TP48200A-D15A1 & H15A3 & H15A5 V300R001
Quick Installation Guide
Issue
06
Date
2013-07-23
HUAWEI TECHNOLOGIES CO., LTD.
Copyright © Huawei Technologies Co., Ltd. 2013. All rights reserved. No part of this document may be reproduced or transmitted in any form or by any means without prior written consent of Huawei Technologies Co., Ltd.
Trademarks and Permissions and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd. All other trademarks and trade names mentioned in this document are the property of their respective holders.
Notice The purchased products, services and features are stipulated by the contract made between Huawei and the customer. All or part of the products, services and features described in this document may not be within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information, and recommendations in this document are provided "AS IS" without warranties, guarantees or representations of any kind, either express or implied. The information in this document is subject to change without notice. Every effort has been made in the preparation of this document to ensure accuracy of the contents, but all statements, information, and recommendations in this document do not constitute a warranty of any kind, express or implied.
Huawei Technologies Co., Ltd. Address:
Huawei Industrial Base Bantian, Longgang Shenzhen 518129 People's Republic of China
Website:
http://www.huawei.com
Email:
[email protected]
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
i
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
About This Document
About This Document Purpose This document describes the TP48200A-D15A1 & H15A3 & H15A5 in terms of its structure, components, installation, and commissioning.
Intended Audience This document is intended for:
Installation and commissioning engineers
Technical support engineers
Symbol Conventions The symbols that may be found in this document are defined as follows.
Symbol
Description Indicates a hazard with a high level or medium level of risk which, if not avoided, could result in death or serious injury.
Indicates a hazard with a low level of risk which, if not avoided, could result in minor or moderate injury.
Indicates a potentially hazardous situation that, if not avoided, could result in equipment damage, data loss, performance deterioration, or unanticipated results. Provides a tip that may help you solve a problem or save time. Provides additional information to emphasize or supplement important points in the main text.
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
ii
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
About This Document
Change History Changes between document issues are cumulative. The latest document issue contains all the changes made in earlier issues.
Issue 06 (2013-07-23) Modified section 7.1.1 UIM02C.
Issue 05 (2013-04-28) Optimized the content of the document, including standardizing the terminology and improving the accuracy of the description.
Issue 04 (2013-02-28) Add the installation dimensions for the cabinet installation holes.
Issue 03 (2013-01-09) This issue is the third official release, which incorporates the following changes: Chapter 6 Installing Components
Modify the picture of Install a temperature and humidity sensor. Chapter 8 Powering On and Commissioning
Set battery fuse break alarm " Enable/Disable" status is added.
Issue 02 (2012-11-12) This issue is the second official release, which incorporates incorporates the following changes: Port description is modified.
Issue 01 (2012-07-28) This issue is used for first office release.
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
iii
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
Contents
Contents About This Document .............................. .................................................... ............................................ ............................................. .......................................... ................... ii 1 Safety Precautions .................................. ........................................................ ............................................ ............................................. ........................................... .................... 1 1.1 Health and Safety ............................................................................................................................................. 1 1.1.1 Overview .............................................................. .............................................................. ..................... 1 1.1.2 Electrical Safety ................................................................................................................. ..................... 3 1.1.3 Inflammable Environment ...................................................................................................................... 4 1.1.4 Battery ....................................................... .............................................................. ................................ 4 1.1.5 Working Working at Heights ............. ................................................................. ................................................... 6 1.1.6 Using Ladders ......................................................................................................................................... 7 1.1.7 Mechanical Safety .......................................................... ............................................................... .......... 7 1.1.8 Bundling Signal Cables ............................................................. .............................................................. 8 1.2 Equipment Safety ............................................................................................................. ................................ 9 1.2.1 Electricity Safety ............................................................ ............................................................... .......... 9 1.2.2 Electrostatic Discharge............................................................................................................................ 9 1.2.3 Laying Cables ....................................................................................................................................... 10
2 Installation Preparations ............................................ ................................................................... ............................................. ........................................ .................. 11 11 2.1 Tools ........................................................ ................................................................. ...................................... 11 2.2 Installation Clearance Requirements .............................................................................................................. 12 2.3 Prepare Cables ............................................................... .............................................................. ................... 12
3 Configuration.............................................. .................................................................... ............................................ ............................................. ..................................... .............. 14 4 Installing the Cabinet........................................... .................................................................. ............................................. ............................................ ......................... ... 18 5 Installing a PGND Cable............................................ ................................................................... ............................................. ........................................ .................. 21 6 Installing Components.................................. Components........................................................ ............................................. ............................................. ................................ .......... 22 6.1 Installing Rectifiers ........................................................................................................................................ 22 6.2 Installing a Smoke Sensor(Optional) ............................................................................................................. 23 6.2.1 Securing the Smoke Sensor ................................................................................................................... 23 6.2.2 Connecting the Smoke Sensor ............................................................. ................................................. 23 6.3 Installing a Temperature and Humidity Sensor(Optional) ........................................................... ................... 24 6.3.1 Securing the Temperature and Humidity Sensor ..................................................... .............................. 24 6.3.2 Connecting the Temperature Temperature and Humidity Sensor ............................................................ ................... 24
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
iv
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
Contents
6.4 Installing a Water Sensor(Optional) ..................................................................................................... .......... 25 6.4.1 Securing the Water Sensor ...................................................................................... .............................. 25 6.4.2 Connecting the Water Sensor .................................................................................. .............................. 25
7 Installing Cables ........................................... .................................................................. ............................................. ............................................. ................................. .......... 27 7.1 Installing Signal Cables and Communication Cables....................................................... .............................. 27 7.1.1 UIM02C ............................................................... .............................................................. ................... 27 7.1.2 Installing Dry Contacts and Boo lean Values Values Signal Cables .................................................................. 29 7.1.3 Installing Sensor Cables ............................................................ ............................................................ 29 7.1.4 Installing Communications Cables ...................................................... ................................................. 30 7.2 Installing Po wer Cables ........................................................... ............................................................... ........ 30 7.2.1 Installing DC Output Cables ................................................................ ................................................. 31 7.2.2 Installing Storage Batteries and Copper Bars ........................... ............................................................ 32 7.2.3 Installing AC Output Cables ........................................................................ ......................................... 34 7.2.4 Installing AC Input Cables ........................................................ ............................................................ 35
8 System Commissioning ............................................................. .................................................................................... .............................................. ......................... .. 38 8.1 Installation Verification ........................................................... ............................................................... ........ 38 8.2 Powering On and Commissioning ................................................................ .................................................. 38 8.2.1 Setting Parameters ................................................................................................................................ 38 8.3 Powering On................................................................................................................................................... 42
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
v
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
1 Safety Precautions
1
Safety Precautions
1.1 Health and Safety 1.1.1 Overview Introduction This section describes the safety precautions you must take before installing or maintaining Huawei equipment.
To ensure safety safety of humans and the equipment, pay attention to the safety symbols on the equipment and all the safety instructions in this document.
The "NOTE", "CAUTION", and "WARNING" "WARNING" marks in other documents do not represent all the safety instructions. They are only supplements to the safety instructions.
Installation and maintenance personnel must understand basic safety precautions to avoid hazards.
When operating Huawei equipment, in addition to following the general precautions in this document, follow the specific safety instructions given by Huawei.
Only trained and qualified personnel are allowed to install, operate, and maintain Huawei equipment.
Local Safety Regulations When operating Huawei equipment, you must follow the local laws and regulations. The safety instructions in this document are only supplements to the local laws and regulations.
General Requirements To minimize risk of personal injury and damage to equipment, read and follow all the precautions in this document before before performing any any installation or maintenance. maintenance. Ensure that the instructions provided in this document are followed completely. completely. This section also provides guidelines for selecting the measuring and testing devices.
Installation
The device (or system) must be installed in an access-controlled location.
The device can be mounted only on concrete or non-combustible surfaces.
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
1
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
1 Safety Precautions
The device must be fixed securely on the floor or to other immovable objects such as walls and mounting racks before operation.
When installing the unit, always make the ground connection first and disconnect it at the end.
Do not block the ventilation while the device is operating. Keep a minimum distance of 5 cm between the device and the wall or other objects that may block the ventilation.
Tighten the thumbscrews by using a tool after initial installation and subsequent access to the panel.
Do not damage the ground conductor or operate the device in the absence of a properly installed ground conductor. conductor. Conduct the electrical inspection carefully.
The device (or system) must be connected permanently to the protection ground before an operation. The cross-sectional area of the protective ground conductor must be at least 2 10 mm .
For AC-supplied models: The device applies to TN or TT power system.
For DC-supplied models: Reinforced insulation or double insulation must be provided to isolate the DC source from the AC mains supply.
For DC-supplied model: The device applies to DC power source that complies with th e Safety Extra-Low Voltage (SELV) requirements in IEC 60950-1 based safety standards.
Prepared conductors are connected to the terminal block, and only the appropriate AWG/Type of wire is secured with the lug terminals.
Ground
Power Supply
Human Safety
Do not operate the device or cables during lightning strikes.
Remove the AC power connector when there is lightning. Do not use fixed terminals or touch terminals or antenna connectors when there is lightning.
To avoid electric shock, do not connect safety extra-low voltage (SELV) circuits to telecommunication network voltage (TNV) circuits.
Move or lift the chassis by b y holding its lower edge. Do not hold the handles on certain modules such as power supply, supply, fans, and boards because they cannot support the weight of the device.
At least two persons are required to lift the chassis. When lifting it, keep your back straight and move stably.
Do not wear jewelry or watches when you operate the device.
Only qualified professional personnel are allowed to install, configure, operate, and disassemble the device.
Only the personnel authenticated or authorized by Huawei are allowed to replace or change the device of the parts of the device (including the software).
Any fault or error that might cause safety problems must be reported immediately to a supervisor.
Only qualified personnel are allowed to remove or disable the safety facilities and to troubleshoot and maintain the device.
Operator
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
2
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
1 Safety Precautions
1.1.2 Electrical Safety High Voltage
The high voltage power supply provides power for the device operation. Direct or indirect contact (through damp objects) with high voltage and AC mains supply may result in fatal danger.
During the installation of the AC power supply facility, follow the local safety regulations. The personnel who install the AC facility must be qualified to perform high voltage and AC operations.
Do not wear conductive articles, such as watches, hand chains, bracelets, and rings during the operation.
When water is found in the rack or the rack is damp, switch off the power supply immediately.
When the operation is performed in a damp environment, make sure that the device is dry.
Non-standard and improper improper high voltage operations operations may result in fire and and electric shock. Therefore, you must abide by the local rules and regulations when bridging and wiring AC cables. Only qualified personnel are allowed to perform high voltage and AC operations.
Before powering on a device, ground the device. Otherwise, personal injury or device damage may be caused by high leakage current.
Tools
Dedicated tools must be used during high voltage and AC operations. Avoid Avoid using ordinary tools.
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
3
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
1 Safety Precautions
High Electrical Leakage
Ground the device before powering it on. Otherwise, personal injury or device damage may be caused by high leakage leakage current. If a "high electrical leakage" tag is present on the power terminal of the device, you must ground the device before powering it on.
Power Cable
Do not install or remove power cables when the device is on. Transient contact between between the core of the power cable and the conductor may generate electric arcs or sparks, which may cause fire or hurt human eyes.
Before installing or removing the power cable, turn off the power switch.
Before connecting a power cable, check that the label on the power cable is correct.
1.1.3 Inflammable Environment Operating the electrical device in an inflammable environment can be fatal.
Do not place the device in an environment that has inflammable and explosive air or gas. Do not perform any operation in this environment.
1.1.4 Battery Storage Battery
Before operating storage batteries, carefully read the safety precautions for battery handling and connection.
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
4
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
1 Safety Precautions
Improper handling of storage batteries causes hazards. When operating storage batteries, avoid short circuit and overflow or leakage of the electrolyte. Electrolyte overflow may damage the device. It will corrode metal parts and circuit boards, and ultimately damage the device and cause short circuit of circuit boards.
Basic Precautions Before installing and maintaining the battery, battery, note the following:
Do not wear metal articles such as wristwatch, hand chain, bracelet, and ring.
Use special insulation tools.
Take care care to protect your eyes when operating the device.
Wear rubber gloves and a protective coat in case of electrolyte overflow.
When handling a storage battery, battery, ensure that its electrodes are upward. Leaning or reversing the storage battery is prohibited.
Short Circuit
Battery short circuit may cause human injuries. Although the voltage of ordinary batteries is low, low, the instantaneous high current caused by the short circuit releases a great deal of energy. energy. There is danger of explosion if the battery is incorrectly replaced. Therefore, Therefore, replace the battery only with the same same or equivalent type recommended recommended by the manufacturer manufacturer..
Keep away metal objects, which may cause battery short circuit, from batteries. If metal objects must be used, first disconnect the batteries in use before performing any other operations.
Hazardous Gas
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
5
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
1 Safety Precautions
Do not use unsealed lead acid storage batteries. Lead acid storage batteries must be placed horizontally and stably to prevent the batteries from releasing flammable gas, which may cause fire or erode the device.
Lead acid storage batteries in use emit flammable gas. Therefore, ventilation and fireproofing measures must be taken at the sites where lead acid storage batteries are used.
Battery Temperature
If a battery overheats, the battery may be deformed or damaged, and the electrolyte may overflow. When the temperature of the battery is higher than 60 ºC, check the battery for electrolyte overflow. overflow. If the electrolyte overflows, absorb and counteract the electrolyte immediately. immediately.
Battery Leakage
When the electrolyte overflows, absorb and counteract the electrolyte immediately. immediately. When moving or handling a battery whose electrolyte leaks, note that the leaking electrolyte may hurt human bodies. When you find the electrolyte leaks, use the following substances to counteract and absorb the leaking electrolyte:
Sodium bicarbonate (baking soda): NaHCO 3
Sodium carbonate (soda): Na 2CO3
Select a substance to counteract and absorb the leaking electrolyte according to the instructions of the battery manufacturer.
1.1.5 Working at Heights
Avoid Avoid object falling when you work at heights. When working at heights, fulfill the following requirements:
Issue 06 (2013-07-23)
Only trained personnel can work at heights.
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
6
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
1 Safety Precautions
Prevent the devices and tools that you carry from falling down.
Take safety and protection measures, for example, wear a helm and safety belt.
Wear warm clothes when working at heights in a cold region.
Before working at heights, check that all the lifting facilities are in good condition.
1.1.6 Using Ladders Checking a Ladder
Before using a ladder, check whether the ladder is damaged. Only the ladder in good condition can be used.
Before using a ladder, ladder, you should know the maximum weight capacity of the ladder. Avoid overweighing the ladder.
Placing a Ladder The recommended gradient of ladders is 75 degrees. You You can measure the gradient of the ladder with an angle square or your arms. When using a ladder, ladder, ensure that the wider feet of the ladder are downward, or take protection measures for the ladder feet to prevent the ladder from sliding. Ensure that the ladder is placed securely. securely.
Climbing Up a Ladder When climbing up a ladder, note the following:
Ensure that the center of gravity of your body does not deviate from the edges of the two long sides.
To minimize the risk of falling, hold your balance on the ladder before any operation.
Do not climb higher than the fourth rung of the ladder (counted from up to down).
If you want to climb up a roof, ensure that the ladder top is at least one meter higher than the roof.
1.1.7 Mechanical Safety Drilling Holes
Do not drill the cabinet at will. Drilling holes without complying with the requirements affects affects the electromagnetic shielding performance of the cabinet and damages the cables inside the cabinet. In addition, if the scraps caused by drilling enter the cabinet, the printed circuit boards (PCBs) may be short circuited.
Before you drill a hole in the cabinet, wear insulated gloves and remove the internal cables from the cabinet.
Wear an eye protector when drilling holes. This is to prevent your eyes from being injured by the splashing metal scraps.
Ensure that the scraps caused by drilling do not enter the cabinet.
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
7
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
1 Safety Precautions
Drilling holes without complying with the requirements affects affects the electromagnetic shielding performance of the cabinet.
After drilling, clean the metal scraps immediately. immediately.
Sharp Objects
Before you hold or carry a device, wear protective gloves to avoid getting injured by sharp edges of the device.
Handling Fans When handling fans, note the following:
When replacing a component, place the component, screws, and tools in a safe place. Otherwise, if any of them fall into the operating fans, the fans may be damaged.
When replacing a component near fans, do not insert your fingers or boards into the operating fans until the fans are switched off and stops running.
Lifting Heavy Objects
When heavy objects are being lifted, do not stand or walk under the cantilever or the lifted object.
1.1.8 Bundling Signal Cables
Do not bundle signal cables with high current cables or high voltage cables.
Maintain a minimum space of 150 mm between adjacent ties.
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
8
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
1 Safety Precautions
1.2 Equipment Safety 1.2.1 Electricity Safety High Electrical Leakage
If the "high electrical leakage" tag is present on the power terminal of the device, you must ground the device before powering it on.
1.2.2 Electrostatic Discharge
The static electricity generated by human bodies may damage the electrostatic-sensitive electrostatic-sensitive components on boards, for example, the large-scale integrated (LSI) circuits. Human body movement, friction between human bodies and clothes, friction between shoes and floors, or handling of plastic articles causes static electromagnetic fields on human bodies. These static electromagnetic fields cannot be eliminated until the static is discharged. To prevent electrostatic-sensitive electrostatic-sensitive components from being damaged by the static on human bodies, you must wear a well-grounded ESD wrist wrist strap when touching the device device or handling boards or application-specific application-specific integrated circuits circuits (ASICs). Figure 1-1 shows how to wear an ESD wrist strap. Figure 1-1 Wearing an ESD wrist strap
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
9
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
1 Safety Precautions
1.2.3 Laying Cables When the temperature is very low, low, violent strike or vibration may damage the cable sheathing. To ensure safety, safety, comply with the following requirements:
Cables can be laid or installed only when the temperature is higher than 0 ºC.
Before laying cables which have been stored in a temperature lower than 0 ºC, move the cables to an environment of the ambient temperature and store them at the ambient temperature for at least 24 hours.
Handle cables with caution, especially at a low temperature. Do not drop the cables directly from the vehicle.
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
10
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
2 Installation Preparations
2
Installation Preparations
2.1 Tools Table 2-1 shows the tools that must be obtained before installation. Table 2-1 Tools
Combination spanner
Marker pen
Rubber hammer
Socket spanner
Wire clippers
Hydraulic pliers
Adjustable spanner
Paper knife
RJ-45.connect or crimping pliers
Issue 06 (2013-07-23)
Phillips screwdriver
Flathead screwdriver
Torque spanner
Diagonal plier
Network cable pliers
Sharp-nose pliers
Wire stripper
Power cable cutting pliers
Power cable crimping pliers
Crimping pliers
ESD-preventiv ESD-preventiv e wrist strap
Percussion drill
Drill bit
Clamp meter
Hot air dun
Steel tape
Vacuum cleaner
Multimeter
Antistatic gloves
Protective gloves
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
11
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
2 Installation Preparations
2.2 Installation Clearance Requirements Figure 2-1 shows the installation clearance requirements. Figure 2-1 Installation clearance requirements
2.3 Prepare Cables Table 2-2 lists the specification of the system cables. Table 2-2 The specification of the system cables
Cable
Cable Diameter and Color
Signal cables to dry contacts, Boolean values, and sensor ports
Not provided
RS485, RS232 or Fast Ethernet (FE) cable
Not provided
DC Power cable to the primary load
Not provided
DC Power cable to the secondary load
Not provided
The PGND cable
Cross-sectional area: 16 mm (0.02 in. )
2
2
Color: yellow green cable AC input power cable
2
single-phase: Cross-sectional area: 25 mm (0.04 2 in. ) 2
2
three-phase: Cross-sectional Cross-sectional area: 16 mm (0.02 in. )
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
12
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
Cable
2 Installation Preparations
Cable Diameter and Color (recommended /Not provided)
Cut cables to a length suitable for the actual cable route, and then add OT terminals or cord end terminals to each end of the cables, as shown in Figure in Figure 2-2, Figure 2-3. Figure 2-2 Prepare OT terminals
Figure 2-3 Prepare cord end terminals.
NOTE
Issue 06 (2013-07-23)
The local cable colors prevail. The cable colors in the figure are for reference only.
Cables routed along the floor should be protected with protection tubes that comply with NFPA70 standards.
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
13
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
3 Configuration
3
Configuration
Specifications Table 3-1 Specifications
Category
Specifications
Dimensions (H x W x D)
Cabinet: 1500 mm (59.06 in.) x 650 mm (25.59 in.) x 650 mm (25.59 in.)
Base: 100 mm (3.94 in.) x 650 mm (25.59 in.) x 650 mm (25.59 in.)
Weight
Issue 06 (2013-07-23)
120 kg (264.6 lb) (without rectifiers or storage batteries)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
14
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
3 Configuration
Interior of the Cabinet Figure 3-1 Interior of the TP48200A-D15A1
(1) Maintenance socket (4) Cable hole (7) Site monitoring monitoring unit (SMU)
Issue 06 (2013-07-23)
(2) AC input circuit breakers (5) Storage battery circuit breakers (8) Space for rectifiers
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
(3) Ground bar (6) Load circuit breakers (9) Battery rack
15
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
3 Configuration
Figure 3-2 Interior of the TP48200A- H15A3
(1) Maintenance socket (4) Cable hole (7) Site monitoring monitoring unit (SMU)
Issue 06 (2013-07-23)
(2) AC input circuit breakers (5) Storage battery circuit breakers (8) Space for rectifiers
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
(3) Ground bar (6) Load circuit breakers (9) Battery rack
16
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
3 Configuration
Figure 3-3 Interior of the TP48200A-H15A5
(1) Maintenance socket (4) Cable hole (7) Site monitoring monitoring unit (SMU) (10) Battery rack
Issue 06 (2013-07-23)
(2) AC input circuit breakers (5) Storage battery circuit breakers (8) Space for rectifiers
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
(3) Ground bar (6) Load circuit breakers (9) Heater
17
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
4 Installing the Cabinet
4
Installing the Cabinet
To install a cabinet, perform the following steps:
Step 1 Remove the cover of the packaging box and locate the marking-off template on the cover interior, as shown in Figure in Figure 4-1. Figure 4-1 Marking-off template
Step 2 Fix the installation hole, as shown in Figure in Figure 4-2. Figure 4-2 Fixing the installation hole
(1) Marker
(2) Marking-off template
(3) Installation Installat ion hole
(4) Concrete pad
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
18
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
4 Installing the Cabinet
in Figure 4-3. Step 3 Drill holes and install expansion sleeves, as shown in Figure Figure 4-3 Drilling holes and install expansion sleeves
(1) Expansion bolt(M12) (5) Concrete pad
(2) Spring washer
(3) Flat washer
(4) Expansion sleeve
Step 4 Remove the cabinet from the pallet, as shown in Figure in Figure 4-4. Figure 4-4 Removing the cabinet
(1) Pallet NOTE
The configuration prevail, the pallet in the figure is for reference only
Step 5 Secure the cabinet on the concrete pad, as shown in Figure 4-5.
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
19
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
4 Installing the Cabinet
Figure 4-5 Securing the cabinet
----End
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
20
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
5 Installing a PGND Cable
5
Installing a PGND Cable
The PGND cable is used to connect PGND screws on the cabinet and the ground busbar outside the cabinet to ensure proper grounding of the cabinet. Install the PGND cable as shown in Figure in Figure 5-1. Figure 5-1 Installing the PGND cable
(1) Ground bar for the site
Issue 06 (2013-07-23)
(2) Ground bar for the cabinet
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
21
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
6 Installing Components
6
Installing Components
6.1 Installing Rectifiers The rated output current of each rectifier is 50 A. The number of rectifiers depends on actual capacity requirements.as shown in Figure in Figure 6-1 and Figure and Figure 6-2. Figure 6-1 Removing the filler panel
Figure 6-2 Installing rectifiers
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
22
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
6 Installing Components
6.2 Installing a Smoke Sensor(Optional) 6.2.1 Securing the Smoke Sensor Secure the smoke sensor base to the cabinet top using two M4 mm screws and fasten the smoke sensor to the base based on the direction shown in the smoke sensor, as shown in Figure 6-3. Figure 6-3 Installing a Smoke Sensor
6.2.2 Connecting the Smoke Sensor Connect one end of the smoke sensor s ignal cable to the "SMOKE" port on the UIM02C and the other end to the port on the smoke sensor, as shown in Figure in Figure 6-4. Figure 6-4 Connect the smoke sensor
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
23
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
6 Installing Components
6.3 Installing a Temperature and Humidity Sensor(Optional) 6.3.1 Securing the Temperature and Humidity Sensor Secure the temperature and humidity sensor base to the cabinet top, as s hown in Figure in Figure 6-5.
Step 1 Secure the temperature and humidity sensor base to the cabinet top using two M4 mm screws. Step 2 Connect and secure signal cables of the temperature and humidity sensor to the cabinet base, as shown in the following figure
Step 3 Install the top cover of the temperature and humidity sensor to the cabinet base. Step 4 The final installation view is as follows. Figure 6-5 Installing a temperature and humidity sensor
----End
6.3.2 Connecting the Temperature and Humidity Sensor Connect one end of the temperature and humidity sensor signal cable to the "TEM-HUM" port on the UIM02C and the other end to the port on the temperature temperature and humidity humidity sensor, as shown in Figure in Figure 6-6.
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
24
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
6 Installing Components
Figure 6-6 Connecting the temperature and humidity sensor
6.4 Installing a Water Sensor(Optional) 6.4.1 Securing the Water Sensor Secure the water sensor to the cabinet bottom using cable ties, as shown in Figure in Figure 6-7. Figure 6-7 Installing a Water Sensor
6.4.2 Connecting the Water Sensor Connect one end of the water sensor signal cable to the "WATER" port on the UIM02C, as shown in Figure in Figure 6-8
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
25
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
6 Installing Components
Figure 6-8 Connecting the water sensor
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
26
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
7 Installing Cables
7
Installing Cables
7.1 Installing Signal Cables and Communication Cables 7.1.1 UIM02C NOTE
All ports in this manual are protected by a security mechanism.
The user interface module (UIM02C) supports eight dry contact outputs, nine Boolean value inputs (including general DI1-6, smoke, water, door status), three analog signals inputs (ambient temperature, humidity, and battery temperature).
Appearance Figure 7-1 UIM02C panel
Port Description Table 7-1 UIM02C port description
Port Type
Silkscreen
Description
Default Mode
Sensor ports
TEM_HUM
Temperature and humidity sensor
-
WATER
Water sensor
-
TEMP1
Connected to environment temperature sensor and used for fan speed adjustment
-
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
27
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
Port Type
Boolean value input ports
7 Installing Cables
Silkscreen
Description
Default Mode
TEMP2
Reserved
-
GATE
Door status sensor
-
SMOKE
Smoke sensor
-
BTEMP
Battery temperature sensor
-
DIN1
Boolean value input 1
Close: alarm Open: normal
DIN2
Boolean value input 2
Close: alarm Open: normal
DIN3
Boolean value input 3
Close: alarm Open: normal
DIN4
Boolean value input 4
Close: alarm Open: normal
DIN5
Boolean value input 5
Open: alarm Close: normal
DIN6
Boolean value input 6
Close: alarm Open: normal
Dry contact output ports Default mode (Close: alarm; Open: normal) can be modified as required.
ALM1
AC power failure alarm
Close: alarm Open: normal
ALM2
ALM3
ALM4
DC undervoltage alarm or DC overvoltage alarm Rectifier faults, Protect and No Response alarm SPD failure alarm
Close: alarm Open: normal Close: alarm Open: normal Close: alarm Open: normal
ALM5
Fuse burn-out alarm
Close: alarm Open: normal
ALM6
ALM7
Battery or environment temperature alarms
Open: normal
Door alarms
Close: alarm
Close: alarm
Open: normal ALM8
Communic ation Port
Issue 06 (2013-07-23)
COM
Heater faults alarms and Fan faults alarms
Close: alarm Open: normal
RS485
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
28
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
7 Installing Cables
7.1.2 Installing Dry Contacts and Boolean Values Signal Cables Install dry contacts and Boolean values signal cables , as shown in Figure in Figure 7-2. Figure 7-2 Installing dry contacts and Boolean values signal cables
(1) White Contact plate
(2) Dry contact
7.1.3 Installing Sensor Cables Connect the sensor cable to the corresponding ports on UIM02C. The pin definitions of the sensor ports refer to Figure to Figure 7-3 and Table and Table 7-2. Figure 7-3 Pins of sensor ports
Table 7-2 Pin Definition
Silk Screen
Pin
Pin definition
WATER
1
12 V
2
WATER
3
GND
4
-
1
12 V
2
ENV_TEMP
TEMHUM
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
29
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
TEMP1
TEMP2
GATE
SMOKE
BTEMP
7 Installing Cables
3
12 V
4
ENV_HUM
1
TEMP1
2
GND
1
TEMP2
2
GND
1
DIN7+
2
JTD7
1
12 V
2
Smoke
1
Btemp1
2
12 V
7.1.4 Installing Communications Cables When in-band monitoring is required, connect the RS485/RS232 port on the SMU to the communications equipment over a cable with an RJ45 connector, when out-of-band monitoring is required, connect the FE port on the SMU to the communications equipment over a cable with an RJ45 connector, as shown in Figure in Figure 7-4. Figure 7-4 Port on the SMU
7.2 Installing Power Cables
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
30
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
7 Installing Cables
CAUTION
Before installing power cables, ensure that all circuit breakers to the OFF position.
Do not bind the ground cable, AC power cables, DC power cales, signal cables, and communications cable together. together.
Open the panel of power distribution unit, as shown in Figure in Figure 7-5. Figure 7-5 Open the panel of power distribution unit
7.2.1 Installing DC Output Cables Install DC output cables, as shown in Figure in Figure 7-6
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
31
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
7 Installing Cables
Figure 7-6 Installing DC output cables
7.2.2 Installing Storage Batteries and Copper Bars
Before installing storage batteries, ensure that the circuit breakers of the storage batteries to the OFF position.
During the installation, avoid short circuits or reverse connections between the positive and negative poles of the storage batteries. All the tools used, such as a screwdriver, screwdriver, must be insulated to prevent the the storage batteries from from being burned and to ensure ensure personal safety.
Step 1 Installing the storage batteries, as shown in Figure in Figure 7-7.
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
32
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
7 Installing Cables
Figure 7-7 Installing two layer storage batteries
Install the copper bar, as shown in Figure in Figure 7-8. Figure 7-8 Installing the copper bar
Step 2 Installing the power the power cables for for storage batteries, as as show in Figure in Figure 7-9.
CAUTION Connect negative power cables and then positive power cables for the batteries.
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
33
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
7 Installing Cables
the powerr cable cabless for for stora storage ge batte batterie riess Figure 7-9 Installing the powe
----End
7.2.3 Installing AC Output Cables Install AC output cables, as shown in Figure in Figure 7-10.
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
34
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
7 Installing Cables
Figure 7-10 Installing AC output cables
7.2.4 Installing AC Input Cables Install three-phase AC input cables refer to Figure to Figure 7-11.
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
35
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
7 Installing Cables
Figure 7-11 Installing three-phase AC input cables
Install single-phase AC input cables, remove the copper bar from the cable bridge on the side panel and connect the copper bar to the AC input circuit breaker to short-circuit the breaker breaker,, as shown in Figure in Figure 7-12.
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
36
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
7 Installing Cables
Figure 7-12 Installing single-phase AC input cables
Recover the panel of power distribution unit, as shown in Figure in Figure 7-13. Figure 7-13 Recover the panel of power distribution unit.
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
37
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
8 System Commissioning
8
System Commissioning
8.1 Installation Verification After installation, verify that:
Step 1 The cabinet is installed properly and the cables are connected properly. (Cables fastened by screws are not easily removable.)
Step 2 Cables are arranged neatly and bound properly by using cable ties. Step 3 The storage battery is connected properly. Step 4 Check for short circuits between the live wires, between the live wire and the ground cable, between the live wire wire and the neutral wire, wire, between the RTN+ and the – the – 48 48 V busbar. Rectify short circuits before powering on the power system. ----End
8.2 Powering On and Commissioning 8.2.1 Setting Parameters Figure 8-1 SMU panel
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
38
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
8 System Commissioning
(1) Running status indicator
(2) Minor alarm indicator
(3) Major alarm indicator
(4) Liquid crystal display (LCD)
(5) FE
(6) Locking latch
(7) Four buttons
(8) USB (Reserved)
(9) RS485/RS232
(10) Hold hands
NOTE
If the Run indicator (green) on the SMU panel is blinking and the LCD is on, the SMU is powered on successfully.
Button Description Button description of SMU panel as shown in Table in Table 8-1 Table 8-1 Button description of SMU panel
Button
Name
Description Descripti on
“▲”or “▼”
“up” up”or ”down” down”
Allows you to view menu items and set the value of a menu item by pressing ▲ or ▼.
“Cancel”
Returns to the previous menu without saving the settings of the current menu item.
“Enter ”
Enters the main menu from the standby screen, enters a submenu from the main menu, or saves the settings of a submenu item.
“
”
“
”
Remark :
After a menu is displayed, the standby screen is displayed and the LCD screen becomes dark if you you do not press any button within 5 minutes. minutes.
You need to log in again if you do not press any button with 8 minutes.
The preset username is admin and the preset password is 001.
Setting Parameters Step 1 Measure the voltage across the input ports of AC input circuit breakers. The voltage must range from 200 V to 240 V. The rated voltage is 220 V. If not, ask professionals to rectify the fault.
Step 2 Switch the AC input circuit breaker to the ON position, measure the voltage between L wiring and N wiring terminal. The voltage must range from 200 V to 240 V. The rated voltage is 220 V.
Step 3 Set the NetEco Main IP, NetEco Bak IP, NetEco Port, LUI Language and Set Time Zone according to actual conditions.
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
39
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
8 System Commissioning
Step 4 Set the Qty of Battery, Rated Capacity, Set Date and Set Time according to actual conditions. (Always set Qty of Battery to 1 and set Rated Capacity to the total capacity of all battery strings.)
Step 5 Set the IP Address, Subnet Mask and Default Gateway according to actual conditions. Table 8-2 Parameter settings
Main Menu
Second-Level Menu
Third-Level Menu
Fourth-Level Menu
Default Value
Settings
Comm Para
NetEco Main IP
-
-
NetEco Bak IP
-
-
NetEco Port
-
31220
System Para
Quick Settings
Host Comm Addr
0
Comm Baudrate
9600
LUI Language
-
ENGLISH
Set Time Zone
-
GMT +08:00
Qty of Battery
-
-
1
Rated Capacity
-
-
150Ah
Set Date
-
-
-
Set Time
-
-
-
IP Address
-
-
192.168.0.10
Subnet Mask
-
-
255.255.255.0
Default Gateway
-
-
192.168.0.1
Step 6 Set battery fuse break alarm " Enable/Disable" status. ----End Table 8-3 Battery fuse break alarm "Enable/Disable" status
Main Menu
Second-Level Menu
Third-Level Menu
Fourth-Level Menu
Set Value
Settings
Alarm Setting
Site Summary
Battery Fuse1 Break
Enable battery fuse blown alarms for the branches with batteries, and disable battery fuse blown alarms for the branches
Battery Fuse2 Break Battery Fuse3 Break Battery Fuse4 Break Battery Fuse5 Break
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
40
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
Main Menu
8 System Commissioning
Second-Level Menu
Third-Level Menu
Fourth-Level Menu
Set Value
Battery Fuse6 Break
without batteries.
Battery Fuse7 Break Battery Fuse8 Break Battery Fuse9 Break Battery Fuse10 Break Battery Fuse11 Break Battery Fuse12 Break NOTE
You can set parameters to modify the default mode of the Boolean value input ports and the dry contact output ports, as shown in Table in Table 8-4.
Table 8-4 Modify the default mode of the Boolean value input ports and the dry contact output ports ports
Main Menu
Second-Level Menu
Third-Level Menu
Default Value
Settings
Site Summary
DI1Alarm
Close
DI2 Alarm
Close
DI3 Alarm
Close
DI4 Alarm
Close
DI5 Alarm
Open
DI6 Alarm
Close
DO1 Alarm Act
Close
DO2 Alarm Act
Close
DO3 Alarm Act
Close
DO4 Alarm Act
Close
DO5 Alarm Act
Close
DO6 Alarm Act
Close
DO7 Alarm Act
Close
DO8 Alarm Act
Close
NOTE
You can set parameters to modify the related relay of the alarm. For example, set Battery1 Lost to DO8, as shown in Table in Table 8-5.
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
41
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
8 System Commissioning
Table 8-5 Set Battery1 Lost to DO8
Main Menu
Second-Level Third-Level Fourth-Level Menu Menu Menu
Default Value
Set Value
Settings
Alarm Setting
None
DO8
Batt Summ
Battery1 Lost
8.3 Powering On
CAUTION To avoid damaging storage batteries, batteries, switch the battery circuit breaker to the ON positions only after correctly setting the storage battery parameters on the SMU. Switch the AC input circuit breakers to the OFF positions.
Step 1 Reinstall the removed copper bar or cable of the s torage battery. Step 2 Switch the storage battery circuit breakers in the PDU to the ON positions. Step 3 Switch the AC input circuit breakers to the ON positions. Check whether the voltage between the RTN+ busbar and DC output terminal are the same as the storage battery voltage and the voltage displayed on the monitoring unit. If not, ask professionals to rectify the fault.
Step 4 Switch the LLVD and BLVD branches to the ON positions, measure whether the voltage between RTN+ and the DC output terminal. The voltage voltage must range from 42 V to 58 V (without load). The rated voltage is 53.5 V. Check whether the loads work normally. If the loads work abnormally, rectify the fault according to the relevant user guides.
Step 5 Switch the circuit breakers for the Maintenance socket, AC input, battery route, BLVD switch, and LLVD switch as required.
Step 6 Check whether the element management system (EMS) can receive the information from the power system. If not, check check whether the IP IP address is set correctly. correctly.
Step 7 Observe the operation of the power system for 15 minutes. If no alarms (except for door alarm) are generated, and current/voltage parameters of the storage battery and loads are set properly, then re-install the cover of the distribution unit, lock the door to the cabinet, give the key of the cabinet door to the customer, and clean the site before leaving.
CAUTION
To make the system run properly, properly, flip the switch to the Normal position.
To power on the battery forcibly, flip the switch to the BAT On position.
Issue 06 (2013-07-23)
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
42
TP48200A-D15A1 & H15A3 & H15A5 Quick Installation Guide
8 System Commissioning
----End
Issue 06 (2013-07-23)