G A S C O National Gas & Industriliazation Company
LPG FILLING PLANTS UPGRADE PROJECT PERFORMANCE TESTING
PERFORMANCE TEST REPORT OF QASSIM CIRCUIT # 1 (JANUARY 29 & 30, 2012)
Submitted by:
Zishan Engineers (Pvt.) Ltd.
An ISO 9001-2008 certified Company Company
Consultants, Designers & Engineers 156, Bangalore Town, Tipu Sultan Road, Karachi-Pakistan. Tel: (+92-21) Tel: (+92-21) 34393045-8, 34550958 & 34550984 Fax: (+92-21) 34533430 E-mail:
[email protected] Web site: www.zishanengineers.com
FEBRUARY - 2012
ZISHAN ENGINEERS (PVT.) LTD.
GASCO UPGRADE PROJECT - QASSIM
CONTENTS S. NO.
DESCRIPTION
SECTION – A1:
PERFORMANCE TEST REPORT – DAY 1
PAGE NO
03
(JANUARY 29, 2012)
SECTION – A2:
PERFORMANCE TEST COUNT TABULATION
11
SHEET DAY 1 (JANUARY 29, 2012)
SECTION – A3:
SITE OBSERVATIONS – DAY 1
13
(JANUARY 29, 2012)
SECTION – B1:
PERFORMANCE TEST REPORT – DAY 2
16
(JANUARY 30, 2012)
SECTION – B2:
PERFORMANCE TEST COUNT TABULATION
24
SHEET DAY 2 (JANUARY 30, 2012)
SECTION – B3:
SITE OBSERVATIONS – DAY 2
27
(JANUARY 30, 2012)
FILE: 217-1-PT-QSM1, REV.0
DOC. NO. 217-1-PT-QSM1, REV.0, DT. 10-02-2012
SHEET 2 OF 35
ZISHAN ENGINEERS (PVT.) LTD.
GASCO UPGRADE PROJECT - QASSIM
CONTENTS S. NO.
DESCRIPTION
SECTION – A1:
PERFORMANCE TEST REPORT – DAY 1
PAGE NO
03
(JANUARY 29, 2012)
SECTION – A2:
PERFORMANCE TEST COUNT TABULATION
11
SHEET DAY 1 (JANUARY 29, 2012)
SECTION – A3:
SITE OBSERVATIONS – DAY 1
13
(JANUARY 29, 2012)
SECTION – B1:
PERFORMANCE TEST REPORT – DAY 2
16
(JANUARY 30, 2012)
SECTION – B2:
PERFORMANCE TEST COUNT TABULATION
24
SHEET DAY 2 (JANUARY 30, 2012)
SECTION – B3:
SITE OBSERVATIONS – DAY 2
27
(JANUARY 30, 2012)
FILE: 217-1-PT-QSM1, REV.0
DOC. NO. 217-1-PT-QSM1, REV.0, DT. 10-02-2012
SHEET 2 OF 35
SECTION – A1 PERFORMANCE TEST REPORT – DAY 1 (JANUARY 29, 2012)
ZISHAN ENGINEERS (PVT.) LTD.
GASCO UPGRADE PROJECT - QASSIM
NATIONAL GAS AND INDUSTRIALIZATION COMPANY (GASCO) LPG FILLING FILLING PLANTS PLANTS UPGRADE PROJECT PERFORMANCE PERFORMANCE TESTING OF QASSIM CIRCUIT#1 1.0
INTRODUCTION
This note is to document the results of the performance testing for 11 kg cylinders th conducted on 29 JANUARY 2012. Basic parameters of the Performance Testing:
2.0
Size of Cylinder Valve Type Specified Capacity Test Duration
– – – –
11 kg Compact (centre valve) 1,740 Cylinders per hours 4 Hours
SUMMARY OF PERFORMANCE TEST
Test conducted between 1002 hrs to 1536 hrs. (Including 94 minutes time out for fixing the problem at Cap Applicator and ET-PT) Total number of cylinders filled during the 4 hours performance test = 6,797 cylinders (including adjustments).
– – – –
Production in 1st Hour = 1,588 cylinders (including adjustments) - Production in 2nd Hour = 1,727 cylinders (including adjustments) - Production in 3rd Hour = 1,787 1, 787 cylinders (including adjustments) - Production in 4th Hour = 1,695 cylinders (including adjustments)
Average cylinders/hour = 1,699 cylinders per hour. The details of the Performance Test are includ ed in the Performance Test Tables attached.
FILE: 217-1-PT-QSM1, REV.0
DOC. NO. 217-1-PT-QSM1, DT. 10-02-2012
SHEET 3 OF 35
ZISHAN ENGINEERS (PVT.) LTD.
3.0
GASCO UPGRADE PROJECT - QASSIM
PERFORMANCE TEST TABLES
The following Table summarizes the details of the Performance Test, as recorded during th test of 29 January 2012: 3.1
PERFORMANCE TEST
PERFORMANCE TEST – DAILY RECORD GASCO QASSIM BRANCH CIRCUIT NO. 1 KOSAN CRISPLANT
Supplier :
th
Date of test:
29 of January 2012
Required production:
11 kg cylinders : 1,740 cylinders per hour
INITIAL UTILITIES CONDITIONS CAROUSEL SPEED ADJUSTMENT
LPG pressure at entrance of carousel before cylinder filling
15 barg
Air pressure at general air network before filling
6.0 barg
Carousel speed (seconds / turn)
54 sec / turn
Entering time of the first cylinder in Steam Sealing Machine (SMS) Time
CYLINDER FILLING PRODUCTION DATA (From the CUC of Steam Sealing Machine )
1002 hrs
Status
Remarks
846 cylinders.
Produced Quantity (Cumulative)
15 barg
LPG pressure at entrance of carousel
After 0.5 hour of production
1032 hrs
6.0 barg
FILE: 217-1-PT-QSM1, REV.0
Air pressure at general network
DOC. NO. 217-1-PT-QSM1, DT. 10-02-2012
SHEET 4 OF 35
ZISHAN ENGINEERS (PVT.) LTD.
CYLINDER FILLING PRODUCTION DATA (From the CUC of Steam Sealing Machine ))
CYLINDER FILLING PRODUCTION DATA (From the CUC of Steam Sealing Machine )
CYLINDER FILLING PRODUCTION DATA (From the CUC of Steam Sealing Machine )
CYLINDER FILLING PRODUCTION DATA (From the CUC of Steam Sealing Machine )
CYLINDER FILLING PRODUCTION DATA (From the CUC of Steam Sealing Machine )
FILE: 217-1-PT-QSM1, REV.0
GASCO UPGRADE PROJECT - QASSIM
1,611 cylinders.
Produced Quantity (Cumulative)
15.5 barg
LPG pressure at entrance of carousel
6.2 barg
AIR pressure at general network
2,480 cylinders.
Produced Quantity (Cumulative)
15 barg
LPG pressure at entrance of carousel
6.2 barg
AIR pressure at general network
2,736 cylinders.
Produced Quantity (Cumulative)
15 barg
LPG pressure at entrance of carousel
6.0 barg
AIR pressure at general network
2,778 cylinders.
Produced Quantity (Cumulative)
15.5 barg
LPG pressure at entrance of carousel
6.2 barg
AIR pressure at general network
3,671 cylinders.
Produced Quantity (Cumulative)
14.9 barg
LPG pressure at entrance of carousel
1102 hrs
1132 hrs
1141 hrs
1315 hrs
1345 hrs
After 1.0 hour of production
After1.5 hours of production
After 1.65 hours of production i.e., at the stoppage of production for time out requested by KC
At the resumption of production after the time out
After 0.5 hour of resumption of production 6.0 barg
AIR pressure at general network
DOC. NO. 217-1-PT-QSM1, DT. 10-02-2012
SHEET 5 OF 35
ZISHAN ENGINEERS (PVT.) LTD.
CYLINDER FILLING PRODUCTION DATA (From the CUC of Steam Sealing Machine )
CYLINDER FILLING PRODUCTION DATA (From the CUC of Steam Sealing Machine )
GASCO UPGRADE PROJECT - QASSIM
4,524 cylinders.
Produced Quantity (Cumulative)
15 barg
LPG pressure at entrance of carousel
6.2 barg
AIR pressure at general network
5,395 cylinders.
Produced Quantity (Cumulative)
15 barg
LPG pressure at entrance of carousel
1415 hrs
1445 hrs
6.2 barg
CYLINDER FILLING PRODUCTION DATA (From the CUC of Steam Sealing Machine )
CYLINDER FILLING PRODUCTION DATA (From the CUC of Steam Sealing Machine )
Produced Quantity (Cumulative)
15 barg
LPG pressure at entrance of carousel
6.2 barg
AIR pressure at general network
6,833 cylinders.
Produced Quantity (Cumulative)
15 barg
LPG pressure at entrance of carousel
6.2 barg
AIR pressure at general network
1515 hrs
FILE: 217-1-PT-QSM1, REV.0
After 1.5 hours of resumption of production
AIR pressure at general network
6,205 cylinders.
1536 hrs
After 1.0 hour of resumption of production
DOC. NO. 217-1-PT-QSM1, DT. 10-02-2012
After 2.0 hours of resumption of production
After 2.35 hours of resumption of production
SHEET 6 OF 35
ZISHAN ENGINEERS (PVT.) LTD.
3.2
GASCO UPGRADE PROJECT - QASSIM
FILLED QUANTITIES (ON THE BASIS OF STEAM SEALING MACHINES CUC COUNT)
ACTUAL CYLINDER FILLING PRODUCTION (At the end of the Performance Test) :
Quantity of filled cylinders given by Steam Sealing Machine CUC counter
6,833
cylinders
Quantity of filled cylinders sorted out by Check Scale
104
cylinders
Quantity of filled cylinders manually sorted out after the Steam Sealing Machine :
-183
cylinders
Quantity of filled cylinders sorted out by the ET-GD Machine :
12
cylinders
Quantity of filled cylinders sorted out by the ET-PT machine :
37
cylinders
36
cylinders
-42
cylinders
6797
cylinders
6,797
cylinders
1,699
cylinders / hour
6,960
cylinders
1,740
cylinders / hour
Quantity of cylinders adjusted due to the 11 sec. stoppage at the Steam Sealing machine for taking reading at each of the 30 min. time interval: Quantity of filled cylinders that passed through the Steam Sealing machine during the time out : TOTAL CYLINDERS FILLING PRODUCTION (ADJUSTED) AT THE END OF PERFORMANCE TEST
TOTAL CYLINDER FILLING PRODUCTION AT THE END OF THE PERFORMANCE TEST
CONTRACTUAL TOTAL CYLINDER FILLING PRODUCTION AT THE END OF THE PERFORMANCE TEST
FILE: 217-1-PT-QSM1, REV.0
DOC. NO. 217-1-PT-QSM1, DT. 10-02-2012
SHEET 7 OF 35
ZISHAN ENGINEERS (PVT.) LTD.
3.3
GASCO UPGRADE PROJECT - QASSIM
FILLED QUANTITIES (ON THE BASIS OF PHYSICAL COUNT) Quantity of pallets of filled cylinders in storage area
191
pallets
6,685
cylinders
6
cylinders
Quantity of filled cylinders sorted out by Check Scale
104
cylinders
Quantity of filled cylinders sorted out by the ET-GD Machine :
12
cylinders
Quantity of filled cylinders sorted out by the ET-PT Machine :
37
cylinders
Quantity of filled cylinders at the palletizing unit at the start of t he PT :
-27
cylinders
-42
cylinders
6,775
cylinders
6,775
cylinders
1,694
cylinders / hour
6,960
cylinders
1,740
cylinders / hour
Quantity of filled cylinders in pallets located in storage area Quantity of filled cylinders remaining on the palletizing unit :
ACTUAL CYLINDER FILLING PRODUCTION (Physical Count at the end of Performance Test)
Quantity of filled cylinders that passed through the Steam Sealing machine during the time out : TOTAL CYLINDERS FILLING PRODUCTION AT THE END OF PERFORMANCE TEST
TOTAL CYLINDER FILLING PRODUCTION AT THE END OF THE PERFORMANCE TEST
CONTRACTUAL TOTAL CYLINDER FILLING PRODUCTION AT THE END OF THE PERFORMANCE TEST
FILE: 217-1-PT-QSM1, REV.0
DOC. NO. 217-1-PT-QSM1, DT. 10-02-2012
SHEET 8 OF 35
ZISHAN ENGINEERS (PVT.) LTD.
GASCO UPGRADE PROJECT - QASSIM
3.4
STOPPAGES RECORDS
3.4.1
PALLET PLANT Time
PALLETIZING UNIT RECORDS (for performance evaluation)
Stop at :
1135 hrs
Start at :
1135 hrs
Stop at :
______hrs
Reason of stoppage : At Stand 4 i.e. Unloading Table; bad pallet lifting bar entangles with the bar lift gripper clamp, takes 30 sec effort to ride properly on the bar lift gripper clamp with the help of operator.
Start at :
_____hrs
Stop at :
_____hrs
Start at :
3.4.2
______hrs
OTHER MACHINES
OTHER EQUIPMENTS RECORDS
Stop at : Start at : Stop at :
1355 hrs
Start at :
1355 hrs
Stop at :
____ hrs
ET-PT
Due to a Cylinder fell down on the main conveyor between the ACA stopper and the conveyor stopper which caused the machine to stop for about 20 secs. at 1355 Hrs.
-
ET-GD Start at :
Machine:
_____hrs _____hrs
CAROUSEL
Machine:
Reason of stoppage :
-
Machine:
Machine:
Time
____ hrs
Stop at :
1141 hrs
Start at :
1315 hrs
CAPPING MACHINE
FILE: 217-1-PT-QSM1, REV.0
At 1141 Hrs. the break / time out for 30 min. was awarded to KC as per their demand for maintenance work initially on the Automatic Cap Applicator which lasted for the 94 min. (till the time of 1315 Hrs.). Also because of the extra maintenance work on the ET-PT machine as well.
DOC. NO. 217-1-PT-QSM1, DT. 10-02-2012
SHEET 9 OF 35
ZISHAN ENGINEERS (PVT.) LTD.
Machine:
GASCO UPGRADE PROJECT - QASSIM
Stop at :
1341 hrs
Start at :
1341 hrs
Stop at :
1355 hrs
Start at :
1355 hrs
Stop at :
1445 hrs
Start at :
1445 hrs
Stop at :
1525 hrs
Start at :
1525 hrs
STEAM SEALING MACHINE
FILE: 217-1-PT-QSM1, REV.0
The cap bundles placement was adjusted in the cap feeding unit tray of Automatic Cap Applicator. The machine stopped for 16 secs. at 1341Hrs At the upstream of the Automatic Cap Applicator, a Cylinder fell down on the main conveyor between the ACA stopper and the conveyor stopper which caused the machine to stop for about 39 secs. at 1355 Hrs. A stoppage occurred at the machine of about 19 secs. KC to elaborate the reason for this stoppage.
A stoppage occurred at the machine of about 10 secs. KC to elaborate the reason for this stoppage.
DOC. NO. 217-1-PT-QSM1, DT. 10-02-2012
SHEET 10 OF 35
SECTION – A2 PERFORMANCE TEST COUNT TABULATION SHEET DAY 1 (JANUARY 29, 2012)
ZISHAN ENGINEERS (PVT.) LTD.
GASCO UPGRADE PROJECT- QASSIM
NATIONAL GAS AND INDUSTRIALIZATION COMPANY (GASCO) LPG FILLING PLANTS UPGRADE PROJECT PERFORMANCE TEST QASSIM CIRCUIT-1 COUNT TABULATION SHEET - FIRST DAY 29TH JANUARY 2012
S.NO.
CYLINDERS HOURS COUNT FROM CUC SMS
ADJ. DUE TO FINAL ADJUSTED 11 SEC. STOP HOURLY HOURLY FOR READ ADJUSTED MANUAL PRODUCTION SMS COUNT FIGURE AFTER SMS
NOS. OF SOURT OUT CYLINDERS AT CHECK SCALE
ET-GD
ET-PT
START
1002
0
0
0
0
0
1
1032
846
11
0
6
36
2
1102
1,611
10
0
9
33
Total (First Hour)
1,611
21
0
15
69
3
1132
2,480
13
0
7
60
4
1141
2,736
9
0
10
18
1,125
22
0
17
78
Total (39 Mins in 2nd Hr.)
1,578
10
1,588
1,578
10
1,588
1,086
5
1,091
1,086
5
1,091
1,776
11
1,787
1,776
11
1,787
1,685
10
1,695
BREAK FOR ADJUSTMENT IN CAP APPLICATOR AND ET-PT START
1315
2,778
0
0
0
0
6
1345
3,671
22
0
3
6
7
1415
4,524
18
1
2
10
1,746
40
1
5
16
Total (Third Hour) 8
1445
5,395
4
0
0
9
9
1515
6,205
17
0
0
8
Total (Forth Hour)
1,681
21
0
0
17
1,685
10
1,695
10
6,833
0
11
0
3
636
0
636
628
0
11
0
3
636
0
636
104
12
37
183
6761
36
6797
PRODUCTION IN FIRST HOUR
=
1,588
Cylinders
PRODUCTION IN 39 MINS. IN SECOND HOUR + 21 MINS. IN LAST HOUR
=
1,727
Cylinders
PRODUCTION IN THIRD HOUR
=
1,787
Cylinders
PRODUCTION IN FORTH HOUR
=
1,695
Cylinders
TOTAL PRODUCTION IN FOUR HOURS
=
6,797
Cylinders
AVERAGE HOURLY PRODUCTION
=
1,699
Cylinders
1536
Total (21 Mins in last Hr.) GRAND TOTAL
FILE: 217-1-PT-QSM1, REV.0
DOC. NO. 217-1-PT-QSM1, DT. 10-02-2012
SHEET 11 OF 35
ZISHAN ENGINEERS (PVT.) LTD.
GASCO UPGRADE PROJECT- QASSIM
PHYSICAL COUNT:
HOURS
HOURLY PRODUCTION
SORT OUT CYLINDERS AT CHECK SCALE, ET-GD AND ET-PT
ADJUSTED HOURLY PRODUCTION
1002 - 1102
1538
36
1,574
1102 - 1141
1,039
39
1,078
BREAK FOR ADJUSTMENT IN CAP APPLICATOR AND ET-PT 1315- 1415
1,740
46
1,786
1415 - 1515
1,655
21
1,676
1515 - 1536
650
11
661
TOTAL
6,622
153
6,775
PR ODUCT ION IN 39 MINS. BEF ORE BR EAK + 21 MINS . AF TER BR EAK =
TOTAL PHYSICAL COUNT
=
TOTAL CYLINDERS IN YARD
=
TOTAL CYLINDERS IN YARD
= 191 x 35 + 6
6,775
Cylinders
Cylinders
191 PALLETS + 6 CYLINDERS AT PALLETIZER 6,691
SORT OUT CYLINDERS AT CHECK SCALE, ET-GD AND ET-P DEDUCTIONS
1,739
CYLINDERS
=
153
= 27 CYLINDERS AT PALLETIZER AT START OF PT AND 42 CYLINDERS UPSTREAM OF SMS PALLETIZED AFTER BREAK
NET PHYSICAL COUNT.
FILE: 217-1-PT-QSM1, REV.0
6691 +153 - 27 - 42
=
DOC. NO. 217-1-PT-QSM1, DT. 10-02-2012
6,775
Cylinders
SHEET 12 OF 35
SECTION – A3 SITE OBSERVATIONS – DAY 1 (JANUARY 29, 2012)
ZISHAN ENGINEERS (PVT.) LTD.
GASCO UPGRADE PROJECT - QASSIM
SITE OBSERVATIONS PT DAY 1 DT 29-01-12
1.
The provided air blowing cap dispensing mechanism in the cap applicator machine, at times have unsatisfactory cap dispensing. As the provided caps are push fit type, therefore the caps have loose seating on the centre valve. Later on KC changes the blowing mechanism with the pneumatically operated pusher rod which reduces the number of sort outs at SMS. As indicated in the Count Tabulation Sheet, the numbers of sort outs cylinders at SMS due to ineffective capping with air blowing mechanism before the time out were 147 in 1 hour and 39 minutes while after installing the pushing rod the figure was 36 in 2 hours and 21 minutes.
2.
Frequent cap falling was observed when the cap blown from the loading tray magazine into the bell.
3.
It was observed that the ET-PT needed to be restarted after the sorting of every other 2 or 3 cylinders.
4.
The Automatic Cap Applicator stops and is needed to be restarted because if it detects that cap is not blown to the dispensing bell.
5.
At the emptying rack, C-type emptying heads are not installed and for this reason cylinders rejected by ET-PT could not be evacuated. KC is required to provide the missing heads.
6.
There is a hole on the floor in the filling hall near the Automatic Cap Applicator machine on which a checker plate is placed to cover it. KC needs to explain the reason for this unsealed hole as there is a possibility of gas residing inside.
7.
Expansion joint filler/caulk material/cork fibre from the floor joint by the floor portion near the cap applicator machine is missing. KC is required to provide the same.
8.
It has been also observed that there was an earth wire disconnected over one of the head of ET-GD.
9.
KC took the time out for replacing the air blowing system for dispensing the caps over the cylinder with the pushing rod on the ACA. Later on when the test was resumed after 94 mins. it was discovered that some maintenance works was also carried out on the ET-PT machine which took the longer time than the approved 30 mins.
10.
It was observed that the Steam sealing machine centring arms were coming hard onto the cylinder at the SMS causing caps tilting or falling off from the valve of the cylinder due to which cylinders comes out from the SMS either without the caps or caps with improper sealing.
FILE: 217-1-PT-QSM1, REV.0
DOC. NO. 217-1-PT-QSM1, DT. 10-02-2012
SHEET 13 OF 35
ZISHAN ENGINEERS (PVT.) LTD.
GASCO UPGRADE PROJECT - QASSIM
11.
ET-PT machine was found to sort out the cylinders falsely as the rejected cylinders when checked were found to have both of the gaskets intact.
12.
The Electrical MCC of the Plant was found to be bolted with only one Allen Bolts. KC is advised to bolt the door of the MCC Panel with all of the required bolts while the LPG filling is progress.
13.
On the sort out (roller) conveyors, locking pins for the rollers are missing. KC to look into the matter.
14. No proper stopper has been provided at the end of each roller conveyor to avoid tilting and falling down of the cylinder on the ground during the circuit run. KC is required to provide a suitable height stopper at the end. 15.
At Stand 4 of Palletizer, one side of the loading sensor (Buffer) table requires a wear plate or stopper to be installed to counter cylinder slippage in the opposite direction of chain conveyor motion, can be caused by the dis-aligned cylinders row push by the pusher.The stopper or wear plate should be the same as provided on conveyor portion in front of stand 6.
16.
Optical sensor installed, at the Stand 2 (Un-stacker table) for sensing the incoming pallet stack required one more bolt at the bracket on which it is installed, so that the position with respect to the line sight of reflector could not get change for any reason.
17.
Cable tray portion running above the downstream of SMS machine, have supports more than 3 meters apart causing a sag in the tray. KC is required to provide another support in the middle to remove the sag as agreed on site.
18.
Cable tray drop at the steam generation machine has vibration because of the longer arm drop from above and only anchored at the floor. KC is required to provide the support as agreed on site.
19.
The tender requirement for the palletizer removing stand i.e. stand 9 could not be verified which says that when the forklift driver completely removes the filled cylinder pallet stack only then the system should allow the waiting pallet at stand 8 to move on to stand 9. It seems that either the interlock is not based on the signals from the optical sensor installed to detect the presence of forklift or the detection range of the optical sensor is not enough. It is understood that the detecting the presence of an object/forklift should be equal to the length of the arms of the forklift. KC to look into the matter for identification of the problem and share the corrective measure taken in this regard. During the test fulfilment of the tender requirement could not be verified and it seems that the transition of pallets from stand 8 to stand 9 is based on some time delay & not on some interlock of the stand 9 Induction sensor & optical sensor.
FILE: 217-1-PT-QSM1, REV.0
DOC. NO. 217-1-PT-QSM1, DT. 10-02-2012
SHEET 14 OF 35
ZISHAN ENGINEERS (PVT.) LTD.
GASCO UPGRADE PROJECT - QASSIM
20.
At upstream of Leak Detector (ET-GD), filled cylinders were entangled with each other at turning on chain conveyor due to the forces exerted by the cylinders train. Manual interruption was made to pull the cylinders out of the conveyor and adjust the train of cylinders for smooth operation. KC to check and sort out this problem.
21.
On first day of the PT, LPG filling tolerance set on Check Scale was ±100 grams and there were 104 number cylinders sorted out by the Check Scale. Out of these 104 cylinders, 84 have weight within tolerance i-e, 27kg ±100 grams, 11 cylinders were overfilled, 4 numbers underfilled cylinders and 5 nos. empty cylinders. KC is required to explain that why the majority of accurately filled cylinders were sorted out by the Check Scale.
22.
Some of the filled cylinders at Carousel were not pushed out to outer conveyor and took two turns despite being fully filled.
23.
In the production management system the RCC application prints the generated report of the production but print preview option looks disable. Whereas, whenever a print out of the graphs of cylinder sort outs, Filling statistics, Interruptions, Residual Gas & Capacity has been asked it gives an error message and on retry or ignore option selection abruptly shut down the RCC application. KC is required to fix the problem. Also it will be appreciated if the generated .gph files be saved as .pdf files.
24.
In the SCADA system “Cylinder Inlet” window is provided for the key in post but no cylinder information or CUC messages has been communicated to show real time data & information during the circuit run. It seems that there is a permanent communication failure between the Key in post CUC and the PMS. KC to look into the matter and rectify the problem.
25.
In the following lines day one PT production counts from PMS, CUC & Physical counts are given for comparison: i) ii) iii)
SMS CUC Count = 6797 (After Adjustment) Physical Count = 6775 (After Adjustment) PMS Report Count = 6950 – 183 = 6767 (Total including sort outs at adjustment scale – Total sort outs at SMS) iv) Sort out at Adjustment Scale = 104 (Physical Count) v) PMS Report Sort out at Scale = 98 vi) Sort out at ET/GD = 12 (Physical Count) vii) PMS Report Sort out at ET/GD = No Data (Report Attached) viii) Sort out at ET/PT = 37(Physical Count) ix) PMS Report Sort out at ET/GD = No Data (Report Attached)
FILE: 217-1-PT-QSM1, REV.0
DOC. NO. 217-1-PT-QSM1, DT. 10-02-2012
SHEET 15 OF 35
SECTION – B1 PERFORMANCE TEST REPORT – DAY 2 (JANUARY 30, 2012)
ZISHAN ENGINEERS (PVT.) LTD.
GASCO UPGRADE PROJECT - QASSIM
NATIONAL GAS AND INDUSTRIALIZATION COMPANY (GASCO) LPG FILLING PLANTS UPGRADE PROJECT PERFORMANCE TESTING OF QASSIM CIRCUIT#1 1.0
INTRODUCTION
This note is to document the results of the performance testing for 11 kg cylinders th conducted on 30 JANUARY 2012. Basic parameters of the Performance Testing:
2.0
Size of Cylinder Valve Type Specified Capacity Test Duration
– – – –
11kg Compact (centre valve) 1,740 Cylinders per hours 4 Hours
SUMMARY OF PERFORMANCE TEST
Test conducted between 1031 hrs to 1431 hrs. Total number of cylinders filled during the 4 hours performance test = 6,816 cylinders (including adjustments).
– – – –
Production in 1st Hour = 1,663 cylinders (including adjustments) - Production in 2nd Hour = 1,755 cylinders (including adjustments) - Production in 3rd Hour = 1,596 cylinders (including adjustments) - Production in 4th Hour = 1,802 cylinders (including adjustments)
Average cylinders/hour = 1,704 cylinders per hour. The details of the Performance Test are includ ed in the Performance Test Tables attached.
FILE: 217-1-PT-QSM1, REV.0
DOC. NO. 217-1-PT-QSM1, DT. 10-02-2012
SHEET 16 OF 35
ZISHAN ENGINEERS (PVT.) LTD.
3.0
GASCO UPGRADE PROJECT - QASSIM
PERFORMANCE TEST TABLES
The following Table summarizes the details of the Performance Test, as recorded during th test of 30 January 2012: 3.1
PERFORMANCE TEST
PERFORMANCE TEST – DAILY RECORD GASCO QASSIM BRANCH CIRCUIT NO. 1 KOSAN CRISPLANT
Supplier :
th
Date of test:
30 of January 2012
Required production:
11 kg cylinders : 1,740 cylinders per hour
INITIAL UTILITIES CONDITIONS CAROUSEL SPEED ADJUSTMENT
LPG pressure at entrance of carousel before cylinder filling
15 barg
Air pressure at general air network before filling
6.1 barg
Carousel speed (seconds / turn)
54 sec / turn
Entering time of the first cylinder in Steam Sealing Machine (SMS) Time
CYLINDER FILLING PRODUCTION DATA (From the CUC of Steam Sealing Machine )
1031 hrs
Status
Remarks
761 cylinders.
Produced Quantity (Cumulative)
15.5 barg
LPG pressure at entrance of carousel
After 0.5 hour of production
1101 hrs
6.2 barg
FILE: 217-1-PT-QSM1, REV.0
Air pressure at general network
DOC. NO. 217-1-PT-QSM1, DT. 10-02-2012
SHEET 17 OF 35
ZISHAN ENGINEERS (PVT.) LTD.
CYLINDER FILLING PRODUCTION DATA (From the CUC of Steam Sealing Machine ) CYLINDER FILLING PRODUCTION DATA (From the CUC of Steam Sealing Machine )
CYLINDER FILLING PRODUCTION DATA (From the CUC of Steam Sealing Machine )
CYLINDER FILLING PRODUCTION DATA (From the CUC of Steam Sealing Machine )
CYLINDER FILLING PRODUCTION DATA (From the CUC of Steam Sealing Machine )
FILE: 217-1-PT-QSM1, REV.0
GASCO UPGRADE PROJECT - QASSIM
1131 hrs
1,612 cylinders.
Produced Quantity (Cumulative)
15 barg
LPG pressure at entrance of carousel
6.2 barg
AIR pressure at general network
2,488 cylinders.
Produced Quantity (Cumulative)
15.3 barg
LPG pressure at entrance of carousel
6.2 barg
AIR pressure at general network
3,398 cylinders.
Produced Quantity (Cumulative)
14.9 barg
LPG pressure at entrance of carousel
6.2 barg
AIR pressure at general network
4,226 cylinders.
Produced Quantity (Cumulative)
15.2 barg
LPG pressure at entrance of carousel
6.2 barg
AIR pressure at general network
5,069 cylinders.
Produced Quantity (Cumulative)
14.8 barg
LPG pressure at entrance of carousel
1201 hrs
1231 hrs
1301 hrs
1331 hrs
After 1.0 hour of production
After1.5 hours of production
After 2.0 hours of production
After 2.5 hours of production
After 3.0 hours of production 6.2 barg
AIR pressure at general network
DOC. NO. 217-1-PT-QSM1, DT. 10-02-2012
SHEET 18 OF 35
ZISHAN ENGINEERS (PVT.) LTD.
CYLINDER FILLING PRODUCTION DATA (From the CUC of Steam Sealing Machine ))
CYLINDER FILLING PRODUCTION DATA (From the CUC of Steam Sealing Machine ))
GASCO UPGRADE PROJECT - QASSIM
1401 hrs
5,974 cylinders.
Produced Quantity (Cumulative)
15.2 barg
LPG pressure at entrance of carousel
6.1 barg
AIR pressure at general network
6,843 cylinders.
Produced Quantity (Cumulative)
15.2 barg
LPG pressure at entrance of carousel
After 3.5 hours of production
1431 hrs
6.2 barg
FILE: 217-1-PT-QSM1, REV.0
After 4.0 hours of production
AIR pressure at general network
DOC. NO. 217-1-PT-QSM1, DT. 10-02-2012
SHEET 19 OF 35
ZISHAN ENGINEERS (PVT.) LTD.
3.2
GASCO UPGRADE PROJECT - QASSIM
FILLED QUANTITIES (ON THE BASIS OF STEAM SEALING MACHINES CUC COUNT)
ACTUAL CYLINDER FILLING PRODUCTION (At the end of the performance test) :
Quantity of filled cylinders given by Steam Sealing Machine CUC counter
6,843
cylinders
Quantity of filled cylinders sorted out by Check Scale
34
cylinders
-186
cylinders
Quantity of filled cylinders sorted out by the ET-GD Machine :
71
cylinders
Quantity of filled cylinders sorted out by the ET-PT machine :
12
cylinders
42
cylinders
6,816
cylinders
6,816
cylinders
1,704
cylinders / hour
6,960
cylinders
1,740
cylinders / hour
Quantity of filled cylinders manually sorted out after the Steam Sealing Machine :
Quantity of cylinders adjusted due to the 11 sec. stoppage at the Steam Sealing machine for taking reading at each of the 30 min. time interval: TOTAL CYLINDERS FILLING PRODUCTION AT THE END OF PERFORMANCE TEST
TOTAL CYLINDER FILLING PRODUCTION AT THE END OF THE PERFORMANCE TEST
CONTRACTUAL TOTAL CYLINDER FILLING PRODUCTION AT THE END OF THE PERFORMANCE TEST
FILE: 217-1-PT-QSM1, REV.0
DOC. NO. 217-1-PT-QSM1, DT. 10-02-2012
SHEET 20 OF 35
ZISHAN ENGINEERS (PVT.) LTD.
3.3
GASCO UPGRADE PROJECT - QASSIM
FILLED QUANTITIES (ON THE BASIS OF PHYSICAL COUNT) Quantity of pallets of filled cylinders in storage area
190
pallets
6,650
cylinders
Quantity of filled cylinders remaining on the palletizing unit :
13
cylinders
Quantity of filled cylinders sorted out by Check Scale
34
cylinders
Quantity of filled cylinders sorted out by the ET-GD Machine :
71
cylinders
Quantity of filled cylinders sorted out by the ET-PT Machine :
12
cylinders
6,780
cylinders
6,780
cylinders
1,695
cylinders / hour
6,960
cylinders
1,740
cylinders / hour
Quantity of filled cylinders in pallets located in storage area
ACTUAL CYLINDER FILLING PRODUCTION (Physical Count at the end of Performance Test)
TOTAL CYLINDERS FILLING PRODUCTION AT THE END OF PERFORMANCE TEST
TOTAL CYLINDER FILLING PRODUCTION AT THE END OF THE PERFORMANCE TEST
CONTRACTUAL TOTAL CYLINDER FILLING PRODUCTION AT THE END OF THE PERFORMANCE TEST
FILE: 217-1-PT-QSM1, REV.0
DOC. NO. 217-1-PT-QSM1, DT. 10-02-2012
SHEET 21 OF 35
ZISHAN ENGINEERS (PVT.) LTD.
GASCO UPGRADE PROJECT - QASSIM
3.4
STOPPAGES RECORDS
3.4.1
PALLET PLANT Time
PALLETIZING UNIT RECORDS (for performance evaluation)
Stop at :
1043 hrs
Start at :
1043 hrs
Stop at :
1045 hrs
Start at :
1049 hrs
Stop at :
1124 hrs
Start at :
1125 hrs
Stop at :
1146 hrs
Start at :
1147 hrs
Stop at :
1256 hrs
Start at :
1257 hrs
Stop at :
1259 hrs
Start at :
1259 hrs
Stop at :
1301 hrs
Start at :
1302 hrs
FILE: 217-1-PT-QSM1, REV.0
Reason of stoppage : Palletizing/loading operation stops at stand 6 as no empty pallet was available at Stand 5 to move to stand 6, this is because of unloading operation halted and waiting to be resume at stand 4 once the unloaded cylinder row at buffer (loading sensor) moves toward carousel inlet which was in turn waiting on inlet module to start injecting the cylinders into the carousel. To break the cycle an empty pallet was put by forklift operator at stand 5 so that loading operation at stand 6 resumes. Introduction of Empty pallet at stand 5 takes 32 sec by the forklift operator. Palletizer operation was disrupted from stand 3 to stand 5 because the locking jacks failed to engage the pallets in time to stop them at the designated position on stands 3, 4, & 5 even the empty cylinder pallet transition from stand 3 to stand 4 was a complete failu re and all the pallets moving on the transfer path on these stands gets entangled with each other. Forklift was employed to remove all these pallets form the transfer path and CUC was reset. The lost time was 4 min 14 sec.
Because of cylinder jamming at the Inlet conveyor palletizing operation stops at stand 6 as the buffer at stand 5 has no empty pallet to move on as waiting on stand 4 to release the empty pallet after unloading the cylinders. It takes 35sec to resume loading at stand 6 once the operation of unloading at stand4 gets completed normally Inlet module stops injecting cylinders into carousel causing jamming at inlet conveyor which in turns halted t he unloading operation at table 4 as no room to push the new row of cylinders on the conveyor. After 37 secs operation resumes. At Stand 4 i.e. Unloading Table; bad pallet lifting bar gets jammed in one of the pallet resting hook, on operator intervention takes 20 sec to release the bar from the resting hook.
Removal of bad pallet from stand 5 by the forklift operator. 14 sec lost time in the resumption of Stand 6 operation.
Stand 6 i.e. loading table operation stops as no pallet was available to load the cylinders. After 40 sec forklift operator put empty pallet at stand 5 which takes 7 sec transition time to reach stand 6.
DOC. NO. 217-1-PT-QSM1, DT. 10-02-2012
SHEET 22 OF 35
ZISHAN ENGINEERS (PVT.) LTD.
3.4.2
GASCO UPGRADE PROJECT - QASSIM
OTHER MACHINES
OTHER EQUIPMENTS RECORDS
Machine:
Machine:
Machine:
Time
Reason of stoppage :
Stop at :
1047 hrs
Start at :
1050 hrs
Carousel inlet stopped as no cylinder available at the inlet conveyor. I t was the consequence of the stoppage at Palletizer Unit at 1045 hrs. The time lost was 3 minutes 14 seconds.
Stop at :
1301 hrs
Start at :
1303 hrs
Stop at :
____hrs
Start at :
_____hrs
Stop at :
____ hrs
CAROUSEL
Carousel inlet stopped as no cylinder available at the inlet conveyor. It was the consequences of the stoppage at Palletizer Unit at 1256 hrs , 1259 hrs and 1301 hrs . The time lost was 1 minute 35 seconds.
ET-PT
-
-
ET-GD Start at :
____ hrs
Stop at :
_____hrs
-
Machine:
Start at :
_____hrs
Stop at :
_____hrs
CAPPING MACHINE
Start at :
_____hrs
Stop at :
______hrs
-
Machine:
Start at :
______hrs
Stop at :
______hrs
STEM SEALING MACHINE
Start at :
FILE: 217-1-PT-QSM1, REV.0
______hrs
DOC. NO. 217-1-PT-QSM1, DT. 10-02-2012
SHEET 23 OF 35
SECTION – B2 PERFORMANCE TEST COUNT TABULATION SHEET DAY 2 (JANUARY 30, 2012)
ZISHAN ENGINEERS (PVT.) LTD.
GASCO UPGRADE PROJECT - QASSIM
NATIONAL GAS AND INDUSTRIALIZATION COMPANY (GASCO) LPG FILLING PLANTS UPGRADE PROJECT PERFORMANCE TEST QASSIM CIRCUIT-1 COUNT TABULATION SHEET - SECOND DAY 30TH JANUARY 2012
S.NO.
HOURS
ADJ. DUE TO FINAL ADJUSTED 11 SEC. STOP HOURLY HOURLY FOR READ ADJUSTE MANUAL PRODUCTION SMS COUNT D FIGURE AFTER SMS
NOS. OF SOURT OUT CYLINDERS
CYLINDERS COUNT FROM CUC SMS
CHECK SCALE
ET-GD
ET-PT
START
1031
0
0
0
0
0
1
1101
761
5
21
1
0
2
1131
1,612
7
4
3
0
Total (First Hour)
1,612
12
25
4
0
3
1201
2,488
7
12
1
21
4
1231
3,398
2
5
0
48
1,786
9
17
1
69
Total (Second Hour) 6
1301
4,226
1
12
1
116
7
1331
5,069
2
14
2
1
1,671
3
26
3
117
Total (Third Hour)
1,653
10
1,663
1,653
10
1,663
1,744
11
1,755
1,744
11
1,755
1,586
10
1,596
1,586
10
1,596
1,791
11
1,802
8
1401
5,974
5
2
2
0
9
1431
6,843
5
1
2
0
1,774
10
3
4
0
1,791
11
1,802
34
71
12
186
6774
42
6816
PRODUCTION IN FIRST HOUR
=
1,663
Cylinders
PRODUCTION IN SECOND HOUR
=
1,755
Cylinders
PRODUCTION IN THIRD HOUR
=
1,596
Cylinders
PRODUCTION IN FORTH HOUR
=
1,802
Cylinders
TOTAL PRODUCTION IN FOUR HOURS
=
6,816
Cylinders
AVERAGE HOURLY PRODUCTION
=
1,704
Cylinders
Total (Forth Hour)
GRAND TOTAL
FILE: 217-1-PT-QSM1, REV.0
DOC. NO. 217-1-PT-QSM1, DT. 10-02-2012
SHEET 24 OF 35
ZISHAN ENGINEERS (PVT.) LTD.
GASCO UPGRADE PROJECT - QASSIM
PHYSICAL COUNT:
NOS. OF PALLETIZED CYLINDERS HOUR LY
SORT OUT CYLINDERS AT CHECK SCALE, ET-GD AND ET-PT
ADJUSTED HOURLY PRODUCTION
1,599
41
1,640
1,726
27
1,753
1,535
32
1,567
1,803
17
1,820
6,663
117
6,780
6,780
Cylinders
HOURS CUMMULAT IVE HALF H OUR LY 1101
725
725
1131
1,599
874
1201
2450
851
1231
3,325
875
1301
4,035
710
1331
4,860
825
1401
5,775
915
1431
6,663
888
TOTAL
6,663
TOTAL PHYSICAL COUNT
=
TOTAL CYLINDERS IN YARD
=
TOTAL CYLINDERS IN YARD
=
190 PALLETS + 13 CYLINDERS AT PALLETIZER 190 x 35 + 13
SORT OUT CYLINDERS AT CHECK SCALE, ET-GD AND ET-PT
TOTAL PHYSICAL COUNT. =
FILE: 217-1-PT-QSM1, REV.0
6,663 + 117
=
=
6,663
CYLINDERS
117
6,780
DOC. NO. 217-1-PT-QSM1, DT. 10-02-2012
Cylinders
SHEET 25 OF 35
ZISHAN ENGINEERS (PVT.) LTD.
GASCO UPGRADE PROJECT - QASSIM
NATIONAL GAS AND INDUSTRIALIZATION COMPANY (GASCO) LPG FILLING PLANTS UPGRADE PROJECT PERFORMANCE TEST QASSIM CIRCUIT-1 SUMMARIZED RESULTS
DAY - 1 (29th Jan 2012)
DAY - 2 (30th Jan 2012)
PRODUCTION CUC COUNT ADJUSTED *
PHYSICAL COUNT AJDUSTED *
CUC COUNT ADJUSTED *
PHYSICAL COUNT AJDUSTED *
1ST HOUR
1,588
1,574
1,663
1,640
2ND HOUR
1727 **
1739 **
1,755
1,753
3RD HOUR
1,787
1,786
1,596
1,567
4TH HOUR
1,695
1,676
1,802
1,820
6,797
6,775
6,816
6,780
FROM CUC COUNT
=
13,613
Cylinders
PHYSICAL COUNT
=
13,555
Cylinders
CONTRACTUAL REQUIREMENT
=
13,920
Cylinders
TOTAL
SUM OF TWO DAYS PRODUCTION :
* SOURT OUT CYLINDERS FROM CHECK SCALE, ET-GD AND ET-PT ADDED IN THE CUC COUNT AND PHYSICAL COUNT ** PRODUCTION IN 39 MINUTES IN SECOND HOUR AND 21 MINUTES IN LAST HOUR
FILE: 217-1-PT-QSM1, REV.0
DOC. NO. 217-1-PT-QSM1, DT. 10-02-2012
SHEET 26 OF 35
SECTION – B3 SITE OBSERVATIONS – DAY 2 (JANUARY 30, 2012)
ZISHAN ENGINEERS (PVT.) LTD.
GASCO UPGRADE PROJECT - QASSIM
SITE OBSERVATIONS PT DAY 2 DT 30-01-12
1.
It was observed that some cylinders were received during the third half hour without caps after Steam Sealing Machine.
2.
The cap bundles placement was found to be improper on the cap feeding unit tray of the Automatic Cap Applicator and the KC operator had to adjust manually the placement of the bundles. Further, it was observed that while the flapper delivers the bundle of caps to the cap feeding unit automatically the machine stops and is started manually by pushing the start button given on the CUC of the machine after placing a cap inside the cap dispensing bell. Hence due to this reason delivery of caps was improper to the cap feeding unit. Further due to this reason the cap was not blown to the dispensing bell causing the machine repeated stoppages.
3.
Also another kind of machine stoppage was observed to occur repeatedly that cap is not blown to the cap dispensing bell as the bundle of caps on the cap feeding unit requiring a push to be released from down under the air nozzle as it gets engaged under this air nozzle as demonstrated by the KC personnel during the PT. KC is requested to make required adjustments in the machine so that such type of stoppage does not occur in the future.
4.
Due to the above mentioned reasons the Automatic Cap Applicator stopped for about 65 times at different time intervals, during the Performance Test.
5.
An Air nozzle is installed on the outlet conveyor as part of site modification at the upstream of the ET-GD to address the leaked LPG accumulation over the shroud of the cylinders (as of KC), which makes sure that there should not be any false detection at ET/GD because of this LPG accumulation. But in the process, as a result the dust sitting on the cylinder also gets air borne and environment becomes dusty which is a health hazard for operators working in that area. KC should evaluate the size of the Air nozzle and the pressure of the air to be blown.
6.
It has been observed that there was still false sorting of cylinders on ET-GD. KC to elaborate the reasons for this false sorting and present the remedial solution to avoid this false sorting.
7.
Before the PT and during the PT, palletizer operation was disrupted because of locking jacks failed to engage the pallets in time to stop them at the designated position on stand 2, 3, 4, & 5 even the empty cylinder pallet transition from stand 3 to stand 4 was a complete failure and all the pallets moving on the transfer path on these stands gets entangled with each other. KC to look into the matter and bring forward the reason whether this failure is caused by the single event i.e. putting an empty pallet at stand 5 as per KCs contention or a failure in the CUC control sequence. In either case KC is bound to deliver a fail-safe system.
FILE: 217-1-PT-QSM1, REV.0
DOC. NO. 217-1-PT-QSM1, DT. 10-02-2012
SHEET 27 OF 35
ZISHAN ENGINEERS (PVT.) LTD.
GASCO UPGRADE PROJECT - QASSIM
8.
The optical sensors provided at stand 1, 5 & 9 have detection of the fork lift presence problem. To our understanding detection range should be equal to the forklift’s lifting arms length at least. On detection of the forklift at these stands, a designated operation control sequence has to be carried out by the CUC for each stated stands accordingly. KC is required to furnish all the operation sequence of their system that has to be carried out on stands 1, 5 & 9 once the fork lift or any other object comes into detection range at these stands. KC is also required to suggest & adjust a suitable detection range of the optical sensor for the sake of safe operation based on their experience.
9.
On second day of the PT, LPG filling tolerance set on Check Scale was ±200 grams and there were 34 number cylinders sorted out by the Check Scale. Out of these 34, 6 cylinders had weight within tolerance i-e, 27kg ±200 grams, 16 cylinders were underfilled and 12 cylinders were found empty. Out of 12 empty cylinders majority had no atmospheric air inside the cylinders, which shows that there were filling heads at Carousel that might not be accurately engaged with cylinders.
10.
At Carousel outlet cylinders came out with slight jerk. KC placed an operator at the outlet to prevent the cylinders to fall. It might be due to the slight difference in the level of outlet conveyor with respect to the level of filling stands.
11.
Many of the completely filled cylinders at Carousel were took two or more turns as they were not pushed out to outer conveyor after first turn. Similarly during PT many times filling stands were found without cylinders. Details of cylinders with two or more turns at Carousel and the filling stand without cylinders are as under :
HOURS
Filling Stand Number
1031
11
Numbers of Turns / Without Cylinder Without Cylinder
1038
12
Without Cylinder
1039
9
Without Cylinder
1040
11
Without Cylinder
1040
20
Without Cylinder
1041
9
Without Cylinder
1042
KC stopped Carousel outlet for 33 Sec for adjustment on Check Scale
1105
25
Two turns
1107
17
Two turns
1108
15
Two turns
1109
11
Two turns
1110
9
Without Cylinder
1110
20
Without Cylinder
FILE: 217-1-PT-QSM1, REV.0
DOC. NO. 217-1-PT-QSM1, DT. 10-02-2012
SHEET 28 OF 35
ZISHAN ENGINEERS (PVT.) LTD.
GASCO UPGRADE PROJECT - QASSIM
HOURS
Filling Stand Number
1111
24
Numbers of Turns / Without Cylinder Two turns
1112
13
Three turns
1114
24
Two turns
1115
22
Two turns
1122
25
Two turns
1123
KC stopped Carousel outlet for 40 Sec for adjustment on Check Scale
1131
13
Two turns
1134
13
Without Cylinder
1135
19
Two turns
1137
15
Two turns
1139
18
Two turns
1139
14
Two turns
1140
25
Two turns
1141
21
Two turns
1143
22
Two turns
1144
11
Two turns
1144
3
Two turns
1145
12
Two turns
1145
11
Without Cylinder
1146
KC stopped Carousel outlet for 40 Sec for adjustment on Check Scale
1148
13
Without Cylinder
1150
13
Two turns
1155
18
Two turns
1156
14
Two turns
1156
27
Two turns
1157
13
Two turns
1158
13
Two turns
1158
20
Without Cylinder
1158
26
Two turns
1201
7
Two turns
1202
14
Two turns
1203
25
Two turns
1204
21
Two turns
1205
17
Two turns
FILE: 217-1-PT-QSM1, REV.0
DOC. NO. 217-1-PT-QSM1, DT. 10-02-2012
SHEET 29 OF 35
ZISHAN ENGINEERS (PVT.) LTD.
GASCO UPGRADE PROJECT - QASSIM
HOURS
Filling Stand Number
1205
13
Numbers of Turns / Without Cylinder Two turns
1205
26
Two turns
1206
13
Without Cylinder
1206
22
Two turns
1207
28
Two turns
1208
24
Two turns
1210
11
Without Cylinder
1211
20
Two turns
1212
11
Without Cylinder
1212
20
Two turns
1213
13
Two turns
1214
13
Two turns
1214
28
Two turns
1215
13
Two turns
1216
13
Two turns
1217
13
Two turns
1218
9
Without Cylinder
1218
13
Two turns
1218
20
Without Cylinder
1219
13
Two turns
1220
13
Two turns
1224
13
Two turns
1225
21
Two turns
1225
26
Two turns
1225
11
Without Cylinder
1226
21
Without Cylinder
1226
13
Two turns
1228
6
Two turns
1229
KC stopped Carousel outlet for 30 Sec for adjustment on Check Scale
1230
13
Two turns
1234
11
Two turns
1236
26
Two turns
1237
13
Without Cylinder
1238
29
Two turns
FILE: 217-1-PT-QSM1, REV.0
DOC. NO. 217-1-PT-QSM1, DT. 10-02-2012
SHEET 30 OF 35
ZISHAN ENGINEERS (PVT.) LTD.
GASCO UPGRADE PROJECT - QASSIM
HOURS
Filling Stand Number
1239
11
Numbers of Turns / Without Cylinder Without Cylinder
1239
28
Two turns
1240
02
Two turns
1241
25
Two turns
1241
15
Two turns
1242
23
Two turns
1242
KC stopped Carousel outlet for 45 Sec for adjustment on Check Scale
1247
25
Two turns
1248
11
Without Cylinder
1248
23
Two turns
1250
15
Two turns
1251
11
Without Cylinder
1252
26
Two turns
1253
13
Two turns
1254
20
Two turns
1254
29
Two turns
1254
KC stopped Carousel outlet for 30 Sec for adjustment on Check Scale
1256
11
Without Cylinder
1259
27
Two turns
1300
9
Without Cylinder
1304
18
Two turns
1304
26
Two turns
1304
11
Without Cylinder
1306
13
Two turns
1309
13
Two turns
1311
11
Without Cylinder
1312
KC stopped Carousel outlet for 15 Sec for adjustment on Check Scale
1312
9
Without Cylinder
1314
14
Without Cylinder
1316
24
Without Cylinder
1317
12
Without Cylinder
1319
25
Two turns
1320
21
Two turns
1321
19
Two turns
FILE: 217-1-PT-QSM1, REV.0
DOC. NO. 217-1-PT-QSM1, DT. 10-02-2012
SHEET 31 OF 35
ZISHAN ENGINEERS (PVT.) LTD.
GASCO UPGRADE PROJECT - QASSIM
HOURS
Filling Stand Number
1321
9
Numbers of Turns / Without Cylinder Without Cylinder
1322
17
Two turns
1322
11
Without Cylinder
1323
11
Without Cylinder
1324
27
Two turns
1324
11
Without Cylinder
1325
1
Two turns
1327
13
Two turns
1327
26
Two turns
1328
24
Two turns
1329
20
Two turns
1333
26
Two turns
1334
13
Two turns
1335
12
Without Cylinder
1336
13
Two turns
1337
27
Two turns
1338
25
Two turns
1338
12
Without Cylinder
1339
21
Two turns
1339
13
Two turns
1340
13
Two turns
1341
25
Without Cylinder
1341
13
Two turns
1342
13
Two turns
1343
13
Two turns
1344
13
Two turns
1345
13
Two turns
1346
13
Two turns
1347
13
Two turns
1348
13
Two turns
1349
13
Two turns
1350
13
Two turns
1351
13
Without Cylinder
1352
13
Without Cylinder
FILE: 217-1-PT-QSM1, REV.0
DOC. NO. 217-1-PT-QSM1, DT. 10-02-2012
SHEET 32 OF 35
ZISHAN ENGINEERS (PVT.) LTD.
GASCO UPGRADE PROJECT - QASSIM
HOURS
Filling Stand Number
1353
29
Numbers of Turns / Without Cylinder Two turns
1354
12
Two turns
1354
27
Two turns
1355
25
Two turns
1355
11
Two turns
1356
24
Two turns
1357
22
Two turns
1357
12
Two turns
1358
21
Two turns
1358
13
Without Cylinder
1401
11
Without Cylinder
1403
22
Two turns
1403
11
Without Cylinder
1404
14
Two turns
1404
21
Two turns
1404
22
Two turns
1404
5
Two turns
1405
27
Two turns
1405
12
Without Cylinder
1406
25
Two turns
1406
8
Two turns
1407
11
Without Cylinder
1407
13
Without Cylinder
1408
11
Without Cylinder
1409
11
Without Cylinder
1411
29
Two turns
1412
24
Two turns
1413
28
Two turns
1414
28
Two turns
1415
13
Two turns
1415
18
Two turns
1416
23
Two turns
1416
26
Two turns
1416
4
Two turns
FILE: 217-1-PT-QSM1, REV.0
DOC. NO. 217-1-PT-QSM1, DT. 10-02-2012
SHEET 33 OF 35
ZISHAN ENGINEERS (PVT.) LTD.
GASCO UPGRADE PROJECT - QASSIM
HOURS
Filling Stand Number
1416
9
Numbers of Turns / Without Cylinder Two turns
1416
29
Two turns
1416
11
Two turns
1416
23
Two turns
1417
1
Two turns
1417
KC stopped Carousel outlet for 21 Sec for adjustment on Check Scale
1420
13
Without Cylinder
1421
13
Two turns
1421
21
Without Cylinder
1421
24
Without Cylinder
1421
11
Without Cylinder
1424
23
Two turns
1425
13
Without Cylinder
1425
21
Two turns
1427
15
Two turns
1427
28
Two turns
1427
13
Without Cylinder th
th
12.
In the RCC generated plant report for 29 & 30 Jan PT, the ET/GD & ET/PT attributes of cylinders handled, cylinder accepted and cylinder sort out information was a complete th black out. KC to look into the matter, as the same information was witnessed in 24 & th 26 Jan, 2012 trial production run report.
13.
In the following lines day two PT production counts from PMS, CUC & Physical counts are given for comparison: i) SMS CUC Count = 6816 (After Adjustment) ii) Physical Count = 6780 (After Adjustment) iii) PMS Report Count = 6911 – 186 = 6725 (Total including sort outs at adjustment scale – Total sort outs at SMS) iv) Sort out at Adjustment Scale = 34 (Physical Count) v) PMS Report Sort out at Scale = 28 vi) Sort out at ET/GD = 71 (Physical Count) vii) PMS Report Sort out at ET/GD = No Data (Report Attached) viii) Sort out at ET/PT = 12 (Physical Count) ix) PMS Report Sort out at ET/GD = No Data (Report Attached)
FILE: 217-1-PT-QSM1, REV.0
DOC. NO. 217-1-PT-QSM1, DT. 10-02-2012
SHEET 34 OF 35