METHOD STATEMENT
Page No. : Page 1 of 6 Revision : 0 Issued : May 2006
:
TCSB-MS-002
Tajar Construction Sdn Bhd
METHOD STATEMENT FOR EARTHWORKS AT TRANS EASTERN KEDAH INTERLAND HIGHWAY. PACKAGE B: FROM PEDU TO SG. CHAPAR AND FROM SG. SOK TO WENG (SEGMENT D: CH.70900 – CH.80300)
Prepared By
Approved by
…………………..………………. Mohd. Azhari Bin Ali
…………………..………………. Ir. Badrul Hisham Bin Mohd Ali
Project Manager
Chief Resident Engineer
Date:……………………...
Date:……………………... 1
METHOD STATEMENT Tajar Construction Sdn Bhd
Page No. : Page 2 of 6 Revision : 0 Issued : May 2006
:
TCSB-MS-002
CONTENTS
PAGE
1.0
SCOPE
3
2.0
MATERIALS
3
3.0
EQUIPMENT & RESOURCES
3
4.0
METHOD STATEMENT FOR SITE CLEARANCE & EARTHWORKS
4
5.0
SAFETY/ HEALTH & ENVIRONMENT
6
2
METHOD STATEMENT Tajar Construction Sdn Bhd
1.0
Page No. : Page 3 of 6 Revision : 0 Issued : May 2006
:
TCSB-MS-002
SCOPE This method statement describes the method and procedures for excavating and replacing with suitable fill material. The scope of works shall include:
2.0
i)
Site survey to establish ROW, levels and all necessary control points
ii)
Mobilisation of machinery to site
iii)
Excavating embankment
iv)
Filling of excavation with suitable fill material
v)
Compaction of fill material
vi)
Excavation of trenches and pits
vii)
Bedding materials and backfilling of pipelines
MATERIALS Material to be used shall be suitable material from approved sources.
3.0
EQUIPEMENT & RESOURCES The following is a list of equipment that is to be used; i) ii) iii) iv) v) vi) vii)
Page No. : Page 4 of 6 Revision : 0 Issued : May 2006
:
TCSB-MS-002
METHOD STATEMENT FOR EARTHWORKS
This method statement covers the requirement for all earthwork from CH.70900 to CH.80300 and including the preparation of formation level. This method statement is to be adopted during the earthwork activities for widening and constructing of JKR road. It describes the controlling element during the execution of earthworks. 4.1
Setting Out
4.1.1
Carry out the demarcation works and establish reference marking on site.
4.1.2
All points shall be confirmed by Engineer’s Representative.
4.2
Mobilisation
4.2.1
All required machineries shall be mobilised to the site.
4.2.2
The machinery comprise of excavators, backhoe, trucks, vibratory roller, bulldozer, compactors and motor grader.
4.3
Excavation of Existing Embankment (Cutting Area)
4.3.1
Existing level shall be recorded and checked.
4.3.2
Cutting of slope embankment shall trim to ratio 1:1 or as shown in the drawing.
4.3.3
The contractor shall ensure that no slippage of soil occurs during excavation of benches.
4.3.3.1
All cut slope (where applicable) shall be hydroseeded and or treated the exposed slope within a week.
4.3.4
The contractor shall proceed any drainage works after trimming of slope finished (where applicable).
4.3.5
Hauling of the materials from the cut areas or importation of the filling materials to other areas of fill can only proceed when there are sufficient spreading and compaction machineries and plant operating at the place of deposition.
4.4
Excavation of Pits and Trenches
4.4.1
The sides of pits and trenches shall be supported where necessary.
4.4.2
Trenches and pits shall be kept free of water.
4
METHOD STATEMENT Tajar Construction Sdn Bhd
Page No. : Page 5 of 6 Revision : 0 Issued : May 2006
:
TCSB-MS-002
4.4.3
The bottom of all excavation shall be formed to the lines and levels shown on the drawings. Any pockets of soft material or loose rock in the bottom of pits and trenches shall be removed and the resulting cavities and any large fissures filled with suitable material.
4.4.4
All excavated material from trenches and pits not required for backfilling shall be disposed.
4.4.5
All backfilling for pits and trenches shall consist of suitable material. It shall be deposited and compacted by approved plant. Excavation supports shall be carefully removed as the backfilling proceeds, except where they are specified to be left in position.
4.5
Forming of Embankment and other Earth Fill (Filling Area)
4.5.1
In areas of shallow filling, where after removal of top soil, before embankment construction is commenced, the surface of the ground shall be graded and compacted.
4.5.2
All filling works shall be deposited and compacted as soon as practicable after excavation. Each layer of compaction shall not exceeding 250mm loose depth.
4.5.3
For each layer of fill, backpusher shall be used to spread loose fill evenly and compacting/vibrating roller shall be used to compact.
4.5.4
Embankment shall be built up evenly over the full width unless otherwise indicated and shall be maintained at all times with sufficient camber and an even surface to enable surface water to drain readily from them.
4.5.5
Filling of embankment shall trim to ratio 1:2 or as shown in the drawing.
4.5.6
All filling slope (where applicable) shall be closed turf or treated the exposed slope within a week.
4.5.7
The contractor shall construct retaining structure (where applicable) while earth filling activity is in progress. (Eg: Gabion wall, RE wall, Stone wall and etc)
4.5.8
The contractor shall proceed any drainage works after trimming of slope finished (where applicable).
4.5.9
During the construction of embankments, construction traffic shall be controlled in order that it act uniformly over their full width. Damage to compacted layers by construction traffic or water erosion shall be made good.
5
METHOD STATEMENT Tajar Construction Sdn Bhd
Page No. : Page 6 of 6 Revision : 0 Issued : May 2006
:
TCSB-MS-002
4.5.10
Hauling of the materials from the cut areas or importation of the filling materials to other areas of fill can only proceed when there are sufficient spreading and compaction machineries and plant operating at the place of deposition.
4.5.11
Work on embankments and cuttings in areas required for the construction of culverts and other structures shall not be carried out until construction of such structures is sufficiently advanced that there is no risk if interference or damage to them.
4.6 4.6.1
5.0
Compaction of Embankment and other Earthfill The whole of the embankment below 300mm of the subgrade formed using suitable material arising from common excavation shall be compacted to not less than 90% (for cohesive material) or 95% (for cohesionless material) of the maximum dry density.
SAFETY, HEALTH & ENVIRONMENT
5.1
Provide PPE to all workers including safety helmet, vest, etc.
5.2
Provide signboards to warn workers and public of dangers associated with construction works.
5.3
Advanced traffic warning signs will be positioned in place along and at entrance of access roads and designated flagmen will be used when working in the vicinity of existing roads if required.
5.4
All lorries will be cleaned to ensure they are free from mud prior to leaving the site.
5.5
Inspect all machinery at site and ensure that it is safe to operate.