Detail Project Report 1MWp SPV Power Plant
Queries@
[email protected]
Acknowledgement This analysis based report is done for the readers of my previous report 1MW Utility Scale SPV Power Power Plant, Plant, mainly mainly for the the readers readers from South South region of INDIA INDIA as they they are are asking asking repeate repeatedly dly about the probability and feasibility-technical & Financial-of a SPV power plant in their region. At the same time it’s not possible for me to design a report for each and every state from South South India, so I took Chennai city. Also the previous report report was not so detail, detail, was very basic and meant to the readers who want to get an overview on how a utility scale power plant works. Now, in this report, I discuss about in depth. From panel’s selection to CB sizing all are presented in very detail. Hope, this time you get a strong knowledge on designing and estima estimatio tion n of 1MW solar solar PV power power plan plant. t. Unlik Unlike e the prev previou iouss repor report, t, the the fina financi ncial al aspec aspectt discussed at the end of the paper. In this paper, the financial financial assessment has done done in very detail and considering the current scenario of SPV market including the cost of solar PV modules, inverters’
cost,
cable,
transformer
etc.
prices
and
the
funding,
interest
rate.
And if you have any queries or need clarification, please contact at
[email protected] or
[email protected] .
Disclaimer The presented data here are NOT TAKEN from any copyright materials and not showing under my name. The meteo data collected from NASA website and NREL database which is free over the internet. Designing of PV system is totally based on the practical experience of the author.
Assumptio Assumption n & Consideration Consideration Shading consideration: No shading has been considered at the site during the calculation design. So it is advised that at the time of execution, please check whether there is any kind of obstacle in the site which may cause partial/full shading on PV strings and/or PV array. If the shading occurs, then the estimated power generation will not match the actual power generated. Load Factor: It is assumed that the produced power from the PV plant will be fed to the local utility grid. So, while designing the system, no unbalanced load considered in 3 phase configuration. Meteo data: The calculation based on the meteo data collected from NASA website which is very reliable. Now, based on the co-ordinates the the values have been presented in this report. report. So, total design is based on this data. For a different location (coordinates), the system design will differ. It is advised not to copy and implement implement the design without consulting the author author or any certified PV professional because this design estimation is valid only for a particular site.
www.renewpowerzone.in
Page Pa ge 1
Detail Project Report 1MWp SPV Power Plant
Queries@
[email protected]
Site consideration: this design design has has been done done by consider considering ing the the PV modules modules & array array will will be 0
ground-mounted and the site-elevation angle taken 3 . Cost Estimation: 1MW Solar PV power plant cost estimation has done considering the current PV market scenario (Sept-Dec 2013), so after few months the cost may vary according the market. CAD design & layout: I have not uploaded/attached uploaded/attached the CAD design. If anybody anybody interested in setting up the plant then only contact at the given e -mail ids to get the design file. Transmission & wheeling losses: Here, in this report, while doing the technical assessment, the distance from nearest substation substation to the 1MW solar PV power plant taken within 1.5 KM and so the wheeling losses considered as 3% of total power transmission. And in the financial assessment, no wheeling charges have been considered. Design Criteria: While designing & estimating the technical technical components components & solutions, solutions, all the required/ap required/applica plicable ble standard standard design design codes codes have been considere considered. d. Mainly Mainly the the IEC (Internati (Internationa onall Electrotec Electrotechnica hnicall Commissio Commission) n) Codes, Codes, IS codes codes from BIS have been considered considered thorough thoroughly. ly.
www.renewpowerzone.in
Page Pa ge 2
Detail Project Report 1MWp SPV Power Plant
Queries@
[email protected]
Contents 1) Introduction
4
2) Project details
5
3) Location metrological details
6
4) Determination of optimum tilt angle
7
5) Solar power plant overview
8
6) Module selection & sizing
9
7) Inverter selection & sizing
11
8) Transformer selection
12
9) Other protective devices including switch gear details
13
10)
Cable sizing & selection
14
11)
Civil works details
16
12)
Performance analysis & simulation
17
13)
Timeline of the project
21
14)
Operation & maintenance structure of the plant
22
15)
Financial calculation, estimation of NCF, Payback period
23
16)
Guide on on selection of various components
27
17)
Conclusion
28
18)
About the Author
28
www.renewpowerzone.in
Page Pa ge 3
Detail Project Report 1MWp SPV Power Plant
Queries@
[email protected]
Introduction India is densely populated and has high solar insolation, an ideal combination for using solar power in India. India is already a leader in wind power generation. In the solar energy sector, some large projects have been proposed, and a 35,000 km2 area of the Thar Desert has been set aside for solar power projects, sufficient to generate 700 GW to 2,100 GW. Also India's Ministry of New and Renewable Energy has released the JNNSM Phase 2 Draft Policy, by which the Government aims to install 10GW of Solar Power and of this 10 GW target, 4 GW would fall under the central scheme and the remaining 6 GW under various State specific schemes. The Electricity Act, 2003, paves way for an innovative approach to solve our country’s power problems. It has paved the way for for a competitive environment; environment; open access to existing transmission transmission and distribution network to transmit electricity across regions; de-licensing de-licensing of generation, captive power and dedicated transmission lines; lines; licensing of distribution and supply supply companies and the restructuring of State Electricity Boards. The Ministry Ministry of Power has mandated mandated to promote cogenerati cogeneration on and renewable renewable sources sources for Power generation under Nodal agencies and hence it will play a major role in mainstreaming renewable energy sector. The advantage or renewable resources includes their capacity to produce energy without producing carbon-based warming and polluting agents into the atmosphere. The financial cost of its applications is not always cheap but but if the environmental costs of using fossil are accounted for, renewable energy wins hands-down. There are also indirect savings on health and its costs as there are no harmful emissions. In the above backdrop, YOUR COMPANY COMPANY NAME has decided to set up a 1/1000 1/1000 MW/KW MW/KW Solar Power Plant. This Detailed Project Report (DPR) brings out all technical details and overall costs justifying the selection of the project. The total power generation is envisaged to be 1050KW from Solar Photovoltaic Cell. It is a very important document that is required for Environmental Impact Assessment Assessment (EIA) studies, fixation of tariff, finalizing Power Purchase Agreement (PPA) and also for submission submission to Financial Institutions for obtaining project funding. The total project cost is expected to be Rs ___ Crores and the average cost of generation is expected to be Rs. 7.5/kWh (ASSUMED). rd
For this project, project, poly-crystal poly-crystalline line technology technology based based 3 generation Solar PV modules modules will be used. Along with this, highly efficient, photon-tested string inverters going to be integr ated to the system. These technologies are the best in the industry. So, It’s clear that our projec t is not compromising with the quality of the materials and or the components which obviously led this project to success.
www.renewpowerzone.in
Page Pa ge 4
Detail Project Report 1MWp SPV Power Plant
Queries@
[email protected]
Client’ details Country
India
Location
CHENNAI
Contact id
[email protected]
Contact Person
abc
company
ABCXYZ
Purpose
Power generation & distribution to State utility grid
Project Details
Site & Meteo Details Location coordinates Ambient 0 Temperature( C)
10.5, 78.5 (assumed)
Max 28. 5
Average 2 7 .2
Min 2 5 .5
Relative humidity
72.5%
Daily Solar irradiationHorizontal Atmospheric Pressure
5.19 KWh/m /day
Wind Speed
2.7 2.7 m/s m/s
Earth temperature Height from sea level
2
100.1 kPA
M ax
Average
Min
29. 6
2 8 .8
2 6 .4
10m
Type of installation
Ground-mounted
Estimated array peak power
1100KWp
Shading consideration
Shade-free
Grid voltage
11KV
Phase connection
3-phase
Grid frequency
50Hz
Available/required area
20000 m (apprx)
Safety level
IP65
2
Site Location/Layout
www.renewpowerzone.in
Page Pa ge 5
Detail Project Report 1MWp SPV Power Plant
Queries@
[email protected]
Solar Irradiation 7 6 Solar Irradiation
5 y a d 4 / 2 m / h 3 W K 2 1 0
31
Air & earth temperature-monthly
30 29 28 27
Air temperature earth temperature
26 25 24 23
www.renewpowerzone.in
Page Pa ge 6
Detail Project Report 1MWp SPV Power Plant
Queries@
[email protected]
Optimum Tilt Angles For Solar PV Array Adjusted by Months Jan
Feb
Mar
Apr
May
Ju n
34°
26°
13°
0°
11°
14°
Jul
Aug
Sep
Oct
Nov
Dec
12°
5°
6°
19°
29°
35°
Figures shown in degrees from vertical
Winter
Summer
Spring/Autumn
104° 104° angl angle e
80° 80° angl angle e
56° angle
On the 21st December, the sun will rise 87° east of due south and set 87° west of due south. On the 21st March/21st September, the sun will rise 91° east of due south and set 91° west of due south. On the 21st June, the sun will rise 95° east of due south and set 95° west of due south.
Irradiation Data on different tilt angles (respect to horizontal surface, KWh/m 2/day) Months January February March April May June July August September October November December Annual avg.
0
10 5 . 04 5 . 98 6 . 51 5 . 76 5 . 78 5 . 28 4 . 99 5 . 09 5 . 33 4 . 67 4 . 27 4 .5 5.26
0
25 5 .3 5 6 .1 6 6 .4 1 5 .3 9 5 .6 5 5 .2 2 4. 9 4. 9 5 .1 4 4 .6 9 4 .4 4 4 .7 8 5.25
0
12 5 .4 1 6 .1 6 6 .5 2 5 .8 5 5 .7 8 5 .2 9 4 .9 9 5 .1 5 .3 4 4 .7 1 4 .4 5 4 .8 4 5.36
0
* Here, Here, 12 angle angle at AM1.5 AM1.5 has been chosen chosen as fixed south south faced model model for the the project project
www.renewpowerzone.in
Page Pa ge 7
Detail Project Report 1MWp SPV Power Plant
Queries@
[email protected]
Solar PV System Design System Overview SPV Array Peak Power No. of SPV strings
1082KWp 206 Series 20KW MPPT based 3 phase string Inverter MPPT & Transform Transformer er Less 53 4/1
Connection of PV modules in each string Inverter Inverter Type/Topology Total no. of Inverters Strings/Inverter
Modular Components Components
Specification
Solar Solar PV module moduless
Quantity
Max Peak Power=250Wp Voc= 36V ;Vmp= 29V Isc= 9.25A ; Imp= 8.65A
Make
4326
Non-Modular Components Components
Electrical Sp Specification
Quantity
Inverters
20KW, 3Phase &MPPT; Vmax= 800V 1250KVA
53
Transformer SCADA/Monitoring System Circuit Breaker
Integrated with Remote Monitoring system web based
1 1
Inverter Inverter to Busbar= Busbar= 46A 3p; busbar/Panel box to transformer transformer= = 1600A 3p; 3p;
53 1
DC Disconnect
1000V,20Amps
206
Switch Gear
Rated voltage=12KV; Rated main busbar current(Max)=1250A; SC withstand capacity = 25KA/3s Dynamic capacity= 50KA
1
Distribution Panel
NA
1
Isolator
Vmax= 12KV; Max cont. current=1250A 2 DC Side Side= = 10 mm mm 2 AC Side=LT: Side=LT: 16mm & HT: 2 185mm
1
Cables
Make
www.renewpowerzone.in
Page Pa ge 8
Detail Project Report 1MWp SPV Power Plant
Queries@
[email protected]
Solar PV Module Specification & Array Sizing Details Required Electrical Characteristics of SPV Modules Design criteria
IEC-61853-1
Watt Watt Peak Peak
250Wp
VOC
37.20V
VMPP
30.10V
ISC
Required Operating Condition Details: Maximum System Voltage (IEC)
1000V
Maximum Fuse use Ra Rating
1 5A
Limiting Reverse Current
15A
8.87A
IMPP
8.30A
Operating Temp Range
(-10 to 60) C
Module Efficiency/module area Power Tolerance
15%
Max Static Loadfront(Snow+Wind)
5500PA
±2%
2500PA
Technology
Si-Poly
Max Static LoadRear(wind)
No. of cells
60 cells in series
0
Model design parameters
Required Temperature Co-efficient Characteristics @ STC o
o
NOCT ( C)
45 ± 2 C
250 ohm
R shunt (G=0)
2100 ohm
R series model
0.29 oh o hm
o
-0.07 ± 0.01
o
-0.43 -0.43 ± 0.05 0.05
R series max
0.37 oh ohm
o
-0.34 -0.34 ± 0.05 0.05
R se series ap apparent
0.47 ohm
(%/ C)
0.065± 0.065± 0.05 0.05
Module Efficiency
(%/ C)
Temp. Co-Eff. Of Pmax (%/ C) Temp. Co-Eff. Of Voc Temp Co-Eff. of Isc
R shunt
(%/ C) o
PV Module Behavior at different irradiance level 2 2 PV Parameters @ 1000W/m @800 W/m
@ 400 400 W/m
PMPP VOC VMPP ISC IMPP Module efficiency Temperature co-eff
1 0 0 .0 0 3 5 .8 V 3 0 .1 V 3. 55 A 3. 33 A 15.27% -0.44%/0C
249.8.2W 3 7 .2 V 3 0 .1 V 8 .8 7 A 8 .3 1 A 15.54% -0.43%/0C
200.6 W 3 6 .8 V 3 0. 2 V 6 .6 4 A 7 .1 0 A 1 5 .3 2 % -0.43%/0C
2
www.renewpowerzone.in
Page Pa ge 9
Detail Project Report 1MWp SPV Power Plant
Solar PV Array Sizing & Connection Connection Details Details 0 conditions At STC (25 C) Suggested array Size Actual Solar PV Array Size Watt Peak of each SPV module Total nos. of SPV module required Total nos. of strings Nos. of SPV modules in each string SPV connection in each string String voltage (V MPP) String current (I SC / IMPP) Connection of strings Array voltage (VOC / VMPP) Array current (ISC / IMPP)
Queries@
[email protected]
0
At Avg. Ambient temp. (28 C)
1100 1100 KWp
1100KWp
1082KWp 250Wp
1100KWp 263Wp
4 326
4 326
2 06 21
2 06 21
Series 6 0 9V
Series 6 3 0V
8.87A/8.3A
9.51A/8.82A
Parallel 780V/635V
Parallel 750V/620V
1830A/1710A
1960A/1816A
www.renewpowerzone.in
Page Pa ge 10
Detail Project Report 1MWp SPV Power Plant
Queries@
[email protected]
Detail Solar Inverter Specification & Design Details Inverter Type Quantity
String Inverter (MPPT) 53
INPUT (DC)
Max. Power
23KW
Max absolute Input Voltage Star Startt Volt Voltag age e
1000V
Nominal Nominal MPP voltage voltage range
490V-800V
Max Input Current per string Nos. of Independent MPP inputs/strings per MPP inputs
41.5A
350V
1/6
OUTPUT (AC)
Rated Output Power Max. Apparent AC Power Power Threshold Nominal AC Voltage/range AC Power Frequency/ range Max. output current Power factor at rated power Feed-In phases/connection phases
20000W 20000VA 20W 3/N/PE;230/460V 50Hz 3x29A 1 3/3
Efficiency
Max. Efficiency
98.7%
Protection Details
DC Disconnect DC Surge Arrester Protection Class Total harmonic distortion Operating Temperature range Noise Emission Self Consumption Cooling option Protection type Remote Monitoring System User Interference & Communication
Available Available I (as per IEC 62103)
<1.8% -25◦-60◦C <35dB <25W Forced Air-cooled IP65 (as per En 60529) With RS-485/Ethernet
Electrically Isolated relay output Status Display Inverter to inverter communication Anti-islanding protection Inverter connection details
Available Available Available Available
Total nos. of inverter Nos. of strings per inverter Connection of string s/inverter Inter-inverter connection Inter-Inverter isolator
53 4 Parallel Parallel into Cu busbar Provided
www.renewpowerzone.in
Page Pa ge 11
Detail Project Report 1MWp SPV Power Plant
Queries@
[email protected]
Transformer Sizing IS-2026 / IEC-60076 Power transformer, transformer, core core type with oil-imme oil-immersed rsed ; 0 65 C winding temp rise ONAN(Oil Natural Air Natural) 1250KVA 11000V 460V 4.7% 7.5% 1250A 20KA/3s DELTA Wye 50Hz ±5% of full load capacity
Design Criteria Transformer type Cooling type Rated KVA High Voltage rating Low Voltage Rating Nominal impedance Impedance tolerance Nominal secondary amps Max SC withst withstand and curren currentt HV connection LV connection Operating frequency Tap changer
Protective devices components
Specification
Quantity
DC Disconnects
String String to inverter= inverter= 1000V, 15A; 2 pole (As per IEC-60947)
206
Switch gear
Rated voltage=12KV; Rated main busbar busbar current(Max)= current(Max)=1250A; 1250A; SC withstand withstand capacity capacity = 25KA/3s Dynamic capacity= 50KA IP55
1
Circuit breakers (MCCB)
Inverter to Busbar= 60A 3p; busbar/Panel box to transformer= A 3p;
53 1
(NOT required if Inverter has inbuilt protection)
Main Mai n Isol Isolato atorr (HT sid side) e) Design cr criteria
IS-9921/IEC-129
Operating frequency
50hz ±3%
Nominal system voltage
1 1K V
Max system voltage
1 2K V
Rated peak withstand current current (KA peak/rms peak/rms)) 1.2/50 micro sec lighting withstand Volts (KV peak)
Max continuous current
2500A
Rated 1 minute power frequency withstand voltage(KV r.m.s) No. of poles
Rated SC current for 3s
4 0K A
Min creepage distance
63.5KA To earth and isolating poles
Across the isolating distances
1 70
195
To earth and isolating poles
Across the isolating distances
75
85
320mm
3
www.renewpowerzone.in
Page Pa ge 12
Detail Project Report 1MWp SPV Power Plant
Queries@
[email protected]
Cable Sizing DC Side Side Cab Cables les (strings to inverter ) Design criteria Cable material Single cable length per string to inverter Cross section per string Voltage drop Relative power loss reference to Max DC power Max withstand temp.
Max withstand current capacity Conductor type Insulation material
IEC-60811 & IEC-60216 Copper 70 ft 2 4 mm 0.18V 0.07% Normal condition Short-circuited condition 0 0 90 C 250 C 42KA/1sec Stranded XLPE
LT Ca Cable bless (Inverters to busbur/distribution panel ) Design criteria Cable material material Max Single cable length per inverter to panel box Cross section Voltage drop (3phase) Relative power loss reference to Max AC nominal power Max withstand temp
IEC-60228 & IEC-60811 Copper 60 ft 2 16 mm 0.46V 0.23% Normal condition
Short-circuited condition 0 250 C
0
90 C
Max withstand current capacity Conductor type Insulation
2KA/1sec Stranded PVC
from distribution panel to feed-in point ) HT Ca Cabl bles es ( from Design criteria Cable material Cable length from distribution panel to feedin point Cross section Voltage drop (total)
Relative Relative power loss reference to to Max AC power Voltage grade SC withstand current capacity Insulation
IEC-60502 Al 25 ft 2
L1 L2 L3
185mm 1.37V 1.37V 1.37V 0.57% 11KV(UE), heavy duty 26KA @1s XLPE
www.renewpowerzone.in
Page Pa ge 13
Detail Project Report 1MWp SPV Power Plant
Queries@
[email protected]
Line Losses DC Side
AC Side
Total
Total cable length Cable cross section
8120 f t 2 4 mm
3070 ft 2 2 16 mm +185 mm
Power loss @ nominal operation Relative power loss @ nominal operation
35 KW
5 KW
11180 f t 2 2 4 mm +16 mm +185 2 mm 40KW
0 .0 7 %
0.76%
0 . 8 3%
Busbar constructional Analysis Busbar material
Main busbar
Auxilury busbar Copper
Busbar insulation
Al alloy E91 E grade Fully insulated
Busbar length Earthing bus materials
Main Aux 3 .5 m t 0.75mt x 52 GS (IEEE std. 80/IEC-60439-1)
Earthing & Lighting Protection Design Criteria
IEEE Standard-80
Grounding System
Eart Earth h grid grid resi resist sta ance nce
Less Less than than 10 ohm ohm
Placing of earth electrode
Earth Pit
Earth Electrode sizing Physical Parameters
Heavy duty GI pipes, 32mm dia, 3mt long
Material
Galvanized Steel(GS), flat type
Min depth of earth pit
600mm
Components grounding
Min 75x10mm GS strip
Lightning Protection Design criteria
As per IEC-62305 IEC-62305
Placing
On the highest panel of array
Dimension
40mm dia with 3m height (vertical air termination)
www.renewpowerzone.in
Page Pa ge 14
Detail Project Report 1MWp SPV Power Plant
Queries@
[email protected]
CIVIL WORKS Live Loads Loads estimati estimation on of contr control ol room + admin build building ing (as per per IS 875:1987) 875:1987) parameters Roof load Grou Ground nd flo floor load load Piping load Electrical + HVAC Seismic load
details 2 1750 kg/ m 2 Cont Contro roll roo room m 18000kg/m 2 Office 5000kg/ m 2 50 kg/ m 2 26 kg/ kg/ m
Remarks As per IS-456 As per IS-456 IS-456 As per IS-456 As per IS-456 As per IS-456
Roof drainage Roof drain heads
6
Construction details Interwall Ceme Cement nt : Sand Sand Interwall thickness Parapet walls Cement : Sand thickness Steel work
1:6 230mm 1:4 115mm Reinforced bars will be provided as per IS 800:2007
PV Array mounting & constructional details PV tilted angle (optimized) Mounting type Overall dimension Foundation Foundati Foundation on grade grade Wind load Fixing type
Total Land required
0
2
13 (@1070 W/m /day) Ground mounted As per design Plain cement concrete (PCC) 1:5:10 9.72 Km/hr SS 304 fasteners fasteners
5 acres
www.renewpowerzone.in
Page Pa ge 15
Detail Project Report 1MWp SPV Power Plant
Queries@
[email protected]
System Performance Analysis & Simulation
Solar Paths at site on monthly basis
Reference Incident energy in collector plane
Normalized production per installed KWp www.renewpowerzone.in
Page Pa ge 16
Detail Project Report 1MWp SPV Power Plant
Performance Ratio (PR)
Daily System Output Energy
Queries@
[email protected]
Normalized Production & Loss factor
SPV Array Power Distribution
www.renewpowerzone.in
Page Pa ge 17
Detail Project Report 1MWp SPV Power Plant
Queries@
[email protected]
www.renewpowerzone.in
Page Pa ge 18
Detail Project Report 1MWp SPV Power Plant
Queries@
[email protected]
Overall Power plant performance Summery Total no. of PV modules 4326 (250Wp) Total nos. of Inverters 53 (20KW) Max DC input per Inverter 21KW Nominal PV power 1082 KWp Max. PV power output 1027 KWdc Nominal AC power 1060KWac Max operating power @ STC 962KWac Max operating power @Ambient Temp. 1027KWac Plant production 1655 MWh/year Specific production 1526KWh/KWp/year Normalized production 4.2 kWh/KWp/day Array losses 0.87 KWh/Kp/day Overall losses 0.22 KWh/KWp/day Performance ratio 0.80
www.renewpowerzone.in
Page Pa ge 19
Detail Project Report 1MWp SPV Power Plant
Queries@
[email protected]
Time line of the project
Design
Land acquisition
PPA
DPR
finance
•Preparation of design & estimation of the plant •15 working days required.
•As per design requirement, proper land selection & acquisition processed. •Time required 1 month
•Power Purchase Agreement(PPA) Agreement(PPA) with private power purchaser need to be finalized at a feasible rate. •Required time is 15 working days
•Preparation of Detailed Project Report including technical f easibility of the project prepared. •Time required 6 working days.
•Arrangement of finance/fund for the project from nationalized or private financing agency with significant interest rate and equity share will be finalized. •Required time for this stage is 1 month.
•After finalizing PPA and arrangement of fund for the project, procurement work starts including preparation & finalizing of vendor selection, BOM, BOQ, order placing, follow- ups of delivery to site/warehouse. procurement •Estimated time for this step is 1 month.
•After the processing of procurement, procurement, first civil construction at the site starts for PV mounting structure set-up and control-room, administrative building. Finishing the civil works, PV installation & all electrical construction works including the Grid Evacuation will be processed. construction •Estimated time for this whole work is 2 months.
•Commissioning of the plant by authorized govt. body or certified 3rd party will be done followed by Completion of project execution. commission •required time for this step is 6 working days.
ing
www.renewpowerzone.in
Page Pa ge 20
Detail Project Report 1MWp SPV Power Plant
Queries@
[email protected]
Operat Operation ion & Mainte Maintenan nance ce of Plan Plantt Why do we need an O&M for Solar Solar PV power plant? plant? As every plant needs a regular maintenance maintenance work to make it functional & in well -condition, so in this case also, a PV power plant also requires a sound & efficient operation & management team to perform all the work after plant plant commissioning. commissioning. A detailed structure of O&M team has been provided here in a hierarchy model to demonstrate in a simpler way.
operation manager
Plant manager
maintenance Engineer (Mech)
Maintenance engineer(E&IE)
Technician1
Technician2
skilled labour1
skilled labour2
control room technician
Skilled la labour1
Supply chain executive
Accounts executive
skilled la labour2
www.renewpowerzone.in
Page Pa ge 21
Detail Project Report 1MWp SPV Power Plant
Queries@
[email protected]
Financial Analysis & feasibility Initial Investment in terms terms of components’ cost cost & service charges Sl. No.
Components/services
Total cost (in INR)
Remarks
1. 2. 3. 4. 5.
Solar PV modules Solar inverters Transformer Protective devices Wires/Cables
45,100,000 1 1 ,6 6 0 ,0 0 0 2 ,9 4 0 ,0 0 0 1 ,2 0 0 , 0 0 0 1 , 0 0 0 ,0 0 0
41rs/Watt peak 11rs/Watt peak From international vendor From international vendor Considering IEC codes & ISO certified
6. 7. 8. 9.
SCADA/RMS Project execution & commissioning Construction works Grid evacuation
1 , 0 0 0 ,0 0 0 2 ,0 0 0 , 0 0 0 4 , 0 0 0 ,0 0 0 1,000,000 (assumed)
10 .
Other official works
1 ,0 0 0 ,0 0 0
Total Project investment
Assumed because of having no sufficient data Subject to change as per rules 70,900 70,900,00 ,000 0 INR
Total expenses over the year for plant O&M and staffing = 2,000,000 This expense is considered for regular maintenance maintenance cleaning of PV array, checking the status of inverter, cable-fault checking, emergency maintenance & replacement of components and annual salaries of O&M team of the plant. Loan Interest rate rate is @12% over 70% of total total project cost which shall be completed within within next 7 years (the rest 30% as equity shares). Estimated time period Total Loan amount Interest rate E MI Monthly interest total Interest paid
7 years 49,630,000 1 2% 876,110 285,270 23,962,830
10 years 49,630,000 1 2% 712,050 298,460 35,815,600
*all the amounts amounts are considered in INR currency. currency.
www.renewpowerzone.in
Page Pa ge 22
Detail Project Report 1MWp SPV Power Plant
Queries@
[email protected]
Detailed Detailed Analysis Analysis of Install Installment, ment, EMI, EMI, Interest Interest of the 70% 70% project finance/fund Sl. No. 1) 2) 3) 4) 5) 6) 7) 8) 9) 10) 11) 12) 13) 14) 15) 16) 17) 18) 19) 20) 21) 22) 23) 24) 25) 26) 27) 28) 29) 30) 31) 32) 33) 34) 35) 36) 37) 38) 39) 40)
Installments
EMI 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39
0 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105
Monthly principle 0 379,805 383,603 387,439 391,314 395,227 399,179 403,171 407,203 411,275 415,387 419,541 423,737 427,974 432,254 436,576 440,942 445,351 449,805 454,303 458,846 463,434 468,069 472,749 477,477 482,252 487,074 491,945 496,864 501,833 506,851 511,920 517,039 522,210 527,432 532,706 538,033 543,413 548,847 554,336
Monthly Interest 0 496,300 492,502 488,666 484,792 480,878 476,926 472,934 468,903 464,831 460,718 456,564 452,369 448,131 443,851 439,529 435,163 430,754 426,300 421,802 417,259 412,671 408,036 403,356 398,628 393,853 389,031 384,160 379,241 374,272 369,254 364,185 359,066 353,896 348,674 343,399 338,072 332,692 327,258 321,769
www.renewpowerzone.in
Page Pa ge 23
Detail Project Report 1MWp SPV Power Plant 41) 42) 43) 44) 45) 46) 47) 48) 49) 50) 51) 52) 53) 54) 55) 56) 57) 58) 59) 60) 61) 62) 63) 64) 65) 66) 67) 68) 69) 70) 71) 72) 73) 74) 75) 76) 77) 78) 79) 80) 81) 82) 83) 84) 85)
40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84
876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105 876,105
559,879 565,478 571,133 576,844 582,613 588,439 594,323 600,266 606,269 612,332 618,455 624,640 630,886 637,195 643,567 650,002 656,502 663,068 669,698 676,395 683,159 689,991 696,891 703,860 710,898 718,007 725,187 732,439 739,763 747,161 754,633 762,179 769,801 777,499 785,274 793,127 801,058 809,068 817,159 825,331 833,584 841,920 850,339 858,842 867,431
Queries@
[email protected] 316,226 310,627 304,972 299,261 293,492 287,666 281,782 275,839 269,836 263,773 257,650 251,466 245,219 238,910 232,538 226,103 219,603 213,038 206,407 199,710 192,946 186,114 179,214 172,246 165,207 158,098 150,918 143,666 136,342 128,944 121,472 113,926 106,304 98,606 90,831 82,979 75,047 67,037 58,946 50,774 42,521 34,185 25,766 17,263 8,674
www.renewpowerzone.in
Page Pa ge 24
Detail Project Report 1MWp SPV Power Plant
Queries@
[email protected]
1000000 900000 800000 700000 600000
Installment EMI
500000
Monthly Principle 400000
Monthly Interest
300000 200000 100000 0 1 4 7 10 13 16 19 22 25 28 3 1 34 37 40 43 46 49 52 55 58 61 64 67 7 0 73 76 79 82 85
Net Cash Flow/year Flow/year Estimation (all amounts are in INR) Initial Investment 70,900,00 Expenses for O&M per year 2 ,0 0 0 ,0 0 0 Total amount paid/year for loan(7 years term 10,513,320 considered) Tolerance factor 2% Total amount to be paid per year 12,763,600 Energy generated per year 1,655MWh PPA rate for next 12 years 7.5rs/KWh REC floor price 12,000rs/MWh (approx.) Gross cash flow through PPA 12,412,500 Gross cash flow through REC trading 19,860,000 Net Cash Flow (NCF) per year 21,759,180
www.renewpowerzone.in
Page Pa ge 25
Detail Project Report 1MWp SPV Power Plant
Queries@
[email protected]
NET CASH CASH FLOW FLOW & PAY BACK BACK PERIOD PERIOD Now according to Discounted Cash Flow method (considering @10% DCF) years 1 2 3 4 5 6 7 8 9 10
Present value of rs.1 @10% 0 .9 0 9 0 .8 2 6 0 .7 5 1 0 .6 8 3 0 .6 2 1 0 .5 6 4 0 .5 1 3 0 .4 6 7 0 .4 2 4 0 .3 8 6
19,779,094.62 17,973,082.68 16,341,144.18 14,861,519.94 13,512,450.78 12,272,177.52 11,162,459.34 92,145,357.80 83,660,898.56 76,162,987.84
So, Pay Back Period= Period= 6 years 1 month month (approx.) (approx.)
www.renewpowerzone.in
Page Pa ge 26
Detail Project Report 1MWp SPV Power Plant
Queries@
[email protected]
Most suitab suitable le vendo vendors/sup rs/suppliers pliers of the pro project ject compo components nents Solar PV modules
Inverter
Transformer
Switch gear DC Disconnect Circuit breaker
SCADA/RMS Cables
Isolator
1. 2. 3. 4. 5. 6. 1. 2. 3. 4. 5. 6. 1. 2. 3. 4. 1. 2. 1. 1. 2.
Vikram Solar Waar Waaree ee Ener Energi gies es Sova Power Canadian Solar lar Trina Solar First Solar Power One SMA Smart Po Power REFusol Delta Schn Schnei eide derr Elec Electr tric ic ABB Schn Schnei eid der Elec Electr tric ic Asco Ascott tt tran transf sfor orme merr Voltech Schn Schnei eide derr Elec Electr tric ic Megawin Schn Schnei eide derr Elec Electr tric ic Megawin ABB
1. 1. 2. 3. 4. 1. 2. 3.
Draker Havells Finolex cables RR Kabels Anchors ABB Schn Schnei eide derr Elec Electr tric ic Megawin
www.renewpowerzone.in
Page Pa ge 27
Detail Project Report 1MWp SPV Power Plant
Queries@
[email protected]
Conclusion I’d like to thank thank you for reading reading the whole whole paper. paper. Hope you have got got clear view on design design & esti estima mati tion on of of 1MW 1MW util utilit ity y scal scale e Sola Solarr PV Pow Power er Pla Plant nt.. Thou Though gh I have have dis discu cuss ssed ed abo about ut the the technical technical part as well as as the financial financial part in in detail, detail, I might might have been forgot forgot to add add anythin anything g more important. So, you are most welcome to give your valuable valuable feedback & suggestion on this report. At the end, I discussed about some companies for the components. I have chosen these compan companies ies becaus because e their produ products cts are are fulfill fulfilling ing my design design criter criteria. ia. It is not that that I’m represen representin ting g these companies companies and their their produc products. ts. About Myself: Myself: I’m a Solar Solar PV profes profession sional al curren currently tly working working with a solar solar EPC compa company ny as Project Engineer. I’ve done B.Tech in Electrical Engineering & holding a PG certificate in Advanced Solar Energy from delft Technical University, Netherlands. Personally Personally I provide provide technic technical al consulti consulting ng including including site survey, survey, technica technicall design, design, CAD design, design, preparation of DPR, guide guide in procurement & Construction.
You can review review my papers/ papers/repo reports rts at www.wbut.academia.edu/amritmandal Conne Connect ct to my profe profess ssio ional nal prof profil ile e in linke linkedI dIn n at – http://www.linkedin.com/pub/amrit-mandal/55/667/a3
Read solar PV related articles & learn about new technologies at- www.renewpowerzone.in Contact me or send your queries at-
[email protected] ,
[email protected]
THANK YOU
www.renewpowerzone.in
Page Pa ge 28