR SUS PIPE *AL- BRASS * Cu –Ni PIPE * STEEL PIPE * STEEL OR SUS PIPE * COPPER TUBE *STEEL OR SUS PIPE * COPPER TUBE * STEEL OR SUS PIPE * COPPER TUBE
6A~25A
Max.210
* STEEL PIPE
25A~40A
Max.180
IF
50A
Max.140
NECESSARY
- 116 -
HALONG SHIP BUILDING Co.
SECTION 5
PAINTING PART
5.1
PRIMAY SURFACE ................................................................................... 118
5.2
preparation grade…………………………………………………119
5.3
shop priming.......................................................................................... 119
5.4
D.f.t control ( new shipbuilding ) ............................................ 120
5.5
D.f.t control ( repair ship )........................................................... 120
5.6
pre- treatment .................................................................................... 121
5.7
treatment of weld part................................................................ 122
5.8
damage part ......................................................................................... 125
5.9
Management ( pre- coating ) ....................................................... 129
5.10
environmental ( temp/ humidity ) .......................................... 129
5.11
final coat condition ..................................................................... 130
- 117 -
HALONG SHIP BUILDING Co.
section 5
painting part
* steel surface
5.1 PRIMARY SURFACE PREPARATION ITEM
Method
Surface preparation grades Sa2
6 t
Shot blasting
1 2
When shot blasting is considered
Rolled hull
impracticable, sand blasting may be
structural steel
applied. 6>t
Pipe 250 d
Sand blasting Sand blasting or hand/ power tooling
Sa2
1
Sa2
1
2
2
or St2-St3
pickling Hand/ power tooling
Outfitting, pipes, supports,
250>d
seat, etc...
pickling
St2-St3 or Sa2
1
St2-St3 or Sa2
1
2
( Blasting at yard’s convenience )
Support, seats, aux. mach. Etc.
Hand/ power tooling ( Blasting at yard’s convenience )
- 118 -
2
HALONG SHIP BUILDING Co.
section 5
painting part
* steel surface
5.2 PREPARATION GRADE IT is assumed that prior to treatment the steel surface has been cleaned of dirt and grease and that the heavier layers of rust have been removed by chipping. ( 1 ) Sa2 1/2 : Blast cleaning. Very thorough blast cleaning, Mill scale, rust and foreign matter shall be removed to the extent that only traces remaining are slight stains in the form of sports or stripes. Finally, the surface is cleaned with a vacuum cleaner, clean dry compressed air or a clean brush. It shall then correspond in appearance to the prints designated Sa 2 1/2. ( 2 ) St2 : Power tool cleaning Thorough scraping and wire-brushing, machine brushing, grinding –etc. The treatment shall remove loose mill scale, rust and foreign matter. Finally, the surface is cleaned with a vacuum cleaner, clean dry compressed air or a clean brush. It should then have a faint metallic sheen. The appearance shall correspond to the prints designated St2. ( 3 ) St3 : Power tool cleaning Very thorough scraping and wire-brushing, machine brushing, grinding-etc. Surface preparation as for st3, but much more thoroughly. After removal of dust, the surface shall have a pronounced metallic sheen and correspond to the prints designated St3. 5.3 SHOP PRIMING Item Shop primer ( Pre- treatment )
D. F. T 15 5
- 119 -
Surface preparation Shop or sand blasting Sa2 1/2
HALONG SHIP BUILDING Co.
section 5
painting part
* D. F. t Control
5.4 Dry film thickness control ( New ship building ) Item Measuring points
Tanks Outside shell
Standard One point/ five square meters One point/ ten square meters 1. Average dry film thickness of the paint to be attained as the specification. 2. At least 85% of the measuring points to meet the specified film thickness. 3. Min. 85% of the specified film thickness to be attained on remaining 15% measuring points.
5.5 Dry film thickness control ( General repair ship ) Item Measuring points
Tanks Our side shell
Standard One point/ Ten square meters One point / 50 square meters 1. Average dry film thickness of paint to be attained as the specification.
D. F. T Control
2. At least 80% of the measuring points to be met the specified film thickness. 3. Min 80% of the specified film thickness to be attained on remaining 20% measuring points.
- 120 -
section 5
HALONG SHIP BUILDING Co.
painting part
* Pre- treatment
5.6 PRE- TREATMENT FOR PAINTING Kind of paint Item MOISTURE
Epoxy resin
Inorganic zinc
Not to be visible to the naked eye
Salt Oil/ grease
“” Not to be visible. Trace of thinner wiping is permitted
Fat Soap solution Zinc salt Fume by welding or cutting Chalk/ slate pencil mark
conventional
“” White deposits are not to be visible To remove white deposits, but the remaining trace may be visible after sweep-blasting or power tooling Not to be remained. To be wiped with rags or brush. The trace be visible In general, not to be removed. In general,
Marking paint
not be removed
But if highly sophisticated special coating system to be applied,
Not to be
usage of marking paint will be
removed
advised by paint manufacturers. Remaining trace may be visible.
Dust or mud contaminants to be removed with rags, broom or Dust/ mud contamination
vacuum cleaner to the possible extent. Flying or suspension properties of fine-dust which could be excluded by self-pressure of spray – gun may be accepted in the normal shipbuilding practice.
- 121 -
section 5
HALONG SHIP BUILDING Co.
painting part
* Pre- treatment
5.7 TREATMENT AT WELDING PART Item
Remarks Stable spatter contracted surface with mother plate more than two-third of spatter width not to be removed.
1) Spatters
Stable spatters
Stable spatter ( O ) Removable or unstable spatters to be removed with grinder, disc-sander or chipping hammer. Unstable spatters
Unstable spatter ( x ) For non-exposed
Remain welding beads
areas. ( Cargo hold spaces, C. O. tanks, W. B tanks, void spaces, covered parts 2) Repair welding bead of notches
of superstructures, etc... ) Welding and grind flush
For exposed areas. ( Exposed deck, outside shells, engine room passageways etc... )
- 122 -
HALONG SHIP BUILDING Co.
section 5
painting part
Item
* Pre- treatment
Remarks Slag to be removed with grinder or disc-sander up to the standard. But if not completely removes, trace or stain may be left.
3) Slag
Rust and heat scale
4) Rust and Heat scale
- 123 -
HALONG SHIP BUILDING Co.
section 5
painting part
Item
* Pre- treatment
Remarks Weld-fume
5) Weld fume
After secondary surface preparation at each stage, the welding defects found are to be repaired as follows Grade
Area
Defects
Repair Method
Butt & Seam lines 1
of side shell
Blow hole
Welding and
Air, Water tight
pin hole
Grinding
boundaries Blow hole
6) Repair of welding defect
pin hole 2
Major structural
3
members
Blow hole pin hole 3
D
Common members 3
Blow hole
rolled angle, flat
Pin hole
- 124 -
Fill up with epoxy putty “
(Bracket, Stiffeners, bar)
“
( Not welding) Repair
HALONG SHIP BUILDING Co.
section 5
painting part
* damage part
5.8 DAMAGED PART Item
Remarks
Preparation and Feathering
1) Rusted part and block joint ( Wire brushing and/ or disc-sweeping etc... ) The surface between coat and touch-up to be treated with an elaborate workmanship as smooth as possible.
Touch-up
Roughness of the profile after feathering to be treated with an elaborate workmanship as smooth as possible. Roughness
- 125 -
HALONG SHIP BUILDING Co.
section 5
painting part
Item
* damage part
Remarks ( 1 ) In case damage reaches to bare steel:
- Adequate cleaning to bare steel according to the standard referred. 2) Mechanical damage on painted area.
- Repair coating as original system. ( 2 ) In case damage dosen’t reach to bare steel:
- adequate cleaning by appropriate methods to the paint film affected. - Repair touching-up as damaged film. Repair criteria of paint film damages. Profile view of typical.
3) Wooden block boundary area. ( New ship building )
- 126 -
HALONG SHIP BUILDING Co.
section 5
painting part
Item
* damage part
Remarks A’ Detail
Repair method Flat Bottom
1. Scraping 2. Fine papering 3. Touch up as specified delicately. * To be repaired as it is.
- Squeezes - Compression
Spot-rusted part 4) Spot rusted area
- 127 -
HALONG SHIP BUILDING Co.
section 5
painting part
Item
Remarks
5) Burnt part
- 128 -
* damage part
HALONG SHIP BUILDING Co.
section 5
painting part
* environmental
5.9 MANAGEMENT OF PAINTING WORKS 1) pre-coating ( Stripe coat )
2) Overrall coating
Airless spraying or air spaying ( if necessary ) to be applied
5.10 ENVIRONMENTAL STANDARDS
1) Substrate temperature to be kept above 50C 1) Temperature
2) Surface temperature to be kept more than 30C above the dew point.
2) Humidity
Relative humidity to be kept below 85%
- 129 -
HALONG SHIP BUILDING Co.
section 5
painting part
* final condition
5.11 SURFACE CONDITION OF FINAL COATING Item
Where appearance of special importance ( Exposed superstructure, cabin, passages, etc...)
For visible parts other than above ( inside of engine room outside shell, exposed part of decks, stores and cargo hold, etc...)
For invisible part, void spaces and cofferdams, cargo tanks, W. B. tanks, etc...
Check Points
a ) Sagging, missing, brush mark, cracking, wrinkling and holiday are not to be visible. b) color of final coating is not to be different from the specified. c) Spray dust is not to be visible.
a) Missing, cracking, wrinkling and holiday are not to be visible remarkably. b) Sagging and brush mark not to be continued to large extent on the surface. c) Final color is not to be different from the specified color but difference of color by aging at working stage which will be equal in the end is permitted.
a) Missing, cracking and holiday are not to be visible remarkably. b) Heavy sagging are not to be continued to large extent on the surface. c) The difference of the appearance is not to be severe.
- 130 -
HALONG SHIP BUILDING Co.
Section 6
Electrical part
6.1 CABLE INSTALLATION…………………………………………………………………….132 - CABLE WAY - UNDER FLOOR METHOD - CABLE TIE & BAND TAPE - CABLE STAIR - ROUND STAIR - STAIR HEIGHT - CABLE PIPE/ DUCT - CABLE RADIUS ACCEPTANCE - CABLE PENETRATION - METHOD OF ENTERING CABLE INTO EQUIPMENT - DETAIL OF CABLE THROUGH WITH M. C. T 6.2 WEATHER DECK FITTINGS ………………………………………………………………148 6.3 CABLE EXPANSION METHOD ……………………………………………………………150 6.4CABLE CONDUCT EARTH METHOD…………………………………………………… 150 6.5 STANDARD OF OPENING THE HULL ……………………………………………………151
- 131 -
HALONG SHIP BUILDING Co.
SECTION 6
ELECTRICAL PART
Item 6.1. Electric cable installation 1.1 Turning method of main cable ways 1.1.1 In case of same height.
* In case of same height in relation to one and another way. 1.1.2. In case of different height
* In case of different height in relation to one and another way.
- 132 -
* CABLE INSTALLATION
HALONG SHIP BUILDING Co.
SECTION 6
ELECTRICAL PART
* CABLE INSTALLATION
Item 1.1.3. In case of curved way * The cable shall be installed on adequate supporter as shown on following figure.
1.2. Branch cable way ( for example )
- 133 -
HALONG SHIP BUILDING Co.
SECTION 6
ELECTRICAL PART
Item 1.3. Vertical main cable ways
- 134 -
* CABLE INSTALLATION
HALONG SHIP BUILDING Co.
SECTION 6
ELECTRICAL PART
Item 1.4. Under floor method
- 135 -
* CABLE INSTALLATION
HALONG SHIP BUILDING Co.
SECTION 6
ELECTRICAL PART
* CABLE Band
Item 1.5. Cable tie and binding tape 1.5.1. Cable tie * The cable tie to be applied inside of switch board, control console, etc cable fastening.
Symbol
L
Remark
CT- 100
100
MIL – S – 23190 D MS 3367 – 4
Ct – 175
175
MIL – S – 23190
- 136 -
MS 3367 - 1
HALONG SHIP BUILDING Co.
SECTION 6
ELECTRICAL PART
* CABLE Band
Item 1.5.2 Cable binding tape
* These binding tapes shall be used for cable securing and selected in accordance with cable kind and / or their location. P. V. C coated BTN – 3, 4 type shall be used for non-metallic sheath or non-armoured cable others ( BTM-1, 2 ) shall be used for metallic sheath or armoured cable. For cable which are exposed to weather or installed in refrigerated rooms, laundry, etc.. stainless steel tape shall be applied. Symbol
w
t
remark
BTN-1
15
0.5
BTN-2
-
“
stainless
BTN-3
“
“
elec. ‘ glav. ‘ steel ( PVC coating )
BTN-4
“
“
Stainless ( P. V. C coating )
elec.’ glav. ‘ steel
- 137 -
HALONG SHIP BUILDING Co.
SECTION 6
ELECTRICAL PART
* cable stair
Item 1.6 Cable stair 1.6.1 Single stair combined method
Type
Hanger
Runner bar
L
LA – 2
L- 2
25x 6 F. B
LA – 3
L–3
LA – 4
W H < 300
H > 300
200
224
292
“
300
324
392
L–4
38 x 6 F.B
400
424
492
LA – 5
L–5
“
500
524
592
LA – 6
L–6
“
600
624
692
LA - 7
L–7
“
700
724
792
LA – 8
L–8
“
800
824
892
LA – 9
L–9
“
900
924
992
LA – 1m
L – 1m
“
1000
1024
1092
H < 300 = 50 x 6. F. B
H > 300 = 40 x 40 x 5 ANG.
- 138 -
HALONG SHIP BUILDING Co.
SECTION 6
ELECTRICAL PART
1.6.2 Double stair combined method
1.6.3. Reversible single stair combined method.
- 139 -
* cable stair
HALONG SHIP BUILDING Co.
SECTION 6
ELECTRICAL PART
1.6.4 Round type stair
1.6.5 Adjustment of stair height
- 140 -
* cable stair
HALONG SHIP BUILDING Co.
SECTION 6
ELECTRICAL PART
* penetration
Item 1.7 Deck and wall penetration 1.7.1 Collar and coaming Coaming dimension.
NO 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
COAMTING A B 100 60 80 ″ 150 60 80 ″ 100 ″ 200 60 80 ″ 100 ″ 160 ″ 250 60 80 ″ 100 ″ 160 ″ 300 60 80 ″ 100 ″ 160 ″ 200 ″ 350 60 80 ″ 100 ″ 160 ″
n
TYPE
NO
30 40 30 40 50 30 40 50 50 30 40 50 50 30 40 50 50 50 30 40 50 50
1 1 1 1 1 1 1 1 2 1 1 1 2 1 1 1 2 2 1 1 1 2
23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44
- 141 -
COAMTING A B 350 200 400 60 80 ″ 100 ″ 160 ″ 200 ″ 450 80 100 ″ 160 ″ 200 ″ 500 80 100 ″ 160 ″ 200 ″ 600 80 100 ″ 160 ″ 200 ″ 700 80 100 ″ 160 ″ 200 ″
n
TYPE
50 30 40 50 ″ ″ 40 50 ″ ″ 40 50 ″ ″ 40 50 ″ ″ 40 50 ″ ″
2 1 1 1 2 2 1 1 2 2 1 1 2 2 1 1 2 2 1 1 2 2
HALONG SHIP BUILDING Co.
SECTION 6
ELECTRICAL PART
* penetration
Item 1.7.2 Substantial for cable penetration a. Substantial for non-watertight penetration i) In case of no heat resisting steel wall, beam, girdes and long etc... to depend the substantials as shown below.
ii) In case of heat resisting. to be fitted to put about 10mm from the heat resisting surface a shown below.
- 142 -
HALONG SHIP BUILDING Co.
SECTION 6
ELECTRICAL PART
Item b. Substantial for watertight penetration i ) In case of fitting of one by one gland
ii) Assembly fitting stuffing gland.
- 143 -
* penetration
HALONG SHIP BUILDING Co.
SECTION 6
ELECTRICAL PART
Item 1.7.3. Method of entering cable into equipment a. For water tight gland
b. For coaming
- 144 -
* method of entering cable
HALONG SHIP BUILDING Co.
SECTION 6
ELECTRICAL PART
Item 1.7.4 Detail of cable through deck & wall a. A and B class steel Wall i) Rectangular collar type
ii) Round collar type
Cable
- 145 -
*wall collar
HALONG SHIP BUILDING Co.
SECTION 6
ELECTRICAL PART
Item b. A class deck i ) Rectangular coaming type
ii ) Round coaming type
- 146 -
* coamings
HALONG SHIP BUILDING Co.
SECTION 6
ELECTRICAL PART
Item c. Multi cable transit For A class deck in electric cable trunk shall be supplied.
- 147 -
* M. c. t
SECTION 6
HALONG SHIP BUILDING Co.
ELECTRICAL PART
* fittings installation
6.2 WEATHER DECK FITTINGS 2.1 Distance between steam pipe to cable
2.2 Cable grand install
2.3 Cable pipe thickness range for on deck and W.T or F.O tank penetration parts. PIPE INTERNAL DIAMETER ( I. D )
MINIMUM THICKNESS
ID < 57.0
4.0
57.0
4.5
ID <152.4
152.4
ID <304.8
5.5
304.8
ID
UNACCEPTABLE
- 148 -
HALONG SHIP BUILDING Co.
SECTION 6
ELECTRICAL PART
- 149 -
* fittings installation
HALONG SHIP BUILDING Co.
SECTION 6
ELECTRICAL PART
6.3 CABLE EXPANTION METHOD * MINIMUM RADIUS: CABLE O.D x 12 Times 3.1. CABLE HANGER TYPE
3.2. CABLE PIPE TYPE
6.4 CABLE CONDUCT EARTH METHOD
- 150 -
* cable expansion
SECTION 6
HALONG SHIP BUILDING Co.
ELECTRICAL PART
* HULL OPENING METHOD
6.5 STANDARD OF OPENING 5.1 TYPICAL
SPACE CONPENSATION
“A” SPACE
“B” SPACE
WITHOUT
WITH
WITHOUT
WITH
CARGO OIL
d 1/5D
d 1/2D
d 1/10D
d 1/4D
TANK
MAX=300
MAX=300
CARGO HOLD
d 1/4D
d 1/2D
d 1/8D
d 1/4D
d 1/3D
d 1/2D
d 1/6D
d 1/4D
d 2/5D
d 1/2D
d 1/5D
d 1/4D
d 3/5D
d 2/3D
-
-
POSITION
REMARK
GIRDER, WEB
ENGINE ROOM SUPER STRUCTURE
SOILD FLOOR, CONFFERDAM WEB DOUBLE BOTTOM SIDE GIRDER, DIAPHRAGM * NOTE:
GENERALLY IN “ C” SPACE, OPENING SHOULD NOT BE CUT, IF UNAVOIDABLE FOR PIPING, ETC.. OPENING COMPENSATION SHOULD BE DESIGNED AFTER CONSIDERING TYPE OF STRUCTUAL MEMBER AND ITS SIZE OF LOAD, ETC. IF TO BE FITTED DOUBLING PLATE COAMING ( RING ) S1 = ( S – 1/2h ).
- 151 -
section 6
HALONG SHIP BUILDING Co.
electrical part
* hull opening method
5.2 MIN. DISTANCE BETWEEN HOLE & HOLE, HOLE & END OF STRUCTURE MEMBER A SPACE
B SPACE
C SPACE
1) HOLE AND HOLE
S
d1 d 2 2
S=d1+d2
1 d 2
S=d
2) HOLE AND DECK S
3) HOLE AND FACE BAR S=d
S=2+d
(Min.75mm)
(Min.75mm)
4) HOLE AND SCALLOP
S
d r 2
(Min.50mm)
S=d+R (Min.50mm)
5) HOLE AND SLOT
IF S S
Bd 2
S=B+d
Bd 2
S=B+d TO BE FITTED COLLAR PLATE
* NOTE: GENERALLY WHEN DOUBLING PLATE OR F.B COAMING HAD SAME AS HULL THICKNESS TO BE DESIGENED, “S” MAY BE REDUCED BY HALF OF DOUBLING PLATE OR F.B COATING. HOWEVER “ S” IS NOT TO BE LESS HALF OF STANDARD. - 152 -
HALONG SHIP BUILDING Co.
section 6
electric part
* hull reinforcement
5.3 HULL STRUCTURE OPENING HOLE REINFORCEMENT METHOD 5.3.1 DOUBLE PLATE INSTALL
a
b/2
t1
t
5.3.2 RING STIFFENER INSTALL
a
b/2
t1
t
d
Min. 25
5.3.3 PARTIAL INCREASING OF WEB DEPTH.
a
1.5h
b
L
h
3d-H - 153 -