SUPPLIER/VENDOR DOCUMENTATION Purchase Order Number:
2MH127
Equipment Description:
N/A
Vendor/Supplier Name:
GAMA QATAR CO. W. L. L.
Document Title:
INSPECTION TEST PLAN FOR INSTALLATION OF HVAC UNIT
Vendor/Supplier Doc Number:
GAM-ITP-QAC-GTL-048
Tag/Item Number(s):
SEE NEXT PAGE
Unit: SEE NEXT PAGE
Vendor/Supplier Code:
LOC470
Vendor/Supplier Revision: C
PCWBS: SEE NEXT PAGE Vendor/Supplier Checked By
Vendor/Supplier Prepared By
Vendor/Supplier Approved By
Initials / Signature
Initials / Signature
SK
Initials / Signature
Vend/Supp Revision Date
AG
08.02.2009
EO
Status of Submission (tick applicable box before submission) For Review/Info: X
Final:
Certified:
As-Built:
Purchaser signature below does not indicate responsibility or liability for accuracy or completeness of this document, nor does it alter any contractual terms or conditions or relieve the Supplier/Vendor of his contractual obligations.
PURCHASER AREA BELOW Contractor Contract Number:
PI – 092
Contractor Name:
Contractor Doc. No: GAMAC-0100-M-PC 1334
Review Code and Status Code 1
No Comments. ACCEPTED. Work May Proceed. Proceed .
Code 2
Comments As Noted. Incorporate Comments, Revise and Resubmit. Work May Proceed. Proceed .
Code 3
REJECTED. Incorporate Comments, Revise and Resubmit. Work May NOT Proceed. Proceed .
Try Scribd FREE for 30 days to access over 125 million titles without ads or interruptions! Start Free Trial Cancel Anytime.
Trusted by over 1 million members
Try Scribd FREE for 30 days to access over 125 million titles without ads or interruptions! Start Free Trial Cancel Anytime.
QATAR SHELL GTL PROJECT (PEARL) C2 AIR SEPARATION UNITS CONSTRUCTION
C
O
08.02.09
Issued for Company Comments
SK
EO
AG
ICC
B
08.02.09
Issued for Review
SK
EO
AG
IFR
A
07.02.09
Issued for Internal Review
SK
EO
AG
IIR
Date
Description
GAMA Rev.
Project Rev
No.
No.
Prepared Checked Approved By By By
Status
ORIGINATOR ORIGINATOR
Document Title:
LINDEGINEERING AG
INSPECTION TEST PLAN FOR INSTALLATION OF HVAC UNIT Document No.
Contractor
Gama Qatar Co. W. L. L.
GAM
ITP
QAC
GTL
048
C
Org.
Doc. Type
Geogr. Area
Seq.
Code
Disc. Code
Rev. No
Project Document Number: T-4.318.613
No
LOC470 Vendor Code
Rev No: O
Trusted by over 1 million members
Try Scribd FREE for 30 days to access over 125 million titles without ads or interruptions! Start Free Trial Cancel Anytime.
Trusted by over 1 million members
Try Scribd FREE for 30 days to access over 125 million titles without ads or interruptions! Start Free Trial Cancel Anytime.
QSGTL PEARL PROJECT
Document No.: GAM-ITP-QAC-GTL-048
C2 ASU Construction Works
ITP FOR INSTALLATION OF HVAC UNIT S. GAMA QATAR
X. CONTRACTOR QC
DATE: 08.02.09 REV. C
C. COMPANY
A. THIRD PARTY (TPI)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS(Notification WITNESS (Notification Required but Presence not Mandatory) Item
Activity
Test Frequency
Acceptance Criteria
Respon sible Party
Verifying Documents
S
X
C
RFC
QCI
RFC
H
R
R
T.4.250.915
DEP 30.10.60.18; T.13.377.433E; T.13.377.441; T.13.377.437E
QCI
Calibration certificate
H
I/R
R
Reference Document
1.0
DOCUMENTATION
1.1
Contractor drawings
100%
1.2
Verify calibration of inspection, measuring and test equipment
100%
2.0
MATERIALS
2.1
Receiving inspection / open box Verification of Material
100%
T.4.250.928
T.13.376.797E; T.13.377.438E
QCI
GAM-QCR-QAC-GTL-079
I
R
R
2.2
Storage & Segregation of Material
100%
T.4.250.928; T.4.250.932
T.13.377.454E; T.13.377.438E
QCI
Visual
I
I
R
3.0
Duct Installation
3.1
Ready for duct installation
100%
T-4.234.564
DEP 31.76.10; DEP 31.76.11
QCI
Linde MC Certificates
I
R
R
3.2
Initial Installation of supports/hangers
100%
T-4.234.564
DEP 31.76.10; DEP 31.76.11
QCI
GAM-QCR-QAC-GTL-172 GAM-QCR-QAC-GTL-172
I
I
S
3.3
Visual inspection of deformation/damage
100%
T-4.234.564
DEP 31.76.10; DEP 31.76.11
QCI
GAM-QCR-QAC-GTL-172 GAM-QCR-QAC-GTL-172
I
I
S
3.4
Installation of Dampers, louvers, sand traps and grills
100%
T-4.234.564
DEP 31.76.10; DEP 31.76.11
QCI
GAM-QCR-QAC-GTL-172 GAM-QCR-QAC-GTL-172
I
I
S
T-4.318 613 Rev.O
T.4.234.542; T.4.250.935; T.4.250.936
Page 4
A
Trusted by over 1 million members
Try Scribd FREE for 30 days to access over 125 million titles without ads or interruptions! Start Free Trial Cancel Anytime.
QSGTL PEARL PROJECT
Document No.: GAM-ITP-QAC-GTL-048
C2 ASU Construction Works
ITP FOR INSTALLATION OF HVAC UNIT S. GAMA QATAR
X. CONTRACTOR QC
DATE: 08.02.09 REV. A
C. COMPANY
A. THIRD PARTY (TPI)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS(Notification WITNESS (Notification Required but Presence not Mandatory) Item
Activity
3.5
Duct work erected as per the drawings & procedure (check gaskets, nipple, silicon joints)
3.6
All ducting, supports, supports, hangers, ancillary equipments and insulated cladding (if applicable)
4.0
Test Frequency
Reference Document
Acceptance Criteria
Respon sible Party
Verifying Documents
S
X
C
100%
T-4.234.564
DEP 31.76.10; DEP 31.76.11
QCI
GAM-QCR-QAC-GTL-172 GAM-QCR-QAC-GTL-172
I
I
S
T-4.234.564
DEP 31.76.10; DEP 31.76.11
QCI
GAM-QCR-QAC-GTL-172 GAM-QCR-QAC-GTL-172
I
I
S
T-4.234.564
DEP 31.76.10; DEP 31.76.11
QCI
GAM-QCR-QAC-GTL-127 GAM-QCR-QAC-GTL-127
I
S
S
S
I
R
R
R
R
100%
A
FINAL INSPECTION
4.1
Erection damage (if any)
4.2
MC Inspection
100%
T-4.234.564
DEP 31.76.10; DEP 31.76.11
QCI
MC Inspection Reports
I
4.3
Handover of Quality Documents
100%
Quality Documents
T.13.377.555G
QCI
QC Inspection Reports
R
T-4.318.613 Rev.O
100%
Page 5