INSPECTION AND TEST PLAN Rev. 0
RESIDUAL OFFSHORE CONSTRUCTION WORK AT PARADIP
Page 2 of 13
CONTRACT NO. PLCC/PHCPL/SPM/0825
RECORD OF AMMENDMENTS SHEET Version
Purpose
A
Issued for Inter Disciplinary Check (IDC)
B
Issued for Client Review
0
Issued for approval for construction
List of updated/modified sections if any IDC comments are incorporated
Intec comments on section 6.1-6.10 have been incorporated and closed out Section 10.5 – Test pressure changed from 20 bar for 4 hours to 225 psig for 3 hours Section 9 – Added “and Mooring Hawser” Section 9 – Added section 9.2, 9.3, and 9.4
50037-QA-PLN-002
25-11-2008
INSPECTION AND TEST PLAN Rev. 0
RESIDUAL OFFSHORE CONSTRUCTION WORK AT PARADIP
Page 3 of 13
CONTRACT NO. PLCC/PHCPL/SPM/0825
TABLE OF CONTENTS
1.0
INTRODUCTION ........................................................................................................................4
2.0
REFERENCES ...........................................................................................................................5
3.0
TERMS AND DEFINITIONS ......................................................................................................6
4.0
INSPECTION AND TEST PLAN................................................................................................7
50037-QA-PLN-002
25-11-2008
INSPECTION AND TEST PLAN Rev. 0
RESIDUAL OFFSHORE CONSTRUCTION WORK AT PARADIP
Page 4 of 13
CONTRACT NO. PLCC/PHCPL/SPM/0825
1.0 INTRODUCTION 1.1
General
Indian Oil Corporation Ltd (IOCL) is setting up a crude oil receiving facility having Single Point Mooring terminal about 20 Kms off the coast of Paradip port in the east coast of India. This facility will enable to unload the crude oil from the VLCCs to meet the crude oil requirement of its refineries located in the eastern part of India. Global Industries Asia Pacific Pte Ltd (GIAP) has been contracted by Indian Oil Corporation Ltd to perform the Residual Offshore works at Paradip, Group I project, which involves the below scope of work. 1.2 • • •
• • • • • • • • • • •
Scope of Work Pre-installation and Anchor clearance Survey. Towing of the CALM Buoy (11.5m dia., approx 250 T, SBM-IMODCO Turn Table Type) from Paradip Port jetty to SPM location (approx 20 km). Locating and marking the ends of all the six anchor chains. Each chain is studless apprx 345 m long, weighing 70 T and secured to anchor piles positioned at a radius 316m from the CALM Buoy location, equally spaced at 60 deg. Cross Tensioning of the anchor chains upto 300 T. Positioning the CALM Buoy at the PLEM centre and affixing the chains to the Buoy. Leak test of the Floating Hose String at the jetty before transportation to the CALM Buoy location. Transportation, Assembly and Hydro testing of the Submarine Hose Strings. Affixing the 20” dia Submarine Hoses and Associated Systems. Affixing the 24” dia Floating hoses. Installation of the Hydraulic Umbilical from HPU to the PLEM Actuators. Installation of the Mooring Hawser and associated Mooring Systems. Leak Testing of the CALM Buoy System. Commissioning support. Post Installation Survey.
1.3 Document Purpose The purpose of Inspection and Test Plan is to define the type and level of inspection requirements, which are to be performed during the installation, mechanical completion and pre commissioning phases of the project. It also identifies the reference documents to be allowed/ acceptance criteria and verifying documents which are needed to provide the documentary evidence of the successful completion of the inspection activity and compliance with specified test requirements. This Inspection and test plan also specifies the mutually agreed type and level of inspection, such as witnessing, hold, review and monitoring by all relevant parties before the commencement of quality control activities in the project. 50037-QA-PLN-002
25-11-2008
INSPECTION AND TEST PLAN RESIDUAL OFFSHORE CONSTRUCTION WORK AT PARADIP
Rev. 0
Page 5 of 13
CONTRACT NO. PLCC/PHCPL/SPM/0825
2.0 REFERENCES The below are the key reference documents for this project. All external codes and standards of latest versions are available for project reference in Global intranet and accessible for all employees. Sl. No
Document No.
Description
2.1
50037-QA-PLN-001
Project Quality Plan
2.2
50037-PM-PLN-001
Project Execution Plan
2.3
50037-SI-PRD-001
CALM Buoy Installation Procedure
2.4
50037-SI-PRD-002
Anchor Handling and Mooring Procedure
2.5
50037-SI-PRD-003
Pre-commissioning Procedure
2.6
50037-SU-PRD-001
Pre-installation Survey Procedure
2.7
50037-SU-DOC-001
Pre-installation Survey report
2.8
50037-SU-PRD-002
As-Built Survey Procedure
2.9
50037-SU-DOC-002
As-Built Survey Report
2.10
50037-ME-DOC-001
Marine Spread Specifications & Certification Dossier
50037-QA-PLN-002
25-11-2008
INSPECTION AND TEST PLAN RESIDUAL OFFSHORE CONSTRUCTION WORK AT PARADIP
Rev. 0
Page 6 of 13
CONTRACT NO. PLCC/PHCPL/SPM/0825
3.0 TERMS AND DEFINITIONS The key terms/ acronyms etc. are defined in the following table or within individual project documents. Terms and definitions shall be as per ISO 9000:2000. AFC
:
‘Approved for Construction’ by Company
Contractor
:
Global Industries Asia Pacific Pte. Ltd (GIAP)
Company
:
India Oil Corporation Limited (IOCL)
CALM
:
Catenary Anchor Leg Mooring Buoy
FIM
:
Free Issued Material
ITP
:
Inspection and Test Plan
MWS
:
Marine Warranty Surveyor
NCR
:
Non Conformance Report Pipeline End Manifold
PLEM PQP
:
Project Quality Plan is a document specifying which procedures and associated resources shall be applied by whom and when to a specific project product, process or contract.
QA
:
Quality Assurance, Part of quality management, focused on providing confidence that quality requirements will be fulfilled.
QC
:
Quality Control, Part of quality management focused on fulfilling quality requirements.
QMS
:
Quality Management System
ROV
:
Remote Operated Vehicle Single Buoy Mooring
SBM 3rd Party
50037-QA-PLN-002
:
Personnel nominated by the Company to review, witness and/or approve project activities wherever applicable.
25-11-2008
INSPECTION AND TEST PLAN RESIDUAL OFFSHORE CONSTRUCTION WORK AT PARADIP.
Rev. 0
Page 7 of 13
CONTRACT NO. PLCC/PHCPL/SPM/0825
4.0 INSPECTION AND TEST PLAN REF. NO. 1
ACTIVITY DESCRIPTION
LOCATION
REFERENCE PROCEDURE/ ACCEPTANCE CRITERIA
VERIFYING DOCUMENTS
SURVEILLANCES BY GIAP
IOCL
3rd PARTY
INSTALLATION PROCEDURES
1.1
CALM Buoy Installation
Singapore
50037-SI-PRD-001: CALM Buoy Installation Procedure
AFC
P/R
R/A
R/A
1.2
Anchor Handling and Mooring
Singapore
50037-SI-PRD-002: Anchor Handling and Mooring Procedure
AFC
P/R
R/A
R/A
1.3
Pre-commissioning
Singapore
50037-SI-PRD-003: Pre-Commissioning Procedure
AFC
P/R
R/A
R/A
1.3
Pre-installation Survey
Singapore
50037-SU-PRD-001: PreInstallation Survey Procedure
AFC
P/R
R/A
R/A
1.4
As-Built Survey
Singapore
50037-SU-PRD-002: As-Built Survey Procedure
AFC
P/R
R/A
R/A
1.5
Derrick Barge Survey and Positioning
Singapore
50037-SU-PRD-003: Derrick Barge Survey and Positioning Procedures
AFC
P/R
R/A
R/A
P/H
R/A
R/A
2
2.1
RECEIPT OF COMPANY FREE ISSUED MATERIALS (FIM)
Inspect & Receive Company’s FIM.
50037-QA-PLN-002
Paradip port
LEGEND :
• • • •
FIM Delivery Notes Shipping documents Materials certificates OSD Check & Visual inspections
Materials Receiving Report
A: APPROVE
NA: NOT APPLICABLE
R: REVIEW
H: HOLD
P: PERFORM
W: WITNESS
25-11-2008
INSPECTION AND TEST PLAN RESIDUAL OFFSHORE CONSTRUCTION WORK AT PARADIP.
Rev. 0
REF. NO. 3
Page 8 of 13
CONTRACT NO. PLCC/PHCPL/SPM/0825
ACTIVITY DESCRIPTION
LOCATION
REFERENCE PROCEDURE/ ACCEPTANCE CRITERIA
VERIFYING DOCUMENTS
SURVEILLANCES BY GIAP
IOCL
3rd PARTY
FABRICATION OF INSTALLATION AIDS (CHAIN TENSIONER & SPREADER BAR)
3.1
Welding Procedures & Welder Qualification records
Batam
AWS D1.1
Approved documents
R
NA
NA
3.2
Visual & dimensions Inspection
Batam
AWS D1.1 & 50037-DWG-005
As-Built Drawing
W
NA
NA
3.3
NDT
Batam
AWS D1.1 , WPS, WQT, ASNT
NDT Reports
R
NA
NA
3.4
Load Testing of Chain Tensioner & Spreader Bar
Batam
50037-DWG-005 : Chain Tensioner
3rd Party - Load Test/ Functional Test Report
W
NA
NA
3.5
Fabrication Documentation
Batam
WPS, Welder Certs, Electrode Certs, Materials Mill certs, NDT reports, As- As-Built Dossier built drawings, etc
R
NA
NA
P/W
NA
NA
P/W
R
R
4
4.1
4.2
MOBILIZATION & TOWING Ensure the following are secured, lashed, seafastened and preserved properly as per drawings • Diving Spread • Installation Aids • Free Issued Materials Ensure "Tow Approval" issued by Marine Warranty Surveyor
50037-QA-PLN-002
LEGEND :
• 50037-ME-DOC-001: Marine
Spread Specifications & Certification Dossier Batam
• Load-out Drawings & Sea
Fastening Drawings
Paradip port
IOCL appointed MWS’s approval
• MPI Report for deck
welds • Rigging gears
certificates
Tow Approval Certificate by MWS
A: APPROVE
NA: NOT APPLICABLE
R: REVIEW
H: HOLD
P: PERFORM
W: WITNESS
25-11-2008
INSPECTION AND TEST PLAN RESIDUAL OFFSHORE CONSTRUCTION WORK AT PARADIP.
Rev. 0
REF. NO. 5
ACTIVITY DESCRIPTION
6
VERIFYING DOCUMENTS
SURVEILLANCES BY GIAP
IOCL
3rd PARTY
P/W
W/A
W/A
P/W
W/A
W/A
SURVEY • 50037-SU-PRD-003: Derrick
(Locating Anchor Chains & Report any significant seabed debris for resolution) Post Installation As Built Survey.
5.2
REFERENCE PROCEDURE/ ACCEPTANCE CRITERIA
LOCATION
Pre Installation Survey 5.1
Page 9 of 13
CONTRACT NO. PLCC/PHCPL/SPM/0825
(SPM position, positions and angles of anchor chains, positions of Under buoy house , floating hoses, coordinates of PLEM, etc)
CALM Terminal Site
Barge Survey and Positioning Procedures • 50037-SU-PRD-001: PreInstallation Survey Procedure
50037-SU-DOC-001: Pre- Installation Survey Report
50037-SU-PRD-002: As-Built Survey 50037-SU-DOC-002: CALM Terminal As-Built Survey Procedure Site Reports
TENSIONING OF ANCHOR CHAINS & INSTALLATION OF SPM
6.1
Check the calibration status of load cell(s)
CALM Terminal Site
50037-SI-PRD-001: CALM Buoy Installation Procedure
Calibration Certificate
R
R
R
6.2
Ensure that chain is pulled through the chain hawse/chaser
CALM Terminal Site
50037-SI-PRD-001: CALM Buoy Installation Procedure
Visual Check
P
W
W
6.3
Check that tension load is ~ 150T or Cross tensioning to be ~ 300T for anchors chains tensioning
CALM Terminal Site
50037-SI-PRD-001: CALM Buoy Installation Procedure
Anchor Chains Tensioning Report
P/W
W/A
W/A
6.4
Check that each chains are marked with indelible florescent colour visible in water
CALM Terminal Site
50037-SI-PRD-001: CALM Buoy Installation Procedure
Visual check
P/W
W
W
50037-QA-PLN-002
LEGEND :
A: APPROVE
NA: NOT APPLICABLE
R: REVIEW
H: HOLD
P: PERFORM
W: WITNESS
25-11-2008
INSPECTION AND TEST PLAN RESIDUAL OFFSHORE CONSTRUCTION WORK AT PARADIP.
Rev. 0
REF. NO.
Page 10 of 13
CONTRACT NO. PLCC/PHCPL/SPM/0825
ACTIVITY DESCRIPTION
LOCATION
REFERENCE PROCEDURE/ ACCEPTANCE CRITERIA 50037-SI-PRD-001: CALM Buoy Installation Procedure 50037-DI-MAN-001 Diving Procedures Manual 50037-SI-PRD-001: CALM Buoy Installation Procedure 50037-DI-MAN-001 Diving Procedures Manual
VERIFYING DOCUMENTS
SURVEILLANCES BY GIAP
IOCL
3rd PARTY
Visual check
P/W
W
W
Visual check
P/W
W
W
6.5
Check the ends of all six chains are fixed to submerged marker buoy
CALM Terminal Site
6.6
Check that each chains are straight line from anchor piles to SPM
CALM Terminal Site
6.7
Check the chain numbers are marked to indentify with respect to PLEM ~ CALM Buoy
CALM Terminal Site
50037-SI-PRD-001: CALM Buoy Installation Procedure
Visual Check
P/W
W
W
6.8
Check the chains are locked off on a reference link by the Chain Stopper
CALM Terminal Site
50037-SI-PRD-001: CALM Buoy Installation Procedure
Visual Check
P/W
W
W
CALM Terminal Site
50037-SI-PRD-001: CALM Buoy Installation Procedure
Visual Check
P/W
W
W
CALM Terminal Site
50037-SI-PRD-001: CALM Buoy Installation Procedure 50037-DI-MAN-001 Diving Procedures Manual
P/W
W/A
W/A
6.9
Check 2 links remain above the chain stopper after excess chains are cut off.
6.10
Ensure the anchor chains have been installed and connected per procedures / drawings.
50037-QA-PLN-002
LEGEND :
• Fugro Survey Report
for Anchor Chains Installation Report • Diver Survey Report
A: APPROVE
NA: NOT APPLICABLE
R: REVIEW
H: HOLD
P: PERFORM
W: WITNESS
25-11-2008
INSPECTION AND TEST PLAN RESIDUAL OFFSHORE CONSTRUCTION WORK AT PARADIP.
Rev. 0
REF. NO.
6.11
7
Page 11 of 13
CONTRACT NO. PLCC/PHCPL/SPM/0825
ACTIVITY DESCRIPTION
LOCATION
Verify the CALM Buoy system has been CALM Terminal installed in specified positions and coordinates Site
REFERENCE PROCEDURE/ ACCEPTANCE CRITERIA
VERIFYING DOCUMENTS
SURVEILLANCES BY GIAP
IOCL
3rd PARTY
Installation Procedure
Fugro Survey Report for CALM Buoy Installation
P/W
W/A
W/A
• 50037-SI-PRD-001: CALM Buoy
INSTALLATION OF UNDER BUOY HOSES
7.1
Ensure the hose identifications with respect to CALM Terminal SPM / PLEM inlets/ manifolds Site
50037-SI-PRD-002: CALM Buoy Installation Procedure
AFC SBM Assembly Drawings
P
W
W
7.2
Bolts types/ spec are correct for the flanges and hoses
CALM Terminal Site
50037-SI-PRD-002: CALM Buoy Installation Procedure
AFC SBM Assembly Drawings
P
W
W
7.3
Ensure the tightening of flange bolts to the required torque values
CALM Terminal Site
50037-SI-PRD-002: CALM Buoy Installation Procedure
Bolt Tensioning/ Tightening Reports
P/W
R/A
R/A
7.4
Ensure the configuration of Under buoy houses installation is as per AFC drawings
CALM Terminal Site
50037-SI-PRD-002: CALM Buoy Installation Procedure
Fugro – Under Buoy Hoses Configuration Survey Report
P/W
R/A
R/A
8.1
Ensure the hose identifications with respect to CALM Terminal SPM / PLEM inlets/ manifolds Site
50037-SI-PRD-001: CALM Buoy Installation Procedure
AFC SBM Assembly Drawings
P
W
W
8.2
Bolts types/ spec are correct for the flanges and hoses
50037-SI-PRD-001: CALM Buoy Installation Procedure
AFC SBM Assembly Drawings
P
W
W
8
INSTALLATION OF FLOATING HOSES
50037-QA-PLN-002
LEGEND :
CALM Terminal Site
A: APPROVE
NA: NOT APPLICABLE
R: REVIEW
H: HOLD
P: PERFORM
W: WITNESS
25-11-2008
INSPECTION AND TEST PLAN RESIDUAL OFFSHORE CONSTRUCTION WORK AT PARADIP.
Rev. 0
REF. NO.
Page 12 of 13
CONTRACT NO. PLCC/PHCPL/SPM/0825
ACTIVITY DESCRIPTION
LOCATION
REFERENCE PROCEDURE/ ACCEPTANCE CRITERIA
VERIFYING DOCUMENTS
SURVEILLANCES BY GIAP
IOCL
3rd PARTY
8.3
Ensure the tightening of flange bolts to the required torque values
CALM Terminal Site
50037-SI-PRD-001: CALM Buoy Installation Procedure
Bolt Tensioning/ Tightening Reports
P/W
R/A
R/A
8.4
Ensure the configuration of Floating houses installation is as per AFC drawings
CALM Terminal Site
50037-SI-PRD-001: CALM Buoy Installation Procedure
Fugro - Floating Hoses Configuration Survey Report
P/W
R/A
R/A
9
INSTALLATION OF UMBILICAL and MOORING HAWSER
9.1
Ensure umbilical identification with respect to PLEM ~ HPU inlets/outlets.
CALM Terminal S50037-SI-PRD-001: CALM Buoy Site Installation Procedure
Fugro - Umbilical Hoses Configuration Survey Report
P/W
A
A
9.2
Ensure mooring hawser has been preassembled as per AFC drawings
50037-SI-PRD-001: CALM Buoy CALM Terminal Installation Procedure Site Drawing No. MR.00.002.7700
AFC Mooring Hawser drawing
P
A/W
A
9.3
Check all shackles and chain support buoys have split pins or other retaining pin to prevent from backing loose.
50037-SI-PRD-001: CALM Buoy CALM Terminal Installation Procedure Site Drawing No. MR.00.002.7700
AFC Mooring Hawser drawing
P
A/W
A
9.4
Ensure mooring hawser has been securely installed to the mooring arm structure
50037-SI-PRD-001: CALM Buoy CALM Terminal Installation Procedure Site Drawing No. MR.00.002.7700
AFC Mooring Hawser drawing
P
A/W
A
10 10.1 10.2
LEAK TESTS (HOSES & CALM BUOY SYSTEM) Ensure pressure gauges are calibrated and CALM Terminal used within specific test range Site
50037-SI-PRD-003: PreCommissioning Procedure
AFC
P
R
R
CALM Terminal Site
50037-SI-PRD-003: PreCommissioning Procedure
AFC
P
R
R
Check the bleed-off air prior to pressurising
50037-QA-PLN-002
LEGEND :
A: APPROVE
NA: NOT APPLICABLE
R: REVIEW
H: HOLD
P: PERFORM
W: WITNESS
25-11-2008
INSPECTION AND TEST PLAN RESIDUAL OFFSHORE CONSTRUCTION WORK AT PARADIP.
Rev. 0
REF. NO.
ACTIVITY DESCRIPTION
LOCATION
10.3
Check the bleed-off air prior to pressurising
10.4
Leak test for Floating and Under buoy hoses.
10.5
Leak Test of CALM Buoy System. (PLEM Valve ~ Blind of Floating Hoses)
11
Page 13 of 13
CONTRACT NO. PLCC/PHCPL/SPM/0825 REFERENCE PROCEDURE/ ACCEPTANCE CRITERIA
VERIFYING DOCUMENTS
SURVEILLANCES BY GIAP
IOCL
3rd PARTY
P
R
R
CALM Terminal Site
50037-SI-PRD-003: PreCommissioning Procedure
Paradip port
50037-SI-PRD-003: PreCommissioning Procedure
Floating and Under Buoy Hoses Leak Test Report
P/W
W/A
W/A
@ 225 psig for 3 hours
CALM Buoy System Leak Test Report
P/W
W/A
W/A
Company approved installation & survey records, & reports
P/R
R/A
R/A
P/R
R/A
R/A
CALM Terminal Site
AFC
AS BUILT DOCUMENTATION
11.1
Ensure that all as-built documentations/ records are reviewed and approved/signed by relevant parties onboard.
Singapore
50037-AB-DOC-001: As-Built Documents
11.2
Submission of As built for Company approval.
Singapore
50037-AB-DOC-001: As-Built Documents
50037-QA-PLN-002
LEGEND :
AFC
A: APPROVE
NA: NOT APPLICABLE
R: REVIEW
H: HOLD
P: PERFORM
W: WITNESS
25-11-2008