RENCANA ANGGARAN BIAYA PENGAWASAN SATKER SNVT
:
PENGEMBANGAN PRASARANAN DAN SARANA PERDESAAN
PEKERJAAN
:
PENGAWASAN / SUPERVISI KONSTRUKSI
LOKASI
:
THN ANGGARAN
:
I.
BIAYA PERSONIL
No.
I
URAIAN KEGIATAN
VOLUME KEGIATAN
Harga Satuan (Rp)
Jumlah (Rp)
Harga
BIAY BIAYA A LAN LANGS GSUN UNG G PER PERSO SONI NIL L (RE (REMU MUNE NERA RATI TION ON))
41,305,800.00
A.
18,900,000.00
TENAGA AHLI 1. Tim Leader
B.
Org / Bulan
1 x 3
6,300,000.00
Org / Minggu
3 x 2.5
2,400,000.00
2. Operator Komputer
Org / Bulan
1 x 3
943,600.00
2,830,800.00
3. Office boy
Org / Bulan
1 x 3
525,000.00
1,575,000.00
BIAYA LANGSUNG NON PERSONIL (REINBURSABLE COST) A.
18,900,000.00 22,405,800.00
TEN TENAGA AGA PEN PENDU DUK KUNG UNG 1. Inspector
II
SATUAN KEGIATAN
18,000.00
1,105,800.00
PERJ PERJAL ALAN ANAN AN DINA DINAS S
990,000.00
1
Tim Leader
Org - Trip
1 x 3
110,000.00
330,000.00
2
Inspector
Org - Trip
3 x 2
110,000.00
660,000.00
B. BIAYA KANTOR
10,068,000.00
1 Pera Perala lata tan n Kant Kantor or
3,150,000.00
a. Sewa Komputer lengkap
Unit - Bulan
1 x 3
1,050,000.00
3,150,000.00 3,750,000.00
2 Oper Operas asio iona nall K Kan anto torr a. Perlengkapan ATK
Bulan
3
550,000.00
1,650,000.00
b. Biaya Listrik, Telepon
Bulan
3
700,000.00
2,100,000.00 3,168,000.00
3 Biay Biaya a Pela Pelapo pora ran n 1. Dokumen laporan mingguan
Eks
72
24,000.00
1,728,000.00
2. Dokumen laporan bulanan
Eks
18
38,000.00
684,000.00
3. Dokumen laporan akhir
Eks
6
126,000.00
756,000.00