this is our project sample for those who need it u can use some of our idea but don't copy itFull description
Example of a Project Proposal
Sample Project Quality Plan
ERP Project Report
Sample project management plan for a community garden projectFull description
Primavera Project Planner Sample Project Prepared by: Luay Dwaikat, MSc. Construction Management 1) Project information: Schedule the following project using Primavera Project Planner considering that the project will start on 1 Jan. 07 without any day off.
Unit price ($) 40 / hr 7 / day 10 / day 11 / day 10 / day 3 /hr 2/m 3 40 / m 200 / ton 2 / m2
3) Three engineers are available and they will be responsible as follows:
S.n
Engineer
Responsible for
1
Ahmad – site engineer
Foundation Inspection Ground slab Columns
2
Ali – excavation engineer
Excavation Leveling Anti-termite
3
Sami – mechanical engineer
Plumbing
Using Ms project 2007, answer the followings: 1) 2) 3) 4) 5) 6)
When will the project end? What is the total project cost? What is the total concrete cost in the project? What is the total steel cost in the project? th How many helpers should be available at site in 5 of Jan.? Assume that you have just 10 helpers in the site, what would be changed in the project?
Luay Dwaikat
2
4) Progress Update: th
The site feedback indicates the following activities status in 18 of Jan 2007:
S. N. 1 2 3
Activity Description Excavation leveling anti termite
Original Duration 1 9 5
Remained Pct Duration 100 % 0 100 % 0 100 % 0
4
Foundation
5
0
100 %
5 6 7 8
inspection Ground slab Plumbing Columns
4 4 6 1
0 4 0 1
100 % 0% 100 % 0%
Notes Started & finished on time Started & finished on time rd Started on 3 of Jan. and Delayed tow days th Started on 12 of Jan. and Delayed one days th Started on 8 of Jan th Started on 18 of Jan Started & finished on time --
Using Primavera Project Planner, update your schedule and answer the followings:
1) 2) 3) 4)
When will the project end? What is you project total cost? What is your actual cost (ACWP) up to date? How much is your cost variance (CV)? and WHY?