Vulcan Gantt Scheduler : Contents
Page 1 of 44
Home > Home > Vulcan Gantt Scheduler
Vulcan Gantt Scheduler Scheduler Note This Note This section contains information about the Vulcan Gantt Scheduler application. For more information about the Gantt options in Envisage, see theGantt theGantt section section of the documentation.
Overview This section provides an overview of the Vulcan Gantt Scheduler feature.
Opening Vulcan Gantt Scheduler This section includes instructions for opening the Gantt Scheduler.
Gantt Scheduler Interface The Gantt Scheduler interface is comprised of several sections, including the ribbon and tabs, the Gantt Chart area, the Summary Report area, and the Notification Center area.
Home Tab The Home tab Home tab of the Gantt Scheduler interface includes options for creating, modifying, and aligning activities displayed in the Gantt chart.
Precedences Tab The Precedences tab Precedences tab includes options for creating, modifying, and removing precedences, as well as creating, selecting, and managing precedence groups.
Resources Tab The Resources tab Resources tab includes options for allocating, applying, and leveling resources and modifying resource settings.
Setup Tab The Setup tab Setup tab includes options for modifying settings, periods, and summary reports.
View Tab The View tab View tab includes options for viewing activities in Envisage as well as filtering, grouping, and sorting activities.
Keyboard Shortcuts This topic includes a list of keyboard shortcuts for the Vulcan Gantt Scheduler.
Need more help? Go to www.maptek.com/support www.maptek.com/support to to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > > Overview
Vulcan Gantt Scheduler Scheduler The Vulcan Gantt Scheduler is is a rate-based Gantt chart scheduler with a suite of tools for attributing, sequencing, animating, resource levelling, and reporting mine plans. Activity durations can be calculated from inherent design properties such as length, volume, or area or from other attributes associated with the design such as mass or fixed time. The main component of the Gantt Scheduler is the Gantt chart type display which includes a data side and a bar chart side. It allows users to define activities (tasks), which are in general related to 3D graphical representation of mine entities. Activities are assigned start and end dates for completion as well as precedence information from other 3D activities or types of activities for the same 3D representation. Those activities will have a series of associated fields with information that will be used in order to drive the schedule and for reporting purposes. Users will be able to create new fields with derived information.
Requirements n n
n
You must have Vulcan installed on your computer and Envisage must be open in order to use the Gantt Scheduler. You must have a valid Gantt Scheduler license for Vulcan. If the Gantt menu option is not displayed in Envisage, contact your local Maptek office to obtain a license for the Gantt Scheduler. You must have Java installed on your computer to use the Gantt Scheduler. If you do not have Java installed already, you can download the latest version at www.java.com www.java.com..
Gantt Scheduler Tutorials Click to view Gantt Scheduler tutorials
Need more help? Go to www.maptek.com/support www.maptek.com/support to to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > > Opening the Gantt Scheduler
Opening the Gantt Scheduler
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 2 of 44
Following are instructions on how to open the Gantt Scheduler from within Envisage Envisage..
Instructions In Envisage, on the Gantt menu, Gantt menu, click Open to Open to open the Gantt Scheduler application and display the Vulcan Gantt Scheduler interface Scheduler interface.. For more information about the Gantt options in Envisage, see the Gantt Gantt section section of the documentation.
Need more help? Go to www.maptek.com/support www.maptek.com/support to to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Home > Vulcan Gantt Scheduler > > Gantt Scheduler Interface
Gantt Scheduler Interface The Gantt Scheduler interface is comprised of several sections, including the ribbon and tabs, tabs, the Gantt Chart area, area, the Summary Report area, area, the Notification Center area, area, and the Quick Access Toolbar .
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 2 of 44
Following are instructions on how to open the Gantt Scheduler from within Envisage Envisage..
Instructions In Envisage, on the Gantt menu, Gantt menu, click Open to Open to open the Gantt Scheduler application and display the Vulcan Gantt Scheduler interface Scheduler interface.. For more information about the Gantt options in Envisage, see the Gantt Gantt section section of the documentation.
Need more help? Go to www.maptek.com/support www.maptek.com/support to to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Home > Vulcan Gantt Scheduler > > Gantt Scheduler Interface
Gantt Scheduler Interface The Gantt Scheduler interface is comprised of several sections, including the ribbon and tabs, tabs, the Gantt Chart area, area, the Summary Report area, area, the Notification Center area, area, and the Quick Access Toolbar .
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 3 of 44
Maptek File Button, File Menu, and Application Options The File menu includes options to create a new project, open an existing project, save a project, and exit the Gantt Scheduler. In addition, you can set application preferences such as language, scheduler start date, and date and time formats.
Quick Access Toolbar The Quick Access Toolbar provides shortcuts to commonly used commands and the ability to minimize the ribbon.
Ribbon and Tabs The Gantt Scheduler interface includes a ribbon along the top of the interface. The ribbon includes tabs for creating and modifying activities, precedences, resources, setup, and viewing.
Gantt Chart Window Area The Gantt Chart window is the visual display of the scheduling information for the project. It includes an Activity Grid area with activity and setting information, a Gantt Chart area which serves as a visual chart with timeline and precedence information, and an Overview area which includes a visual overview of all activity information over the entire timeline of the project.
Summary Report Window The Summary Report window displays report information that is generated from report specifications created in the Summary Report Manager (accessed via the theReport Report Setup option on the Setup tab). The Summary Report shows values for filtered activities in the grid.
Notification Center Window The Notification Center window displays information and notifications regarding actions in the Gantt Scheduler. Notification types include logs, warnings, errors, and resolved issues.
Need more help? Go to www.maptek.com/support www.maptek.com/support to to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > > Gantt Scheduler Interface > File Menu and Application Options
Maptek File Button, File Menu, and Application Options The Gantt Scheduler includes a Maptek File button in the top left corner of the interface. This button displays the File menu which includes options to create a new project, open an existing project, save a project, and exit the Gantt Scheduler. Click Options on the File menu to display the Options panel to set application preferences such as language, scheduler start date, and date and time formats. Maptek File Button
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 4 of 44
Click the Maptek File button to display the File menu.
Menu Options New Click New to create a new project. Open Click Open to open an existing project. You can also open a project by clicking on the file name in the Recent Projects column. Save Click Save to save the project that is currently open. Save As Click Save As to save the project that is currently open with a different name. Options Click Options to display the Options panel.
General Language Select your preferred language from the list. Scheduler Start for new activities Select Project Start Start Day or Current Day to specify what the default start day should be for new activities. Date/Time Format Format Select your preferred date and time format. Layout Overwrite project layout Select this check box to overwrite the default project layout with the current layout. Save Layout Click Save Layout to save the current layout as the default layout for the project. Automatic Backup Number of backups Enter the number of backups you want to keep Backup every
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 5 of 44
Enter the number of minutes you want between backups.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Gantt Scheduler Interface > Quick Access Toolbar
Quick Access Toolbar The Gantt Scheduler interface includes a Quick Access Toolbar along the top title bar of the interface. The Quick Access Toolbar includes shortcuts for the Copy and Paste options. You can also customize the toolbar or use it to minimize the ribbon.
Customizing the Quick Access Toolbar Click the drop-down arrow icon and click Show Below the Ribbon to move the Quick Access Toolbar below the ribbon. To move it back above the ribbon, click the drop-down arrow icon and click Show Above the Ribbon. Minimizing the Ribbon Click the drop-down arrow icon and click Minimize the Ribbon to hide the icons and labels on the ribbon. When the ribbon is minimized, only the tab names will display. To display the ribbon, click the drop-down arrow icon and click Minimize the Ribbon again.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Gantt Scheduler Interface > Ribbon and Tabs
Ribbon and Tabs The Gantt Scheduler interface includes a ribbon along the top of the interface. The ribbon includes tabs for creating and modifying activities, precedences, resources, setup, and viewing. Alternatively, you can right-click on an activity in the Gantt Chart window to view the options for that activity or use keyboard shortcuts for some options.
For information about the options on each tab of the Gantt Scheduler, see the following topics: n
Home tab
n
Precedences tab
n
Resources tab
n
Setup tab
n
View tab
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Gantt Scheduler Interface > Gantt Chart Window
Gantt Chart Window The Gantt Chart window is the visual display of the scheduling information for the project. It includes the following components: n
Activity Grid area with activity and setting information
n
Gantt Chart area which serves as a visual chart with timeline and precedence information
n
Overview area which includes a visual overview of all activity information over the entire timeline of the project
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 6 of 44
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Gantt Scheduler Interface > Summary Report Window
Summary Report Window The Summary Report window displays report information that is generated from report specifications created in theSummary Report Manager , which is accessed via the Report Setup option on the Setup tab.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Gantt Scheduler Interface > Notification Center Window
Notification Center Window The Notification Center window displays information and notifications regarding actions in the Gantt Scheduler. Notification types include logs, warnings, errors, and resolved issues. n
Select which notification types to display from the Show drop-down list.
n
Click Clear
to clear all notifications from the list.
n
Click the Save
icon to save all displayed notifications to a text file.
n
Click the Expand
and Collapse
icons to view more or less information about a notification.
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 7 of 44
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Home
Home Tab The Home tab of the Gantt Scheduler interface includes options for creating, modifying, and aligning activities displayed in the Gantt chart. Alternatively, you can right-click on an activity in the Gantt Chart area to view the options for that activity or use keyboard shortcuts for some options.
Clipboard The Clipboard group on the Home tab includes options for copying and pasting activities in the Gantt Chart window.
Activities The Activities group on the Home tab includes options for creating, deleting, modifying, and updating activities in the Gantt Chart area.
Bars The Bars group on the Home tab includes options for splitting bars and removing splits in the Gantt Chart area.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Home > Clipboard
Clipboard The Clipboard section of the Home tab includes options for copying and pasting activities in the Gantt Chart window.
Copy activity Click Copy activity or press Ctrl + C to copy the data values for the selected activity to the clipboard.
Copy with Headers
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 8 of 44
Click Copy with Headers to copy the data values and attribute name of the selected activity to the clipboard.
Paste activity Click Paste activity or press Ctrl + V to paste the selected activity into the Gantt chart.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Home > Activities
Activities The Activities group on the Home tab includes options for creating, deleting, modifying, and updating activities in the Gantt Chart window. Note: You must set up attributes prior to creating activities. See the Attributes topic for more information.
New Click New or press Shift+A to add a new activity. The Activity Information panel displays.
Delete activity Click Delete activity or press Ctrl+D to delete an activity.
Properties Click Properties or press F4 to view the activity properties on the Activity Information panel.
Update Activities Click Update Activities or press Ctrl+U to update activities with Envisage data. The Updating activities progress bar displays in the bottom right corner of the Gantt Status Bar to indicate the progress of the update.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Home > Activities > New
Activity Information Use the Activity Information panel to add and modify activity information. This panel includes general activity information as well as information about precedences, scheduling constraints, and resource allocation and rates. Note You must set up attributes prior to creating activities. See the Attributes topic for more information.
Tutorials Click to read the Creating Activities and Viewing and Interacting with Activities tutorials.
Instructions On the Home tab, in the Activities group, click New to create a new activity, or Properties to view the properties of an existing activity. This panel has two tabs: the General tab and the Resources tab.
General Tab
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 9 of 44
General This section includes general information about the activity and its progress. Name Enter the name of the activity. Is summary Select this check box if the activity is a summary. Start Enter or select a start date for the activity. End Enter or select an end date for the activity. Work Enter the number of days the activity is expected to take to complete. Percent Completed Enter the percentage of work that has been completed for the activity. Priority Enter a number to indicate the priority of the activity. Predecessors This section displays information about any predecessors that are linked to the activity. For more information about precedences, seePrecedence Information. Predecessor Displays the predecessor's name. Type Select whether the activity should be linked to the start or finish of the predecessor. You may selectStart to Start, Finish to Finish, Start to Finish, or Finish to Start. Lag Enter the number of days that must separate the activity from the predecessor. Successors This section displays information about any successors that are linked to the activity. For more information about precedences, seePrecedence Information. Successor Displays the successor's name.
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 10 of 44
Type Select whether the activity should be linked to the start or finish of the successor. You may select Start to Start, Finish to Finish, Start to Finish, or Finish to Start. Lag Enter the number of days that must separate the activity from the successor. Scheduling Constraint This section specifies any scheduling or time constraints for the activity. Constraint type Select a scheduling constraint type to indicate how early or late the activity can start or finish. You can specify whether the activity must start or finish on/before/after a specific date, or you can specify that the activity should begin as soon or as late as possible. Constraint date Select a date to correspond with the Constraint type you selected. This box is disabled if you select As Soon As Possible or As Late As Possible as the Constraint type. Click the Resources tab to continue.
Resources Tab
Resource Allocation This section includes any resources that are allocated to the activity. For more information about resource settings and allocation, seeResources and Allocate Resources. Resource Select the name of the resource from the list. For more information about adding or modifying resources, see Resource Settings. Rate Displays the rate of the selected resource. Rate This section indicates the rate of the resources that are allocated to the activity. Activity rate Enter the activity rate. Combined resource rate Displays the sum of the rates from all resources that are allocated to the activity. Resource manual rate Enter the manual rate of the resources. Source Select a source from the list to display its current rate. Current rate Displays the current rate of the source selected from the Source list.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
Copyright© 2015 Maptek Pty Limited
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 11 of 44
Home > Vulcan Gantt Scheduler > Home > Bars
Bars The Bars group on the Home tab includes options for splitting bars and removing splits in the Gantt Chart area.
Split Use the Split option to split an activity by date, number of days, or percentage.
Remove Split Use the Remove Split option to remove a split from an activity.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Home > Bars > Split
Split Activity Use the Split Activity panel to split an activity by date, number of days, or percentage.
Instructions In the Gantt Chart area, click on the bar that represent the activity that you want to split, then on the Home tab, in the Bars group, click Split to display the Split Activity panel.
You can split the activity in one of three ways: by date, number of days, or percentage. When you modify one number or date on the panel, the others will adjust according to you value you entered. To split the activity at a specific day, enter a date and time or click the arrow icon
to select the date from the calendar.
To split the activity by number of days, enter the number of days into the activity that the split should occur. To split the activity by percentage, enter the percentage of time into the activity that the split should occur.
Examples: You have an activity that you want to split in half. The activity is scheduled for 30 days from July 1st to July 31st. l
To split the activity by date: Enter or select July 15th in the date format from your preferences (such as 07/15/2014 or 15/07/2014).
l
To split the activity by number of days: Enter 15.
l
To split the activity by percentage: Enter 50.00%.
You can remove a split in three different ways: l
Click on the bar in the Gantt Chart area, then on the Home tab, in the Bars group, click Remove Split.
l
Click on the bar in the Gantt Chart area, then press Ctrl+J.
l
Right-click on the activity's bar in the Gantt Chart area and click Remove Split.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Home > Bars > Remove Split
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 12 of 44
Remove Split Use the Remove Split option to remove a split from an activity.
Instructions You can remove a split in three different ways: n
Click on the bar in the Gantt Chart area, then on the Home tab, in the Bars group, click Remove Split.
n
Click on the bar in the Gantt Chart area, then press Ctrl+J.
n
Right-click on the activity's bar in the Gantt Chart area and click Remove Split.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Precedences
Precedences Tab The Precedences tab includes options for creating, modifying, and removing precedences, as well as creating, selecting, and managing precedence groups. Alternatively, you can right-click on an activity in the Gantt Chart window to view the options for that activity or use keyboard shortcuts for some options.
Gantt Manual The Gantt Manual group is located on the Precedences tab and includes options for creating and removing manual precedences, as well as viewing manual precedence properties.
Envisage Spatial The Envisage Spatial group is located on the Precedences tab and includes options for creating, editing, and removingspatial precedence rules.
Precedence Group The Precedence Group group is located on the Precedences tab and includes options for adding and managing precedence groups as well as selecting current precedence groups.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Precedences > Gantt Manual
Gantt Manual The Gantt Manual group is located on the Precedences tab of the ribbon in the Gantt Scheduler. It includes options for creating and removing manual precedences, as well as viewing manual precedence properties.
Create Click Create to display the Allocate Precedence Group panel to create a new manual precedence.
Remove Click Remove to remove a manual precedence.
Properties Click Properties to view precedence properties. The Precedence Properties panel displays.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
Copyright© 2015 Maptek Pty Limited
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 13 of 44
Home > Vulcan Gantt Scheduler > Precedences > Gantt Manual > Create
Create Use the Create option to create a new manual precedence between activities.
Tutorial Click to read the Creating Precedences tutorial.
Instructions If you want to add the activities to an existing precedence group, select the group name from the Current Group list in the Precedence Group group of the Precedences tab. If a group is selected, the new precedence will automatically be added to that group. Select two or more activities in the Gantt Chart window. On the Precedences tab, in the Gantt Manual group, click Create. If you do not have a group selected in the Current Group list, the Allocate Precedence Group panel displays.
Group Type or select a precedence group name in the box and click OK. If you enter a new group name, the new group will be displayed in the Current Group list and on the Precedence Group Manager panel. A precedence is then created between the activities you specified, and the precedence is added to the selected group.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Precedences > Gantt Manual > Properties
Properties Use the Precedence Information panel to display and modify information about a selected precedence.
Instructions On the Precedences tab, in the Gantt Manual group, click Properties, or right-click on a precedence arrow Precedence Information panel.
in the Gantt Chart area and select Properties to display the
Precedence Predecessor Activity Displays the activity name of the predecessor. Successor Activity Displays the activity name of the successor. Lag Enter the number of days that must separate the activities in the precedence.
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 14 of 44
Type Select whether the precedence should be linked to the start or finish of the predecessor and successor activities. You may select Start to Start, Finish to Finish, Start to Finish, or Finish to Start. Example: Activity A and Activity B are linked together with a precedence. Activity A must be completed before Activity B can begin. You want to wait three days after completing Activity A before starting Activity B. n
Predecessor Activity : Activity A
n
Successor Activity: Activity B
n
Lag: 3 days
n
Type: Finish - Start
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Precedences > Envisage Spatial
Envisage Spatial The Envisage Spatial group is located on the Precedences tab of the ribbon in the Gantt Scheduler. It includes options for creating, editing, and removing spatial precedence rules.
Spatial Precedences Use the Spatial Precedences option to create, edit, or remove precedence rules for spatial precedences.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Precedences > Envisage Spatial > Spatial Precedences
Spatial Precedences Use the Spatial Precedence Rules panel to create, edit, or remove precedence rules for spatial precedences.
Instructions On the Precedences tab, in the Envisage Spatial group, click Spatial Precedences to display the Spatial Precedence Rules panel.
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 15 of 44
Spatial Precedence Rules Adding and Defining a New Precedence Group Click Add
to add a new entry, or press Insert.
Modifying a Precedence Group Select an entry and modify the displayed information as needed. Copying a Precedence Group Select an entry and click Copy
to create a copy of the selected entry or press Ctrl+C.
Removing a Precedence Group Select an entry and click Remove
to remove the selected entry or press Delete. The entry can only be removed if it is not being used in the project.
Moving a Precedence Group Select an entry and click Up
or Down
to move the entry up or down in the list, or press Ctrl+Up Arrow or Ctrl+Down Arrow.
General Name Enter a name for the report. Description Enter a brief description of the report. General Name Enter the name of the rule. Description Enter a description of the rule. Activities Filter Predecessor Activities Filter Select a filter for the predecessor activities. Predecessor Activity Type Select an activity type for the predecessor activities. Successor Activities Filter Select a filter for the successor activities. Successor Activity Type Select an activity type for the successor activities. Search Criteria Predecessor Point Selection Select Start Point, End Point, or Closest Intersection to indicate the method of point selection of the predecessor. Optional Offset
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 16 of 44
Enter a value for the offset and then select the unit of measure from the list. The closest intersection and optional offset allow the Gantt bars to be split and precedences created between parts of activities. The optional offset only works for design data and is in reference to the nominated point (start, end, or closest intersection). Successor Point Selection Select Start Point or End Point to indicate the method of point selection of the predecessor. Optional Offset Enter a value for the offset and then select the unit of measure from the list. The closest intersection and optional offset allow the Gantt bars to be split and precedences created between parts of activities. The optional offset only works for design data and is in reference to the nominated point (start, end, or closest intersection). Precedence Creation Closest (Single) or All (Multiple) Select the method of precedence creation. Gantt Precedence Type Select the Gantt precedence type from the list. Precedence Lag If there is a lag between the predecessor and successor, enter the time and select the unit of measure from the list. Apply Rule Click Apply Rule to apply rule changes to precedences.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Precedences > Precedence Group
Precedence Group The Precedence Group group is located on the Precedences tab of the ribbon in the Gantt Scheduler. It includes options for adding and managing precedence groups as well as selecting current precedence groups.
Group Manager Click Group Manager to display the Precedence Group Manager panel to add, edit, and remove precedence groups.
Current Group Select a precedence group from the drop-down list to set it as the current group.
New Group Click New Group to display the Allocate Precedence Group panel to create a new precedence group.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Precedences > Precedence Group > Group Manager
Group Manager Use the Precedence Group Manager panel to add, edit, and remove precedence groups.
Instructions On the Precedences tab, in the Precedence Group group, click Group Manager to display the Precedence Group Manager panel.
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 17 of 44
Groups Adding and Defining a New Precedence Group Click Add
to add a new entry, or press Insert.
Modifying a Precedence Group Select an entry and modify the displayed information as needed. Copying a Precedence Group Select an entry and click Copy
to create a copy of the selected entry or press Ctrl+C.
Removing a Precedence Group Select an entry and click Remove
to remove the selected entry or press Delete. The entry can only be removed if it is not being used in the project.
Moving a Precedence Group Select an entry and click Up
or Down
to move the entry up or down in the list, or press Ctrl+Up Arrow or Ctrl+Down Arrow.
General Name Enter a name for the group. Description Enter a brief description of the group. Properties Is Current Select this check box to make this precedence group the current group. Applied Select this check box if you want the precedences from this group to be applied. Clear this check box if you do not want the precedences from this group to be applied. Line Style Select a line style for the precedence. This line style will be used for the precedence in the Gantt Chart area. Line Color Select a color for the precedence. This line color will be used for the precedence in the Gantt Chart area. Precedences Remove Selected Highlight activities in the list and then click Remove Selected to remove the activities from the precedence group. Predecessors Displays the predecessor of the activity. Successors Displays the successor of the activity.
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 18 of 44
Lag [Day] Displays the lag time between the precedences. Type Displays the type of precedence, such as Finish-Start or Start-Finish. Source Displays the source of the precedence, such as whether the precedence was created in the Gantt Scheduler or in Envisage.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Precedences > Precedence Group > New Group
New Group Use the Allocate Precedence Group panel to create a new precedence group.
Instructions On the Precedences tab, in the Precedence Group group, click New Group to display the Allocate Precedence Group panel.
New Group Enter a group name in the field and click OK. The new group will be displayed in the Current Group list and in the Group Manager.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Resources
Resources Tab The Resources tab includes options for allocating, applying, and leveling resources and modifying resource settings. Alternatively, you can right-click on an activity in the Gantt Chart area to view the options for that activity or use keyboard shortcuts for some options.
Resources The Resources group includes options for managing and allocating resources.
Resource Leveling The Resource Leveling group includes options for managing leveling and resource rates.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] . Envisage
Copyright© 2015 Maptek Pty Limited
Maptek
Home > Vulcan Gantt Scheduler > Resources > Resources
Resources The Resources section of the Resources tab includes options for creating, modifying, deleting, and allocating resources.
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 19 of 44
Settings Click Settings to display the Resources panel. This panel has options to add, modify, or remove resource definitions.
Allocate resources Click Allocate resources display the Allocate Resources panel. This panel includes options for allocating resources to selected activities.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Resources > Resources > Settings
Resource Settings Use the Resources panel to add, modify, or remove resource definitions.
Instructions: On the Resources tab, in the Resources group, click Settings to display the Resources panel. Alternatively, you can press Ctrl+F10 to display the panel.
Resources Adding and Defining a New Resource Click Add
to add a new entry, or press Insert.
Modifying a Resource Select an entry and modify the displayed information as needed. Copying a Resource Select an entry and click Copy
to create a copy of the selected entry or press Ctrl+C.
Removing a Resource Select an entry and click Remove
to remove the selected entry or press Delete. The entry can only be removed if it is not being used in the project.
Moving a Resource Select an entry and click Up
or Down
to move the entry up or down in the list, or press Ctrl+Up Arrow or Ctrl+Down Arrow.
General
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 20 of 44
Name Enter the name of the resource. Description Enter a description of the resource. Calendar Select a calendar to use for scheduling the resource. Modify Click Modify to modify the selected calendar. Rate Default Rate Enter the default rate for the resource. This rate applies to all activity types for the resource. If you make changes to this value, click Apply rate to apply the rate change. Use variable rate Select this check box to use different rates for different activity types. If you select this option, you can specify a rate for different activity types by selecting the activity type from the Activity Type list and entering a rate in the Rate box. If you do not specify a rate for an activity type, the default rate will be used for that activity type. The Unit box displays the unit type for that activity type. Capacity Default capacity Enter the default capacity for the resource. This capacity applies to all days for the resource. Use variable capacity Select this check box to use different capacities on different days. If you select this option, you can select a start date for the capacity in the Start column and enter the capacity in the Capacity column. This capacity will apply until the next specified start date in the list. If you do not specify a rate for a date, the default capacity will be used for that date.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Resources > Resources > Allocate Resources
Allocate Resources Use the Allocate Resources panel to allocate resources to selected activities.
Tutorial Click to read the Resource Allocation and Leveling tutorial.
Instructions On the Resources tab, in the Resources group, click Allocate resources to display the Allocate Resources panel. Alternatively, you can press Alt+F10 to display the panel.
Resources
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 21 of 44
Allocating a Resource Click Add
to allocate the selected resource to the activity.
Removing a Resource Click Remove
to remove the selected resource from the activity.
Activities Activity Displays the name of the activity. Allocated Resources Displays the resources that have been allocated to the activity. Rate Source Displays the rate source of the activity. Rate Displays the rate of the activity. Rate Source Select Activity Manual, Resource Default, or Resource Manual, Partial Series, or Partial Parallel as the rate source. User defined rate If you select Resource Manual in the Rate Source list, enter a rate for the activity. Activity % If you select Partial Series or Partial Parallel in the Rate Source list, enter the activity percentage. Apply rate Click Apply rate to save your changes and apply the updated rate source, user-defined rate, and activity percentage to the activities.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Resources > Resource Leveling
Resource Leveling The Resource Leveling section of the Resources tab includes options for specifying and applying resource rates and leveling.
Apply Resource Rate Click Apply Resource Rate or press Alt+F11 to apply the default resource rate to the selected activities.
Leveling Setup Click Leveling Setup or press Alt+L to display the Resource Leveling Setup panel. This panel includes options for setting step, date range, priorities, and other options for resource leveling.
Leveling by Capacity Click Leveling by Capacity or press Alt+Y to resolve resource over-allocations based on the settings in the Resource Leveling Setup panel.
Leveling by Rate and Capacity Click Leveling by Rate and Capacity or press Alt+R to resolve resource over-allocations based on the settings in the Resource Leveling Setup panel.
Clear Leveling Delays Click Clear Leveling Delays or press Alt+C to clear the leveling delay from all activities.
Tutorial Click to read the Resource Allocation and Leveling tutorial.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Resources > Resource Leveling > Leveling Setup
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 22 of 44
Leveling Setup Use the Resource Leveling Setup panel to set step, date range, priorities, and other options for resource levelling.
Instructions On the Resources tab, in the Resource Leveling group, click Leveling Setup to display the Resource Leveling Setup panel. Alternatively, you can press Alt+L to display the panel.
Leveling Range Entire Project Select this option to apply resource levelling to the entire project. Date Range Select this option to apply resource levelling only to a specified date range. If you select this option, select the start and finish dates in the Start and Finish boxes. Activity Prioritization Type Select the attribute type by which to prioritize activities from the list. Ascending or Descending Select Ascending or Descending to indicate whether the attributes should be sorted in ascending or descending order. Add Click Add to add the selected attribute to the list. Up Click the Up
icon to move a selected entry up one row in the list.
Down Click the Down
icon to move a selected entry down one row in the list.
Attribute Indicates the attribute name for the entry. Mode Indicates whether the selected attribute is sorted in ascending or descending order. Remove Click Remove to remove the entry from the list. Clear last levelling values Select this check box if you want to clear previous levelling values.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Setup
Setup Tab The Setup tab includes options for modifying settings, periods, and summary reports.
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 23 of 44
Alternatively, you can right-click on an activity in the Gantt Chart area to view the options for that activity or use keyboard shortcuts for some options.
Settings The Settings group is located on the Setup tab of the ribbon in the Gantt Scheduler. It includes options for setting general project options as well as creating, modifying, and removing attributes, activity types, lookup tables, and calendars.
Period The Period group is located on the Setup tab of the ribbon in the Gantt Scheduler. It includes options for selecting and modifying period definitions.
Summary Report The Summary Report group is located on the Setup tab of the ribbon in the Gantt Scheduler. It includes options for setting up reports and exporting reports to CSV files.
Formula Editor Use the Formula Editor panel to assist in creating formulas and expressions for activity attributes.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Setup > Settings
Settings The Settings group is located on the Setup tab of the ribbon in the Gantt Scheduler. It includes options for setting general project options as well as creating, modifying, and removing attributes, activity types, lookup tables, and calendars.
Project Options Click Project Options to display the Project Options panel to define options for the current project.
Attributes Click Setup to display the Attribute Manager panel to add, modify, and remove activity attributes.
Activity Types Click Activity Types to display the Activity Types panel to add, edit, and delete activity types.
Lookup Tables Click Lookup Tables to display the Lookup Tables panel to add, modify, or remove lookup table definitions.
Calendars Click Calendars to display the Calendar Manager panel to define working and non-working times for the project.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Setup > Settings > Project Options
Project Options Use the Project Options panel to define options for the current project.
Instructions On the Setup tab, in the Settings group, click Project Options to display the Project Options panel.
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 24 of 44
General Name Enter a name for the project. Title Enter a title for the project. Subject Enter a subject for the project. Category Enter a category for the project. Company Enter the company name. Mine Enter the mine name. Site Enter the site name. Manager Enter the manager name. Author Enter the author name. Time and Date Start date Displays the date the project was created. Finish date Select or enter a finish date for the project. The finish date defaults to the last day of the last scheduled activity. Schedule from Select Project Start Date or Project Finish Date to specify how to schedule the project. Calendar Select the default project calendar from the list. Project duration format Select the format for the project duration. You can select Minute, Hour, Day, Week, or Month. Work format Select the format for work. You can select Minute, Hour, Day, Week, or Month.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Setup > Settings > Attributes
Attributes Use the Attribute Manager panel to add, modify, and remove activity attributes. Note Attributes must be set up before activities can be created. For information about attribute default values, see the Default Values for Attributes topic.
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 25 of 44
Instructions On the Setup tab, in the Settings group, click Attributes to display the Attribute Manager panel.
Attributes Adding and Defining a New Attribute Click Add
to add a new entry, or press Insert.
Modifying an Attribute Select an entry and modify the displayed information as needed. Copying an Attribute Select an entry and click Copy
to create a copy of the selected entry or press Ctrl+C.
Removing an Attribute Select an entry and click Remove
to remove the selected entry or press Delete. The entry can only be removed if it is not being used in the project.
Note You cannot remove the Activity Name and Priority attributes, nor can you modify their names, descriptions, types, or units. General Name Name of the attribute used in the whole project. Description A brief description of the attribute. Type Select the attribute type from the list. Decimal Places If you selected Double in as the attribute type, enter the number of decimal places to display for the number. Units Enter the unit type. If you select Inherent in the Calculation list in the Data Source section, this box will default to the information specified in the that section. Data Source Calculation Select the type of calculation to use for the data source. Select Manual to enter the information manually. Select Expression to specify a formula for the data source. Enter the expression in the General box, or select the Separate for Design Data/Triangulation check box and enter an expression for design data in the Design Data box and an expression for triangulations in the Triangulation box. If desired, you can use theFormula Editor panel to create the formula by clicking the Formula icon. Select Inherent to use a predefined property and unit of measurement. Select Length, Volume, or Area and then specify a unit of measurement from the list to the right of the property.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
Copyright© 2015 Maptek Pty Limited
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 26 of 44
Home > Vulcan Gantt Scheduler > Setup > Settings > Default Values for Attributes
Default Values for Attributes This topic lists the default values that are used when certain activities do not have a value defined. These values are only assigned for the expression evaluation process. The default values cannot be changed. Only user-defined attributes (the [ATT:] values in the expressions) have these default values because their type is known. Any other kind of metadata value ([DGD:], [TRI:] or [MET:]) do not have a default value when the metadata value does not exist. Attribute Type
Default Value
Double
0.0
Integer
0
Boolean
False
String
(empty string)
D at e
0 0: 00 :0 0. 00 00 00 0, J an ua ry 1 , 0 00 1. ( Mo re i nf o:.NET 4.0, .NET 4.5)
The default values are used when any of the following conditions are met: l
The value of an attribute is #NULL! after evaluating the attribute expression.
l
A manually assigned attribute of an activity type does not have a user-defined default value assigned.
l
An activity type does not have an attribute.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Setup > Settings > Activity Types
Activity Types Use the Activity Types panel to add, edit, and delete activity types. Activity types are a group of activities that share a common work calculation definition. An activity type is a definition that converts an Envisage object (or triangulation) into a Vulcan Gantt activity. The activity type is defined by a quantity attribute and a default rate (to set an initial duration to the activity) and also manages the discretisation of an Envisage object, creating a group of minimum mining units. An activity type has an auto-assigned expression that can be used to assign automatically to an object. Activity groups consist of multiple activity types, sharing a common discretisation definition and operational precedence.
Instructions On the Setup tab, in the Settings group, click Activity Types to display the Activity Types panel.
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 27 of 44
Activity Types Adding and Defining a New Activity Type Click Add
to add a new entry, or press Insert.
Modifying an Activity Type Select an entry and modify the displayed information as needed. Copying an Activity Type Select an entry and click Copy
to create a copy of the selected entry or press Ctrl+C.
Removing an Activity Type Select an entry and click Remove
to remove the selected entry or press Delete. The entry can only be removed if it is not being used in the project.
Moving an Activity Type Select an entry and click Up
or Down
to move the entry up or down in the list, or press Ctrl+Up Arrow or Ctrl+Down Arrow.
General Name Name of the activity type used in the whole project. Description A brief description of the activity type. Work calculation Select Calculate Work or Fixed Work to specify a method for calculating work. Calculate Work Select this option if you want to calculate work based upon a quantity attribute. If you select this option, you must select the attribute, default rate, and units. Quantity attribute Select the attribute upon which you want to calculate work. The list will contain all attributes that have an attribute type of Double on the Attribute Manager panel. Default rate Enter an expression to use for calculating work. To use the Formula Editor panel to enter or modify the expression, click the Formula Editor
icon.
Units Select the unit types for distance and time of the calculation, such as meters per day. Fixed Work Select this option if you want to calculate work using a specific amount of time. Fixed time value Enter the amount of time of the work. Units Select the unit type for the time value from the list. Default auto assign expression Condition Enter a formula for the expression to be evaluated when Envisage objects and triangulations are selected for activity creation. To use the Formula Editor panel to enter or modify the expression, click the Formula Editor icon. If the evaluated expression is true, then the activity type is assigned to the Envisage object. Attributes In the Selected column, select the check boxes next to the applicable attributes that are listed in the Attribute column. Defining Attributes There are three possible sources to populate attribute values in the activity grid: manual, expression, and inherent. Manual Manual attributes can be edited directly in the Gantt Chart window. They can be populated by an optional default value that is defined in the activity type setup, edited individually in the Gantt Chart window, or edited in bulk with Copy and Paste in the Gantt Chart window. Expression Expression attributes are defined using the Formula Editor panel as described above. Inherent The Gantt Scheduler can inherently read the Length (design data only), Area (design data and/or triangulations), and Volume (triangulation and/or design data with assigned primitive) attributes from Envisage.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Setup > Settings > Lookup Tables
Lookup Tables
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 28 of 44
Use the Lookup Tables panel to add, modify, or remove lookup table definitions.
Instructions On the Setup tab, in the Settings group, click Lookup Tables to display the Lookup Tables panel.
Lookup Tables Adding and Defining a New Lookup Table Definition Click Add
to add a new entry, or press Insert.
Modifying a Lookup Table Select an entry and modify the displayed information as needed. Copying a Lookup Table Select an entry and click Copy
to create a copy of the selected entry or press Ctrl+C.
Removing a Lookup Table Select an entry and click Remove
to remove the selected entry or press Delete. The entry can only be removed if it is not being used in the project.
Moving a Lookup Table Select an entry and click Up
or Down
to move the entry up or down in the list, or press Ctrl+Up Arrow or Ctrl+Down Arrow.
General Name Enter a name for the lookup table definition. Description Enter a brief description of the lookup table definition. Details Key Enter text that will serve as the key for that entry in the lookup table definition. Value 1, Value 2, Value 3... Enter a value in each column. Add Click the Add
icon below the table to add a new value column to the table.
Remove Click the Remove
icon below the table to remove the last value column from the table.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page.
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Have feedback on this help topic? Share it with us at
[email protected] .
Page 29 of 44
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Setup > Settings > Calendars
Calendars Use the Calendar Manager panel to define working and non-working times for the project. You can apply a calendar to an entire project, to resources in the resource definitions, or to activities for future development.
Instructions On the Setup tab, in the Settings group, click Calendars to display the Calendar Manager panel.
Calendars Adding and Defining a New Calendar Click Add
to add a new entry, or press Insert.
Modifying a New Calendar Select an entry and modify the displayed information as needed. Copying a Calendar Select an entry and click Copy
to create a copy of the selected entry or press Ctrl+C.
The name of the new calendar will be the name of the copied calendar appended by the word copy. For example, if the original calendar name isHoliday, the new calendar created from the Copy function will be Holiday copy. Removing a Calendar Select an entry and click Remove
to remove the selected entry or press Delete. The entry can only be removed if it is not being used in the project.
Moving a Calendar Up or Down in the List Select an entry and click Up
or Down
to move the entry up or down in the list, or press Ctrl+Up Arrow or Ctrl+Down Arrow.
Calendar Specifications Name Enter a name for the calendar. Description Enter a description for the calendar. Base calendar Select this option if the calendar is not based on another calendar. Base on Select this option if the calendar is based on another calendar, and select the base calendar from the drop-down list. Any information from the chosen base calendar will be
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 30 of 44
included on the new calendar. Calendar, Legend, and Information These sections display the information for dates on the selected calendar. Days with a non-working time exception have a red background, days with modified (non-default) working time have a green background, normal working days have a light grey background, and non-working days have a dark grey background. Information about the selected day is displayed in the Information section. Default Working Time Use this section to set the default working days and times for the week. Select the check boxes next to each default working day. Clear the check boxes next to any default non-working days. Enter the default start and end times in the From and To columns using a four-digit 24-hour notation. For example, enter 06:00 for 6:00 a.m. and 13:00 for 1:00 p.m. Exceptions Use this section to define any exceptions to the default working week. See Calendar Exceptions for more information. Apply a Calendar to the Entire Project You can apply a calendar to the entire project by selecting the name of the calendar from the Calendar drop-down list on the Project Options panel.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Setup > Settings > Calendars > Calendar Exceptions
Calendar Exceptions Use the Exception panel to define any exceptions to standard working and non-working times for the project. You can specify exceptions for non-working time and for non-default working time. Exceptions may be scheduled as single or recurring events. Any dates with exceptions are displayed in theCalendar and Exceptions sections of the Calendar Manager panel.
Instructions On the Calendar Manager panel, click Add to add a new exception, highlight an entry and click Remove to remove the exception from the list, or highlight an entry and click Modify to modify an existing exception. If you click Remove, the exception will be removed from the list. If you click Add or Modify, the Exception panel displays.
General Name Enter a name for the exception. Date Enter the date of the exception in mm/dm/yyyy format or click the calendar
icon to select a date.
Type Select Nonworking for regular non-working time or select Non-default working time to specify that the exception is working time that is outside of the default schedule. If you select Non-default working time, specify the time range in the Working Time section. Working Time Enter the time range in the From and To columns using a four-digit 24-hour notation if you selected Non-default working time in the Type section. For example, enter 06:00 for 6:00 a.m. and 13:00 for 1:00 p.m. Repeat Repetitive Select the Repetitive check box if the exception is recurring. If selected, specify how often and when the event repeats. To change a reoccurring exception to a one-time exception, clear the Repetitive check box. Repeats
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 31 of 44
Select Daily, Weekly, Monthly, or Yearly from the drop-down list to specify how regularly the exception repeats. Every ... days/weeks/months/years Enter a number to indicate the frequency of the exception. For example, if the exception occurs every two weeks, in the Repeats drop-down list, select Weekly, and then in the Every box, enter 2. Starts on Enter the date of the first occurrence of the exception in mm/dm/yyyy format or click the calendar icon to select a date. Ends Select After ... Occurrences to specify a finite number of occurrences or On to specify a date for the last occurrence of the exception. If you select After ... Occurrences, enter the number of occurrences in the box. If you select On, enter the date of the last occurrence in mm/dd/yyyy format or click the calendar icon to select a date.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Setup > Period
Period The Period group is located on the Setup tab of the ribbon in the Gantt Scheduler. It includes options for selecting and modifying period definitions.
Periods Click Periods to display the Period Setup panel to create, modify, or remove period definitions.
Current Period Select a period from the list to set it as the current period definition.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Setup > Period > Periods and Period Setup
Period Setup Use the Period Setup panel to create, modify, or remove period definitions.
Instructions On the Setup tab, in the Period group, click Periods to display the Period Setup panel.
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 32 of 44
Periods Adding and Defining a New Period Click Add
to add a new entry, or press Insert.
Modifying a Period Select an entry and modify the displayed information as needed. Copying a Period Select an entry and click Copy
to create a copy of the selected entry or press Ctrl+C.
Removing a Period Select an entry and click Remove
to remove the selected entry or press Delete. The entry can only be removed if it is not being used in the project.
Moving a Period Select an entry and click Up
or Down
to move the entry up or down in the list, or press Ctrl+Up Arrow or Ctrl+Down Arrow.
Setting the Current Period Select an entry and click Set Current
to set it as the current selection in the tab group. Click Reset Current
to reset the selection.
General Name Enter a name for the period. Description Enter a brief description of the period. Generate Uniform Period List Use this section to generate or modify a uniform period list by specifying a start date and time, increment of time, and number of periods. You can then modify individual periods in the Details section. Start date Enter the start date of the period to be defined. Start time Enter the start time of the period to be defined. Increment Select the increment of time to use when generating the uniform period list. You can select Hour, Day, Week, Month, or Year. Number of periods Enter the number of periods to generate for the definition. Details Once you have generated a period list in the Generate Uniform Period List section, you can modify the time amounts and increments of individual periods. If you make a change to a period, the subsequent periods will be automatically updated.
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 33 of 44
Start date Displays the start date and time of the period. End date Displays the end date and time of the period. Time amount Enter the amount of time per increment for the period. Increment Select the increment of time to use for that period. You can select Hour, Day, Week, Month, or Year.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Setup > Summary Report
Summary Report The Summary Report group is located on the Setup tab of the ribbon in the Gantt Scheduler. It includes options to set up reports and export report to CSV files.
Report Setup Click Report Setup to display the Summary Report Manager Export panel to create, modify, or remove reports and report setup information.
Current Report Select a report from the drop-down list to set it as the current report.
Export to CSV Click Export to CSV to display the Summary Report Export panel to export report information to a CSV file.
Tutorial Click to read the Summary Report tutorial.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Setup > Summary Report > Report Setup
Report Setup Use the Summary Report Manager panel to create, modify, or remove reports and report setup information.
Tutorial Click to read the Summary Report tutorial.
Instructions On the Setup tab, in the Summary Report group, click Report Setup to display the Summary Report Manager panel.
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 34 of 44
Reports Adding and Defining a New Report Click Add
to add a new entry, or press Insert.
Modifying a Report Select an entry and modify the displayed information as needed. Copying a Report Select an entry and click Copy
to create a copy of the selected entry or press Ctrl+C.
Removing a Report Select an entry and click Remove
to remove the selected entry or press Delete. The entry can only be removed if it is not being used in the project.
Moving a Report Select an entry and click Up
or Down
to move the entry up or down in the list, or press Ctrl+Up Arrow or Ctrl+Down Arrow.
Setting the Current Report Select an entry and click Set Current
to set it as the current selection in the tab group. Click Reset Current
to reset the selection.
Managing Report Details Use the icons below the Details section to add, remove, copy, or move report items. Add a new item to the report Click the Add
icon to add a new item to the report.
Remove an item from the report Click the Remove
icon to remove the selected item from the report.
Copy an item on the report Click the Copy
icon to create a copy the selected item.
Move an item to another report Click the Move
icon to move the item to another report.
Copy an item to another report Click the Copy and Move icon
to copy the selected item and move it to another report.
Move an item up or down in the list Click the Up
or Down
icons to move the selected item up or down in the list.
Move an item to the top or bottom of the list Click the Move to Top
or Move to Bottom
icons to move the selected item to the top or the bottom of the list.
General Name
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 35 of 44
Enter a name for the report. Description Enter a brief description of the report. Details Title Enter the title of the report item. Unit Enter the unit of measurement for the report item. Attribute Select the attribute of the report item from the list. Weighted by If the selected attribute is a custom expression, select the attribute by which it is weighted from the list. Expression If the selected attribute is a custom expression, select or enter the formula for the expression. To use the Formula Editor panel to enter or modify the expression, click the Formula Editor icon. Calculation Select the calculation method of the report item from the list. Activity Type Select the activity type(s) of the report item. To select activity types, click the Browse icon to display a list of the available activity types. Click on an activity type in the left column and then click the right arrow to add the activity type to the list, or click the double right arrow to add all activity types to the list. To remove selected activity types, click on the activity in the right column and then click the left arrow to remove the activity type from the list, or click the double left arrow to remove all activity types from the list. Click OK when finished to save selections and return to the Summary Report Manager panel. Resource Select a resource for the report item from the list. Filter Select a filter for the report item from the list. Decimals Enter or select the number of decimals to use for the report item on the report.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Setup > Summary Report > Export to CSV
Export to CSV Use the Summary Report Export panel to export report information to a CSV file.
Tutorial Click to read the Summary Report tutorial.
Instructions On the Setup tab, in the Summary Report group, select the report you want to export from the Current report drop-down list, and then click Export to CSV to display the Summary Report Export panel.
Summary Report Export Start Date Enter a start date for the report.
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 36 of 44
Finish Date Enter an ending date for the report. Separator Enter the character that separates the data fields in the CSV file.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Setup > Formula Editor
Formula Editor Use the Formula Editor panel to assist in creating formulas and expressions for activity attributes. Expression attributes are defined via the expression builder. The syntax for functions is similar to Microsoft Excel, with auto-complete while defining and helpful syntax prompts. The available operands that can be used in expressions are Envisage Metadata, DGD Properties, Triangulation Attributes, and Templated Attributes.
Instructions On the Attribute Manager panel, click the Formula
icon to display the Formula Editor panel.
For additional information about using the expression builder, see: http://www.infragistics.com/help/wpf/xamFormulaEditor_ContextualHelp.html
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > View
View Tab The View tab includes options for viewing activities in Envisage as well as filtering, grouping, and sorting activities.
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 37 of 44
Alternatively, you can right-click on an activity in the Gantt Chart area to view the options for that activity or use keyboard shortcuts for some options.
Envisage The Envisage group includes options for selecting and zooming on activities in Envisage based on selection in Gantt Scheduler as well as the ability to create animations of selected activities.
Filter The Filter group includes options for creating, modifying, and selecting filters for activity data.
Group The Group group includes options for managing and selecting attribute groups.
Sorting The Sorting group includes options for sorting data in ascending or descending order.
View The View group includes an option for selecting all activities in the Gantt Chart area.
Column Format The Column Format group includes options for formatting columns, including aligning, hiding, and displaying columns.
Layout The Layout group includes options for saving, loading, and resetting the layout of the Gantt Scheduler.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > View > Envisage
Envisage The Envisage group is located on the View tab of the ribbon in the Gantt Scheduler. It includes options for selecting and zooming on activities in Envisage based on selection in Gantt Scheduler as well as the ability to create animations of selected activities.
Envisage Selection Click Envisage Selection to automatically select activities in Envisage when you select them in the Gantt Scheduler. This option will remain on until you click Envisage Selection again.
Envisage Zoom Click Envisage Zoom to automatically select and zoom in on activities in Envisage when you select them in the Gantt Scheduler. This option will remain on until you click Envisage Zoom again. Note In order to use the Envisage Zoom option, the Envisage Selection option must also be selected.
Envisage Hide Click Envisage Hide to hide activities in Envisage when you select them in the Gantt Scheduler.
Envisage Shadow Click Envisage Shadow to shadow activities in Envisage when you select them in the Gantt Scheduler.
Select in Envisage Click Select in Envisage to select activities in Envisage when you select them in the Gantt Scheduler.
Zoom in Envisage Click Zoom in Envisage to zoom in on activities in Envisage when you select them in the Gantt Scheduler.
Animation Use the Animation option to display an animation of selected activities in Envisage.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page.
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 38 of 44
Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > View > Envisage > Animation
Animation Use the Animation panel to display an animation of selected activities in Envisage.
Tutorial Click to read the Animation tutorial.
On the View tab, in the Envisage group, click Animation to display the Animation panel.
Step increment Select the increment of time for the animation. You can select Hour, Day, Week, Month, or Year. Rate Enter the number of steps per frame for the animation. Show completed / Show remaining Select whether to animate activities that have been completed or activities that are still remaining. Icons Previous Click the Previous icon
to jump back to the previous step of the animation.
Stop Click the Stop icon
to stop the animation.
Play Click the Play icon
to play the animation.
Pause Click the Pause icon
to pause the animation.
Next Click the Next icon
to jump to the next step of the animation.
Last Click the Last icon
to jump to the last step of the animation.
Loop Click the Loop icon
to continue playing the animation on a loop. When the animation reaches its end, it will return to the beginning and play again.
Refresh Click the Refresh icon
to refresh the animation to include any changes you have made to activities in the Gantt Scheduler.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > View > Filter
Filter The Filter group is located on the View tab of the ribbon in the Gantt Scheduler. It includes options for creating, modifying, and selecting filters for activity data.
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 39 of 44
Filters Click Filters to display the Filter Manager panel. This panel includes options to add, modify, or remove data filters.
Current Filter Select the current filter from the list.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > View > Filter > Filters
Filters Use the Filter Manager panel to add, modify, or remove data filters.
Instructions On the View tab, in the Filter group, click Filters to display the Filter Manager panel.
Reports Adding and Defining a New Filter Click Add
to add a new entry, or press Insert.
Modifying a Filter Select an entry and modify the displayed information as needed. Copying a Filter Select an entry and click Copy
to create a copy of the selected entry or press Ctrl+C.
Removing a Filter Select an entry and click Remove
to remove the selected entry or press Delete. The entry can only be removed if it is not being used in the project.
Moving a Filter Select an entry and click Up
or Down
to move the entry up or down in the list, or press Ctrl+Up Arrow or Ctrl+Down Arrow.
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 40 of 44
Setting the Current Filter Select an entry and click Set Current
to set it as the current selection in the tab group. Click Reset Current
to reset the selection.
General Name Enter a name for the filter. Description Enter a brief description of the filter. Filter ... Select whether you want to include or exclude attributes based on the filter and whether or not to enclose the expression within parentheses. You can select _blank_, (, Not (, or Not. Attribute Select the attribute name from the list. For more information about managing attributes, see Attributes. Rule Select a rule from the list. You can select = (is equal to the specified value), Starts with (attribute starts with the specified value), Ends with (ends with the specified value), or Like (includes the specified value). Value Enter a value for the rule. Wildcards are allowed. ... Select whether or not to include a closing parenthesis for the expression based on your selection in the first column. Logical Operator Select And or Or if you want to add another line to your expression to indicate whether the rules are inclusive or exclusive of each other.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > View > Group
Group The Group group is located on the View tab of the ribbon in the Gantt Scheduler. It includes options for managing and selecting attribute groups.
Groups Click Groups to display the Group Setup panel. This panel includes options to add, modify, and remove attribute groups.
Current Group Select the current group from the list.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > View > Group > Groups
Group Setup Use the Group Setup panel to add, modify, and remove attribute groups.
Instructions On the View tab, in the Group group, click Groups to display the Group Setup panel.
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 41 of 44
Groups Adding and Defining a New Group Click Add
to add a new entry, or press Insert.
Modifying a Group Select an entry and modify the displayed information as needed. Copying a Group Select an entry and click Copy
to create a copy of the selected entry or press Ctrl+C.
Removing a Group Select an entry and click Remove
to remove the selected entry or press Delete. The entry can only be removed if it is not being used in the project.
Moving a Group Select an entry and click Up
or Down
to move the entry up or down in the list, or press Ctrl+Up Arrow or Ctrl+Down Arrow.
General Name Enter a name for the group. Description Enter a brief description of the group. Details Attribute Select an attribute from the list. For more information about managing and modifying attributes, seeAttributes. From Enter a value for the beginning of the group selection. Length Enter the length of the group. Sort Order Select whether to display the results in Ascending or Descending order.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > View > Sorting
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 42 of 44
Sorting The Sorting group is located on the View tab of the ribbon in the Gantt Scheduler. It includes options for sorting data in ascending or descending order.
Ascending Select a column in the Gantt Chart area and then click Ascending to sort activities in ascending order by that column's values.
Descending Select a column in the Gantt Chart area and then click Descending to sort activities in descending order by that column's values.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] . Envisage
Copyright© 2015 Maptek Pty Limited
Maptek
Home > Vulcan Gantt Scheduler > View > View
View The View group is located on the View tab of the ribbon in the Gantt Scheduler. It includes an option for selecting all activities in the Gantt Chart area.
Select all activities Click Select all activities to select all activities displayed in the Gantt Chart area.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > View > Column Format
Column Format The Column Format group is located on the View tab of the ribbon in the Gantt Scheduler. It includes options for formatting columns, including aligning, hiding, and displaying columns.
Left Select a column in the Gantt Chart area and then click Left to left-align the contents of the cells in that column. Alternatively, you can right-click the column header, point at Align, and then click Left.
Center Select a column in the Gantt Chart area and then click Center to center the contents of the cells in that column. Alternatively, you can right-click the column header, point at Align, and then click Center.
Right Select a column in the Gantt Chart area and then click Right to right-align the contents of the cells in that column. Alternatively, you can right-click the column header, point at Align, and then click Right.
Hide Select a column in the Gantt Chart area and then click Hide to hide the column from view. Alternatively, you can right-click the column header and then click Hide. To display a single hidden column, right-click on any column header, point to Show, and then click on the name of the column you want to show.
Show All Click Show All to display all columns in the Gantt Chart area, including any columns that have previously been hidden. Alternatively, you can right-click any column header and click Show All. To display a single hidden column, right-click on any column header, point to Show, and then click on the name of the column you want to show.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
file:///C:/Users/cursos/AppData/Local/Temp/~hh9B4F.htm
Copyright© 2015 Maptek Pty Limited
05-05-2016
Vulcan Gantt Scheduler : Contents
Page 43 of 44
Home > Vulcan Gantt Scheduler > View > Layout
Layout The Layout group is located on the View tab of the ribbon in the Gantt Scheduler. It includes options for saving, loading, and resetting the layout of the Gantt Scheduler.
Save Click Save to save the current Gantt Scheduler layout. If you make changes to the layout after you save it, you can return to the most recently saved layout using the Load option
Load Click Load to return to the most recently saved layout.
Reset Click Reset to return to the default layout.
Need more help? Go to www.maptek.com/support to access the Maptek Client Support page. Have feedback on this help topic? Share it with us at
[email protected] .
Copyright© 2015 Maptek Pty Limited
Home > Vulcan Gantt Scheduler > Keyboard Shortcuts
Keyboard Shortcuts Following is a list of keyboard shortcuts for the Vulcan Gantt Scheduler. The keyboard shortcuts are grouped by the name of the tab on which they appear in the Gantt Scheduler interface. n
Home tab
n
Precedences tab
n
Resources tab
n
Setup tab
n
View tab
Home Tab Option
Keyboard Shortcut
Copy activity
Ctrl+C
Cut activity
Ctrl+X
Paste activity
Ctrl+V
Delete activity
Ctrl+D
Undo
Ctrl+Z
Redo
Ctrl+Y
New
Shift+A
Insert
Ctrl+I
Properties
F4
Update activities
Ctrl+U
Increase indent
Alt+Right Arrow
Decrease indent
Alt+Left Arrow
Precedences Tab Option
Keyboard Shortcut
Create
Ctrl+F12
Remove
Shift+F12
Spatial precedences
F9
Group manager
Ctrl+G
New group
Alt+G
Resources Tab Option
Keyboard Shortcut
Settings
Ctrl+F10
Allocate resources
Alt+F10
Apply resource rate
Alt+F11
Leveling setup
Alt+L
Leveling by capacity
Alt+Y
Leveling by rate and capacity
Alt+R
Clear leveling delays
Alt+C