Pearl GTL Project Shell Project No: HP-3000-QAT Project Document Number: T- 4.250.923
Purchase Order Number:
2MH127
Tag/Item Number(s):
N/A
Unit(s):
ASU
PCWBS:
Z
LINDE ENGINEERING
Contractor Project No: 5887
Project Rev.: A
Page 2 of 27
QATAR SHELL GTL PROJECT (PEARL) C2 AIR SEPARATION UNITS CONSTRUCTION
D
A
14.09.08
Ready for Construction
SK
EO
AG
RFC
C
O
06.03.08
Issued for Company comments
BR
UA
ZG
ICC
B
25.01.08
Issued for Review
BR
UA
ZG
IFR
A
02.01.08
Issued for Internal Review Review
BR
UA
ZG
IIR
Date
Description
GAMA Rev.
Project Rev
No.
No.
Prepared Checked Approved By By By
Status
ORIGINATOR ORIGINATOR
Document Title:
INSPECTION TEST PLAN FOR COMPRESSOR LINDEGINEERING AG Document No.
Contractor
Gama Qatar Co. W. L. L.
GAM
ITP
QAC
GTL
036
D
Org.
Doc. Type
Geogr. Area
Seq.
Code
Disc. Code
Rev. No
Project Document Number: T-4.250.923
No
LOC470 Vendor Code
Rev No: A
QSGTL PEARL PROJECT ITP NO: NO: GAM-ITP-QAC-GTL-036
C2 ASU Construction Works ITP FOR INSTALLATION OF COMPRESSOR (FSI) S. GAMA QATAR
X. CONTRACTOR QC
DATE: 17.09.08-REV. D
C. COMPANY
A. VENDOR (MAN)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS(Notification WITNESS (Notification Required but Presence not Mandatory) Item
1.0
Activity
Test Frequency
Reference Document
Acceptance Criteria
Responsible Party
Verifying Documents
S
A
X
C
DOCUMENTATION
1.1
Contractor drawings, project specifications, manuals, codes
100%
-
-
TECHINICAL OFFICE
-
H
R
R
1.2
Lifting studies (For Heavy Equipments)
100%
T.4.234.084
-
HSSE
-
H
R
R
2.0
EQUIPMENT
2.1
Equipment identification and name plate verification
100%
T-4.250.945
Approved drawing, DEP 31.10.03.10; DEP 31.29.00.10
STORE INCHARGE
GAM-QCR-QAC-GTL-080
I
S
S
2.2
Receiving inspection
100%
T-4.250.945;T.4.250. T-4.250.945;T.4.250.927 927
Approved drawing, DEP DEP 31.29.00.10
STORE INCHARGE
GAM-QCR-QAC-GTL-080
I
I
S
2.3
Storage, preservation and documentation(FSI) documentation(FSI)
100%
T.13.377.360E;T.4.250.932
Approved drawing, DEP 31.29.00.10;DEP 70.10.70.11 T.13.377.454E; Vendor instruction,
QCI
GAM-QCR-QAC-GTL-069
I
R
S
S
2.5
Inspection measuring and test equipment calibration
100%
T.4.250.915
-
QCI
Calibration certificate
H
R
R
R
3.0
INSTALLATION
T-4.250-923 REV-A
Page 4 of 27
QSGTL PEARL PROJECT ITP NO: NO: GAM-ITP-QAC-GTL-036
C2 ASU Construction Works ITP FOR INSTALLATION OF COMPRESSOR (FSI) S. GAMA QATAR
X. CONTRACTOR QC
DATE: 17.09.08-REV. D
C. COMPANY
A. VENDOR (MAN)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS(Notification WITNESS (Notification Required but Presence not Mandatory) Item
Activity
Test Frequency
Reference Document
Acceptance Criteria
Responsible Party
Verifying Documents
S
A
X
C
QCI
GAM-QCR-QAC-GTL-114; GAM-QCR-QAC-GTL-113
H
I
I
I
I
S
I
I
Approved drawing, 3.1
Foundation complete and accepted
100%
T-4.250.945
3.2
Foundation chipping to sound metal
100%
T-4.250.945
3.3
Anchor bolts control & pocket cleaning
100%
T-4.250.945
3.4
Shims Installation
100%
T-4.250.945
3.5
Levelling, orientation & alignment (driven & driver set) (FSI)
100%
T-4.250.945; T.13.377.360E
3.6
Settlement monitoring
100%
T-4.250.945
100%
T-4.250.945
100%
T.4.250.945; T.13.377.360E
3.7
3.8
Checking and recording of “soft f oo oot”
Bolts Tightening(FSI) Tightening(FSI)
T-4.250-923 REV-A
DEP 34.19.20.31; T.13.376.358 DEP 31.29.00.10, Approved drawing, DEP 34.19.20.31; T.13.376.358
QCI
DEP 31.29.00.10, Approved drawing, DEP DEP 34.19.20.31;T.13.376.358 DEP 31.29.00.10, Approved drawing, DEP 31.29.00.10, Approved drawing, DEP 31.29.00.10, Vendor specification Approved drawing, DEP 31.29.00.10,
GAM-QCR-QAC-GTL-114; GAM-QCR-QAC-GTL-113
QCI
GAM-QCR-QAC-GTL-114; GAM-QCR-QAC-GTL-113
I
S
I
I
QCI
GAM-QCR-QAC-GTL-114
I
S
I
I
QCI
GAM-QCR-QAC-GTL-114; GAM-QCR-QAC-GTL-115
H
I
I
I
I
R
S
S
I
I
S
S
H
I
I
S
QCI
GAM-QCR-QAC-GTL-116
Vendor specifications, Approved drawings, DEP 31.29.00.10-sec 3.9.4.7 Approved drawing, DEP DEP 31.29.00.10, Vendor specification,
QCI
QCI
GAM-QCR-QAC-GTL-114 GAM-QCR-QAC-GTL-114; GAM-QCR-QAC-GTL-041
Page 5 of 27
QSGTL PEARL PROJECT ITP NO: NO: GAM-ITP-QAC-GTL-036
C2 ASU Construction Works ITP FOR INSTALLATION OF COMPRESSOR (FSI) S. GAMA QATAR
X. CONTRACTOR QC
DATE: 17.09.08-REV. D
C. COMPANY
A. VENDOR (MAN)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS(Notification WITNESS (Notification Required but Presence not Mandatory) Test Frequency
Reference Document
Acceptance Criteria
Responsible Party
Verifying Documents
S
A
X
C
Grouting
100%
T-4.234.545
DEP34.19.20.31; T.13.376.358;Manufactures Instruction;
QCI
GAM-QCR-QAC-GTL-025
I
I
I
I
Jack screw removal
100%
T-4.250.945
QCI
GAM-QCR-QAC-GTL-114
I
S
S
S
QCI
GAM-QCR-QAC-GTL-104
I
S
I
S
Item
3.9
Activity
Vendor specifications, 3.10
Approved drawings DEP 31.29.00.10, Approved drawing,
3.11
Temporary earthing
100%
T-4.250.945
3.12
Anchor bolts Tightening after grouting(FSI) grouting(FSI)
100%
T.4.250.945; T.13.377.360E
Approved drawing, DEP DEP 31.29.00.10,
QCI
GAM-QCR-QAC-GTL-041
H
I
I
S
3.13
Flange parallelism (FSI) parallelism (FSI)
100%
T-4.250.936 T.13.377.360E
Approved drawing,;DEP 31.29.00.10;DEP 31.38.01.11;T.13.376.815E
QCI
GAM-QCR-QAC-GTL-114; GAM-QCR-QAC-GTL-058
H
I
I
I
100%
T-4.250.936
QCI
GAM-QCR-QAC-GTL-114
H
I
S
S
QCI
GAM-QCR-QAC-GTL-114; GAM-QCR-QAC-GTL-115
H
I
I
I
3.14
All piping installation, installation, alignment, & connection without any objectionable load
DEP 31.29.00.10,
Approved drawing, DEP 31.29.00.10, DEP 31.38.01.11;T.13.376.815E Approved drawing,
3.15
Cold alignment levelling rechecking (FSI)
100%
T-4.250.936; T.13.377.360E
DEP 31.29.00.10, DEP 61.10.08.11; T.13.377.455E Vendor specification
T-4.250-923 REV-A
Page 6 of 27
QSGTL PEARL PROJECT ITP NO: NO: GAM-ITP-QAC-GTL-036
C2 ASU Construction Works ITP FOR INSTALLATION OF COMPRESSOR (FSI) S. GAMA QATAR
X. CONTRACTOR QC
DATE: 17.09.08-REV. D
C. COMPANY
A. VENDOR (MAN)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS(Notification WITNESS (Notification Required but Presence not Mandatory) Item
3.16
Activity
Coupling Installed Properly
Test Frequency
Reference Document
Acceptance Criteria
Responsible Party
T-4.250.936
Approved drawing, DEP DEP 31.29.00.10; DEP 31.38.01.11;T.13.376.815E; DEP 31.29.00.36
QCI
T-4.250.945 T.13.377.360E
DEP 31.29.00.10, DEP 61.10.08.11; T.13.377.455E
100%
T-4.250.930; T.13.377.360E
DEP 31.29.00.10, DEP 61.10.08.11; T.13.377.455E;DEP 70.10.80.11 Vendor specification
100%
T-4.250.936
100%
T.4.251.035
-
Approved drawings, DEP DEP 31.29.00.10
100%
Verifying Documents
GAM-QCR-QAC-GTL-114
S
A
X
C
I
S
I
S
Approved drawing, 3.17
Mechanical seal/Packing installation check(FSI) check(FSI)
100%
QCI
GAM-QCR-QAC-GTL-114
I
I
I
I
QCI
GAM-QCR-QAC-GTL-114; GAM-QCR-QAC-GTL-070
H
H
I
I
QCI
GAM-QCR-QAC-GTL-114
I
S
I
S
QCI
GAM-QCR-QAC-GTL-127 GAM-QCR-QAC-GTL-127
I
I
I
R
QCI
GAM-QCR-QAC-GTL-115
H
I
I
I
QCI
GAM-QCR-QAC-GTL-114
I
I
I
S
Vendor specification
3.18
3.19
3.20
Cleaning, flushing and oil filling (FSI)
Temporary suction strainers Installation check Erection Damage(Equipments)
4.0
FINAL INSPECTION INSPECTION
4.1
Final alignment(FSI) alignment(FSI)
100%
T-4.250.945 T.13.377.360E
4.2
Checking and recording of distance between shaft ends and/or between hubs
100%
T-4.250.945
Approved drawing, DEP 31.29.00.10,
Vendor specifications,
T-4.250-923 REV-A
Approved drawings, DEP DEP 31.29.00.10 -SEC 4.20.9
Page 7 of 27
QSGTL PEARL PROJECT ITP NO: NO: GAM-ITP-QAC-GTL-036
C2 ASU Construction Works ITP FOR INSTALLATION OF COMPRESSOR (FSI) S. GAMA QATAR
X. CONTRACTOR QC
DATE: 17.09.08-REV. D
C. COMPANY
A. VENDOR (MAN)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS(Notification WITNESS (Notification Required but Presence not Mandatory) Item
Activity
Test Frequency
Reference Document
Acceptance Criteria
T.13.377.454E Approved drawings,DEP 31.29.00.10
Responsible Party
Verifying Documents
S
A
X
C
QCI
GAM-QCR-QAC-GTL-114
I
S
I
S
QCI
GAM-QCR-QAC-GTL-114; GAM-QCR-QAC-GTL-070
H
H
I
I
QCI
GAM-QCR-QAC-GTL-114
I
I
I
S
QCI
GAM-QCR-QAC-GTL-065
H
W
H
W
DEP 61.10.08.11; 4.3
Shaft turning freely by hand
100%
T-4.250.945
4.4
Cleanliness check for equipment and associated system (FSI)
100%
T-4.250.930 T.13.377.360E
4.5
Verification of auxiliary system completion
100%
T-4.250.945
Vendor specifications, Approved drawings, DEP 31.29.00.10
4.6
Verification of piping pressure test acceptance – Prior to final alignment
100%
T-4.250.908
DEP 31.40.40.38
Vendor specifications DEP 61.10.08.11; T.13.377.455E; DEP 31.29.00.10DEP 70.10.80.11,
Vendor specifications 4.7
Installation of accessories & coupling guard
100%
T-4.250.945
DEP 61.10.08.11; T.13.377.454E;Approved drawings, DEP 31.29.00.10
QCI
GAM-QCR-QAC-GTL-114
I
S
I
S
4.8
General Punch List (Clearing)
100%
T-4.250.945
-
QCI
GAM-QCR-QAC-GTL-128 GAM-QCR-QAC-GTL-128
H
H
H
R
4.9
Equipment Box up
100%
T-4.250.945
-
QCI
GAM-QCR-QAC-GTL-133
H
I
H
S
Installation Completion and sign-off quality records
100%
T-4.250.945
T.13.377.555G
QCI
All Reports
H
R
H
R
4.10
T-4.250-923 REV-A
Page 8 of 27
C2-ASU PROJECT GAMA QATAR GROUT POUR CARD(PRE/POST POUR)
Form No: GAM-QCR-QAC-GTL-025
Inspection Gr.:
ITP No.:
Laboratory:
Record No:
Date:
TAG NO.: DESCRIPTION: TYPE OF GROUT:
LOCATION: DRAWING: QUANTITY OF GROUT: GAMA/T – Const.
Item No.
TYPE OF ACTIVITY
1.0
Setting Out
2.0
Concrete Surface Preparation
3.0
Equipment / Surface Alignment
4.0
Formworks
5.0
Isolation Joint
6.0
Metal Surface Preparation
7.0
Mixing / Placing / Finishing of Grout (1)
8.0
Curing of Grout (1)
9.0
Removal of Shims
10.0
Mixing / Placing / Finishing of Grout (2)
11.0
Curing of Grout (2)
12.0
Sealant to Isolation Joint
13.0
Final Inspection
Signature
Date
GAMA/T - QC Signature
Date
CONTRACTOR CONTRACTOR Signature
Date
Remarks: Full Name/Signature/Date GAMA QATAR
CONTRACTOR
COMPANY
COMPANY(*) Signature
Date
REMARKS
C2 ASU PEARL GTL PROJECT RASLA FFAN INDUSTRIAL INDUSTRIAL CITY
BOLT TIGHTENING INSPECTION REPORT
Subcontract Ref.:
Report No.:
Item Description:
Inspection Date:
Item Location / Area:
Test Code No.:
Subsystem:
ITP No.:
Ref. DWG / Docs: Used Measuring and test equipment ref. (if applicable): INSPECTIONS
Item No/Spool No
Mark No./Joint No
ORGANIZATIONS y B d e t p e c c A
THIRD PARTY REP. GAMA REP. LINDE REP. QSGTL OR its PMC REP.
GAM-QCR-QAC-GTL-041
Bolting Grade
DATE
Size
NAME
Bolt Tightening (Torque Value)
Inspector’s Signature
SIGNATURE
C2 ASU PEARL GTL PROJECT RASLA FFAN INDUSTRIAL INDUSTRIAL CITY
FLANGE ALIGNMENT INSPECTION REPORT
Subcontract Ref.:
Report No.:
Item Description:
Inspection Date:
Item Location / Area:
Test Code No.:
Subsystem:
ITP No.:
Ref. DWG / Docs: Used Measuring and test equipment ref. (if applicable): INSPECTIONS
Item No/Spool No
Mark No./Joint No
ORGANIZATIONS y B d e t p e c c A
THIRD PARTY REP. GAMA REP. LINDE REP. QSGTL OR its PMC REP.
GAM-QCR-QAC-GTL-058
Face Distance
DATE
Face parallelism
NAME
Centreline offset
Inspector’s Inspector ’s Signature
SIGNATURE
Q A A T T A A R
C2 ASU PEARL PEARL GTL PROJECT PROJECT RAS LAFFAN INDUSTR INDUSTRIAL IAL CITY
Company
Project No:
Project Title:
Location
Piping Test No:
PIPING FIELD Priority System No:
TEST REPORT S/C Prepared By:
Test Media:
Name:
Signature
Description Of Test
Date:
LINDE Acceptance By: Name:
Reference Flow Sheets (List All applicable): Signature
Line Number
Line Size
Date: Drawing or Isometric Number
Rev (At Time of Test)
Fr o m
To
Paint Code
Insul. Code
Equipment Tested Trough:
WELDING INSPECTION RELEASE, READY FOR TEST (All Welding and NDT is complete and per specification and piping is ready for test) GAMA WELDING Inspector: Name
Signature:
Date:
GAM-QCR-QAC-GTL-065
GAMA Inspector: Name
Signature:
LINDE Field Signature:
Date::
QSGTL or its PMC Inspector: Name
supports, valves and components components in place except for items nece Test Witnessed By
LINDE Welding Inspector: Name
Lines/ piping as tabulated above have been tested and found to
Engineer: Name
Signature:
QSGTL or its PMC Signature:
Date::
Inspector: Name
Signature
Piping Test No:
PIPING PIPING FIELD FIELD TEST TEST REPORT REPORT Descrip Descr ipti ti on of Test Test Line Number
GAM-QCR-QAC-GTL-065
Line Size
Drawing or Isometric Number
(Continuation Sheet)
Rev (At Time of Test)
Fr o m
To
Paint Code
Insul. Code
FORM NO:
STORAGE, PRESERVATION AND NITROGEN PURGING REPORT
SHT:
PROJECT: C2 ASU PEARL GTL PROJECT, RAS LAFFAN INDUSTRIAL CITY
EQUIP. TAG.NO.:
DESCRIPTION:
LOCATION:
MANUFACTURER:
DRG.NO.:
RFI NO:
MONTH ACTIVITY
1 Month
Date Checked Check all internal and accessories storage is acceptable Visual Check : Is there any damage Check for protective covers on all the openings Check all warning labels,like N2 warning plate are existent Check Purge – Pressure level If Re-purge is required, indicate pressure level
GAMA SIGN WITH DATE LINDE SIGN WITH DATE DATE QSGTL or its PMC NOTE:
GAM-QCR-QAC-GTL-069
2
3
4
5
6
7
8
9
10
11
12
C2 ASU PEARL GTL PROJECT RAS LAFFAN INDUSTRIAL CITY
Q A A
CLEANLINESS CLEA NLINESS ACCEPTENCE REPORT REPORT
A A R
Sub Contract Ref:
Item Location Area:
Isometric No:
Item Description:
sub system:
Form No:
t e e h s
Cleanliness class
Spool
Cleaning Method
GAM-QCR-QAC-GTL-070
Inspection method
In s p ec t i o n Res u l t
Pre Fabrication
Er ec t i o n
Report No: Inspection Date GA MA QA TA R Si g n at u r e
Dat e
L INDE Si g n at u r e
QSGTL o r i t s PMC Dat e
Si g n at u r e
Dat e
C2 ASU PEARL GTL PROJECT RAS LAFFAN INDUSTRIAL CITY
Q A A T T A A R
PERIODIC PREVENTIVE MAINTENANCE CHECK
Subcontract Ref.:
Report No.
Item Description:
Inspection Date:
Item Location / Area:
Vendor IMOI Ref:
Subsystem:
Equipt.Tag No
Ref. DWG / Documents: Used Measuring and test equipment ref. (if applicable):
Date Date of Inspection
PRESERVATION REQUIREMENTS (ROTATIC EQUIPMENT) EQUIPMENT) 1.General Inspection-Weather Protection/Painting Protection/Painting
2. All openings sealed including Motor junction Box. 3. All Mechanical surfaces protected against rust. 4.Check Nitrogen Pressure 5.Anchor bolts/shims covered with grease 6.Rotate all shafts,pulleys,lubricators by 21/4 turns
7.Check oil levels of-bearing housing, gear/crank casing, tanks 8.Check for water at drain points 9.Flange faces-protection denso tape & dust blinds in place
ORGANIZATIONS y THIRD PARTY REP. B d e GAMA REP. t p e c LINDE REP. c A
QSGTL REP.
GAM-QCR-QAC-GTL-073
DATE
NAME
SIGNATURE
C2 ASU PEARL GTL PROJECT RAS LA FFAN INDUSTRIAL INDUSTRIAL CITY
EQUIPMENT RECEIPT CHECK SHEET
ITEM No:
PO No:
UNIT No:
MANUFACTURER :
ITEMS TO BE CHECKED
REQ No:
INSPECTOR INITIAL
REMARKS
1 Name Plate 2 Preparation and painting 3 Desiccant installed 4 Moisture present 5 Nozzle flange faces acceptable 6 Temporary nozzle protection acceptable 7 Internals and accessories complete and storage acceptable 8 Purge - pressure: Purge monitoring date: Date of initial inspection:
Name and signature of Inspector:
GAM-QCR-QAC-GTL-080
Pressure
C2 ASU PEARL GTL PROJECT RAS LAFFAN INDUSTRIAL CITY
EARTHING INSPECTION TEST REPORT
Test No.: Client: Location: Description:
System: Project: Relevant Drawings & Specifications: Location:
Inspection - Earthing Installation Item no
Description
1
Installed in accordance with relevant drawings and specifications
2
Earth terminal mechanical protection correct
3
Earth terminal supported correctly
4
Neutral earthing resistor resistive resistive value at ___________ oC:
5
Neutral earthing resistor insulation resistance to earth:
6
Earth boss correctly fitted
7
Continuity
Accept
Reject Reject
N/A N/A
Accept
Reject Reject
N/A N/A
Inspection – After concrete Item no
Descripti Descripti on
1
Location & Elevation
2
Proper projection
3
Free Movement of Threads
4
Resistivity
5
Continuity
Remarks:
GAMA QATAR
Name: Signature: Date: GAM-QCR-QAC-GTL-104
LINDE
QSGTL or its PMC
Report No:
FOUNDATION INSPECTION REPORT
Date: PROJECT:
C2 ASU PEARL GTL PROJECT-RAS LAFFAN INDUSTRIAL INDUSTRIAL CITY
Tag No:
Drg. No:
Area:
Unit:
ELEVATION
0
Plot Plan: 90
180
°
°
270
°
°
REQUIRED ACTUAL DEVIATION TOLERANCE REMARKS
ORIENTATION
ACCEPTED
REJECTED REQUIRED
POCKET CLEANING
ACTUAL
DEVIATION
ACCEPTED
TOLERANCE
REJECTED
REMARKS
NO. OF ANCHOR BOLTS ANCHOR BOLT DIA ANCHOR BOLT LENGTH FOUNDATION POCKET POCKET DEPTH FOUNDATION CHIPPING
REQUIRED
NOT REQUIRED
IF REQUIRED THICKNESS
NOTE:
THE ABOVE MENTIONED FOUNDATION IS ACCEPTED AND RELEASED FOR ERECTION ACTIVITIES
GAMA Name Sign Date GAM-QCR-QAC-GTL-113
LINDE
QSGTL QSGTL or it s PMC
C2 ASU PEARL GTL PROJECT RAS LAFFAN INDUSTRIAL CITY
Q A A T T A A R
COMPRESSOR INSTAL LA TION PROCESS SHEET
Item No:
Report No:
Item Description:
Date:
Drawing No:
Area:
Item No
Description
Signature & Date Gama Linde QSGTL
1.
Foundation complete, Level & Accepted.
2.
Compressor & Driver Set
3.
Base Anchor Bolts Tight
4.
Grouted
5.
Pre alignment check of compressor & Driver Before Pipe Connection Verify Piping pressure test acceptance Before final alignment
6. 7. 8.
Piping connections complete with no objectionable loads or strains on the flanges Shaft Turning Freely
9.
Final alignment
10.
Jacking Screws Removed
11.
Seals Installed & Complete
12. 13.
Accessories Installed & Ready for service (Guards,Vents,Drains,sample connection,strainers,etc) Auxiliary System Complete(Seal,Flush,Water Complete(Seal,F lush,Water cooling etc)
14.
Temporary Suction Screens in Place
15.
Cleanliness Checked
Remarks: The Installation of the above compressor has been satisfactorily completed in accordance with the Drawings & Specifications ORGANIZATIONS
GAMA QATAR REP LINDE REP QSGTL REP GAM-QCR-QAC-GTL-114
DATE
NAME
SIGNATURE
EQUIPMENT LEVELLING & ALIGNMENT REPORT
Report No: Date:
PROJECT: C2 ASU PEARL GTL PROJECT-RAS PROJECT-RAS LAFFAN INDUSTRIAL INDUSTRIAL CITY
Tag No:
Manufacturer:
Drg. No:
Equip. Description No. of reading
Orientation
ORIE ORIENT NTAT ATIO ION N: LEVELLING GRADIENT / SLOPE
Elevation
Plumpness
ACCE ACCEPT PTED ED
Tolerance
Remarks
REJE REJECT CTED ED
REQUIRED
ACTUAL
ACC
REJECTED
REQUIRED
ACTUAL
ACC
REJECTED
GAM-QCR-QAC-GTL-115
PAGE 1 OF 2
REMARKS: …………………………………………………………………………………………………….. …………………………………………………………………………………………………………………… …………………………………………………………………………………………………………………… ……………………………………………………………………………………………………………………
GAMA
LINDE
QSGTL QSGTL or it s PMC
Name Sign Date
GAM-QCR-QAC-GTL-115
PAGE 2 OF 2
EQUIPMENT- SETTLEMENT MONITORING
REPORT NO: DATE:
PROJECT: C2 ASU PEARL GTL PROJECT-RAS LAFFAN INDUSTRIAL INDUSTRIAL CITY
AREA:
ITEM NO:
WEIGHT:
NAME:
DATE
PLANNED LEVEL
LEVEL/DIFFERENCE LEVEL/DIFFERENCE 0°
90°
180°
PLUMB
270°
BOTTOM
MIDDLE
ORIENTATION ORIENTATION TOP
A
B
C
SIGN D
TCM
TSKJN
180° 270°
TOLERANCE
LEVEL :
: _________________ _________________
PLUMB :
: _________________ _________________
ORIENTATION:_________________
GAM-QCR-QAC GAM-QCR-QAC-GTL-1 -GTL-116 16
PAGE 1 OF 2
THE SETTLEMENT OF THE ABOVE EQUIPMENT HAS BEEN SATISFACTORILY COMPLETED IN ACCORDA NCE WITH THE DRAWINGS AND SPECIFICATIONS (PA INTING AND INSTAL LATION LA TION EXCEPTION). REMARKS: -----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
ORGANIZATIONS
NAME
DATE
SIGNATURE
GAMA
LINDE
QSGTL or its PMC
GAM-QCR-QAC GAM-QCR-QAC-GTL-1 -GTL-116 16
PAGE 2 OF 2
REPORT NO.:
SITE INSPECTION REPORT PROJECT:
DATE:
C2 ASU PEARL GTL PROJECT –RAS LAFFAN INDUSTRIAL CITY
Originator
Date of observation:
Location / Area:
Unit No :
Discipline:
SYSTEM NUMBER:
Drawing / Specification Numbers
Description of Discrepancy/Observation (Be specific, events, time, date, location, etc :)
Corrective Action:
Originator: Name: _______________________ _____________________________Signature: ______Signature: _____________________Date: _____________________Date: ________________ NCR Required
YES
NO
(Circle one)
CTQ to Contractor Required
YES
NO
(Circle one)
Remarks if any:
Site Engineer:
Name:
_______________________ Signature: ________________ Date: ______________
QA/QC Manager: Name:
_________________________ _____________________ ____ Signature: _______________ Date: ______________
Discrepancy Corrected/Remarks:
GAMA Representative:
Name: ____________________
Close-out of Corrective Action - Remarks:
Site Engineer:
Name:
Signature:
______________ Date: ________________
NCR No.: ___________________
___________________
Signature: __________________ Date: ___________
DISTRIBUTION (Original QA/QC file)
QA/QC Manager
Site Manager
Site Engineer
Project Manager
Construction Manager
Originator
GAM-QCR-QAC-GTL-127
CTQ No: ______________
C2 ASU PEARL GTL PROJECT RAS LAFFAN INDUSTRIAL CITY
Q AA TT AA R
GENERAL PUNCH LIST
Sub contractor Ref:
Report No:
Item Description:
Inspection Date:
Item Location / Area:
SYSTEM NUMBER:
Sub System:
TAG NUMBER:
Ref Dwg/Documents:
LOOP FOLDER:
EQUIPMENT
ITE ITEM NO NO
ISO ISO or or DW DWG NU NUMBER
CIVIL
STRUCTURAL
DESCRIPTION OF WORK
PAINTING
COMPLETED(Date/Initials)
PRIORITY/ CATEGORY (A,B,C,D,E) (X,Y,Z)
INSULATION
GAMA
LINDE
QSGTL or its PMC
ALL PRIORITY A ITEMS SHOWN ABOVE HAVE BEEN VERIFIED AND ARE COMPLETED .INCOMPLETE PRIORITY B ITEMS WILL BE TRANSFERRED TO THE MECHANICAL COMPLETION PUNCH LIST PRIORITY A : ITEMS SHALL BE C OMPLETED BEFORE MECHANICAL COMPLETION (MC) PRIORITY B : ITEMS MAY BE COMPLETED AFTER MC PRIORITY C : ITEMS WILL BE COMPLETED BEFORE SYSTEM RFSU (READY FOR START UP UNIT) IS ACHIEVED PRIORITY D : ITEMS SHALL BE COMPLETED BEFORE RFSU IS ACHIEVED PRIORITY E : ITEMS SHALL BE C OMPLETED BEFORE ACCEPTENCE IS ACHIEVED CATEGORY X: CONSTRUCTION GROUP IS RESPONSIBLE FOR COMPLETION OF ITEM. CATEGORY Y: ENGINEERING INPUT IS REQUIRED FOR COMPLETION OF ITEM. CATEGORY Z: COMMISSIONING GROUP IS RESPONSIBLE FOR COMPLETION OF ITEM.
ORGANIZATIONS B D E T B E C C A
GAMA REP LINDE REP QSGTL or its PMC GAM-QCR-QAC-GTL-128
DATE
NAME
SIGNATURE
C2 ASU PEARL GTL PROJECT RAS LA FFAN INDUSTRIAL INDUSTRIAL CITY
Q A A T T A A R
Equipment Box-Up Accept ance Shee Sheett
Report No: Date: Area:
It is hereby certified that the Equipment referenced referenced has been mechanically mechanically comp leted in accordance with Drawings, Specifications, Inspection and Test Records. The referenced Equipment is ready for box-up. Equipment No Equipment Designation Designation Vendor / Manufacturer PID No
Acc ept ed GAMA
C h ec k l i s t
2
Name Plate, CE-marking (if applicable) Internals Internals installed
3
Internal Internal pipin g installed
4
Fillings completed
5
Refractory completed
6
Internal Internal tr ansport prot ection removed
7
Equipment internally clean and dry
8
Nozzles Nozzles / manholes clos ed acc. drawing
9
Specified Specified bli nd fl anges installed
10
Specified nozzle gaskets installed
11
Specified Specified bolts and nuts in stalled
12
Specified Specified to rques applied
13
Bolts lubricated (covers, manholes)
1
Accep Ac cep ted VENDOR
Acc ept ed Acc ept ed LINDE QSGTL
14
Remarks /
ORGANIZATIONS GAMA VENDOR LINDE QSGTL or its PMC GAM-QCR-QAC-GTL-133
NAME
DATE
SIGNATURE