Pearl GTL Project Shell Project No: HP-3000-QAT Project Document Number: T- 4.250.922
Purchase Order Number:
2MH127
Tag/Item Number(s):
N/A
Unit(s):
ASU
PCWBS:
Z
LINDE ENGINEERING
Contractor Project No: 5887
Project Rev.: A
Page 2 of 27
QATAR SHELL GTL PROJECT (PEARL) C2 AIR SEPARATION UNITS CONSTRUCTION
E
A
21.10.08
Issue for Review
SK
EO
AG
IFR
D
A
16.09.08
Issue for Review
SK
EO
AG
IFR
C
O
06.03.08
Issued for Company comments
BR
UA
ZG
ICC
B
03.02.08
Issued for Review
BR
UA
ZG
IFR
A
31.01.08
Issued for Internal Review
BR
UA
ZG
IIR
Date
Description
GAMA Rev.
Project Rev
No.
No.
Prepared Checked Approved By By By
Status
ORIGINATOR ORIGINATOR
Document Title:
INSPECTION TEST PLAN FOR PUMPS LINDEGINEERING AG Document No.
Contractor
Gama Qatar Co. W. L. L.
GAM
ITP
QAC
GTL
035
E
Org.
Doc. Type
Geogr. Area
Seq.
Code
Disc. Code
Rev. No
Project Document Number: T-4.250.922
No
LOC470 Vendor Code
Rev No: A
QSGTL PEARL PROJECT
ITP NO: NO: GAM-ITP-QAC-GTL-035
C2 ASU Construction Works ITP FOR INSTALLATION INSTALLATION OF PUMPS PUMPS (FSI) S. GAMA QATAR
X. CONTRACTOR QC
C. COMPANY
DATE: 21.10.08-REV.E DATE: 21.10.08-REV.E A. THIRD PARTY (TPI)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS(Notification WITNESS (Notification Required but Presence not Mandatory) Item
Test Frequency
Activity
Reference Document
Acceptance Criteria
Responsible Party
Verifying Documents
S
X
C
TECHINICAL OFFICE
-
H
R
R
1.0
DOCUMENTATION
1.1
Contractor drawings, project specifications, manuals, codes
100%
1.2
Lifting studies (For Heavy Equipments)
100%
T.4.234.084
-
HSSE
-
H
R
R
2.0
EQUIPMENT
2.1
Equipment identification and name plate verification
100%
T-4.250.945
Approved drawing, DEP 31.10.03.10; DEP 31.29.00.10
STORE INCHARGE
GAM-QCR-QAC-GTL-080
I
S
S
2.2
Receiving inspection
100%
T-4.250.945
Approved drawing, DEP DEP 31.29.00.10
STORE INCHARGE
GAM-QCR-QAC-GTL-080
I
I
S
2.3
Storage, preservation and documentation (FSI)
100%
T.13.377.360E;T.4.250.932
QCI
GAM-QCR-QAC-GTL-069
I
S
S
2.4
Periodic Preventive maintenance
100%
T-4.250.945;T.4.250.932
QCI
GAM-QCR-QAC-GTL-073
H
S
S
100%
T.4.250.915
QCI
Calibration certificate
H
R
R
2.5
Inspection measuring and test equipment calibration
3.0
INSTALLATION
-
-
Approved drawing, DEP 31.29.00.10;DEP 70.10.70.11 T.13.377.454E; Vendor instruction, DEP 70.10.70.11; T.13.377.454E DEP 31.29.00.10 Vendor instruction, -
A
Page 4
T-4.250-922 REV-A
QSGTL PEARL PROJECT
ITP NO: NO: GAM-ITP-QAC-GTL-035
C2 ASU Construction Works ITP FOR INSTALLATION INSTALLATION OF PUMPS PUMPS (FSI) S. GAMA QATAR
X. CONTRACTOR QC
C. COMPANY
DATE: 21.10.08-REV.E DATE: 21.10.08-REV.E A. THIRD PARTY (TPI)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS(Notification WITNESS (Notification Required but Presence not Mandatory) Item
Activity
Test Frequency
Reference Document
100%
T-4.250.945
100%
T-4.250.945
Acceptance Criteria
Responsible Party
Verifying Documents
S
X
C
QCI
GAM-QCR-QAC-GTL-120; GAM-QCR-QAC-GTL-113
H
I
I
I
I
I
I
I
I
I
I
I
A
Approved drawing, 3.1
3.2
3.3
3.4
Foundation complete and accepted
Foundation chipping to sound metal Anchor bolts control & pocket cleaning
Shims installation
DEP 34.19.20.31; T.13.376.358 DEP 31.29.00.10 Approved drawing, DEP DEP 34.19.20.31; T.13.376.358
QCI
DEP 31.29.00.10 100%
T-4.250.945
100%
T-4.250.945
Approved drawing, DEP DEP 34.19.20.31;T.13.376.358 DEP 31.29.00.10 Approved drawing, T.13.376.358
QCI
QCI
DEP 31.29.00.10 Levelling, orientation & 3.5
alignment (pump & driver
100%
T-4.250.945 T.13.377.360E
3.7
3.8
Settlement monitoring(FSI) monitoring (FSI) Checking and recording of “soft f oo oot”
Bolts Tightening(FSI) Tightening(FSI)
100%
T-4.250.945
100%
T-4.250.945
100%
T-4.250.945; T.13.377.360E
Approved drawing, DEP 31.29.00.10,
GAM-QCR-QAC-GTL-120; GAM-QCR-QAC-GTL-113
GAM-QCR-QAC-GTL-120 GAM-QCR-QAC-GTL-120 GAM-QCR-QAC-GTL-115
H
I
I
QCI
GAM-QCR-QAC-GTL-116
I
S
S
QCI
GAM-QCR-QAC-GTL-120
I
S
S
QCI
GAM-QCR-QAC-GTL-120 GAM-QCR-QAC-GTL-041
H
I
S
Vendor specifications, Approved drawings, DEP 31.29.00.10 SEC-3.9.4.7 Approved drawing, DEP DEP 31.29.00.10, Vendor specification,
T-4.250-922 REV-A
GAM-QCR-QAC-GTL-113
QCI
Vendor specification
set)(FSI) set)(FSI) 3.6
Approved drawing, DEP DEP 31.29.00.10,
GAM-QCR-QAC-GTL-120;
Page 5
QSGTL PEARL PROJECT
ITP NO: NO: GAM-ITP-QAC-GTL-035
C2 ASU Construction Works ITP FOR INSTALLATION INSTALLATION OF PUMPS PUMPS (FSI) S. GAMA QATAR
X. CONTRACTOR QC
C. COMPANY
DATE: 21.10.08-REV.E DATE: 21.10.08-REV.E A. THIRD PARTY (TPI)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS(Notification WITNESS (Notification Required but Presence not Mandatory) Item
Test Frequency
Activity
Reference Document
Acceptance Criteria
Responsible Party
Verifying Documents
S
X
C
QCI
GAM-QCR-QAC-GTL-120; GAM-QCR-QAC-GTL-113
H
I
I
I
I
I
I
I
I
I
I
I
A
Approved drawing, 3.1
3.2
3.3
3.4
Foundation complete and accepted
Foundation chipping to sound metal
100%
T-4.250.945
100%
T-4.250.945
DEP 34.19.20.31; T.13.376.358 DEP 31.29.00.10 Approved drawing, DEP DEP 34.19.20.31; T.13.376.358
GAM-QCR-QAC-GTL-120;
QCI
GAM-QCR-QAC-GTL-113
DEP 31.29.00.10
Anchor bolts control & pocket cleaning
Shims installation
100%
T-4.250.945
100%
T-4.250.945
Approved drawing, DEP DEP 34.19.20.31;T.13.376.358 DEP 31.29.00.10 Approved drawing, T.13.376.358
GAM-QCR-QAC-GTL-120; GAM-QCR-QAC-GTL-113
QCI
QCI
GAM-QCR-QAC-GTL-120
DEP 31.29.00.10 Levelling, orientation & 3.5
alignment (pump & driver
100%
T-4.250.945 T.13.377.360E
3.7
3.8
QCI
GAM-QCR-QAC-GTL-120 GAM-QCR-QAC-GTL-115
H
I
I
QCI
GAM-QCR-QAC-GTL-116
I
S
S
QCI
GAM-QCR-QAC-GTL-120
I
S
S
QCI
GAM-QCR-QAC-GTL-120 GAM-QCR-QAC-GTL-041
H
I
S
Vendor specification
set)(FSI) set)(FSI) 3.6
Approved drawing, DEP DEP 31.29.00.10,
Settlement monitoring(FSI) monitoring (FSI) Checking and recording of “soft f oo oot”
Bolts Tightening(FSI) Tightening(FSI)
100%
T-4.250.945
100%
T-4.250.945
100%
T-4.250.945; T.13.377.360E
Approved drawing, DEP 31.29.00.10, Vendor specifications, Approved drawings, DEP 31.29.00.10 SEC-3.9.4.7 Approved drawing, DEP DEP 31.29.00.10, Vendor specification,
Page 5
T-4.250-922 REV-A
QSGTL PEARL PROJECT
ITP NO: NO: GAM-ITP-QAC-GTL-035
C2 ASU Construction Works ITP FOR INSTALLATION INSTALLATION OF PUMPS PUMPS (FSI) S. GAMA QATAR
X. CONTRACTOR QC
C. COMPANY
DATE: 21.10.08-REV.E DATE: 21.10.08-REV.E A. THIRD PARTY (TPI)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS(Notification WITNESS (Notification Required but Presence not Mandatory) Item
Activity
Test Frequency
Reference Document
Acceptance Criteria
Responsible Party
Verifying Documents
S
X
C
DEP34.19.20.31; T.13.376.358 ;Manufactures Instruction
QCI
GAM-QCR-QAC-GTL-025
I
I
I
I
I
S
3.9
Grouting
100%
T-4.234.545
3.10
Jack screw removal
100%
T-4.250.945
3.11
Temporary earthing
100%
T-4.250.945
100%
T-4.250.945; T.13.377.360E
100%
T-4.250.945; T-4.250.936; T.13.377.360E
100%
T-4.250.936
3.12
3.13
Anchor bolts Tightening Tightening after grouting(FSI) grouting(FSI)
Flanges parallelism (FSI) All piping installation, installation,
3.14
alignment, & connection
DEP 31.29.00.10 Vendor specification, Approved drawing,
QCI
GAM-QCR-QAC-GTL-120
QCI
GAM-QCR-QAC-GTL-120
I
I
S
Approved drawing, DEP DEP 31.29.00.10,
QCI
GAM-QCR-QAC-GTL-120
H
I
S
Approved drawing, DEP 31.29.00.10 DEP 31.38.01.11;T.13.376.815E
QCI
GAM-QCR-QAC-GTL-120 GAM-QCR-QAC-GTL-058
H
I
I
QCI
GAM-QCR-QAC-GTL-120
H
S
S
QCI
GAM-QCR-QAC-GTL-120
H
I
I
QCI
GAM-QCR-QAC-GTL-132
I
I
I
DEP 31.29.00.10,
A
Approved drawing,
without any objectionable load
DEP 31.29.00.10, DEP 31.38.01.11;T.13.376.815E Approved drawing,
3.15
Cold alignment & levelling rechecking(FSI) rechecking(FSI)
100%
T-4.250.936; T.13.377.360E
DEP 31.29.00.10, DEP 61.10.08.11; T.13.377.455E
T-4.250.936
Approved drawing, DEP DEP 31.29.00.10; DEP 31.38.01.11;T.13.376.815E; DEP 31.29.00.36
Vendor specification 3.16
Coupling Installation check
T-4.250-922 REV-A
100%
Page 6
QSGTL PEARL PROJECT
ITP NO: NO: GAM-ITP-QAC-GTL-035
C2 ASU Construction Works ITP FOR INSTALLATION INSTALLATION OF PUMPS PUMPS (FSI) S. GAMA QATAR
X. CONTRACTOR QC
C. COMPANY
DATE: 21.10.08-REV.E DATE: 21.10.08-REV.E A. THIRD PARTY (TPI)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS(Notification WITNESS (Notification Required but Presence not Mandatory) Item
Activity
Test Frequency
Reference Document
Acceptance Criteria
Responsible Party
Verifying Documents
S
X
C
DEP34.19.20.31; T.13.376.358 ;Manufactures Instruction
QCI
GAM-QCR-QAC-GTL-025
I
I
I
I
I
S
3.9
Grouting
100%
T-4.234.545
3.10
Jack screw removal
100%
T-4.250.945
3.11
Temporary earthing
100%
T-4.250.945
100%
T-4.250.945; T.13.377.360E
100%
T-4.250.945; T-4.250.936; T.13.377.360E
100%
T-4.250.936
3.12
3.13
Anchor bolts Tightening Tightening after grouting(FSI) grouting(FSI)
Flanges parallelism (FSI) All piping installation, installation,
3.14
DEP 31.29.00.10 Vendor specification, Approved drawing,
QCI
GAM-QCR-QAC-GTL-120
QCI
GAM-QCR-QAC-GTL-120
I
I
S
Approved drawing, DEP DEP 31.29.00.10,
QCI
GAM-QCR-QAC-GTL-120
H
I
S
Approved drawing, DEP 31.29.00.10 DEP 31.38.01.11;T.13.376.815E
QCI
GAM-QCR-QAC-GTL-120 GAM-QCR-QAC-GTL-058
H
I
I
QCI
GAM-QCR-QAC-GTL-120
H
S
S
QCI
GAM-QCR-QAC-GTL-120
H
I
I
QCI
GAM-QCR-QAC-GTL-132
I
I
I
DEP 31.29.00.10,
A
Approved drawing,
alignment, & connection without any objectionable load
DEP 31.29.00.10, DEP 31.38.01.11;T.13.376.815E Approved drawing,
3.15
Cold alignment & levelling
100%
rechecking(FSI) rechecking(FSI)
T-4.250.936; T.13.377.360E
DEP 31.29.00.10, DEP 61.10.08.11; T.13.377.455E Vendor specification
3.16
Coupling Installation check
100%
T-4.250.936
Approved drawing, DEP DEP 31.29.00.10; DEP 31.38.01.11;T.13.376.815E; DEP 31.29.00.36
Page 6
T-4.250-922 REV-A
QSGTL PEARL PROJECT
ITP NO: NO: GAM-ITP-QAC-GTL-035
C2 ASU Construction Works ITP FOR INSTALLATION INSTALLATION OF PUMPS PUMPS (FSI) S. GAMA QATAR
X. CONTRACTOR QC
C. COMPANY
DATE: 21.10.08-REV.E DATE: 21.10.08-REV.E A. THIRD PARTY (TPI)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS(Notification WITNESS (Notification Required but Presence not Mandatory) Item
Activity
Test Frequency
Reference Document
Acceptance Criteria
T-4.250.945; T.13.377.360E
DEP 31.29.00.10, DEP 61.10.08.11; T.13.377.455E
Responsible Party
Verifying Documents
S
X
C
QCI
GAM-QCR-QAC-GTL-120
I
I
I
QCI
GAM-QCR-QAC-GTL-120 GAM-QCR-QAC-GTL-070
H
H
I
QCI
GAM-QCR-QAC-GTL-120
I
I
S
A
Approved drawing, 3.17
Mechanical seal/packing installation check(FSI) check(FSI)
100%
Vendor specification
3.18
Cleaning, flushing and oil filling(FSI) filling(FSI)
100%
T-4.250.930;T.13.377.360E
DEP 31.29.00.10, DEP 70.10.80.11, DEP 61.10.08.11;T.13.377.455E Vendor specification,
3.19
Temporary suction strainers
Approved drawing, DEP 31.29.00.10 DEP 31.38.01.11;T.13.376.815E
100%
T-4.250.936; T-4.250.945
100%
T-4.251.035
-
QCI
GAM-QCR-QAC-GTL-127 GAM-QCR-QAC-GTL-127
I
I
R
100%
T-4.250.945:T.13.377.360E
Approved drawings,DEP 31.29.00.10
QCI
GAM-QCR-QAC-GTL-115
H
I
I
100%
T-4.250.945
DEP 61.10.08.11 Approved drawings, DEP 31.29.00.10 Sec 4.20.9
QCI
GAM-QCR-QAC-GTL-120
I
I
S
100%
T-4.250.945
DEP 61.10.08.11; T.13.377.455EApproved drawings, DEP 31.29.00.10
QCI
GAM-QCR-QAC-GTL-120
I
I
S
installation check 3.20
Equipment if any damage
4.0
FINAL INSPECTION
4.1
Final alignment(FSI) alignment(FSI) Checking and recording of
4.2
distance between shaft ends and/or between hubs
4.3
Shaft turning freely by hand
T-4.250-922 REV-A
Page 7
QSGTL PEARL PROJECT
ITP NO: NO: GAM-ITP-QAC-GTL-035
C2 ASU Construction Works ITP FOR INSTALLATION INSTALLATION OF PUMPS PUMPS (FSI) S. GAMA QATAR
X. CONTRACTOR QC
C. COMPANY
DATE: 21.10.08-REV.E DATE: 21.10.08-REV.E A. THIRD PARTY (TPI)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS(Notification WITNESS (Notification Required but Presence not Mandatory) Item
Test Frequency
Activity
Reference Document
Acceptance Criteria
T-4.250.945; T.13.377.360E
DEP 31.29.00.10, DEP 61.10.08.11; T.13.377.455E
Responsible Party
Verifying Documents
S
X
C
QCI
GAM-QCR-QAC-GTL-120
I
I
I
QCI
GAM-QCR-QAC-GTL-120 GAM-QCR-QAC-GTL-070
H
H
I
QCI
GAM-QCR-QAC-GTL-120
I
I
S
A
Approved drawing, 3.17
Mechanical seal/packing
100%
installation check(FSI) check(FSI)
Vendor specification
3.18
Cleaning, flushing and oil
100%
filling(FSI) filling(FSI)
T-4.250.930;T.13.377.360E
DEP 31.29.00.10, DEP 70.10.80.11, DEP 61.10.08.11;T.13.377.455E Vendor specification,
3.19
Temporary suction strainers
Approved drawing, DEP 31.29.00.10 DEP 31.38.01.11;T.13.376.815E
100%
T-4.250.936; T-4.250.945
100%
T-4.251.035
-
QCI
GAM-QCR-QAC-GTL-127 GAM-QCR-QAC-GTL-127
I
I
R
100%
T-4.250.945:T.13.377.360E
Approved drawings,DEP 31.29.00.10
QCI
GAM-QCR-QAC-GTL-115
H
I
I
100%
T-4.250.945
DEP 61.10.08.11 Approved drawings, DEP 31.29.00.10 Sec 4.20.9
QCI
GAM-QCR-QAC-GTL-120
I
I
S
100%
T-4.250.945
DEP 61.10.08.11; T.13.377.455EApproved drawings, DEP 31.29.00.10
QCI
GAM-QCR-QAC-GTL-120
I
I
S
installation check 3.20
Equipment if any damage
4.0
FINAL INSPECTION
4.1
Final alignment(FSI) alignment(FSI) Checking and recording of
4.2
distance between shaft ends and/or between hubs
4.3
Shaft turning freely by hand
Page 7
T-4.250-922 REV-A
QSGTL PEARL PROJECT
ITP NO: NO: GAM-ITP-QAC-GTL-035
C2 ASU Construction Works ITP FOR INSTALLATION INSTALLATION OF PUMPS PUMPS (FSI) S. GAMA QATAR
X. CONTRACTOR QC
C. COMPANY
DATE: 21.10.08-REV.E DATE: 21.10.08-REV.E A. THIRD PARTY (TPI)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS(Notification WITNESS (Notification Required but Presence not Mandatory) Item
Activity
Test Frequency
Reference Document
Acceptance Criteria
T-4.250.930;T.13.377.360E
DEP 61.10.08.11Approved drawings, DEP 31.29.00.10
equipment and associated
100%
system(FSI) system(FSI)
4.5
Verification of auxiliary system completion
Verifying Documents
S
X
C
QCI
GAM-QCR-QAC-GTL-120 GAM-QCR-QAC-GTL-070
H
I
I
QCI
GAM-QCR-QAC-GTL-120
I
I
S
A
Vendor specifications
Cleanliness check for 4.4
Responsible Party
DEP 70.10.80.11
100%
T-4.250.945
Vendor specifications Approved drawings, DEP DEP 31.29.00.10 DEP 61.10.08.11
4.6
Verification of piping pressure test acceptance – Prior to final alignment(FSI) alignment(FSI)
4.7
Installation of accessories & coupling guard
4.8 4.9
4.10
T-4.250.945; T-4.250.908 T.13.377.360E
Approved drawing DEP 31.38.01.11;T.13.376.815E
QCI
GAM-QCR-QAC-GTL-065
H
H
W
100%
T-4.250.945
Vendor specifications DEP 61.10.08.11;T.13.377.455E Approved drawings, DEP DEP 31.29.00.10
QCI
GAM-QCR-QAC-GTL-120
I
I
S
General Punch List(Clearing)
100%
T-4.250.945
-
QCI
GAM-QCR-QAC-GTL-128 GAM-QCR-QAC-GTL-128
H
H
R
Final Equipment box up
100%
T-4.250.945
-
QCI
GAM-QCR-QAC-GTL-133
H
H
S
100%
T-4.250.945
T.13.377.555G
QCI
ALL REPORTS
H
H
R
Installation Completion and sign-off quality records
T-4.250-922 REV-A
100%
Page 8
QSGTL PEARL PROJECT
ITP NO: NO: GAM-ITP-QAC-GTL-035
C2 ASU Construction Works ITP FOR INSTALLATION INSTALLATION OF PUMPS PUMPS (FSI) S. GAMA QATAR
X. CONTRACTOR QC
DATE: 21.10.08-REV.E DATE: 21.10.08-REV.E
C. COMPANY
A. THIRD PARTY (TPI)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS(Notification WITNESS (Notification Required but Presence not Mandatory) Item
Test Frequency
Activity
Reference Document
Acceptance Criteria
T-4.250.930;T.13.377.360E
DEP 61.10.08.11Approved drawings, DEP 31.29.00.10
equipment and associated
100%
system(FSI) system(FSI)
4.5
Verifying Documents
S
X
C
QCI
GAM-QCR-QAC-GTL-120 GAM-QCR-QAC-GTL-070
H
I
I
QCI
GAM-QCR-QAC-GTL-120
I
I
S
A
Vendor specifications
Cleanliness check for 4.4
Responsible Party
DEP 70.10.80.11
Verification of auxiliary system completion
100%
Vendor specifications Approved drawings, DEP DEP 31.29.00.10
T-4.250.945
DEP 61.10.08.11 4.6
Verification of piping pressure test acceptance – Prior to final alignment(FSI) alignment(FSI)
4.7
Installation of accessories & coupling guard
4.8 4.9
4.10
T-4.250.945; T-4.250.908 T.13.377.360E
Approved drawing DEP 31.38.01.11;T.13.376.815E
QCI
GAM-QCR-QAC-GTL-065
H
H
W
100%
T-4.250.945
Vendor specifications DEP 61.10.08.11;T.13.377.455E Approved drawings, DEP DEP 31.29.00.10
QCI
GAM-QCR-QAC-GTL-120
I
I
S
General Punch List(Clearing)
100%
T-4.250.945
-
QCI
GAM-QCR-QAC-GTL-128 GAM-QCR-QAC-GTL-128
H
H
R
Final Equipment box up
100%
T-4.250.945
-
QCI
GAM-QCR-QAC-GTL-133
H
H
S
100%
T-4.250.945
T.13.377.555G
QCI
ALL REPORTS
H
H
R
Installation Completion and sign-off quality records
100%
Page 8
T-4.250-922 REV-A
C2-ASU PROJECT GAMA QATAR GROUT POUR CARD(PRE/POST POUR)
Form No: GAM-QCR-QAC-GTL-025
Inspection Gr.:
ITP No.:
Laboratory:
Record No:
Date:
TAG NO.: DESCRIPTION: TYPE OF GROUT:
LOCATION: DRAWING: QUANTITY OF GROUT: GAMA/T – Const.
Item No.
TYPE OF ACTIVITY
1.0
Setting Out
2.0
Concrete Surface Preparation
3.0
Equipment / Surface Alignment
4.0
Formworks
5.0
Isolation Joint
6.0
Metal Surface Preparation
7.0
Mixing / Placing / Finishing of Grout (1)
8.0
Curing of Grout (1)
9.0
Removal of Shims
10.0
Mixing / Placing / Finishing of Grout (2)
11.0
Curing of Grout (2)
12.0
Sealant to Isolation Joint
13.0
Final Inspection
Signature
Date
GAMA/T - QC Signature
Date
CONTRACTOR CONTRACTOR Signature
Date
Remarks: Full Name/Signature/Date GAMA QATAR
CONTRACTOR
COMPANY
COMPANY(*) Signature
Date
REMARKS
C2-ASU PROJECT GAMA QATAR GROUT POUR CARD(PRE/POST POUR)
Form No: GAM-QCR-QAC-GTL-025
Inspection Gr.:
ITP No.:
Laboratory:
Record No:
Date:
TAG NO.: DESCRIPTION: TYPE OF GROUT:
LOCATION: DRAWING: QUANTITY OF GROUT: GAMA/T – Const.
Item No.
TYPE OF ACTIVITY
1.0
Setting Out
2.0
Concrete Surface Preparation
3.0
Equipment / Surface Alignment
4.0
Formworks
5.0
Isolation Joint
6.0
Metal Surface Preparation
7.0
Mixing / Placing / Finishing of Grout (1)
8.0
Curing of Grout (1)
9.0
Removal of Shims
10.0
Mixing / Placing / Finishing of Grout (2)
11.0
Curing of Grout (2)
12.0
Sealant to Isolation Joint
13.0
Final Inspection
Signature
Date
GAMA/T - QC Signature
CONTRACTOR CONTRACTOR
Date
Signature
Date
COMPANY(*) Signature
REMARKS
Date
Remarks: Full Name/Signature/Date GAMA QATAR
CONTRACTOR
COMPANY
C2 ASU PEARL GTL PROJECT RASLA FFAN INDUSTRIAL INDUSTRIAL CITY
BOLT TIGHTENING INSPECTION REPORT
Subcontract Ref.:
Report No.:
Item Description:
Inspection Date:
Item Location / Area:
Test Code No.:
Subsystem:
ITP No.:
Ref. DWG / Docs: Used Measuring and test equipment ref. (if applicable): INSPECTIONS
Item No/Spool No
Mark No./Joint No
Bolting Grade
Size
Bolt Tightening (Torque Value)
Inspector’s Signature
C2 ASU PEARL GTL PROJECT RASLA FFAN INDUSTRIAL INDUSTRIAL CITY
BOLT TIGHTENING INSPECTION REPORT
Subcontract Ref.:
Report No.:
Item Description:
Inspection Date:
Item Location / Area:
Test Code No.:
Subsystem:
ITP No.:
Ref. DWG / Docs: Used Measuring and test equipment ref. (if applicable): INSPECTIONS
Item No/Spool No
Mark No./Joint No Grade
ORGANIZATIONS y B d e t p e c c A
Bolting
DATE
THIRD PARTY REP. GAMA REP. LINDE REP. QSGTL OR its PMC REP.
GAM-QCR-QAC-GTL-041
C2 ASU PEARL GTL PROJECT
Size
NAME
Bolt Tightening (Torque Value)
Inspector’s Signature
SIGNATURE
C2 ASU PEARL GTL PROJECT RASLA FFAN INDUSTRIAL INDUSTRIAL CITY
FLANGE ALIGNMENT INSPECTION REPORT
Subcontract Ref.:
Report No.:
Item Description:
Inspection Date:
Item Location / Area:
Test Code No.:
Subsystem:
ITP No.:
Ref. DWG / Docs: Used Measuring and test equipment ref. (if applicable): INSPECTIONS
Item No/Spool No
Mark No./Joint No
ORGANIZATIONS y B d e t p e c c A
Face Distance
DATE
Face parallelism
Centreline offset
NAME
Inspector’s Inspector ’s Signature
SIGNATURE
THIRD PARTY REP. GAMA REP. LINDE REP. QSGTL OR its PMC REP.
GAM-QCR-QAC-GTL-058
Q A A T T A A R Company
C2 ASU PEARL PEARL GTL PROJECT PROJECT RAS LAFFAN INDUSTR INDUSTRIAL IAL CITY Project No:
Piping Test No:
Q A A T T A A R
C2 ASU PEARL PEARL GTL PROJECT PROJECT RAS LAFFAN INDUSTR INDUSTRIAL IAL CITY
Company
Project No:
Project Title:
Location
Piping Test No:
PIPING FIELD Priority System No:
TEST REPORT S/C Prepared By:
Test Media:
Name:
Signature
Description Of Test
Date:
LINDE Acceptance By: Name:
Reference Flow Sheets (List All applicable): Signature
Line Number
Line Size
Date: Drawing or Isometric Number
Rev (At Time of Test)
Fr o m
To
Paint Code
Insul. Code
Equipment Tested Trough:
WELDING INSPECTION RELEASE, READY FOR TEST (All Welding and NDT is complete and per specification and piping is ready for test) GAMA WELDING
Lines/ piping as tabulated above have been tested and found to supports, valves and components components in place except for items nece Test Witnessed By
Inspector: Name
Date:
Signature:
LINDE Welding
GAMA Inspector: Name
Signature:
LINDE Field
Inspector: Name
Signature:
Date::
QSGTL or its PMC
Engineer: Name
Signature:
QSGTL or its PMC
Inspector: Name
Signature:
Date::
Inspector: Name
Signature
GAM-QCR-QAC-GTL-065
Piping Test No:
PIPING PIPING FIELD FIELD TEST TEST REPORT REPORT Descrip Descr ipti ti on of Test Test Line Number
Line Size
Drawing or Isometric Number
(Continuation Sheet)
Rev (At Time of Test)
Fr o m
To
Paint Code
Insul. Code
Piping Test No:
PIPING PIPING FIELD FIELD TEST TEST REPORT REPORT Descrip Descr ipti ti on of Test Test Line Size
Line Number
Drawing or Isometric Number
(Continuation Sheet)
Rev (At Time of Test)
Fr o m
To
Paint Code
Insul. Code
GAM-QCR-QAC-GTL-065
C2 ASU PEARL GTL PROJECT RAS LAFFAN INDUSTRIAL CITY
Q A A
CLEANLINESS CLEA NLINESS ACCEPTENCE REPORT REPORT
A A R
Sub Contract Ref:
Item Location Area:
Isometric No:
Item Description:
sub system:
Form No:
t e e h s
Cleanliness class
Spool
Cleaning Method
Inspection method
In s p ec t i o n Res u l t
Pre Fabrication
Er ec t i o n
Report No: Inspection Date GA MA QA TA R Si g n at u r e
Dat e
L INDE Si g n at u r e
QSGTL o r i t s PMC Dat e
Si g n at u r e
Dat e
C2 ASU PEARL GTL PROJECT RAS LAFFAN INDUSTRIAL CITY
Q A A
CLEANLINESS CLEA NLINESS ACCEPTENCE REPORT REPORT
A A R
Sub Contract Ref:
Item Location Area:
Isometric No:
Item Description:
sub system:
Form No:
t e e h s
Cleanliness class
Spool
Cleaning Method
Inspection method
In s p ec t i o n Res u l t
Pre Fabrication
Report No: Inspection Date GA MA QA TA R
Er ec t i o n
Si g n at u r e
Dat e
L INDE Si g n at u r e
QSGTL o r i t s PMC Dat e
Si g n at u r e
GAM-QCR-QAC-GTL-070
C2 ASU PEARL GTL PROJECT RAS LAFFAN INDUSTRIAL CITY
Q A A T T A A R
PERIODIC PREVENTIVE MAINTENANCE CHECK
Subcontract Ref.:
Report No.
Item Description:
Inspection Date:
Item Location / Area:
Vendor IMOI Ref:
Subsystem:
Equipt.Tag No
Ref. DWG / Documents: Used Measuring and test equipment ref. (if applicable):
Date Date of Inspection
PRESERVATION REQUIREMENTS (ROTATIC EQUIPMENT) EQUIPMENT) 1.General Inspection-Weather Protection/Painting Protection/Painting
2. All openings sealed including Motor junction Box. 3. All Mechanical surfaces protected against rust. 4.Check Nitrogen Pressure 5.Anchor bolts/shims covered with grease 6.Rotate all shafts,pulleys,lubricators by 21/4 turns
7.Check oil levels of-bearing housing, gear/crank casing, tanks 8.Check for water at drain points 9.Flange faces-protection denso tape & dust blinds in place
ORGANIZATIONS
DATE
NAME
SIGNATURE
Dat e
C2 ASU PEARL GTL PROJECT RAS LAFFAN INDUSTRIAL CITY
Q A A T T A A R
PERIODIC PREVENTIVE MAINTENANCE CHECK
Subcontract Ref.:
Report No.
Item Description:
Inspection Date:
Item Location / Area:
Vendor IMOI Ref:
Subsystem:
Equipt.Tag No
Ref. DWG / Documents: Used Measuring and test equipment ref. (if applicable):
Date Date of Inspection
PRESERVATION REQUIREMENTS (ROTATIC EQUIPMENT) EQUIPMENT) 1.General Inspection-Weather Protection/Painting Protection/Painting
2. All openings sealed including Motor junction Box. 3. All Mechanical surfaces protected against rust. 4.Check Nitrogen Pressure 5.Anchor bolts/shims covered with grease 6.Rotate all shafts,pulleys,lubricators by 21/4 turns
7.Check oil levels of-bearing housing, gear/crank casing, tanks 8.Check for water at drain points 9.Flange faces-protection denso tape & dust blinds in place
ORGANIZATIONS
DATE
NAME
SIGNATURE
y THIRD PARTY REP. B d e GAMA REP. t p e c LINDE REP. c A
QSGTL REP.
GAM-QCR-QAC-GTL-073
C2 ASU PEARL GTL PROJECT RAS LAFFAN INDUSTRIAL CITY
Q A A T T A A R
INITIAL STORAGE AND PRESERVATION PRESERVATION CHECK
Subcontract Ref.:
Report No.
001
Item Description:
HEX BOX FC21
Inspection Date:
Item Location / Area:
COLD BOX - FC
Vendor IMOI Ref:
Subsystem:
RFI NO : 1850
08.06.08
Equipt.Tag No
Ref. DWG / Documents:
T.4.115.028 , T.4.250.501
Used Measuring and test equipment ref. (if applicable):
Signature
PRESERVATION REQUIREMENTS (STATIC EQUIPMENT) GAMA 1. Check the name plate is installed and legible. 2.Check for protective covers on all the openings 3.Ensure that dessicant is installed and properly sealed 4.check for moisture present 5.check nozzle flange face is acceptable 6.check for rust preventive coating on all exposed surfaces 7.check that internal and accessories storage is acceptable 8.Equipment low point drains shall be opened and checked for water ` 9. Check for “no welding permitted” signs stenciled at conspicuous location. 10. Check that test holes in reinforcement plates are open and g reased. 11. Check purge pressure and re-purge if required. 12. Check surface for any transit damage and paint removal. Carry out touch up if required.
LINDE
QSGTL QSGTL or its PMC
C2 ASU PEARL GTL PROJECT RAS LAFFAN INDUSTRIAL CITY
Q A A T T A A R
INITIAL STORAGE AND PRESERVATION PRESERVATION CHECK
Subcontract Ref.:
Report No.
001
Item Description:
HEX BOX FC21
Inspection Date:
Item Location / Area:
COLD BOX - FC
Vendor IMOI Ref:
Subsystem:
RFI NO : 1850
08.06.08
Equipt.Tag No
Ref. DWG / Documents:
T.4.115.028 , T.4.250.501
Used Measuring and test equipment ref. (if applicable):
Signature
PRESERVATION REQUIREMENTS (STATIC EQUIPMENT) GAMA
LINDE
1. Check the name plate is installed and legible. 2.Check for protective covers on all the openings 3.Ensure that dessicant is installed and properly sealed 4.check for moisture present 5.check nozzle flange face is acceptable 6.check for rust preventive coating on all exposed surfaces 7.check that internal and accessories storage is acceptable 8.Equipment low point drains shall be opened and checked for water ` 9. Check for “no welding permitted” signs stenciled at conspicuous location. 10. Check that test holes in reinforcement plates are open and g reased. 11. Check purge pressure and re-purge if required. 12. Check surface for any transit damage and paint removal. Carry out touch up if required. ORGANIZATIONS
DATE
NAME
SIGNATURE
GAMA REP. LINDE REP. QSGTL REP.
GAM-QCR-QAC-GTL-074
C2 ASU PEARL GTL PROJECT RAS LA FFAN INDUSTRIAL INDUSTRIAL CITY
EQUIPMENT RECEIPT CHECK SHEET
ITEM No:
PO No:
UNIT No:
MANUFACTURER :
ITEMS TO BE CHECKED
1 Name Plate 2 Preparation and painting 3 Desiccant installed 4 Moisture present
INSPECTOR INITIAL
REQ No:
REMARKS
QSGTL QSGTL or its PMC
C2 ASU PEARL GTL PROJECT RAS LA FFAN INDUSTRIAL INDUSTRIAL CITY
EQUIPMENT RECEIPT CHECK SHEET
ITEM No:
PO No:
UNIT No:
MANUFACTURER :
ITEMS TO BE CHECKED
REQ No:
INSPECTOR INITIAL
REMARKS
1 Name Plate 2 Preparation and painting 3 Desiccant installed 4 Moisture present 5 Nozzle flange faces acceptable 6 Temporary nozzle protection acceptable 7 Internals and accessories complete and storage acceptable 8 Purge - pressure: Purge monitoring date: Date of initial inspection:
Name and signature of Inspector:
GAM-QCR-QAC-GTL-080
Pressure
Report No:
FOUNDATION INSPECTION REPORT
Date: PROJECT:
C2 ASU PEARL GTL PROJECT-RAS LAFFAN INDUSTRIAL INDUSTRIAL CITY
Tag No:
Drg. No:
Area:
Unit:
ELEVATION
0
Plot Plan: 90
180
°
°
270
°
°
REQUIRED ACTUAL DEVIATION TOLERANCE REMARKS
ORIENTATION
ACCEPTED
REJECTED REQUIRED
POCKET CLEANING
ACTUAL
DEVIATION
ACCEPTED
TOLERANCE
REJECTED
REMARKS
NO. OF ANCHOR BOLTS ANCHOR BOLT DIA ANCHOR BOLT LENGTH FOUNDATION POCKET POCKET DEPTH FOUNDATION CHIPPING
REQUIRED
NOT REQUIRED
IF REQUIRED THICKNESS
NOTE:
THE ABOVE MENTIONED FOUNDATION IS ACCEPTED AND RELEASED FOR ERECTION ACTIVITIES
GAMA Name Sign Date GAM-QCR-QAC-GTL-113
LINDE
QSGTL QSGTL or it s PMC
EQUIPMENT LEVELLING & ALIGNMENT REPORT
Report No: Date:
PROJECT: C2 ASU PEARL GTL PROJECT-RAS PROJECT-RAS LAFFAN INDUSTRIAL INDUSTRIAL CITY
Tag No:
Manufacturer:
Drg. No:
Equip. Description No. of reading
Orientation
ORIE ORIENT NTAT ATIO ION N: LEVELLING GRADIENT / SLOPE
Elevation
Plumpness
ACCE ACCEPT PTED ED
Tolerance
Remarks
REJE REJECT CTED ED
REQUIRED
ACTUAL
ACC
REJECTED
REQUIRED
ACTUAL
ACC
REJECTED
GAM-QCR-QAC-GTL-115
PAGE 1 OF 2
REMARKS: …………………………………………………………………………………………………….. …………………………………………………………………………………………………………………… …………………………………………………………………………………………………………………… ……………………………………………………………………………………………………………………
GAMA
LINDE
QSGTL QSGTL or it s PMC
Name Sign Date
GAM-QCR-QAC-GTL-115
PAGE 2 OF 2
EQUIPMENT- SETTLEMENT MONITORING
REPORT NO: DATE:
PROJECT: C2 ASU PEARL GTL PROJECT-RAS LAFFAN INDUSTRIAL INDUSTRIAL CITY
AREA:
ITEM NO:
WEIGHT:
NAME:
DATE
PLANNED LEVEL
LEVEL/DIFFERENCE LEVEL/DIFFERENCE 0°
90°
180°
PLUMB
270°
BOTTOM
MIDDLE
ORIENTATION ORIENTATION TOP
A
B
C
SIGN D
TCM
TSKJN
180° 270°
TOLERANCE
LEVEL :
: _________________ _________________
PLUMB :
: _________________ _________________
ORIENTATION:_________________
GAM-QCR-QAC GAM-QCR-QAC-GTL-1 -GTL-116 16
PAGE 1 OF 2
THE SETTLEMENT OF THE ABOVE EQUIPMENT HAS BEEN SATISFACTORILY COMPLETED IN ACCORDA NCE WITH THE DRAWINGS AND SPECIFICATIONS (PA INTING AND INSTAL LATION LA TION EXCEPTION). REMARKS: -----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
ORGANIZATIONS
NAME
DATE
SIGNATURE
GAMA
LINDE
QSGTL or its PMC
GAM-QCR-QAC GAM-QCR-QAC-GTL-1 -GTL-116 16
PAGE 2 OF 2
THE SETTLEMENT OF THE ABOVE EQUIPMENT HAS BEEN SATISFACTORILY COMPLETED IN ACCORDA NCE WITH THE DRAWINGS AND SPECIFICATIONS (PA INTING AND INSTAL LATION LA TION EXCEPTION). REMARKS: -----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
ORGANIZATIONS
NAME
DATE
SIGNATURE
GAMA
LINDE
QSGTL or its PMC
GAM-QCR-QAC GAM-QCR-QAC-GTL-1 -GTL-116 16
PAGE 2 OF 2
C2 ASU PEARL GTL PROJECT RAS LAFFAN INDUSTRIAL CITY
Q A A T T A A R
PUMP INSTALLATION PROCESS SHEET
Item No:
Report No:
Item Description:
Date:
Drawing No:
Area:
Item No
Description
1.
Foundation complete, Level & Accepted.
2.
Pump & driver set
3.
Base anchor bolts tight
4.
Grouted
5.
7.
Coupling set screws tight & jacking screws removed Piping connections complete with no objectionable loads or strains on the flanges Verify piping pressure test acceptance before final alignment
8.
Coupling check
9.
Rotate driver & pump with coupling open
10.
Alignment complete complete
11.
Jacking screws removed Mechanical seals or packing installed Shafts turn freely, by hand
6.
12. 13.
Signature & Date Gama Linde QSGTL
C2 ASU PEARL GTL PROJECT RAS LAFFAN INDUSTRIAL CITY
Q A A T T A A R
PUMP INSTALLATION PROCESS SHEET
Item No:
Report No:
Item Description:
Date:
Drawing No:
Area:
Item No
Description
Signature & Date Gama Linde QSGTL
1.
Foundation complete, Level & Accepted.
2.
Pump & driver set
3.
Base anchor bolts tight
4.
Grouted
5.
7.
Coupling set screws tight & jacking screws removed Piping connections complete with no objectionable loads or strains on the flanges Verify piping pressure test acceptance before final alignment
8.
Coupling check
9.
Rotate driver & pump with coupling open
10.
Alignment complete complete
11.
16.
Jacking screws removed Mechanical seals or packing installed Shafts turn freely, by hand Coupling lubed & closed Accessories Installed & Ready for service, guards Vents, Drains, sample connection, strainers, etc.) Oil rings in & free
17.
Auxiliary system system complete complete (i.e. seal flush, flush, water cooling, cooling, etc.) etc.)
6.
12. 13. 14. 15.
18.
Temporary suction screens in place
19.
Cleanliness checked 20. Coupling guard secure Remarks: The Installation of the above compressor has been satisfactorily completed in accordance with the Drawings & Specifications ORGANIZATIONS
DATE
NAME
SIGNATURE
GAMA QATAR REP LINDE REP QSGTL REP GAM-QCR-QAC-GTL-120
REPORT NO.:
REPORT NO.:
SITE INSPECTION REPORT PROJECT:
DATE:
C2 ASU PEARL GTL PROJECT –RAS LAFFAN INDUSTRIAL CITY
Originator
Date of observation:
Location / Area:
Unit No :
Discipline:
SYSTEM NUMBER:
Drawing / Specification Numbers
Description of Discrepancy/Observation (Be specific, events, time, date, location, etc :)
Corrective Action:
Originator: Name: _______________________ _____________________________Signature: ______Signature: _____________________Date: _____________________Date: ________________ NCR Required
YES
NO
(Circle one)
CTQ to Contractor Required
YES
NO
(Circle one)
Remarks if any:
Site Engineer:
Name:
_______________________ Signature: ________________ Date: ______________
QA/QC Manager: Name:
_________________________ _____________________ ____ Signature: _______________ Date: ______________
Discrepancy Corrected/Remarks:
GAMA Representative:
Name: ____________________
Close-out of Corrective Action - Remarks:
Site Engineer:
Name:
Signature:
______________ Date: ________________
NCR No.: ___________________
___________________
Signature: __________________ Date: ___________
DISTRIBUTION (Original QA/QC file)
QA/QC Manager
Site Manager
Site Engineer
Project Manager
Construction Manager
Originator
GAM-QCR-QAC-GTL-127
CTQ No: ______________
C2 ASU PEARL GTL PROJECT RAS LAFFAN INDUSTRIAL CITY
Q AA TT AA R
GENERAL PUNCH LIST
Sub contractor Ref:
Report No:
Item Description:
Inspection Date:
Item Location / Area:
SYSTEM NUMBER:
Sub System:
TAG NUMBER:
Ref Dwg/Documents:
LOOP FOLDER:
EQUIPMENT
ITE ITEM NO NO
ISO ISO or or DW DWG NU NUMBER
CIVIL
STRUCTURAL
DESCRIPTION OF WORK
PAINTING
COMPLETED(Date/Initials)
PRIORITY/ CATEGORY (A,B,C,D,E) (X,Y,Z)
INSULATION
GAMA
LINDE
QSGTL or its PMC
ALL PRIORITY A ITEMS SHOWN ABOVE HAVE BEEN VERIFIED AND ARE COMPLETED .INCOMPLETE PRIORITY B ITEMS WILL BE TRANSFERRED TO THE MECHANICAL COMPLETION PUNCH LIST PRIORITY A : ITEMS SHALL BE C OMPLETED BEFORE MECHANICAL COMPLETION (MC) PRIORITY B : ITEMS MAY BE COMPLETED AFTER MC PRIORITY C : ITEMS WILL BE COMPLETED BEFORE SYSTEM RFSU (READY FOR START UP UNIT) IS ACHIEVED PRIORITY D : ITEMS SHALL BE COMPLETED BEFORE RFSU IS ACHIEVED PRIORITY E : ITEMS SHALL BE C OMPLETED BEFORE ACCEPTENCE IS ACHIEVED CATEGORY X: CONSTRUCTION GROUP IS RESPONSIBLE FOR COMPLETION OF ITEM. CATEGORY Y: ENGINEERING INPUT IS REQUIRED FOR COMPLETION OF ITEM. CATEGORY Z: COMMISSIONING GROUP IS RESPONSIBLE FOR COMPLETION OF ITEM.
ORGANIZATIONS B D E T B E C C A
DATE
NAME
GAMA REP LINDE REP QSGTL or its PMC GAM-QCR-QAC-GTL-128
C2 ASU PEARL GTL PROJECT RAS LA FFAN INDUSTRIAL INDUSTRIAL CITY
SIGNATURE
C2 ASU PEARL GTL PROJECT RAS LA FFAN INDUSTRIAL INDUSTRIAL CITY
Q A A T T A A R
MECHANICAL EQUIP EQUIPMENT MENT ALIGNME AL IGNMENT NT REPORT
ITEM NO
REPORT NO
COUPLING MANUFACTURER
DATE:
COUPLING TYPE
AREA
COUPLING GAP
UNIT NO
PRELIMINARY ALIGNMENT (BEFORE PIPING CONNECTED): DRIVER
DRIVEN
AXIAL
DATE:
TOTAL DIAL INDICATOR READINGS
TIME:
TEMP:
SIGNED : GAMA
NAME
DATE:
LINDE
NAME
DATE:
QSGTL or its PMC
NAME
DATE:
SIGNED :
SIGNED :
COLD ALIGNMENT (AFTER PIPING CONNECTED) : DRIVER
AXIAL
DATE:
DRIVEN
TOTAL DIAL INDICATOR READINGS
TIME:
TEMP:
SIGNED : GAMA
NAME
DATE:
LINDE
NAME
DATE:
QSGTL or its PMC
NAME
DATE:
SIGNED :
SIGNED :
GAM-QCR-QAC-GTL-132
C2 ASU PEARL GTL PROJECT RAS LA FFAN INDUSTRIAL INDUSTRIAL CITY
Q A A T T A A R
Equipment Box-Up Accept ance Shee Sheett
Report No: Date: Area:
It is hereby certified that the Equipment referenced referenced has been mechanically mechanically comp leted in accordance with Drawings, Specifications, Inspection and Test Records. The referenced Equipment is ready for box-up. Equipment No Equipment Designation Designation Vendor / Manufacturer PID No
Acc ept ed GAMA
C h ec k l i s t
2
Name Plate, CE-marking (if applicable) Internals Internals installed
3
Internal Internal pipin g installed
4
Fillings completed
5
Refractory completed
6
Internal Internal tr ansport prot ection removed
7
Equipment internally clean and dry
8
Nozzles Nozzles / manholes clos ed acc. drawing
9
Specified Specified bli nd fl anges installed
10
Specified nozzle gaskets installed
11
Specified Specified bolts and nuts in stalled
12
Specified Specified to rques applied
13
Bolts lubricated (covers, manholes)
1
Accep Ac cep ted VENDOR
Acc ept ed Acc ept ed LINDE QSGTL
14
Remarks /
ORGANIZATIONS GAMA VENDOR LINDE QSGTL or its PMC GAM-QCR-QAC-GTL-133
NAME
DATE
SIGNATURE