400KV PROTECTION PREPARED BY GOPALA KRISHNA PALEPU ADE/MRT(PROTECTION)
[email protected], Mobile:9440336984
BASICS OF ONE AND HALF CIRCUIT BREAKER SCHEME PREPARED BY GOPALA KRISHNA PALEPU ADE/MRT(PROTECTION)
ONE & HALF BREAKER DESCRIPTION BUS-1
1. IN THIS TWO BUSES ARE PRIOVIDED.
BUS-1
BUS-2
BUS-2
ONE & HALF BREAKER DESCRIPTION BUS-1
2. THESE TWO BUSES ARE INTER-CONNECTED BY THREE CIRCUIT BREAKERS.
BUS-1
BUS-2
BUS-2
ONE & HALF BREAKER DESCRIPTION BUS-1
3. THEY ARE DESIGNATED AS 1-52 CB, 2-52 CB, 3-52 CB.
1-52 CB
BUS-1
BUS-2
1-52 CB
3-52 CB
2-52 CB
2-52 CB
3-52 CB BUS-2
ONE & HALF BREAKER DESCRIPTION BUS-1
4. LINE - 1 IS CONNECTED IN BETWEEN 1-52 CB & 2-52 CB. 5. LINE - 2 IS CONNECTED IN BETWEEN 3-52 CB & 2-52 CB.
1-52 CB
LINE-1
BUS-1
BUS-2
1-52 CB
3-52 CB
2-52 CB
LINE-2 2-52 CB
3-52 CB LINE-1 BUS-2
LINE-2
ONE & HALF BREAKER DESCRIPTION BUS-1 1-52 CB
LINE-1
6. LINE-1 HAVING TWO FEEDING PATHS i.e A. VIA BUS-1 & 1-52 CB B. VIA BUS-2, 3-52 CB & 2-52 CB 7. LINE-2 HAVING TWO FEEDING PATHS i.e A. VIA BUS-2 & 3-52 CB B. VIA BUS-1, 1-52 CB & 2-52 CB
BUS-1
BUS-2
1-52 CB
3-52 CB
2-52 CB
LINE-2
2-52 CB
3-52 CB LINE-1 BUS-2
LINE-2
ONE & HALF BREAKER DESCRIPTION BUS-1
8. FOR INTURUPTING LINE-1 THE 1-52CB AND 2-52CB IS TO BE TRIPPED. 9. FOR INTURUPTING LINE-2 THE 3-52CB AND 2-52CB IS TO BE TRIPPED.
1-52 CB
LINE-1
BUS-1
BUS-2
1-52 CB
3-52 CB
2-52 CB
LINE-2 2-52 CB
3-52 CB LINE-1 BUS-2
LINE-2
ONE & HALF BREAKER DESCRIPTION BUS-1
10. FOR ANY PROBLEM IN LINE-1 OR LINE-2 ALONG WITH MAIN BREAKER THE MIDDLE BREAKER OR SAY TIE BREAKER (2-52 CB) MUST TRIP.
1-52 CB
LINE-1
BUS-1
BUS-2
1-52 CB
3-52 CB
2-52 CB
LINE-2 2-52 CB
3-52 CB LINE-1 BUS-2
LINE-2
ONE & HALF BREAKER DESCRIPTION BUS-1 1-52 CB
LINE-1
11. NORMALLY IN ALL TYPES OF BUSBAR CONFIGUARATIONS ONE BREAKER IS SUFFICIENT FOR ONE FEEDER. 12. HERE TWO FEEDERS ARE CONTROLED BY THREE BREAKERS. 13. SO THESE TWO FEEDERS CONTROLLED BY THREE CIRCUIT BREAKERS IT IS CALLED ONE & HALF BREAKER SYSTEM.
BUS-1
BUS-2
1-52 CB
3-52 CB
2-52 CB
LINE-2 2-52 CB
3-52 CB LINE-1 BUS-2
LINE-2
1-52 CB
LINE-1
2-52 CB
LINE-2
14. THE BAY BETWEEN BUS-1 & LINE-1 IS CALLED MAIN BAY FOR FEEDER-1.
BUS-1
MAIN BAY(1ST BAY) FOR FEEDER-1
BUS-1
MAIN BAY(1ST BAY) FOR FEEDER-1
ONE & HALF BREAKER DESCRIPTION
BUS-2
1-52 CB
3-52 CB
2-52 CB
3-52 CB LINE-1 BUS-2
LINE-2
LINE-1
2-52 CB
LINE-2
15. THE BAY BETWEEN LINE-1 & LINE-2 IS CALLED TIE BAY FOR FEEDER-1 & 2.
BUS-1
MAIN BAY(1ST BAY) FOR FEEDER-1
1-52 CB
TIE BAY (2ND BAY ) FOR FEEDER-1 & 2
BUS-1
MAIN BAY(1ST BAY) FOR FEEDER-1
ONE & HALF BREAKER DESCRIPTION
BUS-2
1-52 CB
3-52 CB
2-52 CB
3-52 CB LINE-1 BUS-2
LINE-2
TIE BAY (2ND BAY ) FOR FEEDER-1 & 2.
LINE-2
3-52 CB BUS-2
BUS-1
BUS-2
1-52 CB
3-52 CB
2-52 CB
LINE-1
LINE-2
TIE BAY (2ND BAY ) FOR FEEDER-1 & 2.
MAIN BAY(3RD BAY) FOR FEEDER-2
2-52 CB
16. THE BAY BETWEEN BUS-2 & LINE-2 IS CALLED MAIN BAY FOR FEEDER-2.
MAIN BAY(1ST BAY) FOR FEEDER-1
LINE-1
TIE BAY (2ND BAY ) FOR FEEDER-1 & 2
1-52 CB
MAIN BAY(3RD BAY) FOR FEEDER-2
BUS-1
MAIN BAY(1ST BAY) FOR FEEDER-1
ONE & HALF BREAKER DESCRIPTION
LINE-2
3-52 CB BUS-2
BUS-1
BUS-2
1-52 CB
3-52 CB
2-52 CB
LINE-1
LINE-2
TIE BAY (2ND BAY ) FOR FEEDER-1 & 2.
MAIN BAY(3RD BAY) FOR FEEDER-2
2-52 CB
17. IN THIS SYSTEM FULL DIA MEANS 2 FEEDERS CONTROLLED BY 3 CBs. 18. HALF DIA MEANS 1 FEEDER CONTROLLED BY 2 CBs. (Nothing but Double CB System)
MAIN BAY(1ST BAY) FOR FEEDER-1
LINE-1
TIE BAY (2ND BAY ) FOR FEEDER-1 & 2
1-52 CB
MAIN BAY(3RD BAY) FOR FEEDER-2
BUS-1
MAIN BAY(1ST BAY) FOR FEEDER-1
ONE & HALF BREAKER DESCRIPTION
ONE & HALF BREAKER DESCRIPTION
3-52 CB BUS-2
BUS-2
1-52 CB
3-52 CB
2-52 CB
LINE-1
LINE-2
TIE BAY (2ND BAY ) FOR FEEDER-1 & 2.
MAIN BAY(3RD BAY) FOR FEEDER-2
LINE-2
BUS-1
MAIN BAY(1ST BAY) FOR FEEDER-1
2-52 CB
GOPALA KRISHNA PALEPU ADE/MRT/ T&C/400KV SS/ O/O CE/400KV / L&SS/ VS APTRANSCO, HYDERABAD
[email protected] Mobile: 9440336984
MAIN BAY(1ST BAY) FOR FEEDER-1
LINE-1
TIE BAY (2ND BAY ) FOR FEEDER-1 & 2
1-52 CB
MAIN BAY(3RD BAY) FOR FEEDER-2
BUS-1
SUBSTATION DESIGN/LAYOUT (I-CONFIGUARATION)
BAY16 BAY18
BAY17
BAY14
BAY11
BAY13
DIA6
BAY15
BAY6
FEEDER11
DIA5
BAY12
BAY5
BAY1 BAY2 BAY3
DIA4 BAY10
DIA3
BAY4
DIA2
FEEDER9
FEEDER7
BAY8
BUS-1 DIA1
FEEDER5
BAY7
FEEDER3
BAY9
FEEDER1
BUS-2
FEEDER2
FEEDER4
FEEDER6
FEEDER8
FEEDER10
FEEDER12
SUBSTATION DESIGN/LAYOUT (D-CONFIGUARATION) FEEDER10 BAY14
BAY13
BAY7
DIA1
FEEDER9
BAY8
BAY3
BAY1
BAY2
FEEDER6
DIA3
BAY15
FEEDER5
FEEDER2
BAY9
FEEDER1
DIA5
BUS-1
BAY5
FEEDER3
BAY11
FEEDER4
FEEDER7
FEEDER8
DIA6
BAY18
BAY16
DIA4
BAY12
BAY10
DIA2
BAY6
BAY4
BUS-2
BAY17
FEEDER11
FEEDER12
SUBSTATION DESIGN/LAYOUT (DOUBLE BUS & DOUBLE BREAKER SYSTEM) FEEDER1
FEEDER3
FEEDER1
FEEDER3
BAY6
BAY5
BAY2
BAY1
BAY7
BAY5
BAY3
BAY1
BUS-1
BUS-1
BAY8
BAY7
BAY4
BAY3
BAY8
BAY6
BAY4
BAY2
BUS-2
BUS-2
FEEDER2
FEEDER4
FEEDER2
FEEDER4
FOR ECONOMICAL& RELIABULITY PURPOSE THIS SYSTEM ADOPTED IN 800KV SYSTEM
FEEDER 8
FEEDER 1 1-52 CB
FEEDER 2 2-52 CB
3-52 CB
8-52 CB
FEEDER 7
MESH / RING LAYOUT 4-52 CB
7-52 CB
5-52 CB
6-52 CB FEEDER 6
FEEDER 3
FEEDER 5
FEEDER 4
SUBSTATION DESIGN/LAYOUT (DOUBLE MAIN BUS & TRANSFER BUS SYSTEM) T/F-1
T/F-2
BUS-2
BAY3 BAY1
BAY2
FEEDER1 FEEDER2
BAY4
TRANSFER BUS
BAY5
TRANSFER BUS COUPLER
BUS COUPLER
BUS-1
BAY6
BAY7
BAY8
FEEDER3 FEEDER4
FOR ECONOMICAL& RELIABULITY PURPOSE THIS SYSTEM ADOPTED IN 400 & 220 KV SYSTEM
SUBSTATION DESIGN/LAYOUT (DOUBLE MAIN BUS & CB BYPASS ISO SYSTEM) T/F-1
BAY2
BAY6
BAY4
BAY7
BUS COUPLER
BAY1
T/F-2
BUS-1
BUS-2
BAY3
BAY5
WHEN ANY CB PROBLEM OR FOR PREVENTIVE MAINTANENCE THEN ALL OTHER FEEDERS SHIFTED TO ANOTHER BUS OF FAULTED CB BUS AND CLOSE THE BYPASS ISOLATOR, THEN PROTECTION IS SHIFTED TO BUS COUPLER AND OPEN THE FAULTY CB.
FEEDER1
FEEDER2
FEEDER3
FEEDER4
FOR ECONOMICAL& RELIABULITY PURPOSE THIS SYSTEM ADOPTED IN 220KV SYSTEM
SUBSTATION DESIGN/LAYOUT (SINGLE BUS & TRANSFER BUS SYSTEM) T/F-2
T/F-1
TRANSFER BUS COUPLER
TRANSFER BUS
BUS-1 BAY1
FEEDER1
BAY2
FEEDER2
BAY3
BAY4
BAY5
BAY6
FEEDER3
BAY7
FEEDER4
FOR ECONOMICAL& RELIABULITY PURPOSE THIS SYSTEM ADOPTED IN 220 & 132 KV SYSTEM
CT METHODS IN ONE AND HALF CIRCUIT BREAKER SCHEME PREPARED BY GOPALA KRISHNA PALEPU ADE/MRT(PROTECTION)
DIFFERENT CT METHODS OF ONE & HALF BREAKER SYSTEM
CB LINE CB LINE CB LINE
CB
CB 4 CT METHOD
CB
CB
CB
AT/F AT/F
CB
CB
6 CT METHOD CB
LINE
CB
5 CT METHOD
LINE LINE
CB 3 CT METHOD
CB
CB
6 CT METHOD CB
CB 6 CT METHOD
CB
AT/F AT/F AT/F AT/F
ONE & HALF BREAKER SYSTEM (3CT METHOD) BUS-1
BUS-2
1-89
3-89
1-52CB 1-CT
3-52CB P2
P2
3 3-CT
3
P1
P1
1-89A
3-89A
3 3
2-CT
2-89A 2-52CB 1-89L
P1
P2
2-89B 3-89T
LINE 1 T/F-1
ONE & HALF BREAKER SYSTEM (4CT METHOD) BUS-1
BUS-2
1-89
3-89
1-52CB 1-CT
3-52CB P2
P2
3 3-CT
3
P1
P1
1-89A
3-89A
2-89A 1-89L
P1
2-BCT P1
2-52CB
3
P2
3
2-ACT
P2
2-89B 3-89T
LINE 1 T/F-1
ONE & HALF BREAKER SYSTEM (5CT METHOD) BUS-1
BUS-2
1-89
3-89
1-52CB 1-CT
3-52CB P2
P2
3 3-CT
3P1
P1
1-89A
3-89A
P1
2-89A
2-52CB
3
2-CT P2
2-89B
1-89L 1L-CT
3-89T P2
3P1
P2
3T-CT 3 P1
LINE 1 T/F-1
ONE & HALF BREAKER SYSTEM (6CT METHOD) BUS-1
BUS-2
1-89 P2 P1
3-89
3 1A-CT
3A-CT
P2
3
1-52CB
3-52CB
P1
3B-CT
1B-CT 3 P2
1-89A
3
P1 P2
3-89A
2-89A
P1
2B-CT P1
2-52CB
3
P2
3
2A-CT
1-89L
P1
P2
2-89B 3-89T
T/F-1 LINE 1
ONE & HALF BREAKER SYSTEM (6CT METHOD) BUS-1
BUS-2
1-89
3-89
1-52CB
3-52CB
P2
3-CT
1-CT 3 P1
1-89A
2-89A
P1
2B-CT P1
2-52CB
3
3
P2
P2
2-89B
1-89L 1L-CT 3 P1
LINE 1
P1
3-89A 2A-CT
P2
3
P2
3-89T
3T-CT
P2
3 P1
T/F-1
ONE & HALF BREAKER SYSTEM (6CT METHOD) BUS-1
BUS-2
1-89 P2
P2
3 1-CT
1-52CB
3-52CB
1-89A
3-89A
2-89A
P1
2B-CT P1
2-52CB
3
P2
3
2A-CT
P2
2-89B
1-89L 1L-CT 3 P1
LINE 1
3 3-CT
P1
P1
P2
3-89
3-89T
3T-CT
P2
3 P1
T/F-1
ONE & HALF BREAKER SYSTEM (8CT METHOD) BUS-1
BUS-2
1-89 P2 P1
3-89
3 1A-CT
3A-CT
P2
3
1-52CB
3-52CB
P1
3B-CT
1B-CT 3 P2
3
1-89A
P1 P2
3-89A
2-89A
P1
2B-CT P1
2-52CB
3
P2
3
2A-CT
P2
2-89B 3-89T
1-89L P2
P1
3 1L-CT P1
3T-CT
P2
3
P1
T/F-1 LINE 1
TYPICAL ONE & HALF BREAKER SYSTEM ADOPTED IN GIS DS : DISCONNECTOR SWITCH, GS: GROUNDING SWITCH, CT: CURRENT TRANSFORMER, VD: VOLTAGE DIVIDER
TYPICAL ONE & HALF BREAKER SYSTEM ADOPTED IN GIS DS : DISCONNECTOR SWITCH, GS: GROUNDING SWITCH, CT: CURRENT TRANSFORMER, VD: VOLTAGE DIVIDER
1-1/2 CB SYSTEM (SIEMENS VATECH) VD
VD
CT DS
CT CB
CT DS
DS
CT CB
GS
GS
GS
GS
VD GS
GS
GS
GS
VD
CT DS
DS
CT CB
DS
CORE WISE APLICATION OF CTs IN ONE AND HALF CIRCUIT BREAKER SCHEME PREPARED BY GOPALA KRISHNA PALEPU ADE/MRT(PROTECTION)
CURRENT TRANSFORMER CONNECTIONS IN 3CT METHOD 1 – CT 2 – CT 3 – CT BUSBAR-1 2CT’s SECONDARIES ARE CONNECTED IN PARALLEL AND CORE – 1 ( PS)
CORE – 2 ( PS)
CORE – 3
PROTECTION
CONNECTED TO MAIN PROTECTION FOR TRANSFORMER
BUSBAR-1 CHECKUP PROTECTION (SPARE)
2CT’s SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO BACKUP PROTECTION AFTER LBB/BFR FOR TRANSFORMER
SPARE
METERING & ENERGY METER FOR AT/F
( 0.5 / 0.2)
CORE – 4
METERING & ENERGY METER FOR FEEDER
SPARE
2CT’s SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO MAIN-2 PROTECTION AFTER LBB/BFR FOR FEEDER
BUSBAR-2 CHECKUP PROTECTION (SPARE)
2CT’s SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO MAIN-1 PROTECTION FOR FEEDER
BUSBAR-2 PROTECTION
(0.5 / 0.2)
CORE – 5 ( PS)
CORE – 6 ( PS)
CURRENT TRANSFORMER CONNECTIONS IN 3CT METHOD 1 – CT 2 – CT 3 – CT BUSBAR-1 2CT’s SECONDARIES ARE CONNECTED IN PARALLEL AND CORE – 1 ( PS)
CORE – 2 ( PS)
CORE – 3
PROTECTION
CONNECTED TO MAIN PROTECTION FOR TRANSFORMER
BUSBAR-1 CHECKUP PROTECTION (SPARE)
2CT’s SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO BACKUP PROTECTION AFTER LBB/BFR FOR TRANSFORMER
METERING & ENERGY METER FOR FEEDER
SPARE
2CT’s SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO MAIN-2 PROTECTION AFTER LBB/BFR FOR FEEDER
BUSBAR-2 CHECKUP PROTECTION (SPARE)
2CT’s SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO MAIN-1 PROTECTION FOR FEEDER
BUSBAR-2 PROTECTION
(0.5 / 0.2)
CORE – 4 ( PS)
CORE – 5 ( PS)
BUSHING CT METERING CORE (0.5 / 0.2)
NORMALLY THIS SYTEM ADOPTS, WHEN ONE SIDE LINE, OTHER SIDE AUTO TRANSFORMER / BUS REACTOR IS PROVIDED IN A DIA OF ONE AND HALF BREAKER SYSTEM, IF BUSHING CT METERING CORE IS AVAILABLE, THEN IT IS USED FOR METERING & ENERGY METER FOR AT/F OR BUS REACTOR.
CURRENT TRANSFORMER CONNECTIONS IN 4CT METHOD CORE-1 (PS)
CORE-2 (PS)
CORE-3 (0.5/0.2)
CORE-4 (PS)
CORE-5 (PS)
1- CT
2-BCT
2-ACT
3-CT
CT SECONDARY CORE IS CONNECTED TO BUSBAR-1 PROTECTION
SPARE
SPARE
CT SECONDARY CORE IS CONNECTED TO BUSBAR-2 PROTECTION
BUSBAR-1 CHECKUP PROTECTION (SPARE)
SPARE
SPARE
BUSBAR-2 CHECKUP PROTECTION (SPARE)
2CT’s SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO PANEL METERS & ENERGY METER
2CT’s SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO PANEL METERS & ENERGY METER
2CT’s SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO MAIN-2 PROTECTION AFTER LBB/BFR
2CT’s SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO BACKUP PROTECTION AFTER LBB/BFR
2CT’s SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO MAIN-1 PROTECTION
2CT’s SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO MAIN PROTECTION
CURRENT TRANSFORMER CONNECTIONS IN 5CT METHOD 1-CT
1-LCT
2-CT
3-TCT
3-CT
BUSBAR-1 PROTECTION
TEED PROT-1 (BAY 1&2)
TEED PROT-1 (BAY 2&3)
TEED PROT-1 (BAY 2&3)
BUSBAR-2 PROTECTION
BUSBAR-1 CHECKUP PROTECTION (SPARE)
TEED PROT-2 (BAY 1&2)
TEED PROT-2 (BAY 2&3)
TEED PROT-2 (BAY 2&3)
BUSBAR-2 CHECKUP PROTECTION (SPARE)
CORE-3 (0.5/0.2)
SPARE
METERING & ENERGY METER
SPARE
METERING & ENERGY METER
SPARE
CORE-4 (PS)
TEED PROT-2 (BAY 1&2) AFTER LBB/BFR (1-52)
MAIN-2 PROTECTION
TEED PROT-2 (BAY 1&2) AFTER LBB/BFR (2-52)
BACKUP PROTECTION
TEED PROT-2 (BAY 2&3) AFTER LBB/BFR (3-52)
CORE-5 (PS)
TEED PROT-1 (BAY 1&2)
MAIN-1 PROTECTION
TEED PROT-1 (BAY 1&2)
MAIN PROTECTION
TEED PROT-1 (BAY 2&3)
CORE-1 (PS) CORE-2 (PS)
Paralleling of 2Nos CTs to the Main-1/Main-2/Backup line protection is not required. This gives better transient response. Separate STUB protection can be connected (Nothing BUT TEED Protection).
CURRENT TRANSFORMER CONNECTIONS IN 6CT METHOD (GIS or AIS with DEAD TANK CBs) 1B-CT CORE-1 (PS) CORE-2 (PS)
BUSBAR-1 PROTECTION
BUSBAR-1 CHECKUP PROTECTION
(SPARE)
CORE-3 (0.5/0.2)
SPARE
1A-CT
2B-CT
2A-CT
3A-CT
2CT’s SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO MAIN-1 PROTECTION
2CT’s SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO MAIN-1 PROTECTION
2CT’s SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO MAIN-2 PROTECTION AFTER LBB/BFR
2CT’s SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO BACKUP PROTECTION AFTER LBB/BFR
2CT’s SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO PANEL METERS & ENERGY METER
2CT’s SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO PANEL METERS & ENERGY METER
3B-CT BUSBAR-2 PROTECTION
BUSBAR-2 CHECKUP PROTECTION
(SPARE)
SPARE
CURRENT TRANSFORMER CONNECTIONS IN 6CT METHOD 1-CT
1L-CT
2A-CT
2B-CT
3T-CT
3-CT
CORE-1 (PS) CORE-2 (PS)
BUSBAR-1 PROTECTION
TEED PROT-1 (BAY 1&2)
SPARE
SPARE
TEED PROT-1 (BAY 2&3)
BUSBAR-2 PROTECTION
BUSBAR-1 CHECKUP
TEED PROT-2 (BAY 1&2)
SPARE
SPARE
TEED PROT-2 (BAY 2&3)
BUSBAR-2 CHECKUP
CORE-3 (0.5/0.2)
SPARE
METERING & ENERGY METER
SPARE
SPARE
METERING & ENERGY METER
SPARE
CORE-4 (PS)
TEED PROT-2 (BAY 1&2)
MAIN-2 PROTECTION
TEED PROT-2 (BAY 2&3)
TEED PROT-2 (BAY 1&2)
BACKUP PROTECTION
TEED PROT-2 (BAY 2&3)
CORE-5 (PS)
TEED PROT-1 (BAY 1&2)
PROTECTION (SPARE)
PROTECTION (SPARE)
AFTER LBB/BFR (1-52)
AFTER LBB/BFR (2-52)
MAIN-1 PROTECTION
TEED PROT-1 (BAY 2&3)
TEED PROT-1 (BAY 1&2)
AFTER LBB/BFR (3-52)
MAIN PROTECTION
TEED PROT-1 (BAY 2&3)
CURRENT TRANSFORMER CONNECTIONS IN 8CT METHOD 1B-CT
1A-CT
1L-CT
2B-CT
2A-CT
3T-CT
3A-CT
3B-CT
BUSBAR-1 MAIN-1 PROTECTION
LBB PROT (BAY-1)
TEED PROT-1 (BAY 1&2)
LBB PROT (BAY-2)
LBB PROT (BAY-2)
TEED PROT-1 (BAY 2&3)
LBB PROT (BAY-3)
BUSBAR-2 MAIN-1 PROTECTION
BUSBAR-1 MAIN-2 PROTECTION
LBB PROT (BAY-1)
TEED PROT-2 (BAY 1&2)
TEED PROT-1 (BAY 2&3)
TEED PROT-2 TEED PROT-2 (BAY 2&3) (BAY 2&3)
LBB PROT (BAY-3)
BUSBAR-2 MAIN-2 PROTECTION
MAIN-2
TEED PROT-2 (BAY 1&2)
TEED PROT-1 (BAY 1&2)
TEED PROT-1 (BAY 2&3)
TEED PROT-2 (BAY 2&3)
CORE-1 (PS) CORE-2 (PS) CORE-3 (PS)
TEED PROT-2 TEEDPROT-1 (BAY 1&2) (BAY 1&2)
CORE-4 (PS)
TEED-1 FOR BAY-1 & 2 IS: 1L-CT, 1A-CT & 2A-CT
CORE-5 (0.5/0.2)
TEED-2 FOR BAY-1 & 2 IS: 1L-CT, 1B-CT & 2B-CT
PROTECTION
MAIN-1 PROTECTION METERING & ENERGY METER
SOME TIMES DUPLICATED BUSBAR PROTECTION WITH DUPLICATE LBB IS REQUIRED
BACKUP PROTECTION
MAIN PROTECTION METERING & ENERGY METER
TEED-1 FOR BAY-2 & 3 IS: 3T-CT, 3A-CT & 2B-CT TEED-2 FOR BAY-2 & 3 IS: 3T-CT, 3B-CT & 2A-CT
CT CORES CONEECTION DIAGRAMS IN ONE AND HALF CIRCUIT BREAKER SCHEME PREPARED BY GOPALA KRISHNA PALEPU ADE/MRT(PROTECTION)
1
3 3 3
3 2
BB-EVT / CVT 1-52CB
3
1
3 3 3
3
3
CORES 3 4
MAIN-1 PROTECTION
MAIN-2/BACKUP PROTECTION
3
2
3
BUS
METERING
BUS BAR CHECKUP PROT
1-89 1
3
P2
BUS BAR PROTECTION
3
SINGLE BUS SYSTEM 1-CT 5 P1
1-89L 1-CVT
2
3
ONE & HALF BREAKER ( 3 CT METHOD) WITH PROTECTION SCHEME 87BB1 BUSBAR-1 79 CVT VBB1
21M1 VBB1
VL1
25
VL1 / VL2 OR VBB2
BF 87L
21M2
VL1
CVT
VL1 FEEDER1 / LINE1
79 VL1 / VBB1 VL2 / VBB2
25
BF
FEEDER2 / LINE2 CVT VL2
MAIN-1 BF VL2 / VL1 OR VBB1 CVT VBB2
VBB2
MAIN-2
PROTECTION OF LINE2 (OR TRANSFORMER, IF APPLICABLE)
79 25 BUSBAR-2 87BB2
FOR TRANSFORMER PROTECTION & METERING VOLTAGE SELECTION RELAYS FOR BUS-1, BUS-2& LINE ARE PROVIDED .
ONE & HALF BREAKER ( 4 CT METHOD) WITH PROTECTION SCHEME 87BB1 BUSBAR-1 79 CVT VBB1
21M1 VBB1
VL1
25
VL1 / VL2 OR VBB2
BF 87L
21M2
VL1
CVT
VL1 FEEDER1 / LINE1
79 VL1 / VBB1 VL2 / VBB2
25
BF
FEEDER2 / LINE2 CVT VL2
MAIN-1 BF VL2 / VL1 OR VBB1 CVT VBB2
VBB2
MAIN-2
PROTECTION OF LINE2 (OR TRANSFORMER, IF APPLICABLE)
79 25 BUSBAR-2 87BB2
FOR TRANSFORMER PROTECTION & METERING VOLTAGE SELECTION RELAYS FOR BUS-1, BUS-2& LINE ARE PROVIDED .
ONE & HALF BREAKER ( 6 CT METHOD) WITH PROTECTION SCHEME 87BB1 BUSBAR-1 CVT
21M1
VBB1
BF
79 VBB1
VL1
25
87L
VL1 / VL2 OR VBB2
21M2
VL1
CVT
VL1 FEEDER1 / LINE1
79 VL1 / VBB1 VL2 / VBB2
25
BF
FEEDER2 / LINE2 CVT VL2
MAIN-1 VL2 / VL1 OR VBB1 CVT VBB2
VBB2
BF
79
MAIN-2
PROTECTION OF LINE2 (OR TRANSFORMER, IF APPLICABLE)
25 BUSBAR-2 87BB2
FOR TRANSFORMER PROTECTION & METERING VOLTAGE SELECTION RELAYS FOR BUS-1, BUS-2& LINE ARE PROVIDED .
ONE & HALF BREAKER ( 5 CT METHOD) WITH PROTECTION SCHEME 87BB1 BUSBAR-1 21M1
79
87 TD1 HZ
CVT VBB1
VBB1
VL1
25
VL1 / VL2 OR VBB2
BF
.
87L
87 TD2 LZ
21M2
VL1
CVT
VL1 FEEDER1 / LINE1
79 VL1 / VBB1 VL2 / VBB2
25
BF
FEEDER2 / LINE2
. BF VL2 / VL1 OR VBB1 CVT VBB2
VBB2
CVT VL2 MAIN-1 87 TD2 LZ
PROTECTION OF LINE2 (OR TRANSFORMER, IF APPLICABLE) MAIN-2
79 87 TD1 HZ
25
BUSBAR-2 87BB2
FOR TRANSFORMER PROTECTION & METERING VOLTAGE SELECTION RELAYS FOR BUS-1, BUS-2& LINE ARE PROVIDED .
ONE & HALF BREAKER ( 6 CT METHOD) WITH PROTECTION SCHEME 87BB1 BUSBAR-1 21M1
79
87 TD1 HZ
CVT VBB1
VBB1
VL1
25
VL1 / VL2 OR VBB2
BF
.
87L
87 TD2 LZ
21M2
VL1
CVT
VL1 FEEDER1 / LINE1
79 VL1 / VBB1 VL2 / VBB2
25
BF
FEEDER2 / LINE2
. BF VL2 / VL1 OR VBB1 CVT VBB2
VBB2
CVT VL2 MAIN-1 87 TD2 LZ
PROTECTION OF LINE2 (OR TRANSFORMER, IF APPLICABLE) MAIN-2
79 87 TD1 HZ
25
BUSBAR-2 87BB2
FOR TRANSFORMER PROTECTION & METERING VOLTAGE SELECTION RELAYS FOR BUS-1, BUS-2& LINE ARE PROVIDED .
ONE & HALF BREAKER ( 6 CT METHOD) WITH PROTECTION SCHEME 87BB1 BUSBAR-1 21M1
VL1
87 TD1 HZ
CVT VBB1
BF 87 TD2 LZ
79 VBB1
87L
21M2
VL1
CVT
VL1
25
VL1 / VL2 OR VBB2
FEEDER1 / LINE1
79 VL1 / VBB1 VL2 / VBB2
VL2 / VL1 OR VBB1 VBB2
25
BF
FEEDER2 / LINE2 79 CVT VL2 25
MAIN-1 87 TD2 LZ
PROTECTION OF LINE2 (OR TRANSFORMER, IF APPLICABLE) MAIN-2
BF
VBB2 CVT
87 TD1 HZ BUSBAR-2 87BB2
FOR TRANSFORMER PROTECTION & METERING VOLTAGE SELECTION RELAYS FOR BUS-1, BUS-2& LINE ARE PROVIDED .
ONE & HALF BREAKER ( 6 CT METHOD) WITH PROTECTION SCHEME CVT VBB1 (WITH LATEST CONCEPT) BUSBAR-1 VL1 / VL2 OR VBB2
21M1
25
VL1
VBB1 79
87BB
BF
87L
21M2
VL1
CVT
VL1 FEEDER1 / LINE1
VL1 / VBB1 VL2 / VBB2 25 79
87BB
BF
IN THIS CONCEPT FOR ONE & HALF BREAKER SYSTEM A NEW RELAY DEVELOPED WHICH INCLUDES AUTO RECLOSURE + CHECK SYN + LBB RELAY(79+25+50). FROM THIS RELAY TO BUSBAR RELAY ONLY FIBRE OPTIC CONNECTION(NO PHYSICAL). THE DATA WILL BE COMMUNICATED BETWEEN 87BB & LBB. IN THIS 1+1 DUPLICATED BUSBAR PROTECTION IS ADOPTED. FEEDER2 / LINE2
BF 79
CVT VL2
MAIN-1 MAIN-2
PROTECTION OF LINE2 (OR TRANSFORMER, IF APPLICABLE)
VBB2 VL2 / VL1 OR VBB1
25 BUSBAR-2 CVT VBB2
FOR TRANSFORMER PROTECTION & METERING VOLTAGE SELECTION RELAYS FOR BUS-1, BUS-2& LINE ARE PROVIDED .
MET+SYN
MAIN-1 MAIN-2
3-52CB
2-52CB
BUS-II
87T1- ICT DIFF PROT1
87 BB M1 BUSBAR PROTN MAIN-1 87 BB M2 BUSBAR PROTN MAIN-2 67HV- ICT DIR O/C,E/F
21L1- LINE DIST PROT1 21L2- LINE DIST PROT2 87 BB M2 BUSBAR PROTN MAIN-2 87 BB M1 BUSBAR PROTN MAIN-1
1-52CB
MAIN-1 MAIN-2
BUS-I
MAIN-1 MAIN-2 MET+SYN
ONE & HALF BREAKER ( 3 CT METHOD) WITH PROTECTION SCHEME
MET+SYN
DISTURBANCE RECORDER, EVENT RECORDER, FAULT LOCATOR ARE IN BUILT FUNCTIONS IN BOTH NUMERICAL DIST PROT RELAYS 21L1 & 21L2
DISTURBANCE RECORDER, EVENT RECORDER, ARE IN BUILT FUNCTIONS IN BOTH NUMERICAL DIFF PROT RELAYS 87T1 & 87T2
87T2- ICT DIFF PROT2
LATEST CONCEPT REDUNDANT LINE PROTECTION REDUNDANT ICT PROTECTION REDUNDANT BUSBAR PROTECTION LBB IS IN BUILT FUNCTION OF BUSBAR
FOR ICT CVT IS NOT AVAILABLE. ACCORDING TO CONDITION IT IS SELECTED BUS-1 CVT OR BUS-2 CVT OR LINE CVT HV & LV OVER FLUX PROT ARE IN BUILT. ICT HV METERING IS BUSHING CT
MET+SYN
DISTURBANCE RECORDER, EVENT RECORDER, FAULT LOCATOR ARE IN BUILT FUNCTIONS IN BOTH NUMERICAL DIST PROT RELAYS 21L1 & 21L2
DISTURBANCE RECORDER, EVENT RECORDER, ARE IN BUILT FUNCTIONS IN BOTH NUMERICAL DIFF PROT RELAYS 87T1 & 87T2
87T2- ICT DIFF PROT2
LATEST CONCEPT REDUNDANT LINE PROTECTION REDUNDANT ICT PROTECTION REDUNDANT BUSBAR PROTECTION LBB IS IN BUILT FUNCTION OF BUSBAR
FOR ICT CVT IS NOT AVAILABLE. ACCORDING TO CONDITION IT IS SELECTED BUS-1 CVT OR BUS-2 CVT OR LINE CVT HV & LV OVER FLUX PROT ARE IN BUILT
MET+SYN
MAIN-1 MAIN-2
3-52CB
2-52CB
BUS-II
87 BB M1 BUSBAR PROTN MAIN-1 87 BB M2 BUSBAR PROTN MAIN-2 67HV- ICT DIR O/C,E/F 87T1- ICT DIFF PROT1
21L1- LINE DIST PROT1 21L2- LINE DIST PROT2 87 BB M2 BUSBAR PROTN MAIN-2 87 BB M1 BUSBAR PROTN MAIN-1
1-52CB
MAIN-1 MAIN-2
BUS-I
MAIN-1 MAIN-2 MET+SYN
ONE & HALF BREAKER ( 4 CT METHOD) WITH PROTECTION SCHEME
NUMERICAL BUSBAR SCHEME INCL LBB/BFR/CBF (DECENTRALISED & CENTRALISED ARCHITECTURE) DECENTRALISED CONCEPT FO
CENTRALISED CONCEPT
(REB 500) ABB
BU/PU
(REB 670) ABB
OR (7 SS 52) SIEMENS
(487B) SEL
FO OR
OR
BU/PU
OR (MICOM P740) AREVA
(MICOM P746) AREVA
BU/PU FO
BU / PU TO BUSBAR DIGITAL COMMUNICATION LBB INBUILT FEATURE
LBB INBUILT FEATURE
COMPARISION BETWEEN DIFFERENT CT METHODS CT PURPOSE
3 CT METHOD
4 CT METHOD
6 CT (S) METHOD
5 CT METHOD
6 CT (T1) METHOD
6 CT (T2) METHOD
BUSBAR & BUSBAR CHECKUP PROTECTION
1 CT
1 CT
1B CT
1 CT
1 CT
1 CT
MAIN-1 MAIN-2 PROTECTION & METERING
ADDITIONAL PROTECTION AVAILABLE
BLIND ZONE
ADVANTAGES
ABOVE FOR BUS-1
&
BELOW FOR BUS-2
3 CT
3 CT
3B CT
3 CT
3 CT
3 CT
1 - CT & 2 - CT
1 CT & 2 B - CT
1 A – CT & 2 B – CT
1 L - CT
1 L - CT
1 L - CT
ABOVE CT SECONDARIES ARE CONNECTED PARALLEL FOR FEEDER-1 BELOW CT SECONDARIES ARE CONNECTED PARALLEL FOR FEEDER-2 3 - CT & 2 – CT
3 - CT & 2 A - CT
3 A - CT & 2 A - CT
ABOVE FOR FEEDER-1 BELOW FOR FEEDER-2 3 L - CT
3 L - CT
3 L – CT
STUB-1 & STUB-2 PROTECTION FOR LINE & AT/F
TEED-1 & TEED-2 PROTECTION FOR LINE & AT/F
STUB-1 & STUB-2 PROTECTION IS A NORMALLY INBUILT PROTECTION FOR MAIN-1 & MAIN-2 RELAYS, IN CASE OF LATEST NUMERICAL RELAYS. STUB PROTECTION WORKS WHEN LINE ISOLATOR OPEN CONDITION ONLY.
TEED–1 IS NORMALLY HIGH IMPEDENCE DIFFERENTIAL RELAY & TEED-2 IS NORMALLY LOW IMPEDENCE DIFFERENTIAL RELAY. THESE ARE NOT INBUILT FUNCTIONS OF MAIN-1 & MAIN-2 RELAYS.
A FAULT BETWEEN CIRCUIT BREAKERS AND CT (END FAULT) MAY THEN STILL BE FED FROM ONE SIDE EVEN WHEN THE BREAKER HAS BEEN OPENED. CONSEQUENTLY, FINAL FAULT CLEARING BY CASCADED TRIPPING HAS TO BE ACCEPTED IN THIS CASE. THIS SITUATION LBB/BFR OPERATES AND TIME TAKEN TO CLEAR FAULT IS ABOUT 300 mSECs. THIS IS BLIND ZONE AREA. MINIMUM CT METHOD. REDUCING THE COST OF CTs
TIE CB BLIND ZONE AREA IS TAKEN CARE.
MAIN CB & TIE CB BLIND ZONE AREA IS TAKEN CARE
WHEN THE FAULT IS TAKEN PLACE BETWEEN THE MAIN CB, TIE CB & LINE ISOLATOR, DURING SERVICE ONLY, DISTANCE SCHEME SHOULD TAKE CARE.
BLIND ZONE FOR MAIN CB & TIE CB
TIE CB BLIND ZONE AREA IS TAKEN CARE
TIE CB BLIND ZONE AREA IS TAKEN CARE
WHEN THE FAULT IS TAKEN PLACE BETWEEN THE MAIN CB, TIE CB & LINE ISOLATOR DURING SERVICE ONLY, TEED PROTECTION IN ADDITION TO DISTANCE SCHEME SHOULD TAKE CARE.
400KV C.T. INFORMATION P1
PRIMARY CONNECTIONS : P1 – P2 CURRENT RATING : 2000 AMPS
500/ 1A
1S1 – 1S3
1S1 – 1S2 1S2 – 1S3
__
PS
BUSBAR CHECKUP 2S1 – 2S3 PROTECTION
2S1 – 2S2 2S2 – 2S3
CORE-3 0.5 / 0.2
METERING
3S1 – 3S3 3S4 – 3S2
CORE-4
MAIN-2 4S1 – 4S3 4S1 – 4S2 4S1 – 4S4 PROTECTION 4S4 – 4S2 4S4 – 4S3 5S1 – 5S2 5S4 – 5S3
3
U
5S1 – 5S3 5S4 – 5S2
3
2S12 2S 3 2S
1 5S S2 5 S3 5 S4 5
U
MAIN-1 5S1 – 5S4 PROTECTION
3
U
PS
1 1S S1 1S 2 3
4S1 4S2 4S3 4S4
3S1 3S2 3S3 3S4
CORE-5
PS
3S1 – 3S4
__ 3S1 – 3S2 3S4 – 3S3
3 3
2S1 2S2 2S3
3
CORE-2
1S1 1S2 1S3
U
BUSBAR PROTECTION
5S1 5S2 5S3 5S4 4S1 4S2 4S3 4S4
3S1 3S2 3S3 3S4
PS
CORE-1
3
1000/ 1A
U
2000/ 1A
3
PURPOSE
U
CLASS
P1 P2
3 3
CORES
SECONDARY CONNECTIONS CURRENT RATING : 1A
P2
HAIR PIN / U SHAPE DESIGN
EYE BOLT DESIGN
DEAD TANK DESIGN
MAIN-1, MAIN-2 PROTECTION & METERING FOR LINE ADOPTED IN ONE AND HALF CIRCUIT BREAKER SCHEME
PREPARED BY GOPALA KRISHNA PALEPU ADE/MRT(PROTECTION)
NORMS OF PROTECTION FOLLOWED IN APTRANSCO FOR TRANSMISIION LINES & DISTRIBUTION LINES ( FEEDER / LINE PROTECTION )
Sr.No 1. 2. 3. 4.
VOLTAGE 11 KV LINES 33 KV LINES 66 KV LINES 132 KV LINES
MAIN- 1 PROTECTION
MAIN-2 PROTECTION/ BACKUP PROTECTION
2 O/L + E/F ( 51 + 51N )
-
3 O/L + E/F ( 51 + 51N )
-
SWITCHED DISTANCE SCHEME OR NUMERICAL DISTANCE SCHEME (21P+ 21N)
DIRECTIONAL O/L & E/F RELAYS WITH HIGH SET ( 67 + 67N )
NON SWITCHED DISTANCE SCHEME OR
SWITCHED DISTANCE SCHEME OR
5.
220 KV LINES NUMERICAL DISTANCE SCHEME (21P + 21N) NUMERICAL DISTANCE SCHEME (21P+ 21N)
6.
DISTANCE SCHEME (21P + 21N) NUMERICAL DISTANCE SCHEME (21) OR LINE 400 KV LINES NUMERICAL + in BUILT DEF RELAY(67N) DIFFERENTIAL SCHEME (87L) WITH 67N
7.
DISTANCE SCHEME (21P + 21N) NUMERICAL DISTANCE SCHEME (21) OR LINE 765 KV LINES NUMERICAL + in BUILT DEF RELAY(67N) DIFFERENTIAL SCHEME (87L) WITH 67N
IF MAIN-1 & MAIN-2 ARE NUMERICAL RELAYS, BOTH SHOULD BE SEPARATE MEASURING PRINCIPLES (CHARECTERESTICS), MODELS AND ALGORITHAMS (SHOULD NOT BE DUPLICATED) AND ALL FEATURES SHOULD BE AVAILABLE IN BOTH SCHEMES AND BOTH RELAYS SHOULD BE 100% REDENDENCY IN ALL ASPECTS ( COMPLEMENTARY TO EACH OTHER ) . DISSIMILAR CARRIER SCHEMES ARE TO BE SELECTED ( POTT & PUTT or BLOCK & UNBLOCK). OTHER WISE MAIN-2 MAY BE DIFFERENT MAKE OR PHASE COMPARISION PROTECTION/LINE DIFFERENTIAL PROTECTION WITH BACKUP DISTANCE PROTECTION IS TO BE ADOPTED. BOTH M1 & M2 SHOULD CONTAIN DIRECTIONAL EARTH FAULT PROTECTION (67N) WITH DIRECTIONAL COMPARISION PICKUP SCHEME AS INBUILT FUNCTION. ZONE-1: 80% OF MAIN LINE ZONE-2: 100% OF MAIN LINE + 50% OF SHORTEST LINE AT OTHER END ZONE-3: 100% OF MAIN LINE + 100% OF SHORTEST LINE AT OTHER END ZONE-4: 100% OF MAIN LINE + (100% OF SHORTEST LINE + 20% OF LONGEST LINE) AT
OTHER END.
MAIN-1 PROTECTION FOR LINE (21L1) P2 P2 P2
CT MB
IR5 / A511 IY5 / A531 IB5 / A551
1-CT CTR: 2000-1000-500/1A
3 3 3
CORE-5
(4CT METHOD)
5S4
5S4
5S4
5S2
5S2
5S2
IN5 / A571
CLASS: PS
VR11 / E111 VY11 / E131 VB11 / E151 VN11 / E171 1-CVT
3 CT METHOD : 1-CT & 2-CT 4 CT METHOD : 1-CT & 2-BCT 6 CT METHOD : 1-ACT & 2-BCT
CORE – 1 200VA CLASS: 3P
CT MB
2-BCT CTR: 2000-1000-500/1A
3 3 3
CORE-5
5S2
5S2
5S2
5S4
5S4
5S4
CLASS: PS
P2 P2 P2
MAIN-1 PROTECTION FOR LINE (21L1) (4CT METHOD) (NEW DEVELOPMENT) P2 P2 P2
CT MB IR5 / A511 IY5 / A531 IB5 / A551
1-CT CTR: 2000-1000-500/1A
3 3 3
CORE-5
5S4
5S4
5S4
5S2
5S2
5S2
IN5 / A571
3 CT METHOD : 1-CT & 2-CT 4 CT METHOD : 1-CT & 2-BCT 6 CT METHOD : 1-ACT & 2-BCT
CLASS: PS
ESC
IN5 / A571
3 3 3
CTR: 2000-1000-500/1A
ENABLED TRIP
CT MB
2-BCT CORE-5
IA =250.10 A IB =250.10 A IC =250.10 A VAB =400.0 KV VBC =400.0 KV VCA =400.0 KV
5S2
5S2
5S2
5S4
5S4
5S4
CLASS: PS
IB5 / A551 IY5 / A531 IR5 / A511
P2 P2 P2
INST TIME COMM SOTF ZONE1 ZONE2 ZONE3 ZONE4
SEL
ENT
TARGET RESET
PH-A PH-B PH-C GND 50 51 79 RESET 79 LOCKOUT
SEL- 421 PROTECTION AUTOMATION CONTROL
VR11 / E111 VY11 / E131 VB11 / E151 VN11 / E171
1-CVT CORE – 1 200VA CLASS: 3P
MAIN-1 PROTECTION FOR LINE (21L1) (5CT METHOD)
P2 P2 P2
IR5 / A511 IY5 / A531 IB5 / A551
1-LCT CTR: 2000-1000-500/1A
CLASS: PS
3 3 3
CORE-5
CT MB
5S4
5S4
5S4
5S2
5S2
5S2
IN5 / A571
VR11 / E111 VY11 / E131 VB11 / E151 VN11 / E171 1-CVT CORE – 1 200VA CLASS: 3P
MAIN-2 PROTECTION FOR LINE (21L2) (4CT METHOD) P2 P2 P2
50Z LBB/BFR
CT MB
1-CT CTR: 2000-1000-500/1A
3 3 3
CORE-4
4S4
4S4
4S4
4S2
4S2
4S2
IN4 / C471
CLASS: PS
VR21 / E211 VY21 / E231 VB21 / E251 VN21 / E271 1-CVT
3 CT METHOD : 1-CT & 2-CT 4 CT METHOD : 1-CT & 2-BCT 6 CT METHOD : 1-ACT & 2-BCT
200VA CLASS: 3P
CT MB
3 3 3
CTR: 2000-1000-500/1A
21 L2
CORE – 2
2-BCT CORE-4
IR4 / C411 IY4 / C431 IB4 / C451
4S2
4S2
4S2
4S4
4S4
4S4
CLASS: PS
P2 P2 P2
50ZT LBB/BFR
MAIN-2 PROTECTION FOR LINE (21L2) (4CT METHOD) ( NEW DEVELOPMENT) P2 P2 P2
CT MB IR4 / C411 IY4 / C431 IB4 / C451
1-CT CTR: 2000-1000-500/1A
3 3 3
CORE-4
4S4
4S4
4S4
4S2
4S2
4S2
IN4 / C471
3 CT METHOD : 1-CT & 2-CT 4 CT METHOD : 1-CT & 2-BCT 6 CT METHOD : 1-ACT & 2-BCT
CLASS: PS
CT MB
2-BCT CTR: 2000-1000-500/1A
3 3 3
CORE-4
IN4 / C471 4S2
4S2
4S2
4S4
4S4
4S4
CLASS: PS
P2 P2 P2
IB4 / C451 IY4 / C431 IR4 / C411
VR21 / E211 VY21 / E231 VB21 / E251 VN21 / E271
1-CVT CORE – 2 200VA CLASS: 3P
MULTI FUNCTION NUMERICAL RELAY FOR MULTI BREAKER, MULTI CT & CVT/PT APPLICATION 3-52 CB
BUS-1 PT
BUS-2 PT 59
50 BF-1 50 BF-2
79-1 79-2 25-1
25-2
21P 50P 51P 67P 27 21N 50N 51N 67N
3
3 LINE CVT LINE
3
3
3 3
2-52 CB
3
1-52 CB
3
(NEW APPLICATION) (ONE & HALF BREAKER SYSTEM or RING BUS SYSTEM)
1-52,2-52: MAIN & TIE CIRCUIT BREAKER 21P: PHASE DISTANCE PROTECTION 21N: GROUND DISTANCE PROTECTION 27: UNDER VOLTAGE RELAY 67: DIRECTIONAL RELAY 50: INST OVER CURRENT RELAY 51: TIME OVER CURRENT RELAY 59: OVER VOLTAGE RELAY 64: EARTH FAULT RELAY 50BF-1: LBB/BFR OF MAIN CB 50BF-2: LBB/BFR OF TIE CB 79-1,2: AUTO RECLOSURE RELAY OF MAIN & TIE CB 25-1,2: CHECK SYNCHRONISAM RELAY FOR MAIN & TIE CB
MAIN-2 PROTECTION FOR LINE (21L2) (5CT METHOD)
P2 P2 P2
IR4 / C411 IY4 / C431 IB4 / C451
1-LCT CTR: 2000-1000-500/1A
CLASS: PS
3 3 3
CORE-4
CT MB
4S4
4S4
4S4
4S2
4S2
4S2
IN4 / C471
VR21 / E211 VY21 / E231 VB21 / E251 VN21 / E271 1-CVT CORE – 2 200VA CLASS: 3P
MULTI FUNCTION PANEL METERING & ENERGY METER (4CT METHOD) P2 P2 P2
CT MB IR3 / D311 IY3 / D331 IB3 / D351
1-CT CTR: 2000-1000-500/1A
3 3 3
CORE-3
3S4
3S4
3S4
3S2
3S2
3S2
IN3 / D371
3 CT METHOD : 1-CT & 2-CT 4 CT METHOD : 1-CT & 2-BCT 6 CT METHOD : 1-ACT & 2-BCT
CLASS: 0.5
CT MB
2-BCT CTR: 2000-1000-500/1A
3 3 3
CORE-3
3S2
3S2
3S2
3S4
3S4
3S4
CLASS: 0.5
VR31 / E311 VY31 / E331 VB31 / E351 VN31 / E371 1-CVT CORE – 3 100VA
P2 P2 P2
CLASS: 0.5/0.2
MULTI FUNCTION PANEL METERING & ENERGY METER (5CT METHOD) P2 P2 P2
IR3 / D311 IY3 / D331 IB3 / D351
1-LCT CTR: 2000-1000-500/1A
3 3 3
CORE-3
CT MB
3S4
3S4
3S4
3S2
3S2
3S2
CLASS: 0.5/0.2 IN3 / D371
VR31 / E311 VY31 / E331 VB31 / E351 VN31 / E371 1-CVT CORE – 3 100VA CLASS: 0.5/0.2
LBB & BUSBAR PROTECTION SCHEMES ADOPTED IN ONE AND HALF CIRCUIT BREAKER SCHEME PREPARED BY GOPALA KRISHNA PALEPU ADE/MRT(PROTECTION)
BASICS OF LBB/BFR PROTECTION LOCAL BREAKER BACKUP PROTECTION A PROTECTION WHICH IS DESIGNED TO CLEAR A SYSTEM FAULTY BY INITIATING TRIPPING OTHER CIRCUIT BREAKER(S) IN THE CASE OF FAILURE TO TRIP OF THE APPROPRIATE CIRCUIT BREAKER. IN MODERN NETWORKS THE CRITICAL FAULT CLEARING TIME MAY BE LESS THAN 200ms. HENCE, IF THE FAULT IS NOT CLEARED DUE TO FAILURE OF THE PRIMARY PROTECTIVE RELAYS OR THEIR ASSOCIATED CIRCUIT BREAKER, A FAST ACTING BACKUP PROTECTIVE RELAY MUST CLEAR THE FAULT. THERE ARE TWO BASIC FORMS. REMOTE BACK-UP. LOCAL BACK-UP.
REMOTE BACK-UP PROVIDES BACK-UP PROTECTION FOR THE BOTH THE RELAYS (MAIN-1 & MAIN-2) AND BREAKERS AT REMOTE SUBSTATION.
LOCAL BACK-UP LOCAL BACK-UP PROTECTION CAN BE DEVIDED INTO TWO CATAGORIES. RELAY BACK-UP BREAKER BACK-UP
RELAY BACK-UP z
DUPLICATE PRIMARY PROTECTION. i.e ONE IS NON SWITCHED DISTANCE PROTECTION AND ANOTHER IS SWITCHED DISTANCE SCHEME OR OTHER WISE BOTH SCHEMES CHARECTERSTICS ARE DIFFERENT (QUADRALATERAL, MHO CIRCULAR, TAMOTO & OPTICAL ) OR DIFFERENT MANUFACTURERS(ABB, ALSTOM, SIEMENS, EASUN REYROLL, SEL, GE, NXT PHASE OR BASLER) OR DIFFERENT METHODS (i.e ELECTROMECHANICAL, STATIC, NUMERICAL{MICROPROCESSOR &DSP}). IF MAIN-1 & MAIN-2 ARE NUMERICAL RELAYS BOTH SHOULD BE SEPARATE CHARECTERESTICS AND SEPARATE MODELS AND ALL FEATURES SHOULD BE AVAILABLE IN BOTH SCHEMES AND BOTH RELAYS SHOULD BE 100% REDENDENCY IN ALL ASPECTS. TO INCREASE THE SECURITY, THE CIRCUIT BREAKER HAS TWO TRIP COILS, ONE IS CONNECTED TO MAIN-1 PROTECTION AND ANOTHER IS CONNECTED TO MAIN-2 PROTECTION.
BREAKER BACK-UP BECAUSE OF THE HIGH COST OF HIGH VOLTAGE CIRCUIT BREAKERS, IT IS NOT FEASIBLE TO DUPLICATE THEM. IN CASE OF A BREAKER FAILURE THE OTHER CIRCUIT BREAKERS CONNECTED TO THE SAME BUS AS THE FAULTED BREAKER MUST THERE FORE BE TRIPPED.
LBB/BFR FLOW CHART MAIN PROTECTION OPERATED
YES
TRIP MAIN BREAKER
FAULT CLEARED
NO
RETRIP
YES
INITIATE BFR
YES
RESET BREAKER FAILURE SCHEME
WAIT FOR FAULT CLEARENCE
AND
TRIP BACK-UP/ Adjacent BREAKERS
The Breaker Failure Protection (LBB/BFR) can operate single-stage/two-stage. When used as single-stage protection, the Bus trip command is given to the adjacent Circuit Breakers if the protected feeder Breaker fails. When used as two-stage protection, the first stage can be used to repeat the trip command to the relevant feeder Breaker, normally on a different trip coil, if the initial trip command from the feeder protection is not successful. The second stage will result in a Bus trip to the adjacent Breakers, if the command of the first stage is not successful.
LBB/BFR TIME CO-ORDINATION CHART FAULT OCCURS
NORMAL CLEARING TIME
NORMAL CLEARING PROTECTIVE RELAY FOR EX: DISTANCE RELAY
RESETTING TIME OF THE CURRENT MEASURING UNITS
BREAKER INTURUPTING TIME
~30ms
~60ms
MARGIN
<12ms
SET TIME OF THE TIME MEASURING UNIT
INOPERATIVE BREAKER
TRIPPING RELAY TIME
BACK-UP BREAKER INTERUPTING TIME
BREAKER FAILURE RELAY START TOTAL CLEARING TIME OF THE BREAKER FAILURE RELAY MAXIMUM FAULT CLEARING TIME BEFORE SYSTEM INSTABILITY
MARGIN
LBB/BFR LOGIC CURRENT INPUTS PHASE L1
LED (PHASE START) ALARM RELAY (PHASE START)
A/D CONVERTER PHASE CURRENT SET POINT
~
I > ISET
&
PHASE L2/E PHASE L3
>1 I > ISET |||
& ALARM RELAY (EARTH START)
EARTH CURRENT SET POINT
OUT PUT OF DISTANCE RELAY OR SHORT CIRCUIT CURRENT RELAY
LED (EARTH START)
BINARY INPUT CIRCUIT BREAKER FAILURE INITIATE
TIMING/OUTPUT STAGE
TRIP T1 RELAY
TIME STAGE T1
LED
& 0
1
TIME STAGE T2 SWITCHED OFF
>1
TIME STAGE T2
O& 0
ALARM T1 RELAY
&
1
TRIP T2 RELAY
LED LED CB FAILURE INITIATE
LBB/BFR PROTECTION LINE1 BUS-1
¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾
AT/F-1 1-52CB
50Z
2-52CB
50ZT
3-52CB
50Z
BUS-2
LBB/BFR IS LOCAL BREAKER BACKUP PROTECTION/ BREAKER FAILURE RELAY. 1No RELAY IS PROVIDED FOR EACH BREAKER. THIS IS CURRENT OPERATED RELAY. THIS RELAY IS ENERGISED WHEN MASTER TRIP RELAY(86-A OR/AND 86-B) OPERATES OR SINGLE PHASE TRIP RELAYS OPERATES AND GIVEN SIGNAL TO BREAKER FOR TRIP. IN THIS RELAY TIME DELAY IS PROVIDED. THIS RELAY OPERATES WHEN THE BREAKER IS UNDER TROUBLE/ FAILS TO OPERATE. AFTER ENERGISED THE RELAY AND TIME DELAY COMPLETES, EVEN CURRENT IS THERE THIS THINKS BREAKER FAIL TO OPERATE AND GIVEN SIGNAL AS PER SCHEME DESCRIBED NEXT PRESENTATION. NEW CONCEPT: Normally the CT connections for LBB/BFR relay is in series with Main-2 Protection. In case of Numerical Distributed LBB/BFR and Centralized Bus-Bar System, the CT connections for Bus-Bar are terminated at LBB/BFR and Centralized Bus-Bar is interconnected by Fiber-Optic cable.
1-52 CB LBB/BFR OPERATION 86-A
50Z
DIRECT TRIP 1&2 VIA CARRIER TO OTHER END BUSBAR-1 PROTECTION OPTD AND BUSBAR-1 ISOLATED
TO 86-B TRIP RELAY OF TIE CB(2-52CB)
1-52CB TC-1 BUS-1
ABB REL316 MAIN-2
86-B
86-B
86-A
ABB REL521 MAIN-1
TC-2
2-52CB TC-2 TC-1
3-52CB BUS-2
Breaker Failure Relay of the Main Circuit Breaker Trips the Connected Bus, Tie Circuit Breaker, and Remote End Circuit Breaker
2-52 CB LBB/BFR OPERATION ABB RET521 MAIN-1
86-A
ABB REL521 MAIN-1
86-B
ABB REL316 MAIN-2
ABB RET316 MAIN-2
50ZT DIRECT TRIP 1&2 VIA CARRIER TO OTHER END
INTER TRIP TO LVCB & TBCCB
TO 86-B TRIP RELAY OF AT/F(ICT) CB (3-52CB)
TO 86-B TRIP RELAY OF LINE CB(1-52CB)
2-52CB
1-52CB TC-1 BUS-1
3-52CB TC-2 BUS-2
Breaker Failure Relay of the Tie Circuit Breaker Trips the Both Main Circuit Breakers and Remote End Circuit Breakers ( In case of Transformer LV Circuit Breaker)
3-52 CB LBB/BFR OPERATION
ABB RET316 MAIN-2
86-A 86-B
86-B
86-A
ABB RET521 MAIN-1
50Z INTER TRIP TO LV CB & TBC CB BUSBAR-2 PROTECTION OPTD AND BUSBAR-2 ISOLATED
TO 86-B TRIP RELAY OF TIE CB(2-52CB)
2-52CB
1-52CB TC-1 BUS-1
3-52CB TC-2
TC-2
TC-1 BUS-2
Breaker Failure Relay of the Main Circuit Breaker Trips the Connected Bus, Tie Circuit Breaker, and Remote End Circuit Breaker ( In case of Transformer LV Circuit Breaker)
BASICS OF BUSBAR PROTECTION NEED FOR BUSBAR PROTECTION ¾ IN ITS ABSENCE FAULT CLEARING TAKES PLACE IN ZONE-2 OF DISTANCE RELAY BY REMOTE END TRIPPING. ¾ THIS MEANS SLOW AND UNSELECTIVE TRIPPING AND WIDE SPREAD BLACKOUT.
EFFECT OF DELAYED CLEARENCE ¾ GREATER DAMAGE AT FAULT POINT. ¾ INDIRECT SHOCK TO CONNECTED EQUIPMENT LIKE SHAFTS OF GENERATOR AND WINDINGS OF TRANSFORMER.
BASIC THEORY ¾ KIRCHOFF’s CURRENT LAW STATES THAT THE SUM OF THE CURRENTS ENTERING A GIVEN NODE MUST BE EQUAL TO THE CURRENTS LEAVING AT THAT NODE.
BUS BAR PROTECTION SYSTEMS 1. 2. 3. 4.
HIGH IMPEDENCE DIFFERENTIAL PROTECTION MODERATE-IMPEDENCE DIFFERENTIAL PROTECTION LOW-IMPEDENCE DIFFERENTIAL PROTECTION NUMERICAL BUS DIFFERENTIAL PROTECTION
HIGH IMPEDENCE DIFFERENCIAL PROTECTION THE HIGH IMPEDENCE PROTECTION SCHEME, ON THE OTHER HAND, IS A GOOD SOLUTION FOR SINGLE BUSBAR ARRANGEMENTS , ONE & HALF BREAKER SYSTEMS OR RING BUSBARS, PROVIDING THAT APPROPRIATE DEDICATED CT CORES ARE AVAILABLE FOR THIS USE ALONE. IT IS SENSTIVE, STABLE & FAST PROTECTION. HOWEVER, SPECIAL CT REQUIREMENTS, ADDITIONAL HIGH VOLTAGE DEVICE PROTECTION, DEMANDING MAINTANENCE etc PUT RESTRICTIONS IN ITS APPLICATIONS. A MEASURING CIRCUIT COMPRISES A HIGH-IMPEDENCE STABILIZING RESISTOR CONNECTED ACROSS THE CIRCULATING CURRENT ARRANGEMENT OF ALL THE CTs IN PARALLEL. THE VALUE OF THE STABILIZING RESISTOR IS CHOOSEN SUCH THAT THE VOLTAGE DROP ACROSS THE RELAY CIRCUIT IS INSUFFICIENT TO OPERATE THE FAULTS OUTSIDE THE PROTECTED ZONE.
LIMITATIONS OF CONVENTIONAL HIGH IMPEDENCE DIFFERENTIAL RELAY PUTS STRINGENT REQUIREMENTS ON CT’s. Class X for all CT Cores. NEED FOR DEDICATED CT CORES. Separate CT Cores for BUSBAR and CHECK ZONE Protection. IDENTICAL CT RATIO, MAGNETISING IMPEDENCE. AUX CT’s RATIO CORRECTIONS UNACCEPTABLE. IN ABILITY TO COPE WITH INCREASING FAULT CURRENT. SLOW RESPONSE. Advantage of Numerical Protection Technology (e.g. Fault recording, Communication etc) not available. BASIC OPERATING TIME EXCLUDING RELAY TIME IS 15 – 20ms. THIS RELAY REQUIRES CHECK ZONE FEATURE. THE TRIP COMMAND IS ONLY GIVEN WHEN BOTH A DISCRIMINATING & CHECK ZONE SYSTEM OPERATES.
MEDIUM IMPEDENCE DIFFERENTIAL PROTECTION MANY OF THE LIMITATIONS OF HIGH IMPEDENCE PROTECTION CAN BE OVERCOME USING MODERATE MEDIUM IMPEDENCE PROTECTION (OR STABILIZED HIGH-IMP SCHEME), WHICH IS A COMBINATION OF THE NORMAL HIGH-IMP AND STABILIZED DIFFERENTIAL SCHEMES.
LOW IMPEDENCE DIFFERENTIAL PROTECTION LOW IMPEDENCE PROTECTION(PERCENTAGE BIASED BUS DIFFERENTIAL RELAY) IS MOST SUITABLE PROTECTION SCHEME FOR DOUBLE AND MULTIPLE BUSBAR SYSTEMS (WITH OR WITHOUT TRANSFER BUS) WITH FEEDERS BEING SWITCHED BETWEEN SECTIONS OF BUSBAR, WHICH OPERATES WITH FULL SELECTIVITY FOR ALL POSSIBLE BUSBAR CONFIGUARATIONS.
ADVANTAGES ¾ ¾ ¾ ¾
FREE OF ANY NEED FOR MATCHED CT CHARACTERESTICS OR RATIOs, LOW LEAKAGE REACTANCE OR RESISTANCE. OTHER PROTECTIVE RELAYS CAN BE INCLUDED IN THE SAME CIRCUIT. STABLE FOR INFINITE FAULT LEVELS. INSENSITIVE TO CT SATURATION. DETECTS FAULTS WITHIN 1 – 2ms & INITIATES TRIPPING WITHIN 5 – 7ms.
BASICS OF BUS BAR PROTECTION BASIC THEORY KIRCHOFF’s CURENT LAW STATES THAT THE SUM OF THE CURRENTS ENTERING A GIVEN NODE MUST BE EQUAL TO THE CURRENTS LEAVING THAT NODE
EXTERNAL FAULT
INTERNAL FAULT IF
I1
I1 I2
I3
I2 I3
I4 I5
I4 I5
I6
I6
IF
IF= I6= I1+I2+I3+I4+I5
IF= I1+I2+I3+I4+I5+I6
HIGH IMPEDENCE BUSBAR PROTECTION 87BBC
UU
UU
UU
UU
UU
UU
UU
UU
UU
UU
UU
UU
87BBM
96 BBC : BUSBAR CHECK TRIPPING RELAY
52 CIRCUIT BREAKER TRIP COIL
- VE A varistor is normally applied across the relay input terminals to limit the voltage to a value safely below the insulation voltage of the secondary circuits
+ VE
96 BBM : BUSBAR MAIN TRIPPING RELAY
UU
UU OVER CURRENT COIL
UU
Is
Id
OVER CURRENT STARTER RELAYS
.
UU
UU 52 CIRCUIT BREAKER TRIP COIL
UU
OPERATING COIL
LOW IMPEDENCE BUSBAR PROTECTION RESTRAINT COIL
+VE
96 BUS BAR TRIPPING RELAY
-VE
DIFFERENCE BETWEEN BUSBAR SCHEMES HIGH IMPEDENCE BUSBAR PROTECTION
PERCENTAGE BIASED LOW IMPEDENCE BUS BAR PROTECTION
PRINCIPLE
THE CURRENTS ENTERING AND LEAVING THE BUSBAR ARE COMPARED CONTINUOSLY. IT INVOLVES CHOOSING OF IMPEDENCE HIGH ENOUGH STABLISE THE RELAY FOR HEAVY EXTERNAL FAULTS. THIS IS CIRCULATING CURRENT PRINCIPLE.
IT HAS DIFFERENTIAL AND BIAS SETTING. THE RESULTANT BIAS IS PROPOTIONAL TO ARITHMATIC SUM OF ALL CURRENTS, WHEREAS THE OPERATING CURRENT IS VECTOR SUM OF ALL CIRCUIT CURRENTS.
CTs
IT REQUIRES ALL IDENTICAL CT RATIO’s & TURNS RATIO. LOW IT CAN WORK WITH CTs OF UNEQUAL RATIOS ALSO. FREE OF RESISTANCE OF SECONDARY WINDING. Class X for all CT Cores. ANY NEED OF MATCHED CT CHARACTERESTIC OR RATIOs LOW MINIMUM KNEE POINT VOLTAGE OF 300-500V. LEAKAGE REACTANCE OR RESISTANCE. OTHER PROTECTIVE LOW MAGNETISING CURRENT(FEW MILLIAMPS). RELAYS CAN BE INCLUDED IN THE SAME CIRCUIT.
BURDEN
IMPOSES COMPARATIVELY HIGH BURDEN ON CTs. AUXILIARY CTs IMPOSES LESS BURDEN ON CTs. AUXILIARY CTs HAVE NO REDUCE THE PERFORMANCE OF THE SCHEME EFFECT ON PERFORMANCE OF SCHEME.
CT SATURATION
OPERATION OF SCHEME EVEN WHEN CTs GET SATURATED DURING OPERATION OF SCHEME EVEN WHEN CTs GET SATURATED INTERNAL FAULTS. DURING INTERNAL FAULTS. INSENSITIVE TO CT SATURATION.
UTILISATION
IT IS GOOD SOLUTION FOR SINGLE BUSBAR ARRANGEMENTS, ONE & MOST SUITABLE FOR DOUBLE AND MULTIPLE BUSBAR SYSTEMS HALF BREAKER SYSTEMS OR RING BUSBAR SYSTEMS. ( WITH OR WITHOUT TRANSFER BUS).
OPERATING TIME
BASIC OPERATING TIME EXCLUDING RELAY TIME IS 15 – 20 mS.
DETECTS FAULTS WITH IN 1 –2 mS AND INITIATES TRIPPING WITH IN 5-7 mS.
STABILITY
INABILITY TO COPE WITH INCREASING FAULT CURRENT.
STABLE FOR INFINITE FAULT LEVEL.
PERFORMANCE
HIGHLY SENSITIVE FOR INTERNAL FAULTS AND COMPLETELY STABLE HIGHLY SENSITIVE FOR INTERNAL FAULTS AND COMPLETELY FOR EXTERNAL FAULTS. STABLE FOR EXTERNAL FAULTS.
ADDITIONAL PROTECTION
THIS RELAY REQUIRES CHECK ZONE FEATURE. THE TRIP COMMAND IS THIS RELAY HAS IN BUILT CHECK ZONE FEATURE (NO SEPARATE ONLY GIVEN WHEN BOTH A DISCRIMINATING & CHECK ZONE SYSTEM CHECKZONE FEATURE) i.e OVER CURRENT STARTING RELAY OPERATES. PROVIDED.
DETAILS
BUS BAR MAIN & CHECHUP PROTECTION (ANY CT METHOD) P2 P2 P2
CT MB
1-CT CTR: 2000-1000/1A
IN1 / B171
3 3 3
CORE-1
BUS BAR PROTECTION FOR BUS-1
1S3
1S3
1S3
1S1
1S1
1S1
IB1 / B151
CLASS: PS
IY1 / B131 IR1 / B111
CT MB IR1 / B111 IY1 / B131
3-CT CTR: 2000-1000/1A
3 3 3
CORE-1
IB1 / B151 1S1
1S1
1S1
1S3
1S3
1S3
IN1 / B171
CLASS: PS
P2 P2 P2
BUS BAR PROTECTION FOR BUS-2
DUPLICATE BUS BAR PROTECTION (NEW DEVELOPMENT) P2 P2 P2
CT MB
BUS BAR PROTECTION FOR BUS-1
LBB 1-CT CTR: 2000-1000/1A
3 3 3
CORE-1
IN1 / B171 1S3
1S3
1S3
1S1
1S1
1S1
IB1 / B151
CLASS: PS
IY1 / B131 IR1 / B111
50Z
MAINCB LBB IS PART OF BUSBAR PROTECTION
LBB CT MB IR1 / B111 IY1 / B131
3-CT CTR: 2000-1000/1A
3 3 3
CORE-1
IB1 / B151 1S1
1S1
1S1
1S3
1S3
1S3
IN1 / B171
CLASS: PS
50Z P2 P2 P2
BUS BAR PROTECTION FOR BUS-2
BUS-2
87 – BB2 BUS BAR-2 PROTECTION
UU
10-CT
UU
13-CT
UU
16-CT
UU
UU
12-CT
UU
15-CT
UU
18-CT
UU
12-52
15-52
18-52
21-52
20-52
17-52
14-52
11-52
19-CT
7-CT
9-CT
19-52
16-52
13-52
10-52
7-52
4-52
1-52
87 – BB1
21-CT
UU
UU
9-52 8-52
4-CT
UU
1-CT
UU
6-CT
5-52
2-52
UU
3-CT
UU
6-52
3-52
BUS BAR PROTECTION BUS BAR-1 PROTECTION
BUS-1
NUMERICAL BUSBAR SCHEME INCL LBB/BFR/CBF (DECENTRALISED & CENTRALISED CONCEPTS) DECENTRALISED CONCEPT FO
CENTRALISED CONCEPT
(REB 500) ABB
MAIN CB LBB
(REB 670) ABB
OR (7 SS 52) SIEMENS
OR (487B) SEL
FO OR
OR
TIE CB LBB
OR (MICOM P740) AREVA
OR (MICOM P746) AREVA
MAIN CB LBB FO
LBB TO BUSBAR DIGITAL COMMUNICATION
LBB INBUILT FEATURE
LBB INBUILT FEATURE
NUMERICAL BUSBAR SCHEME INCL LBB/BFR/CBF (DECENTRALISED CONCEPT- DUPLICATE ) DECENTRALISED CONCEPT
(REB 500) ABB
DECENTRALISED CONCEPT FO FO
(REB 500) ABB
MAIN CB LBB MAIN CB LBB
OR
FO
(7 SS 52) SIEMENS
(7 SS 52) SIEMENS
TIE CB LBB
FO
OR
OR
OR
TIE CB LBB
(MICOM P740) AREVA
(MICOM P740) AREVA MAIN CB LBB MAIN CB LBB FO FO
LBB TO BUSBAR DIGITAL COMMUNICATION
LBB TO BUSBAR DIGITAL COMMUNICATION
NUMERICAL BUSBAR SCHEME INCL LBB/BFR/CBF (CENTRALISED CONCEPT - DUPLICATE) CENTRALISED CONCEPT
CENTRALISED CONCEPT
(REB 670) ABB
(REB 670) ABB
OR
OR (487B) SEL
(487B) SEL
OR OR (MICOM P746) AREVA
(MICOM P746) AREVA
LBB INBUILT FEATURE
LBB INBUILT FEATURE
BUSBAR-1 PROTECTION TRIPPING SCHEME HIGH SPEED TRIP RELAY FOR 1-52 CB
1-52 CB PANEL TRIP FROM 50 LBB TO START 50 LBB
4-52 CB PANEL
HIGH SPEED TRIP RELAY FOR 4-52 CB
TRIP FROM 50 LBB TO START 50 LBB
7-52 CB PANEL HIGH SPEED TRIP RELAY FOR 7-52 CB
TRIP FROM 50 LBB TO START 50 LBB
HIGH SPEED TRIP RELAY FOR 10-52 CB
10-52 CB PANEL TRIP FROM 50 LBB
1-52 CB PANEL TO CLOSE CKT INTERLOCK TO BLOCK A/R TO TRIP COIL-1 TO TRIP COIL-2 DIRECT TRIP SEND CH-1 DIRECT TRIP SEND CH-2 TO DISTURBENCE RECORDER
4-52 CB PANEL TO CLOSE CKT INTERLOCK TO BLOCK A/R TO TRIP COIL-1 TO TRIP COIL-2 DIRECT TRIP SEND CH-1 DIRECT TRIP SEND CH-2 TO DISTURBENCE RECORDER
7-52 CB PANEL TO CLOSE CKT INTERLOCK TO BLOCK A/R TO TRIP COIL-1 TO TRIP COIL-2 DIRECT TRIP SEND CH-1 DIRECT TRIP SEND CH-2 TO DISTURBENCE RECORDER
10-52CB PANEL TO CLOSE CKT INTERLOCK TO BLOCK A/R TO TRIP COIL-1 TO TRIP COIL-2 DIRECT TRIP SEND CH-1 DIRECT TRIP SEND CH-2 TO DISTURBENCE RECORDER
TO START 50 LBB
HIGH SPEED TRIP RELAY FOR 13-52 CB
13-52 CB PANEL TRIP FROM 50 LBB TO START 50 LBB
16-52 CB PANEL
HIGH SPEED TRIP RELAY FOR 16-52 CB
TRIP FROM 50 LBB TO START 50 LBB
+VE
BUSBAR PANEL
13-52 CB PANEL TO CLOSE CKT INTERLOCK TO BLOCK A/R TO TRIP COIL-1 TO TRIP COIL-2 DIRECT TRIP SEND CH-1 DIRECT TRIP SEND CH-2 TO DISTURBENCE RECORDER
16-52 CB PANEL TO CLOSE CKT INTERLOCK TO BLOCK A/R TO TRIP COIL-1 TO TRIP COIL-2 DIRECT TRIP SEND CH-1 DIRECT TRIP SEND CH-2 TO DISTURBENCE RECORDER
BUSBAR-2 PROTECTION TRIPPING SCHEME HIGH SPEED TRIP RELAY FOR 3-52 CB
3-52 CB PANEL TRIP FROM 50 LBB TO START 50 LBB
6-52 CB PANEL
HIGH SPEED TRIP RELAY FOR 6-52 CB
TRIP FROM 50 LBB TO START 50 LBB
9-52 CB PANEL HIGH SPEED TRIP RELAY FOR 9-52 CB
TRIP FROM 50 LBB TO START 50 LBB
HIGH SPEED TRIP RELAY FOR 12-52 CB
12-52 CB PANEL TRIP FROM 50 LBB
3-52 CB PANEL TO CLOSE CKT INTERLOCK TO BLOCK A/R TO TRIP COIL-1 TO TRIP COIL-2 DIRECT TRIP SEND CH-1 DIRECT TRIP SEND CH-2 TO DISTURBENCE RECORDER
6-52 CB PANEL TO CLOSE CKT INTERLOCK TO BLOCK A/R TO TRIP COIL-1 TO TRIP COIL-2 DIRECT TRIP SEND CH-1 DIRECT TRIP SEND CH-2 TO DISTURBENCE RECORDER
9-52 CB PANEL TO CLOSE CKT INTERLOCK TO BLOCK A/R TO TRIP COIL-1 TO TRIP COIL-2 DIRECT TRIP SEND CH-1 DIRECT TRIP SEND CH-2 TO DISTURBENCE RECORDER
12-52CB PANEL TO CLOSE CKT INTERLOCK TO BLOCK A/R TO TRIP COIL-1 TO TRIP COIL-2 DIRECT TRIP SEND CH-1 DIRECT TRIP SEND CH-2 TO DISTURBENCE RECORDER
TO START 50 LBB
HIGH SPEED TRIP RELAY FOR 15-52 CB
15-52 CB PANEL TRIP FROM 50 LBB TO START 50 LBB
18-52 CB PANEL
HIGH SPEED TRIP RELAY FOR 18-52 CB
TRIP FROM 50 LBB TO START 50 LBB
+VE
BUSBAR PANEL
15-52 CB PANEL TO CLOSE CKT INTERLOCK TO BLOCK A/R TO TRIP COIL-1 TO TRIP COIL-2 DIRECT TRIP SEND CH-1 DIRECT TRIP SEND CH-2 TO DISTURBENCE RECORDER
18-52 CB PANEL TO CLOSE CKT INTERLOCK TO BLOCK A/R TO TRIP COIL-1 TO TRIP COIL-2 DIRECT TRIP SEND CH-1 DIRECT TRIP SEND CH-2 TO DISTURBENCE RECORDER
DISTRIBUTED LBB & NUMERICAL CENTRALISED BUS BAR PROTECTION (REB 500) ABB
(7 SS 52) SIEMENS
(MICOM P740) AREVA
OR
OR
OR
OR
14-52 15-52
13-52
11-52
10-52
BUS-2
12-52
7-52 8-52 9-52
5-52 6-52
4-52
2-52 3-52
1-52
BUS-1
LATEST DEVELOPMENT IN NUMERICAL CENTRALISED BUS BAR PROTECTION
ABB
SIEMENS
AREVA
BUSBAR PROTECTION CENTRAL UNIT BAY UNIT ABB Network Partner AG
REL531
ABB Network Partner AG
1 2 3 4 5 6 7 8
LINE PROTECTION
REC 316*4
9 10 11 12 13 14 15 16
C
C
E E
21 L2
21 L1 ABB Network Partner AG
REL531
ABB Network Partner AG
1 2 3 4 5 6 7 8
TRANSFORMER PROTECTION 87 T1 1. 2. 3.
DESCRIPTION 4.
21 L1
21 L2
21 L1
21 L2
87 T1
87 T2
87 T1
87 T2
REC 316*4
9 10 11 12 13 14 15 16
C
C
E
E
87 T2
IN THIS NO SEPARATE CORE IS REQUIRED FOR EITHER BUSBAR PROTECTION OR LBB / BFR. CENTRALISED BUSBAR IS CONNECTED FROM BAY UNIT OR LBB OR BFR THROUGH FIBRE OPTIC. BAY UNIT / BFR / LBB IS CONNECTED FROM MAIN-1 & MAIN-2 OF LINE PROTECTION OR MAIN & BACKUP PROTECTION OF TRANSFORMER THROUGH FIBRE OPTIC FOR REDUNDANCY TO BAY UNIT. THE CURRENT DATA IS TRANSFERED TO BAY UNIT TO BUSBAR CENTRAL UNIT FROM LINE / TRANSFORMER PROTECTIONS FOR NUMIRICAL ALGORITHAM OF LBB & BUSBAR CENTRAL UNIT AND IT WILL OPERATE FOR INTERNAL FAULTS AND DOES NOT OPERATE FOR THROUGH / EXTERNAL FAULTS.
MISCELENEOUS RELAYS & PROTECTIONS ADOPTED FOR LINE IN ONE AND HALF CIRCUIT BREAKER SCHEME (STUB, TEED AND AUTO RECLOSURE FUNCTIONS) PREPARED BY GOPALA KRISHNA PALEPU ADE/MRT(PROTECTION)
LINE-1
STUB-1&2 (BAY 1&2) 1-89L REL 521 REL 316
DISTANCE / ATF RELAYS CONVERTED TO STUB/BUS OVER LOAD RELAYS WHEN LINE ISOLATOR OPENS
3
2-52CB
3
1-52CB
3
BUS-1
3
STUB-1/ STUB-2 PROTECTION 3-52CB
STUB-3&2 (BAY 3&2) 3-89T
BUS-2
AT/F-1
RET 521 RET 316
WHEN A LINE IS SUPPLIED VIA TWO CIRCUIT BREAKERS IN A ONE & HALF CIRCUIT BREAKER ARRANGEMENT, THE LINE PROTECTION INCLUDES THE AREA BETWEEN THE TWO CT’s. HOWEVER, WHEN THE LINE ISOLATOR IS OPEN THE LINE CVT‘s FOR THE DISTANCE PROTECTION ARE CONNECTED TO THE LINE AND CANNOT PROVIDE THE CORRECT VOLTAGE FOR THE STUB END.(i.e THE AREA BETWEEN THE LINE ISOLATOR AND CT’s) (STUB = DEAD END) TO PROVIDE PROTECTION FOR A FAULT IN THIS AREA, REL 521/ REL 316 IS PROVIDED WITH A STUB PROTECTION WHICH GIVES AN BUS OVER CURRENT TRIP IF THE LINE ISOLATOR IS OPEN AND THE CURRENT EXCEEDS THE SET VALUE IN ANY PHASE.
STUB-1 (BAY 1&2 OR BAY 3&2) OPERATES
STUB-2 (BAY 1&2 OR BAY 3&2) OPERATES
IT OPERATES THE 3-PH TRIP GR-A MAIN CB (1-52CB OR 3-52CB) AND 3-PH TRIP GR-A TIE CB (2-52CB) IT OPERATES THE 3-PH TRIP GR-B MAIN CB (1-52CB OR 3-52CB) AND 3-PH TRIP GR-B TIE CB (2-52CB)
2-52CB
TEED-1&2 (BAY 1&2)
3
3
1-52CB
3
BUS-1
3
TEED-1/ TEED-2 PROTECTION 3
3-52CB
BUS-2
TEED-1&2 (BAY 2&3)
LINE-1 AT/F-1 TEED PROTECTION IS BASED ON KIRCHOFF’S CURRENT LAW. THREE SETS OF CTS ARE CONNECTED IN STAR FASHION. SOME OF THE CURRENTS MUST BE ZERO. IF ANY UNBALANCE CURRENTS ARE NOTICED THEN IMMEDIATELY TEED PROTECTION OPERATES. IF TEED PROTECTION BAY 1&2 OPERATED THEN IT TRIPS 1-52CB & 2-52CB. SIMILARLY IF TEED PROTECTION BAY 2&3 OPERATED THEN IT TRIPS 2-52CB & 3-52CB.
TEED-1 PROTECTION
SUMMATION OF INDIVIDUAL PHASES OF T-SHAPED 3 CTs BEFORE REACHING TO RELAY. THIS IS CIRCULATING CURRENT PRINCIPLE. THE CURRENT FLOWING THROUGH IS ZERO DURING BALANCED CONDITION. HIGH IMPENDENCE THREE PHASE DIFFERENTIAL RELAY IS USED AS TEED-1 PROTECTION.
TEED-2 PROTECTION
T- SHAPED 3 CTs ARE CONNECTED TO RELAY. THE RELAY HAVING OPERATING COIL & RESTAIRING COIL. BASED ON THE DIFFERENTIAL CURRENT FLOWING THROUGH THE OPERATING COIL THE RELAY OPERATES. LOW IMPEDENCE PERCENTAGE BIASED THREE TERMINAL THREE PHASE DIFFERENTIAL RELAY IS USED AS TEED-2 PROTECTION.
TEED-1 PROTECTION {BAY1&2}(5CT METHOD)
P2 P2 P2
IR5 IY5 IB5
1-CT CTR: 2000-1000-500/1A
3 3 3
CORE-5
5S4
5S4
5S4
5S2
5S2
5S2
CLASS: PS
87 TEED-1
IN5 P1 P1 P1 P2 P2 P2
IR5 IY5 IB5
2-CT CTR: 2000-1000-500/1A
3 3 3
CORE-5
5S4
5S4
5S4
5S2
5S2
5S2
CLASS: PS
IN5 P1 P1 P1 P2 P2 P2
1-LCT CTR: 2000-1000/1A
CLASS: PS
IN1 1S3
1S3
1S3
1S2
1S2
1S2
3 3 3
CORE-1
IB1 IY1 IR1 P1 P1 P1
IT WORKS ON CIRCULATING CURRENT PRINCIPLE AND IT IS HIGH IMPEDENCE DIFFERENTIAL RELAY. TEED-1 PROTECTION FOR BAY 2&3 IS ALSO SAME AS ABOVE AND THE FOLLOWING CTs & CORES ARE USED 3-CT(CORE-5), 2-CT(CORE-1) & 3-TCT(CORE-1) ARE STARRED AND CONNECTED TO TEED-1 PROTECTION
TEED-2 PROTECTION 1-CT CTR: 2000-1000-500/1A
3 3 3
CORE-4
4S4
4S4
4S4
4S2
4S2
4S2
CLASS: PS
CT MB
87 TEED-2
RAICA LBB/BFR
CT MB
RAICA LBB/BFR
{BAY1&2}(5CT METHOD) P2 P2 P2
P2 P2 P2
4S4
4S4
4S4
4S2
4S2
4S2
3 3 3
2-CT CORE-4 CTR: 2000-1000-500/1A
P2 P2 P2 CT MB 1-LCT CTR: 2000-1000/1A
CLASS: PS
3 3 3
CORE-2
2S3
2S3
2S3
2S2
2S2
2S2
CLASS: PS
TEED-2 PROTECTION FOR BAY 2&3 IS ALSO SAME AS ABOVE AND THE FOLLOWING CTs & CORES ARE USED. 3-CT(CORE-4), 2-CT(CORE-2) & 3-TCT (CORE-2) ARE CONNECTED TO TEED-2 PROTECTION. IT WORKS ON KIRCHOFF’S CURRENT PRINCIPLE & IT IS PERCENTAGE BIASED LOW IMPEDENCE DIFFERENTIAL RELAY
TEED / STUB PROTECTION TRIP SCHEME ABB Network Partner AG
1 2 3 4 5 6 7 8
REC 316*4
9 10 11 12 13 14 15 16
C E
STUB OR TEED-1
86-A MTR/ HSTR
TRIP COIL-1 1-52CB TRIP COIL-2
(BAY 1&2) (BAY 1&2)
86-A MTR/ HSTR
TRIP COIL-1 2-52CB TRIP COIL-2
(BAY 2&3) (BAY 2&3)
TEED-2 OR STUB
86-B MTR/ HSTR
TRIP COIL-1 3-52CB TRIP COIL-2 BUS-2
BUS-1 86-B ABB REL521 MTR/ MAIN-1 HSTR
86-A MTR/ HSTR
STUB OR TEED-1
TEED-2 OR STUB
86-B MTR/ HSTR
86-A : GROUP-A MASTER TRIP RELAY / HIGH SPEED TRIP RELAY 86-B : GROUP-B MASTER TRIP RELAY / HIGH SPEED TRIP RELAY LINE/TRANSFORMER ISOLATOR OPENS THIS INTERLOCK WILL INITIATE 21 L1 / 87 T1 & 21 L2 / 87 T2 CONVERTED STUB-1 & 2 PROTECTION
AUTO RECLOSURE BASICS ¾ FAULTS ARE THREE TYPES 1. TRANSIENT FAULT: These are cleared by the immediate tripping of Circuit Breakers and do not reoccur when the line is re-energized. 2. SEMI-PERMANENT FAULTS: These require a time interval to disappear before a line is charged again. 3. PERMANENT FAULTS: These are to be located and repaired before the line is re-energized. ¾ About 80-90% of the faults occurring are transient in nature. Hence the Automatic Reclosure of breaker (after tripping on Fault) will result in the line being successfully re-energized. ¾ ADVANTAGES: A. Decreasing outage time. B. Improving Reliability. C. Improving system stability. D. Reduce fault damage and Maintenance Time. ¾ DEAD TIME: The time between the Auto-reclosing Scheme being energized and the operation of the contacts which energize the Circuit Breaker closing circuit. ¾ RECLAIM TIME: The Time Following a successful closing operation measured from the instant the Auto-Reclosing relay closing contacts make which must elapse before the Auto-Reclosing relay initiates another reclosing attempt. In other words, it may be said to be the time between 1st and 2nd Auto-Reclosure.
¾ TYPES OF AUTO-RECLOSING SCHEMES: 1. BASED ON PHASE A. THREE PHASE AUTO-RECLOSING: This type of Auto-Reclosing causes an immediate drift part of the two systems and hence no interchange of synchronizing power can take place during the dead time. B. SINGLE PHASE AUTO-RECLOSING: In this, only the faulty phase(only SLG Faults) is reclosed without causing interruption in interchange synchronizing power between two systems through other two healthy phases. 2. BASED ON ATTEMPTS OF RECLOSURE A. SINGLE SHOT AUTO-RECLOSING: In this scheme, Breaker is reclosed only once on a given fault before lockout of Circuit Breaker Occurs. High-Speed Auto-Reclosing for EHT System is invariably Single Shot. B. MULTI-SHOT AUTO-RECLOSING: In this scheme, more than one reclosing attempts made for a given fault before lockout of Circuit Breaker occurs. B.I. DISADVANTAGES: Repeated closure attempts has with high fault level would seriously affect the Circuit Breaker, Equipment and System Stability. B.ii. CIRCUIT BREAKER LIMITATIONS: Ability of Circuit Breaker to Perform several Trip Close operations in quick succession. B. iii. SYSTEM CONDITIONS: In the percentage of the semi-Permanent faults (which could be burnt out) is moderate, For example on the lines through the forest, multi shot Auto-Reclosing is followed. 3. DEPENDING ON SPEED: A. HIGH-SPEED AUTO-RECLOSING: This aids in fast restoration of supply but should be done by taking into account the following factors. I. System disturbance time can be tolerated without loss of system stability. ii. Characteristics of Protection Schemes and Circuit Breaker. B. LOW SPEED OR DELAYED AUTO RECLOSING: This is suitable for highly interconnected systems where the loss of a single line is unlikely to cause two sections of the system to drift apart and loose synchronism.
¾ METHOD OF ADOPTION IN ONE AND HALF BREAKER SYSTEM: The Auto-Reclosure Functions used for the Bus Breakers 1-52CB & 3-52CB are set as Masters and one for the Center Breaker 2-52CB(TIE) as Follower. Co-ordination is required between the Auto-Reclosure Functions. A Synchrocheck function is also loaded in each Relay to permit 3 pole Auto-Reclosing. Each Line Protection relays starts both MAIN & TIE Circuit Breakers to trip for the Concerned line. After a Successful reclosure of the Main Breaker, The Tie Breaker will be reclosed after a supplementary time delay. Should the Main CB AutoReclosure relay not be successful in its reclosing attempts, the Tie CB AutoReclosure is blocked. If the Main CB is Open or its Auto-Reclosure Relay is not ready or Out of service, The TIE CB Auto-Reclosure will reclose The TIE Breaker after its own dead time without any supplementary time delay. ¾ CHOICES OF EHV SYSTEM: 1. CHOICE OF DEAD TIME: A. Lower limit is decided by deionising of Circuit Breaker. B. Upper Limit is decided by Transient Stability and Synchronism. C. Longer Transmission Lines Require Longer dead Time. D. The dead time for High Speed Auto-Reclosing scheme with EHV System is 0.3 to 1.2 sec. 2. CHOICE OF RECLAIM TIME: This should not be set to such a low value that the operating cycle of Breaker is exceeded when two faults incident occurs close together. The reclaim time will be in the range of 10 to 30 sec., depending the breaker opening and closing mechanisms. 3. CHOICE OF ZONE: This should normally kept in Zone-1. It is a Zone-1 fault and SLG fault only autoreclosure is comes in to picture. In other zones the auto reclosure is blocked.
AUTO-RECLOSURE FOR ONE & HALF BREAKER SCHEME TRIP COMMANDS AUTO RECLOSURE COMMANDS
79 (A/R)+ 25(SYNC) RAAAM RASC
79 (A/R)+ 25(SYNC) RAAAM RASC
79 (A/R)+ 25(SYNC) RAAAM RASC
1-52CB
2-52CB
3-52CB
ABB Network Partner AG ABB Network Partner AG
ABB Network Partner AG
LINE-1
1 2 3 4 5 6 7 8
C E
21 MAIN-1 REL 521
REL531
REL531
21 MAIN-2 REL 316
ABB Network Partner AG
REC 316*4
1 2 3 4 5 6 7 8
9 10 11 12 13 14 15 16
REC 316*4
9 10 11 12 13 14 15 16
LINE-2 C
C
E
E
21 MAIN-1 REL 521
C E
21 MAIN-2 REL 316
AUTO RECLOSING TIMING CHART INSTANT OF FAULT OPERATES
RESETS
TRANSIENT FAULT
PROTECTION OPERATING TIME
TRIP COIL CONTACTS ARC CONTACTS ENERGISED SEPARATE EXTINGUISHED FULLY OPEN
CIRCUIT BREAKER OPENING TIME
CLOSING TIME
ARCING TIME
OPERATING TIME OPERATES
DEAD TIME
RESETS
RECLOSE ON TO FAULT
OPERATING TIME
TRIP COIL CONTACTS ARC CONTACTS ENERGISED SEPARATE EXTINGUISHED FULLY OPEN
CIRCUIT BREAKER
OPERATES
RESETS
PROTECTION
PERMANENT FAULT
CLOSING COIL CONTACTS CONTACTS MAKE FULLY CLOSED ENERGISED
OPENING TIME
CLOSING COIL CONTACTS CONTACTS ENERGISED MAKE FULLY CLOSED
CLOSING TIME
ARCING TIME
OPERATING TIME
DEAD TIME
ARC CONTACTS CONTACTS SEPARATE EXTINGUISHED FULLY OPEN
TRIP COIL ENERGISED
SYSTEM DISTURBANCE TIME RECLOSE INITIATED BY PROTECTION
RELAY READY TO RESPOND TO FURTHER FAULT INCIDENTS (AFTER SUCEESFUL RECLOSRE)
AUTO RECLOSE RELAY DEAD TIME
CLOSING PULSE TIME RECLAIM TIME
TIME
CARRIER INTERTRIPPING SCHEMES ADOPTED IN ONE AND HALF CIRCUIT BREAKER SCHEME PREPARED BY GOPALA KRISHNA PALEPU ADE/MRT(PROTECTION)
TYPES OF CARRIER TRIPPING SCHEMES PERMISSIVE TRIPPING Permissive trip commands are always monitored by a protection relay. The circuit breaker is tripped when receipt of the command coincides with operation of the protection relay at the receiving end responding to a system fault. The receipt of an incorrect signal must coincide with operation of the receiving end protection for a trip operation to take place. Normally, the risk of a spurious trip is lesser. The intention of these schemes is to speed up tripping for faults occurring within the protected zone.
BLOCKING SCHEME Blocking commands are initiated by a protection element that detects faults external to the protected zone. Detection of an external fault at the local end of a protected circuit results in a blocking signal being transmitted to the remote end. At the remote end, receipt of the blocking signal prevents the remote end protection operating if it had detected the external fault. Loss of the communications channel is less serious for this scheme than in others as loss of the channel does not result in a failure to trip when required. However, the risk of a spurious trip is higher.
TYPES OF CARRIER TRIPPING SCHEMES Conventional time-stepped distance protection has One of the main disadvantages is that the instantaneous Zone 1 protection at each end of the protected line cannot be set to cover the whole of the feeder length and is usually set to about 80%. This leaves two 'end zones', each being about 20% of the protected feeder length. Faults in these zones are cleared in Zone 1 time by the protection at one end of the feeder and in Zone 2 time (typically 0.25 to 0.5 seconds) by the protection at the other end of the feeder. This situation cannot be tolerated in some applications, for two main reasons: I). Faults remaining on the feeder for Zone 2 time may cause the system to become unstable. II). Where high-speed auto-reclosing is used, the non-simultaneous opening of the circuit. Breakers at both ends of the faulted section results in no 'dead time' during the auto- reclose cycle for the fault to be extinguished and for ionized gases to clear. This results in the possibility that a transient fault will cause permanent lockout of the circuit breakers at each end of the line section. Even where instability does not occur, the increased duration of the disturbance may give rise to power quality problems, and may result in increased plant damage. Unit schemes of protection that compare the conditions at the two ends of the feeder simultaneously positively identify whether the fault is internal or external to the protected section and provide high-speed protection for the whole feeder length. This advantage is balanced by the fact that the unit scheme does not provide the back up protection for adjacent feeders given by a distance scheme. The most desirable scheme is obviously a combination of the best features of both arrangements, that is, instantaneous tripping over the whole feeder length plus back-up protection to adjacent feeders. This can be achieved by interconnecting the distance protection relays at each end of the protected feeder by a communications channel. The purpose of the communications channel is to transmit information about the system conditions from one end of the protected line to the other, including requests to initiate or prevent tripping of the remote circuit breaker. The former arrangement is generally known as a 'transfer tripping scheme' while the latter is generally known as a 'blocking scheme'. However, the terminology of the various schemes varies widely, according to local custom and practice.
TYPES OF CARRIER TRIPPING SCHEMES 1. ZONE 1 EXTENSION SCHEME (Z1X SCHEME) 2. TRANSFER TRIPPING SCHEMES I. DIRECT UNDER REACH TRANSFER TRIP SCHEME (DUTT) II. PERMISSIVE UNDER REACH TRANSFER TRIP SCHEME (PUTT) III. PUTT – FWD SCHEME IV. PERMISSIVE UNDER REACH ACCELERATED SCHEME V. PERMISSIVE OVER REACH TRANSFER TRIP SCHEME (POTT) VI. WEEK IN FEED CONDITIONS. 3. BLOCKING OVER REACHING SCHEMES I. BLOCKING OVER-REACHING PROTECTION SCHEME USING ZONE 2. OR DIRECTIONAL COMPARISION BLOCKING SCHEME
II. BLOCKING OVER-REACHING PROTECTION SCHEME USING ZONE 1. III. WEEK IN FEED CONDITIONS. 4. DIRECTIONAL COMPARISON UNBLOCKING SCHEME
PROPERTIES OF COMMAND PROTECTION SYSTEMS OPERATING MODE
UNDER REACHING SENDING
OVER REACHING SENDING
PERMISSIVE CRITERIA RECEIVING
GENERAL REQUIREMENTS
UNDER IMPEDENCE UNDER VOLTAGE OVER CURRENT DISTANE & DIRECTION
SECURE & FAST
PERMISSIVE UNDER REACH (PUTT)
ZONE-1
- - -
PERMISSIVE OVER REACH (POTT)
- - -
ZONE-2
DIRECT TRIP
ZONE-1
- - -
DISTANCE & DIRECTION
DEPENDABLE
ACCELERA TED UNDER REACH
ZONE-1
- - -
ZONE-2
SECURE & FAST
BLOCKING OVER REACH
- - -
REVERSE LOCKING
DISTANCE & DIRECTION
SECURE & FAST SECURE &
FAST & DEPENDABLE
PREFFERED APPLICATIONS OF TELE/ CARRIER TRIPPING SCHEMES PARAMETERS
Signal Transmission System
PUTT
POTT
Dependable and secure communication channel 1. Power line carrier with frequency shift modulation. HF signal coupled to 2 phases of the protected line, or even better, to a parallel circuit to avoid transmission of the HF signal through the fault location. 2. Microwave radio, especially digital(PCM) 3. Fibre -optic cables
Characteristic Best suited for longer lines - where Of line the Under-reach zone provides sufficient resistance coverage.
1. Excellent coverage On short lines in the Presence of fault resistance. 2. Suitable for the Protection of multiterminal lines with intermediate infeed.
BLOCKING
UNBLOCKING
Reliable communication channel (only required during external faults) 1. Power line carrier With amplitude Modulation (ON/OFF). The same frequency may be used on all terminals) All line types – Preferred practice in the USA.
Dedicated channel With continuous signal Transfer 1. Power line carrier With frequency shift keying. Continuous Signal transmission must be permitted.
Same as POTT
COMPARISION OF TELE/ CARRIER TRIPPING SCHEMES On normal two-terminal lines the main deciding factors in the choice of the type of scheme, apart from the reliability of the signalling channel, operating speed and the method of operation of the system. Table compares the important characteristics of the various types of scheme.
Criterion Speed of operation
Transfer Tripping Scheme Fast
Blocking scheme Not as Fast
Speed with in-service testing Slower
As fast
Suitable for auto Re Close
Yes
Yes
Security against mal-operation due to: Current reversal
Special features required
Special features required
Loss of communications
Poor
good
Weak In feed/Open CB
Special features required
Special features required
Modern digital or numerical distance relays are provided with a choice of several schemes in the same relay. Thus scheme selection is now largely independent of relay selection, and the user is assured that a relay is available with all the required features to cope with changing system conditions.
ADVANTAGES & DRAWBACKS OF TELE/ CARRIER TRIPPING SCHEMES PARAMETERS
PUTT
POTT
ADVANTAGES
1. Simple technique 2. No coordination Of zones and times With the opposite End required. 3.The combination Of different relay Types therefore presents no Problems.
1. Can be applied without Under reaching zone1 stage (e.g. overcompensated Series compensated lines). 2. Can be applied on Extremely short lines (impedance less than minimum relay setting) 3. Better for parallel lines as mutual coupling is not critical for the overreach zone 4. Weak in feed terminals are no problem. (Echo and Weak In feed logic is included)
Same as POTT
DRAWBACKS
1. Overlapping of the zone 1 reaches must be ensured. On parallel lines, teed feeders and tapped lines, the influence of zero sequence coupling and intermediate In feeds must be carefully considered to make sure a minimum overlapping of the zone 1 reach is always present. 2. Not suitable for weak In feed terminals
1. Zone reach and signal timing coordination with the Remote end is necessary (current reversal).
Same as POTT Same as 1. Slow tripping – all POTT Tele-protection trips must be delayed to wait for the eventual blocking signal. 2. Continuous channel Monitoring is not Possible.
BLOCKING
UNBLOCKING Same as POTT but: 1. If no signal is Received (no block and no unblock) then tripping by the overreach zone is released after 20 ms
ADVANTAGES & DRAWBACKS OF TELE/ CARRIER TRIPPING SCHEMES PARAMETERS
Short Line
Weak Infeed Amplitude Modulated Power Line Carrier Frequency or Phase Modulated Power Line Carrier Communication
independent of Power Line
PUTT Not Suitable as the Zone1 Operation is essential and Zone1 setting in X and R direction must be small on Short Lines.
POTT
BLOCKING
UNBLOCKING Suitable Same as POTT.
Suitable as the Z1B setting may be substantially larger than the Line impedance so that signal Transmission is secure for all faults on the Line. Suitable as the Strong end detects all the Line Faults with the OverReaching Z1B. The Weak In-feed end then echos the received Signal.
Suitable as Reverse Reach Setting is independent of Line Length.
Not Suitable as the Signal must be Transmitted through the Fault Location which Attenuates the Signal.
Not Suitable same as PUTT.
Suitable as the Signal is only sent when the Line is not Faulted.
Not Suitable Same as PUTT.
Suitable as the Signal can be Transmitted through the Fault Location.
Suitable same as PUTT.
Suitable as the Signal can be Transmitted under all Conditions.
Suitable Same as PUTT.
Suitable.
Suitable.
Suitable.
Suitable.
Not Suitable as the Zone1 Operation is essential at Both Ends for 100% Coverage.
Partially Suitable Suitable Same as as the Reverse Fault POTT. is also Detected at the Weak In-feed end but no trip at Weak In-feed end.
PROTECTION COUPLER PANEL NSD 50/ NSD 70 ACTIVE
START
TRIP
5
6
ALARM-1 250V DC
1C S
2+ 5C R
6+
1-
TX TRIP A(C)
RX TRIP A(C)
C S
2+ 5C R
6+
TX TRIP C(A)
RX TRIP C(A)
C
7
8
ALARM-2 250V DC
DISPLAY
E
C S
910+
C R
1314+
G4AA TB: V9LB
9-
TX TRIP B(D)
RX TRIP B(D)
G4AC TB: V9LC
C S
10+ 13C R
14+
TX TRIP D(B)
RX TRIP D(B)
GA4D TB:V9LC
PROTECTION COUPLERS FOR 400KV LINE ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾
FOR EACH LINE 2Nos PROTECTION COUPLER PANELS PROVIDED. FOR EACH LINE 1NO CARRIER SPEECH PANEL PROVIDED. SO, ONE LINE REQUIRES TOTAL 3 PANELS. CARRIER SPEECH PANEL PURELY FOR VOICE COMMUNICATION BETWEEN TWO SUBSTATIONS, i.e THE LINE CONNECTED SUBSTATIONS. THE VOICE COMMUNICATION ARE TWO METHODS PROVIDED. ONE IS HOTLINE COMMUNICATION/DEDICATED/ LIFT&TALK METHOD. ANOTHER IS DIAL METHOD. IN PROTECTION COUPLER PANEL-1 TOTAL 3 CARDS ARE IMPORTANT FOR SENDING & RECEIVING TRIP SIGNALS. ONE CARD FOR ALARM i.e G4AA. ONE CARD FOR PERMISSIVE/PROTECTION TRIP i.e G4AC & ANOTHER CARD FOR DIRECT TRIPS i.e G4AD. IN PROTECTION COUPLER-2 PANEL ALSO 3 CARDS ARE PROVIDED SIMILAR TO PROTECTION COUPLER-1 PANEL. THE PROTECTION COUPLER PANEL DRAWING IS SHOWN IN PREVIOUS MENU. 1SET TX & RX FOR PERMISSIVE/ PROTECTION TRIP(G4AC) 1SET TX & RX FOR BACKUP FOR PERMISSIVE/ PROTECTION IN ANOTHER PANEL(G4AC). 1SET TX & RX FOR DIRECT TRIP CHANNEL-1( G4AD). 1SET TX & RX FOR SPARE UNDER EMERGENCY(G4AD). THE ABOVE ARRANGEMENT SIMILAR FOR PROTECTION COUPLER PANEL-2. G4AA CARD FOR ALARM.
NSD 50
MAIN-1 PROTECTION CARRIER INTER TRIPPING G4AC V9LC 1 LINE
G4AC V9LC 6
IN OUT CARRIER RECEIVE
G4AC V9LC 5
ABB
CR -VE
CS
G4AC V9LC 2
CARRIER SEND
G4AA V9LB 5 G4AA V9LB 6 PANEL-1
NSD 50
21L1
ALARM
+VE
-VE
G4AC V9LC 10 G4AC V9LC 13 G4AC V9LC 14
ABB
G4AC V9LC 9
PANEL-2
THIS IS BACKUP FOR PERMISSIVE/ PROTECTION TRIP AND CONNECTED IN ANOTHER PANEL
NSD 50
MAIN-2 PROTECTION CARRIER INTER TRIPPING G4AC V9LC 1 LINE
G4AC V9LC 6
IN OUT CARRIER RECEIVE
G4AC V9LC 5
ABB
CR -VE
CS
G4AC V9LC 2
CARRIER SEND
G4AA V9LB 5 G4AA V9LB 6 PANEL-2
NSD 50
21L2
ALARM
+VE
-VE
G4AC V9LC 10 G4AC V9LC 13 G4AC V9LC 14
ABB
G4AC V9LC 9
PANEL-1
THIS IS BACKUP FOR PERMISSIVE/ PROTECTION TRIP AND CONNECTED IN ANOTHER PANEL
DIRECT TRIP SEND CARRIER CHANNEL-1 96 BUSBAR PROT-2 PANEL 87 BUSBAR TRIP (ZONE-2)
PANEL-1
96 BUSBAR PROT-1 PANEL
ABB NSD 50
87 BUSBAR TRIP (ZONE-1)
DC +VE FROM PANEL
CONTROL PANEL T NC
MAIN CB(1-52CB)
R
Y
B
TIE CB (2-52 CB)
T NC
TIE CB(2-52CB)
R
Y
B
MAIN CB (1-52 CB)
G4AD V9LC 2 G4AD V9LC 1
50 LBB/BFR FOR MAIN CB / RAICA 59L1 / OVER VOLTAGE STAGE-1 59L2 / OVER VOLTAGE STAGE-2 87 HZ / TEED-1 PROTECTION 87 LZ / TEED-2 PROTECTION 50 LBB/BFR FOR TIE CB / RAICA
DC –VE FROM PANEL CONDITIONS FOR DIRECT TRIP 1. TIE CB OPEN CONDITION + MAIN CB REMOTE HAND TRIP GIVEN. 2. MAIN CB OPEN CONDITION + TIE CB REMOTE HAND TRIP GIVEN. 3. TIE CB OPEN CONDITION + 96 BUSBAR-1 OPERATED. 4. MAIN CB OPEN CONDITION + 96 BUSBAR-2 OPERATED (FOR HALF DIA ONLY). 5. MAIN CB 50 LBB/BFR OPERATED. 6. TIE CB 50 LBB/BFR OPERATED. 7. 59L1 OVER VOLTAGE STAGE-1 OPERATED. 8. 59L2 OVER VOLTAGE STAGE-2 OPERATED. 9. 87 HZ TEED-1 PROTECTION OPERATED 10. 87 LZ TEED-2 PROTECTION OPERATED.
DIRECT TRIP SEND CARRIER CHANNEL- 2 96 BUSBAR PROT-2 PANEL
PANEL-2
87 BUSBAR TRIP (ZONE-2)
ABB NSD 50
96 BUSBAR PROT-1 PANEL 87 BUSBAR TRIP (ZONE-1)
DC +VE FROM PANEL
CONTROL PANEL T NC
MAIN CB(1-52CB)
R
Y
B
TIE CB (2-52 CB)
T NC
TIE CB(2-52CB)
R
Y
B
MAIN CB (1-52 CB)
G4AD V9LC 2 G4AD V9LC 1
50 LBB/BFR FOR MAIN CB / RAICA 59L1 / OVER VOLTAGE STAGE-1 59L2 / OVER VOLTAGE STAGE-2 87 HZ / TEED-1 PROTECTION 87 LZ / TEED-2 PROTECTION 50 LBB/BFR FOR TIE CB / RAICA
DC –VE FROM PANEL CONDITIONS FOR DIRECT TRIP 1. TIE CB OPEN CONDITION + MAIN CB REMOTE HAND TRIP GIVEN. 2. MAIN CB OPEN CONDITION + TIE CB REMOTE HAND TRIP GIVEN. 3. TIE CB OPEN CONDITION + 96 BUSBAR-1 OPERATED. 4. MAIN CB OPEN CONDITION + 96 BUSBAR-2 OPERATED (FOR HALF DIA ONLY). 5. MAIN CB 50 LBB/BFR OPERATED. 6. TIE CB 50 LBB/BFR OPERATED. 7. 59L1 OVER VOLTAGE STAGE-1 OPERATED. 8. 59L2 OVER VOLTAGE STAGE-2 OPERATED. 9. 87 HZ TEED-1 PROTECTION OPERATED 10. 87 LZ TEED-2 PROTECTION OPERATED.
DIRECT TRIP RECEIVE CHANNEL-1&2 PANEL-1
ABB NSD 50
TO 86-A MASTER TRIP RELAY (HIGH SPEED TRIP RELAY) FOR MAIN CB(152CB)
DC +VE
TO 86-A MASTER TRIP RELAY (HIGH SPEED TRIP RELAY) FOR TIE CB(252CB)
G4AD V9LC 6 G4AD V9LC 5 PANEL-2
DIRECT TRIP-1 CARRIER RECEIVE RELAY
+VE
-VE
ABB NSD 50
TO 86-B MASTER TRIP RELAY (HIGH SPEED TRIP RELAY) FOR MAIN CB(152CB)
DC +VE
TO 86-B MASTER TRIP RELAY (HIGH SPEED TRIP RELAY) FOR TIE CB(252CB)
G4AD V9LC 6 G4AD V9LC 5
DIRECT TRIP-2 CARRIER RECEIVE RELAY
PLCC CARRIER PROTECTION SYSTEM (TELEPROTECTION) ABB Network Partner AG
REL531
ABB Network Partner AG
REL531
REL 521 MAIN-1 PROTECTION C
C
E
E
ELECTRICAL CONNECTION NSD 50 PANEL
NSD 50 PANEL PLCC PANEL
ELECTRICAL POWER LINE
PLCC PANEL NSD 50 PANEL
NSD 50 PANEL ELECTRICAL CONNECTION ABB Network Partner AG
REC 316*4
ABB Network Partner AG
1
9
1
9
2 3 4 5 6
10 11 12 13 14
2 3 4 5 6
10 11 12 13 14
7 8
15 16
7 8
15 16
C
E
REL 316 MAIN-2 PROTECTION
REC 316*4
C
E
FIBRE OPTIC PROTECTION SYSTEM (TELEPROTECTION) ABB Network Partner AG
REL531
ABB Network Partner AG
REL531
REL 521 MAIN-1 PROTECTION C
C
E
E
ELECTRICAL CONNECTION
TUNOS
TUNOS
FOX-U FOX-515
FOX-U FOX-515
GECOD/ SIFOX
NSD 70 PANEL
NSD 70 PANEL GECOD/ SIFOX
NSD 70 PANEL
NSD 70 PANEL
ELECTRICAL CONNECTION ABB Network Partner AG
REC 316*4
ABB Network Partner AG
1
9
1
9
2 3 4 5 6
10 11 12 13 14
2 3 4 5 6
10 11 12 13 14
7 8
15 16
7 8
15 16
C
E
REL 316 MAIN-2 PROTECTION
REC 316*4
C
E
FIBRE OPTIC CARRIER PROTECTION SYSTEM (TELEPROTECTION) DIGITAL RELAY CONNECTION VIA FIBRE OPTIC ABB Network Partner AG
REL531
ABB Network Partner AG
REL531
REL 521 MAIN-1 PROTECTION
ABB Network Partner AG
FOX-U FOX-515
REC 316*4
ABB Network Partner AG
1
9
1
9
2 3 4 5 6
10 11 12 13 14
2 3 4 5 6
10 11 12 13 14
7 8
15 16
7 8
15 16
C
E
REL 316 MAIN-2 PROTECTION
OTERM
E
TUNOS
C
E
TUNOS
OTERM
FOX-U FOX-515
C
REC 316*4
C
E
MAIN-1 & MAIN-2 PROTECTION FOR AUTO TRANSFORMER ADOPTED IN ONE AND HALF CIRCUIT BREAKER SCHEME PREPARED BY GOPALA KRISHNA PALEPU ADE/MRT(PROTECTION)
BASICS OF TRANSFORMER PROTECTION 1.
2.
3.
PURPOSE OF POWER TRANSFORMER PROTECTION POWER T/F PROTECTION IS USUALLY INSTALLED TO DISCONNECT THE T/F AT: A. INTERNAL SHORT CIRCUITS AND EARTH FAULTS IN THE T/F AND ITS CONNECTED CIRCUITS. B. EXTERNAL FAULTS ON OTHER CIRCUITS. (BACK-UP PROTECTION) C. ABNORMAL SERVICE CONDITIONS SUCH AS OVERLOAD & OVER VOLTAGE. PROTECTION DEVICES INBUILT OR MOUNTED ON POWER T/F A. OIL IMMERSED POWER T/F USUALLY HAVE A GAS DETECTOR AND OIL SURGE. DETECTOR (BUCHHOLZ ALARAM & TRIP DEVICES), WHICH ARE EXCELLENT FOR DETECTING INTERNAL FAULTS. B. LOAD TAPCHANGER COMPARTMENTS MAY HAVE A SIMILAR OVER PRESSURE DEVICE. C. TEMPARATURE MONITORS FOR OIL & WINDING PROVIDE GOOD OVER LOAD PROTECTION. D. PRESSURE RELIEF DEVICE IS PROVIDED TO SAFE GUARD THE T/F FROM HIGH PRESURES. TRANSFORMER DIFFERENTIAL PROTECTION IT IS WIDELY USED AS INSTANTANEOUS PROTECTION FOR SHORT CIRCUIT FAULTS WITH IN THE DIFFERENTIAL ZONE. THIS IS TREATED AS MAIN-1 PROT FOR T/F. THE MOST COMMON TYPE OF PROTECTION IS THE CURRENT RESTRAINT TYPE. SOME TYPE OF DIFFERENTIAL RELAYS REQUIRE INTERPOSING CTs FOR CT RATIO MATCHING AND/OR PHASE SHIFT. HIGH IMPEDENCE DIFFERENTIAL PROTECTION CAN BE USED ON AUTO T/F & REACTORS. IT COVERS ONE GALVANICALLY INTERCONNECTED WINDING (WDG DIFF). BUT NOT A SEPARATE TERTIARY WINDING. IT REQUIRES A THREE PHASE SET OF CTs AT THE NEUTRAL SIDE OF WINDING.
4.RESTRICTED EARTH FAULT PROTECTION AT/Fs are used to couple EHV Power Networks, If the Ratio of their Voltages is Moderate. An Alternative to Differential Protection that can be applied to AT/Fs. A Circulating Current System is arranged between Equal Ratio Current Transformers in the Two Groups of Line Connections and the Neutral End Connections. The Line Current Transformers can be connected in Parallel to A Single Element Relay, Thus providing a Scheme Responsive to Earth Faults Only. If Current Transformers are fitted in Each Phase at the Neutral End of the Windings and a Three-Element Relay is used, A Differential System can be provided, giving Full Protection against Phase and Earth Faults. This Provides High-speed Sensitive Protection. It is Unaffected by Ratio Changes on the Transformer due to Tap-changing and is immune to the Effects of Magnetizing In Rush Current. It does not respond to Interturn Faults. In Addition, This Scheme does not respond to any Fault in a Tertiary Winding. Unloaded Delta-connected Tertiary Windings are often not Protected.
5. BACK UP PROTECTION A VARIETY OF RELAYS ARE AVAILABLE. A. OVER CURRENT & EARTH FAULT PROTECTION. ( 50, 50N, 51, 51N, 67, 67N - ANY COMBINATION OF THESE) B. UNDER IMPEDENCE / DISTANCE ( Z<)(21T). C. NEUTRAL DISPLACEMENT PROTECTION (Un>).
6.OTHER TYPES OF RELAYS A. OVER VOLTAGE RELAY (U >). B. OVER FLUX/ EXCITATION (V/F >)( INVERSE TIME & DIFENITE TIME). FOR 400KV/220KV & 765/400KV TRANSFORMERS BOTH SIDES( i.e HV & LV) OVER FLUX RELAYS ARE PROVIDED BECAUSE BOTH SIDES HAVING GRID. C. AT/F NEUTRAL CURRENT RELAY (51N).
NORMALLY ADOPTED POWER TRANSFORMERS CAPACITIES IN 400KV / 220KV CAPACITY OF TRANSFORMER
HV VOLTAGE
HV CURRENT
LV VOLTAGE
LV CURRENT
315 MVA 500 MVA 630 MVA
400 KV 400 KV 400 KV
454.68 A 721.71 A 909.35 A
220 KV 220 KV 220 KV
0826.68 A 1312.20 A 1653.37 A
NORMS OF PROTECTION FOLLOWED BY UTILITIES FOR POWER TRANSFORMERS & AUTO TRANSFORMERS
31.5, 50
220 / 33
6
220 / 66
7
31.5, 50 & 100 100, 200 & 250
400 / 132
8
100 & 160
220 / 132
9
315, 500 & 630
400 / 220
10
1000 & 1500
765 / 400
HV & LV REF 64
HV
LV
3 OL + 1 EL (51)
3 DIR OL (HIGHSET) + 1 DIR EL (HIGHSET)
3 OL + 1 DIR EL (51P + 67N) 3 DIR OL (HIGHSET) + 1 DIR EL (HIGHSET)
ADDITIONAL SPECIAL PROTECTION PROTECTION BUCHHOLZ, OLTC OSR OIL TEMP WDNG TEMP
BUCHHOLZ OVER FLUX OLTC OSR PRV/PRD OIL TEMP WDNG TEMP
64REF IS 1-PH HIGH IMPEDANCE DIFFERENTIAL RELAY 87TH IS 3-PH HIGH IMPEDANCE DIFFERENTIAL RELAY (PRINCPLE : CIRCULATING CURRENT)
5
BACK UP PROTECTION
3 OVER LOAD + 1 DIRECTIONAL EARTH FAULT RELAY ( 51P + 67N)
132 / 33
87 TH / 64 REF
16 , 31.5 50 & 80
HV REF (64)
4
132 / 11
NIL
3
MAIN-2
PROTECTION
87 TL DIFFERENTIAL RELAY
66 / 33
2
MAIN-1
( LOW IMPEDANCE PERCENTAGE BIASED PHASE SEGREGATED DIFFERENTIAL RELAY PRINCIPLE: MERZ PRICE)
66 / 11
7.5 & 16 7.5 , 16 & 25 7.5 , 16 , 25 & 31.5
T Y P E
2 WINDING TRANSFORMER (STAR/STAR) ICT / AUTO TFR
1
VOLTAGE RATIO IN KV
3 OVER LOAD + 1 EARTH FAULT RELAY ( 51 )
CAPACITY S.No IN MVA
OVER LOAD ALARM RELAY + NEUTRAL CURRENT E/F RELAY
ICT BUSHING CT INFORMATION S.No
ITEM /MVA
1
CORE
2
RATIO
100 160 315 500
HV 1
2
600/1 800/1 1000/1 1600/1
300/1 500/1 600/1 1000/1
IV
NEUTRAL
3
1
2
--
600/1 800/1 1000/1 1600/1
500/1 800/1 1000/1 1600/1
LV
3
1
2
3
--
600/1 800/1 1000/1 1600/1
600/1 800/1 1000/1 1600/1
--
NEUTRAL BUSHING CT : CORE-1 : BEFORE STAR FORMATION IN RYB PHASES, CORE-2 : AFTER STAR FORMATION FOR 100, 160, 315 MVA TRANSFORMERS
6 7
MET
WTI
0.2 CL AND BURDEN 30 VA ISF:5
MET
WTI
600 V 800 V 1000 V 1600 V 1.5 2.0 2.5 4.0 100 80 60 25 PS 87/64 REF
600 V 800 V 1000 V 1600 V 1.5 2.0 2.5 4.0 100 80 60 25 PS NCT PROT
Parameters of WTI CT for each winding shall be provided by the contractor
5
0.2 CL AND BURDEN 30 VA ISF:5
600 V 800 V 1000 V 1600 V 1.5 2.0 2.5 4.0 100 80 60 25 PS 87/64 REF
Parameters of WTI CT for each winding shall be provided by the contractor
4
600 V 800 V 1000 V 1600V 1.5 2.0 2.5 4.0 100 80 60 25 PS 87/64 REF
Parameters of WTI CT for each winding shall be provided by the contractor.
3
100 VKNEE FOR 160 PS & VA 315 FOR MET 500 100 160 RCT IN OHMS 315 500 100 I MAGNETISING 160 IN mA at 315 VKNEE 500 CLASS OF ACURACY PURPOSE
WTI
MAIN / DIFFERENTIAL PROTECTION FOR AT/F (4 CT METHOD)
3-CT CTR: 2000-1000-500/1A
3 3 3
CORE-5
5S4
5S4
5S4
5S3
5S3
5S3
3 CT METHOD : 3-CT & 2-CT 4 CT METHOD : 3-CT & 2-ACT 6 CT METHOD : 3-ACT & 2-ACT
CLASS: PS
5S1
5S1
5S1
5S3
5S3
5S3
3 3 3
CORE-5 CTR: 1200-800/1A
CLASS: PS
5S3
5S3
5S3
5S4
5S4
5S4
CLASS: PS
P2 P2 P2
AUX.CT Y/ 0.91 / 0.577A
CT MB
3 3 3
CTR: 2000-1000-500/1A
CT MB
P2 P2 P2 LV-CT
2-ACT CORE-5
87 T1
AUX.CT Y/ 0.689 / 0.577A
CT MB
AUX.CT Y/ 0.91 / 0.577A
P2 P2 P2
IN CASE OF 1&1/2 CB SYSTEM, THE DIFFERENTIAL PROTECTION CTs ASSOCIATED WITH MAIN & TIE CBs SHOULD BE CONNECTED TO SEPARATE BIAS WINDINGS AND THESE SHOULD NOT BE PARALLED IN ORDER TO AVOID FALSE OPERATION DUE TO DISSIMILAR CT TRANSIENT RESPONSE.
NUMERICAL RELAYS DOES NOT REQUIRE AUX CTs
MAIN / DIFFERENTIAL PROTECTION FOR AT/F (5 CT METHOD) 87 T1
CTR: 2000-1000-500/1A
CLASS: PS
3 3 3
CORE-5
5S4
5S4
5S4
5S3
5S3
5S3
AUX.CT Y/ 0.689 / 0.577A
3-TCT
CT MB
AUX.CT Y/ 0.91 / 0.577A
P2 P2 P2
CT MB
5S1
5S1
5S1
5S3
5S3
5S3
3 3 3
P2 P2 P2 LV-CT CORE-5 CTR: 1200-800/1A
CLASS: PS
NORMALLY LOW IMPEDENCE BIASED DIFFERENTIAL RELAY IS USED FOR TRANSFORMER DIFFERENTIAL PROTECTION NUMERICAL RELAYS DOES NOT REQUIRE AUX CTs
SELECTION OF AUX.CTs FOR DIFFERENTIAL PROTECTION ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾ ¾
NORMALLY 400KV/220KV AUTO TRANSFORMERS ARE OF CAPACITY 315MVA. FOR MERZ PRICE PROTECTION IF TRANSFORMER IS CONNECTED IN STAR/STAR THEN CT SECONDARIES ARE TO BE CONNECTED IN DELTA/DELTA. CORRECT RATIO CTs ARE NOT AVAILABLE, THEN AUX.CTs ARE TO BE PROVIDED FOR ACHEVING SUITABLE CURRENTS. IF AUX CTs ARE USING THEN MAIN CT SECONDARIES ARE CONNECTED IN STAR. THIS IS BROUGHT TO AUX CTs. AUX CTs PRIMARY IS CONNECTED IN STAR & SECONDARIES ARE CONNECTED IN DELTA. NORMALLY THE RELAY RATED CURRRENT IS 1A. AUX.CT s SECONDARIES ARE CONNECTED IN DELTA. FOR ACHIEVING 1A TO RELAY, AUX.CT SECONDARY CURRENT IS TO BE 0.577A. THE FULL LOAD PRIMARY CURRENT OF 315MVA AT/F IS 454.7A. BUT THE 400KV CTs RATIOs ARE AVAILABLE : 2000-1000-500/1A NEAREST VALUE TO FULL LOAD CURRENT IS 500/1A. HENCE IT IS ADOPTED. HENCE AT FULL LOAD HV CURRENT i.e 454.7A, THEN SECONDARY OF CT CURRENT WILL BE 0.91A. SO HV SIDE AUX.CT RATIO IS 0.91/0.577A. THE FULL LOAD SECONDARY CURRENT OF 315MVA AT/F IS 826.7A. BUT THE 220KV CTs RATIOs ARE AVAILABLE: 1200-800/1A. NEAREST VALUE TO FULL LOAD CURRENT IS 1200/1A. HENCE IT IS ADOPTED. HENCE AT FULL LOAD LV CURRENT i.e 826.7A,THEN SECONDARY OF CT CURRENT WILL BE 0.689A. SO LV SIDE AUX CT RATIO IS 0.689/0.577A. SPECIAL INFORMATION: LATEST NUMERICAL RELAYS NEED NOT REQUIRE AUX CTs. IN THESE RELAYS, CT RATIOS MATCHING CAN BE PROGRAMMED.
BACKUP PROTECTION FOR AT/F HV (4 CT METHOD) P2 P2 P2
CT MB
3-CT CTR: 2000-1000-500/1A
3 3 3
CORE-4
4S4
4S4
4S4
4S3
4S3
4S3
CLASS: PS
50Z
IN4 / C471
VB11 / E151
VY11 / E131
3 CT METHOD : 3-CT & 2-CT 4 CT METHOD : 3-CT & 2-ACT 6 CT METHOD : 3-ACT & 2-ACT
3 3 3 E172 E174
4S3
4S3
4S3
4S4
4S4
4S4
CLASS: PS
P2 P2 P2
3
3 3
CVT SELECTION BUS-1 CVT / BUS-2 CVT / LINE CVT
CT MB
3 3 3
CTR: 2000-1000-500/1A
VR11 / E111
VN11 / E171
2-ACT CORE-4
IR4 / C411 IY4 / C431 IB4 / C451
CORE-1 VA : 200
IB4 / C451 IY4 / C431 IR4 / C411
CLASS: 3P
BACKUP PROTECTION FOR AT/F HV (5 CT METHOD) VR11 / E111 VY11 / E131 VB11 / E151 P2 P2 P2 3-TCT CTR: 2000-1000-500/1A
CLASS: PS
3 3 3
CORE-4
4S4
4S3
4S4
4S4
4S3
4S3
CT MB
IR4 / C411 IY4 / C431 IB4 / C451
VN11 / E171
IN4 / C471
E172 E174
3 3 3 3
3 3
CVT SELECTION BUS-1 CVT / BUS-2 CVT / LINE CVT CORE-1 VA : 200
CLASS: 3P
BACKUP PROTECTION FOR AT/F LV P1 P1 P1
CT MB
LV-CT CTR: 1200 – 800 /1A
3 3 3
CORE-4
4S2
4S2
4S2
4S1
4S1
4S1
CLASS: PS
50Z
IR4 / C411 IY4 / C431 IB4 / C451
VR11 / E111
IN4 / C471
VB11 / E151
VY11 / E131
VN11 / E171
3 3 3
P2 P2 P2
E172 E174
3
3 3 VOLTAGE
SELECTION BUS-1 PT / BUS-2 PT CORE-1 VA : 200
CLASS: 3P
MISCELLENEOUS RELAYS & PROTECTIONS ADOPTED FOR AUTO TRANSFORMER IN ONE AND HALF CIRCUIT BREAKER SCHEME (OVER FLUX & REF FUNCTIONS) PREPARED BY GOPALA KRISHNA PALEPU ADE/MRT(PROTECTION)
OVER EXCITATION/FLUX RELAY {FOR AUTO TRANSFORMER HV & LV} VOLTAGE SELECTION
99 T HV
BUS-1 PT / BUS-2 PT CORE-1 VA : 200
CLASS: 3P
CVT SELECTION BUS-1 CVT / BUS-2 CVT / LINE CVT CORE-1 VA : 200
CLASS: 3P
99 T LV
315MVA, 400KV/220KV/33KV AT/F RESTRICTED EARTH FAULT RELAY P2 P2 P2 400KV HV CORE-1
S2
S2
S2
S1
S1
S1
3 3 3
BUSHING CT CTR: 1000/1A
CLASS: PS P1 P1 P1 P1 P1 P1 NEUTRAL CORE-1
S1
S1
S1
S2
S2
S2
3 3 3
BUSHING CT CTR: 1000/ 1A
CLASS: PS P2 P2 P2 P1 P1 P1 220KV LV CORE-1 CTR: 1000/1A
S1
S1
S1
S2
S2
S2
3 3 3
BUSHING CT
CLASS: PS
P2 P2 P2
315MVA, 400KV/220KV/33KV AT/F 3-PH HIGH IMPEDENCE DIFFERENTIAL RELAY P2 P2 P2 400KV HV CORE-1
S2
S2
S2
S1
S1
S1
3 3 3
BUSHING CT CTR: 1000/1A
CLASS: PS P1 P1 P1 P1 P1 P1 NEUTRAL CORE-1
S1
S1
S1
S2
S2
S2
3 3 3
BUSHING CT CTR: 1000/ 1A
CLASS: PS P2 P2 P2 P1 P1 P1 220KV LV CORE-1 CTR: 1000/1A
S1
S1
S1
S2
S2
S2
3 3 3
BUSHING CT
CLASS: PS
P2 P2 P2
315MVA, 400KV/220KV AT/F VOLAGE SELECTION BUS-1
LINE1
1-52CB
2-52CB
3-52CB
BUS-2
AT/F-1
FEEDER HAVING LINE CVTs &BUSES ARE HAVING BUS CVTs BUT AT/Fs ARE NOT HAVING CVTs. FOR TRANSFORMER PANEL, PT SUPPLY IS SELECTED AS PER SELECTION DESCRIBED BELOW FOR METERING AND PROTECTION, WHICH IS FIRST SELECTED .
BUS-1 CVT BUS-2 CVT LINE CVT
If AT/F is feeding from Bus-1 and 1-52CB & 2-52CB is closed. Then Bus-1 CVT is selected and this supply is extended to Control & Relay Panels for Auto Transformer. If AT/F is feeding from Bus-2 and 3-52 CB is closed & 2-52CB is open. Then Bus-2 CVT is selected and this supply is extended to Control & Relay Panels for Auto Transformer. If AT/F is feeding from Direct Line and 2-52CB is closed & 1-52 CB & 3-52 CB is open and 389T ISO is Closed . Then line CVT is selected and this supply is extended to Control & Relay Panels for Auto Transformer.
1-PH UNITS OF 500 MVA TRANSFORMER ( EACH 167 MVA ) WITH CHANGE OVER FACILITY Y
B
1
2
3
R
Y
B
4
SPARE
R
R
Y
B
5
6
7
R
Y
B
MAIN-1 & MAIN-2 PROTECTION FOR SHUNT REACTOR ADOPTED IN ONE AND HALF CIRCUIT BREAKER SCHEME PREPARED BY GOPALA KRISHNA PALEPU ADE/MRT(PROTECTION)
BASICS OF SHUNT REACTOR 1. TYPES OF REACTORS : A. BASED ON REACTOR CONNECTION i. SHUNT REACTOR. ii. SERIES REACTOR. B. BASED ON REACTOR LOCATION i. BUS REACTOR ii. LINE REACTOR C. BASED ON CONTROL i. 3-PH OIL IMMERSED REACTOR WITH GAPPED IRON CORE. ii. THYRISTOR CONTROLLED REACTOR (STATIC VAR COMPENSATOR) (APTRANSCO UTILISING SHUNT REACTORS FOR BUS & LINE IN 400KV NETWORK) 2. NEED OF SHUNT REACTOR: A. LINE REACTOR SHUNT REACTORS ARE USED IN ORDER TO COMPENSATE FOR THE CAPACITIVE SHUNT REACTANCE OF TRANSMISSION LINES. THE REACTOR IS CONNECTED PARALLEL TO THE LINE. THE LOCATION OF REACTOR IS OUT GOING SIDE OF LINE i.e AFTER CIRCUIT BREAKER. LENGTH OF LINE IS MORE THERE MAY BE VOLTAGE IS RAISING DUE TO FARANTI EFFECT(CAPACITANCE) DURING CHARGING. IN CASE OF ZONE-2 (OPEN JUMPER) FAULT, THE FAULT CLEARED BY REMOTE END IS FAST, BUT THIS END IT WILL TAKE TIME DELAY DUE TO ZONE-2. DURING THIS TIME, VOLTAGE MAY RAISING. SO, LINE REACTOR IS USED FOR CONTROLLING THE SWITCHING OVER VOLTAGES AND SAFEGUARD THE OPERATING EQUIPMENT. NORMALLY IT IS ALWAYS IN SERVICE. NORMALLY BOTH ENDS LINE REACTORS ARE PROVIDED. THE ELECTRICAL INTERLOCK IS PROVIDED THAT IF REACTOR ISOLATOR CLOSSED POSITION ONLY WILL GIVE PERMIT TO CLOSE THE LINE ISOLATOR. SIMILARLY FOR OPENING REACTOR ISOLATOR THE LINE ISOLATOR SHOULD BE IN OPEN POSITION. NEUTRAL REACTOR CONNECTED BETWEEN THE STAR POINT OF EHV SHUNT REACTOR AND THE GROUND, LIMITS THE SECONDARY ARC CURRENT TO A LOW VALUE OF AROUND 10 AMPS TYPICALLY FOR 400KV SYSTEM TO ENSURE COMPLETE DE-IONISATION OF ARC PATH WHEN EHV SYSTEM DEVELOPS A SINGLE LINE TO GROUND FAULT. ARC EXTINCTION DURING LINE SINGLEPHASE AUTORECLOSE DEAD TIME IS ASSISTED BY THIS NEUTRAL REACTOR.
3.
4.
B. BUS REACTOR THE REACTOR IS CONNECTED PARALLEL TO THE BUS i.e LIKE A FEEDER/LINE. DURING LIGHTLY LOADED CONDITIONS THERE MAY BE POSSIBULITY OF RAISING BUS VOLTAGES. FOR SAFEGUARD THE OPERATING EQUIPMENT BUS REACTORS ARE UTILISING. NORMALLY IT IS NOT IN SERVICE. WHENEVER THE VOLTAGE RAISES TO 4%TO 5% MORE THAN THE RATED VOLTAGE THIS MAY BE KEPT IN SERVICE AND 2% TO 3% LESS THAN THE RATED VOLTAGE THIS MAY BE KEPT OUT OF SERVICE. SELECTION OF REACTOR A. LINE REACTOR NORMALLY LINE REACTORS ARE PROVIDED IF THE LINE IS MORE OR EQUAL TO 250KM. IN APTRANSCO NETWORK MAXIMUM LENTH OF LINE IS 350KM. AS PER SYSTEM STUDIES RECOMANDATIONS IF LINE LENGTH IS 250KM TO 300KM 50MVAR REACTOR IS TO BE USED. IF MORE THAN 300KM 63MVAR REACTOR IS TO BE USED. B. BUS REACTOR NORMALLY BUS REACTORS ARE PROVIDED IF THE SUBSTATION BUS VOLTAGE IS RAISING 5% MORE THAN THE RATED VOLTAGE DURING LIGHTLY LOADED CONDITION. BASED ON THE SYSTEM STUDIES RECOMANDATIONS BUS REACTORS ARE TO BE PROVIDED. CALCULATIONS ARE REQUIRED FOR PROVIDING BUS REACTOR. IN THIS THERE IS NO STANDARDISATION. LOCATION OF REACTORS WITH CAPACITY IN APTRANSCO A. LINE REACTOR 1. 400KV KALAPAKA-KHAMMAM 1 AT BOTH ENDS – 63MVAR 2. 400KV KALAPAKA-KHAMMAM 2 AT BOTH ENDS – 63MVAR B. BUS REACTOR 1. 400KV KALAPAKA SS – 2 X 50 MVAR 2. 400KV NUNNA SS(PGCIL BAYS) – 1 x 63 MVAR
5.
6.
7.
8.
9.
PURPOSE OF SHUNT REACTOR PROTECTION THE PURPOSE OF THE PROTECTION RELAYING IS TO DISCONNECT THE REACTOR AND LIMIT DAMAGE IN CASE OF INTERNAL SHORT CIRCUITS, EARTH FAULTS, INTERTURN FAULTS AND OVER VOLTAGE OR OVER LOAD.THE REACTOR FORMS CERTAIN IMPEDENCE FOR RATED FREQUENCY, AND AS IT IS SHUNT CONNECTED, AS OVER LOAD MAY BE CAUSED BY OVER VOLTAGE OR HARMONICS IN VOLTAGE AND CURRENT. PROTECTION DEVICES INBUILT OR MOUNTED ON REACTOR A. OIL IMMERSED REACTOR USUALLY HAVE A GAS DETECTOR AND OIL SURGE. DETECTOR (BUCHHOLZ ALARAM & TRIP DEVICES), WHICH ARE EXCELLENT FOR DETECTING INTERNAL FAULTS. B. TEMPARATURE MONITORS FOR OIL & WINDING PROVIDE GOOD OVER LOAD PROTECTION. C. PRESSURE RELIEF DEVICE IS PROVIDED TO SAFE GUARD THE REACTOR FROM HIGH PRESURES. REACTOR DIFFERENTIAL PROTECTION IT IS WIDELY USED AS INSTANTANEOUS PROTECTION FOR SHORT CIRCUIT FAULTS WITH IN THE DIFFERENTIAL ZONE. THIS IS TREATED AS MAIN-1 PROT FOR REACTOR. IT CAN BE OF HIGH IMPEDENCE TYPE OR OF A SENSITIVE CURRENT STABILISED TYPE. HIGH IMPEDENCE DIFFERENTIAL PROTECTION RELAYS REQUIRE AN EQUAL CT TURNS RATIO ON THE PHASE AND NEUTRAL SIDE. SENSITIVITY IS 5% OF NOMINAL REACTOR CT CURRENT. BACK-UP PROTECTION A VARIETY OF RELAYS ARE AVAILABLE. A. OVER CURRENT & EARTH FAULT PROTECTION. ( 50, 50N, 51, 51N, 67, 67N - ANY COMBINATION OF THESE) B. UNDER IMPEDENCE / DISTANCE ( Z<)(21R). C. NEUTRAL DISPLACEMENT PROTECTION (Un>). RESTRICTED EARTH FAULT PROTECTION IF, FOR SOME REASON, A SENSITIVE DIFFERENTIAL PROTECTION NOT CHOOSEN A RESTRICTED EARTH FAULT PROTECTION CAN BE UTILISED.
SHUNT REACTOR (BUS & LINE) (ONE AND HALF CIRCUIT BREAKER SYSTEM ) BUS-1
BUS-2
1-89
IL INTER LOCK FACILITY: WHEN 1-89R CLOSES ONLY PERMIT TO CLOSE 1-89L AND 1-89L OPENS ONLY PERMIT TO OPEN 1-89R.
3-89
1-52CB 1-CT
3-52CB P2
P2
3 3-CT
3
P1
P1
1-89A
.
UUU
1-PH NEUTRAL GROUNDING REACTOR
UUU
IL
LINE SHUNT REACTOR
2-CT
1-89L
2-89A
2-52CB
P2
2-89B 3-89R
UUUU
.
P1
3
1-89R
3-89A
LINE 1
BUS SHUNT REACTOR
REACTOR BUSHING CT INFORMATION CAPACITY OF 400KV REACTORS : 50, 63, 80, 125 MVAR Sr NO 1
SHUNT REACTOR ITEM
400KV / LINE SIDE
CORE-2 CORE -3 CORE-4
3 RCT IN OHMS 1 OHM
1 OHM
CLASS OF ACURACY
PS
PS
PURPOSE
87 R DIFF
64 R REF1
200V
1000500250V
1000500250V
1.0 CL AND 10 – 5 – 10 – 5 BURDEN – 2.5 10 VA 1 OHM 2.5
PS
OHM
OHM
PS
PS
FOR 21L2 FOR 21L1 21 R /TEED-2 / /TEED-1 / MET IMP BBC BBM
Parameters of WTI CT for each winding shall be provided by the contractor
200V
5
CORE-1
2000- 2000200/1 200/1 200/1 1000- 1000- 200/1 WTI 200/1 200/1 500/1 500/1 NEUTRAN BUSHING CT : BEFORE STAR FORMATION IN RYB PHASES
VKNEE FOR PS 2 & VA FOR 200V MET
4
LINE SIDE EARTH SIDE
STAR / NEUTRAL SIDE
CORE-1 CORE -2 CORE-3 CORE-4 CORE-5
RATIO
NGR
CORE-1
CORE-2
200/1
200/1
200V
200V
200V
200V
1 OHM
1 OHM
1 OHM
1 OHM
PS
PS
PS
PS
87 R DIFF
64 R REF1
64 R REF2
64 R REF1/2
SHUNT REACTOR PROTECTION ONE & HALF BREAKER SYSTEM
CORES
LINE
BUS
DOUBLE BUS & TRANSFER BUS SYSTEM LINE
BUS
400KV SIDE CORE-1
87R – 3Ph, 2Wdg REACTOR DIFFERENTIAL RELAY EITHER LOW or HIGH IMPEDANCE TYPE.
CORE-2
64R - REACTOR RESTRICTED EARTH FAULT PROTECTION OF1-POLE HIGH IMPEDANCE TYPE. (REF1)
CORE-3
21R – 3Ph, REACTOR BACKUP IMPEDANCE RELAY OF SUITABLY SHAPED CHARECRESTICS EITHER SINGLE / DOUBLE ZONE TYPE.
CORE-4 CORE-5
21L2
87 TEED-2
21L2
(M_CT + T_CT – R_CT)
(M_CT, T_CT, R_CT)
(M_CT+T_CT – R_CT)
21L1
87 TEED-1
21L1
(M_CT + T_CT – R_CT)
(M_CT, T_CT, R_CT)
(M_CT + T_CT – R_CT)
M_CT: Main CT, T_CT: Tie CT, R_CT: Reactor CT
87 BBC/BB-2 87 BBM/BB-1
SHUNT REACTOR PROTECTION CORES
ONE & HALF BREAKER SYSTEM LINE
BUS
DOUBLE BUS & TRANSFER BUS SYSTEM LINE
BUS
STAR / NEUTRAL SIDE CORE-1
METERING OF REACTOR
CORE-2
WINDING TEMPARETURE OF REACTOR
CORE-3
87R – 3Ph, 2Wdg REACTOR DIFFERENTIAL RELAY EITHER LOW / HIGH IMPEDANCE TYPE.
CORE-4
64R - REACTOR RESTRICTED EARTH FAULT PROTECTION OF1-POLE HIGH IMPEDANCE TYPE .(REF1)
NEUTRAL GROUNDING REACTOR SIDE CORE-1
64 REF1
--
64 REF2
--
CORE-2
64 REF1
--
64 REF 1 / 2
--
3
3
CORE -2
3 3
3 3
CORE -4
3
3
3
CORE -5
UUU
UUU
UUU
3 3 3
3
CORE -3
3
3
3 3 3
LINE SHUNT REACTOR
3 3
CORE -4
.
CORE -1 CORE -2
CORE -1
UUU
3 3
1-PH NEUTRAL GROUNDING REACTOR
CORE -3
3
3 3
REACTOR BUSHING CT INFORMATION
3
3
CORE -1
CORE -2
3 3 3
3 3 3
3
3
3
CORE -5
UUU
UUU
UUU
CORE -3
3 3 3
3
CORE -3
3
3
3 3 3
BUS SHUNT REACTOR
CORE -2
3
3 3
REACTOR BUSHING CT INFORMATION
3 3
3
3
CORE -4
CORE -1
CORE -4
.
CORE -1 CORE -2
ONE & HALF BREAKER LINE & BUS SHUNT REACTOR PROTECTION SCHEME 87BB1 BUSBAR-1 79 CVT VBB1
VL1
21M1 VBB1
25
VL1 / VL2 OR VBB2
BF 87L
21M2
VL1
CVT
VL1 FEEDER1 / LINE1
79
UUU 64R 21R
79 25
PROTECTION OF BUS REACTOR 21R BUSBAR-2
87BB2
64R
TEED-2 VBB1/VBB2
VL2 / VL1 OR VBB1 CVT VBB2
87R
UUU TEED-1
BF
OR
VL1/VBB1/VBB2
25
BF
VBB2
UUU
VL1 / VBB1 VL2 / VBB2
87R
FOR REACTOR PROTECTION & METERING VOLTAGE SELECTION RELAYS FOR BUS-1, BUS-2& LINE ARE PROVIDED .
LINE/BUS REACTOR DIFFERENTIAL PROTECTION (LOW / HIGH IMPEDANCE DIFFERENTIAL PROTECTION) CT MB
P2 P2 P2
RET 670
CT MB
CTR: 200/1A
3 3 3
CORE-1
1S2
1S2
1S2
1S1
1S1
1S1
ACTIVE
START
3S1
3S1
3S2
3S2
3S2
3 3 3
R-CT HV BUSHING
3S1
TRIP
P2 P2 P2 R-CT
CLASS: PS
STAR BUSHING
DISPLAY
CORE-3 CTR: 200/1A
CLASS: PS
C
E
NORMALLY LOW / HIGH IMPEDENCE DIFFERENTIAL RELAY IS USED FOR BUS / LINE REACTOR DIFFERENTIAL PROTECTION
IN CASE OF REACTOR BUSHING CT P2 IS AWAY FROM REACTOR & P1 IS TOWARDS REACTOR
LINE/BUS REACTOR DIFFERENTIAL PROTECTION (HIGH IMPEDANCE DIFFERENTIAL PROTECTION) P2 P2 P2 R-CT HV CORE-1
3 3 3
BUSHING CT
RET 670 1S2 1S2 1S2 ACTIVE START
TRIP
1S1 1S1 1S1
CTR: 200/1A
CLASS: PS P1 P1 P1
DISPLAY C E
P1 P1 P1 R-CT STAR CORE-3 CTR: 200/1A
3S1 3S1 3S1
3 3 3
BUSHING CT
3S2 3S2 3S2
CLASS: PS
P2 P2 P2
NORMALLY LOW / HIGH IMPEDENCE DIFFERENTIAL RELAY IS USED FOR BUS / LINE REACTOR DIFFERENTIAL PROTECTION IN CASE OF REACTOR BUSHING CT P2 IS AWAY FROM REACTOR & P1 IS TOWARDS REACTOR
LINE/BUS REACTOR REF PROTECTION (NGR IS NOT AVAIALBLE) P2 P2 P2 R-CT HV CORE-2
3 3 3
BUSHING CT
RET 670 2S2 2S2 2S2 ACTIVE START
TRIP
2S1 2S1 2S1
CTR: 200/1A
CLASS: PS P1 P1 P1
DISPLAY C E
P1 P1 P1 R-CT STAR CORE-4 CTR: 200/1A
4S1 4S1 4S1
3 3 3
BUSHING CT
NORMALLY HIGH IMPEDENCE VOLTAGE/CURRENT OPERATED SINGLE POLE RELAY IS USED FOR BUS / LINE REACTOR RESTRICTED EARTH FAULT PROTECTION. PRESENTLY NUMERICAL DIFFERENTIAL RELAYS HAVING IN BUILT FUNCTION OF 2 REF OR 2 SEF PROTECTIONS.
4S2 4S2 4S2
CLASS: PS
P2 P2 P2
IN CASE OF REACTOR BUSHING CT P2 IS AWAY FROM REACTOR & P1 IS TOWARDS REACTOR
LINE REACTOR REF PROTECTION (NGR IS AVAIALBLE) P2 P2 P2 R-CT HV CORE-2
3 3 3
BUSHING CT
RET 670 2S2 2S2 2S2 ACTIVE START
TRIP
2S1 2S1 2S1
CTR: 200/1A
CLASS: PS P1 P1 P1
DISPLAY C E
P1 P1 P1 NGR-CT EARTH CORE-2 CTR: 200/1A
2S1 2S1 2S1
3 3 3
BUSHING CT
NORMALLY HIGH IMPEDENCE VOLTAGE/CURRENT OPERATED SINGLE POLE RELAY IS USED FOR BUS / LINE REACTOR RESTRICTED EARTH FAULT PROTECTION. PRESENTLY NUMERICAL DIFFERENTIAL RELAYS HAVING IN BUILT FUNCTION OF 2 REF OR 2 SEF PROTECTIONS.
2S2 2S2 2S2
CLASS: PS
P2 P2 P2
IN CASE OF REACTOR BUSHING CT P2 IS AWAY FROM REACTOR & P1 IS TOWARDS REACTOR
LINE REACTOR 2 NOs REF PROTECTIONS (NGR IS AVAIALBLE) P2 P2 P2
P2 P2 P2
CT MB R-CT HV CORE-2
3 3 3
BUSHING CT
RET 670 2S2 2S2 2S2 ACTIVE START
TRIP
CTR: 200/1A
CLASS: PS P1 P1 P1
E
R-CT STAR CORE-4 CTR: 200/1A
4S1 4S1 4S1
3 3 3
BUSHING CT
4S2 4S2 4S2
CLASS: PS
P2 P2 P2
1S2
1S2
1S1
1S1
1S1
DISPLAY C
P1 P1 P1
1S2
3 3 3
2S1 2S1 2S1
NORMALLY HIGH IMPEDENCE VOLTAGE/CURRENT OPERATED SINGLE POLE RELAY IS USED FOR BUS / LINE REACTOR RESTRICTED EARTH FAULT PROTECTION. PRESENTLY NUMERICAL DIFFERENTIAL RELAYS HAVING IN BUILT FUNCTION OF 2 REF OR 2 SEF PROTECTIONS.
P1 P1 P1 NGR-CT BUSHING CT CORE - 1 & 2 CTR: 200/1A
CLASS: PS
P1 P1 P1
CT MB
2S1
2S1
2S1
2S2
2S2
2S2
3 3 3
P2 P2 P2
LINE/BUS REACTOR B/U IMPEDANCE PROTECTION
P2 P2 P2
IR3 / A311 IY3 / A331 IB3 / A351
R-CT HV CORE-3 CTR: 200/1A
3 3 3
BUSHING CT
CT MB
3S2
3S2
3S2
3S1
3S1
3S1
IN3 / A371
REL 670 ACTIVE START
TRIP
CLASS: PS
DISPLAY C
VR11 / E111 VY11 / E131 VB11 / E151 VN11 / E171 CVT SELECTION BUS-1 CVT / BUS-2 CVT / LINE CVT CORE-1 VA : 200
E
CLASS: 3P
LINE REACTOR PROTECTION FOR LINE P2 P2 P2
3 3 3
CTR: 2000-1000-500/1A
(MAIN-1 PROTECTION) IR5 / A511 IY5 / A531 IB5 / A551
1-CT CORE-5
CT MB
5S4
5S4
5S4
5S2
5S2
5S2
IN5 / A571
REL 521 ACTIVE START
TRIP
VR11 / E111 VY11 / E131 VB11 / E151 VN11 / E171 1-CVT
CLASS: PS
DISPLAY
CORE – 1 200VA CLASS: 3P
C
2-CT CTR: 2000-1000-500/1A
3 3 3
CORE-5
5S2
5S2
5S2
5S4
5S4
5S4
CLASS: PS
P2 P2 P2 LR-CT 400KV CTR: 2000-1000-500/1A
3 3 3
CORE-5
5S4
5S4
5S4
5S2
5S2
5S2
CLASS: PS P1 P1 P1
E
LINE REACTOR PROTECTION FOR LINE (MAIN-2 PROTECTION) P2 P2 P2
IR4 / A411 IY4 / A431 IB4 / A451
1-CT CTR: 2000-1000-500/1A
3 3 3
CORE-4
CT MB
4S4
4S4
4S4
4S2
4S2
4S2
IN4 / A471
REL 316 ACTIVE START
TRIP
VR21 / E211 VY21 / E231 VB21 / E251 VN21 / E271 1-CVT
CLASS: PS
DISPLAY
CORE – 2 200VA CLASS: 3P
C
2-CT CTR: 2000-1000-500/1A
3 3 3
CORE-4
4S2
4S2
4S2
4S4
4S4
4S4
CLASS: PS
P2 P2 P2 LR-CT 400KV CTR: 2000-1000-500/1A
3 3 3
CORE-4
4S4
4S4
4S4
4S2
4S2
4S2
CLASS: PS P1 P1 P1
E
BUS REACTOR TEED-1 PROTECTION {BAY3&2}
P2 P2 P2
IR5 IY5 IB5
3-CT CTR: 2000-1000-500/1A
3 3 3
CORE-5
5S4
5S4
5S4
5S2
5S2
5S2
CLASS: PS
IN5
RET 670 P1 P1 P1 P2 P2 P2
IR5 IY5 IB5
2-CT CTR: 2000-1000-500/1A
3 3 3
CORE-1
1S4
1S4
1S4
1S2
1S2
1S2
CLASS: PS
IN5
ACTIVE START
TRIP
DISPLAY C
P1 P1 P1
E
P2 P2 P2 BR-LCT CTR: 2000-1000-500/1A
CLASS: PS
IN1 4S4
4S4
4S4
4S2
4S2
4S2
3 3 3
CORE-5
IB1 IY1 IR1 P1 P1 P1
IT WORKS ON CIRCULATING CURRENT PRINCIPLE AND IT IS HIGH IMPEDENCE DIFFERENTIAL RELAY. TEED-1 PROTECTION FOR BAY 2&3 AND THE FOLLOWING CTs & CORES ARE USED 3-CT(CORE-5), 2-CT(CORE-1) & BR-CT (CORE-5) ARE STARRED AND CONNECTED TO TEED-1 PROTECTION
BUS REACTOR TEED-2 PROTECTION CT MB
3-CT CTR: 2000-1000-500/1A
3 3 3
CORE-4
4S4
4S4
4S4
4S2
4S2
4S2
CLASS: PS
CT MB
RET 670 ACTIVE
START
RAICA LBB/BFR
P2 P2 P2
RAICA LBB/BFR
{BAY3&2} P2 P2 P2
2S4
2S4
2S4
2S2
2S2
2S2
3 3 3
TRIP
2-CT CORE-2
DISPLAY
CTR: 2000-1000-500/1A
CLASS: PS
P2 P2 P2 CT MB BR-CT CTR: 2000-1000-500/1A
CLASS: PS
3 3 3
CORE-4
C 4S4
4S4
4S4
4S2
4S2
4S2
E
IT WORKS ON KIRCHOFF’S CURRENT PRINCIPLE & IT IS PERCENTAGE BIASED LOW IMPEDENCE DIFFERENTIAL RELAY. TEED-2 PROTECTION FOR BAY 2&3 IS THE FOLLOWING CTs & CORES ARE USED. 3-CT(CORE-4), 2-CT(CORE-2) & BR-CT (CORE-4) ARE CONNECTED TO TEED-2 PROTECTION.
REACTOR MULTI FUNCTION PANEL METERING P2 P2 P2
IR2 / D211 IY2 / D231 IB2 / D251
R-CT STAR CORE-2
3 3 3
BUSHING CT
CT MB
2S2
2S2
2S2
2S1
2S1
2S1
CTR: 200/1A
CLASS: 0.2
IN2 / D271
VR31 / E311 VY31 / E331 VB31 / E351 VN31 / E371 BASED ON SELECTION LINE CVT / BUS-1 CVT / BUS-2 CVT CORE – 3 100VA CLASS: 0.2
OVER EXCITATION/FLUX RELAY {FOR LINE & BUS REACTORS} VOLTAGE SELECTION
CVT SELECTION BUS-1 CVT / BUS-2 CVT / LINE CVT CORE-1 VA : 200
CLASS: 3P
RATUB
BUS-1 PT /
V/F RELAY LINE
CORE-1
RATUB V/F RELAY BUS
BUS-2 PT VA : 200
CLASS: 3P
CARRIER INTERTRIPPING OF LINE SHUNT REACTOR LINE SHUNT REACTOR PROTECTION TRIPPINGS WILL BE USED AS DIRECT TRIPPINGS OF LINE IN ADDITION TO OTHER TRIPPINGS. BUS SHUNT REACTOR NEED NOT REQUIRE CARRIER INTER TRIPPING FACILITY. 87R REACTOR DIFFERENTIAL RELAY RET 670 21R REACTOR IMPEDENCE RELAY REL 670
ABB NSD 50
LINE PROTECTION COUPLER PANEL-1
DC +VE FROM PANEL
64R RESTRICTED EARTH FAULT RELAY
RET 670 REACTORS INTERNAL FAULTS
G4AD V9LC 2
GROUP-1/A TRIPPINGS
G4AD V9LC 1 87R REACTOR DIFFERENTIAL RELAY RET 670 21R REACTOR IMPEDENCE RELAY REL 670
ABB NSD 50
DC –VE FROM PANEL
LINE PROTECTION COUPLER PANEL-2
DC +VE FROM PANEL
64R RESTRICTED EARTH FAULT RELAY
RET 670 REACTORS INTERNAL FAULTS
G4AD V9LC 2
GROUP-2/B TRIPPINGS
G4AD V9LC 1
DC –VE FROM PANEL
ADDITIONAL AND SPECIAL FUNCTIONS ADOPTED IN ONE AND HALF CIRCUIT BREAKER SCHEME (EVENT LOGGER & DISTURBANCE RECORDER) PREPARED BY GOPALA KRISHNA PALEPU ADE/MRT(PROTECTION)
400KV SUBSTATION: MAMIDIPALLY 19 MAR 2004 13:00:00 A 13:09:37.090 # 195 A 13:09:37.096 # 188 A 13:09:37.097 # 187 A 13:09:37.100 # 181 A 13:09:37.104 # 162 A 13:09:37.110 # 196 A 13:09:37.110 # 170 A 13:09:37.111 # 161 A 13:09:37.111 # 163 A 13:09:37.111 # 169 A 13:09:37.112 # 168 A 13:09:37.113 # 182 A 13:09:37.126 # 199 A 13:09:37.140 # 185 N 13:09:37.147 # 195 N 13:09:37.148 # 196 N 13:09:37.175 # 187 N 13:09:37.176 # 181 N 13:09:37.176 # 188 N 13:09:37.185 # 182 N 13:09:37.257 # 199 N 13:09:37.279 # 185 19 MAR 2004 14:00:00 N 14:09:48.702 # 163 N 14:09:48.704 # 161 N 14:09:48.720 # 162 N 14:10:00.903 # 169 N 14:10:00.907 # 168 N 14:10:00.907 # 170 19 MAR 2004 15:00:00
EVENT LOGGER EVENTS INFORMATION
400KV SRISAILAM-2 MAIN-2 RAZFE PROT TRIP 400KV SRISAILAM-2 MAIN-1 REL100 PROT START’Y’ 400KV SRISAILAM-2 MAIN-1 REL100 PROT START’R’ 400KV SRISAILAM-2 MAIN-1 REL100 PROT TRIP 400KV SRISAILAM-2 MAIN CB 752 Y-PH OPEN 400KV SRISAILAM-2 MAIN-2 RAZFE CARRIER SEND 400KV SRISAILAM-2 AT/F-2 TIE CB 852 B-PH OPEN 400KV SRISAILAM-2 MAIN CB 752 R-PH OPEN 400KV SRISAILAM-2 MAIN CB 752 B-PH OPEN 400KV SRISAILAM-2 AT/F-2 TIE CB 852 Y-PH OPEN 400KV SRISAILAM-2 AT/F-2 TIE CB 852 R-PH OPEN 400KV SRISAILAM-2 MAIN-1 REL100 CARRIER SEND 400KV SRISAILAM-2 CARRIER PROT CH-2 RECEIVED 400KV SRISAILAM-2 CARRIER PROT CH-1 RECEIVED 400KV SRISAILAM-2 MAIN-2 RAZFE PROT TRIP RESET 400KV SRISAILAM-2 MAIN-2 RAZFE CARRIER SEND RESET 400KV SRISAILAM-2 MAIN-1 REL100 START ‘R’ RESET 400KV SRISAILAM-2 MAIN-1 REL100 PROT TRIP RESET 400KV SRISAILAM-2 MAIN-1 REL100 START ‘Y’ RESET 400KV SRISAILAM-2 MAIN-1 REL100 CARRIER SEND RESET 400KV SRISAILAM-2 CARRIER PROT CH-2 RECEIVED RESET 400KV SRISAILAM-2 CARRIER PROT CH-1 RECEIVED RESET 400KV SRISAILAM-2 MAIN CB 752 B-PH CLOSE 400KV SRISAILAM-2 MAIN CB 752 R-PH CLOSE 400KV SRISAILAM-2 MAIN CB 752 Y-PH CLOSE 400KV SRISAILAM-2 AT/F-2 TIE CB 852 Y-PH CLOSE 400KV SRISAILAM-2 AT/F-2 TIE CB 852 R-PH CLOSE 400KV SRISAILAM-2 AT/F-2 TIE CB 852 B-PH CLOSE
DISTURBANCE RECORDER
R PH VOLTAGE Y PH VOLTAGE B PH VOLTAGE OPEN DELTA VOLTAGE R PH CURRENT Y PH CURRENT B PH CURRENT STAR/NEUTRAL CURRENT MAIN CB R PH OPEN MAIN CB Y PH OPEN MAIN CB B PH OPEN TIE CB R PH OPEN TIE CB Y PH OPEN TIE CB B PH OPEN MAIN/TIE CB LBB OPTD DIRECT TRIP CH-1/2 OPTD BUSBAR PROT OPTD MAIN-1 PROT OPTD MAIN-2 PROT OPTD OVER VOLTAGE STAGE-1/2 OPTD STUB PROT-1/2 OPTD MAIN-1 PROT CARRIER RECEIVE MAIN-2 PROT CARRIER RECEIVE DF/DT OPTD EVENT NO NAME OF FEEDER DATE & TIME
PREFERRED DISTURBANCE RECORDER 400 KV LINES
400 KV TRANSFORMER
ANALOG CHANNELS
ANALOG CHANNELS
DIGITAL CHANNELS
1. 2. 3. 4. 5. 6. 7. 8.
1. HV 2. HV 3. HV 4. HV 5. LV 6. LV 7. LV 8. LV 9. HV 10. HV 11. HV 12. HV 13. LV 14. LV 15. LV 16. LV
1. HV MAIN CB R-PH OPEN 2. HV MAIN CB Y-PH OPEN 3. HV MAIN CB B-PH OPEN 4. HV TIE CB R-PH OPEN 5. HV TIE CB Y-PH OPEN 6. HV TIE CB B-PH OPEN 7. LV 220 CB R-PH OPEN 8. LV 220 CB Y-PH OPEN 9. LV 220 CB B-PH OPEN 10 87 LZ DIFF RLY OPERATED 11. HV 67 ABCN OPERATED 12. LV 67 ABCN OPERATED 13. 51 O/L RLY OPERATED 14. 64 REF / 87 HZ RLY OPERATED 15. NDR RLY OPERATED 16. HV 99T OVER FLUX OPTD 17. LV 99T OVER FLUX OPTD 18. HV 400 BUSBAR OPERATED 19. LV 220 BUSBAR OPERATED 20. HV MAIN CB LBB OPERATED 21. HV TIE CB LBB OPERATED 22. LV 220 CB LBB OPERATED 23. HV 86 GR-A/B RELAY OPTD 24. LV 86 GR-A/B RELAY OPTD 25. AT/F 21T UZ RELAY OPERATED 26. OIL TEMP HIGH TRIP 27. WNDG TEMP HV/IV/LV TRIP 28. BUCHHOLZ MAIN/OLTC TRIP 29. PRD 1/ 2 TRIP 30. AT/F NEUTRAL CURRENT TRIP
R-PH VOLTAGE Y-PH VOLTAGE B-PH VOLTAGE OPEN DELTA VOLTAGE R-PH CURRENT Y-PH CURRENT B-PH CURRENT NEUTRAL/STAR CURRENT
DIGITAL CHANNELS 1. HV MAIN CB R-PH OPEN 2. HV MAIN CB Y-PH OPEN 3. HV MAIN CB B-PH OPEN 4. HV TIE CB R-PH OPEN 5. HV TIE CB Y-PH OPEN 6. HV TIE CB B-PH OPEN 7. 21 MAIN1 REL 521 OPERATED 8. 21 MAIN2 REL 316 OPERATED 9. 87 BUSBAR RELAY OPERATED 10. MAIN CB A/R OPERATED 11. TIE CB A/R OPERATED 12. PSB OPERATED 13. SOTF OPERATED 14. 27 O/V STG-1/2 OPERATED 15. 51 STUB-1/2 OPERATED 16. 87HZ / LZ TEED-1/2 OPERATED 17. MAIN CB LBB OPERATED 18. TIE CB LBB OPERATED 19. DIRECT TRIP CH-1/2 TRIP 20. 21M1 / 21M2 CARRIER RECEIVE 21. 86 GR-A/B RELAY OPERATED 22. 67N DEF/TEF RLY OPERATED 23. DF/DT RELAY OPERATED
R-PH VOLTAGE Y-PH VOLTAGE B-PH VOLTAGE OPEN DELTA VOLTAGE R-PH VOLTAGE Y-PH VOLTAGE B-PH VOLTAGE OPEN DELTA VOLTAGE R-PH CURRENT Y-PH CURRENT B-PH CURRENT NEUTRAL/STAR CURRENT R-PH CURRENT Y-PH CURRENT B-PH CURRENT NEUTRAL/STAR CURRENT
CONFIGUARATION OF CONTROL & RELAY PANELS IN ONE AND HALF CIRCUIT BREAKER SCHEME
PREPARED BY GOPALA KRISHNA PALEPU ADE/MRT(PROTECTION)
CONFIGUARATION OF C & R PANEL CONTROL PANEL
CB RELAY PANEL
LINE PROTECTION PANEL
1. AMMETERS IN 3Phs 2. VOLTMETER WITH SEL. SWITCH 3. WATTMETER 4. VAR METER 5. 20W ANNUCIATION FACIA 6. CB CONTROL (TNC) SWITCH 7. ISO CONTROL (TNC) SWITCH 8. SEMAPHORE FOR EARTH SWITCH 9. INDICATING LAMPS FOR CB G&R 10. INDICATING LAMPS FOR ISO 11. INDICATING LAMPS FOR DC 12. INDICATING LAMPS FOR ISO I/L 13. PUSH BUTTON FOR ANNUNCIATION 14. SYNCHRONISING SOCKET FOR CB 15. SYNCHRONISING SEL.SWITCH 16. PROTECTION TRANSFER 17. MIMIC TO REPRESENT SLD 18. CUTOUT FOR RWTI WITH SEL .SWI. 19. PANEL INDICATING LABEL
1. BREAKER FAILURE RELAY 2. AUTO RECLOSURE RELAY 3. CHECK SYNCHRONISING RELAY 4. CB ALARM RELAYS 5. CB TRIP CKT SUPERVISION RELAYS 6. 3-PH TRIP UNITS 86-GA & 86-GB 7. 1-PH TRIP RELAYS M1, M2 - 1 2 Nos 8. DIRECT TRIP RECEIVE RELAYS 9. DC SUPERVISION RELAYS 10. U/V RELAY E/S I/L 11. CB MULTIPLICATION RELAY 12. TEST TERMINAL BLOCK 13. ENERGY METER 14. AUX RELAYS 15. PANEL INDICATING LABEL
1. MAIN-1 NUM. DIST. PROT 2. MAIN-2 NUM. DIST. PROT. 3. O/V STAGE-1 (EXT/IN BUILT) 4. O/V STAGE-2 (EXT/IN BUILT) 5. DISTURBANCE RECORDER(EXT/INBUILT) 6. DISTANCE TO FAULT (EXT/ INBUILT) 7. DC SUPERVISION RELAYS 8. TEED-1 PROTECTION 9. TEED-2 PROTECTION 10. STUB-1/2 PROTECTION (EXT/ INBUILT) 11. AUXILIARY RELAYS 12. MAIN-1 CARRIER SEL.SWITCH 13. MAIN-2 CARRIER SEL.SWITCH 14. CARRIER RECEIVE RELAYS 15. FLAG RELAYS 16. TIMERS 17. PANEL INDICATING LABEL
* IN CASE OF ONE AND HALF CB SYSTEM CONTROL PANEL FOR FULL DIA IS TO BE AVAILABLE
CONFIGUARATION OF C & R PANEL TRANSFORMER PROTECTION PANEL HV PROTECTION PANEL
1. T/F DIFFERENTIAL PROTECTION 2. REF PROTECTION RELAY 3. DIRECTIONAL O/L E/F RELAYS 4. OVER FLUX PROTECTION 5. OVER LOAD PROTECTION 6. VOLTAGE SELECTION RELAYS 7. FUSE FAILURE RELAY 8. AUX RELAYS FOR T/F TROBLES 9. FLAG RELAYS 10. TIMERS 11. CIRCUIT LABEL
MV PROTECTION PANEL
1. DIRECTIONAL O/L E/F RELAYS 2. OVER FLUX PROTECTION 3. NEUTRAL DISPALCEMENT RELAY 4. VOLTAGE SELECTION RELAYS 5. FUSE FAILURE RELAY 6. AUX RELAYS FOR T/F TROBLES 7. FLAG RELAYS 8. TIMERS 9. CIRCUIT LABEL
REACTOR PROTECTION PANEL 1. REACTOR DIFFERENTIAL PROTECTION 2. REF PROTECTION RELAY 3. REACTOR IMPEDENCE PROTECTION 4. CVT SELECTION RELAYS 5. FLAG RELAYS 6. AUX RELAYS 7. TIMERS 8. CIRCUIT LABEL
IN ADDITION TO THE ABOVE THE FOLLOWING PANELS WILL BE AVAILABLE 1. CONTROL PANELS FOR LINE, T/F, B/C, TBC, BUS REACTOR (AS & WHEN REQ) 2. COMMON CONTROL PANEL 3. BUS BAR PROTECTION PANELS 4. TRANSFER BUS COUPLER PROTECTION PANEL(IN CASE OF DMT/SMT SCHEME) 5. BUS COUPLER PROTECTION PANEL (IN CASE OF DMT/DB SCHEME) I. NOMINCLATURE FOR PANELS ARE NORMALLY MAIN CB PANEL – RLA, TIE CB PANEL – RTB, HV CB PANEL – RTRA, LV CB PANEL – RTRD LINE PROTECTION PANEL – RLB, HV PROTECTION PANEL – RTRB, LV PROTECTION PANEL – RTRC, LINE REACTOR PROTECTION PANEL – RLRC, BUS REACTOR PROTECTION PANEL – RBRA, BUS BAR PANEL – RBBA, CONTROL PANEL – CP, KP, KT, KBC, KTBC,KL,CCP
400KV INTEGRATED CONTROL PANELS
400KV LINE CB RELAY & PROTN PANEL 4RLA
4RTB
4RLB
79 + 25 (AUTO RECLOSURE + CHECK SYNC RELAY)
79 + 25 (AUTO RECLOSURE + CHECK SYNC RELAY)
50 Z (LBB / BFR)
50 Z (LBB / BFR)
21 MAIN 1
CB TROUBLE ALARAM AND TRIP RELAYS TSR TC-1
DC I & II
CB TROUBLE ALARAM AND TRIP RELAYS
TSR TC-1I
TSR TC-1
DC I & II
TSR TC-1I
21 MAIN 2 86 GR -A
1-PH TRIP RELAYS -6 FOR 21M2
D/T CH-1 RECEIVE RELAYS
D/T CH-2 RECEIVE RELAYS
59 L1 59 L2 O/V STG-1 O/V STG-1i
BREAKER UNDER VOLTAGE MULTIPLICA RELAY TION RELAY
DC-1I
86 GR -B
DC-1
86 GR -A
1-PH TRIP RELAYS -6 FOR 21M1
21 MAIN 1 21 MAIN 1i AUX RELYS AUX RELYS
87 HIGH TEED-1
87 LOW TEED-2
1-PH TRIP RELAYS -6 FOR 21M1
86 GR -B
1-PH TRIP RELAYS -6 FOR 21M2
D/T CH-1 RECEIVE RELAYS
D/T CH-2 RECEIVE RELAYS BREAKER MULTIPLICA TION RELAY
400KV LINE + R CB RELAY & PROTN PANEL 4RLA 79 + 25 (AUTO RECLOSURE + CHECK SYNC RELAY)
4RLRB
4RTB
4RLC
79 + 25 (AUTO RECLOSURE + CHECK SYNC RELAY)
75 A 75 B 75 L
50 Z (LBB / BFR)
87 MAIN HIGH IMP
21 MAIN 1
CB TROUBLE ALARAM AND TRIP RELAYS
21 IMP DISTANCE
1-PH TRIP RELAYS -6 FOR 21M1 1-PH TRIP RELAYS -6 FOR 21M2
D/T CH-1 D/T CH-2 RECEIVE RECEIVE RELAYS RELAYS UNDER BREAKER VOLTAGE MULTIPLIC ATION RELAY RELAY
DC I & II
86 GR -A
HIGH SPEED
64 REF AUX TRIP RELAYS
TSR TC-1I
21 MAIN 2
DC-1I
86 GR -B
TSR TC-1
DC-1
86 GR -A
TSR TC-1I
DC-1I
DC I & II
CB TROUBLE ALARAM AND TRIP RELAYS
DC-1
TSR TC-1
50 Z (LBB / BFR)
59 L1 59 L2 O/V STG-1 O/V STG-1i 21 MAIN 1 21 MAIN 1i AUX RELYSAUX RELYS
87 HIGH TEED-1
87 LOW TEED-2
1-PH TRIP RELAYS -6 FOR 21M1
86 GR -B
1-PH TRIP RELAYS -6 FOR 21M2
D/T CH-1 RECEIVE RELAYS
D/T CH-2 RECEIVE RELAYS BREAKER MULTIPLICA TION RELAY
400KV ICT HV + IV CB RELAY & PROTN PANEL 4RTRA
4RTRC
4RTRB 75 A 75 B 75 L
75 A 75 B
50 Z (LBB / BFR)
50 Z (LBB / BFR)
87 MAIN 1 LOW IMP
CB TROUBLE ALARAM AND TRIP RELAYS TSR TC-1I
TSR TC-1
87 MAIN 2 HIGH IMP
86 GR -A
86 GR -B
INTER TRIP INTER TRIP RECEIVE RECEIVE RELAYS RELAYS
HIGH SPEED AUX TRIP RELAYS
67 HV
BREAKER MULTIPLICA TION RELAY
99T HV O/F
DC I & II
TSR TC-1I
86 GR -B
DC-1I
86 GR -A
DC I & II
DC-1
TSR TC-1
CB TROUBLE ALARAM AND TRIP RELAYS
67 IV
99T IV O/F
ICT / ATF TROUBLES ALARAM & TRIP FLAG RELAYS AUX RLYS FOR HV
AUX RLYS FOR IV
87 HIGH TEED-1
87 LOW TEED-2
AUX RLYS AUX RLYS INTER TRIP INTERTRIP RECEIVE RECEIVE BREAKER MULTIPLICA TION RELAY
400KV BUS REACTOR CB RELAY & PROTN PANEL 4RBRA
4RTB
4RBRB
79 + 25 (AUTO RECLOSURE + CHECK SYNC RELAY)
75 A 75 B
50 Z (LBB / BFR)
50 Z (LBB / BFR)
87 MAIN HIGH IMP
CB TROUBLE ALARAM AND TRIP RELAYS TSR TC-1I
21 IMP DISTANCE
64 REF BREAKER MULTIPLICA TION RELAY
TSR TC-1
DC I & II
86 GR -A
86 GR -B
DC-1I
86 GR -A
DC I & II
DC-1
TSR TC-1
CB TROUBLE ALARAM AND TRIP RELAYS
87 HIGH TEED-1
HIGH SPEED AUX TRIP RELAYS 87 LOW TEED-2
TSR TC-1I
1-PH TRIP RELAYS -6 FOR 21M1
86 GR -B
1-PH TRIP RELAYS -6 FOR 21M2
D/T CH-1 RECEIVE RELAYS
D/T CH-2 RECEIVE RELAYS BREAKER MULTIPLICA TION RELAY
400KV BUSBAR PROTECTION & COMMON CONTROL PANEL 4RBB2 BBM1 + 96 UNITS
4RBB3 BBM2 + 96 UNITS
CONFIGUARATION OF C & R PANEL BUSBAR PANEL 1. BCU-1 2. BCU-2 3. BUSBAR CENTRAL UNIT 4. BUS-1 ES CMR 5. BUS-2 ES CMR 6. DC-1 HEALTHY INDICATION 7. DC-2 HEALTHY INDICATION 8. BUSBAR PROT AUX RELAYS 9. CLOSING AUX RELAYS * IN CASE OF DUPLICATE PROTECTION 2 NOS BUSBAR CENTRAL UNITS ARE AVAILABLE
CB RELAY PANEL
LINE PROTECTION PANEL
1. BAY CONTROL UNIT 2. BREAKER FAILURE RELAY 3. AUTO RECLOSURE RELAY 4. CHECK SYNCHRONISING RELAY 5. CB ALARM RELAYS 6. CB TRIP CKT SUPERVISION RELAYS 7. 3-PH TRIP UNITS 86-GA, 86-GB & 96/50Z 8. 1-PH TRIP RELAYS M1, M2 - 1 2 Nos 9. DIRECT TRIP RECEIVE RELAYS 10. DC SUPERVISION RELAYS 11. U/V RELAY E/S I/L 12. CB EMERGENCY TNC SWITCH 13. CLOSING AUX RELAYS 14. ENERGY METER WITH TTB 15. PANEL INDICATING LABEL
1. MAIN-1 NUM. DIST. PROT 2. MAIN-2 NUM. DIST. PROT. 3. O/V STAGE-1 (EXT/IN BUILT) 4. O/V STAGE-2 (EXT/IN BUILT) 5. DISTURBANCE RECORDER(EXT/INBUILT) 6. DISTANCE TO FAULT (EXT/ INBUILT) 7. DC SUPERVISION RELAYS 8. TEED-1 PROTECTION 9. TEED-2 PROTECTION 10. STUB-1/2 PROTECTION (EXT/ INBUILT) 11. MAIN-1 CARRIER SEL.SWITCH 12. MAIN-2 CARRIER SEL.SWITCH 13. CARRIER RECEIVE RELAYS 14.PANEL INDICATING LABEL
CONFIGUARATION OF C & R PANEL TRANSFORMER PROTECTION PANEL
BUS REACTOR CB RELAY PANEL
LINE / BUS REACTOR PROTECTION PANEL
1. T/F DIFFERENTIAL PROTECTION-1 2. T/F DIFFERENTIAL PROTECTION-2 3. DIRECTIONAL O/L E/F RELAYS-HV 4. DIRECTIONAL O/L E/F RELAYS-LV 4. OVER FLUX PROTECTION-HV & LV 5. OVER LOAD PROTECTION 6. VOLTAGE SELECT RELAYS- HV & LV 7. FUSE FAILURE RELAY- HV & LV 8. AUX RELAYS FOR T/F TROBLES 9. CIRCUIT LABEL
1. BAY CONTROL UNIT 2. BREAKER FAILURE RELAY 3. CB ALARM RELAYS 4. CB TRIP CKT SUPERVISION RELAYS 5. 3-PH TRIP UNITS 86-GA, 86-GB & 96/50Z 6. DC SUPERVISION RELAYS 7. U/V RELAY E/S I/L 8. CB EMERGENCY TNC SWITCH 9. MFM WITH TTB 10. PANEL INDICATING LABEL
1. REACTOR DIFFERENTIAL PROT 2. REF PROTECTION RELAY 3. REACTOR IMPEDENCE PROTECTION 4. CVT SELECTION RELAYS 5. FLAG RELAYS 6. AUX RELAYS 7. TIMERS 8. CIRCUIT LABEL
IN ADDITION TO THE ABOVE THE FOLLOWING PANELS WILL BE AVAILABLE 1. CONTROL & RELAY PANEL B/C, B/S, TBC (AS & WHEN REQ) 2. COMMON CONTROL PANEL IS PART OF BUSBAR PANEL I. NOMINCLATURE FOR PANELS ARE NORMALLY MAIN CB C&RPANEL – RLA, TIE CB C&R PANEL – RTB, HV CB C&RPANEL – RTRA, LV CB C&R PANEL – RTRC, LINE PROTECTION PANEL – RLB, ICT PROTECTION PANEL – RTRB, LINE REACTOR PROTECTION PANEL – RLRC, BUS REACTOR PROTECTION PANEL – RBRA, BUS BAR PANEL – RBB,
400KV & 220KV BUSBAR & COMMON CONTROL PANEL 4RBB
2 RBB
BCU1
BCU1
BCU2
BCU2 BCU3
BUSBAR CENTRAL UNIT
DC -1 DC -2
89BB2 AE CMR
Bus Bar Aux relays
89BB1 AE CMR
89BB2 AE CMR
89BB1 AE CMR
BUSBAR CENTRAL UNIT Bus Bar Aux relays
DC -1 DC -2
¾ APTRANSCO IS FOLLOWING SINGLE BUS BAR PROTECTION. ¾ POWERGRID IS FOLLOWING DUPLICATE BUS BAR PROTECTION. ¾ ABB, AREVA, SIEMENS, TOSHIBA ARE HAVING DISTRIBUTED ARCHITECTURE. ¾ ABB, AREVA, GE, ER, ERL PHASE, SEL ARE HAVING CENTRALISED ARCHITECTURE. ¾ LBB IS THE PART OF BUSBAR IS LATEST CONCEPT. ¾ INCASE OF DISTRIBUTED ARCHITECTURE BAY/PERIPHERAL UNIT IS DATA AQUSITION UNIT AND COMMUNICATE TO CENTRAL UNIT THROUGH FIBER OPTIC CABLE. ¾ DICTRIBUTED/ CENTRALISED ARCHITECTURE - LBB IS INBUILT LOGIC. FINALLY THE CONCEPT AS FOLLOWS IN FUTURE FOR FEEDER : REDUNDANT DISTANCE PROTECTION. FOR ICT : REDUNDANT DIFFERENTIAL PROTECTION. FOR BUSBAR : REDUNDANT BUSBAR PROTECTION.
400KV LINE + REACTOR CB RELAY & PROTN PANEL 4RLA
4RLRC1/RBR3
4RLB
4RTB2
75A,B,L
LBB/ BU 50Z TRIP COIL
186 R1,Y1,B1 86 GR-A R2,Y2,B2
DC-1
286 86 R1,Y1,B1 GR-B R2,Y2,B2
DC-2
CB 1&2 TROUBLES HEALTHY & ALARMS LEDS
96 50Z
A/R+SC 79+25
64R
21L2
LBB/ BU 50Z TRIP COIL
CB 1&2 TROUBLES HEALTHY & ALARMS LEDS
Reactor Trouble Alarms & Trips
21R
59-1&2 CB PB
BAY2 BCU
186 86 R1,Y1,B1 GR-A R2,Y2,B2
DC-1
A/R+SC 79+25
87R
21L1
286 86 R1,Y1,B1 GR-B R2,Y2,B2
DC-2
BAY1 BCU
50 ZT
D/T-1 D/T-2 Receive Receive Relays Relays
99R
CB PB
400KV ICT CB RELAY & PROTN PANEL 4RTRA3
75A,B,L
LBB/ BU 50Z
186 86 R1,Y1,B1 GR-A R2,Y2,B2
DC-1
286 86 R1,Y1,B1 GR-B R2,Y2,B2
DC-2
50 ZT
CB PB
LV BAY BCU
LBB/ BU 50Z
LBB/ BU 50Z
87T2
TRIP COIL
CB 1&2 TROUBLES HEALTHY & ALARMS LEDS
86 GR-A 86 GR-B
DC-1
TRIP COIL
CB 1&2 TROUBLES HEALTHY & ALARMS LEDS
87T1
BAY3 BCU
DC-2
A/R+SC 79+25
75A,B
Transformer Trouble Alarms & Trips
67HV
Inter 96/ Trip 50Z Relays CB PB
MFM
67IV
TRIP COIL
CB 1&2 TROUBLES HEALTHY & ALARMS LEDS
86 GR-A 86 GR-B 96/ 50Z
99HV
99IV
DC-1
BAY2 BCU
4RTRC3
4RTRB3
DC-2
4RTB2
Inter Trip Relays CB PB
MFM
220KV FEEDER CB RELAY & PROTN PANEL 2RLA1
2RLB1
75A 75B BAY1 BCU
A/R+SC 79+25
21L1
LBB/ BU 50Z TRIP COIL
21L2
186 86 R1,Y1,B1 GR-A R2,Y2,B2
DC-1
286 86 R1,Y1,B1 GR-B R2,Y2,B2
DC-2
CB 1&2 TROUBLES HEALTHY & ALARMS LEDS
96 / 50Z
TTS CB PB
MFM
D/T-1 D/T-2 Receive Receive Relays Relays
220KV BC, TBC & BS CB RELAY & PROTN PANELS 2RTBC
TBC BCU
LBB/ BU 50Z TRIP COIL
96 50Z
186 86 R1,Y1,B1 GR-A R2,Y2,B2
DC-1
286 86 R1,Y1,B1 GR-B R2,Y2,B2
DC-2
86 GR-B
CB PB
50/51 A,B C,N
TRIP COIL
CB 1&2 TROUBLES HEALTHY & ALARMS LEDS
DC-1
86 GR-A
LBB/ BU 50Z
DC-2
CB 1&2 TROUBLES HEALTHY & ALARMS LEDS
A/R+SC 79+25
BS BCU
96 50Z
CB PB
LBB/ BU 50Z
LBB/ BU 50Z TRIP COIL
CB 1&2 TROUBLES HEALTHY & ALARMS LEDS
DC-1
BC BCU
LBB/ BU 50Z
2RBC
86 GR-A
DC-2
2RBC
86 GR-B 96 50Z
CB PB
50/51 A,B C,N
SUBSTATION AUXILIARIES & TERMINAL PANELS SSAUX For AC 415V System-1 BCU1 For DC 220V System-1 BCU3 For DC 48V System-1 BCU5 For Air condition System
For AC 415V System-2 BCU2 For DC 220V System-2 BCU4 For DC 48V System-2
Base System Alarm Unit
BCU6 For Fire Fighting System
BCU7
BCU8
For Diesel Generator System
For fire & Smoke Detector
BCU9
BCU10 COM581
Alarm Unit
Main Server ABB Network Partner AG
COM581
Redunt Server ABB Network Partner AG
COM581
C E
C E
Communication Gateway Network Partner
SSLTA 88 SERVICE RS232
ABB Network Partner AG
Hot Standby
SRS485M
SRS485M
RS485
RS485
SREDU/M
1MRSC60029 1MRSC60028 1MRSC60028 1MRSC60028 1MRSC60028 1MRSC60028 1MRSC60028
Ethernet Switch
Router to ALDC/SLDC Network Partner
SSLTA 88 SERVICE RS232
SRS485M
SRS485M
RS485
RS485
SREDU/M
1MRSC60029 1MRSC60028 1MRSC60028 1MRSC60028 1MRSC60028 1MRSC60028 1MRSC60028
Ethernet Switch
C E
Surveillance system
Line Printer for Alarm / Event
Metering Values DOT Matrix Printer
SUBSTATION AUTOMATION
2 Ports for RCC & 2 Ports for ALDC/SLDC COMMUNICATION GATEWAY TO RCC & ALDC RCC LDC
Base System
Service Modem
DM Printer For 15 Min Metering & Trends
Engineering & DR work Station LAPTOP
Base System
Alarm Unit
Alarm Unit
Hardcopy Printer + MFD
Auxiliary Alarm Annunciation
Alarm/Event Line Printer
GPS Meinberg
Printer Server
POWER V1 OVP
ACQR LOCK
GPS 166 SATELLITE CONTROLLED CLOCK
NORMAL OPERATION WED 11.12.1996 MEZ 11.42.25 SV 24 > SYN
MENU CLR NEXT INC ACK MEINBERG
Ethernet (TCP/IP) Network Partner
Rugged Com/Equivalent Ethernet Switches forming ‘Redundant Managed switched Ethernet LAN on fiber optic medium Interbay bus on IEC61850 Communication Gate way with hot standby for RCC and SLDC’ For Control and Protection Relays.
SSLTA 88SRS485MSRS485MSREDU/M SERVICE RS232 RS485
RS485
1MRSC60029 1MRSC60028 1MRSC60028 1MRSC60028 1MRSC60028 1MRSC60028 1MRSC60028
M
M
M
LOCAL
?
REMOTE
SET OPERATION
DIGITAL PLCC/ OLTE SYSTEM
DIGITAL PLCC/ OLTE SYSTEM
ABB Network Partner AG
9 10 11 12 13 14 15 16
9 10 11 12 13 14 15 16
DIGITAL PLCC/ OLTE SYSTEM
9 10 11 12 13 14 15 16
C E M
M
M
LOCAL
?
REMOTE
M
SET OPERATION
CARR PROT SYSTEM
ABB Network Partner AG
1 2 3 4 5 6 7 8
9 10 11 12 13 14 15 16
LOCAL REMOTE
M
SET OPERATION
EM
M
M
LOCAL
?
CARR PROT SYSTEM
REMOTE
1 2 3 4 5 6 7 8
C E
9 10 11 12 13 14 15 16
C E
M
M
?
REL531
9 10 11 12 13 14 15 16
C E
CARR PROT SYSTEM
9 10 11 12 13 14 15 16
HYD RAN
1 2 3 4 5 6 7 8
9 10 11 12 13 14 15 16
1 2 3 4 5 6 7 8
9 10 11 12 13 14 15 16
C E
SET OPERATION
CARR PROT SYSTEM
ABB Network Partner AG
REL531
9 10 11 12 13 14 15 16
9 10 11 12 13 14 15 16
CARR PROT SYSTEM
CARR PROT SYSTEM
9 10 11 12 13 14 15 16
9 10 11 12 13 14 15 16
EM
HYD RAN
EM
HYD RAN
EM
AVR
EM
AVR
EM
OTH
EM
OTH
C E C E
M
M
M
LOCAL
?
REMOTE
EM
AVR
EM
OTH
SET
1 2 3 4 5 6 7 8
9 10 11 12 13 14 15 16
1 2 3 4 5 6 7 8
OPERATION
C E
M
M
M
?
LOCAL REMOTE
9 10 11 12 13 14 15 16
C E
ABB Network PartnerREL511 AG
SET OPERATION
C E
Network Partner
SSLTA 88SRS485MSRS485MSREDU/M SERVICE RS232 RS485
RS485
1MRSC60029 1MRSC60028 1MRSC60028 1MRSC60028 1MRSC60028 1MRSC60028 1MRSC60028
TRIP LOGICS OF ONE AND HALF CIRCUIT BREAKER SCHEME PREPARED BY GOPALA KRISHNA PALEPU ADE/MRT(PROTECTION)
GROUP-A & GROUP-B TRIPPINGS FOR 400KV STATIONS THERE SHALL BE TWO SEPARATE BATTERY SYSTEMS AVAILABLE FOR PROTECTION, CONTROL & TRIPPING/CLOSING OPERATIONS. TO OBTAIN REDUNDENCY AND TO BE ABLE TO TAKE PROTECTION OUT FOR MAINTANENCE, WHILE EQUIPMENT IS IN SERVICE, THE RELAYS ARE ELECTRICALLY AND PHYSICALLY SEGREGATED IN TO TWO GROUPS. GROUPING IS DONE TO THE EXTENT POSSIBLE IN SUCH A WAY THAT EACH GROUP CAN INDEPENDENTLY CARRYOUT PROTECTIVE FUNCTIONS WITH NEAR EQUAL REDUNDENCY. INTER CONNECTION OF THESE TWO GROUPS SHALL NOT BE GENERALLY BE ATTEMPTED. DISTRIBUTION OF DC SUPPLY SHALL BE DONE BAY WISE TO FEED THE FOLLOWING 1. PROTECTION 2. CB CONTROL 3. ISOLATOR / EARTH SWITCH CONTROL 4. ANNUNCIATION / INDICATION
LINE PROTECTION
TRANSFORMER PROTECTION
REACTOR PROTECTION
GROUP-A
GROUP-A
GROUP-A
MAIN-1 PROTECTION M1 BUILT IN FUNCTIONS TEED-1 PROTECTION OVER VOLTAGE STAGE-1 PROT DIRECT TRIP CHANNEL-1 RECEIVED
T/F DIFFERENTIAL RELAY T/F HV BACKUP RELAY T/F IMP / 21T RELAY T/F HV OVERFLUX RELAY OIL TEMP HIGH TRIP PRESURE RELIEF TRIP TERITIARY DELTA WNDG NDR PROT
REACTOR DIFFERENTIAL RELAY REACTOR BACKUP / 21R RELAY OIL TEMP HIGH TRIP PRESURE RELIEF TRIP
GROUP-B MAIN-2 PROTCTION M2 BUILT IN FUNCTIONS TEED-2 PROTECTION OVER VOLTAGE STAGE-2 PROT LBB/BFR RELAY DIRECT TRIP CHANNEL-2 RECEIVED
GROUP-B T/F REF / HIGH Z DIFF RELAY BUCHHOLZ TRIP T/F LV BACKUP RELAY T/F NEUTRAL CURRENT / 51 O/C RLY T/F LV OVERFLUX RELAY OVER LOAD PROT (ALARM ONLY) OLTC BUCHHOLZ TRIP WINDING TEMP HIGH TRIP LOW/ HIGH OIL LEVEL TRIP
GROUP-B REACTOR REF RELAY BUCHHOLZ TRIP WINDING TEMP HIGH TRIP LOW/ HIGH OIL LEVEL TRIP FIRE PROTECTION TRIP
SOTF, PSB
MAIN-1/MAIN-2 CARRIER SEND
X
X
X
X
X
X
X
INITIATE 400KV B/B PROT
X
DIRECT TRIP CARRIER SEND
INITIATE SCADA (DR & SOE)
X
INITIATE ALARM
X
X
BLOCK T_CB A/R RELAY
1-PH
X
BLOCK M_CB A/R RELAY
B
START T_CB A/R RELAY
21 M2
X
START M_CB A/R RELAY
MAIN-2 PROTECTION
INITIATE T_CB 1PH TRIP UNIT GR-B INITIATE T_CB 3PH TRIP UNIT GR-B
X
INITIATE T_CB 3PH TRIP UNIT GR-A
1-PH
INITIATE T_CB 1PH TRIP UNIT GR-A
OUTPUT
A
INITIATE M_CB 3PH TRIP UNIT GR-B
GROUP
21 M1
INITIATE M_CB 1PH TRIP UNIT GR-B
SYMBOL
MAIN-1 PROTECTION
INITIATE M_CB 3PH TRIP UNIT GR-A
PROTECTION RELAY
INITIATE M_CB 1PH TRIP UNIT GR-A
MAIN CB FOR LINE (1-52CB)TRIPPING LOGICS
IN BUILT FUNCTIONS OF DISTANCE SCHEME
OVER VOLTAGE STAGE-1 & STAGE-2 (BUILT – IN 21 M1)
59 L1 & L2
A
3-PH
OVER VOLTAGE STAGE-1 & STAGE-2 (BUILT – IN 21 M2)
59 L1 & L2
B
3-PH
STUB, TOC, BOC, TEF, DEF, (BUILT- IN 21M1)
A
3-PH
STUB, TOC, BOC, TEF, DEF, (BUILT- IN 21M2)
B
3-PH
TEED PROT-1
87T HZ
A
3-PH
TEED PROT-2
87T LZ
B
3-PH
DIRECT TRIP CH-1 RECD
A
3-PH
DIRECT TRIP CH-2 RECD
B
3-PH
M_CB BFR / LBB PROT
B
3-PH
T_CB BFR / LBB PROT
B
3-PH
X
X
X
X
X
X
X X
X X
X X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X X
X X
X
X X
X
INITIATE T_CB A/R PRIORITY
INITIATE ALARM
TO SCADA (DR & SOE)
1-PH & 3PH
X
X
X
X
SYNC CHECK RELAY (BUILT IN 21M1 & 21M2)
25 SYNC
A&B
3-PH
X
X
X
X
1-PH TRIP UNIT GR-A
186
A
1-PH
X
X
X
3-PH TRIP UNIT GR-A
86 GR A
A
3-PH
X
X
X
X
X
1-PH TRIP UNIT GR-B
286
B
1-PH
X
X
X
3-PH TRIP UNIT GR-B
86 GR B
B
3-PH
X
X
X
X
X
TRIP SIGNAL FROM 400KV BUSBAR PROTECTION
96 BB
3-PH
X
X
X
LINE UNDER VOLTAGE RELAY
27 UV
89LE C LOSE PERMISSION
OUTPUT
A&B
START LBB/BFR M_C B
GROUP
79 A/R
INITIATE M_C B TRIP COIL-2
SYMBOL
AUTO RECLOSURE RELAY (BUILT IN 21M1 & 21M2)
INITIATE M_C B TRIP COIL-1
PROTECTION RELAY
CLOSE MAIN CB
MAIN CB FOR LINE (1-52 CB) TRIPPING LOGICS
X
PROTECTION RELAY SYMBOL GROUP OUTPUT
T_CB BFR / LBB PROT 50 ZT B 3-PH
M_CB BFR / LBB PROT (152 CB & 352 CB) 50 Z B 3-PH
AUTO RECLOSURE RELAY 79 A/R A & B 1-PH & 3-PH
SYNC CHECK RELAY 25 3-PH
1-PH TRIP UNIT GR-A 186 A 1-PH X X
3-PH TRIP UNIT GR-A 86A A 3-PH X X
1-PH TRIP UNIT GR-B 286 B 1-PH X X
3-PH TRIP UNIT GR-B 86B B 3-PH X X
DIRECT TRIP CH-1 RECD A 3-PH
DIRECT TRIP CH-2 RECD B 3-PH X
X X
INITIATE SCADA (DR & SOE)
X
INITIATE ALARM
X
DIRECT TRIP CARRIER SEND
252 START LBB/BFR OF T_CB 252 CLOSE T_CB
252 INITIATE T_CB TRIPCOIL-1 & COIL-2
352 INITIATE M_CB 1PH TRIP UNIT GR-B 352 INITIATE M_CB 3PH TRIP UNIT GR-B
352 INITIATE M_CB 1PH TRIP UNIT GR-A 352 INITIATE M_CB 3PH TRIP UNIT GR-A
252 INITIATE T_CB 1PH TRIP UNIT GR-B 252 INITIATE T_CB 3PH TRIP UNIT GR-B
252 INITIATE T_CB 3PH TRIP UNIT GR-A
252 INITIATE T_CB 1PH TRIP UNIT GR-A
152 INITIATE M_CB 1PH TRIP UNIT GR-B 152 INITIATE M_CB 3PH TRIP UNIT GR-B
152 INITIATE M_CB 1PH TRIP UNIT GR-A 152 INITIATE M_CB 3PH TRIP UNIT GR-A
TIE CB TRIPPING LOGICS
X X X
X X X
X X X
X X X
X X
X X
INITIATE SCADA ( SOE)
HV BACKUP PROTECTION
67 ABCN
A
3-PH
X
X
X
X
X
X
HV OVER FLUX PROT
99T HV
A
3-PH
X
X
X
X
X
X
OVER LOAD RELAY
51 O/L
A
3-PH
X
X
X
X
X
X
HV PROT TRIP UNIT GR-A & B
86 GR-A/B
A/B
3-PH
X
X
X
REF PROTECTION
64T(HZ)
B
3-PH
X
X
X
TEED PROT-1 / 2
87T HZ/LZ
A/B
3-PH
X
X
X
X
STUB PROT
50 STUB
A
3-PH
X
X
X
X
AT/F TROUBLE TRIP HV & LV
86 GR-A/B
A/B
3-PH
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X X
X X
X
X
X X
X
X
X
X
X
X X
X
X
X
X
X
INITIATE LV_CBTRIP COIL-2
X
INITIATE LV_CB TRIP COIL-1
X
START LV_CB LBB/BFR RELAY
X
START M_CB LBB/BFR RELAY
X
INITIATE 220KV B/B PROT
X
INITIATE 400KV B/B PROT
X
INTER TRIP CIRCUIT HV & LV
3-PH
INITIATE M_CBTRIP COIL-2
A
INITIATE M_CB TRIP COIL-1
INITIATE ALARM
INITIATE LV_CB 3PH TRIP UNIT GR-B
INITIATE M_CB 3PH TRIP UNIT GR-A
INITIATE LV_CB 3PH TRIP UNIT GR-A
OUTPUT
87T(LZ)
INITIATE T_CB 3PH TRIP UNIT GR-B
GROUP
DIFFERENTIAL RELAY
INITIATE T_CB 3PH TRIP UNIT GR-A
PROTECTION RELAY
SYMBOL
INITIATE M_CB 3PH TRIP UNIT GR-B
MAIN CB FOR AT/F (3-52CB)TRIPPING LOGICS
AT/F TROUBLE ALRM M_CB BFR / LBB PROT
50Z
B
3-PH
X
T_CB BFR / LBB PROT
50ZT
B
3-PH
X
LV_CB BFR / LBB PROT
50Z
B
3-PH
X
400KV B/B PROT
87 BB
96
3-PH
X
X
220KV B/B PROT
87 BB
96
3-PH
X
X
LV BACKUP PROTECTION
67 ABCN
B
3-PH
X
X
X
X
X
X
LV OVER FLUX PROT
99T LV
B
3-PH
X
X
X
X
X
X
TERI NEUTRAL DISP PROT
151N
A
3-PH
X
X
X
LV PROT TRIP UNIT GR-A & B
86 GR-A/B
A/B
3-PH
X
X
X
X
X
X
X
X
X
X
X X
X
X
X
X
X
X
X
PROTECTION TRIP SCHEME ABB Network Partner AG ABB Network Partner AG
REL531
REL531
87 T LZ
21 MAIN 1
86-A MTR/ HSTR
C
86-A MTR/ HSTR
C
E
E
TRIP COIL-1 1-52CB TRIP COIL-2 BUS-1
ABB Network Partner AG
TRIP COIL-1 2-52CB
TRIP COIL-1 3-52CB
TRIP COIL-2
TRIP COIL-2 BUS-2 ABB Network Partner AG
REC 316*4
21 MAIN 2
86-B ABB REL521 MTR/ MAIN-1 HSTR
1
9
2 3 4 5 6
10 11 12 13 14
7 8
15 16
C
E
86-A MTR/ HSTR
1
86-B MTR/ HSTR
REC 316*4
87 T HZ 9
2 3 4 5 6
10 11 12 13 14
7 8
15 16
C
86-B MTR/ HSTR
E
86-A : GROUP-A MASTER TRIP RELAY / HIGH SPEED TRIP RELAY 86-B : GROUP-B MASTER TRIP RELAY / HIGH SPEED TRIP RELAY
MAIN-1/ MAIN-2 ZONE-1 & SINGLE PHASE FAULT INITIATE MAIN CB GR-A 1-PH TRIP UNIT ( INTURN IT WILL TRIP 1-POLE )
REL 521 ACTIVE
START
TRIP
INITIATE TIE CB GR-A 1-PH TRIP UNIT ( INTURN IT WILL TRIP 1-POLE ) START MAIN CB AUTO RECLOSURE START TIE CB AUTO RECLOSURE
DISPLAY
C
E
REL 316 ACTIVE
START
TRIP
CARRIER SEND INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME) TO DISTURBANCE RECORDER TO EVENT RECORDER ( SOE/ SCADA ) TO LBB/BFR INITIATION
INITIATE MAIN CB GR-B 1-PH TRIP UNIT ( INTURN IT WILL TRIP 1-POLE ) INITIATE TIE CB GR-B 1-PH TRIP UNIT ( INTURN IT WILL TRIP 1-POLE ) START MAIN CB AUTO RECLOSURE START TIE CB AUTO RECLOSURE
DISPLAY
CARRIER SEND INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES)
C
INITIATE ALARM (ANNUNCIATION COME) TO DISTURBANCE RECORDER
E
TO EVENT RECORDER ( SOE/ SCADA ) TO LBB/BFR INITIATION
AUTO RECLOSURE
¾
CONDITIONS REQUIRED FOR A/R OPERATION
1. 2. 3.
7. 8. 9.
CB CLOSE CONDITION. TIME LAPSED MORE THAN RECLAIM TIME. OPERATING PRESSURE OF CB SUITABLE FOR AUTORECLOSURE OPERATION. DC SUPPLY TO AUTORECLOSURE SHOULD BE AVAILABLE. PREPARE 3-PH TRIP RELAY SHOULD BE RELEASED CONDITION. NO BLOCKING SIGNAL TO AUTORECLOSURE RELAY. POLE DISTURBANCE RELAY TIME SHOULD BE MORE THAN TWICE OF DEAD TIME OF AUTO RECLOSURE. CARRIER FAIL SIGNAL SHOULD NOT COME AT BOTH ENDS. CARRIER SWITCH SHOULD BE IN SERVICE CONDITION. SINGLE PHASE & ZONE-1 FAULT ONLY.
¾
AUTO RECLOSURE OPERATION
1. 2. 3. 4.
TRIP MAIN CB SINGLE POLE. TRIP TIE CB SINGLE POLE. CLOSE MAIN CB AFTER DEAD TIME. IF A/R SUCCESS FOR MAIN CB THEN AFTER SUPPLEMENTARY TIME DELAY CLOSE TIE CB.(NORMALLY SUPPLEMENTARY TIME DELAY IS DEAD TIME) IF A/R UNSUCCESS THEN TRIP MAIN & TIE CBs. IF MAIN CB OPEN CONDITION, THEN NO SUPPLEMENTARY DELAY TIME FOR TIE A/R. IT WILL OPERATE ITs OWN DEAD TIME.
4. 5. 6. 7.
5. 6.
MAIN-1/ MAIN-2 ZONE-1 & TWO / THREE PHASE FAULT INITIATE MAIN CB GR-A 1-PH TRIP UNITS ( INTURN IT WILL TRIP 3-POLES )
REL 521 ACTIVE
START
TRIP
INITIATE TIE CB GR-A 1-PH TRIP UNITS ( INTURN IT WILL TRIP 3-POLES ) BLOCK MAIN CB AUTO RECLOSURE BLOCK TIE CB AUTO RECLOSURE
DISPLAY
C
E
REL 316 ACTIVE
START
TRIP
CARRIER SEND INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME) TO DISTURBANCE RECORDER TO EVENT RECORDER ( SOE/ SCADA ) TO LBB/BFR INITIATION
INITIATE MAIN CB GR-B 1-PH TRIP UNITS ( INTURN IT WILL TRIP 3-POLES ) INITIATE TIE CB GR-B 1-PH TRIP UNITS ( INTURN IT WILL TRIP 3-POLES ) BLOCK MAIN CB AUTO RECLOSURE BLOCK TIE CB AUTO RECLOSURE
DISPLAY
CARRIER SEND INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES)
C
INITIATE ALARM (ANNUNCIATION COME) TO DISTURBANCE RECORDER
E
TO EVENT RECORDER ( SOE/ SCADA ) TO LBB/BFR INITIATION
MAIN-1/ MAIN-2 ZONE-2 & 1 / 2 / 3 PHASE FAULT INITIATE MAIN CB GR-A 1-PH TRIP UNITS ( INTURN IT WILL TRIP 3-POLES )
REL 521
CARRIER SIGNAL ACTIVE START RECEIVED & ZONE-2 STARTER IS PICKUP CONDITION
TRIP
C
E
REL 316 ACTIVE
START
BLOCK MAIN CB AUTO RECLOSURE BLOCK TIE CB AUTO RECLOSURE
DISPLAY
CARRIER SIGNAL RECEIVED & ZONE-2 STARTER IS PICKUP CONDITION
INITIATE TIE CB GR-A 1-PH TRIP UNITS ( INTURN IT WILL TRIP 3-POLES )
TRIP
TO LBB/BFR INITIATION INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION CAME) TO DISTURBANCE RECORDER TO EVENT RECORDER ( SOE/ SCADA )
INITIATE MAIN CB GR-B 1-PH TRIP UNITS ( INTURN IT WILL TRIP 3-POLES ) INITIATE TIE CB GR-B 1-PH TRIP UNITS ( INTURN IT WILL TRIP 3-POLES ) BLOCK MAIN CB AUTO RECLOSURE BLOCK TIE CB AUTO RECLOSURE
DISPLAY
CARRIER SEND ( IF PUTT OR2 SCHEME SELECTED ) INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES)
C
INITIATE ALARM (ANNUNCIATION COME) TO DISTURBANCE RECORDER
E
TO EVENT RECORDER ( SOE/ SCADA ) TO LBB/BFR INITIATION
MAIN-1/ MAIN-2 ZONE- 3/4/5 & 1 / 2 / 3 PHASE FAULT INITIATE MAIN CB GR-A 1-PH TRIP UNITS ( INTURN IT WILL TRIP 3-POLES )
REL 521 ACTIVE
START
TRIP
INITIATE TIE CB GR-A 1-PH TRIP UNITS ( INTURN IT WILL TRIP 3-POLES ) BLOCK MAIN CB AUTO RECLOSURE BLOCK TIE CB AUTO RECLOSURE
DISPLAY
C
E
REL 316 ACTIVE
START
TRIP
TO LBB/BFR INITIATION INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION CAME) TO DISTURBANCE RECORDER TO EVENT RECORDER ( SOE/ SCADA )
INITIATE MAIN CB GR-B 1-PH TRIP UNITS ( INTURN IT WILL TRIP 3-POLES ) INITIATE TIE CB GR-B 1-PH TRIP UNITS ( INTURN IT WILL TRIP 3-POLES ) BLOCK MAIN CB AUTO RECLOSURE BLOCK TIE CB AUTO RECLOSURE
DISPLAY
TO LBB/BFR INITIATION INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES)
C
INITIATE ALARM (ANNUNCIATION COME) TO DISTURBANCE RECORDER
E
TO EVENT RECORDER ( SOE/ SCADA )
DISTANCE SCHEME TRIPPING OUTPUTS TIE CB
MAIN CB CO
CO
186 R
186 R
REL 521
TO TRIP COIL-1 TO TRIP COIL-2
ACTIVE
START
TO TRIP COIL-1 TO TRIP COIL-2
TRIP
186 Y
186 Y
DISPLAY
TO TRIP COIL-1 TO TRIP COIL-2
TO TRIP COIL-1 TO TRIP COIL-2
C 186 B
186 B
E
TO TRIP COIL-1 TO TRIP COIL-2
TO TRIP COIL-1 TO TRIP COIL-2 CO
CO
286 R
286 R
REL 316
TO TRIP COIL-1 TO TRIP COIL-2
ACTIVE
START
TRIP
286 Y
286 Y
DISPLAY
TO TRIP COIL-1 TO TRIP COIL-2 286 B TO TRIP COIL-1 TO TRIP COIL-2
TO TRIP COIL-1 TO TRIP COIL-2
TO TRIP COIL-1 TO TRIP COIL-2
C 286 B
E TO TRIP COIL-1 TO TRIP COIL-2
MAIN LBB
INITIATION 1-PH TRIP RELAYS OF MAIN-1 PROTECTION
INITIATE BUSBAR PROTECTION ( INTURN IT WILL TRIP CONNECTED BUS CBs)
RAICA ACTIVE
START
TRIP
DIRECT TRANSFER TRIP-2 CARRIER SEND TO OTHER END
DISPLAY 86-GR-A MASTER TRIP RELAY
CLOSE INTERLOCK OF MAIN CB & TIE CB INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES)
C
86-GR-B MASTER TRIP RELAY
INITIATE ALARM (ANNUNCIATION COME) TO DISTURBANCE RECORDER
E
96 BB BUSBAR RELAY
TO EVENT RECORDER ( SOE/ SCADA )
TIE LBB
INITIATION
1-PH TRIP RELAYS OF MAIN-2 PROTECTION OF LINE-1 (BAY1) & LINE-2 (BAY 3)
BLOCK MAIN CB & TIE CB AUTO RECLOSURE DIRECT TRANSFER TRIP-1 CARRIER SEND TO OTHER END
1-PH TRIP RELAYS OF MAIN-2 PROTECTION
1-PH TRIP RELAYS OF MAIN-1 PROTECTION OF LINE-1(BAY1) & LINE-2 (BAY3)
INITIATE TIE CB 86-GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES )
INITIATE MAIN CB 86-GR-B 3-PH TRIP UNIT (TRIP BAY1 CB 3-POLES )
RAICA ACTIVE
START
TRIP
INITIATE MAIN CB 86-GR-B 3-PH TRIP UNIT ( TRIP BAY3 CB 3-POLES ) BLOCK MAIN CB OF BAY1 & BAY3 AUTO RECLOSURE BLOCK TIE CB AUTO RECLOSURE CLOSE INTERLOCK OF MAIN CB OF BAY1 & BAY 3 CLOSE INTERLOCK OF TIE CB
DISPLAY
DIRECT TRANSFER TRIP-1 CARRIER SEND TO BAY1 & BAY3 LINES DIRECT TRANSFER TRIP-2 CARRIER SEND TO BAY1 & BAY3 LINES
86-GR-A MASTER TRIP RELAY
C 86-GR-B MASTER TRIP RELAY
INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME) TO DISTURBANCE RECORDER (BAY1 & BAY3)
E
TO EVENT RECORDER ( SOE/ SCADA )
BUS BAR PROTECTION INITIATE ALL CBs TRIP UNITS CONNECTED TO THIS BUS AND OPERATE. TO TRIP COIL-1 CONCERNED BAY CB
REB 500 ACTIVE
START
TRIP
TO TRIP COIL-2 CONCERNED BAY CB TO CLOSE CIRCUIT INTERLOCK OF CONCERN CB DIRECT TRIP SEND CHANNEL-1 TO OTHER END DIRECT TRIP SEND CHANNEL-2 TO OTHER END
DISPLAY
TO LBB/BFR INITIATION FROM LBB/BFR TO BUS BAR TRIPPING
C
TO DISTURBANCE RECORDER OF MAIN-1 TO DISTURBANCE RECORDER OF MAIN-2
E
TO EVENT RECORDER ( SOE/ SCADA ) INITIATE ALARM (ANNUNCIATION COME)
INITIATE ALL CBs TRIP UNITS CONNECTED TO THIS BUS AND OPERATE. TO TRIP COIL-1 CONCERNED BAY CB
REB 670 ACTIVE
START
TRIP
TO TRIP COIL-2 CONCERNED BAY CB TO CLOSE CIRCUIT INTERLOCK OF CONCERN CB DIRECT TRIP SEND CHANNEL-1 TO OTHER END DIRECT TRIP SEND CHANNEL-2 TO OTHER END
DISPLAY
TO LBB/BFR INITIATION FROM LBB/BFR TO BUS BAR TRIPPING
C
TO DISTURBANCE RECORDER OF MAIN-1 TO DISTURBANCE RECORDER OF MAIN-2
E
TO EVENT RECORDER ( SOE/ SCADA ) INITIATE ALARM (ANNUNCIATION COME)
STUB PROTECTION INITIATE MAIN CB 86-GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES )
REL 521 ACTIVE
LINE /AT/F ISOLATOR OPENS
START
TRIP
BLOCK MAIN CB AUTO RECLOSURE BLOCK TIE CB AUTO RECLOSURE
DISPLAY
C
E
REL 316 ACTIVE
LINE /AT/F ISOLATOR OPENS
INITIATE TIE CB 86-GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES )
START
TRIP
CLOSE INTERLOCK OF MAIN CB CLOSE INTERLOCK OF TIE CB INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME) TO DISTURBANCE RECORDER TO EVENT RECORDER ( SOE/ SCADA )
INITIATE MAIN CB 86-GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE TIE CB 86-GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) BLOCK MAIN CB AUTO RECLOSURE BLOCK TIE CB AUTO RECLOSURE
DISPLAY
CLOSE INTERLOCK OF MAIN CB CLOSE INTERLOCK OF TIE CB
C
INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME)
E
TO DISTURBANCE RECORDER TO EVENT RECORDER ( SOE/ SCADA )
TEED PROTECTION INITIATE MAIN CB 86-GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES )
RET 521
87 T1 (HZ)
ACTIVE
START
TRIP
DISPLAY
E
RET 670
(LZ)
BLOCK MAIN CB AUTO RECLOSURE BLOCK TIE CB AUTO RECLOSURE
C
87 T2
INITIATE TIE CB 86-GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES )
ACTIVE
START
TRIP
CLOSE INTERLOCK OF MAIN CB CLOSE INTERLOCK OF TIE CB INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME) TO DISTURBANCE RECORDER TO EVENT RECORDER ( SOE/ SCADA )
INITIATE MAIN CB 86-GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE TIE CB 86-GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) BLOCK MAIN CB AUTO RECLOSURE BLOCK TIE CB AUTO RECLOSURE
DISPLAY
CLOSE INTERLOCK OF MAIN CB CLOSE INTERLOCK OF TIE CB
C
INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME)
E
TO DISTURBANCE RECORDER TO EVENT RECORDER ( SOE/ SCADA )
MAIN-1/ MAIN-2 OVER VOLTAGE STAGE-1 INITIATE MAIN CB 86-GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) 110% OF V 4 SECS FOR FEEDER-1 5 SECS FOR FEEDER-2
REL 521 ACTIVE
START
TRIP
INITIATE TIE CB 86-GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) BLOCK MAIN CB & TIE CB AUTO RECLOSURE DIRECT TRANSFER TRIP-1 CARRIER SEND TO OTHER END
DISPLAY
C
E
REL 316
110% OF V ACTIVE START 4 SECS FOR FEEDER-1 5 SECS FOR FEEDER-2
TRIP
DIRECT TRANSFER TRIP-2 CARRIER SEND TO OTHER END CLOSE INTERLOCK OF MAIN CB & TIE CB INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME) TO DISTURBANCE RECORDER TO EVENT RECORDER ( SOE/ SCADA )
INITIATE MAIN CB 86-GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE TIE CB 86-GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) BLOCK MAIN CB & TIE CB AUTO RECLOSURE DIRECT TRANSFER TRIP-1 CARRIER SEND TO OTHER END
DISPLAY
DIRECT TRANSFER TRIP-2 CARRIER SEND TO OTHER END CLOSE INTERLOCK OF MAIN CB & TIE CB
C
INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME)
E
TO DISTURBANCE RECORDER TO EVENT RECORDER ( SOE/ SCADA )
OVER VOLTAGE STAGE-2 INITIATE MAIN CB 86-GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES )
REU 521 ACTIVE
START
TRIP
INITIATE TIE CB 86-GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) BLOCK MAIN CB & TIE CB AUTO RECLOSURE DIRECT TRANSFER TRIP-1 CARRIER SEND TO OTHER END
120% OF V 20m SECS
DISPLAY
C
E
DIRECT TRANSFER TRIP-2 CARRIER SEND TO OTHER END CLOSE INTERLOCK OF MAIN CB & TIE CB INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME) TO DISTURBANCE RECORDER (MAIN-1 & MAIN-2) TO EVENT RECORDER ( SOE/ SCADA )
UNDER VOLTAGE RELAY REU 521 ACTIVE
1O% OF V
START
TRIP
DISPLAY
C
E
LINE EARTH SWITCH CLOSE PERMISSION ONLY.
CARRIER TRIPPING SCHEMES(TELEPROTECTION) DETAILS
PERMISSIVE TRIPPING
CHANNEL-1 SEND
MAIN-1 PROTECTION : IT SENDS SIGNAL PARALLEL VIA PLCC PROTECTION COUPLER PANEL-1 AS A MAIN CHANNEL & PLCC PROTECTION COUPLER PANEL-2 AS A ALTERNATE CHANNEL..
CHANNEL-2 SEND
DIRECT TRIPPING
HERE CHANNEL-1 & CHANNEL-2 SIGNALS ARE MAIN & ALTERNATE CHANNEL 1. TIE CB OPEN CONDITION + MAIN CB REMOTE HAND TRIP GIVEN. 2. MAIN CB OPEN CONDITION + TIE CB REMOTE HAND TRIP GIVEN. 3. TIE CB OPEN CONDITION + 87 BUSBAR-1 OPERATED. 4. MAIN CB OPEN CONDITION + 87 BUSBAR-2 OPERATED (FOR HALF DIA ONLY). MAIN-2 PROTECTION : 5. MAIN CB 50 LBB/BFR OPERATED. 6. TIE CB 50 LBB/BFR OPERATED. IT SENDS SIGNAL PARALLEL VIA PLCC PROTECTION COUPLER PANEL-2 AS A MAIN CHANNEL & 7. 59L1 OVER VOLTAGE STAGE-1 OPERATED. PLCC PROTECTION COUPLER PANEL-1 AS A ALTERNATE 8. 59L2 OVER VOLTAGE STAGE-2 OPERATED. 9. 87 TEED-1 PROTECTION OPERATED CHANNEL. 10. 87 TEED-2 PROTECTION OPERATED
CHANNEL-1 RECEIVE
MAIN-1 PROTECTION : 1. TO 86-A MASTER TRIP RELAY (HIGH SPEED TRIP RELAY) FOR MAIN CB. IT RECEIVES SIGNAL PARALLEL VIA 2. TO 86-A MASTER TRIP RELAY (HIGH SPEED TRIP RELAY) FOR TIE CB. PLCC PROTECTION COUPLER PANEL-1 AS A MAIN CHANNEL & PLCC PROTECTION COUPLER PANEL-2 AS A ALTERNATE CHANNEL.
CHANNEL-2 RECEIVE
MAIN-2 PROTECTION : 1. TO 86-B MASTER TRIP RELAY (HIGH SPEED TRIP RELAY) FOR MAIN CB. IT RECEIVES SIGNAL PARALLEL VIA PLCC PROTECTION COUPLER PANEL-2 AS A MAIN CHANNEL & 2. TO 86-B MASTER TRIP RELAY (HIGH SPEED TRIP RELAY) FOR TIE CB. PLCC PROTECTION COUPLER PANEL-1 AS A ALTERNATE CHANNEL.
CARRIER TRIPPING SCHEMES(TELEPROTECTION) 21 M1 – REL 521 ABB Network Partner AG
REL531
CARRIER PROTECTION PANEL-1
CARRIER PROTECTION PANEL-1
PT SEND
PT SEND
21 M1 – REL 521 ABB Network Partner AG
REL531
C
E
DIRECT TRIP SEND CH-1 MAIN CB 86-A TIE CB 86-A
21 M2 REL 316 ABB Network Partner AG
1
9
2 3 4 5 6
10 11 12 13 14
7 8
15 16
C
PT RECEIVE
PT RECEIVE
PT SEND
PT SEND
PT RECEIVE
PT RECEIVE
DT SEND
DT SEND
DT RECEIVE
DT RECEIVE
ONE END CARRIER PROTECTION PANEL-2
REC 316*4
C
OTHER END CARRIER PROTECTION PANEL-2
PT SEND
PT SEND
PT RECEIVE
PT RECEIVE
E
DIRECT TRIP SEND CH-1 MAIN CB 86-A TIE CB 86-A
21 M2 REL 316 ABB Network Partner AG
1
9
2 3 4 5 6
10 11 12 13 14
7 8
15 16
REC 316*4
C
E
PT SEND
PT SEND
DIRECT TRIP SEND CH-2
PT RECEIVE
PT RECEIVE
DT SEND
DT SEND
MAIN CB 86-B
DT RECEIVE
DT RECEIVE
TIE CB 86-B
E
PT : PERMISSIVE PROTECTION TRANSFER TRIP DT : DIRECT TRANSFER TRIP
DIRECT TRIP SEND CH-2 MAIN CB 86-B TIE CB 86-B
DIRECT TRANSFER TRIP CHANNEL – 1 / 2 RECEIVED INITIATE MAIN CB 86-GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES )
85 LO X1 ACTIVE
DIRECT TRIP CHANNEL-1 RECEIVED
START
TRIP
BLOCK MAIN CB AUTO RECLOSURE BLOCK TIE CB AUTO RECLOSURE
DISPLAY
C
E
85 LO X2 ACTIVE
DIRECT TRIP CHANNEL-2 RECEIVED.
INITIATE TIE CB 86-GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES )
START
TRIP
CLOSE INTERLOCK OF MAIN CB CLOSE INTERLOCK OF TIE CB INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME) TO DISTURBANCE RECORDER TO EVENT RECORDER ( SOE/ SCADA )
INITIATE MAIN CB 86-GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE TIE CB 86-GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) BLOCK MAIN CB AUTO RECLOSURE BLOCK TIE CB AUTO RECLOSURE
DISPLAY
CLOSE INTERLOCK OF MAIN CB CLOSE INTERLOCK OF TIE CB
C
INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME)
E
TO DISTURBANCE RECORDER TO EVENT RECORDER ( SOE/ SCADA )
DIRECT TRIP CHANNEL-1 RECEIVED SOTF PROTECTION (INBUILT MAIN-1) DEF,TOC, BOC, STUB (INBUILT MAIN-1) TEED-1 PROTECTION
86-GA MASTER TRIP / HIGH SPEED TRIP RELAY
OVER VOLTAGE STAGE-1 ( IN BUILT MAIN-2 )
86-GB MASTER TRIP / HIGH SPEED TRIP RELAY
DIRECT TRIP CHANNEL-2 RECEIVED SOTF PROTECTION ( IN BUILT MAIN-2 ) OVER VOLTAGE STAGE-2 DEF, TOC, BOC, STUB ( IN BUILT MAIN-2 ) MAIN LBB OPERATED TIE LBB OPERATED TEED-2 PROTECTION
86-GB MASTER TRIP / HIGH SPEED TRIP RELAY
TRIP COIL -2
MAIN CB
OVER VOLTAGE STAGE-1 (INBUILT MAIN-1)
TIE CB
TRIP COIL-2
86-GA MASTER TRIP / HIGH SPEED TRIP RELAY
TRIP COIL-1
TRIP COIL -1
86-GA & 86 GB MASTER TRIP / HIGH SPEED TRIP LOCKOUT RELAY OPERATION
MASTER TRIP RELAYS HIGH SPEED TRIP RELAYS LOCKOUT RELAYS PUSH BUTTON FOR RESETTING.
PUSH BUTTON FOR RESETTING.
TO CLOSING INTERLOCK OF CONCERNED BAY CB
86-GA MASTER TRIP / HIGH SPEED TRIP RELAY
TO INITIATE LBB/BFR OF CONCERNED BAY BLOCK AUTO RECLOSURE OF CONCERNED BAY TO TRIP COIL-1 CONCERNED BAY CB TO TRIP COIL-2 CONCERNED BAY CB INITIATE FLAG RELAY (FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME) TO DISTURBANCE RECORDER (MAIN-1 & MAIN-2) TO EVENT RECORDER ( SOE/ SCADA )
TO CLOSING INTERLOCK OF CONCERNED BAY CB
86-GB MASTER TRIP / HIGH SPEED TRIP RELAY
TO INITIATE LBB/BFR OF CONCERNED BAY BLOCK AUTO RECLOSURE OF CONCERNED BAY TO TRIP COIL-1 CONCERNED BAY CB TO TRIP COIL-2 CONCERNED BAY CB INITIATE FLAG RELAY (FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME) TO DISTURBANCE RECORDER (MAIN-1 & MAIN-2) TO EVENT RECORDER ( SOE/ SCADA )
TRANSFORMER PROTECTION (DIFFERENCIAL & REF / 3-PH HZ DIFF PROTECTION) INITIATE 400KV MAIN CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES )
RET 670 ACTIVE
87 T1
START
TRIP
INITIATE 400KV TIE CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 220KV MAIN CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 220KV TBC CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES )
DISPLAY
(LZ) C
INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME) TO EVENT RECORDER ( SOE/ SCADA )
E
RET 521
64 T2 REF (HZ)
ACTIVE
START
TRIP
INITIATE 400KV MAIN CB GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 400KV TIE CB GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 220KV MAIN CB GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 220KV TBC CB GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES )
DISPLAY
INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME)
C
E
TO EVENT RECORDER ( SOE/ SCADA )
TRANSFORMER PROTECTION ( BACKUP DIRECTIONAL O/L & E/F PROTECTION FOR HV & LV)
INITIATE 400KV MAIN CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES )
REF 610
67 HV ABCN
ACTIVE
START
TRIP
INITIATE 400KV TIE CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 220KV MAIN CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 220KV TBC CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES )
DISPLAY
C
INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME) TO EVENT RECORDER ( SOE/ SCADA )
E
REX 521 ACTIVE
67 LV ABCN
START
TRIP
INITIATE 400KV MAIN CB GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 400KV TIE CB GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 220KV MAIN CB GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 220KV TBC CB GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES )
DISPLAY
INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME)
C
E
TO EVENT RECORDER ( SOE/ SCADA )
TRANSFORMER PROTECTION ( OVER FLUX PROTECTION FOR HV & LV) INITIATE 400KV MAIN CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES )
RALK
99T HV
ACTIVE
START
INITIATE 400KV TIE CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES )
TRIP
INITIATE 220KV MAIN CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 220KV TBC CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES )
DISPLAY
C
INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME) TO EVENT RECORDER ( SOE/ SCADA )
E
RATUB ACTIVE
START
TRIP
99T LV
INITIATE 400KV MAIN CB GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 400KV TIE CB GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 220KV MAIN CB GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 220KV TBC CB GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES )
DISPLAY
INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME)
C
E
TO EVENT RECORDER ( SOE/ SCADA )
OVER VOLTAGE (LINE) AND OVER FLUX(TRANSFORMER ) PROTECTION TRIP SCHEME 86-A MTR/ HSTR
ABB O/V – 1 O/V – 2
86-A MTR/ HSTR
ABB RALK O/F- HV (BAY 2&3 / HV)
(BAY 1&2)
TRIP COIL-1 1-52CB TRIP COIL-2 BUS-1 86-B ABB REL521 MTR/ MAIN-1 HSTR
TRIP COIL-1 2-52CB
TRIP COIL-1
TRIP COIL-2
TRIP COIL-2 BUS-2
3-52CB
(BAY 1&2)
ABB O/V – 1 O/V – 2
OVER VOLTAGE STAGE-1 & STAGE-2 ARE IN BUILT FUNCTIONS OF MAIN-1 & MAIN-2 NUMERICAL RELAYS. IF EXTERNAL RELAYS ARE UTILISED THEN STAGE-1 IS GR-A & STAGE-2 IS GR-B TRIPPING IS TO UTILISED.
86-A MTR/ HSTR
86-B MTR/ HSTR
86-B MTR/ HSTR
TRIP COIL-2
86-B MTR/ HSTR
LV - CB (BAY LV)
ABB RATUB O/F- LV
TRIP COIL-1
86-A MTR/ HSTR
TRANSFORMER PROTECTION INITIATE 400KV MAIN CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES )
RXIG 21
51 O/L
ACTIVE
START
TRIP
INITIATE 400KV TIE CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 220KV MAIN CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 220KV TBC CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES )
DISPLAY
C
INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME) TO EVENT RECORDER ( SOE/ SCADA )
E
RAEDK1 ACTIVE
START
TRIP
NDR
INITIATE 400KV MAIN CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 400KV TIE CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 220KV MAIN CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 220KV TBC CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES )
DISPLAY
INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME)
C
E
TO EVENT RECORDER ( SOE/ SCADA )
MAIN LBB
INITIATION
INITIATE BUSBAR PROTECTION ( INTURN IT WILL TRIP CONNECTED BUS CBs)
86-GR-A MASTER TRIP RELAY 86-GR-B MASTER TRIP RELAY
RAICA ACTIVE
START
TRIP
INITIATE TIE CB 86-GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INTER TRIP TO 220KV LV MAIN CB INTER TRIP TO 220KV LV TBC CB CLOSE INTERLOCK OF MAIN CB & TIE CB
96 BB BUSBAR RELAY
DISPLAY
INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME)
C
TO EVENT RECORDER ( SOE/ SCADA )
E
TIE LBB
INITIATION 1-PH TRIP RELAYS OF MAIN-1 PROTECTION OF LINE-1(BAY1)
1-PH TRIP RELAYS OF MAIN-2 PROTECTION OF LINE-1 (BAY1)
INITIATE MAIN CB 86-GR-B 3-PH TRIP UNIT (TRIP BAY1 CB 3-POLES )
RAICA ACTIVE
START
TRIP
INITIATE MAIN CB 86-GR-B 3-PH TRIP UNIT ( TRIP BAY3 CB 3-POLES ) BLOCK MAIN CB OF BAY1 AUTO RECLOSURE BLOCK TIE CB AUTO RECLOSURE CLOSE INTERLOCK OF MAIN CB OF BAY1 & BAY 3 CLOSE INTERLOCK OF TIE CB
DISPLAY
DIRECT TRANSFER TRIP-1 CARRIER SEND TO BAY1 & BAY3 LINES DIRECT TRANSFER TRIP-2 CARRIER SEND TO BAY1 & BAY3 LINES
86-GR-A MASTER TRIP RELAY
C 86-GR-B MASTER TRIP RELAY
INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME) TO DISTURBANCE RECORDER (BAY1)
E
TO EVENT RECORDER ( SOE/ SCADA )
B/U O/C & E/F PROTN RLY 67 ABCN INTER TRIP FROM LV SIDE ICT TROUBLES GR-A PROTECTION TRIP ICT HV OVER FLUX RELAY
86-GA MASTER TRIP / HIGH SPEED TRIP RELAY
RESTRICTED EARTH FAULT RELAY 64 REF/T
86-GB MASTER TRIP / HIGH SPEED TRIP RELAY
INTER TRIP FROM LV SIDE ICT TROUBLES GR-B PROTECTION TRIP STUB RELAY 50ST MAIN LBB OPERATED TIE LBB OPERATED ICT LV OVER FLUX RELAY INTER TRIP FROM TBC LBB & MANUAL TRIP OF 220KV
86-GB MASTER TRIP / HIGH SPEED TRIP RELAY
TRIP COIL -2
MAIN CB
T/F DIFFERENTIAL RELAY 87 T
TIE CB
TRIP COIL-2
86-GA MASTER TRIP / HIGH SPEED TRIP RELAY
TRIP COIL-1
TRIP COIL -1
86-GA & 86 GB MASTER TRIP / HIGH SPEED TRIP LOCKOUT RELAY OPERATION
AUTO TRANSFORMER INTER TRIP CIRCUITS HV INTER TRIP CIRCUITS(TO LV) FOR LV MASTER TRIP RELAY 86 GR-A 1. TIE CB OPEN CONDITION + MAIN CB REMOTE HAND TRIP GIVEN. 2. MAIN CB OPEN CONDITION + TIE CB REMOTE HAND TRIP GIVEN. 3. TIE CB OPEN CONDITION + 96 BUSBAR-1 OPERATED. 4. MAIN CB OPEN CONDITION + 96 BUSBAR-2 OPERATED (FOR HALF DIA ONLY). 5. MAIN CB 50 LBB/BFR OPERATED. 6. TIE CB 50 LBB/BFR OPERATED. 7. 87 TEED-1 PROTECTION OPERATED 8. 87 TEED-2 PROTECTION OPERATED. FOR LV MASTER TRIP RELAY 86 GR-B 1. TIE CB OPEN CONDITION + MAIN CB REMOTE HAND TRIP GIVEN. 2. MAIN CB OPEN CONDITION + TIE CB REMOTE HAND TRIP GIVEN. 3. TIE CB OPEN CONDITION + 96 BUSBAR-1 OPERATED. 4. MAIN CB OPEN CONDITION + 96 BUSBAR-2 OPERATED (FOR HALF DIA ONLY). 5. MAIN CB 50 LBB/BFR OPERATED. 6. TIE CB 50 LBB/BFR OPERATED. 7. 87 TEED-1 PROTECTION OPERATED 8. 87 TEED-2 PROTECTION OPERATED.
LV INTER TRIP CIRCUIT(TO HV)
FOR HV M-CB MASTER TRIP RELAY 86 GR-A 1. LV CB REMOTE HAND TRIP GIVEN. 2. LV 87 BB(96) BUSBAR-1/2 (ISO SELECTION) OPERATED. 3. LV CB 50 LBB/BFR OPERATED. FOR HV M-CB MASTER TRIP RELAY 86 GR-B 1. LV CB REMOTE HAND TRIP GIVEN. 2. LV 87 BB(96) BUSBAR-1/2 (ISO SELECTION) OPERATED. 3. LV CB 50 LBB/BFR OPERATED. FOR HV T-CB MASTER TRIP RELAY 86 GR-A 1. LV CB REMOTE HAND TRIP GIVEN. 2. LV 87 BB(96) BUSBAR-1/2 (ISO SELECTION) OPERATED. 3. LV CB 50 LBB/BFR OPERATED. FOR HV T-CB MASTER TRIP RELAY 86 GR-B 1. LV CB REMOTE HAND TRIP GIVEN. 2. LV 87 BB(96) BUSBAR-1/2 (ISO SELECTION) OPERATED. 3. LV CB 50 LBB/BFR OPERATED.
TRANSFORMER TROUBLES TRIPPING GR-A 86 AX
OIL TEMP TRIP
TO 3PH GR-A 400KV MAIN CB TO 3PH GR-A 400KV TIE CB
DIFF RELAY 87T
TO 3PH GR-A 220KV MAIN CB
BUCHHOLZ TRIP
TO 3PH GR-A 220KV TBC CB
OL RELAY 51OL PRD-1 TRIP
HV O/L+E/F PROT 67 PRD-2 TRIP
NDR RELAY 151N
HV O/F RELAY 99T
86 AY
TRANSFORMER TROUBLES TRIPPING GR-B 86 BX
OLTC BUCHHOLZ-R TRIP TO 3PH GR-B 400KV MAIN CB TO 3PH GR-B 400KV TIE CB
OLTC BUCHHOLZ-Y TRIP
REF RELAY 64REF
TO 3PH GR-B 220KV MAIN CB TO 3PH GR-B 220KV TBC CB
STUB RELAY 50ST OLTC BUCHHOLZ –B TRIP
LV O/L+E/F PROT 67 WNDG TEMP-HV TRIP
LV O/F RELAY 99T WNDG TEMP-LV TRIP
WNDG TEMP-IV TRIP
86 BY
TRIP COIL-1 CIRCUITS TRIP COIL-1 186R1
186Y1
186B1
186R2
186Y2
186B2
286R1
286Y1
286B1
286R2
286Y2
286B2
186R1, 186R2, 186Y1, 186Y2, 186B1, 186B2 ARE CB 1-PH TRIP UNIT OF GR-A. THESE ARE SELF RESETING. 286R1, 286R2, 286Y1, 286Y2, 286B1, 286B2 ARE CB 1-PH TRIP UNIT OF GR-B. THESE ARE SELF RESETING. THE BELOW ARE HAND RESETING. 86GR-A, 86GR-B ARE 3-PH TRIP UNITS. 96 BB IS BUSBAR TRIPPING RELAY
86GR-A
.
.
.
86GR-B
.
96BB
.
.
TRIP COIL – 2 CIRCUITS TRIP COIL-2 186R1
186Y1
186B1
186R2
186Y2
186B2
286R1
286Y1
286B1
286R2
286Y2
286B2
186R1, 186R2, 186Y1, 186Y2, 186B1, 186B2 ARE CB 1-PH TRIP UNIT OF GR-A. THESE ARE SELF RESETING. 286R1, 286R2, 286Y1, 286Y2, 286B1, 286B2 ARE CB 1-PH TRIP UNIT OF GR-B. THESE ARE SELF RESETING. THE BELOW ARE HAND RESETING. 86GR-A, 86GR-B ARE 3-PH TRIP UNITS. 96 BB IS BUSBAR TRIPPING RELAY
86GR-A
.
.
.
86GR-B
.
96BB
.
.
ISOLATOR INTERLOCKS
NOTE: All Earth Switches in the Bay are towards Circuit Breaker side only. The Line and Transformer Earth Switches are towards Line & Transformer. O: OPEN C: CLOSE A: ACTED
BB189E : BUSBAR-1 EARTH SWITCH . BB289E : BUSBAR-2EARTH SWITCH . UV RELAY: UNDER VOLTAGE RELAY.
S.NO
ISOLATOR OPEN/CLOSE
EQUIPMENT-1
EQUIPMENT-2
EQUIPMENT-3
EQUIPMENT-4
INTERLOCKS REQUIRED FOR CONCERNED ISOLATOR / EARTH SWITCH OPEN OR CLOSE
BAY - 1 1
1 - 89
ISO
BB189 E
O
189 AE
O
189 E
O
152 CB
O
2
1 – 89 E
ES
189 A
O
189
O
--
-
--
-
3
1 – 89 A
ISO
189 AE
O
189 E
O
152 CB
O
--
-
4
1 – 89 AE
ES
189 A
O
189
O
--
-
--
-
5
1 – 89 L
ISO
189 LE
O
152 CB
O
252 CB
O
--
-
6
1 – 89 LE
ES
189 L
O
UV RELAY
A
--
-
--
-
7
2 – 89 A
ISO
289 BE
O
289 AE
O
252 CB
O
--
-
8
2 – 89 AE
ES
289 B
O
289 A
O
--
-
--
-
9
2 – 89 B
ISO
289 BE
O
289 AE
O
252 CB
O
--
-
10
2 – 89 BE
ES
289 B
O
289 A
O
--
-
--
-
11
3 – 89
ISO
BB289 E
O
389 AE
O
389 E
O
352 CB
O
12
3 – 89 E
ES
389 A
O
389
O
--
-
--
-
13
3 – 89 A
ISO
389 AE
O
389 E
O
352 CB
O
--
-
14
3 – 89 AE
ES
389 A
O
389
O
--
-
--
-
15
3 – 89 T
ISO
LV89 E2
O
389 TE
O
252 CB
O
352 CB
O
16
3 – 89 TE
ES
389 T
O
LV89 T
O
--
-
--
-
BAY - 2
BAY - 3
BB189E 1-89AE 1-89E 1-52CB 1-52CB 1-89AE 1-89E
1-52CB 1-89LE 2-52CB 1-89 1-89A 1-89 1-89A 1-89L U/V RLY
ISOLATOR & CB INTERLOCKS
OPEN OPEN OPEN
& OPERATION
OPEN 1-89
1-89E
OPEN
1-89AE
OPEN
2-89AE
OPEN
& OPERATION
1-89A
2-89BE
OPEN 3-89E 3-89AE
OPEN OPEN
& OPERATION
86GR-A
1-89L
86GR-B
OPEN
96BB
2-89AE 2-89BE
CLOSE CLOSE
LOCAL CLOSE
& 1-52CB
CLOSE CLOSE
&
& 2-52CB
OPEN 3-89A
OPERATION
&
LOCAL CLOSE
& 3-52CB
RESET RESET
REMOTE CLOSE
& 1-52CB
OPEN
&
OPERATION
1-89E
86GR-A 86GR-B
OPEN OPEN
&
OPERATION
1-89AE
3-89T
OPERATION
ACTED
&
OPERATION
1-89LE
OPEN OPEN
86GR-A 96BB
OPEN
2-89B
& OPERATION 2-89A
RESET
REMOTE CLOSE
& 2-52CB
3-89E 3-52CB 3-52CB 3-89AE
OPEN
OPEN
&
3-89AE
OPEN OPEN
3-89E 3-52CB 3-89TE 2-52CB LV89E2
OPEN 3-89E
OPERATION
&
OPEN
3-89 3-89A
OPEN 86GR-B
OPEN
RESET
OPEN
OPEN
RESET
BB289E
OPEN OPEN
LOCAL CLOSE
CLOSE CLOSE
3-89
OPERATION
OPEN
2-89A 2-52CB
OPEN
2-89A 2-89B
RESET RESET RESET
&
REMOTE CLOSE
3-89AE
3-52CB 3-89TE
OPERATION
OPERATION
&
OPEN OPEN
&
OPEN
3-89 3-89A 3-89T LV89T
OPEN OPEN
& OPERATION 2-89AE
OPEN OPEN
& OPERATION 2-89BE
2-52CB 2-89AE 2-89BE
OPEN OPEN OPEN
& OPERATION 2-89B
CLOSING INTERLOCK OF MAIN & TIE CB 96 BB
86 GR-A
86 GR-B + VE T N C
21M1 AR
MAIN CB
SYN SOCKET
+ve
-ve
CB REMOTE CLOSE
CB AUTO RECLOSE
21M2 AR
86 GR-A
86 GR-B + VE T N C
TIE
AR
TIE CB
SYN SOCKET
+ve
-ve
CB REMOTE CLOSE
CB AUTO RECLOSE
ADVANTAGES & DISADVANTAGES OF ONE & HALF BREAKER SYSTEM A.
ADVANTAGES:
1. 2.
7. 8.
THREE CIRCUIT BREAKERS IN A FULL DIA ARE ALWAYS IN CLOSED POSITION. IF MAIN CB PROBLEM / FOR PERIODICAL MAINTANENCE, DURING THAT PERIOD THE FEEDER IS FEEDING FROM TIE CB & OTHER BUS . NEED NOT REQUIRE TRANSFER THE FEEDER. IF TIE CB PROBLEM / FOR PERIODICAL MAINTANENCE, DURING THAT PERIOD THE FEEDER IS FEEDING FROM MAIN CB & CONNECTED BUS. EVEN IF BOTH MAIN BREAKERS UNDER TROUBLE, DURING THAT PERIOD ONE FEEDER WORKS AS INCOMING AND OTHER FEEDER WORKS AS OUTGOING VIA TIE CB. (WITHOUT INTERUPTION TO FEEDERS) IF BUSBAR-1 OPERATED / FOR PERIODICAL MAINTANENCE, ONLY THE MAIN BREAKERS CONNECTED TO BUSBAR-1 WILL TRIP. DURING THAT PERIOD THE FEEDERS CONNECTED TO BUS-1 ARE FEEDING VIA TIE CB FROM BUS-2. IF BUSBAR-2 OPERATED / FOR PERIODICAL MAINTANENCE, ONLY THE MAIN BREAKERS CONNECTED TO BUSBAR-2 WILL TRIP. DURING THAT PERIOD THE FEEDERS CONNECTED TO BUS-2 ARE FEEDING VIA TIE CB FROM BUS-1. IN THIS BUSBAR PROTECTION IS SIMPLE AND NEED NOT REQUIRE SELECTION OF ISOLATOR. IT IS MORE RELIABLE SYSTEM FOR OPERATION & MAINTANENCE POINT OF VIEW.
B.
DISADVANTAGES
1.
CT CONNECTIONS & PROTECTION TRIP LOGICS ARE SOME WHAT COMPLICATED. COMPLEX CONTROL & PROTECTION PHILOSOPHY COST TOWARDS CTs, CIRCUIT BREAKERS & PANELS ARE TO BE INCREASED DUE TO EXTRA BAY. THE COST COMPARISION TABLE SHOWN IN NEXT PRESENTATION. THE OPERATIONS FOR OPERATOR POINT OF VIEW IS LITTLE BIT COMPLICATED WHEN COMPARED TO CONVENTIONAL SYSTEM. SPACE OCUPATION FOR BAY IS MORE i.e COST OF LAND IS INCREASE.
3. 4.
5.
6.
2. 3. 4.
COST COMPARISION BETWEEN CONVENTIONAL SYSTEM & ONE AND HALF BREAKER SYSTEM FOR FEEDER S.No
EQUIPMENT
CONVENTIONAL SYSTEM
1.
CIRCUIT BREAKERS
1 No
CURRENT TRANSFORMERS
FULL DIA (FOR 2 FEEDERS)
% INCREASE IN COST
3 Nos
50%
HALF DIA % INCREASE (FOR 1 FEEDER) IN COST 2 Nos
100%
INCLUDES THE COST OF CT MARSHELLING BOXES. 3 Sets
50%
2 Sets
100%
4 Sets
100%
2 Sets
100%
5 CT METHOD
5 Sets
125%
3 Sets
200%
6 CT METHOD
6 Sets
200%
3 Sets
200%
3 SETS
30%
2 SETS
30%
3 CT METHOD 2.
ONE & HALF BREAKER SYSTEM
4 CT METHOD
1 Set
I SET
3.
CONTROL & RELAY PANELS
4.
BAY MARSHALLING BOXES
1 No
3 Nos
50%
2 Nos
30%
5.
CONTROL CABLES
8 KM
30 KM
100%
20 KM
150%
NORMALLY EXTRA PANEL IS TIE BAY PANEL. IT IS ARROUND 30% COST OF MAIN PANEL. BECAUSE IT IS NOT HAVING PROTECTION RELAYS ( M-1 & M-2 AND OTHER RELAYS) . ONLY TIE CB TRIPPING RELAYS & ASSOCIATED RELAYS(A/R +LBB).
OTHER INFORMATION REGARDING RELAYS AND TESTING EQUIPMENT PREPARED BY GOPALA KRISHNA PALEPU ADE/MRT(PROTECTION)
ABB RELAYS ABB Network Partner AG
ABB Network Partner AG
REL 521
REL 316*4
ABB Network Partner AG
1
9
2
10
3
11
4
12
5
13
6
14
7
15
8
16
C
C
C E
EE
ABB Relays ABB Network Partner AG
REL 512
c E
AREVA RELAYS
P445
P443
P437
E-PAC
P442
GE MULTILIN RELAYS
B90 – 87BB C60 – BCU D60 – 21L D90 – 21L
L60 – 87L L90 – 87L T60 – 87T D25 – BCU
F90 – 67/51 G60 – GEN M60 – MOTOR N90 – NETWORK
SIEMENS RELAYS
SEL RELAYS ENABLED TARGET RESET
TRIP
IA =250.10 A IB =250.10 A IC =250.10 A VAB =400.0 KV VBC =400.0 KV VCA =400.0 KV ESC
ENT
INST TIME COMM SOTF
1
INST TIME COMM SOTF ZONE 1 ZONE 2 ZONE 3 ZONE 4
PH - A PH - B PH - C GND
79 RESET 79 LOCKOUT
4
A
B
ZONE C
G
FAULT TYPE
TARGET TARGET FAULT SET RESET NO / YES / CANCEL SELECT
Q
51
COMM ENABLED
RECLOSE ENABLED
ALT SETTINGS
CB CLOSED
RELAY TEST
CB OPEN
SEL- 321- 5 - 2
TARGET RESET
TRIP
EN
MC ENABLED
50 51
2ENABLED 3
TRIP
SPT ENABLED
PROTECTION AUTOMATION CONTROL
50 O/C
METER STATUS OTHER GROUP EXIT
SEL
SEL- 421 PROTECTION AUTOMATION CONTROL
SEL
VA TECH REYROLLE RELAYS
ERL PHASE RELAYS
RELAY HARDWARE 16 / 32 BIT
PC MODEM
IRIG-B RE/CC
NORMALLY 400KV RELAYS SUPPLIED WITH CONFIGUARATION/HARDWARE 1. MIN 4Nos MAX 8Nos COMMAND/TRIP OUTPUTS 2. MIN 24Nos SIGNAL OUTPUTS 3. MIN 14 LED INDICATIONS 4. MIN 24 BINARY INPUTS
FOLLOWING
RELAY SIGNAL DATA FLOW
FUNCTIONS AVAILABLE NUMERICAL DISTANCE RELAYS 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. 24. 25.
4 TO 6 SETTING IMPEDENCE ZONES WITH 4 TO 6 SETTING GROUPS (21 + 21N). DIR / INST / TIME OVERCURRENT & EARTH FAULT FUNCTION( 50 / 51 / 67 P+G). EIGHT COMMUNICATION SCHEMES. SWITCH ON TO FAULT PROTECTION(21 SOTF). PHASE SELECTION(R,Y,B). POWER SWING BLOCKING(PSB)(68 + 68T). FUSE FAILURE SUPERVISION(PT FFR). AUTO RECLOSER WITH CHECK SYNCHRNISATION & VOLTAGE CHECK(79 + 25 +86). WEEK END INFEED LOGIC(27 WI). SYSTEM SUPERVISION. STUB PROTECTION(STUB). OVER VOLTAGE/ UNDER VOLTAGE FUNCTION(27+ 59). LBB/BFR FUNCTION(50 BF). DISTANCE TO FAULT LOCATOR(21 FL).(SHOWS IN 1. %, 2. KM 3. MILES & 4. R+JX ) 16 PROGRAMABLE SIGNALLING RELAYS WITH LEDs. RECORDABLE 10Nos LATEST DISTRUBANCES WITH BASIC EVALUATION DISTURBANCE RECORDER. EVENT RECORDER RELATED TO RELAY EVENTS. PRE-FAULT, FAULT & POST-FAULT VALUES OF ANALOG POINTS WITH IMPEDENCE DETAILS. USER CAN BE CONFIGUARED PROGRAMABLE LOGIC FUNCTIONS. TELE / CARRIER INTER TRIPPING SCHEMES(85 +21)(PUTT, POTT). TRIP CIRCUIT MONITORING(74 TC). METERING FUNCTION (INSTANTANEOUS VALUES DISPLAY FUNCTION). 4 QUADRANT ENERGY METER FUNCTION (KWH,KVAH,KVARH)(KYZ PULSE OUTPUT). MINIMUM 8 COMMOND/ TRIP RELAYS, 24 SIGNAL RELAYS MINIMUM 20 BINARY INPUTS, 14 LEDs
DISTANCE RELAYS CHARACTERESTICS ( MHO CIRCULAR )
DISTANCE RELAYS CHARACTERESTICS ( QUADRILATERAL-1 )
DISTANCE RELAYS CHARACTERESTICS ( QUADRILATERAL-2 )
DISTANCE RELAYS CHARACTERESTICS ( BULLET )
DISTANCE RELAYS CHARACTERESTICS ( TRIANGLER )
DISTANCE RELAYS CHARACTERESTICS ( LENS / OPTICAL )
DISTANCE RELAYS CHARACTERESTICS ( TOMATO )
DISTANCE RELAYS CHARACTERESTICS ( PEANUT )
RELAY MODELS OF LINE (DISTANCE) & TRANSFORMER( M & B ) OF DIFFERENT MANUFACTURERS MANUFACTURERS
TRANSMISSION LINE PROTECTION CURVES
MAIN-2 REL 316 REL 512 MICOM P437 E-PAC 3000, OPTIMHO
CURVES
T/F PROTECTION DIFFERENTIAL RET 521 / 670 RET 316
DIR O/L,E/F REL 505 REX 521
QUAD/ MHO
MICOM P633 KBCH/ MBCH
MICOM P141 MICOM P127
AREVA (ALSTOM)
MAIN-1 REL 521 REL 670 MICOM P443/P444/ P442/P445
SIEMENS ( SIPROTEC )
SIPROTEC 7SA62/3
QUAD/ MHO
SIPROTEC 7SA522
QUAD/ MHO
7UT 613/ 2 7UT 513/ 2
7SJ 62/3/4/5 7SJ 52/3/4/5
SEL
SEL 421
QUAD/ MHO
SEL 321 SEL 311C
QUAD/ MHO
SEL 387
SEL 351
GE MULTILIN
D-60, ALPS
QUAD/ MHO
L-60/L-90 D-30
QUAD/ MHO
T-35 / T-60 SR 7465
F-60 SR 750/60
EASUN REYROLL
THR 4 PE 24
MHO
MHO
---
MIT
NXT PHASE
L-PRO
QUAD/ MHO
L-PRO
LENS/ TOMAT0
T-PRO
F-PRO
VA TECH REYROLL
OHMEGA 402
QUAD/ MHO
OHMEGA 311/308
QUAD/ MHO
DUOBIAS M
ARGUS
ABB
QUAD
QUAD/ MHO
THR 4 PE 16
THR 3 PE 18
QUAD/ BULLET
IEC 61850 RELAY MODELS OF DIFFERENT MANUFACTURERS MANUFACTURERS
BCU CB CONTROL
FEEDER 67
DISTANCE 21
LINE DIFFERENTIAL DIFFERENTIAL 87 T 87 L
BUSBAR 87 BB
ABB
REC 670
REX 610
REL 670
RED 670
RET 670
AREVA
MICOM C264
MICOM P141
MICOM P44 2/3/4
MICOM P543/547
MICOM P633/P643
REB 670 REB 500 MICOM P74 1/3/6
GE D 25 MULTILIN SIEMENS SIPROTEC
F 60
D 60, D 90
L 60, L 90
T 60
B 90, B 30
SIPROTEC
SIPROTEC
SIPROTEC
SIPROTEC
SIPROTEC
( SIPROTEC )
6MD66/3
7SJ 62/3/4
7SA 522/6..
7SD 522/61_
7UT 633/13/2
7 SS 52
SEL
SEL 451-4
SEL 451
SEL 421/321
SEL 487E
TOSHIBA
GRD 150
GRD 140
GRZ 100
SEL 387L GRL 100 / 150
SEL 487B GRB 100/150
GRT 100
RELAY TESTING EQUIPMENTS 1. PROGRAMA_GE (MODEL: FREEJA-300) 3. OMICRON (MODEL: CMC 256-6)
2. MANTA TEST SYSTEMS (MODEL: MTS 4000) 4. DOBLE ( MODEL: F 6150)
RELAY TESTING EQUIPMENTS 1. MEEGER_AVO (MODEL: MPRT 8430) 3. KOCOS (MODEL: ARTES 440 II)
2. RES (MODEL: APTS 3) 4. EURO SMC ( MODEL: TRES)
400KV SUBSTATIONS IN APTRANSCO S.No
400KV SUBSTATION
CAPACITY
1.
MAMIDIPALLY (HYDERABAD)
3 X 315 MVA
1. SRISAILAM 1&2 2. GHANAPUR (PGCIL)
3. KHAMMAM 1&2(PGCIL) 4. YEDDUMAILARAM 1&2**
2.
NURNOOR (KURNOOL)
(2 + 1**) X 315 MVA
1. SRISAILAM 2. GHANAPUR (PGCIL)
3. GOOTY (PGCIL) 4. KURNOOL**(PGCIL765)
3.
KALAPAKA (VISHAKHAPATNAM)
2 X 315 MVA
1. SIMHADRI 1,2,3&4 (NTPC) 2. GAJUWAKA 1&2 (PGCIL)
3. KHAMMAM 1&2 (PGCIL) 4. VEMAGIRI 1&2
2 X 315 MVA
1. KALAPAKA 1&2 2. GAJUWAKA 1&2 (PGCIL) 3. NUNNA 1&2 (PGCIL) 4. NUNNA 3&4 (NRPT** 1&2)
5. GVK EXTN 1&2 (IPP) 6. GOWTHAMI 1&2 (IPP) 7. KONASEEMA 1&2 (IPP) 8. GMR VASAVI 1&2 (IPP)
1. TALLAPALLY
2. RAICHUR
1. CHENNAI RED HILLS 3. KRISHNAPATNAM**1&2
2. KADAPA
4. 5.
VEMAGIRI (RAJHAMUNDRY) VELTUR (MB NAGAR)
(1 + 2**) X 315 MVA (1 + 1**) X 315 MVA
FEEDERS
6.
CHITTOR(VEPANJIR)
7.
NELLORE(MANUBOLU)
2 X 315 MVA
8.
DICHPALLY (NIZAMABAD)
2 X 315 MVA
1. RAMAGUNDAM
9.
GAJWEL (MEDAK)
2 X 315 MVA
1. RAMAGUNDAM 3. BTPS 1&2**
2. GHANAPUR 4. YEDDUMAILARAM 1&2**
10.
MALKARAM* (SECUNDRABAD)
2 X 315 MVA
1. RAMAGUNDAM 3. VTPS**1&2
2. GHANAPUR
11.
YEDDUMAILARAM** (RR, SHANKARPALLY)
3 X 315 MVA
1. GAJWEL 1&2
2. MAMIDIPALLY 1&2
12.
NARASARAOPETA**(GUNTUR)
2 X 315 MVA
1. SRISAILAM 1&2 2. NUNNA 1&2 (VTPS*)
3. VEMAGIRI 1&2
13.
SURYAPETA** (NALGONDA)
2 X 315 MVA
1. VTPS 1&2
2. MALKARAM 1&2
400KV SUBSTATIONS OF PGCIL IN AP S.No
400KV SUBSTATION
1.
RAMAGUNDAM(NTPC)
2.
GHANAPUR (HYDERABAD)
3.
GAJUWAKA (VISHAKHAPATNAM)
CAPACITY 2 X 200 MVA 2 X 250 MVA 1 X 315 MVA
FEEDERS 1. GHANAPUR 1&2 2. GAJWEL(GHNP3) 3. MALKARAM(GHNP4)
4. TALLAPALLY 1&2 5. DICHPALLY 6. KHAMMAM (WRNGL) 7. CHANDRAPUR 1&2
3 X 315 MVA
1. RAMAGUNDAM 1&2 2. MAMIDIPALLY 3. GAJWEL(RMGNDM3)
4. NAGARJUNA SAGAR 5. KURNOOL 6. MALKARAM (RMGNDM4)
2 X315 MVA
1. NUNNA 2. KALAPAKA1&2 5. SIMHADRI**1&2
3. VEMAGIRI 1&2 4. JAIPUR(HVDC) 4. VEMAGIRI 3&4 (#) 5. KHAMMAM 6. NELLORE 1&2 7. KONDAPALLY*1&2
4.
NUNNA (VIJAYAWADA)
2 X315 MVA
1. GAJUWAKA 2. SRISAILAM 1&2 (VTPS) 3. VEMAGIRI 1&2
5.
TALLAPALLY (NAGARJUNA SAGAR)
3 X 315 MVA
1. RAMAGUNDAM 1&2 2. GHANAPUR 3. MAHABOOBNAGAR
4. GOOTY(KNL765*) 5. CHINAKAMPALLY 1&2
2 X 315 MVA
1. RAMAGUNDAM (WGL) 2. NUNNA 5. KTPS**1&2
4. MAMIDIPALLY 1&2 5. KALAPAKA 1&2 4. NEELAMANGALA 5. RAICHUR 1&2
6.
BUDIDAMPADU (KHAMMAM)
7.
GOOTY
2 X 315 MVA
1. TALLAPALLY 2. SOMANAHALLY 3. KURNOOL
8.
CHINAKAMPALLY
2 X 315 MVA
1. TALLAPALLY 1&2 2. SOMANAHALLY
3. KOLAR 4. CHITTOR
9.
NELLORE(MANUBOLU)
1. NUNNA 1&2
2. ALAMATHI 1&2 (NLR765**)
10.
MULUGU* (WARANGAL)
1. RAMAGUNDAM 2. KHAMMAM
3. BTPS(KTPS)* 1&2
2 X 315 MVA
1. RAMAGUNDAM TO GHANAPUR CKT-2 IS PROPOSED TO TAKE LILO AT MALKARAM (APTRANSCO) SS. 2. RAMAGUNDAM TO KHAMMAM CKT IS PROPOSED TO TAKE LILO AT WARANGAL SS. 3. 765KV KURNOOL IS ABOUT TO START, 765KV DC TO RAICHUR & 400KV KUMPP-DC, KNL 400-DC, LILO TLPLY-GOOTY. 4. 765KV NELLORE IS UNDER FORMULATION STAGE. 5. 765KV EITHER EAST GODAVARI OR SRIKAKULAM IS UNDER FORMULATION STAGE.
400KV NETWORK IN AP DICHPALLY CHANDRAPUR TALLAPALLY (MAHARASTRA)
IPP4 KTPS
VEMAGIRI
SRISAILAM
MBNGR
GOOTY CHITTOR
RAICHUR MAMIDIPALLY
CHENNAI
GUNTUR(NRPT)
KADAPA
KOLAR
MALKARAM NLR**765 ALAMETHI / CHENNAI
KHAMMAM
KRNL 765
KPPTS
BANGALORE
VTPS SURYAPETA
NELLORE
KPPTS
KURNOOL
BANGALORE
NUNNA
GHANAPUR
KRNL 765
IPP2 YEDDUMAILARAM
IPP1
MALKARAM
IPP3
BTPS
GAJWEL
KALAPAKA
WARANGAL
HVDC
JAIPUR
RAMAGUNDAM
SIMHADRI
GAJUWAKA
VEMAGIRI SUBSTATION DISPLAY NUNNA – I (PGCIL)
315MVA, 400/220KV AUTO TRANSFORMER-I
NUNNA – II (PGCIL)
315MVA, 400/220KV AUTO TRANSFORMER-II
KALAPAKA – I KALAPAKA – II
GUNTUR – I
GUNTUR – II
GAJUWAKA – I GAJUWAKA – II GOWTHAMI – I GOWTHAMI – II FUTURE – I (PGCIL) (PGCIL) PHES
KOPCL – II VPGCL – I VPGCL – II KOPCL – I GMR VASAVI GMR VASAVI KONASEEMA KONASEEMA
GVK EXT – I
FUTURE – II PHES
GVK EXT – II
DISPLAY