[ü[
Detailed Proj ect Reporf Section 205 Silver Creek Dam Early Warning System
October 2A04
Table of Contents 1.0 INTRODUCTION....
Authority ................... 1.3 Study Sponsorship .............. 1.4 Project Location 1.5 Previous Studies. 2.0 STUDY AREA CHARACTERISTICS 2.1 Socioeconomic Characteristics ........ 2.2 Basin Conditions .................... 2.2.1 Climatology and Hydrology .......... 1.2
2.2.2Basin 2.3 Current Dam..... 2.4 Existing Condition ............... 2.5 Review of Existing Dam Safety Monitoring Program. 2.5.7 Piezometers. 252Flow Measurements from Drains 2.5.3 Survey Points 2.5.4 Reservoir Level. 2.5.5 Visual Observations............ 2. 5 .6 D ata Evaluation/Management
4 4 4 4
4 .4 .6 .6 6
6 6 7 7 8
8 .
8
I 8
9 9
3.0 PLAN FORMULATION......... 3.1 Problems and Opportunities........... 3.2 Planning Objectives ... 3.3 Evaluation of Conditions before Project Improvements 3.3. 1 Overtopping Scenario .. 3.3.2 Piping Failure Scenario.... 3.3.3 Seepage Failure Scenario... 3.4 Seepage Failure Scenario before Project Improvements 3.4. I Overview............ 3.4.2 Property Damagos.............. Estimate of Residential Content Damages . Estimate of Non-Residential Content Damages 3.5 Alternative Analysis....... 3.5.1 Flood Warning System... 3.5.2 Flood'Warning System Costs 3.6 Potential Reduction to Property Damages with Flood Warning Time... 3.7 Comparison of Benefits to Costs 4.0 RECOMMENDED PLAN....... 4.1 Overview............. 4.2Detection System 4.2. I Reservoir Monitoring
2
10 10
10 10 10 11 11
t2 12 13
t3 13
t4 14 15 15
l6 t7 t7 t7 t7
Upgrading Piezometers W eir Box Instrumentation .. Monitoring Station....... Reservoir Gauge Measurement Control Units......... 4.2.7 Additional Detection System Detai1s............. 4.3 Notifrcation System..... 4.3. I Alternative Notification Options 4.3.2 Recommended Notification System 4.3.3 Specific Notification System Components . 4.4 Evacuation Plan ...... 4.4. 1 Recommended Evacuation Zones. 4 .4 .2 Ev acuations of Special Facilities/Structure s 4.4.3 Coordination of Emergency Response ........ 4.4.3.1 Police ........ 4.4.3.2 Cify 4.4.3.3 Fire............ 4 .4.3 .4 Interagency Coordination ........... 4.5 Environmental Impacts.... 4.6 Cultural Resources ................... 4.7 Geotechnical 4.9 Cost Estimate ..... 5.0 COMPLIANCE AND COORDINATION 5.1 Regulatory Compliance and Environmental Statutes... 5.2 Public and Agency Coordination 6.0 IMPLEMENTATION PLAN AND SCHEDULE.. 6. 1 Finalizing Remaining Implementation Details 6.2 Tasks and Responsibilities .... 6.3 Acceptance Criteria Plan 6.4 Schedule..... 7.0 CONCLUSIONS AND RECOMMENDATION .............. 7.1 Conclusion .......... 7.2 Recommendation
t7 t7 t7
4.2.2 4.2.3 4.2.4 4.2.5 4.2.6
18 18
................... I 8 ................... 19
...................19 22 22
Appendix A- Geotechnical lnvestigation of Silver Creek Dam Appendix B- Baseline Cost Estimate for Silver Creek Dam Early Warning System
J
23 23 23
.24 .24 .24 .24 .25 .25 .25
25
26 .27 .27 .27 ..28 ..28 28
29 .29 30 30 30
l.O INTRODUCTION 1.1 Purpose Potential flood problems associated with the Silver Creek Dam, and opportunities to minimize the consequences with the implementation of a flood warning system are explored in this Detailed Project Report (DPR). This study is a feasibility level decision document, prepared using the current guidance contained in Engineering Regulation (ER) I105-2-100, Planning Guidance Notebook and current cost sharing requirements cited in the Water Resources Development Act
of 1986, as amended. The specific purpose of this study is to identifr a project that will reduce the risk of loss of life and flood damage in the City of Silverton while minimizing or avoiding environmental and
cultural impacts. 1.2 Authority This report was prepared under authority of Section 205 of the Flood Control Act of 1948, as amended. The Northwestern Division, Corps of Engineers granted specific authority to conduct this analysis through correspondence dated 8 August 2003.
1.3 Study Sponsorship In a letter dated March 6,2002, the City of Silverton requested a study under the Section 205 Continuing Authority to evaluate the viability of a flood warning system for Silver Creek, and acknowledged their financial obligations after the first $100,000 study cost and requirements for implementation of a solution. 1.4 Project Location Silver Creek Dam is located on Silver Creek abotfi2 miles upstream of the City of Silverton, in Marion County, Oregon (figure 1). Silver Creek meanders through the City of Silverton and the potential flood zone encompasses the majority of the city. 1.5 Previous Studies A substantial amount of information is available in work previously completed by others for the Cþ of Silverton, including geotechnical, hydrologic, and system cost studies. Following is a list of the most relevant studies used in this evaluation. o Supplemental Information, Silver Creek Dam (Silverton, Oregon), Prepared by U.S. Army Corps of Engineers, July 2003. o Silver Creek Dam Early Warning System Preliminary Design Report, Prepared for City of Silverton, Oregon by Squier Associates, April2002. ¡ Silver Creek Dam Break Analysis Final Report, Prepared for City of Silverton, Oregon by Philip Williams & Associates, Ltd, January 18,2000. ¡ Phase I Inspection Report, Prepared by Oregon Water Resources Department in
o
cooperation with the U.S. Army Corps of Engineers, June 1981. Seismic Stability Analysis, Silver Creek Dam, Prepared for City of Silverton by Cornforth Consultants, July 21, 1999.
4
Insert Figure I
5
2.0 STUDY AREA CHARACTERISTICS
2.1 Socioeconomic Characteristics The City of Silverton home page indicates that the history of Silverton began with the first settlers who came to the banks of Silver Creek in the 1800s. In 1846, a sawmill and small settlement called Milford was established. By 1854, Milford was abandoned and the businesses moved downstream to the current site of the city of Silverton. Silverton was incorporated in 1885. By 1894, the population was about 900. By 1921, Silverton industries were producing goods. The Fischer Flour Mills on South Water Street was flourishing. Power for the mill was obtained by damming Silver Creek at a point near the present pool, diverting water into a millrace that ran along the creek to the mill and then dumped back into the creek. A short way downstream from the Fischer mill, the creek was dammed again to furnish power for a sash and door plant. Timber drove local industry, and the Silver Falls Timber Co. was once the largest sawmill of its kind in the world. Metal piping was also part of the economy. Today, those kinds of industries have been replaced with others. The newest major industry for the area is Champion Homes, a manufactured home plant. The Oregon Garden attracts tourism. Silverton's major employers include the Silver Falls School District (more than 400), Silverton Hospital (over 400), Champion Homes (more than 200), Brucepac, a meat packing plant (more than 100), and Mallorie's Dairy (e0). The Oregon Employment Department's"2}l2 Regional Economic Profile" shows 2000 Census data for population: Marion County had a population just under 285,000; Salem, the largest city in Marion County, had a population just under 137,000; and, Silverton had a population of 7,414. Thereportalsoshowed a7999 percapitaincomefigureof $23,828forMarionCounty. The principal industries in Marion County are government, agriculture, food processing, wood products, retail trade, education and tourism.
2.2 Basin Conditions
2.2.1 Climatology and Hydrology The study area has a temperate maritime climate dominated by airflow from the Pacific Ocean. Warm, dry summers and mild, wet winters are typical. Daily average temperature ranges from 40 degree Fahrenheit. Average temperature in January is 40 degrees Fahrenheit, and in July is 66 degrees Fahrenheit. Annual average precipitation is about 50 inches over the basin with almost 70 percent of that falling between November and March, inclusive. Most major floods in Silverton occur as a result of general winter storms during December, January and February. These are caused by heavy rainfall from storms off the North Pacific falling on sno\ry in the Silver Creek Basin. Recent large flood events have occurred in 1964, 1972,1976 and 1996.
2.2.2B,asir' Silver Creek is located in the mid-Willamette Valley. It runs generally SE to NW, draining off the lower western slope of the Cascade Mountains. It is a tributary to the Pudding River about 3 miles downstream of Silverton, Oregon. Drainage area at the Silver Creek Dam is about 45.6 square miles. Silver Creek has a drainage basin made up of forested foothills of the Cascade
6
Mountains, which has maximum elevations of about 4000 feet in the basin. Silver Creek has cut a relatively deep channel through most of the community of Silver Creek. The basin is fairly naffow with channel slopes upstream of Silver Lake Dame in excess of 100 feet per mile. The upper drainage basin is forested and includes portions of Silver Lake State Park and Santiam State Forest. Some logging still occurs. Debris in the form of logs and felled timber enters the lake during large winter storms and some partial blockage of the spillway has occured. These are typically a single large tree and have not caused major problems in the past. Based on historical operation and maintenance records, debris has not and will not likely become a significant emergency problem at the project.
2.3 Current Dam The Silver Creek Dam is located in Silverton, Oregon. Silverton is located about 10 miles northeast of Salem, Oregon, along Silver Creek. The dam was constructed in 1974by the City of Silverton for municipal water supply and recreation. It is owned and maintained by the City of Silverton. The dam is a zoned earth and rockfill embankment with a maximum height above the original ground surface of 65 feet. Embankment slopes are 2H:lV downstream and 3H:1V upstream. Crest width is 20 feet, and crest length 680 feet, including the spillway. The spillway is located on the right abutment and consists of a converging concrete chute with an entrance width of 120 feet. The dam stores approximately 1300 acre-feet of water and is approximately 2 miles upstream from the Silverton downtown area.
2.4 Existing Condition In June 1981, the U.S. Army Corps of Engineers and the Oregon Water Resources Depaftment completed a Phase 1 Inspection Report. It identified the Silver Creek Dam as a high hazatd dam because of the potential loss of life risk and the level of potential property damage. The inspection evaluated abutment and foundation conditions, embankment stability, hydraulic and hydrologic conditions, and structural/mechanical features. The inspection found the dam to be in satisfaetory condition for continued operation. Following a 1993 earthquake, preliminary inquiries were initiated concerning the seismic stabilþ of the dam, and the potential for loss of life and property in the event of a failure of the 65-foot structure. The City of Silverton contracted with Cornforth Consultants to prepare a Seismic Stability Analysis for the Silver Creek Dam. The 1999 report concluded that it is unlikely that an earthquake would result in failure of the dam. Then, in 2000, the City of Silverton contracted with Philip Williams & Associates (PWA) to perform a Dam Break Analysis, based on two dam failure scenarios: piping and overtopping. The study indicates that if a failure due to piping or overtopping were to occur, the failure would be catastrophic to the City of Silverton. The report notes, "Piping failure occurs if water migrates through the dam material and develops a passage. This could be due to inadequate compaction during construction of the dam, or to changes to dam integrity caused by seismic activity, slope failure or vegetation. As water flows (pipes) through the dam material, it continues to carry away more material and the passage grows in size. Eventually the size of the passage compromises the structural integrity of the dam and causes collapse of the structure itself." An overtopping failure is also described generically in the PIWA report. "Over-topping failure occurs when sustained
7
reservoir inflow is greater than the combined spillway discharge and reseryoir storage capacity Eventually the water surface elevation in the reservoir rises above the dam crest, causing flow down the face. Flow over the downstream face of the dam causes erosion. Eventually, the erosion compromises the structural integrity and a breach develops." An overtopping failure scenario was not used as justification for commencement of this study
2.5 Review of Existing Dam Safety Monitoring Program The existing dam safety monitoring program consists of collecting and evaluating water level readings on an annual basis from piezometers installed in the embankment and the right abutment. Flow measurements are also collected from the horizontal drains and the 4-inch diameter perforated pipe drains along the toe of the drainage berm. During this annual inspection visual observations of the total flow and presence of any turbidity in the water from the downstream contact along the left abutment are also made. The results of the measurements and observations are documented in a memorandum that is sent to the Oregon Water Resources Department (OWRD), Dam Safety Division. 2.5.1 Piezometers The water levels in piezometers are read on an annual basis. Typically, readings are made during the month of June after the reservoir has refilled and held full for several months which allows for seepage and ground water conditions to equilibrate with full pool condition. Generally, this is when highest ground water condition occurs. Water level readings are obtained by manually sounding the standpipe using an electronic probe. The probe is lowered into the standpipe until an audible signal indicates that the probe has been submerged in water. The depth to the water from the top of the standpipe is then recorded. The elevation of the water level is calculated by subtracting the depth to water from the elevation of the top of the standpipe.
2.5.2 Flow Measurements from Drains Flow measurements are collected from horizontal drains, and from the 4-inch diameter perforated drain pipes that run along the toe of the drainage berm. Measurements are taken using the timed bucket method. The amount of time that it takes to fill up a bucket of known volume is recorded and used to calculate the flow rate. 2.5.3 Survey Points Four settlement monuments are located on the crest of the dam. The settlement monuments consist of a l-inch diameter steel rod set in concrete. Survey monuments consisting of a bronze disc set in concrete are located on the left and right abutments. This network of survey points is used to monitor for settlement and horizontal offset of the dam crest. Both concrete and survey momuments are set a minimum of 18-inches below the ground surface to provide stability against frost heave and effects of wetting and drying of the soils.
2.5.4 Reservoir Level The reservoir level is recorded during the inspection for comparison with the instrumentation data and seepage observations. This is accomplished using a staff gauge that is located on the spillway training wall, Inspection typically is made during the month of June each year after the reservoir has refilled to full pool and held for several months.
I
2.5.5 Visual Observations Visual observations are made of the general condition of the dam during the inspections. A visual inspection checkoff list is used to maintain consistency over time. The list includes observations of erosion on both the upstream and downstream side of the embankment, the presence of woody vegetation, burrowing animals and wet areas that may indicate seepage, and the flow at weirs and presences of turbidity in the flow. Specific observations have also been documented regarding seepage that is occurring along the downstream contact of the left abutment. These observations have included estimates of the flow rate, the extent of the seepage area, and the clarity of the flow. 2.5 .6 D ata Evaluation/Management The instrument readings are recorded daily and presented as time history plots. The results are compared to reservoir level changes and evaluated regarding increasing or decreasing trends in the seepage performance of the dam. The instrument plots and visual observations are then documented in the memorandum that is sent to the OWRD, Dam Safety Division.
9
3.0 PLAN FORMULATION 3.1 Problems and Opportunities The "silver Creek Dam Break Analysis" report prepared by Philip Williams & Associates in 2000 concluded that an overtopping failure or piping failure would be catastrophic to the City of Silverton. If either were to occur, there is a potential for both significant loss of life and property damage.
Providing a flood warning system would increase the amount of time residents have to evacuate, thereby reducing the risk of loss of life and reducing some portion of damage to property and vehicles.
3.2 Planning Objectives The planning objective is to contribute to the National Economic Development (NED) in a way consistent with protecting the Nation's environment. NED features are those that increase the net value of goods and services provided to the economy of the United States as a whole. Only benefits contributing to the NED may be claimed for economic justification of the project. The specific objective is to reduce the risk of flood damage to Silverton while minimizingor avoiding environmental and cultural impacts to the area. While reducing the risk of life is not a NED planning objective it is an important component. The City of Silverton is situated along Silver Creek two miles downstream of the dam. The results of dam failure would be catastrophic for the City of Silvefion. In the event the dam failed significant portions of the valley would be inundated putting thousands of people in harms way. 3.3 Evaluation of Conditions before Project Improvements Three potential without project scenarios were considered.
I
Overtopping Scenario The "silver Creek Dam Break Analysis" prepared by Philip Williams & Associates in 2000 defined the overtopping scenario. "Over-topping failure occurs when sustained reservoir inflow is greater than the combined spillway discharge and reservoir storage capacity. Eventually the water surface elevation in the reservoir rises above the dam crest, causing flow down the face. Flow over the downstream face of the dam causes erosion. Eventually, the erosion compromises the structural integrity and a breach develops." 3.3.
The report indicates that the water surface elevation (WSE) in the reservoir associated with the overtopping scenario is taken just below the crest of the dam (at 439.3 ft). In order for the WSE to reach this elevation it assumed there is a debris blockage of the spillway. Conceptual flaws in the logic of the debris blockage scenario became apparent with further evaluation. The capacity of the spillway is about 22,400 cubic feet per second (cfs). At one-foot below the top of the dam the capacþ of the spillway is on the order of 18,500 cfs. This is a capacity of 2-ll2 times the 0.2 percent annual probability peak discharge so even very infrequent flood flows would safely pass through the dam spillway. Dam failure due to overtopping would require a blockage of 60 to 75 percent of the spillway capacity. Based on historical operation and
10
maintenance records, debris has not and will not likely become a problem at this project. Therefore, improvements to the existing structure are not required based on the capacity to pass a large flood event. .2 Piping Failure Scenario The Philip Williams and Associates 2000 Dam Break analysis identified potential consequences of a piping failure, but there was no analysis indicating that such a failure is likely to occur. Their piping failure analysis assumed high water. Such high water conditions would require a blockage of the spillway and this has been determined to be highly unlikely. 3 .3
3.3.3 Seepage Failure Scenario Silver Creek Dam was designed and constructed in accordance with the state of the industry at the time, and is considered a safe dam, but all dams have some risk of failure. The dam was designed and constructed in the early 1970s in accordance with the state of the industry atthattime. The structure failed to perform in an acceptable manner due to seepage problems affecting the right side of the dam and the right abutment. Mitigative actions were implemented which appear to have successfully corrected the problem. The structure has performed in a satisfactory manner since, and has been deemed to be safe for continued operation
with no restrictions. Historically 2.0 percent of embankment dams experience failure or incidents of unsatisfactory behavior due to internal erosion or piping (Fell et aL.2003). Seepage occurs in all dams, and is not a problem unless the seepage is able to move material in the structure causing it to be less able to resist additional seepage, normally referred to as internal erosion or piping. Seepage in dams can over time develop conditions that will result in higher volumes of flow and significant internal erosion of the structure, abutments, or foundation. This erosion, if not detected, will normally result in failure of the structure. In most earthen dams seepage is controlled by the interaction of an impervious zone, upstream and downstream filters, and the material making up the mass of the dam. Seepage problems result when there is an incompatibility of embankment materials or an incompatibility of the embankment materials and the foundation or abutments. There is usually some attempt made to ensure the abutments and foundation of the structure are compatible with the structure and are themselves not prone to seepage failure. In some cases embankment material can be eroded into a more porous foundation or abutment, resulting in eventual failure of the structure, but with no obvious downstream seepage. An example being the failure of the right abutment of Canyon Meadows Dam, Grant County, Oregon, where embankment material'was over time eroded into a more pervious right abutment landslide deposit. This condition eventually lead to the inability of the structure to store water and would have resulted in a catastrophic failure of the dam had it not been for the nature of the downstream shell of the dam. In the case of Silver Creek Dam, the right abutment is composed of landslide material. The formation is relatively porous in nature, and probably prone to seepage problems, based upon observation made in the two borings made during foundation investigations. In an attempt to prevent excessive abutment seepage an upstream impervious blanket was placed on the abutment from the dam for some distance upstream. The purpose of the blanket was to increase the length ofthe seepage path so that seepage pressures would be reduced to an acceptable level. Conditions in the abutment were not as assumed or the upstream blanket was compromised in
11
filling of the dam. The seepage was downstream shell of the dam, into the and believed to be coming through the abutment horizontal drains were threatening the stability of the structure. The pool was drawn down, installed into the abutment, and additional material was added to the downstream slope of the dam at the abutment. These actions appear to have been successful in controlling the seepage at the present time. However, some potential for unsatisfactory performance in the future remains. some manner resulting in excessive seepage during the f,rst
Determination of the Probability of Unsatisfoctory Perþrmance: The probability of unsatisfactory performance due to seepage was evaluated using a procedure developed by MA Foster, R. Fell, and M. Spannagle (1998) "Analysis of Embankment Dam Incidents," The University of New South Wales, UNIGIV Report No. R-374. This procedure evaluates the structure against the performance of other similar embankment dams, is intended only to determine the probability of unsatisfactory performance, and does not determine a factor of safety for seepage related problems. A spreadsheet was developed based upon this procedure. The formulas and selected weighting factors and the procedure and weighting factor selection criteria are shown in Appendix A. The computed annual probability of failure due to seepage and piping is 0.0032. Determination of Rate of Failure: The time required for failure of the structure is that amount of time from initiation of piping to the loss of pool. The value was determined using the procedure presented by Fell, Wan, Cyganiewicz, and Foster (April 2003) "Time for Development of Internal Erosion and Piping in Embankment Dams" Journal of Geotechnical and Geoenvironmental Engineering,Yol. 729,Issue 4. As with the above process to estimate probability of unsatisfactory performance this procedure generates a rate offailure based upon the historical performance of similar structures. Based upon this procedure it is probable that the time between initiation of a piping failure and actual failure will be between 12 and 24 hours.
3.4 Seepage Failure Scenario before Project Improvements 3.4.1 Overview Although all three failure scenarios were found to be highly unlikely, the seepage failure scenario was determined to be the most likely and therefore carried forward in this analysis. The Silver Creek Dam Break Analysis report (PWA 2000) indicates that a flood wave would travel down the Silver Creek channel reaching the downtown area within 15 minutes of the failure with flood wave heights in excess of 10 feet in some areas.
If failure were to occur, there is a potential for both significant loss of life and property damage. The potential for loss of life is high because of the proximity of the Silver Creek Dam to the population in the city of Silverton. While loss of life is not considered part of the economic justification for a flood warning system, it is a key issue. The Silver Creek Dam sets just 2 miles upstream of a highly populated area in the city. The Dam Break Analysis indicates that in the existing condition, water could travel to the downtown area within 15 minutes and that the floodwave would progress through the study area in approximately I hour. The average wave speed through the 4.12-mile study area is approximately 6 feet per second (fps). The depth of water would vary, but would range between 6.0 feet and 15.8 feet within the area impacted by the 1 percent annual flood event. With the depth, velocity, and short timeframe, several lives could be lost.
t2
3.4.2Property Damages A significant number of properties lie within the flood inundation boundary. Therefore, there is a corresponding potential for significant property losses ifthe dam failure event occurs. Structural damages to residential and commercial properties cannot be prevented by a flood warning system. However, some portion of damages to contents and vehicles can be prevented. Consequently, only those categories are evaluated.
Residential Properties;Average home cost in Silverton is $203,956 (source: Coldwell Banker)' Assuming thatTl3 of the value is for land, then remaining average structure value is about $135,000. EGM 0l-03 for generic depth-damage relationships shows content damages as a percentage of structure value. Housing stock is split between 1-story no basement and 2-story no basement structures. Percentage damages are38.4o/o and32.0Yo, respectively. As an average, use 35%ofor the average l0-foot floodwater depth. There are over 800 residential properties in the zone of dam failure inundation.
Structure Value Content Damase%o
$
135,000
3s%
Subtotal: properties Number of Total Content Damage:
$13s,000 0.3s
s47,250 800
800
$37.800,000
Based on the seepage evaluation, an event has a frequency of I in3l2 years. It is estimated such an event would result in over $37 million dollars in residential content damages, and equates to $173,900 in average annual damages.
Non-Residential Properfies.' Assume a conservative structure value of $200,000 for nonresidential properties. There are a few fairly large properties, as well as many small commercial properties. There are two schools and a care home in the inundation zone. There are over 100 non-residential properties in the zone of dam failure inundation. For this estimate, the 1995 FIA commercial contents depth-damage relationship will be used. At a depth of 10 feet, the percentage of content damages is 59.98% (round to 60%). For this estimate, contents are assumed to be half the value of the structure or $100,000.
Contents Value Content DamageYo Subtotal properties Number of
$100,000
$100,000
60%
0.6
$60,000 100
100
$6.000.000
Total
Based on the seepage evaluation, an event has a frequency of I in3l2 years. It is estimated such an event would result in $6 million dollars in non-residential content damages, and equates to $27,600 in average annual damages.
13
Vehicles: It is assumed there are L5 vehicles per residence. The Institute for Water Resources (IWR) funded a post flood survey in Salem, Oregon following the 1996 flood, with over 800 residences in the sample, and it showed that there were 1.5 vehicles per home in the flooded area (IWR 1997). With over 800 residences in the inundation footprint, it is assumed there are 1200 vehicles in the footprint. While more vehicles may happen to be at non-residential properties during an event, they were not accounted for so as to avoid double-counting. Also, some residents may be gone to work outside the footprint during an event. To be conservative, it will be assumed that 80 percent of the vehicles will be in the footprint during an event in the night and evening hours, while 50 percent will be in the footprint during work hours. Weighting the two equally, a conservative approach, results in about 65 percent ofthe 1200 vehicles having a probability of being in the footprint during an event. Sixty-five percent of 1200 vehicles is 780 vehicles. With an average water depth of l0 feet, assume the loss of the vehicles. Assume an average value of$7,500 per vehicle, for 780 vehicles, or $5,850,000. Based on the seepage evaluation, an event has a frequency of I in3I2 years. It is estimated such an event would result in almost $6 million dollars in vehicle damages, and equates to $26,900 in average annual damages.
3.5 Alternative Analysis Typically, in addition to the without project condition (no action plan), both structural and nonstructural alternatives would be considered. However, there are no reasonable structural improvements to consider and the Sponsor is not interested in pursuing structural alternatives. One non-structural alternative to be considered is a flood warning system. Given the short warning time the only feasible approach is to establish a flood warning system that will: 1. Detect a developing condition and2. Provide time to initiate the notification/evacuation of people based on a "failure is imminent" condition.
3.5.1 Flood Waming System A flood warning system that provides sufficient time for residents to evacuate in the event of a dam failure will reduce or eliminate the loss of life and a portion of the property damages (typically contents and vehicles). The proposed early warning system consists of the detection system and the notification system/evacuation plan. The detection system is to identif, a developing condition of concern in advance of failure. The notification system is used to communicate to all inhabitants in the inundation area of Silverton. The evacuation plan outlines how people are to exit the inundation zone.
The detection component includes improvements to the current monitoring equipment and installation of new equipment. Design components include reservoir level monitoring instruments, piezometers with vibrating wire pressure transducers to detect changes in seepage performance, weir box instruments to collect and measure seepage, and installing an onsite
monitoring station. The notification system/evacuation plan will be a combination of methods to insure evacuation of the inundation zone. The proposed system consists of a siren network and a personal notification
t4
component. In addition, certain procedures and policies such as notification flow charts, ongoing testing, maintenance and public education will be required.
3.5.2 Flood Warning System Costs The cost estimate for installation of a flood warning system at Silverton is $616,100 plus $5,000 peryear in operation and maintenance expense. Average annual costs are $37,000 based on the discount rate of 5.625 percent and 50 year project life plus $5,000 peryear in operation and maintenance expense. Refer to the Recommended Plan Section and Baseline Cost Estimate Appendix for additional details. 3.6 Potential Reduction to Property l)amages with Flood'Warning Time The Day Curve estimates potential reductions in content damages, given additional flood warning time. (See the "National Economic Development Procedures Manual-Urban Flood Damage," IWR Report 88-R-2, dated March 19S8). Results are summarized in the following two tables, based on the potential additional time provided by a flood warning system. The estimates based on engineering judgment indicate potential flood warning time ranging from 6 to 18 hours.
Potential Reduction in Residential and Non-Residential Content
(HOURS)
REDUCTION IN DAMAGES
EXPECTED REDUCTION IN AVERAGE ANNUAL CONTENT DAMAGES
6
13.5
s27,200
t8
26
$52,400
ADDITIONAL TIME
PERCENT
Potential Reduction in Vehicle REDUCTION IN DAMAGES
EXPECTED REDUCTION IN AVERAGE ANNUAL VEHICLE DAMAGES
6
80
$21,s00
18
90
s24,200
ADDITIONAL TIME (HOURS)
PERCENT
The following table is a summary of benefits due to the implementation of a Flood Warning System depending on the additional time to evacuate the inundation zone.
15
of Benefits Due to Added Flood
6
l8
4.0 RECOMMENDED PLAN 4.1 Overview The early warning system itself consists of two subsystems that have individual performance objectives but are fully integrated into the overall system. These include the detection system and the notification system. A third and critical component of a flood-warning program is the evacuation plan. The evacuation plan identifres specific evacuation zones within the inundation area andthe routes for the movement of the evacuees out of the inundation areas. The primary objective of the detection system is to identifu a developing condition of concern tn advance of failure to allow time for making a decision regarding evacuation. The detection system has a secondary purpose of providing information to assist in the decision making process during a developing condition of concern. The notification system is used to communicate the need to evacuate once the decision that failure is imminent has been made. The objective of the Silver Creek Dam notification system design is to provide notification to all inhabitants in the downstream inundation area within the city limits of Silverton, so that they may be evacuated. The following sections describe the recommended design for the detection and notification system. The described system is similar to what was presented in the preliminary design report prepared for the City of Silverton by Squier Associates (April 2003).
4.2Detection System The recommended detection system consists of improving the monitoring capability by enhancing existing instruments and adding new instruments installed at various locations on the dam. The improvements will include: 4.2. 1 Reservoir Monitoring Install a reservoir level monitoring instrument that includes the use of a vibrating wire pressure transducer to monitor the reservoir water level, and detect a rapidly rising/dropping reservoir level condition. Redundancy will be provided by a reservoir staff gauge that can be read manually or by remote video camera. Consideration will be made of using a second pressure transducer to provide redundancy.
4.2.2 Upgrading Piezometers Outfit the existing piezometers with vibrating wire pressure transducers to detect changes in the seepage performance of the dam and abutments. 4.2.3 Wefu Box Instrumentation Install new weir box instruments to collect and measure seepage at the toe of the dam, the contact with the left abutment, and from the horizontal drains. The weirs will be used to monitor changes in the seepage performance of the dam. 4.2.4 Monitoring Station Install a monitoring station at the dam to provide a base station for on-site monitoring during an alarm condition.
1,7
4.2.5 Reservoir Gauge A new Reservoir Level Site Gauge will be installed to provide a back-up point of reference for visual monitoring during high flow condition. A remote controlled camera will be installed to visually observe the reservoir staffgauge and to observe the critical outlet controls for security purposes.
4.2.6 Measurement Control Units sensors would be connected to Measurement Control Units (MCU) that would collect the data from the sensors and compare the readings to predetermined threshold values. If a threshold value is exceeded and verified by redundant instrument values, then the MCU network will initiate a phone call to the assigned city personnel to alert of a developing condition of concern.
All of the automated
4.2.7 Additional Detection System Details A more detailed discussion of the individual system components follows Automated Data Acquisition and Alarm Notffication: The MCU located at the dam will collect the data from the instruments and compare the data to threshold values. This MCU will also collect and store readings on a daily basis from the other MCU's for use in long term performance and trending evaluations. Each MCU will be programmed with logic such that it will independently poll its sensor's and compare the readings to predetermined threshold levels. This architecture strengthens the integrity of the system by reducing the risk of the entire system going down due to an equipment failure of one component. Resemoir Level Monitoring: An automated sensor will be installed to monitor the reservoir level. This instrument will be located on the upstream face of the dam and will be installed within a PVC pipe buried on the face. The sensor will be located at approximately elevation 400 feet. The instrument will be monitored hourly and compared to the threshold levels. If the reservoir level rises to within 8 feet of the crest, then the system will activate the callout procedure to City personnel to indicate a condition of concern. The reservoir level monitoring will also be used during an alarm condition to keep track of the reservoir level and rate of rise. During normal operation, daily readings will be stored for use in evaluating the historical performance of the piezometers and weirs. A manually read site gauge will also be installed to provide a visual confirmation of the reservoir level during a flooding condition. This gauge will be constructed in the vicinity of the right abutment at an elevation of 430 feet so it can be easily observed during a developing unstable condition. Piezometer Level Monitoring: Ín order to improve the ability to detect changes in the seepage performance of the dam and right abutment, automated sensors will be added to the existing piezometers. These sensors will be monitored hourly and compared to predetermined threshold levels. If a threshold level is exceeded, the system will activate the callout procedure to City personnel to indicate a developing condition of concern. In addition to the hourly readings, daily readings will be stored for historical evaluation purposes.
Monitoring: Excessive seepage through the dam or at the contact with the abutments could lead to a developing unstable condition. To monitor for this condition, weir boxes will be installed. The weir boxes will measure the flow rates from the horizontal drains and 4-inch diameter toe drains that are currently installed in the dam. One of the weir boxes will be Seepage Flow
18
used to collect and measure seepage from the left abutment contact area. Flow measurement will be collected hourly and compared to predetermined threshold values. If a threshold level is exceeded, then the system will activate the callout procedure to City personnel to indicate a developing condition of concern. In addition to the hourly readings, daily readings will be stored
for historical evaluation purposes. Data Evaluation/Management: Data will be recorded daily for historical evaluation purposes. The purpose of collecting and evaluating this performance data on a regular basis is to identiff developing conditions ofconcern through observation of increasing or decreasing trends in the dam's long-term performance. This regular monitoring is a key part of developing an understanding of how the dam normally performs so that changes in performance can be detected and properly evaluated regarding the on-going safety of the dam. Because of the quantity of data being collected and the long term monitoring objective of the system, a database application needs to be integrated with the system. The database application will be installed on a personal computer in the City's ofhce and will be used to manage and evaluate the data. The database will also aid in dam-safety reporting tasks. On-Site Monitoring Station: In addition to the automated instruments, an On-site Monitoring Station will be constructed on the right abutment above the fish ladder. The On-site Monitoring Station will be used during alarm conditions to monitor the on-going instrument readings and to make visual observations of the dam structure. The structure will be a prefabricated building that will house the MCU station. In addition, the building will be equipped with floodlights for use in observing the condition ofthe dam at night and a telephone that can be used to call out as part of the notification callout procedures. A permanently installed generator within the station building will power the floodlights in the event of a power failure. The building will also have a laddèr installed to provide access to the roof of the building to provide a better vantage point for observing the dam.
4.3 Notification System The Notification System is designed to provide evacuation notification to the people inhabiting the flood inundation area (Figure I shows inundation area). This includes inhabitants with disabilities such as the hearing-impaired and the blind. In addition to the people inhabiting the flood inundation area, certain emergency response personnel must be notified in a timely fashion to assure proper and orderly execution of the emergency response plan. The boundaries of the flood inundation area are based on the failure scenario as presented in the Silver Creek Dam Break Analysis Report, (PWA, January 18, 2000). The evacuation notice would be issued as a result of an "imminent dam failure condition". In order to properly discern a dam failure notification from other types of disasters, the Notification System would also include instructions to the public as to the nature of the evacuation. 4.3.
I Alternative Notihcation Options
Various notification altematives with different strengths and weaknesses were evaluated TV or Radio Broadcast Notification: This type of notification is based on using television or radio station broadcasts to provide flood notification to the public. In an emergency, special messages would be broadcasted to the public. Strengths:
t9
. Instant communication to all affected people. . Gives detailed information and can keep people up-to-date. . Generally available (most people have TV's). Weaknesses:
. Emergency management control is limited (involvement by broadcast stations
is
voluntary).
. Only applicable to local cable and antenna broadcast stations (satellite or non-local programming would not carry the broadcast). . Limited usefulness during most times of day or when TV/radio is turned off. . Limited usefulness for people outside of the house at time of emergency. . Not a selective broadcast audience so emergency message will carry to all people receiving TV/radio signal. . Not available during po\À/er outages. . Not able to reach sight or hearing-impaired citizens unless specially equipped with TDD/TDY equipment. This type of notification is typically used for school closures and other types of warning or news information affecting alarge population area with notifications that do not require immediate action. Therefore, using this type of notification for the early warning system is not feasible. Audible Sirens: Audible sirens provide immediate notification by broadcasting a tone consisting of a siren wail and a voice message. Audible sirens typically consist of equipment mounted on a utility pole and can include options to broadcast prerecorded voice messages to provide instructions during an evacuation. Most sirens are powered by AC povver with a battery backup system in case of power outages and can be controlled via a direct telephone type connection or individually via radio signal from a central Siren Control Unit. Audible sirens are available in both a directional signal of varying degrees and an omni- directional signal broadcasting in a 360o circle. Both types of sirens come in models that can broadcast varying distances up to approximately 5,000 feet. In order to assure appropriate sound quality, the audible sirens are driven by speaker amplifiers similar to those used in public address systems or large music concerts. Strengths:
. Instant communication to all affected people. . Can give detailed informatión as to what action to take. . Easily maintained and City owned. . Flexible and expandable for future emergency action plans. . Available during both phone and electric outages. Weaknesses:
. Limited usefulness for people inside sound dampening facilities/buildings at time of emergency, or for the hearing-impaired. . Not a selective broadcast audience so emergency message will carry to all people within sound range.
An additional method of siren notification is via sirens or warning lights installed within special structures or facilities such as police departments, fire stations, hospitals, etc. Buzzers, sirens,
20
and/or waming lights can be installed within the structures or buildings housing these facilities to provide notification to the occupants or special personnel within these facilities.
Notification Via Automated Telephone Service: The use of automated telephone services is another type of notification system available. Automated telephone notification is a service provided by an outside (non-City) service provider that uses a computer to phone the affected population, delivering a warning message or evacuation notice. If the line is busy or does not answer the computer keeps dialing the number. If an answering machine answers the phone then the notification message is recorded. To initiate this type of notification system, a phone call is placed to the telephone service provider. Once security authentication is completed, the service provider starts a call-out operation to notifu the population of the need to evacuate. Most service providers operate with the ability to place 200 calls simultaneously, with the average callout capacity of approximately 3000 calls in one hour (based on a 2O-second notification message). Typically, these service providers charge an initial "setup fee", an annual "subscriber fee", and a per call charge for each number called during the emergency. Strengths:
. Targeted, rapid notification to only those affected or "on the phone call lisf' . Can give detailed information as to what action to take. . Relatively low cost. Weaknesses:
. Only effective if people have a phone,
and it is turned on, it is not in use, and they answer the call. . Cannot reach people if they are not within reach of the phone (outdoors). . Not available during telephone outages. . Not effective for hearing-impaired people unless TDD/TDY equipment is used.
Mobile Loudspeakers.' Another type of notification method is the use of loudspeakers mounted in vehicles. Police or fire crews typically carry out this notification method by driving a vehicle with a loudspeaker through the effected area broadcasting a live or recorded message to the public. Strengths:
. Targeted notification to only those affected. . High degree of credibility to audience. Weaknesses:
. Limited information can be delivered. . Only a limited area can be notified quickly. . Cannot reach hearing-impaired people. . Messages can be hard to decipher if people are indoors. . Risks exposure to personnel delivering message. . Ijses equipment and personnel that could be used more efficiently elsewhere. Personal Notification: Waming each and every citizen personally in the aflected area is also a method of notification. With this method, police officers, ftre crew, or City personnel would
2l
spread out and blanket the entire inundation area, delivering the evacuation notice personally to all occupants. While this method does insure notification to everyone within the inundation zone, it is not feasible to use it as the only notification system because of the limited amount of time available to get the notice to the evacuees. Similar to the use of mobile loudspeakers, this method of notification is only effective for small areas and taking the crews away from other more essential tasks and risking the personnel and equipment going door-to-door.
Strengths:
. Targeted notification to only those affected. . High degree of credibility to audience. . Very strategic notification. . Can reach all people, including those with disabilities. Weaknesses:
. Extremely time consuming . Risks exposure to personnel delivering message. . Uses equipment and personnel that could be used more efficiently elsewhere 4. 3.2 Recommended Notification System After examining the strengths and weakness of each of the systems, it is recommend that a combination of methods should be used to provide evacuation notification for the early warning system. The recommended system improvements consist of a siren network and a personal notification component. In addition to notification sirens and personal notification, certain procedures and polices such as notification flow charts, on-going testing, maintenance, and public education, are recommended to assure proper operation of the notification system. When the evacuation notice is executed, the audible siren network will be used to notiff the majority of the population. The notification flow chart will be used as a guide to notif, certain City, police, and fire department personnel as part of the emergency response plan. For the population within the inundation zone with disabilities, the personal notification component will be used to assure they receive the evacuation notification and assistance as necessary.
4.3.3 Specific Notification System Components Audibte Sirens: To provide audible notification to the general public, four sirens will be installed. Locations are shown on Figure l. Each of the audible sirens is controlled by a centrally located Siren Control Unit which uses radio frequency broadcasts to control the sirens located throughout the evacuation zones. When the evacuation notice is executed, the sirens will broadcast a wail tone followed by a prerecorded voice message such as: "Silver Creek Dam emergency. Evacuate the area immediately". In addition to the warning tone and message, an all clear message such as: "It is safe to return; Silver Creek Dam is secure" will be used to indicate when the flood risk has subsided.
Notification Flow Charts: Details of who will be notified should be evaluated and incorporated into the City's Emergency Action Plan as Notification Flow Charts. The Notification Flow charts will be used as a guide to execute a call out to certain City staff and crew that are expected to respond to the evacuation emergency action plan. Any inter-agency coordination or notification (i.e., interagency coordinators, Marion County, downstream communities, etc.) will also be warned via the Notification Flow Charts. The specific details will be developed as part of the
22
design and construction phases
Personal Notificationfor the People l{ith Disabilities: Another vital component of the Notification System is a system or procedure to provide notification to the population within the flood inundation area that have disabilities. The police department should maintain a list of addresses of households for people with disabilities that will be affected by the flood inundation. This list of households will then be used during an evacuation event so that police and fire personnel will notifr those households personally and can provide assistance as necessary. The individual who will be responsible for assuring the households have been notified and evacuated should be identified in the Notification Flow Charts. Policies and Procedures: Policies and procedures should be incorporated into the City's Emergency Action Plan to assure proper execution of an evacuation. These policies and procedures should include:
. . . . . .
A Notification Flow Chart. A comprehensive public education program. An on-going public awareness program. An on-going interagency and interdepartmental coordination program. Regular scheduled maintenance of the notification equipment. Regular testing of the notification system and evacuation procedures.
4.4 Evacuation Plan A preliminary evacuation plan for the Silver Creek Dam Early Warning System has been formulated. Essentially the evacuation plan shows how the inundation area is subdivided into specific evacuation zones and identifies general routes for the movement of the evacuees out of the inundation areas. For this plan, it is assumed that most evacuees will use automobiles as the method of evacuation. Some areas located in remote locations adjacent to Silver Creek might be required to evacuate on foot if floods or other conditions have damaged roads or private driveways to the point where they are impassible by automobile. Evacuation of the facilities located within the inundation zone requiring special attention, such as schools, are also discussed. Coordination ofemergency personnel is vital to the success ofan evacuation and a brief description of that effort is provided.
I
Recommended Evacuation Zones To facilitate movement of inhabitants within the inundation zone, evacuation zones will be identified. It has been determined that for each zone there will be more than one evacuation route with a road or highway to be used to carry the flow of vehicular traffic. [n order to facilitate vehicular traffic flow during the evacuation, an Evacuation Traffic Control Plan will be created by the City and made part of the evacuation plan. Recommended road closures, vehicle traffic counts, one-way traffic flow, and traffic direction by emergency personnel, barricades, etc. will be considered and planned for. 4.4.
4 .4 .2 Ev acuations of Spe cial Facilities/Structure s In addition to evacuation zones, special facilities such as schools or other buildings that have a large number of inhabitants require special coordination to assure that the occupants are evacuated. Both Eugene Field Elementary School and Silverton Union High School are located within the inundation zone. Each of these schools should receive the notification of the
23
"Developing Alarm" condition and should initiate procedures to prepare for evacuation before the evacuation order is given. Occupants from the Silverton Union High School may be able to evacuate on foot to higher ground outside of the inundation zone to the west. However, the location of Eugene Field Elementary School precludes this alternative, and busing of the students will most likely be required.
4.4.3 Coordination of Emergency Response During an evacuation, the coordination of City, police, fire, and medical personnel is essential. To achieve an orchestrated response and to assure the proper personnel are notified, two notification flow charts should be developed. The notification flow charts should be based on the following alarm conditions : . Unstable Condition has Developed . Failure is Imminent or Has Occurred The flow charts should provide a detailed process of notification for the individual alarm conditions. The notification flow chart should detail the names, titles, and phone numbers of those who are responsible for notification, from the individual observer to the responsible agency representatives. The flow chart should denote the priority or order in which each person on the chart is notified. The Notification Flow Chart should be distributed to all key supervisory and operational employees. The chart itself should be posted at key locations such as, but not limited to:
. On-site Monitoring Station at the dam; . City Hall (administrative offices); . Police Station (dispatch); . City Shops (maintenance facilities); and . Fire Stations. In addition to the notification flow charts, all personnel must be hained on the proper response including where and how they report in and what their responsibilities are during the alarm conditions. Each assignment must be fully understood and coordinated. The agency that will coordinate the evacuation must be identified and an emergency chain of command must be established in advance. The following is a brief description of some of the responsibilities that each agency should be planning for. The final evacuation plan should include the names of the individuals and what they will be responsible for under each alarm condition.
4.4.3.1Police Generally, the police department should direct the evacuation operations. They should establish and maintain an outer perimeter to maintain the outward flow of traffic from the inundation area. They should provide for traffic and crowd control. They should be prepared to provide security for any emergency housing or shelter facilities established during the evacuation.
4.4.3.2 City Staff During an evacuation order, City Staffshould be prepared to provide resources such as vehicles equipment, and personnel to assist with traffic movement and crowd control. They should also be prepared to keep evacuation routes open and free ofdebris and to provide signs and barricades for traffic control.
4.4.3.3 Fire Fire personnel should establish and maintain an inner perimeter of the inundation zones. They
24
should be prepared to rescue trapped victims within the inundation zones or provide assistance to evacuees with special needs that cannot otherwise leave the area on their own. They should provide fire stations for use as reception points for the evacuees. They should assist in the evacuation process as requested by the Police department or incident command. 4.4.3 .4 Interagency Coordination
In addition to the coordination of the City services, interagency coordination must be established to aid in the evacuation process and to notifr other populated areas downstream of the City of the Silverton. The City's Emergency Management Coordinator should compile a list of all agencies that should be notifred when the City's evacuation order is given.
4.5 Environmental Impacts The early warning system will include a detection system and notification system. The detection system will require minor ground disturbance to install sensors within the dam structure itself, improvements and upgrades to current monitoring equipment, and the installation of a small, prefabricated shed to house the monitoring station. The notification system will require the installation of a siren network that will include four, pole-mounted sirens on existing right-ofways within the city of Silverton. No in-water work is planned for the construction activities. The scale of construction activities for this project is considered small' Federally listed species that may occur in the proposed project area include bald eagle (Haliaeetus leucocephalzs), Fender's blue butterfly (Icaricia icarioidesfenderi), golden Indian paintbrush (Castilleja levisectc), Willamette daisy (Erigeron decumbens var. decumbens), Howellia (Howellia aquatilis), Bradshaw's lomatium (Lomatium bradshav,ii), Kincaid's lupine (Lupinus sulphureus var. kincaidil), Nelson's checker-mallow (sidalcea nelsoniana), steelhead (Onc or hync hus my ki s s), and Chinook s almon (Onc ho rync hu s t s høwyt s c ha). Based upon site surveys, literature searches, discussions with natural resource agency personnel, and considering the scale of disturbance associated with this project, it was determined that there will no effect to any threatened or endangered species or critical habitat.
4.6 Cultural Resources will be minor earth disturbance to install and upgrade sensor and monitoring equipment at the Silver Creek Dam. The siren network will include installing four, pole-mounted sirens on existing road right-of-ways at locations within the city of Silverton. All construction activity will occur on or adjacent to the existing dam structure or on previously disturbed sites. The scale of construction activities for this proposal is considered small. It is unlikely that any cultural resources would be affected by construction activities.
There
4.1 Geotechnical
Silver Creek Dam is located in the foothills of the Cascade Range Physiographic Province of Oregon near the margin of the Willamette Valley. The area is characterizedby eroded terrain of accordant peaks and ridges, with moderate to steep sided dendritic stream valleys. At the dam site elevations range from 350 feet in the valley floor to over 1000 feet on the surrounding ridges. Landforms along the creek include alluvial terraces, benches, bluffs formed by basalt flows, and hummocky surfaces of landslide deposits. Extensive landslides have been mapped along the north side of the valley at, and near the dam site. These landslides have developed at locations
25
where weak marine sedimentary rocks underlie thick flows of Columbia River Basalt, and at deeply incised portions of the stream valley. The slide debris at the site is generally composed of fragmented angular basalt with a fine-grained plastic silt matrix. The material is dense to very dense. No major geologic structures have been identified at the dam site. Columbia River Basalt is exposed in the left abutment, and alluvial deposits of sandy gravel cover the valley floor. There are no known regional faults at the site.
4.8 Real Estate The lands, easements and rights of way in possession of the city are adequate to fulfill project requirements. The lands for Silver Creek Dam, where the dam monitoring instruments will be sited, were acquired by the City of Silverton through a condemnation action in June 1974. Itis located in the NE %, NE % of Section 12, Township 7 South, Range 1 West, Willamette Meridian, Marion County, Oregon. Access to the dam is via boat. A boat ramp currently exists on Silverton Reservoir only a few hundred yards away from the dam. In addition to monitoring instrumentation, four sirens are proposed throughout the city of Silverton. Although the exact footprint of each siren location will be determined during plans and specifications, the towers for each siren will be on city owned property or right-of-way. The total acreage for the dam safety monitoring structures, associated warning systems, and appurtenant equipment is estimated to be 0.1 acres. A slightly modified utility easement estate has been used for LERRD crediting purposes. The total LERRD credit for the project is considered to have a value of $4,000 ($500 x 4 tower sites * $2,000 for improvements on or near the dam). The city understands and has agreed to the requirements established by P.L. 97-646, although no relocations are expected. 4.9 Cost Estimate Estimated costs for the implementation phase are presented in the complete Baseline Cost Estimate shown in Appendix B. The cost estimate is based on the design as described in the previous sections, equipment and material quotes, standard labor rates, anticipated time required to complete the work, and on typical unit costs. Consideration was given to constructability. To allow for uncertainties and unknowns that will remain until the design and installation details are finalized in the next phase of work, the cost estimate includes a 15 percent contingency.
26
5.0 COMPLIANCE AND COORDINATION 5.1 Regulatory Compliance and Environmental Statutes
The proposed action does not have significant effects on the qualþ of the human environment. Under EF.-200-2-2 (Procedures for Implementing NEPA), the proposed action is categorically excluded. The Categorical Exclusion satisfies the requirement for meeting the National Environmental Policy Act (NEPA) compliance procedures. An environmental assessment is not required. Endangered Species Act: It was determined that there would be no effect to any endangered or threatened species or their critical habitat. Clean Water
Act:
There
will
be no
fill in any waters
of the United States.
Cultural Resources: Due to the scale of proposed activities, it is unlikely that any cultural resources would be affected by construction, operation, and maintenance activities. 5.2 Public and Agency Coordination The proposed action has been coordinated with resource agencies including the U.S. Fish and Wildlife Service, NOAA-Fisheries, and the Oregon Department of Fish and Wildlife.
27
6.0 IMPLEMENTATION PLAN AND SCHEDULE Implementation of the system improvements includes new instrumentation, the Automated Data
Acquisition System (ADAS), the data evaluation/management tool, and the notification system and would need to be programmed and installed. 6.1 Finalizing Remaining Implementation Details The remaining design and installation details that need to be determined in the implementation phase consist of 1) developing project database and data management tools using Damsmart,2) interconnecting the system into the City's Scada system, 3) developing threshold levels for the instrumentation, 4) final siting of the siren locations, and 5) frnalizing the details of the notification and evacuation procedures. In addition, the City is concerned about vandalism at the dam site. The final installation details will need to consider methods for reducing the exposure of the equipment. A detailed implementation schedule should be prepared that defines when the components will need to be installed and operational. 6.2 Tasks and Responsibilities In general, the implementation phase will include six main tasks: 1) System construction, 2) System installation, 3) System calibration and testing, 4) Preparing Operations and Maintenance Documentation, 5) Training on the use and required maintenance of the monitoring and early warning system, and 6) Educating the public about the system and how they should respond during an
incident. The system construction task will consist of procuring the instrumentation, ADAS, and notification equipment; programming the ADAS; development and programming of the database tool; and performing bench tests of the detection and notification system components. The bench testing is performed in a controlled environment to assure that the system components are working properly and communicating appropriately before they are installed. Installation of the systems would then proceed with 1 ) installing the new instrumentation, 2) installing the MCU' s, 3) installing the data evaluation database tool, 4) installing the notification sirens and 5) performing a complete test of the system operation to demonstratethat it is functioning properly. Operations and maintenance documentation will be prepared to provide guidance for the operation and maintenance of the detection and notification systems. This would also include documentation on the system configuration. The operations and maintenance documents will serve as the main references for the training task. After the system has been successfully installed and tested, the training task will be performed. The training will involve a discussion of the response procedures for alarm conditions, activation ofthe notification system and how to operate and maintain the system. The task will also include "hands on" experience for the users in performing the typical operations that will be required for successful operation of the system, including the education of the public. This task will be considered complete when the system has been accepted in accordance with the plan as described in the following section.
28
6.3 Acceptance Criteria Plan The Acceptance Criteria Plan (ACP) outlines necessary acceptance criteria for successful completion of the implementation phase. The ACP is initially developed by the system developers and then reviewed and commented on by the City of Silverton personnel. The acceptance criteria plan will be used during the system training session for final acceptance of the system. The system will be deemed successfully complete when the following items are completed to the satisfaction of the City or otherwise resolved with the development team. 1. Demonstrated ability to detect and notiff City personnel of an exceedance of threshold levels representing a developing condition of concern at the Dam. 2. Demonstrated ability to transfer historical instrument data from MCU to the designated City workstation PC using a telephone modem communication link. 3. Demonstrated the abilþ to initiate a reading of the instruments from the remote workstation PC and the on-site monitoring station using a laptop PC. 4. Demonstrated the ability to activate the evacuation notification system. 5. Demonstrated the ability to test (silent and/or audible) the evacuation notihcation system. 6. Demonstrated the ability to load the dam monitoring instrumentation data into the database application and generate the required time history plots for on going dam safety
evaluation. 7.The Operations and Maintenance provides the information needed to operate and maintain the system. 8. The user training session objectives have been completed. 9. Public has been notified and educated.
6.4 Schedule Plans and Specifications Phase: Initiate December 2004 Construction Phase: Initiate April2005
29
7.0 CONCLUSIONS AND RECOMMENDATION 7.1 Conclusion Installation of a flood warning system in Silverton is economically justified based on the analysis of the benefits and costs. Assuming the more conservative estimate of 6 additional hours for evacuation, the benefit to cost ratio is 1.2 to l 0.
Most importantly, providing a flood warning system would increase the amount of time residents have to evacuate, thereby reducing the risk ofloss oflife. 7.2 Recommendation The results of this study provide a design for an improved monitoring and early warning system for the Silver Creek Dam in Silverton, Oregon. The system design is based on the need to improve the ability to detect a developing condition of concern regarding the safety of the dam, and to provide a system for notif,ing the downstream inhabitants of the need to evacuate under and imminent failure condition. phase of work include finalizing the remaining design and installation details, and implementing the design improvements as recommended in this report.
It is recommended the next
30
LIST OF REFERENCES
Cornforth Consultants , July 21,1999, Seismic Stability Analysis, Silver Creek Dam, Prepared for City of Silverton. Foster, M.4., R. Fell, and M. Spannagle, 1998, "Analysis of Embankment Dam Incidents," The University of New South Wales, UNIGIV Report No. R-374.
Fell, R., Wan, Cyganiewicz, and Foster, April2003, "Time for Development of Internal Erosion and Piping in Embankment Dams" Journal of Geotechnical and Geo-Environmental Engineering, Yol.729,Issue 4. Oregon Water Resources Department in cooperation with the U.S. Army Corps of Engineers, June 1981, Phase 1 Inspection Report.
Philip Williams & Associates, Ltd, January 18, 2000, Silver Creek Dam Break Analysis Final Report, Prepared for City of Silverton, Oregon. Squier Associates, April2002, Silver Creek Dam Early Warning System Preliminary Design Report, Prepared for City of Silverton, Oregon.
U.S. Army Corps of Engineers, July 2003, Supplemental Information, Silver Creek Dam (Silverton, Oregon). U.S. Army Corps of Engineers, Institute for Water Resources, July 1997, Unpublished Residential, Commercial, and Vehicle Damage Data due to Flooding in Salem in 1996. U.S. Army Corps of Engineers,Institute for rWater Resources, March 1988, "National Economic Development Procedures Manual-Urban Flood Damage," IWR Report 88-R-2. U.S. Army Corps of Engineers, Engineering Regulation (ER) 1105-2-100, Planning Guidance Notebook and current cost sharing requirements cited in the Water Resources Development Act
of
1986, as amended.
U.S. Army Corps of Engineers,Institute for Water Resources, March 1988, "National Economic Development Procedures Manual-Urban Flood Damage," IWR Report 88-R-2.
31
Appendix A Geotechnical Investigation of Silver Creek Dam
32
Geotechnical Investigation of Silver Creek Dam Silver Creek Dam Silverton Or. Probability of X'ailure due to
Probability of Failure by Piping
Seepage
(From "Analysis of Embankment Dam Incidents" Foster, Fell, and Spannagle; University ofNew South Wales, UNIGIV ReportNo. R-374, Sep 1998.)
Weighing Factors Ws
W¡
wnr'
Embankment Mode
Foundation Mode
Emb into Found (filt) I (cot) I
(frlt) (ego) (cst) (cc) (con)
(ft) (obs)
(mon)
WE
0.2 1.25
L2 1.2 1
1.2
(filt) (fnd) (crt) (rg) (obs) (mon)
1.2 s
0.9 3
2 2
2 2
r.728
64.8
(fnd) (ecm)
l.s
(se)
1.3
5
(er)
s
(cog) (cst) (cc) (ft) (obs) (mon)
1.25
L2 1
1.1 3
2
482.625
w¡n
Average Probability of Failure for Zoned Earthfrll
Embankment P": 0.000025
Foundation
Pr:
0'000019
Emb into Found
P"r:
0.000004
Probabilíty of Failure byPiping Po: w6P" * wpP¡* \ilsFPer
Pp: Inverse
0'0032049
Po:
312.022216
ESTIMATED FAILURE TIME - (From table 8 "Time for Development of lnternal Erosion and Piping in Embankment Dams" Fell, Wan, Cyganiewicz, and Foster; Journal of Geotechnical Engineering, Apr 2003)
Time from initiating pipe to development of Breach
JJ
-
12
to 24Hrs.
Justiflrcation for Selection of Weighting Factors Weighting Factors for Piping through the Embankment (Factors from Table 11.2) Embankment Filters Ws (slt) - A factor of 0.2 was selected because the embankment was constructed with a filter but there are no indications that a specific gradation was specified nor that any test were performed on the material. It must therefore be assumed that the filter may be
poor quality. Core Geologic Origin WE (ceot)- The core material is of colluvial origin therefore the selected factor is 1.25 Core Soil Type W¡ i.,9 - The core material is described as plastic silts and clays therefore a factor
or 1.2 was selected. Compaction We (".) - Available information indicates that at least a modest amount of control was maintained during compaction, which would lead to the selection of a factor of 1.2. Conduits Vy'e ("on) - The outlet conduit is located at the embankment foundation interface, construction drawing indicate that the conduit \ilas constructed using practices similar to USBR practices of the time, which allowed a factor of L0 to be selected. Foundation Treatment Ws(n) - Drawings indicate that the foundation contained some irregularities and steep areas, but was treated using standard practices of the time allowing a factor of 1.2 to be selected. Observations of Seepage WE(or.) - Seepage was initially observed on the right side of the downstream face during initial filling. Horizontal drains were installed into the right abutment, which to date appears to be controlling the seepage. Seepage continues to flow from the left abutment contract but does not appear to be increasing at a detectable rate. Based upon these conditions a factor or 2 was selected.
Monitoring and Surveillance W¡ 1.on¡ of 2 was selected.
-
The embankment in monitored annually, therefore a factor
Weighting Factors for Piping through the Foundation (Factors from Tabte 11.3) Filters W¡ (rr,) - A factor of 1.2 was selected because the design drawing show no foundation
filter. Foundation Type Wp 1¡,q - A factor of 5 was selected because about half of the embankment is founded on slide debris.
Cutoff Type Soil Foundation W¡1"1.¡- Construction drawing show a cutoff trench with an upstream blanket on the right side and a cut of to rock (well constructed cut off trench on the left. The left abutment is the more critical in this case therefore a weighting factor of 0.9 was selected,
34
Soil/Rock Geology Type W¡ 1.r¡¡ - The left abutment is basalt rock, the right abutment is derived from landslide debris. A factor of 3 was selected due to the basalt bedrock. The factor could possibly have been set at a higher number but soils of landslide origin are not addressed. Observations of Seepage Wp (ou,) - Seepage was initially observed on the right side of the downstream face during initial filling. Horizontal drains were installed into the right abutment, which to date appears to be controlling the seepage. Seepage continues to flow from the left abutment contract but does not appear to be increasing at a detectable rate. Based upon these conditions a factor or 2 was selected.
Monitoring and Surveillance W¡1.on¡ - The embankment in monitored annually, therefore a factor of 2 was selected. Weighting Factors for Piping from the embankment into the Foundation @actors from Table 11.4) Filters War
(nr,) -
From table 1 1.4, all cases have a factor of
l.
Foundation Cutoff Trench Ws¡i"og - A factor of 1 was selected. The cutoff trench is considered to be of average depth and width.
Foundation Type W¡¡ 16,a¡ - The embankment is partly founded on rock and partly on slide debris. The partly founded on rock condition appears to control therefore a weighting factor of l 5 was selected.
Erosion Control Measures of Core Foundation Ws¡(""r)- A factor of 5 was selected due to the lack of erosion control measures in the landslide debris. The landslide debris were considered equivalent to open jointed bedrock or open work gravels.
Grouting of Foundation Wsp6¡- Records indicate that grouting of the rock did not occur, therefore a weighting factor of 1.3 was selected. Soil Geology Type War (rct) - The left abutment is basalt rock, the right abutment is derived from landslide debris and considered similar to colluvial material. A factor of 5 was selected due to the nature ofthe soil.
Soil Geology Type W¡¡ 1"go¡ - The core material is believed to have been borrowed form colluvial deposits at the site, therefore a weighting factor of 1.25 was selected. Core Soil Type Wsp p.9 - The description of core material best representing the material used is Clayey and Silty sands with a weighting factor of 1.2. Foundation Treatment WEr (r) - Drawings indicate that the foundation contained some inegularities and steep areas, but was treated using standard practices of the time allowing a factor of 1.1 to be selected. Observations of Seepage W¡r(ouÐ - Seepage was initially observed on the right side of the downstream face during initial hlling. Horizontal drains were installed into the right abutment,
35
which to date appears to be controlling the seepage. Seepage continues to flow from the left abutment contract but does not appear to be increasing at a detectable rate. Because of the way the seepage initially manifested itself it was felt that a factor of 2.0 was probably inappropriate, but since seepage flows have not increased significantly a factor of 10 seemed to high, therefore a weighting factor of 3 was selected. The embankment in monitored annually, therefore a
Monitoring and Surveillance Ws¡1-oo; factor of 2 was selected.
-
Document from UNICIV Report
Analysis of Embankment I)am Incidents. September
-
1998. Page 123.
To assess the annual probability of failure of an embankment dam by piping:
1.
Determine the average annual probabilities of failure from Table 11.1 for each of the three modes of piping failure: - piping through the embankment - piping through the foundation, and - piping from the embankment into the foundation, allowing for the age of the dam, i.e. whether less than or older than 5 years (about 213 of
piping failures occur on first filling or in the first 5 years of operation).
2.
Calculate the weighting factors WE, WF mad WEF from Tables 77.2,11.3 and 11.4 to take account of the characteristics of the dam, such as core properties, compaction and foundation geology, and to take account of the past performance of the dam. The weighting factors are obtained by multiplying the individual weighting factors from the relevant table. So, for example,
WE : WE(filt) X WE(cgo) X WE(cst) X WE(cc) X WE(con) X WE(ft) X WE(obs) X WE(mon).
3.
Obtain the overall annual probability of failure by piping (Pp) by summing the weighted
probabilities: SO
Pp:
WEPe + WFPf + WEFPef.
If the probabilities
are high, allowance must be made for the union of events in this
calculation.
36
I)ocument from UNICIV Report
- AnalysÍs of Embankment I)am Incidents.
September
1998.
Tabte 11.1: Average probability of failure of embankment dams by mode of piping and dam zoning.
FOUNDATION
AVER-
AVERAGE ANNUAL
AVER-
AVERAGE ANNUAL
AVER-
pe
AGE
Pf
AGE Ptef
AGE
(x 10-6) After
Pte
(xl0-3
First 5
(x 10-6)
PTf 5
Years
Years
Ooeration 2080
Ooeration
l6 1.5
190
3t
8.9
I 160
160
Zoned earthfill
t.2
160
25
Zoned earth
1.2
150
24
(<1.1)
(<140)
(<34)
5.3
690
75
(
(<130)
(<17)
93
t200
38
Homogeneous
EMBANKMENT INTO
FOUNDATION
EMBANKMENT
ZONING CATEGORY
AVERAGEANNUAL Pef(x 10-6)
(x l0-
First 5
After
3)
Years
Years
Operation
Operation
t.7
255
19
0.18
19
4
1,7
255
19
0.t8
t9
4
5
(xl0-3)
First 5
After
Yea¡s C)neration
Years Ooeration
5
190
earthfill Earthfill with
filter Earthfill with rock toe
and
rockfill
Central core earth and
rockfill Concrete face
earthfill Concrete face
rockfill Puddle core
earthfill Earthfill with
(
(<130)
(<8)
(
(<130)
(<13)
corewall
Rockfrll with corewall Hydraulic
fill
ALL DAMS
Notes: (1) (2)
(
(
450
56
PTe, Ptg and Ptef ars the average probabilities of failure over the Pe, Pq and Pef are the average annual probabilities of failure.
37
life of the dam.
I)ocument from UMCfV Report 1998. Page 124
If a factor
-
Analysis of Embankment Dam Incidents. September
has two or more possible weighting factors that can be selected for a particular dam
characteristic, such as different zoning types or different foundation geology types, then the weighting factor with the greatest value should be used. This is consistent with the method of analysis that was used to determine the weighting factors, as only the characteristics relevant to the piping incident were included in the analysis. The method is intended for preliminary assessments only. It is ideally suited as a risk ranking method for portfolio type risk assessments to identiff which dams to prioritize for more detailed studies. Since the method is based on a dam performance database approach, it tends to lump together these factors which influence the initiation and progression of piping, and it is not possible to assess what influence each of the factors is having. It is recommended that more rigorous event tree based methods be used for detailed studies so as to gain a greater understanding of how each of the factors influences either the initiation or progression of piping, or the formation of a breach. The user of the method is cautioned against varying the weighting factors significantly when applying the method to actual dams as they have been calibrated to the population of dams so that the net effect on the population is neutral.
It is recommended that the effect of the length of the dam is not included in the assessment of the probability of failure using this method. Vanmarke (1977) demonstrates the length of the dam might be expected to influence the probability of failure of sliding as long dams are more likely to have some defect or other feature in the dam or foundation that could potentially cause failure of the dam. However, for piping this is considered not to be a significant factor, as the piping failures often occurred at locations such as conduits passing through the dam or steep abutments, which are independent of the length of the dam.
0
38
I)ocument from UNICIV Report 1998, Page 125
-
Analysis of Embankment Dam Incidents. September
Table 11.2: Summary of the weighting factors for piping through the embankment mode of failure GENERAL FACTORS INFLUENCING LIKELIHOOD OF FAILURE LESS LIKELY MUCH LESS NEUTRAL MORE LIKELY
FACTOR
MUCHMORE LIKELY ZONING
EMBANKMENT FTLTERS WB(filr)
LIKELY
Refer to Table I 1. I for the average annual probabilities of failure by piping through the embankment depending on zoninq type Embankment filter Other dam types No embankment present-well present-poor filter (for dams quality designed and which usually have constructed filters (refer to
text)
CORE
GEOLOGICAL ORIGIN we(CGO)
Alluvial
CORE SOIL TYPE WB(cst)
Dispersive clays
U.5l
Acolian, Colluvial
u 2sl tsl
Clayey and silty sands (SC, SM)
Low plasticity silts
Í1.21
(ML)
t-l
121
Residual, Lacustrine, Marine, Volcanic [1.0ì Well graded and poorly graded gravels (GW. GP) t1.01
t2.51
Glacial Clayey and
siþ
gravels
(MH)
tl0ì
[0.5]
High plasticity clays (CH)
(GC, GM)
t0.31
t0.81
High Plasticity silts
Poorly and well graded sands (SP,
Low plasticity clays [0.8]
sw) t2l COMPACTION WElcc) CONDUITS WE(con)
t02'l
I
Rolled, modest control [1.21
Puddle, Hydraulic
compaction [5ì Conduit through the embankmentmany poor details
Conduit through the embankmentsome poor details
Conduit through embankment-
Conduit through embankmenl-
Rolled, good control [0 5l No conduit through the embankment
typical USBR
including
t0.51
t5l
l2l
practice
Untreated vertical faces or overhangs in core foundation
Irregularities in foundation or
No formal
fill
n.Ot
[.0]
downstream filters t0.8.|
FOLTNDATION
TREATMENT
t21
OBSERVATIONS OF SEEPAGE WE
Muddy leakage
(obs)
in leakage [up to
Sudden increases 101
MONITORING
AND SURVEILLANCE WE(mon)
Inspections annually
abutment, Steep abutments [1.21 Leakage gradually increasing, clear, Sinkholes, Seepage emerglng on downstream slope t21 Inspections
monthly
t2t
Ir.2l
Careful slope modification by cutting, filling with concrete [0 9]
Leakage steady, clear or not 0] obsewed
Minor leakage
Leakage measured
none or very small
[
t0.sl
t0.71
Irregular seepage
Weekly-monthly
observations, inspections weekly
seepage
tl.01
monitoring, weekly inspections t0 8l
Daily monitoring of seepage, daily inspections t0.51
39
Document from IIÌ\IICIV Report 1998,Page126. Table 11.3:
of
S
- Analysis
MUCHMORE LIKELY FILTERS WF(frlt)
LIKELY
required
(Rock foundation)
No foundation
u.0l
rock substance[1.01 Partially
Shallow or no
cutofftrench
lr.2l Well constructed diaphragm wall
tl.sl
WF(ctr)
the
Foundation
filter Rock-clay infilled or open fracfures and/or erodible
tsl
Sheetpile wall Poorly constructed diaphragm wall [3]
of failure
Í1.21
Soil foundation
CUTOFF TYPE (Soil foundation) WF(cts) OR CUTOFF TYPE
OF FAILURE MUCH LESS LESS LIKELY
NEUTRAL
Refer to table I l. I for the No foundation filter present when
ZONING
the foundation mode of failure
factors for GENERAL F MORE LIKELY
FACTOR
FOUNDATION TYPE (below cutoff) WF(fnd)
of Embankment Dam Incidents. September
penetrating sheetpile wall or poorly constructed slurry trench wall
filter(s) present I0.8t Better rock quality
Upstream
Partially
blanket,
penetrating deep cutoff trench
Partially penetrating
well
t1.01
Average cutoff trench [.0]
t0.71
constructed
slurry trench \4iall [0.8] Well constructed cutofftrench [0.9]
SOIL GEOLOGY
Dispersive soils [5]
TYPES (below cutoff) WF(sg), OR
Volcanic
ROCK GEOLOGY
Limestone
tsl
TYPES (below
Dolomite
t3l
cutoff) WF(rg)
Saline(gypsum) t5l Basalt t3l
Ash
Residual
U.2l
t51
Aeolian, Colluvial, Lacustrine, Marine
[l
0]
Muddy leakage
OF SEEPAGE
Sudden increases in leakage fup to
wF(obs) OR OBSERVATIONS
l0l
OF PORE PRESSURES
Sudden increases in pressures [up to
WF(obp)
101
MONITORING
AND SURVEILLANCE WF(mon)
Sandstone, Shale,
Rhyolite Ma¡ble
12)
Homfels [0.7]
I2l
Agglomerate, Volc. Breccia [0.8|
t21 Leakage gradually increasing, clear, Sinkholes,
Sandboils A)
obsewed tl.0l
mcreasrng pressufes ln
t0.71
Slate
t0.51
or very small Low pore pressures in foundation [0.8]
foundation U.0l Irregular seepage observations, inspections weekly
tl
Ir.2l
Schist, Phyllite,
l0.sl
121
monthly
Conglomerate [0 5] Andesite, Gabbro
Leakage measure none
High pressures measured in
Gradually
t0.51
t0.21
Minor leakage
Leakage steady, clea¡ or not
Glacial
[0.5] Granite, Gneiss
l.sl
Inspections
t2l
t0.91
Tuff
foundation Inspections annually
Alluvial Siltstone, Claystone, Mudstone,
Ouafzits OBSERVATIONS
Rock-closed fractures and nonerodible substance t0.05t
0l
Weekly-monthly seepage
monitoring, weekly
inspections
t0.81
Daily monitoring
of
seepage, daily
inspections t0.sl
40
I)ocument from UNICIV Report 1998, Page 127,128.
-
Analysis of Embankment Dam Incidents. September
Table 11.4: Summary of weighting factors for piping from the embankment into the foundationaccidents and failures. FACTOR
GENERAL FACTORS INFLUENCING LIKELIHOOD OF INITIATION OF PIPING-ACCIDENTS AND FAILURES LESS LIKELY MUCH LESS NETJTRAL MORE LIKELY MUCH MORE
ZONING FILTERS
from embankment into foundation Refer to Table I I .l for the Appears to be independent ofpresence/absence ofembankment or foundation filters [1.0]
I,IKELY
LIKELY
WEF(filt) FOUNDATION CUTOFF TRENCH
Average cutoff trench width and
Deep and narrow
cutofftrench [1.5]
depth
rWEF(cot)
CORE
FOUNDATION
cutofftrench [0.8]
tl.Ol
No erosion control
Founding on or partly on rock foundations [l.51 No erosion control
No erosion control
Erosion control
measures, open
moasufes, average
measures, good
measures presgnt,
jointed bedrock or open work gravels [up to 5]
foundation conditions
foundation conditions
poor foundations
FOTINDATION TYPE WEF(fridO ERIOSION CONTROL MEASURES OF
Shallow or no
tt.2\
Founding on or partly on soil foundations [0.51 Good to very good erosion control measures present and good
t0.sl
foundation
t1.01
t0.3-0.1-l
WEF(ecm)
No grouting on rock foundations
GROUTINGS OF FOUNDATIONS
tt.3l
SOIL GEOLOGY
Colluvial
TYPES wEF(sg), OR
Sandstone
Dolomite, Tuff,
interbedded with shale or limestone
Quartzite
ROCKGEOLOGY TYPES wEF(rg)
t5l
t3l Limestone,
gypsum CORE
Soil foundation only-not applicable tl.01
tzl
Glacial
U.5l
Rhyolite, Basalt,
Marble
ll.2l
Alluvial [l 5l
grouted
t0.81
Residual
t0.81
Lacustrine, Marine,
Colluvial
[1.25]
Volcanic
Conglomerate [0 8]
Granite, Andesite, Gabb¡o, Gneiss
Schist, Phyllite, Slate, Homfels
Sandstone,
tl.0l Acolian,
Alluvial, Aeolian,
Agglomerate, Volcanic breccia
12.51
GEOLOGICAL ORIGIN
Rock foundations
Shale, Siltstone, Mudstone, Claystone t0.21
t0.61
Glacial [0.5]
Residual, Lacustrine, Marine,
Volcanic
[0.5]
tl.01
WEF(ceo)
CORE SOIL TYPE WEF(cst)
Dispersive clays[5] Low plasticity silts I2.sl Poorly and well
(lvfr-)
Clayey and silty sands (SC, SM) [1.2]
Well graded and poorly graded gravels (GW, GP)
tl.0l High plasticity silts
graded sands (SP,
sw)
t0.31
[0.8]
Low plasticity clays (CL)
(MH)
t2l
High plasticity clays (CH)
Clayey and silty gravels (GC, GM)
t0 8l t1.0.1
of compaction-all compaction types
Appears to
CORE
[
.0]
COMPACTION WEF(est)
FOUNDATION TREATMENT
Ilntreated vertical faces or overhangs
Irregularities in foundation or
wEF(ft)
in core foundation'
abutmenl, Steep
I
l.sl
OBSERVATIONS
Muddy leakage,
OF SEEPAGE WEF(obs)
Sudden increases
MONITORING
AND SURVEILLANCE
in leakage lup to I 0l Inspections annually t21
abutments
Careful slope modification by cutting, filling with concrete
t0.el
tl.ll
Leakage gradually increæing, clear, Sinkholes tz'l Inspections
Leakage steady,
Minor leakage
clear, or not monitored
Leakage measured none or very small t0.71
n.0l Irregular seepage observations, inspections weekly
monthly
u.2l
t1.01
4t
t0.5ì
Weekly-monthly seepage
monitoring, weekly
inspections
I0.81
Daily monitoring ofseepage, daily inspections t0 5l
Appendix B
Baseline Cost Estimate for Silver Creek Dam Early Warning System Section 205 Project
42
Insert Total Project Cost Summary sheet 1.
43
Insert Overall Project Summary Page
44
Narrative 1. Proiect Description: Silver Creek Dam is located just south of the city of Silverton, OR. It is a 65 foot high embankment dam with a concrete spillway. The early waming
system is intended to reduce potential hazards posed by dam. The system will measure piezometers and weirs, route the information through control units and to cþ offices. A siren notification system is also included. 2. Basis
of
Desisn and Estimate:
a. Basis
of Design .
The basis of the design is the Feasibility Report for subject
project dated I|lIay 2004. b. Basis of Estimate. The estimate for this project was developed using information provided by the designers, including plans and quantities. The construction cost estimate is a detailed MII estimate using labor and equipment crews, quantities, production rates, and equipmentlmaterial price quotes. The Total Project Cost Summary sheet includes costs for construction; real estate; planning, engineering and design; construction management; contingencies; and infl ation. 3. Construction Schedule: Construction will be accomplished during the summer of 2005, taking about one month to complete. a.
Overtime. Assume that no overtime will be required.
b.
Construction Windows. In-water work periods are not applicable to this project.
4. Acquisition Plan. It is anticipated that this job will be accomplished through either an A-E contract or a sole source construction contract. 5. Subcontracting Plan. It is envisioned that all work will be done by the prime contractor except earthwork, electrical and telephone work. 6. Project Construction. Site Access. Access to the right abutment and spillway will be via highway. Access to the main embankment will be by a boat crossing the reservoir.
a.
b. Borrow Areas. Not applicable. c. Construction Description. A description of required work is given below:
45
Mob & Demob. Assume mob/demob will be from the Portland area. Equipment mobilized will include an excavator /loader, a small crane, a small boat and a small barge for transporting equipment to the south side of the dam. A direct cost of $5,000 was allowed. 1)
2) Miscellaneous Prime Contractor Work. The prime contactor will likely be a geotechnical engineering AE hrm that specializes in this type of
work. A
two-man crew is likely to perform the installation of instrumentation equipment. Labor ratçs are assumed to be similar to typical for geotechnical engineers. a) Contractor Manaqement of Subcontractors. This is assumed at
40 hours.
b) Field Inspection of Subcontractors. Allow 4 weeks, or 160 hours. c) Order Equipment from Suppliers. Allow 40 hours. 3) Measurement and Control Units. The units would be Geomation MCUs or equal. Three MCUs will be procured and installed. Each MCU will be configured somewhat differently, see report and backup for details. MCU equipment costs were estimated using costs for similar MCUs installed for a recent job at John Day Dam. It is anticipated that each MCU will require 2 crew-hours to install, using a2-man crew. MCUs are to be installed at locations shown in the report. One will be installed on the north side of the dam, while the other two will be installed on the other side of the reservoir, and will have to be transported by boat.
4) Prefab Building. A 10' by 12' f,rberglass building was assumed for this building. A quote was received from TRACOM, Inc. for the building, see backup. Assume the site will be prepared and a 4" thick concrete slab will be placed. The building will be erected (20 crew hours), then wired for power and phone service (covered in Electrical Work and Phone Lines items). Costs for an access road and floodlights were computed using Cost Book items. The cost for a backup generator was obtained from the Grainger catalog. 5) Electrical Work. This item covers all power needed for MCU-I, transducers, weir sensors, and the prefab building. Power would be brought over to the building from a nearby restroom in the park. MCUs on the south side of the spillway would transmit data to MCU-1 via radio signals, and these MCU's would have solar power. So no power or phone lines would need to be installed to these MCUs. Quantities for required trenching and cable installation were provided by the designer. Appropriate Cost Book items were used to price these items. Production rates were reduced due to the small quantities on this job.
46
6) Phone Lines. This item covers installation of a phone line from a nearby neighborhood across the highway from the dam, to the prefab building. Again, quantities for required trenching and cable installation were provided by the designer. Appropriate Cost Book items were used to price these items. Production rates were reduced due to the small quantities on this 7) Pressure Transducers for Piezometers. The transducers would be installed in 10 existing piezometers at the site. Quotes were obtained from Geokon for the transducers. The cost ofjunction boxes, transient protection, grounding rods, modifications to the tops of the piezometer casings, and miscellaneous hardware were estimated at $1,000 per transducer. Grounding rods must be installed 10 to 20 feet deep. An estimated 3 crew-hours would be required for installation of each transducer. 8) Pressure Transducer for Reservoir Level. This would be another Geokon transducer installed near the upstream toe of the dam, underwater. The transducer would be installed via a boat. Cables would be placed as necessary to carry signals to MCU3. Again, the cost ofjunction boxes, transient protection, grounding rods, and miscellaneous hardware was estimated at $1,000 for this transducer. An estimated 8 crew-hours would be required for installation of this transducer in the water.
9) Reservoir Level Staff Gage. This item covers a staff gage to be installed on the south side of the spillway. It would be a2x6 section of lumber, about l0 feet long, with a white piece of plastic fastened to its surface. Elevations would be marked on the plastic. The gage would be installed on the spillway wall. An elevation survey would be required to assure installation at the proper level. A rough cost of $1,000 was obtained from Bruce Duffe for materials and installation, complete. 10) Pressure Transducer for Barometric Correction. This would be another Geokon transducer. It would be installed inside of MCU1, to measure barometric pressure. About 1 crew hour would be required for installation.
Weirs. Four weir boxes are to be installed. Anticipate using fiberglass weir boxes. The weirs will be placed on concrete pads. A quote was obtained from TRACOM, Inc. for the weirs boxes, see backup. A Geokon weir-measuring sensor will be installed in each weir box. As above, the cost ofjunction boxes, transient protection, grounding rods, and miscellaneous hardware was estimated at $1,000 for each weir. Installation will require about 4 crew-hours for each weir. 11)
12) Testine and Troubleshooting System. Estimated to require 16 crew-
hours 13) Emergency Operations Center (EOCI. This item covers computers and software required to process instrument data collected at the dam. Pricing and crew-
47
hours were estimated by David Scofield of the NV/P Geotechnical Design Section. Items include: a) A standard PC and a laptop PC at the EOC in a City of Silverton building. b) A PC at the dam site, installed in the prefab building. c) Damsmart software (single users). d) Geonet Module for Damsmart. e) Programming. Estimated to require 40 crew-hours. Ð MS Office Suite (Excel and Access). g) Data backup. h) Installation at EOC. Estimated to require 16 crew-hours. i) Miscellaneous Hardware. Estimated at $1,000. 14) Notifrcation System. This covers all work related to installation of the siren system. Four sirens are to be installed. This system may be constructed by the City of Silverton. Design and cost data were obtained from Barry Myers. Included are: a) Siren Activation Panel. b) Radio Transmitter. c) Siren Control Station. 1. Sirens (Federal Signal MOD6024 or equal) 2. Utility Poles (decorative style) 3. Wiring 4. Power to each siren d) Testing System. 15) Operations Manual. Estimated at 160 man-hours at
$100/hr:
$16,000. 16) Evacuation Plan. These items would be developed during design and implemented by the City of Silverton. An Evacuation Plan and Brochures would be
developed. 17) Training and Svstem Support. Training materials would be developed and training would be provided after the system was installed. Then system support would be provided for a short period after system installation was completed. Costs and
hours were estimated during discussions with Dave Scofield. d. Ouantities. Quantities were provided by a designer in Geotechnical Section. e. Government Furnished Property. There is no government furnished property
on this job.
f. Unusual Conditionq (Soil, Vy'ater, V/eather). There are no unusual conditions expected on thisjob.
48
g. Unique Construction Techniques
. N/A
h. Equipmenllabor Availability and Distance Traveled. Equipment and labor will be provided by the Contractor. Assume labor and equipment originates in Portland.
i. Overhead. Proht and Bond. A low JOOH percentage (5%) was used because several overhead type items were detailed in the estimate. Standard percentages were used for HOOH and bond. Profit was computed using weighted guidelines. 7. Environmental Concerns. The contractor must assure that no hazardous construction materials enter the reservoir or creek.
8. Contingencies. A contingency of l5o/o is used for all activities to cover uncertainties in design and quantities. Dates for Labor. Equipment. Material Pricing. Effective date for all pricing is March 2004. The most recent Davis-Bacon labor rates were used. The 2001 Cost Book database was employed, covering labor, equipment and unit price items.
9. Effective
Costs: Costs for Real Estate, Engineering and Design, and Construction 10. Management were provided by the project manager
49