JOB HAZARD ANALYSIS WORKSHEET
307013-W
PROJECT MAJOR WORK ACTIVITY LOCATION SIMOPS DESCRIPTION OF CONCURRENT ACTIVITIES NO 1.
B11LQ HUC PROJECT B11 LQ JHA 23
COLD CUTTING IN OPEN AREA B11 - LQ ü Production Online
B11DR-A Shut down but pressurised
Shut down but not pressurised
MECHANICAL EQUIPMENT & ASSOCIATE PIPING INSTALLATION, CABLES PULLING, GLAND & TERMINATION SCAFFOLDING WORKS & COMMISSIONING WORKS
GUIDEWORD
CAUSES
Increased ingition Euipment over heated, sources Welding, Cutting & Grinding
2.
Unignited HC release– N/A Toxic/Asphyxiatin g Release
3.
High Pressure Liquid / Gas Release
Actylene & oxy hoses parted or burst,Defective cutting torch, Equipments failure, gas leak from existing piping system
4.
High / Low Temperature Liquid / Gas
Hot Surface, Weather, Air supply hoses parted,Oxy & Actylene parted
5.
Dropped Fualty Lifting Equipment, Objects/Swinging Crane Operation & Capacity, loads Loose Materials , Weather
6.
Ship Impact
N/A
7.
Structural Failure / Buoyancy Loss
Weldings and Cutting
P
BEFORE A E R
3B 3B 3B 2B
CONSEQUENCES Fire, explosion, personnel injury
3B 2B 2B 2B Explosion , Personnel injuries or Fire, Clear Accessway & Escape Route,
Personnel injuries, 3B 3B 3B 2B
CONTROLS, BARRIERS
P
AFTER A E R
Fire Extinguishers & Firewatcher on standby, Welding habitat to contain all sparks
Properly secured all fitting and connection, Clear Accessway & Escape Route,Gas test before start any works,Fire extingusher,Firewatcher on standby Wear proper PPE, Fire Extinguisher, Firewatcher on standby & Obey Safety signage
ACTION PARTY/DATE The machine is fitted wirh spark Huc Team / arrestor,Moving parts fitted with Welders /Millwrights Guard,M-oil at the right and Pipe Fitters 0 level,Machine properly grounded Fire extinguisher & Fire watcher on standby RECOMMENDATION
1B 1B
0
1B
0
0
0
Always be alert of your Huc Team / Riggers surrounding, Proper PPE, Keep / Welder & 0 walkway clear & Escape Clear pipefitter at all time
0
1B 1B
3B 3B 2B 2B Personnel injury, Properties & Equipment Damage
Inspect all lifting equipment prior 1B 1B 0 to use, Clear Communication between crane operator & rigging supervisor & signalman, tag line in place place, Secure all loose materials
2B 2B 2B 1B Structure damage
Welding Procedures in place
1B 1B
0
0
Properly Secure all fitting Huc Team / Riggers &hoses connections, Clear Welders & Pipe Accessway & Escape Route Fitters PTW Gas test before start any works, Fire extinguisher,Firewatcher on stadby
Proper job planning, coordination, Communication between all parties
0 Proper Welding Procedures Regular inspection & Supervision
Huc Team / Rigging Team/Boat / Crane operator
Huc Team/ QC/Structural Welders & fitters
JOB HAZARD ANALYSIS WORKSHEET
307013-W
PROJECT MAJOR WORK ACTIVITY LOCATION SIMOPS DESCRIPTION OF CONCURRENT ACTIVITIES NO 8.
B11LQ HUC PROJECT
B11 - LQ ü Production Online
CAUSES Incorrect handling Technique Lifting Equipment Failure
9.
Chemical Handling
B11DR-A Shut down but pressurised
Shut down but not pressurised
MECHANICAL EQUIPMENT & ASSOCIATE PIPING INSTALLATION, CABLES PULLING, GLAND & TERMINATION SCAFFOLDING WORKS & COMMISSIONING WORKS
GUIDEWORD Manual Handling
B11 LQ JHA 23
COLD CUTTING IN OPEN AREA
BEFORE CONSEQUENCES P A E R 2B 2B 2B 1B Personnel injury, Slip , Trip & Fall Fall
CONTROLS, BARRIERS Proper Handling Techniques, Housekeeping, Clear accessway , Escape Route Use correct tool
P 1B
AFTER A E R 0 0 0
RECOMMENDATION Proper Handling Techniques, Housekeeping,Clear accessway , Escape Route,Use correct tool
N/A
ACTION PARTY/DATE Huc Team / Riggers / Scaffolders
10. Access / Egress
Poor housekeeping, blocked accessways / escape route
2B 2B 2B 1B Personnel injury , slip ,Trip, Fall
Good Housekeeping , Clear Accessway , Escape Route
1B
0
0
0
Good Housekeeping, Clear Accessway & Escape Route
Huc Team / riggers/ pipe fitters
11. Escape/Evacuatio n
Poor housekeeping, blocked accessways/ escape route
2B 2B 2B 2B Personnel injury, trap, Slip , Trip and Fall
Good Housekeeping , Clear Accessway , Escape Route
1B
0
0
0
Good Housekeeping, Clear Accessway & Escape Route
Huc Team / riggers/ fitters
Proper H2S detection & escape equipments, Clear Accessway & Escape Route
1B
0
0
0
Proper training & provision of equipments , Clear Accessway & Escape Route
Huc Team / Riggers/ fitters
Grounding in place,personnel competency,PTW
1B
0
0
0 Proper training & provsision of equipment, Don’t repair any electrical equipment if you are qualified
1B
0
0
0 Proper H2S Detector, Escape Huc Team / riggers/ equipment, TBM, Proper PPE, fitters Obey Safety Signage
1B
0
0
0
12. Location / Escalation
H2S area, weather, Congested 3B area
0
13. Electricity
Source from welding machine, grounding & live equipment at vicinity,damage equipment
2B 2B 2B 2B Personnel injury ,electric shock, death
14. Working Conditions, e.g. heat, noise, bad weather etc
H2S Area , Direct Sunlight , Congested Area, Noise from Running Equipments , Bad Weather
3B
15. Cold cutting in open area
Broken hacksaw blade or cutting machine bits
3B 2B 1B 1B Personnel injury
0
3B 3B Personnel injury & Slip , Trip and Fall.
3B 3B Personnel injuries , Heat Proper H2S detector & Escape Stroke, Hearing lose & Health Equipment , Ear plug & Proper Problem PPE Obey Safety Signages Wear safety glasses/face shield, handglove
Concurrent Activities Not Permitted/Restricted: 1) Restrict rigging and lifting activities when divers are in water. 2) Hot works will be restricted during operation activities which results in hydrocarbon release to atmosphere.
Wear safety glasses/face shield,handgloves
Huc Team / electrician
Huc Team / riggers