Pearl GTL Project Shell Project No: HP-3000-QAT Project Document Number: T- 4.234.557
Purchase Order Number:
2MH127
Tag/Item Number(s):
N/A
Unit(s):
ASU
PCWBS:
Z
LINDE ENGINEERING
Contractor Project No: 5887
Project Rev.: O
Page 2 of 17
QATAR SHELL GTL PROJECT (PEARL) C2 AIR SEPARATION UNITS CONSTRUCTION
D
O
11.02.09
Company Comments Incorporated
SK
EO
AG
CCI
C
O
27.01.09
Issued for Company Comments
SK
EO
AG
IFR
B
27.01.09
Issued for Review
SK
EO
AG
IFR
A
12.01.09
Issued for Internal Review Review
SK
EO
AG
IIR
Date
Description
GAMA Rev.
Project Rev
No.
No.
Prepared Checked Approved By By By
Status
ORIGINATOR ORIGINATOR
Document Title:
LINDEGINEERING AG
INSPECTION TEST PLAN FOR INSTALLATION OF MAC/BAC/ST MACHINERY UNIT Document No.
Contractor
Gama Qatar Co. W. L. L.
GAM
ITP
QAC
GTL
046
D
Org.
Doc. Type
Geogr. Area
Seq.
Code
Disc. Code
Rev. No
Project Document Number: T-4.234.557
No
LOC470 Vendor Code
Rev No: O
QSGTL PEARL PROJECT ITP NO: GAM-ITP-QAC-GTL-046 GAM-ITP-QAC-GTL-046
C2 ASU Construction Works
ITP FOR INSTALLATION OF MAC/BAC/ST MACHINERY UNIT S. GAMA QATAR
X. CONTRACTOR QC
C. COMPANY
DATE:
11.02.09-REV. D
A. VENDOR (MAN)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS(Notification WITNESS (Notification Required but Presence not Mandatory) Item
1.0
Activity
Test Frequency
Reference Document
Acceptance Criteria
Responsible Party
Verifying Documents
S
A
X
C
DOCUMENTATION
1.1
Contractor drawings, project specifications, manuals, codes
100%
-
-
TECHINICAL OFFICE
-
H
R
R
1.2
Lifting studies (For Heavy Equipments)
100%
T.4.234.084,T.4.129.859
-
HSSE
-
H
R
R
2.0
EQUIPMENTS
2.1
Receiving inspection (Including nameplate verification) & Open Box Inspection during unpacking
100%
T-4.250.945;T.4.250.927
Packing list DEP 31.29.00.10 DEP 31.10.03.10
STORE INCHARGE
2.2
Storage, preservation and documentation(FSI) documentation(FSI)
100%
T.13.377.360E;T.4.250.932
Approved drawing, DEP 31.29.00.10;DEP 70.10.70.11 T.13.377.454E; Vendor instruction, instruction,
FSI
2.3
Inspection measuring and test equipment calibration
100%
T.4.250.915
-
QCI
3.0
INSTALLATION
3.1
Foundation complete and accepted
T-4.095.567, T-4.250.945
DEP 34.19.20.31; T.13.376.358 DEP 31.29.00.10,
QCI
GAM-QCR-QAC-GTL-080
I
S
I
S
I
R
S
S
Calibration certificates
H
R
R
R
Ref. ITP 023; MC certificates
H
R
R
R
GAM-QCR-QAC-GTL-069
MC documents,
T-4.234-557 REV-O
100%
Page 4 of 17
QSGTL PEARL PROJECT ITP NO: GAM-ITP-QAC-GTL-046 GAM-ITP-QAC-GTL-046
C2 ASU Construction Works
ITP FOR INSTALLATION OF MAC/BAC/ST MACHINERY UNIT S. GAMA QATAR
X. CONTRACTOR QC
C. COMPANY
DATE:
11.02.09-REV. D
A. VENDOR (MAN)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS(Notification WITNESS (Notification Required but Presence not Mandatory) Item
Activity
Reference Document
100%
T-4.095.805, T-4.250.945
Sole plates spindles/wedges or Installation
3.3
Erection of pre alignment of coolers/wash water unit/steel structure of skid/ oil system
100%
T-4.095.567, T-4.250.945,
3.4
Installation/levelling of struts for base frame
100%
T-4.095.567, T-4.250.945, T-4.233.680
3.5
Installation & alignment of skid on steel structure
100%
T-4.095.567, T-4.250.945, T-4.233.680
3.6
Check alignment of gear box (soft foot, coupling, slope etc.)
100%
T-4.095.567, T-4.250.945, T-4.233.680
3.7
Steam Turbine alignment / coupling check
100%
T-4.095.567, T-4.250.945, T-4.233.680
3.8
MAC Alignment turbine
100%
T-4.095.805, T-4.250.945, T-4.233.680
3.9
BAC Alignment to gear box
100%
T-4.095.805, T-4.250.945, T-4.233.680
T-4.234-557 REV-O
steel
steam
Acceptance Criteria
Responsible Party
Approved drawings,
3.2
to
and shims
Test Frequency
T-4.260.824 DEP 31.29.00.10,
QCI
Approved drawings, T-4.260.824 DEP 31.29.00.10,
QCI
Approved drawings, T-4.260.824 DEP 31.29.00.10,
QCI
Approved drawings, T-4.260.824 DEP 31.29.00.10,
QCI
Verifying Documents
GAM-QCR-QAC-GTL-169 Surveyor report GAM-QCR-QAC-GTL-169 Surveyor report GAM-QCR-QAC-GTL-038
GAM-QCR-QAC-GTL-169
S
A
X
C
I
I
S
S
I
I
S
S
H
I
S
S
H
I
I
I
H
I
I
S
Approved drawings, T-4.260.824 DEP 31.29.00.10,
QCI
GAM-QCR-QAC-GTL-170
Approved drawings, T-4.260.824 DEP 31.29.00.10,
QCI
Linde/MAN Report
H
I
I
S
QCI
Linde/MAN Report
H
I
I
S
QCI
Linde/MAN Report
H
I
I
S
Approved drawings, T-4.260.824 DEP 31.29.00.10, Approved drawings, T-4.260.824 DEP 31.29.00.10,
Page 5 of 17
QSGTL PEARL PROJECT ITP NO: GAM-ITP-QAC-GTL-046 GAM-ITP-QAC-GTL-046
C2 ASU Construction Works
ITP FOR INSTALLATION OF MAC/BAC/ST MACHINERY UNIT S. GAMA QATAR
X. CONTRACTOR QC
C. COMPANY
DATE:
11.02.09-REV. D
A. VENDOR (MAN)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS(Notification WITNESS (Notification Required but Presence not Mandatory) Item
Activity
Test Frequency
Reference Document
3.10
Pre alignment of coolers MAC/BAC to machine skid and ACC Condensate Piping to steam turbine
100%
T-4.095.805, T-4.250.945, T-4.233.680
3.11
Oil Unit foundation
100%
T-4.095.451, T-4.209.390, T-4.250.945
Alignment
on
3.12
Alignment of Motor – Pump for oil unit
100%
T-4.250.927, T-4.209.390, T-4.248.567
3.13
Grouting Release for all unit contents
100%
T-4.095.567, T-4.250.945, T-4.233.680
3.14
Recheck grouting
100%
T-4.095.805, T-4.250.945, T-4.233.680
Alignment
after
3.15
All piping installation, installation, alignment, & connection without any objectionable load
3.16
Verification of piping pressure test acceptance – Prior to final alignment
3.17
Erection Damage(Equipments)
T-4.234-557 REV-O
Acceptance Criteria
Responsible Party
Verifying Documents
S
A
X
C
QCI
Linde/MAN Report
H
I
I
S
H
I
I
S
H
I
I
S
H
I
I
S
I
I
I
R
Approved drawings, T-4.260.824 DEP 31.29.00.10, Approved drawings, T-4.285.227 DEP 31.29.00.10,
QCI
GAM-QCR-QAC-GTL-115
Approved drawings, T-4.285.227 DEP 31.29.00.10,
QCI
Linde/MAN Report
QCI
Ref. ITP 024
Approved drawings, T-4.260.824 DEP 31.29.00.10, Approved drawings, T-4.260.824 DEP 31.29.00.10,
QCI
GAM-QCR-QAC-GTL-115
Ref. ITP 033 (T-4.250.918 Rev. A)
Ref. ITP 033 (T-4.250.918 Rev. A)
100%
T.4.251.035
-
QCI
GAM-QCR-QAC-GTL-127
Page 6 of 17
QSGTL PEARL PROJECT ITP NO: GAM-ITP-QAC-GTL-046 GAM-ITP-QAC-GTL-046
C2 ASU Construction Works
ITP FOR INSTALLATION OF MAC/BAC/ST MACHINERY UNIT S. GAMA QATAR
X. CONTRACTOR QC
C. COMPANY
DATE:
11.02.09-REV. D
A. VENDOR (MAN)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS(Notification WITNESS (Notification Required but Presence not Mandatory) Item
Activity
Test Frequency
Reference Document
4.0
FINAL INSPECTION INSPECTION
4.1
Final alignment checks
100%
T-4.095.805, T-4.250.945, T-4.233.680
4.2
FSI Checks preservation)
100%
T-4.095.805, T-4.250.945, T-4.233.680
4.3
MC Inspections
100%
T-4.095.805, T-4.250.945, T-4.233.680
4.4
Installation Completion , signoff quality records and hand over to Linde MC Dept
100%
T-4.250.945
T-4.234-557 REV-O
(cleaning,
Acceptance Criteria
Responsible Party
Approved drawings, T-4.260.824 DEP 31.29.00.10,
QCI
Approved drawings, T-4.260.824 DEP 31.29.00.10
FSI
Verifying Documents
GAM-QCR-QAC-GTL-117
GAM-QCR-QAC-GTL-0 GAM-QCR-QAC-GTL069
S
A
X
C
I
I
S
S
I
I
S
S
Approved drawings, T-4.260.824 DEP 31.29.00.10
QCI
Linde MC Records
I
S
I
S
T.13.377.555G
QCI
All Reports
H
R
R
R
Page 7 of 17
C2 ASU PEARL GTL PROJECT RASLAFFAN INDUSTRIAL CITY STEEL STRUCTURES ELEVATION REPORT
( BASED ON SURVEY REPORT) Subcontract Ref.:
Report No.:
Item Description: Description:
Inspection Date:
Item Location / Area:
Test Code No.:
Subsystem:
ITP No.:
Ref. DWG / Documents: Used Measuring and test equipment ref. (if applicable): INSPECTIONS Column No
Planned Level
Actual Level
Level/Difference
Plumb 0 Degree
ORGANIZATIONS y B d e t p e c c A
THIRD PARTY REP. GAMA REP. LINDE REP. QSGTL OR its PMC REP.
GAM-QCR-QAC-GTL-038 Rev. O
DATE
NAME
90 Degree
SIGNATURE
FORM NO:
STORAGE, PRESERVATION AND NITROGEN PURGING REPORT
SHT:
PROJECT: C2 ASU PEARL GTL PROJECT, RAS LAFFAN INDUSTRIAL CITY
EQUIP. TAG.NO.:
DESCRIPTION:
LOCATION:
MANUFACTURER:
DRG.NO.:
RFI NO:
MONTH ACTIVITY
1 Month
Date Checked Check all internal and accessories storage is acceptable Visual Check : Is there any damage Check for protective covers on all the openings Check all warning labels,like N2 warning plate are existent Actual Pressure level level Required Pressure Level
GAMA SIGN WITH DATE LINDE SIGN WITH DATE QSGTL or its PMC NOTE:
GAM-QCR-QAC-GTL-069 GAM-QCR-QAC-GTL-069 Rev. O
2
3
4
5
6
7
8
9
10
11
12
C2 ASU PEARL GTL PROJECT RAS LAFFAN INDUSTRIAL CITY
EQUIPMENT RECEIPT CHECK SHEET
ITEM No:
PO No:
UNIT No:
MANUFACTURER :
ITEMS TO BE CHECKED
REQ No:
INSPECTOR INITIAL
REMARKS
1 Name Plate 2 Preparation and painting 3 Desiccant installed 4 Moisture present 5 Nozzle flange faces acceptable 6 Temporary nozzle protection acceptable 7 Internals and accessories complete and storage acceptable 8 Purge - pressure: Purge monitoring date: Date of initial inspection:
Name and signature of Inspector:
GAM-QCR-QAC-GTL-080 Rev. O
Pressure
EQUIPMENT LEVELLING & ALIGNMENT REPORT
Report No: Date:
PROJECT: C2 ASU ASU PEARL GTL PROJECT-RAS LAFFAN INDUSTRIAL CITY
Tag No:
Manufacturer:
Drg. No:
Equip. Description No. of reading
Orientation
ORIENTATION : LEVELLING GRADIENT / SLOPE
Elevation
Plumpness
ACCEPTED
Tolerance
Remarks
REJECTED
REQUIRED
ACTUAL
ACC
REJECTED
REQUIRED
ACTUAL
ACC
REJECTED
GAM-QCR-QAC-GTL-115
Rev. O
PAGE 1 OF 2
REMARKS: ……………………………………………………… ……………………………………………. .
……………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………
GAMA
LINDE
QSGTL or its PMC
Name Sign Date
GAM-QCR-QAC-GTL-115
Rev. O
PAGE 2 OF 2
C2 ASU PEARL GTL PROJECT RAS LAFFAN INDUSTRIAL CITY
Q A A T A A R
TURBINE INSTALLATION PROCESS SHEET
Item No:
Report No:
Item Description:
Date:
Drawing No:
Area:
Item No
Description
Signature & Date Gama Linde QSGTL
1.
Foundation complete, Level & Accepted.
2.
Sole plates level
3.
Align base
4.
Align casing
5.
Align rotor
6.
Anchor bolts tight
7. 8.
Piping complete co mplete & connected with no objectionable loads or strains on the flanges Verify pressure test accepted
9.
Coupling face gap checked & acceptable
10.
Final alignment checked
11.
Coupling set screws tight
12. 13. 14.
Accessories Installed & Ready for service (i.e,Vents,Drains,strainers,etc) Auxiliary System Complete(i.e. lube system, Water cooling etc) Lubrication system flushed & recharged with appropriate lubricant
15.
Turbine rolls freely, By hand
16.
Governor Mechanism: Linkages checked Manual Trip Level Free
17. Relief valves checked & installed 18. Expansion bellows for condensing turbines installed properly Remarks:
The Installation of the above compressor has been satisfactorily completed in accordance with the Drawings & Specifications ORGANIZATIONS GAMA QATAR REP
LINDE REP QSGTL REP GAM-QCR-QAC-GTL-117 Rev. O
DATE
NAME
SIGNATURE
REPORT NO.:
SITE INSPECTION REPORT PROJECT:
DATE:
C2 ASU PEARL GTL PROJECT –RAS LAFFAN INDUSTRIAL CITY
Originator
Date of observation:
Location / Area:
Unit No :
Discipline:
SYSTEM NUMBER:
Drawing / Specification Numbers
Description of Discrepancy/Observation (Be specific, events, time, date, location, etc :)
Corrective Action:
Originator: Name: _____________________________Signat ure: _____________________Date: ________________ NCR Required
YES
NO
(Circle one)
CTQ to Contractor Required
YES
NO
(Circle one)
Remarks if any:
Site Engineer:
Name:
______________________ _ Signature: ________________ Date: ______________
QA/QC Manager: Name:
_________________________ Signature: _______________ Date: ______________
Discrepancy Corrected/Remarks:
GAMA Representative:
Name: ____________________
Close-out of Corrective Action - Remarks:
Site Engineer:
Name:
Signature:
______________ Date: ________________
NCR No.: ___________________
___________________
Signature: __________________ Date: ___________
DISTRIBUTION (Original QA/QC file)
QA/QC Manager
Site Manager
Site Engineer
Project Manager
Construction Manager
Originator
GAM-QCR-QAC-GTL-127 Rev. O
CTQ No: ______________
C2 ASU PEARL GTL PROJECT RAS LAFFAN INDUSTRIAL CITY
Q A A T A A R
MAC/BAC/ST MACHINERY UNIT INSTALLATION PROCESS SHEET
Item/Tag No:
Report No:
Item Description:
Date:
Drawing No:
Area:
System No:
Subsystem No:
Item No
Description
Signature & Date Gama Linde QSGTL
1.
Foundation complete, Level & Accepted.
2.
Sole plates and spindles/wedges or shims installation accepted
3. 4.
Erection of pre alignment of coolers/wash water unit/steel structure of skid/oil system Skid alignment accepted
5.
Alignment of all equipment accepted
6. 7.
Piping complete & connected with no objectionable loads or strains on the flanges Verify pressure test accepted
8.
Coupling Installation (face gap checked & acceptable)
9.
Final alignment checked
10. 11.
Accessories Installed & Ready for service (i.e. Vents, Drains, strainers, etc) Auxiliary System Complete(i.e. lube oil system, Water cooling etc)
12. 13.
Turbine rolls freely, By hand Governor Mechanism
13.1
Linkages checked
13.2
Manual Trip Level Free
14.
Expansion bellows for condensing turbines installed properly
Remarks:
The Installation of the above Machinery Unit has been satisfactorily completed in accordance with the Drawings & Specifications ORGANIZATIONS GAMA QATAR REP
LINDE REP QSGTL REP GAM-QCR-QAC-GTL-169 Rev. O
DATE
NAME
SIGNATURE
Report No:
GEAR BOX LEVELLING & ALIGNMENT REPORT
Date: System No:
PROJECT: C2 ASU ASU PEARL GTL PROJECT-RAS LAFFAN INDUSTRIAL CITY
Tag No:
Manufacturer:
Drg. No:
Equip. Description: No. of reading
Orientation
Elevation
Plumpness
Tolerance
SOFT FOOT :
ACCEPTED
REJECTED
ORIENTATION :
ACCEPTED
REJECTED
LEVELLING GRADIENT / SLOPE
Remarks
REQUIRED
ACTUAL
ACC
REJECTED
REQUIRED
ACTUAL
ACC
REJECTED
GAM-QCR-QAC-GTL-170
Rev. O
PAGE 1 OF 2
REMARKS: ……………………………………………………… ……………………………………………. .
……………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………
GAMA
LINDE
QSGTL or its PMC
Name Sign Date
GAM-QCR-QAC-GTL-170
Rev. O
PAGE 2 OF 2