SOUTH AFRICAN COUNCIL FOR PROJECT AND CONSTRUCTION MANAGEMENT PROFESSIONS (SACPCMP)
LOG BOOK FOR REGISTERED CANDIDATES
NAME OF THE CANDIDATE:
JOSCELYN BERNARD NARTEY
DURATION OF CANDIDATURE:
FOUR(4) YEARS
REGISTRATION NUMBER:
B/903/2010
Application for Registration as a Professional Construction Project Manager submitted by JOSCELYN BERNARD NARTEY (PrCPM (Cand) ) – Sept 2017: CANDIDATE LOG BOOK 111/30
I. CANDIDATURE PLAN NAME OF CANDIDATE:
JB Nartey
REGISTRATION NO.:
B/903/2010
DURATION OF CANDIDATURE:
4 years
CANDIDATURE GOALS
Provide the candidate with experience to practice and apply project management methods to a real life project
Project Stage
Minimum 1600-3000 man-ho urs
Stage Description
PMBOK Area
Time Allocated (Man-hours)
Planning & Integratio n
124
2 010
J
1
2
3
4
5
6
Project Initiatio n & Briefing
Concept & Feasibility
Design Development
Tender Documentation & Procurement
Construction Documentation & Management
Project Close out
Total s
Scoping
160
Stakeholders
340
Candidate Interviews/Evaluation
2
Planning & Integratio n
200
Scoping Procurement
200 200
Candidate Interviews/Evaluation
4
Scope
200
Time
200
C ost
200
Quality Communication
200 200
Risk
200
Candidate Interviews/Evaluation
2
Scope
100
Communication C ost
100 100
Risk
100
Quality
100
Candidate Interviews/Evaluation
4
Communication
250
C ost Risk
120 60
Candidate Interviews/Evaluation
4
Procurement
0
Planning & Integratio n
66
Resource Candidate Interviews/Evaluation
0
F M A M J
J
20 12
A S O N D J
F M A M J
J
201 6
A S O N D J
F M A M J
J
2 3 436
Milestone Achievements
Application for Registration Registration as a Professional Construction Construction Project Manager Manager submitted by JOSCELYN BERNARD NARTEY (PrCPM (Cand) ) – Sept 2017: CANDIDATE LOG BOOK 211/30
II.A. RECORD OF PRACTICE- WORK-BASED ACTIVITIES
2 017
A S O N D J
F M A M J
J
A S O N D
II.A. RECORD OF PRACTICE- WORK-BASED ACTIVITIES
Application for Registration as a Professional Construction Project Manager submitted by JOSCELYN BERNARD NARTEY (PrCPM (Cand) ) – Sept 2017: CANDIDATE LOG BOOK 311/30
RECORD OF PRACTICE REPORT
YEAR
2010
PROJECT DETAILS 2010 Legacy projects ;Upgrading of Buffalo City(ABSA) Stadium
PROJECT NAME PROJECT DESCRIPTION
Rehabilitation & Expansion of Existing sports facilities at the Buffalo City(ABSA) Stadium to ensure that it is used as a training base camp for 2010 World Cup.
DURATION
START DATE
June, 2008
30th June, 2010
END DATE
Project Coordinator/Leader
PROJECT ROLE
EMPLOYER'S DETAILS DBSA Deployee/Technical Expert DBSA ( Co-Funder)
JOB TITLE NAME OF EMPLOYER SUPERVISOR'S NAME/CONTACT DETAILS
Ayanda Skewbu, 043-7052834 043-7052834
CANDIDATE ACTIVITY REPORT PROJECT STAGE G N I F E I R B & N O I T A I T I N I 1
PMBOK AREA
Drafted a Business Case/Plan for the project Drafted IPIP/Memorandum of Agreement(MOA)/SLA Agreement(MOA)/SLA between t he Planning & Integration implementing agent(BCM) & EC DSRAC( Sponsors)
Stakeholders Planning/ Integration
Y T I L I B I S A E F & T P E C N O C . 2
Procurement
Stakeholders Time
T N E M P O L E V E D N G I S E D . 3
ACTIVITY/TASK PERFORMED
Cost
START DATE 20/07/2008
29/09/2008
29/09/2008
30/09/2008
Organised and Conducted a Project Launch Meeting for the project
27/11/2009
Facilitated stakeholder engagements engagements on the scope o f works; proposed list of stadia facilities to be targeted for beneficiation.
30/06/2008
Developed an Inception Report for the Project
29/09/2008
01/10/2008
Drafted a Project Procurement Strategy/Plan for the procurement of professional service providers
31/10/2008
20/11/2008
Prepared Project Brief/TOR/RFP for the appointment of Consultants or professional team or consortium(PSPs)
23/01/2009
Conduct and recorded proceedings of Tender Briefing & Site Inspection Session for Professional Service Providers
17/02/2009
Drafted an Addendum to the alterations/additions to the EOI for the Professional Service Providers
20/02/2009
Risk Planning/Integration Procurement
MAN-HOURS EARNED 40 8 8 4 16
16 16 4 2
Prepared an Evaluation Report of the received EOIs from the professional service providers
11/05/2009, 15/06/2009,10/07/2009
Evaluation of Tenders & Preparation of Tender Evaluation Report for PSPs
10/03/2009, 25/05/2009
12 16
Drafted appointment letters for PSPs
16/04/2009
1
Drafted PSP Agreements
11/08/2009
1
Drafted a stakeholder engagement strategy for the project
23/03/2009
6
Prepared a tentative implementation program for the procurement and construction stages
02/03/2009
8
Agreed with BCM on the financial reporting, institutional systems and processes including policies for the program
30/11/2008
2
Monitored and Cordinated the preparation of the Project Capital Cost Estimates
11/09/2009
Prepared the 3-year MTREF MTREF Capital budgets for multi-year medium term projects
Quality
END DATE
Secured and agreed on the design and maintenance guidelines for the sports facilities in line with FIFA requirements
13/10/2010
20/11/2008
30/11/2008
29/04/2009
Development of a Risk Register Quarterly Updated the IPIPs and Cashflow Budgets
12/10/2010
40 8
8 8
1/O7/2008
30/06/2010
16
Drafted a TOR/RFP for t he he so lilicitation of So ci cial Facilitation Services 09/07/2009
10/07/2009
16
Application for Registration as a Professional Construction Project Manager submitted by JOSCELYN BERNARD NARTEY (PrCPM (Cand) ) – Sept 2017: CANDIDATE LOG BOOK 411/30
RECORD OF PRACTICE REPORT( CONT'D)
PROJECT NAME PROJECT DESCRIPTION DURATION PROJECT ROLE JOB TITLE NAME OF EMPLOYER
YEAR
2010
PROJECT DETAILS 2010 Legacy projects ;Upgrading of Buffalo City(ABSA) Stadium Rehabilitation & Expansion of Existing sports facilities at the Buffalo City(ABSA) Stadium to ensure that it is used as a training base camp for 2010 World Cup. 30th June, 2010 June, 2008 START DATE END DATE Project Coordinator/Leader EMPLOYER'S DETAILS DBSA Deployee/Technical Expert DBSA
SUPERVISOR'S NAME/CONTACT DETAILS
( Co-Funder)
Ayanda Skewbu, 043-7052834
CANDIDATE ACTIVITY REPORT PROJECT STAGE
PMBOK AREA
ACTIVITY/TASK PERFORMED
Drafted Letters to Bidders informing/Soliciting acceptance of Change of Scope
Communication
Cost
T N E M E R U C O R P & N O I T A T N E M U C O D R E D N E T . 4
Risk
Quality
Planning/ Integration
Procurement
Stakeholders
Drafted a response to the procurement objection to the contract award raised by a tenderer
START DATE
3 0 / 0 7 /2 0 0 9
END DATE
MANHOURS EARNED
3 1 /0 7 /2 0 0 9
19/10/2009
2
2
Drafted a letter of motivation for additional funding to the project sponsors;DSRAC
1 4 / 0 8 /2 0 0 9
2 0 /0 8 /2 0 0 9
2
Reviewed and Updated the CAPEX Expenditure for the PSC and Municipal Council.
1 / O 7 /2 0 0 8
3 0 /0 6 /2 0 1 0
48
Checked the Alignment of Conditional/Unconditional Grant Budget Allocations with the DORA Report
1 / O 7 /2 0 0 8
3 0 /0 6 /2 0 1 0
48
Prepared a Cashflow budget for the project
26/10/2009
6
Updated the Risk Register
11/05/2009
2
Conducted quality review & approval of Tender Documents for the appointment of Contractors for floodlights upgrade
12/06/2009
8
Preparation & Submission of a monthly project status report
1 / O 7 /2 0 0 8
3 0 /0 6 /2 0 1 0
19 2
Assessed the cost and time impact of the costdeliverable trade offs or the scope reduction 2 1 / 0 7 /2 0 0 9 proposals and their feasibility
2 2 /0 7 /2 0 0 9
16
Drafting of a Procurement Strategy for the procurement of contractors
0 8 /0 5 /2 0 0 9
16
0 7 / 0 5 /2 0 0 9
Drafted an agenda and recorded the minutes of the tender briefing of Contractors
17/06/2009
8
Prepared Tender Report on bid results for the floodlights upgrade contract
10/07/2009
2
07/07/2009, 24/07/2009, Preparation of Bid Evaluation Reports for the 19/10/2009,19floodlights upgrade,electrical 20/08/2009,03/09/2009 works,building/civil works and turf works Drafted and Completed the contract declaration 08/09/2009 form for pitch/turf and drainage renovation works contract Drafted Appointment Letters for pitch/turf and 09/11/2009,08/09/2009,19/ drainage works renovation, building & civil 10/2009 works, electrical works and floodlights upgrade Conducted Stakeholder Engagement Session to 24/07/2009 discuss and gain support from stakeholders on scope reduction proposals
Application for Registration as a Professional Construction Project Manager submitted by JOSCELYN BERNARD NARTEY (PrCPM (Cand) ) – Sept 2017: CANDIDATE LOG BOOK 511/30
18
1
8
8
RECORD OF PRACTICE REPORT( CONT'D)
YEAR
2010
PROJECT DETAILS 2010 Legacy projects projects ;Upgrading of Buffalo City(ABSA) Stadium
PROJECT NAME
PROJECT DESCRIPTION DURATION
Rehabilitation & Expansion of Existing sports facilities at the Buffalo City(ABSA) Stadium to ensure that it is used as a training base camp for 2010 World Cup. START DATE
June, 2008
30th June, 2010
END DATE
Project Coordinator/Leader
PROJECT ROLE
EMPLOYER'S DETAILS DBSA Deployee/Technical Expert
JOB TITLE
DBSA
NAME OF EMPLOYER SUPERVISOR'S NAME/CONTACT DETAILS
( Co-Funder)
Ayanda Skewbu, 043-7052 043-7052834 834 CANDIDATE ACTIVITY REPORT
PROJECT STAGE
PMBOK AREA
ACTIVITY/TASK PERFORMED Drafting of Agenda/Minutes for Progress/Technical Meetings Site Visit & Work Progress Report Preparation-ABSA Stadium & others
Communication
START DATE
02/10/2009
Cost
Monthly Updates of the DORA Expenditure Reports on the conditional/unconditional grant budget allocations Completion and submission of fee claim payment authorisation forms
Risk
128
16
15/06/2010
2
27/01/2010
Preparation of project capex budget roll overs and motivations for next financial year Preparation of CAPEX Expenditure Reports for the PSC and the Municipal Council.
07/06/2010
MAN-HOURS EARNED
20/04/10,19/05/10
Draft Motivation for unspent conditional/unconditional grant funding(DORA) Roll-overs Preparation of Montrhly Progress Reports for the PSC and Municipal Council
END DATE
02/06/2010
16/07/2010
1/O7/2008
30/06/2010
48
2
48
Monthly
6 17/06/2009,30/09/2009,14/01/2010
Preparation of Fee Claim reconciliation statement
14/01/2010
2
Update of the Risk Register
06/06/2009
1
02/10/2009,22/01/2010, 04/05/2009
6
Review and approval of precontractual documentationsInsurance,Performance Surety etc o c e , ev ew e we approve procurement documentations for the selected sub-contractors for the Solicited, Reviewed and approved the Initial Contract Program Drafted variation orders for works omissions and the associated cost savings
2 19/10/2009 2 22/10/2009 8 05/11/2009
Application for Registration as a Professional Construction Project Manager submitted by JOSCELYN BERNARD NARTEY (PrCPM (Cand) ) – Sept 2017: CANDIDATE LOG BOOK 611/30
Facilitated and participated in the health & safety audit of the project ac a e e e an over an issued site handover certificate for works commencement for the
8 11/11/2009, 19/04/2010 20/11/2009
Facilitated the signing of the contract documents for the pitch/turf and drainage works renovation contract
2 25/11/2009
Prepared a request for variation order approval approval for additional civil works in the parking lot
30/11/2009
2
Prepared a Variation Order & Submitted for Approval for the building works
08/01/2010
2
Drafted & submitted a request for acceleration of critical works(change rooms)
T N E M E G A N A M & N O I T A T N E M U C O D N O I T C U R T S N O C . 5
4
Reviewed and approved the accelerated program of works and associated additional cost for the change rooms
2 12/01/2010
6 13/01/2010
Assisted in the resolution of issues around the change of the external water supply meters and Procurement Control/ reconnection with the Water Contract Admin department Received, Reviewed and Approved Interim Payment Certificate and fee claims for contractors and consultants
14/01/2010
2 18/01/2010
30/06/2010
16
03/03/2010
Monitored and cordinated the preparation of a Special Investigation Report on the geotechnical problem encountered in the parking lot 04/03/2010
16 05/03/2010
Issued Instructions for the Signage of the stadium Seats
26/04/2010
1
Monitor the preparation of a Variation Order & Submission for Approval for the VOC/Media Center & Signage of Seats
28/04/2010
4
Supervised the preparation of a monthly project employment reports for DSRAC,EC
27/01/2010
02/06/2010
12
Adjudicated and approved extension of time claims for electrical works
10/11/2009
8
Prepared a request for variation order for floodlights upgrade
13/11/2009
8
Reviewed and approved variation orders for floodlights upgrade
11/01/2010
8
Drafted proposals for a pitch/turf maintenance contract for the stadium
22/01/2010
8
Monitored and cordinated the valuation of additional works needed for stadium operational safety
26/04/2010
8
Application for Registration as a Professional Construction Project Manager submitted by JOSCELYN BERNARD NARTEY (PrCPM (Cand) ) – Sept 2017: CANDIDATE LOG BOOK 711/30
Received,Reviewed and Adjudicated 27/10/2010 extra fees claims for additional work
Stakeholders
03/11/2010 12
Planned,cordinated and monitored the snagging/de-snagging and issue of practical completion lists for building/civil works
04/05/2010, 10/06/2010
Planned,cordinated and monitored the snagging/de-snagging and issue of practical completion lists for electrical works in the change rooms and passages
20/05/2010
Planned,cordinated and monitored the final testing of floodlights
01/06/2010
Planned,cordinated and monitored the Snagging of completed works and issue of snag list for the pitich/turf renovation works
02/06/2010
8
Planned and conducted a site walkover, change room light testing & pre-handover Meeting
07/06/2010
8
Attended and recorded the minutes of Special Meetings with key stakeholders
06/11/2009
8
Discussion of reviewed scope with stakeholders-Ward Councillors to solicit their acceptance
03/05/2010
4
Led the Infrastructure oversight mayoral sub-committee to undertake organised tours of the stadium facility
25/05/2010
8
Assisted in the the resolution of the disputes over payment of allowances/stipends to Local PSC Members
03/11/2009
4
16
8
8
Application for Registration as a Professional Construction Project Manager submitted by JOSCELYN BERNARD NARTEY (PrCPM (Cand) ) – Sept 2017: CANDIDATE LOG BOOK 811/30
RECORD OF PRACTICE REPORT( CONT'D)
YEAR
2010
PROJECT DETAILS 2010 Legacy projects ;Upgrading ;Upgrading of Buffalo City(ABSA) City(ABSA) Stadium
PROJECT NAME PROJECT DESCRIPTION
Rehabilitation & Expansion of Existing sports facilities at the Buffalo City(ABSA) Stadium to ensure that it is used as a training base camp for 2010 World Cup.
DURATION
START DATE
30th June, 2010
END DATE
June, 2008
Project Coordinator/Leader Coordinator/Leader EMPLOYER'S DETAILS DBSA Deployee/Technical Expert
PROJECT ROLE JOB TITLE NAME OF EMPLOYER
DBSA
SUPERVISOR'S NAME/CONTACT DETAILS
( Co-Funder)
Ayanda Skewbu, 043-7052834 043-7052834 CANDIDATE ACTIVITY REPORT
PROJECT STAGE
PMBOK AREA
ACTIVITY/TASK PERFORMED Drafting of a project close out Schedule based on the JBCC Contract. O&M Training Inclusive Planned and conducted the final inspection and issue of final approval certificate for electrical works and floodlights
T U O E S O L C T C E J O R P . 6
START DATE
END DATE
MAN-HOURS EARNED
02/05/2010
2
17/05/2010
8
Planned and conducted the final inspection and issue of final approval certificate for pitch/turf and drainage renovation works
19/05/2010
8
Planned,cordinated and monitored the de-snagging of completed works and issue of works completion certificate for building/civil works.
14/06/2010
8
Received and reviewed the lease Planning/Integration agreement for stadium tenants; BRFU
02/06/2010
18/06/2010
8
Received, Reviewed and approved the final accounts
10/09/2010
8
Planned,cordinated and monitored the training of Stadium operational staff on the operation & maintenance of the installed irrigation systems & lighting
30/07/2010
8
Prepared & Submitted final project status report
04/11/2010
4
Updated the final Project Implementation Plan(PIP)/Cashflow budget
04/11/2010
Facilitated and cordinated the conduct a project post-completion audit
11/11/2010
4
TOTALS
8 66
Application for Registration as a Professional Construction Project Manager submitted by JOSCELYN BERNARD NARTEY (PrCPM (Cand) ) – Sept 2017: CANDIDATE LOG BOOK 911/30
RECORD OF PRACTICE REPORT
YEAR
2012-2014
PROJECT DETAILS EPWP Program-Phase 2
PROJECT NAME
Planning, implementation, monitoring and evaluation of the MMC Special Initiative; An EPWP Initiative to recruit and train over 120 workers for EPWP Field data capturing
PROJECT DESCRIPTION DURATION
START DATE
June 2014
END DATE
March 2012 Project Manager
PROJECT ROLE
EMPLOYER'S DETAILS Project Manager ORTambo District Municipality
JOB TITLE NAME OF EMPLOYER SUPERVISOR'S NAME/CONTACT DETAILS
Thandy Somana,
047-5016432
CANDIDATE ACTIVITY REPORT PROJECT STAGE & N G O I I T N F A I E I T I R B N I 1 & Y T T I P L E I C B I N S O A E C . 2 F
PMBOK AREA
Drafted authorisation memo for the commencement of the Planning & Integration initiative Prepared a Business Plan for the initiative
START DATE END DATE
10/03/2012 10/04/2012
15/05/2012
MAN-HOURS
2 40
Organised & Conducted a Project Launch/Initiation Meeting for the initiative
13/03/2012
Planning/Integration
Organised & Conducted a Project Kick-off Meeting
21/06/2012
8
Time
Review of the draft Work Program for the Initiative
15/06/2012
2
Cost
Developed Developed a Progr Program am Budget Budget /Expendi /Expenditure ture plan for approval approval
Risk
Developed a Draft Risk Register for the Initiative
Communication
Planning/Integration T N E M P O L E V E D N G I S E D . 3
ACTIVITY/TASK PERFORMED
Resource
Stakeholders
8
04/07/20 04/07/2012 12 10/07/20 10/07/2012 12 20/04/2012
12 8
Conducted a study tour of Ethekwini and Ekurhuleni municipalities municipalities epwp programs to assist build capacity to develop proper strategies and policies for the epwp initiatives
03/06/2012
05/06/2012
24
Recruited & Appointed 120 EPWP Field Wo rk rkers
19/03/2012
03/04/2012
96
Recruited & Appointed 5 EPWP Data Capturers
03/04/2012
8
Conducted EPWP Program Orientation of 120 EPWP Field Workers in the EPWP Program and the Initiative
13/03/2012
8
Assigned 120 EPWP Workers to existing infrastructure infrastructure project Sites
13/03/2012
8
Instituted Work Ethics for EPWP field workers based on the EPWP Code of Practice & Ministerial Determination
25/01/2013
2
Faciliatated training of 5 No.EPWP data capturers in the use of the EPWP-MIS
10/04/2012
8
Conducted Road Shows to project sites to educate and obtain contractor and community buy-ins into the initiative
06/06/2012
06/07/2012
Application for Registration as a Professional Construction Project Manager submitted by JOSCELYN BERNARD NARTEY (PrCPM (Cand) ) – Sept 2017: CANDIDATE LOG BOOK 1011/30
176
RECORD OF PRACTICE REPORT(CONT'D)
YEAR
2012-2014
PROJECT DETAILS PROJECT NAME PROJECT DESCRIPTION DURATION PROJECT ROLE
EPWP Program-Phase 2 Planning, implementation, monitoring and evaluation of the MMC Special Initiative; An EPWP Initiative Initiative to recruit recruit and train train over 120 workers workers for EPWP Field data capturing capturing
START DATE
June 2014
March 2012 END DATE Project Manager
EMPLOYER'S DETAILS Project Manager
JOB TITLE NAME OF EMPLOYER SUPERVISOR'S NAME/CONTACT DETAILS
ORTambo District Municipality
Thandy Somana, Somana,
047-5016432
CANDIDATE ACTIVITY REPORT PROJECT STAGE
& N O I T A T T N N E E M M E U R C U O C D O R R E P D N E T . 4
T N E M E G A N A M & N O I T A T N E M U C O D N O I T C U R T S N O C . 5
PMBOK AR AREA
ACTIVITY/TASK PE PERFORMED
START DA DATE
Facilitated the establishment of a 04/09/2012 well-equipped EPWP data centre.
Procurement
Invited quotations from Suppliers of Personal Protective Equipments(PPE) for EPWP Field Evaluated the Quotations and Selected Suppliers for the program Placed an order for the purchase of 125 set of PPEs for EPWP Field Workers Receipt of Orders for 125 set of PPEs for EPWP Field Workers
END DA DATE
MAN-HOURS EARNED
25/01/2013
24
19/10/2012
2
26/10/2012
2
27/10/2012
2
30/11/2012
2
As and When Required
54
Communication
Responded to stakeholder requests and queries
Time
Updated Monthly the Work Program
01/03/2012
30/06/2014
54
Cost
Prepare Program Expenditure Reports- Certificates of Expenditure & Revenue
01/03/2012
30/06/2014
54
Risk
Updated Monthly the Risk Register
01/03/2012
30/06/2014
54
54
Quality
Planning/Integration
Embarked on monthly follow-up site visits to ensure smooth implementation of the initiative Received & Reviewed the quality of EPWP Field Reports on job opportunities for data capturing Developed a Monitoring & Evaluation System for the initiative
01/03/2012
30/06/2014
01/0 01/03/ 3/20 2012 12
30/0 30/06/ 6/20 2014 14
31/01/2013
05/02/2013
10
Prepare Project Performance Reports on the initiative
01/03/2012
30/06/2014
54
54
Reviewed and Commented on the 14/03/2013 Quarterly the EPWP M&E Report received from DRPW Administered and checked Monthly Work Attendance 01/03/2012 30/06/2014 Registers for EPWP Field Workers
Resource
Renewed yearly the Employment Contracts of EPWP Field Workers Facilitated Training of EPWP Data capturers and EPWP Field Workers in the EPWP program
01/03/2012
30/06/2014
22/01/2013
TOTALS
8
27
16
8
479
Application for Registration as a Professional Construction Project Manager submitted by JOSCELYN BERNARD NARTEY (PrCPM (Cand) ) – Sept 2017: CANDIDATE LOG BOOK 1111/30
RECORD OF PRACTICE REPORT
YEAR PROJECT DETAILS KZN School Sanitation Program;Phase 2
PROJECT NAME PROJECT DESCRIPTION DURATION
2016-2017
To initiate, plan, construct, complete and handover ablution facilities and associated works for 179 schools in the North Coast Region of KZN
START DATE
Uncompleted
END DATE
30/09/2015
Principal Agent/Program Manager
PROJECT ROLE
EMPLOYER'S DETAILS Project Manager
JOB TITLE
Consult three Architects
NAME OF EMPLOYER SUPERVISOR'S NAME/CONTACT DETAILS
Bandile Boyana, 083 989 9337/031-9405258
CANDIDATE ACTIVITY REPORT PROJECT STAGE
PMBOK AREA
Planning & Integration
G N I F E I R B & N O I T A I T I N I 1
Scoping
ACTIVITY/TASK PERFORMED Prepared,cordinated Prepared,cordinated and monitored the Program Initiation Program
28/04/2016 28/04/2016
3 0 / 0 4 /2 0 1 6
Planned and conducted Site Condition Assessments & developed Site Condition Assessment Report for the client
0 2/ 2/ 08 08 /2 /2 01 015
1 7/ 7/ 01 01 /2 /2 01 016
Secured and agreed on DOPW Procurement Standards/Policy for the Program
MANHOURS EARNED 2 24
160 27/06/2016
Drafted & Presented Procurement Strategy 0 9/ 0 5 / 2 0 1 6 for the appointed of consultants to the client
Procurement
END DATE
Prepared a preliminary program viability assessment report
1 0 / 0 5 /2 0 1 6
1
8
Drafted TOR/RFP for the solicitation of principal consultants- QS, Civil/Structural & MEP Consultants
15/05/2016
8
Drafted Appointed Letters for principal consultants- QS, Civil/Structural & MEP Consultants
28/09/2015
8
Developed & Presented a preliminary Planning/Integrat Program Implementation Strategy to Client ion Listed the names and coordinates of 40 Schools with Borehole Requirement
Y T I L I B I S A E F & T P E C N O C . 2
START DATE
22/04/2016
24
10/04/2016 06/10/2016
2
Scoping
Development of a WBS for the project team
31/05/2016
4
Procurement
Drafted TOR/RFP for the solicitation of subconsultants- Geotechnical Engineer, Land Surveyor,Health & Safety Consultant
15/01/2016
8
Drafted Appointment letters for SubConsultants-Land Consultants-Land Surveyor
17/02/2016
4
Solicited and agreed with the client the format for cost control and reporting
21/05/2016
2
Cost
Time
Resource
Cordinated and facilitated the preperation of the Preliminary Cost Estimates Drafted an indicative work program for the stages 03 to 05 Developed & Presented a RAM/RACIindicating the roles and responsibilities of the project team Determined the Project Management Management Capacity Requirements
3 1/ 1/ 05 05 /2 /20 16 16
0 2/ 2/ 06 06 /2 /2 01 016
15/07/2016
8 8
28/09/2016
4
08/10/2016
8
Application for Registration as a Professional Construction Project Manager submitted by JOSCELYN BERNARD NARTEY (PrCPM (Cand) ) – Sept 2017: CANDIDATE LOG BOOK 1211/30
RECORD OF PRACTICE REPORT( CONT'D)
YEAR PROJECT DETAILS KZN School Sanitation Program;Phase 2
PROJECT NAME PROJECT DESCRIPTION DURATION PROJECT ROLE
2016-2017
To initiate, plan, construct, complete and handover ablution facilities and associated works for 179 schools in the North Coast Region of KZN
START DATE
JOB TITLE NAME OF EMPLOYER SUPERVISOR'S NAME/CONTACT DETAILS
Uncompleted
END DATE Principal Agent/Program Manager EMPLOYER'S DETAILS Project Manager
30/09/2015
Consult three Architects
Bandile Boyana, 083 989 9337/031-9405258
CANDIDATE ACTIVITY REPORT PROJECT STAGE
PMBOK AREA
Scoping
ACTIVITY/TASK PERFORMED
Cost
17/07/2016
Updated the Program Cost Expenditures
2
19/07/2016
08/03/2017 4 26 /07/2016
28 /07/2016
8
27/09/2016
28/09/2016
8
14/10/2016
14/03/2017
16/03/2017
25/10/2016
27/10/2016
18/11/2016
29/10/2016
31/03/2017
8
24
2
34
6 17/11/2016
19/11/2016
6
Coordinated & Monitored the development of Cost Build up for 22/11/2016 schools with higher cost above the
29/11/2016
14
Planned and cordinated the Review of drawings & BOQs
Quality
MAN-HOURS EARNED
8
Developed a Schedule for the production of R&R Drawings and Building Specifications Secured Cost Variance Reports and motivated for negative variations from preliminary approved Cordinated and facilitated the preparation and review of the final cost estimates Facilitated and cordinated the analysis of the Project Cost - Cost per unit toilet prototype/block Monitored the development of DOE Commitment Budget2016/17 FY Q3 & Q4 Received,Reviewed and approved the Program Cashflows for submission Assisted in the Completion, Reviews & Submission of new BAC benchmarking Cost Template Facilitated and monitored the remeasurement of the provisional quantities of Civil Works & R&R
END DATE
30/06/2016
Updated the WBS Updated the indicative work program for stages 03 to 05
Time
START DATE
Planned,cordinated and monitored the design error corrections ,Value 13/12/2016 Engineering/Design optimisation & Cordinated and monitored the review of the R&R Drawing & R&R 01/03/2017 Building Specifications and Cost Developed QMP for the program based on ISO9001;2015 01/06/2017 Requirements; Quality
16/05/2016
4
31/03/2017
48
21/05/2017
24
02/06/2017
Application for Registration as a Professional Construction Project Manager submitted by JOSCELYN BERNARD NARTEY (PrCPM (Cand) ) – Sept 2017: CANDIDATE LOG BOOK 1311/30
8
Communication
Developed a template for project status reports
10/09/2016
2
Developed a Program Communication Directory
06/05/2016
1
Drafted a Design Status Report for Management
09/08/2016
4
Drafted an agenda, sent an invitation & conducted a meeting with H&S Sub-Consultant
15/10/2016
4
Drafted a Project Comm.Schedule/Calendar
T N E M P O L E V E D N G I S E D . 3
Risk
Planning/Integration
Program Strategic Meetings/Teleconference to resolve program issues & Drafted a letter to the Municipalities for comments on the Municipal Sewer Permit Developed a Risk Register & Solicited the input from the project team Planned, Conducted and recorded minutes of the design,specifications,document Planned, Conducted and recorded proceedings of the architectural/civil design reviews, Facilitated the municipality sewer permit applications for 4 schools with municipal sewer connections Spacial planning & clustering of Schools based on geographical proximities using the GIS Developed a project change control system and a change log sheet Prepared Special Report on the Implications of changing the design standards at the Prepared and sent RFQ to EnviroPRO for Water Use licence applications for 7 schools with
18/07/2017
23/08/2017 12
1/08/2016
31/05/2017
16/05/2017
22/06/2016
1
30/06/2016 10 20/05/2016
8
27/06/16
19/09/2016
88
06/05/2016
30/05/2016
24
19/08/2016
05/11/2016
Completion of Client Information Forms(CIF) for EnviroPRO
11/11/2016
6
28
02/03/17
4
21/04/2017
2
Facilitated and monitored the Borrow pit material surveys & 24/07/2017 25/08/2017 investigations Drafted letter of request for 08/05/2017 comments for Municipal Approval of Building plans for 4 Schools with Drafted Letters of appointment for Health & Safety Consultant
18/05/2016
Drafted Letters of appointment for Geotechnical Engineer
30/05/2016
Developed and presented a Procurement Strategy for the procurement of Contractors Drafted RFQ for geotechnical & geo-hydrological investigationsBore-hole Works
10
30
1
1
1 05/06/2016
08/06/2016
08/06/2016
Application for Registration as a Professional Construction Project Manager submitted by JOSCELYN BERNARD NARTEY (PrCPM (Cand) ) – Sept 2017: CANDIDATE LOG BOOK 1411/30
32
4
Procurement
Resource
Drafted RFQ for the socilitation of a PMIS Vendor - Assessment Manager & PPO
09/08/2016
4
Drafted a PMIS Vendor Evaluation Report
25/09/2016
6
24/09/2016
8
Facilitated and an conducted a Meeting with PPO Vendors in Pretoria Drafted TOR/RFP for the appointment of Social 15/11/2016 Facilitators/ISD Consultants Collected & Analysed the List of Prospective Social Facilitators/Social Workers Facilitated and cordinated the resolution of conflict between the 16/09/2016 architects & structural engineers Developed & Posted Project office organogram & communication structure Developed a Program Organisational structure-Strong Matrix structure Updated PM Organisational structure
Stakeholders
Developed Stakeholder engagement plan
26/08/2016
16/11/2016
26/07/2017
17/09/2016
8
8
4
16/08/2016
2
16/10/2016
6
09/09/2016
1
27/08/2016
Application for Registration as a Professional Construction Project Manager submitted by JOSCELYN BERNARD NARTEY (PrCPM (Cand) ) – Sept 2017: CANDIDATE LOG BOOK 1511/30
8
RECORD OF PRACTICE REPORT( CONT'D)
YEAR
2016-2017
PROJECT DETAILS KZN School Sanitation Program;Phase 2 To initiate, plan, construct, complete and handover ablution facilities and associated works for 179 schools in the North Coast Region of KZN Uncompleted START DATE END DATE 30/09/2015 Principal Agent/Program Manager EMPLOYER'S DETAILS Project Manager
PROJECT NAME PROJECT DESCRIPTION DURATION PROJECT ROLE JOB TITLE
Consult three Architects
NAME OF EMPLOYER SUPERVISOR'S NAME/CONTACT DETAILS
Bandile Boyana, 083 989 9337/031-9405258
CANDIDATE ACTIVITY REPORT PROJECT STAGE
PMBOK AREA
Scope
Communication
ACTIVITY/TASK PERFORMED
Assessed the time and cost impact and the feasibility of scope changes; 24 Omitted Omitted Schools
START DATE
12/01/2017
END DATE
15/01/2017
MANHOURS EARNED 24
Facilitated and cordinated a meeting to assess client requirements on tender documentations
24/05/2016
4
Developed an HRM Filing System for RE/COWs
22/07/2016
1
Developed a Programt Filing System
22/07/2016
2
Facilitated and cordinated a Special Meeting with client on Documentation & Cost Estimates
13/12/2016
4
Issued Instructions to H&S Consultant to convert generic OHS specs to school specific
16/01/2017
4
Drafted a Response to to Client’s feedback on procurement documents-32 schools
22/01/2017
1
Issued Instructions to MEP Sub-Consultants for for drawings & Specifications on Lightning protection installations as an additional service
10/02/2017
1
Planned and Conducted weekly Project Team meetings
1/04/2017
31/05/2017
16
Prepared an agenda and recorded minutes of all program review meetings with client
1/08/2016
30/09/2017
24
Developed & Updated the Project Communication Schedule
28/08/2017
4
Responded to Client Client Queries/Report Queries/Report on on Cost Estimates
13/12/2016
4
Coordinated and facilitated the preparation of the Pre-tender Cost Estimates & the completion of the DAC Forms
26/07/2016
8
Received an and Re Reviewed pr pre-tender co cost es estimates 27/07/2016
Reviewed the revised Cashflow Budget
28/07/2016
07/12/2016
8
4
Rece Receiived ved and and Rev Reviewe iewed d the Cost ost Est Estimat imate es/BO s/BOQs Qs 13/1 13/12/ 2/20 2016 16
31/0 31/03/ 3/20 2017 17
16
Facilitated and monitored the re-assessment/re 24/02/2017 measurement of renovation Works on 49 Schools
14/03/2017
16
Received, Processed & Approved payment claims 04/05/2017 from Sub-Consultants- H&S Consultant
05/05/2017
4
Cost
Application for Registration as a Professional Construction Project Manager submitted by JOSCELYN BERNARD NARTEY (PrCPM (Cand) ) – Sept 2017: CANDIDATE LOG BOOK 1611/30
Prepared a 3-year MTEF Implementation & Capital Budget -clusters 1,3&5
15/08/2017
23/08/2017 16
Receive,Review Receive,Review and approve Fee Claims/Invoices for sub-consultants
10/07/2017
Developed a Fee Invoice Tracking Template
14/07/2017
2
8
Risk
Developed a Travel & Disbursement Schedule for 06/06/2017 cluster 1
09/06/2017
Updated Monthly the Risk Register
1/08/2016
30/09/2017
12
Attending to Client’s feedback/requests feedback/requests for changes on tender documents for re-submission
1/08/2016
30/09/2017
96
Facilitated & Cordinated the work of the Client's QA Audit of the Program
04/10/2016
06/10/2016
6
Faciliated and monitored the In-house QMS Training Workshop for the project team Review & Re-Submission of Procurement documents;tender documents;tender documents,procureme documents,procurement nt strategy & cost estimates ISO 9001;2015 QMS- Prepared & reviewed flow charts for project investment appraisals,Risk Management Process etc
Quality
T N E M E R U C O R P & N O I T A T N E M U C O D R E D N E T . 4
09/12/2016, 23/03/17
13/12/2016
31 31/03/2017
16
32
23/02/2017
4
ISO 9001;2015 QMS-Development of a project office organisational structure
24/02/2017
4
Participated in a QMS Workshop and Training
24/03/2017
6
Revise Technical Specifications for Building Works ( New Block+ R&R Works)
02/03/2017
8
Revised Contract Periods on the tender documents
03/05/2017
8
Participated in QMS Roadshows/Awareness Roadshows/Awareness campaign
31/05/2017
8
Participated in QMS-Time Sheet Process Audit
02/06/2017
2
Attended a Quality Management Review Meeting
23/06/2017
4
Facilitated and monitored the resolution of Civil/Building Specs and BOQs discrepancies
22/08/2017
8
Participated in a QMS Internal Audit
26/06/2017
4
Response to QMS Internal Audit Findings
13/07/2017
4
Update of IPIP Template for Q2 of the 201617FY
22/09/2016
8
Assessed & Communicated the Impact of the new 22/03/2017 PPPFA on the procurement strategy to the client Drafted an addendum to the project implementation implementation strategy due to the new PPPFA
Planning/Integration
12
Assessment of the Impact of proposed Procurement Document Changes-Splitting of Clusters 3-8
31/03/2017
01/06/2017
07/07/2017
08/07/2017
Application for Registration as a Professional Construction Project Manager submitted by JOSCELYN BERNARD NARTEY (PrCPM (Cand) ) – Sept 2017: CANDIDATE LOG BOOK 1711/30
18
4
16
Project Status Report Updates
1/08/2016
31/05/2017
10
Program Issue Logging
1/08/2016
31/05/2017
10
Solicited Client Procurement policy,Procurement 12/05/2016 Requirements/Guidelines,Procurement documentatiuon templates, Contract ConditionsDeveloped & briefed client on revised procurement strategy for ECDP Contractors05/08/2016 17/08/2016 Clusters 1&2 Revised Procurement Strategy for Clusters 1&2ECDP SMME Contractors
22/08/2016
2
24
3
Addressed clients request for changes in procurement documents
18/10/2016
20/10/2016
12
Developed a Procurement Schedule
19/01/2017
21/01/2017
12
Monitoring & Control of the Procurement Schedule
13/12/2016
31 31/03/2017
12
Conducted a Procurement Market Research & Analysis-CIDB Register & the ECDP Database
28/04/2017
02 02/05/2017
40
Procurement
Reviewed and updated the Procurement Schedule
27/02/2017
Drafted TOR for Recruitment of an Additional QS to conduct quality review of BOQs and Cost 20/06/2017 21/06/2017 Estimates Developed proposals for an additional services of participating in the tender 17/07/2017 18/08/2017 evaluation/adjudication evaluation/adjudication process 15/06/16, 30/06/16, 17Received, Reviewed,& Submitted tender 18/08/16, 17/09/16, 26/06/17 documents,Cost Estimates & Procurement & 04/08/17,01/12/16, Strategies to client Secured & Analysed the ECDP Database/Project Register
26/07/2017
2
8
16 16
2
Assessed the Project Management & Project Team Capacity Requirements
30/09/2016
02/11/2016
24
Drafted TOR/RFP for the recruitment of REs/COWs
18/07/2016
20/07/2016
12
Drafted Invitations for RE/COW candidate Interview
29/07/2016
1
Reviewed HR Sub-Consultants fee quotations
29/07/2016
1
Negotiated Negotiated with H R Sub-Consultants on fee quotations
01/08/2016
1
Drafted LOI for the engagement of Res/COWs
06-08/10/16
4
Developed RE/COW Candidate interview scoring sheet
05/08/2016
2
Conducted RE/COW Interviews
06/08/2016
6
Prepared an RE/COW Interview evaluation report
29/09/2016
2
Prepared RE/COW Appointment List
31/09/2016
1
Conducted In-house training on SACPCMP IDOW for PMs
20/08/2016
1
Application for Registration as a Professional Construction Project Manager submitted by JOSCELYN BERNARD NARTEY (PrCPM (Cand) ) – Sept 2017: CANDIDATE LOG BOOK 1811/30
Resource
Conducted In-house Training Session-Project Scope Change Management
27/08/2016
1
Conducted In-housing training session-GANTT CHART
31/08/2016
1
Conducted In-house training-Project Status Report
10/09/2016
1
Conducted Time Sheet reviews and approvals
1/05/2017
31/08/2017
8
Assessed Resource Requirement for tender document printing,compilation & binding
03/11/2016
8
Drafted job description for Project office Administrator
04/11/2016
2
Conducted Interviews for Project office administrator
05/11/2016
4
Prepared Job Candidate Evaluation Report
05/11/2016
2
Prepared a Local consultancy enterprise development report & updates Updated Monthly the Resource Management Plan Facilitated and cordinated the JBCC 6.1 in-house Training
06/06/16, 10/02/17, 14/06/17
1/08/2016
31/05/2017
24
10
19/07/2017
1
Weekly
3
Conducted Mentorship Mentorship Training for Project Administrators/Office Administrators/Office Manager Drafted Proposals for Client resource capacitation 06/06/2017
08/06/2017
9
Prepared and Presented Program status at DOE Client Feedback/Liaison Meetings
31/05/2017
20
1/08/2016
Stakeholders Informed team members about the impact of the 24 omitted schools or scope changes
16/01/2017
TOTALS
1
1589
Application for Registration as a Professional Construction Project Manager submitted by JOSCELYN BERNARD NARTEY (PrCPM (Cand) ) – Sept 2017: CANDIDATE LOG BOOK 1911/30
II.A II. A
RECORD OF PRACTICE- TRAINING ACTIVITIES-CPDs ACTIVITIES-CPDs
Application for Registration as a Professional Construction Project Manager submitted by JOSCELYN BERNARD NARTEY (PrCPM (Cand) ) – Sept 2017: CANDIDATE LOG BOOK 2011/30
11. TRAINING ACTIVITY REPORT- CONTINUOUS PROFESSIONAL DEVELOPMENT(CPD) DEVELOPMENT(CPD) NAME OF CANDIDATE:
JB Nartey
REGISTRATION NO.:
B/903/2010
DURATION OF CANDIDATURE:
4 ye ars
CANDIDATURE GOALS
Provide the candidate with experience to practice and apply project management methods to a real life project
Minimum 1600-3000 man-hours
Training Contact Hour Worksheet Completion Date Number
Course Title
Start Date
Institution Name
Ve nue
PMI,USA
Johanne sburg,South Africa
Contact Hours Earned
CPDs Have Course Have Course Earned Certificate? Curriculum
Comment
TRAINING
3 PMP Exams
1 Masters in Project Management(MPM) 1.1 Research Assignment; Reseearch Report 1.2 Resear Research ch Assign Assignmen ment; t; Reseea Reseearch rch Prop Proposa osall 1.3 Projec Projectt Manage Managemen mentt Practi Practice ce 1.4 Legal Legal Aspe Aspects cts of Proj Project ect Manage Managemen mentt 1.5 Strate Strategic gic Projec Projectt Manage Management ment 1.6 Engine Engineeri ering ng Servic Services es Manage Managemen mentt 1.7 1.7 Proj Projec ectt Quali Quality ty Mana Managem gemen entt 1.8 Projec Projectt Human Human Resour Resource ce Mana Manageme gememt mt 1.9 1.9 Resea Researc rch h Metho Methodo dolo logy gy 1.10 1.10 Projec Projectt Proc Procure uremen mentt Mana Manageme gement nt 1.11 1.11 Proj Projec ectt Risk Risk Man Manag agem emen entt 1.12 1.12 Introd Introduct uction ion to Proj Project ect Manage Managemen mentt 1.13 1.13 Projec Projectt Finan Finance ce & Cost Cost Manag Managemen ementt 1.14 1.14 Proj Projec ectt Syste System m Engine Engineer erin ing g 1 .1 .1 5 M PM PM Te Te am am B ui ui ld ld in in g
University of Pretoria University of Pretoria University of Pretoria University of Pretoria University of Pretoria University of Pretoria University of Pretoria University of Pretoria University of Pretoria University of Pretoria University of Pretoria University of Pretoria University of Pretoria University of Pretoria University of Pretoria Mcintosh Xaba & Labor Intensive construction management-NQF Associates/Misha Projects & Level 5 &7 2 Eng
Pre toria,South Africa Pre toria,South Africa Pre toria,South Africa Pre toria,South Africa Pre toria,South Africa Pre toria,South Africa Pre toria,South Africa Pre toria,South Africa Pre toria,South Africa Pre toria,South Africa Pre toria,South Af Africa Pre toria,South Africa Pre toria,South Africa Pre toria,South Africa Pre toria,South Africa
27 Feb.2014
Jan .2014 to date Aug -13 Oct.2013 25 Aug.2013 27 Au g.2013 18 Aug.2013 20 Au g.2013 10 March,2013 12 Mar. 2013 5 March,2013 7 Mar.2013 27 Aug.2012 29 Au g.2012 25 Aug.2012 27 Au g.2012 20 Aug.2012 22 Au g.2012 18th Aug. 2012 20th Aug.2012 5th Ma March.2012 7th Ma March.2012 3rd March 2012 5th March 2012 26th Feb.2012 28th Feb.2012 24th Feb.2012 26th Feb.2012 25th Jan.2012
ORTDM, Umtata,South Umtata,South Africa 1 June,2011
3 June,2011
T O T AL S
3
0,375 No
Yes
Resul ts Slip At tached
20 20 20 20 20 20 20 20 20 20 20 20 20 20 8
2,5 No 2,5 No No 2,5 No No 2,5 No No 2,5 No No 2,5 No No 2,5 No No 2,5 No No 2,5 No No 2,5 No No 2,5 No No 2,5 No No 2,5 No No 2,5 No No 1 No
Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes
Uncompleted Course Transcri pts Att ach ed Course Transcripts At tached Course Transcripts At tached Course Transcripts At tached Course Transcripts At tached Course Transcripts At tached Course Transcripts At tached Course Transcripts At tached Course Transcri pts Att ach ed Course Tr Transcri pts At Att ach ed Course Transcri pts Att ach ed Course Transcripts At tached Course Transcripts At tached Course Transcri pts Att ach ed
24
3 Ye Yes
Yes
Course Certificate Attached
315 39,375
Application for Registration Registration as a Professional Construction Construction Project Manager Manager submitted by JOSCELYN BERNARD NARTEY (PrCPM (Cand) ) – Sept 2017: CANDIDATE LOG BOOK 2111/30
11. TRAINING ACTIVITY REPORT- CONTINUOUS PROFESSIONAL DEVELOPMENT(CPD)---CONT'D NAME OF CANDIDATE:
JB Nartey
REGISTRATION NO.:
B/903/2010
DURATION OF CANDIDATURE:
4 years
CANDIDATURE GOALS
Provide the candidate with experience to practice and apply project management methods to a real life project Training Contact Hour Worksheet
Number
Course Title
Min imum 1600-3000 man-hours
Institution Na me
Venue
Completion Date
Start Date
Contact Hours
CPDs Earned
Have Course Certificate?
Have Course Curriculum Comment
CONFERENCES/WORKSHOPS/SEMINARS
1 Contract Admin & Management( GCC2015)
D-Tech Tactical
Pre-Mortems Versus Post-Mortems: Assuring H&S throughout a project's stages versus learning by 2 Accident" Achasm Summit ACHASM
3 Contract Admin & Management( GCC2015)
D-Tech Tactical
Sustainable Urban Development/Water Sensitive 4 Urban Design Workshop/Seminar SAICE 5 20 2 014/15 Green Drop Water Services Audit Symposi D WA Geo-synthetics in Pipelines & Water Containment 6 Applications in South Africa SAICE Road to ECSA Registration for Mature Candidates 7 –Candidate Academy SAICE
8 EPWP Phase 3 Orientation Workshop 1st Legal & Financial compliance for Contract 9 Management in Government & SOE’S 10 3rd EPWP Municipal Summit Planning, programming and budgeting of MIG 11 Infrastructure Projects
Manzini,Swaziland
29-Jun-17
30-Jun-17
16
2 yes
yes
Certificate of Appreciation Attached
Westville Country Club, Durban
10 Oct. 2016
11 Oct.2016
16
2 yes
Yes
Course Certificate Attached Certificate of Appreciation Attached
Durban,South Africa SAICE, Amathole Branch, East London Golf Club East Lon don IDZ
19 Sept. 2016
20 Sept.2016
16
2 No No
Yes
02 December. 2015 13-Jul-15 14 July 2015
4 16
0,5 yes 2 No No
Yes Yes
8
1 yes
Yes
SAICE, Amathole Branch, East London Offices
12-Feb-15
Course Certificate Attached
Course Certificate Attached
King David Hotel, East Lon don 28-Jul-14
29 July 2014
16
2 No
Yes
DOPW Intelligence Transfer Centre
Mpekweni Beach Resor Resort, t,Por Portt Alf Alfre red d
10 June June,2 ,201 014 4
13 June 2014
32
4 yes
Yes
Course Certificate Attached
CSIR Convention Centre,Pretoria
21-May-13
22nd May 2013
16
2 No
Yes
Thank you letter Attached
DOPW
Midrand, Midrand, South South Africa Africa 26 Nov.201 Nov.2012 2
28 Nov. 2012
24
3 No
Yes
DLGTA
Garden Court,Umtata, South Africa 06-Aug-12
8 Augu st 2012
24
3 No
Yes
2nd Annual Dam Management & Rehabilitation In Intelligence Transfer Centre 12 Africa IWEE, Dept of Civil Eng, University of Stellenbosch, South Africa 13 Water and Waste water treatment
Gallagher Centre,Midrand,South Africa 24-Jul-12 IWEE, Dept of Civil Eng, University of Stellenbosch, South Afri ca 13 Feb.2012
14 2nd EPWP Municipal Summit
DOPW
Midrand, Midrand, South South Africa Africa 2 Nov.2011 Nov.2011
EPWP Infrastructure Project Compliance 15 Workshop Contract Administration & Management(GCC 16 2010)
ECDC Building, DOPW/EPWP Technical Su Mthatha, South Africa 28th Sept,2011 ORTDM, Umtata,South Afri ca 14-Jun-11 SAFCEC 15 June 2011 DEPT OF SOCIAL
25-Jul-12
16
2 No
Yes
Letter of Appreciation Attached
15 Feb.2012
24
3 yes
Yes
Course Certificate Attached
4 Nov.2011
24
3 No
Yes
8
1 No
Yes
16
2 yes
Yes
Course Certificate Attached
11. TRAINING ACTIVITY REPORT- CONTINUOUS PROFESSIONAL DEVELOPMENT(CPD)---CONT'D NAME OF CANDIDATE:
JB Nartey
REGISTRATION NO.:
B/903/2010
DURATION OF CANDIDATURE:
4 years
CANDIDATURE GOALS
Provide the candidate with experience to practice and apply project management methods to a real life project Training Contact Hour Worksheet
Number
Course Title
Min imum 1600-3000 man-hours
Institution Na me
Venue
Completion Date
Start Date
Contact Hours
CPDs Earned
Have Course Certificate?
Have Course Curriculum Comment
CONFERENCES/WORKSHOPS/SEMINARS
1 Contract Admin & Management( GCC2015)
D-Tech Tactical
Pre-Mortems Versus Post-Mortems: Assuring H&S throughout a project's stages versus learning by 2 Accident" Achasm Summit ACHASM
3 Contract Admin & Management( GCC2015)
D-Tech Tactical
Sustainable Urban Development/Water Sensitive 4 Urban Design Workshop/Seminar SAICE 5 20 2 014/15 Green Drop Water Services Audit Symposi D WA Geo-synthetics in Pipelines & Water Containment 6 Applications in South Africa SAICE Road to ECSA Registration for Mature Candidates 7 –Candidate Academy SAICE
8 EPWP Phase 3 Orientation Workshop 1st Legal & Financial compliance for Contract 9 Management in Government & SOE’S 10 3rd EPWP Municipal Summit Planning, programming and budgeting of MIG 11 Infrastructure Projects
TOTALS
Manzini,Swaziland
29-Jun-17
30-Jun-17
16
2 yes
yes
Certificate of Appreciation Attached
Westville Country Club, Durban
10 Oct. 2016
11 Oct.2016
16
2 yes
Yes
Course Certificate Attached Certificate of Appreciation Attached
Durban,South Africa SAICE, Amathole Branch, East London Golf Club East Lon don IDZ
19 Sept. 2016
20 Sept.2016
16
2 No No
Yes
02 December. 2015 13-Jul-15 14 July 2015
4 16
0,5 yes 2 No No
Yes Yes
8
1 yes
Yes
SAICE, Amathole Branch, East London Offices
12-Feb-15
Course Certificate Attached
Course Certificate Attached
King David Hotel, East Lon don 28-Jul-14
29 July 2014
16
2 No
Yes
DOPW Intelligence Transfer Centre
Mpekweni Beach Resor Resort, t,Por Portt Alf Alfre red d
10 June June,2 ,201 014 4
13 June 2014
32
4 yes
Yes
Course Certificate Attached
CSIR Convention Centre,Pretoria
21-May-13
22nd May 2013
16
2 No
Yes
Thank you letter Attached
DOPW
Midrand, Midrand, South South Africa Africa 26 Nov.201 Nov.2012 2
28 Nov. 2012
24
3 No
Yes
DLGTA
Garden Court,Umtata, South Africa 06-Aug-12
8 Augu st 2012
24
3 No
Yes
2nd Annual Dam Management & Rehabilitation In Intelligence Transfer Centre 12 Africa IWEE, Dept of Civil Eng, University of Stellenbosch, South Africa 13 Water and Waste water treatment
Gallagher Centre,Midrand,South Africa 24-Jul-12 IWEE, Dept of Civil Eng, University of Stellenbosch, South Afri ca 13 Feb.2012
14 2nd EPWP Municipal Summit
DOPW
Midrand, Midrand, South South Africa Africa 2 Nov.2011 Nov.2011
EPWP Infrastructure Project Compliance 15 Workshop Contract Administration & Management(GCC 16 2010)
ECDC Building, DOPW/EPWP Technical Su Mthatha, South Africa 28th Sept,2011 ORTDM, Umtata,South Afri ca 14-Jun-11 SAFCEC 15 June 2011
17 NYS and Training co-ordination workshop
DEPT OF SOCIAL DEVEL OP ME NT
18 BCM Women’s football Academy development
BCM
East Lon don,SA Blue Lagoon Hotel, East London, South Africa.
25-Jul-12
16
2 No
Yes
Letter of Appreciation Attached
15 Feb.2012
24
3 yes
Yes
Course Certificate Attached
4 Nov.2011
24
3 No
Yes
8
1 No
Yes
16
2 yes
Yes
26th May,2011
8
1 No
Yes
26th August,2010
8
1 No
Yes
292
36,5
Application for Registration as a Professional Construction Project Manager submitted by JOSCELYN BERNARD NARTEY (PrCPM (Cand) ) – Sept 2017: CANDIDATE LOG BOOK 2211/30
Course Certificate Attached
11. TRAINING ACTIVITY REPORT- CONTINUOUS PROFESSIONAL DEVELOPMENT(CPD)---CONT'D NAME OF CANDIDATE: JB Nartey REGISTRATION NO.:
B/903/2010
DURATION OF CANDID 4 years
CANDIDATURE GOALS
Minimum 1600-3000 man-hours
Provide the candidate with experience to practice and apply project management methods to a real life project Training Contact Hour Worksheet Completion Date
Number
Course Title
Start Date
Institution Name
Venue
1 Microsoft Proect 2010
BYTES PEOPLE SOLUTIONS
2 EPWP_MIS
DRPW
Savoy Hotel, Mthatha, South Africa 07-Ma -12 OR Tambo DM, Mthatha, South Africa 15 April,2012
Contact Hours Earned
Have Course Have Course CPDs Earned Certificate? Curriculum
Comment
SOFTWARE TRAINING COURSES
Organizational/Individual performance management System(PMS), DIMS Inter Ma 3 version 3
TOTALS
4 MIG_MIS Version 2.04
DLGTA
Desi ner 2011 5 Civil De Project Portfolio Office6 PMIS
Knowled e Base DBSA
7 AUTOCAD 2010
Auto Desk, South Africa,
OR Tambo House, Mthatha, South Africa
11 Ma 2012
40
5 es
Yes
18 April 2012
32
4 No
Yes
8
1 No
Yes
40
5 No
Yes
21 Jan 2011
16
2 es
Yes
16 A ril 2010
16
2 No
Yes
25 October 2009
40
5 yes
Yes
8TH February, 2012.
ORTDM, Mthatha, So South Africa 7 F eb eb.2011 Autodesk Authorized training center, East London, South Africa 20-Jan-11 Malachite Guest house, Midrand, South Africa 15 A pr pril,2010 Autode Autodesk sk author authorize ized d traini training ng centr centre-, e-,Por Portt Elizab Elizabet eth, h, South South 21-Oct-09 Africa
11-Feb-11
192
24
Application for Registration as a Professional Construction Project Manager submitted by JOSCELYN BERNARD NARTEY (PrCPM (Cand) ) – Sept 2017: CANDIDATE LOG BOOK 2311/30
Course Certificate Attached
Course Certificate Attached
Course Certificate Attached
II.B. RECORD OF PRACTICE- INDIVIDUAL ACTIVITIES ACTIVITIES
Application for Registration as a Professional Construction Project Manager submitted by JOSCELYN BERNARD NARTEY (PrCPM (Cand) ) – Sept 2017: CANDIDATE LOG BOOK 2411/30
II. INDIVIDUAL PRACTICE PRACTICE REPORT NAME OF CANDIDATE:
JB Nartey
REGISTRATION NO.:
B/903/2010
DURATION OF CANDIDATURE:
4 years
CANDIDATURE GOALS
Provide the candidate with experience to practice and apply project management methods to a real life project
Min 1600-3000 man-hours
Man Hour Worksheet
Start Start Date Date
Man Hours Compl Completi etion on Date Date Earn Earned ed
Lectured Project management course to BTECH Civil Engineering East London Students Campus
Feb.2012
Jun-16
Full-Time Lectureship
Lectured Civil Engineering Documentation & Construction Management, Construction Materials etc to ND Civil Eng.Students
Butterworth Campus
May.2013
Sept .2 .20 16 16
742,5 Lett e errs of of Ap Appoint m me ent s At tta ached
Exam Moderator
Moderated Exam papers and Marked Scripts for Construction Materials.Construction Methods etc
East London & Butterworth Campus
May.2013
Sept.2016
24 Letters of of Ap Appointments At Attached
Walter Sisulu University
Course Advisory Board Membership
Member-Civil Eng.Dept.Advisory Board
Evaluated, commented and advised on the relevance of subject material taught on Engineering courses.
ECSA Course Accreditation Workshop
ECSA Course Accreditation
Course Accreditee
Compilation of Course files for Accreditation
Institution
Assignment
Role
Work Performed
C ou ou rs rse L ec ec tu tu re re sh sh ip ip
Part-Time Lectureship
Venue
Comm Commen entt
LECTURESHIP
Wa lt lt er er S is isu lu lu U ni ni ve ver si si ty ty
Wa lt lt er er S is isu lu lu U ni ni ve ver si si ty ty
Walter Sisulu University
C ou ou rs rse L ec ec tu tu re re sh sh ip ip
Exam Moderation
East London & Butterworth Campus East London & Butterworth Campus
288 Letters of Appointments Attached
3rd Dec.2014 26th Nov., 20 14
6 Letters Letters of Invitation Attached Attached
27th No Nov., 2014
TOTALS
16 Letters Letters of Invitation Attache Attached d 1076,5
Application for Registration Registration as a Professional Construction Construction Project Manager Manager submitted by JOSCELYN BERNARD NARTEY (PrCPM (Cand) ) – Sept 2017: CANDIDATE LOG BOOK 2511/30
II. INDIVIDUAL PRACTICE REPORT_CONT'D NAME OF CANDIDATE:
JB Nartey
REGISTRATION NO.:
B/903/2010
DURATION OF CANDIDATURE:
4 years
CANDIDATURE GOALS
Provide the candidate with experience to practice and apply project management methods to a real life project
Min 1600-3000 man-hours
Man Hour Worksheet
Institution
Assignment
Role
Topic
Venue
Start Da Date
Completion Da Date
Man Hours Earned
Comment
PUBLICATIONS & PRESENTATIONS
Intelligence Transfer Centre
Intelligence Transfer Centre
South African Institution of Civil Engineers
D-Tech Tactical
D-Tech Tactical TOTALS
1st Legal & Financial compliance for Contract Management in Government & SOE’SResource Person 2nd Annual Dam Management & Rehabilitation In Africa
Writing an Article for Publication
Resource Person
Professional Member
Good Contract Management practices- A Municipal perspective ;
Dam Rehabilitation And Management: The Role Of Municipalities;
CSIR Convention Centre,Pretoria 21-May-13
Thank you letter 16 Attached
25-Jul-12
Letter of Appreciation 16 Attached
Gallagher Centre,Midrand, South Africa 24-Jul-12
‘Build relationships not bid packages’,
22nd May 2013
Mthatha Jul-11
Course Presentation
Course Facilitator
Contract Admin & Management ( GCC2015)
Manzini, Swaziland
Course Presentation
Course Facilitator
Contract Admin & Management ( GCC2015)
Durban, South Africa
16
Published in the SAICE Journal, July 2011 edition, South Africa
29-Jun-17
30-Jun-17
Certificate of 16 Appreciation Attached
19 Sept. 2016
20 Sept.2016
Certificate of 16 Appreciation Attached 80
II. INDIVIDUAL PRACTICE REPORT_CONT'D NAME OF CANDIDATE:
JB Nartey
REGISTRATION NO.:
B/903/2010
DURATION OF CANDIDATURE:
4 years
CANDIDATURE GOALS
Provide the candidate with experience to practice and apply project management methods to a real life project
Min 1600-3000 man-hours
Man Hour Worksheet
Institution
Assignment
Role
Topic
Venue
Start Da Date
Completion Da Date
Man Hours Earned
Comment
PUBLICATIONS & PRESENTATIONS
Intelligence Transfer Centre
Intelligence Transfer Centre
South African Institution of Civil Engineers
D-Tech Tactical
D-Tech Tactical
1st Legal & Financial compliance for Contract Management in Government & SOE’SResource Person 2nd Annual Dam Management & Rehabilitation In Africa
Writing an Article for Publication
Resource Person
Professional Member
Good Contract Management practices- A Municipal perspective ;
Dam Rehabilitation And Management: The Role Of Municipalities;
CSIR Convention Centre,Pretoria 21-May-13
22nd May 2013
Thank you letter 16 Attached
25-Jul-12
Letter of Appreciation 16 Attached
Gallagher Centre,Midrand, South Africa 24-Jul-12
‘Build relationships not bid packages’,
Mthatha
Manzini, Swaziland Durban, South Africa
Jul-11
Course Presentation
Course Facilitator
Contract Admin & Management ( GCC2015)
Course Presentation
Course Facilitator
Contract Admin & Management ( GCC2015)
16
Published in the SAICE Journal, July 2011 edition, South Africa
29-Jun-17
30-Jun-17
Certificate of 16 Appreciation Attached
19 Sept. 2016
20 Sept.2016
Certificate of 16 Appreciation Attached
TOTALS
80
Application for Registration as a Professional Construction Project Manager submitted by JOSCELYN BERNARD NARTEY (PrCPM (Cand) ) – Sept 2017: CANDIDATE LOG BOOK 2611/30
II. INDIVIDUAL PRACTICE REPORT_CONT'D NAME OF CANDIDATE:
JB Nartey
REGISTRATION NO.:
B/903/2010
DURATION OF CANDIDATURE 4 years CANDIDATURE GOALS
Min 1600-3000 man-hours
Provide the candidate with experience to practice and apply project management methods to a real life project Man Hour Worksheet
Institution
Start Date
Completion Date
Man Hours Earned Comment
Assignment
Role
Work Performed
Venue
Zaathi Engineers & Project Managers
Executive hotel upgrade and conversion, Butterworth
Project Manager
Feasibility Studies & Business plan Dev’t,
Butterworth
SOSK Civils
Greenville Hospital: Repairs & Maintenance of water & sanitation system, Dept.of Health/Dept of Public Works
Contract Manager
Contract administration and supervision of Greenville Hospital: Repairs & Maintenance of water & sanitation system, Dept.of Health/Dept of Public Works
Bizana
Oct.2015
Feb.2016
Reports Available 408 upon request
Masizhake Developments
Rezoning of Amberdate Farm, Portion 47 of Portion 12, Queenstown; Project Manager
Estimation of the availability and capacity of bulk services, Compilation of Engineering Services Report, Analysis of current/future traffic flow and Compilation of traffic impact assessment report.
Queenstown
Apr-16
Jul-16
Reports Available 264 upon request
OR Tambo District Municipality
Quarry and bitumen premix plant near Qumbu
Project Manager
Preparation of an RFQ for the recruitment of Consulting Engineers to carry out Feasibility Studies /B /Business P la lan De Development
Qumbu
29-Jan- 13 13
5 Feb.2013
ECTTC/SPROUT Fuels
20 No.Fuel Depot & Distribution Facilities in EC- Pilot Phase
Project Manager
Prepared a Soft Brief
East London
ECTTC/SPROUT Fuels
21 No.Fuel Depot & Distribution Facilities in EC- Pilot Phase
Project Manager
Prepared a Project Development Strategy
East London
Zaathi Engineers & Project Managers Zaathi Engineers & Project Managers
Waste to Energy Project in Ghana Waste to Energy Project in Ghana
Preparation of Ghana Energy Industry Survey Report Drafting of a Project Procurement Model
Ghana;Accra & Kumasi Ghana;Accra & Kumasi
PRIVATE CONSULTING
Project Manager Project Manager
Jul-13
11th June 2015 11th June 2015
19th June 2015
1st Feb.2016 Feb.2016 11th Feb.2016 Feb.2016 11th Feb.2016
TOTALS
Reports Available 176 upon request
Reports Available 64 upon request Reports Available 2 upon request Reports Available 72 upon request Reports Available 88 upon request Reports Available 8 upon request 1082
Application for Registration as a Professional Construction Project Manager submitted by JOSCELYN BERNARD NARTEY (PrCPM (Cand) ) – Sept 2017: CANDIDATE LOG BOOK 2711/30
Application for Registration as a Professional Construction Project Manager submitted by JOSCELYN BERNARD NARTEY (PrCPM (Cand) ) – Sept 2017: CANDIDATE LOG BOOK 2811/30