PIC has submitted EOT claims. Awaiting for Approval
4
4
16
Early approval is required so practical schedule could be followed.
RIBEX11
Construction of Water Tank & Pump Room
Late construction can lead to delay in start of Exp‐C
4
4
16
Need to start construction of Water Tank immediately
RIBEX12
Provisional Sum ‐ Elevators & Escalators
Suplier for Elevators and Escalators has been finalized by ALG.
3
4
12
RIBEX13
Provisional Sum ‐ Light Fittings
Late Decision can lead to delay in procurement and hence completion of project
3
3
RIBEX14
Extensionof Time (EOT) Claim (Rev‐02)
Late approval will lead to ambiguous dates for activities.
3
RIBEX15
DEWA approved Drawings for Sub‐station ‐ A
RIBEX16
ALG
Managed
31‐Aug‐14
ALG / PIC
I mp ac te d
3 0‐Sep‐14
Early decision are required to avoild delay
NA KH EE L/ AL G
A cti ve
30‐Sep‐14
9
Early decision are required to avoild delay
NA KH EE L/ AL G
A cti ve
30‐Sep‐14
4
12
ALG & Nakheel has to review Claims at earliest so PIC would be able revise Baseline program as per approval
NA KH EE L/ AL G
A cti ve
30‐Sep‐14
4
3
12
ALG / P IC
M an ag ed
DEWA approved Drawings for Sub‐station ‐ B
4
3
12
ALG / P IC
M an ag ed
RIBEX17
DEWA approved Drawings for LV Room ‐ C
4
3
12
ALG / P IC
M an ag ed
RIBEX18
Approval of Sub Contractors & Design of Pile Works
3
3
9
ALG / P IC
M an ag ed
RIBEX19
Approval of Sub Contractors & Design of Precast Slabs A & B
3
3
9
ALG / P IC
M an ag ed
RIBEX20
Precast Beams and Slab for Exp ‐ C
3
3
9
ALG / PIC
Open
RIBEX21
Approval of Sub Contractors & Design of Steeel structure
3
3
9
ALG / PIC
Active
RIBEX22
Approval of Supplier and Material of FAHU
3
3
9
ALG / PIC / CON
Managed
RIBEX23
Approval of Subcontractor and Material for Aluminum Works
3
3
9
ALG / PIC
Active
RIBEX24
Approval of Supplier / Sub‐con and Materials for Fire Fighting Works
3
3
9
ALG / PIC
Active
RIBEX25
Approval of Supplier / Sub‐con and Materials for Fire Alarm System
3
3
9
ALG / PIC
Active
RIBEX26
Approval of Supplier and Material for LPG Works
4
4
16
ALG / PIC
Active
RIBEX27
Material for Flooring
3
3
9
ALG / P IC
P ro po se d
RIBEX28
Completion / Inspection of Substation ‐ A
3
3
9
PIC / CON
Proposed
RIBEX29
Completion / Inspection of Substation ‐ B
3
3
9
PIC / CON
Proposed
RIBEX30
Completion / Inspection of LV Room ‐ C
3
3
9
PIC / CON
Proposed
RIBEX31
Laying of HV Cable and installation of Transformer
3
4
12
PIC / CON
Acti ve
Switch
from Old Sub
Substation
Since relocation of Exisiting HV cable is required to proceed for work thereore early resolution of the issue is required to avoid further delay in Exp C