Alcatel-Luc Alcat el-Lucent ent GSM Upgrade 9100 BTS with AN/SUM/TRE Evolution Modules
BTS Document Reconfiguration Method Release Release B10
3BK 17430 0803 RJZZA Ed.06
BLANK PAGE BREAK
Status
RELEASED
Short title
MPI80 / MDR3 All rights reserved. reserved. Passing Passing on and copying copying of this document, document, use and communication of its contents not permitted without written authorization from Alcatel-Lucent.
2 / 33
3BK 17430 0803 RJZZA Ed.06
BLANK PAGE BREAK
Status
RELEASED
Short title
MPI80 / MDR3 All rights reserved. reserved. Passing Passing on and copying copying of this document, document, use and communication of its contents not permitted without written authorization from Alcatel-Lucent.
2 / 33
3BK 17430 0803 RJZZA Ed.06
Contents
Contents Preface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5
1
7
Overvi rview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.1
1.2
1.3 1.4 1.5
2
Presentation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.1.1 Cases . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.1.2 Options . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.1.3 Restrictions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.1. 1.1.4 4 Grou Groupe ped d Task ask Sequ Sequen enc ce . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.2.1 Prerequisites . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.2. 1.2.2 2 Site Site Spec Specif ific ic Inf Informa ormati tion on . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.2.3 Externa rnal Tasks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Scheduling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Telecom elecom/Su /Superv pervisi ision on Outage Outage and Operat Operating ing Imp Impact act . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Resources . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.5.1 Tools . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.5.2 Supplies . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.5. 1.5.3 3 Appli pplica cab ble Do Docu cum ments ents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
8 8 8 9 9 10 10 10 10 11 13 15 15 15 16
Scenario . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17 2.1 2.1 2.2
2.3 2.3
2.4 2.4
2.5
Befor efore e Going oing Onsi Onsite te . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Before You Start . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.2.1 Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.2. 2.2.2 2 Requi equire red d Kno Knowledg ledge e ................................................... Scena cenari rio o Descr escrip ipti tion on . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3.1 Initial Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3. 2.3.2 2 Disp Displa lay y BTS BTS Ch Char arac acte teris risti tics cs and and Sett Settin ings gs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3. 2.3.3 3 Shut Shut Do Down wn Impa Impact cted ed Ce Cell lls s and and Mo Modu dule les s .................................. 2.3. 2.3.4 4 Chang hange e Modul odules es Insi Inside de BTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3. 2.3.5 5 Unlo Un loc ck Impa Impact cted ed Ce Cell lls s or Mo Modu dule les s ....................................... 2.3.6 Call Tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3.7 Final Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Reverse erse Proce rocedu dure re . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.4. 2.4.1 1 Shut Shut Do Down wn Impa Impact cted ed Ce Cell lls s and and Mo Modu dule les s .................................. 2.4. 2.4.2 2 Chan Ch ange ge Mo Modu dule les s Insi Inside de the the BTS BTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.4. 2.4.3 3 Unlo Un loc ck Impa Impact cted ed Ce Cell lls s or Mo Modu dule les s ....................................... 2.4.4 Call Tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.4.5 Final Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Move Rail . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3BK 17430 0803 RJZZA Ed.06
18 19 19 19 20 20 20 21 22 24 27 27 28 28 29 30 31 31 32
3 / 33
Contents
4 / 33
3BK 17430 0803 RJZZA Ed.06
Preface
Preface Purpose
This document describes how to upgrade the 9100 BTS with Evolution modules. It is applicable to BSS at technical release level B10.
What’s New
In Edition 06 In the entire document “BTS Terminal” was replaced with “BTS NEM” except the tasks referring to G2 BTS.
In Edition 05 Update in sections: Cases (Section 1.1.1) Applicable Documents (Section 1.5.3) Display BTS Characteristics and Settings (Section 2.3.2) Change Modules Inside BTS (Section 2.3.4) Update with the new equipment naming.
In Edition 04 Delivered in release. Update in section Unlock Impacted Cells or Modules (Section 2.3.5) The following sections have been updated due to system evolution: Applicable Documents (Section 1.5.3) Display BTS Characteristics and Settings (Section 2.3.2) Change Modules Inside BTS (Section 2.3.4) Unlock Impacted Cells or Modules (Section 2.3.5) Change Modules Inside the BTS (Section 2.4.2) Unlock Impacted Cells or Modules (Section 2.4.3) First official release of the document for B10 MR2.
In Edition 03
3BK 17430 0803 RJZZA Ed.06
5 / 33
Preface
The following sections were improved as a result of ystem evolution changes: Presentation (Section 1.1) Cases (Section 1.1.1) Change Modules Inside BTS (Section 2.3.4) Unlock Impacted Cells or Modules (Section 2.3.5) Change Modules Inside the BTS (Section 2.4.2) Unlock Impacted Cells or Modules (Section 2.4.3)
In Edition 02 Update in section Unlock Impacted Cells or Modules (Section 2.3.5)
In Edition 01 Update in sections: Scheduling (Section 1.3)and Telecom/Superv ision Outage and Operating Impact (Section 1.4) Update in section 2.3.4 Change Modules Inside BTS (Section 2.3.4) Overall document quality was improved following an editorial review. Shut Down Impacted Cells and Modules (Section 2.3.3), Change Module s Inside BTS (Section 2.3.4) and Unlock Impacted Cells or Modules (Section 2.3.5) were updated due to modifications in system behavior. The following sections were modified due to system evolution: Options (Section 1.1.2) Prerequisites (Section 1.2.1) Unlock Impacted Cells or Modules (Section 2.3.5). First official release of the document for B10.
Audience
This document is intended for: Field service technicians Specialists Project managers Foremen.
Assumed Knowledge
The reader must have a general knowledge of: Planning: Network architecture and reshuffling principles Scheduling. Implementation: Alcatel-Lucent operations and maintenance concepts for the BSS 9153 OMC-R operation Equipment (BSC, BTS) hardware configurations Windows environment.
6 / 33
3BK 17430 0803 RJZZA Ed.06
1 Overview
1 Overview This Overview gives information needed by project managers and foremen, for presentation to the customer and for site planning.
3BK 17430 0803 RJZZA Ed.06
7 / 33
1 Overview
1.1 Presentation This scenario is applicable if: There is no change in the BTS configuration (e.g. no TRE, sector, GPRS addition/removal during the operation) When the type of TRE is changed, the TRE frequency band remains unchanged When the ANX is changed to ANC, ANB, AGX, AGY, AGC and AGC9P, the sector frequency band remains unchanged The ANB boards can only be used for reduced configurations.
1.1.1 Cases The following cases apply: C1: Replace TRE modules: C1.1: Replace one or several TREs with Evolution TREs (EDGE compatible) C1.2: Replace one TRE/TRA with a TWIN TRA (1 TRX, Non-TX-Div, 2 RX-Div) C1.3: Replace two TRE/TRA with a TWIN TRA (2 TRX, Non-TX-Div, 2 RX-Div). C2: Replace an old SUM board with a new SUM board, where old SUM board can be SUMP or SUMA and new SUM board can be SUMA or SUMX. C3: Replace one or several ANx (ANX, ANC, ANB) modules with ANC, ANB, AGX, AGY, AGC or AGC9P modules, without SUM board move C4: Replace one or several ANx (ANX, ANC, ANB) modules with ANC, ANB or AGX, AGY, AGC or AGC9P modules, with SUM board move.
Note:
Several cases can be combined at the same time. For the reduced configurations, the ANX modules can be replaced by the ANB boards.
1.1.2 Options None.
8 / 33
3BK 17430 0803 RJZZA Ed.06
1 Overview
1.1.3 Restrictions The following restrictions apply to 9100 BTS: For 9100 BTS Mini 3x1 TRE (indoor and outdoor), ANX cannot be replaced with ANC (even if all ANX are replaced with ANC) With the old subrack version (STASR 3BK 07193 AAxx), ANX must not be replaced with ANC or with ANB (no holes for ANC or ANB screws).
1.1.4 Grouped Task Sequence The following figure shows the grouped task sequence for this scenario. OMC−R site
BTS site
Initial Checks
Display BTS Characteristics and Settings Shut Down Impacted Cells or Modules
Change Modules Inside the BTS Unlock Impacted Cells or Modules
CAll Tests
Final Checks
Figure 1: Upgrade 9100 BTS with AN / SUM / TRE Evolution Modules
3BK 17430 0803 RJZZA Ed.06
9 / 33
1 Overview
1.2 Preparation 1.2.1 Prerequisites The following prerequisites apply: For cases C1.2 and C1.3, the BTS must be equipped with SUMA The BTS must not contain any G3 TREs for a configuration with more than 12 TREs.
1.2.2 Site Specific Information You must have the following specific information to complete the scenario: At the OMC-R, availability of a workstation, with the server User Name and Password, allowing network configuration Input: customer reports about the final Alcatel-Lucent 9100 BTS configuration (which modules must be replaced).
1.2.3 External Tasks None.
10 / 33
3BK 17430 0803 RJZZA Ed.06
1 Overview
1.3 Scheduling Note:
Time based on technical constraints In the following table, the number of resources shown does not take into account individual customer or safety requirements.
Grouped Task
OMC-R
BTS
Time / Task
Initial Checks.
1 ope.
-
20 min.
1 ope.
1 Com Team
C2: 4 min.
C2: 2 min.
C2: 2 min.
C4: 2 min
-
C1: 6 min.
20 min. Display BTS Characteristics and Settings.
C4: 2 min. Shut Down Impacted Cells and Modules.
1 ope. C1: 6 min.
C2: 5 min.
C2: 5 min.
C3: 6 min.
C3: 6 min.
C4: 6 min.
C4: 6 min. Change Modules Inside the BTS.
C2: 2 min.
1 Com Team
C4: 2 min.
C1: 2 min. + 4 min. x TRE + 3 min./ board + 7 min.xTRE
C1: 2 min. + 4 min. x TRE + 3 min./ board + 7 min.xTRE C2: 12 min.
C2: 10 min.
C3: 16 min. to 41 min.
C3: 16 min. to 41 min.
C4: 2 min. + 33 min. to 58 min.
C4: 33 min. to 58 min. Unlock Impacted Cells or Modules.
1 ope.
1 Com Team
C1: 2 min.
1 min./TRE + 2 min./TRE + 2 min./TRE + 2 min. +
C2: 17 min. C3: 1 min. C4: 10 min.
C1: 4 min. + 2min. /TRE
1 Com Team 1 min./TRE + 2 min./TRE + 2 min./TRE + 2 min C1: 6 min. + 2min. /TRE C2: 17 min.
C2: -
C3: 6 min.
C3: 5 min.
C4: 16 min.
C4: 6 min. Call Tests.
3BK 17430 0803 RJZZA Ed.06
1 ope.
1 Com Team
5 min./cell
5 min./cell
5 min. /cell + 5 min. /cell
11 / 33
1 Overview
Grouped Task
OMC-R
BTS
Time / Task
Final Checks.
1 ope.
-
20 min.
1 min./TRE + 2 min./TRE + 2 min./TRE + 2 min + 5 min. / cell
40 min. + 1 min./TRE + 2 min./TRE + 2 min./TRE + 2 min + 5 min. / cell + 5 min. / cell
20 min. 40 min. + 5 min. / cell
TOTAL
+ C1: 8 min. +C2: 26 min. + C3: 7 min. + C4: 20 min.
ope.
: OMC-R operator
Com Team
: Commissioning Team
Note:
12 / 33
+ C1: 6 min. + 4 min. x TRE + 3 min./ board +C1: 14 min. + 4 + 7 min.xTRE + + min. x TRE + 3 min./ 2min. /TRE board + 7 min.xTRE + + 2min. /TRE +C2: 12 min. + C2: 38 min. + C3: 16 min. to 41 min. + 5 min. + C3: 12 min. + 16 min. to 41 min. + C4: 33 min. to 58 min. + 6 min + C4: 26 + 33 min. to 58 min
Durations are given in minutes.
3BK 17430 0803 RJZZA Ed.06
1 Overview
1.4 Telecom/Supervision Outage and Operating Impact The following table describes the traffic outage and loss of supervision caused by each grouped task. Out.Grouped Task Ref.
Tel. Out
Tel. Red
Sup. Out
Oper. Impact
Impacts ...
-
Initial Checks.
-
-
-
-
-
-
Display BTS Characteristics and Settings.
-
-
-
-
-
1, 2
Shut Down Impacted Cells and Modules.
C2: 5 min.
C1: 6 min.
-
C1: 2 min. + 4 min.xTRE + 3 min. / board + 7 min. x TRE
C2: 8 min.
C2 or C4: supervision outage on upgraded BTS and downstream BTSs
C2, C3 or C4: traffic outage on upgraded sector / BTS (from ’Lock cell’ to ’Unlock cell’) (2)
C3: 6 min. C4: 6 min.
1, 2
Change Modules Inside the BTS.
C2: 12 min. C3: 16 min. to 41 min.
C4: 17 min.
C4: 35 min. to 60 min. 1, 2
Unlock Impacted Cells or Modules.
C2: 3 min. C4: 3 min.
2 min. + 1 min. /TRE + 2 min. / TRE + 2 min. /TRE
C1: Traffic reduction or outage on upgraded cell (from ’Lock RSL’ to ’Unlock RSL’) (1)
C2: 2 min. C4: 2 min.
+ C1: 6 min. + 2 min. / TRE.
-
Call Tests.
3BK 17430 0803 RJZZA Ed.06
-
-
-
-
-
13 / 33
1 Overview
Out.Grouped Task Ref.
Tel. Out
Tel. Red
Sup. Out
Oper. Impact
Impacts ...
-
Final Checks.
-
-
-
-
-
TOTAL
C2: 20 min.
2 min. + 1 min. /TRE + 2 min. / TRE + 2 min. /TRE
C2: 10 min.
C3: 22 min. to 47 min. C4: 44 min. to 69 min.
Note:
C4: 19 min.
+C1: 14 min. + 4 min.xTRE + 3 min. / board + 7 min. x TRE + 2 min. / TRE.
Duration is given in minutes. Telecom outage particularities: C1: Only telecom reduction, except if an impacted TRE/TRA supports BCCH: related cell has 2 min. telecom outage (during BCCH recovery). If all TREs of a cell are impacted: telecom Outage1 C2 and C4: Telecom Outage1 on all cells of the BTS + telecom Outage2 (13 min. to 39 min.) on all cells of downstream BTSs (if any). On Slave BTSs, short telecom outage (all ongoing calls stopped) when the master clock comes back C3: Telecom Outage1 on the impacted cell only (only telecom reduction in the case of secondary sector).
14 / 33
3BK 17430 0803 RJZZA Ed.06
1 Overview
1.5 Resources 1.5.1 Tools 1.5.1.1 Hardware Tools Item
Part Number
Use at ...
Installation tools (for modules and radio cables installation).
-
BTS
Trace bi-band mobiles equipped with SIM cards.
-
BTS
BTS NEM (PC with CD-ROM drive and cables).
-
BTS
1.5.1.2 Software Tools Item
Part Number
Use at ...
BTS Terminal B10 software for G1/ G2 BTS, BTS NEM B10 software for 9100 / 9110 BTS.
-
BTS
Customer Documentation CD with the version associated with the current document edition. Remember that the document you are reading cannot be used as a paper version. It is online documentation using hypertext links which take you to other parts of a document on the same CD-ROM. All words in italics are hypertext links.
-
BTS, OMC-R
1.5.1.3 Forms None.
1.5.2 Supplies The following table describes the necessary supplies. Item
Part Number
Contents
Use at ...
Topology regarding operation.
-
Must be provided by customer.
BTS, OMC-R
Evolution modules.
-
Modules only, cables are reused.
BTS
3BK 17430 0803 RJZZA Ed.06
15 / 33
1 Overview
1.5.3 Applicable Documents You must have the following documents or have electronic access to the following documents: B10 BSS Methods Handbook BSS Configuration Handbook BSS Surveillance Handbook Network Reconfiguration Recommendations 9100 BTS Hardware Description BTS NEM User Guide .
16 / 33
3BK 17430 0803 RJZZA Ed.06
2 Scenario
2 Scenario This Scenario presents all checks needed before beginning the scenario, and all detailed tasks to be performed on each site.
3BK 17430 0803 RJZZA Ed.06
17 / 33
2 Scenario
2.1 Before Going Onsite Before going onsite, you must check that the following information and supplies are available: All Prerequisites (Section 1.2.1) are met The customer has been informed of the: Date and time Site name and address Purpose of operation. Personnel are available (refer to Scheduling (Section 1.3)) Site Specific Information (Section 1.2.2) is available Tools (Section 1.5.1) are available and ready for operation Supplies (Section 1.5.2) are available and ready for operation Applicable Documents (Section 1.5.3) are available. Ensure that the technical release level of the delivered board is in accordance with the BSS hardware technical release document. Ensure that the method used at the BSS site is at the same level as at the OMC-R.
18 / 33
3BK 17430 0803 RJZZA Ed.06
2 Scenario
2.2 Before You Start 2.2.1 Checks Perform the following operations: Check that all Prerequisites (Section 1.2.1) are met Check the availability of all necessary Tools (Section 1.5.1) and Supplies ( Section 1.5.2) Inform the operator. Among the cases described in Cases (Section 1.1.1) and the options described in Options (Section 1.1.2), identify which cases and options apply to you.
2.2.2 Required Knowledge You must be familiar with the following: Safety Rules and Precautions Telecom/Supervision Outage and Operating Impact (Section 1.4) Reverse Procedure Grouped Task Sequence (Section 1.1.4) Operating Hints How to document Faults and Anomalies .
3BK 17430 0803 RJZZA Ed.06
19 / 33
2 Scenario
2.3 Scenario Description This section describes how to upgrade an Alcatel-Lucent 9100 BTS with Evolution modules, in front of an Alcatel-Lucent BSC.
2.3.1 Initial Checks Note
Task Description
Site
To do
Outage
-
Perform an Audit Alarm State for the BSS.
OMC-R
10 min.
None.
-
View Status of Managed Objects and Alarms for the impacted BTS.
OMC-R
10 min.
None.
Display Cell Report for the impacted cells.
Print the list for Final Checks (Section 2.3.7).
2.3.2 Display BTS Characteristics and Settings Note
Task Description
Site
To do
Outage
C2
Display BTS Characteristics and take note of all downstream and Slave BTSs (if any).
OMC-R
2 min.
None.
Connect the BTS NEM to the old SUM of the selected BTS.
BTS
2 min. (parallel task)
None.
C4 C2
Display BTS General View window to note the Q1address , displayed in ’General Information’ panel. Display SUM Board Configuration to note the BTS position (middle or end of chain). Display SUM Board - OMU Mapping to note the OMU1 time slot value displayed. Display SUM Initial Settings to note the Line Impedance value (75 / 120 Ohms).
20 / 33
3BK 17430 0803 RJZZA Ed.06
2 Scenario
2.3.3 Shut Down Impacted Cells and Modules Note
Task Description
Site
To do
Outage
C1
Shut Down RSL Resource (WTC = 3 min.) of each selected TRE/TRA.
OMC-R
4 min.
START1
INPUT
C1 INPUT
If all TREs/TRAs of a cell are impacted, replace Shut Down RSL Resource with Shut Down Cell Traffic . Lock BSC or BTS Function (TRE/TRA) of each selected TRE/TRA.
Shut Down Cell Traffic (WTC = 3 min.).
C3
C2 and C4: For all cells mapped on the selected BTS, and for all cells mapped on its downstream BTSs (if any).
INPUT
C3 C4
1 min.
Outage1
If all TREs/TRAs of a cell are impacted, replace "Lock TRE” with Lock BSC or BTS Function (RA).
C2
C4
OMC-R
C3: For each cell mapped on the selected sectors.
OMC-R
4 min.
START1 + 2
For C3: For each cell where only the secondary sector is impacted, replace "Shut Down Cell Traffic" with Shut Down RSL Resource (WTC = 3 min.) on each TRE of this sector (cell traffic is still supported by the main sector).
Lock BSC or BTS Functions (RA) for the selected sector(s).
OMC-R
1 min.
Outage1 + 2
Inform BTS site team that they can start modules upgrade.
OMC-R / BTS
1 min.
Outage1 + 2
INPUT EXCH
3BK 17430 0803 RJZZA Ed.06
21 / 33
2 Scenario
2.3.4 Change Modules Inside BTS Note
Task Description
Site
To do
Outage
C1
When it becomes possible, from the BTS NEM, Start HW Modification .
BTS
1 min.
Outage1
Remove cables and extract ANXs (and ANYs, if necessary).
BTS
5 min. to 30 min.
Outage1 + 2
C3 C4 C3 C4
Reconfiguration of other ANYs may be necessary (uncabling / recabling).
C4: add 3 min.
Use the 9100 BTS Hardware Description to define which hardware change to do. C3 C4
Perform Move Rail (Section 2.5) if the configuration of a sector is changed (AGx instead of ANx, or the position of an antenna module belonging to this sector).
BTS
5 min.
Outage1 + 2
Remove cables and extract old TREs.
BTS
4 min.x TRE
Outage 1 + 2
For the selected TREs perform: Remove HW
BTS
1 min.
Outage 1+ 2
If a HW Configuration Modification is running perform:
BTS
4 min.
Outage1
In this case, extract all involved ANXs, ANBs, ANCs, AGCs and AGC9Ps of this sector from the backplane. Use the BTS NEM to select Remove Module(s) and remove the involved sector. C1.1 C1.2 C1.3 INPUT C1.1 C1.2 C1.3 INPUT C2 C4
Remove HW for all unplugged AN Stop HW Modification
Note: If the BTS has no AN modules left in the cabinet, ignore the Hardware Audit Alarm at the OMC-R
Wait for the ’Hardware and Alarm Audit’ at the OMC-R to finish. C2 C4 C2 C4
22 / 33
Lock BTS O&M Capability of the selected BTS, and of downstream BTSs (if any).
OMC-R
1 min.
Outage1 + 2
Inhibit Alarm Reporting on Abis TP of the selected BTS.
OMC-R
1 min.
Outage1 + 2
3BK 17430 0803 RJZZA Ed.06
2 Scenario
Note
Task Description
Site
To do
Outage
C2
Remove cables and extract the old SUM.
BTS
3 min.
Outage1 + 2
INPUT Install the new SUM and connect cables (BTS NEM and BTSCA), except the PCM (Abis) cable.
Use the 9100 BTS Hardware Description to define which hardware change to perform. C4
Remove cables, move SUM board, and reconnect all cables.
BTS
10 min.
Outage1 + 2
C3
Next, install and cable ANCs, ANBs or AGX / AGY / AGCs / AGC9Ps (disconnect bridges if necessary) to antennas, and to TREs or ANYs.
BTS
5 min.
Outage1 + 2
C4
Reconnect all modules (ANXs, ANBs, ANCs or AGCs, AGC9Ps) which should be part of the final configuration.
C1.2
Install and cable the TWIN TRA
Note: If bridges are not used, keep them on the ANC / AGX / AGY / AGC / AGC9P (screwed on the TXxOUT connectors) for future use. BTS
3 min./board
C1.3 INPUT
Outage 1 + 2
Note:Use the required configuration for the TWIN TRA for each case. C1.1
Install and cable Evolution TREs (TRAs).
BTS
7 min.xTRE
INPUT
Outage 1 + 2
Use the 9100 BTS Hardware Description to define which hardware change to perform. C2
Update the new SUM parameters:
BTS
2 min.
Outage1 + 2
BTS
1 min.
Outage1 + 2
Open Edit Q1 Address window to update the Q1 address Open SUM Initial Settings window to update the Line Impedance value (75 / 120 Ohms) of the BTS Open SUM Board Configuration window to update the BTS position (middle or end of chain). OpenSUM Board - OMU Mapping window to update the OMU1 time slot value. C2
Connect the PCM cable to the new SUM
3BK 17430 0803 RJZZA Ed.06
23 / 33
2 Scenario
2.3.5 Unlock Impacted Cells or Modules Note
Task Description
Site
To do
Outage
C2
Allow Alarm Reporting on Abis TP of the selected BTS (if not already the case), and acknowledge the alarms of Abis and downstream BTSs (if any).
OMC-R
1 min.
Outage1 + 2
When the Abis connection is done (Abis link no longer in alarm state), Unlock BTS O&M Capability of the selected BTS, and of the downstream BTSs (if any).
OMC-R
1 min.
Outage1 + 2
Unlock Cell Traffic for cells of downstream BTSs (if any).
OMC-R
1 min.
Outage1
C4 C2 C4 C2
END2 (downstream BTSs)
C4
C2 C4
Wait for end of software downloading into the selected BTS, and automatic ’Hardware and Alarm Audit’. BSS Equipment View is updated with new and moved modules.
OMC-R
During this, acknowledge alarm (MCL-XCLK) on Slave BTSs, if any.
C2: up to 13 min.
Outage1
C4: 6 min. Note:There is a short outage (ongoing calls stopped) on the Slave BTSs, when the synchronization clock from the Master BTS comes back.
C2 C4 C3 C4 INPUT
If a HW Configuration Modification was done, perform: Start HW Modification .
BTS
1 min.
Outage1
When new ANCs and/or ANBs and/or AGX / AGY / AGCs / AGC9Ps are detected by the BTS, Edit Sector Mapping and update the table.
BTS
1 min.
Outage1
Then, click on [ SAVE ]. Wait for the EEPROM update and ’cabling detection’ to finish.
C1.1
Init Single TRE for each new TRE.
Note: For ANC / AGX / AGY / AGC / AGC9P, select ’bridge’ if it is used for this antenna If the removed ANXs are still displayed, do not change their sector values. BTS
2 Outage1 min./TRE
If all TREs of a cell are impacted, replace "Initialize Single TRE" with Init Single Sector . C1.1
24 / 33
End Commissioning
BTS
2 min.
Outage1
3BK 17430 0803 RJZZA Ed.06
2 Scenario
Note
Task Description
Site
To do
Outage
C1
Stop HW Modification
BTS
1 min.
Outage1
C3
Note:The "TWIN TRE Mode Configuration" window automatically opens if the BTS is equipped with a TWIN TRA module.
C4
C1.2
Twin - TRA Settings
BTS
1 min.
Outage 1
The OMC-R automatically triggers a ’Hardware and Alarm Audit’. The BSS Equipment View is updated with new and moved modules.
-
4 min. - 10 min.
Outage1
C1.3 C1 C3 C4 On the: BTS site, wait for the config result:
success / Boot source:
message and "SBL Module States" window update Abis
OMC-R site, wait for the ’Hardware Audit’ to end and new hardware to be displayed in ’BSSUSM Main View’ (Equipment View). -
For TWIN TRAs, from the BTS NEM, Disable SBLs Other Than BTS_TEL.
BTS
1 min./ Outage TRE 1
-
Init Single TRE for each new TRE/TWIN TRA.
BTS
2 Outage1 min./TRE
-
End Commissioning
BTS
2 min.
Outage1
-
For TWIN TRAs, from the BTS NEM, Init .
BTS
2 min. / TRE
Outage1
C3
Unlock BSC or BTS Function (RA) for the disabled sector if necessary.
BTS
3 min.
Outage1
C2
Unlock Cell Traffic for disabled cells of the selected BTS.
OMC-R
1 min.
Outage1
C3
If the BTS has secondary sectors, replace "Unlock Cell Traffic" with Unlock RSL Resources for the disabled TREs.
C4
C4
Acknowledge the alarm (loss of TCH) on linked cells.
3BK 17430 0803 RJZZA Ed.06
Note: If a TRE is also changed (C1), a "loss of TCH " alarm will be displayed at the OMC-R. This will disappear after TREs initialization (C2 was not performed.)
25 / 33
2 Scenario
Note
Task Description
Site
To do
Outage
C1.1
When the HW audit is finished,Unlock BSC and BTS Function (TRE) for each selected TRE.
OMC-R
1 min.
Outage1
If all TREs of a cell are impacted, replace "Unlock TRE" with Unlock BSC and BTS Function (RA). C1.1
Unlock RSL Resources of impacted TREs.
OMC-R
1 min.
END1 (C1)
If all the TREs of a cell are impacted, replace ’Unlock RSL’ with Unlock Cell Traffic (when RA is initialized).
26 / 33
3BK 17430 0803 RJZZA Ed.06
2 Scenario
2.3.6 Call Tests Note
Task Description
Site
To do
Outage
-
Call Test on the BTS.
BTS
5 min./ cell
None.
This task must done in parallel with the OMC-R tasks in order to save time. ’Unlock Cell’ from Call Test is not required. CHECK
Display USD Detailed Cell Information to check if calls are made on impacted cells.
OMC-R
5 min./ cell
None.
Note:From this point, if the call tests failed, perform the Reverse Procedure (Section 2.4).
2.3.7 Final Checks Note
Task Description
Site
To do
Outage
-
Perform an Audit/Alarm State for the BSS.
OMC-R
10 min.
None.
-
View Status of Managed Objects and Alarms for the impacted BTS.
OMC-R
10 min.
None.
Display Cell Report for the impacted cells.
3BK 17430 0803 RJZZA Ed.06
Note:Compare the status of Managed Objects and alarms with the results printed in the Initial Checks (Section 2.3.1).
27 / 33
2 Scenario
2.4 Reverse Procedure The reverse procedure describes how to return to the initial BTS configuration. Once the "Sector Mapping" table exists inside the BTS, it cannot be deleted. ANX rotary switches are no longer effective. The "Sector Mapping" table in the BTS Remote Inventory must be updated with the initial configuration parameters.
2.4.1 Shut Down Impacted Cells and Modules Note
Task Description
Site
To do
C1
When possible, from the BTS, Shut Down RSL Resource (WTC = 3 min.) of each selected TRE/TWIN TRA.
OMC-R
4 min.
Lock BSC or BTS Functions (TRE) for each selected TRE/TWIN TRA.
OMC-R
INPUT
C1 INPUT
Shut Down Cell Traffic (WTC = 3 min.)
C3
C2 and C4: For all cells mapped on the selected BTS, and for all cells mapped on its downstream BTSs (if any).
C4
C3 C4
If all TREs/TWIN TRAs of a cell are impacted, replace Shut Down RSL Resource with Shut Down Cell Traffic . 1 min.
-
If all TREs/TWIN TRAs of a cell are impacted, replace "Lock TRE" with Lock BSC or BTS Functions (RA).
C2
INPUT
Outage
C3: For each cell mapped on the selected sectors.
OMC-R
4 min.
-
For each cell where only the secondary sector is impacted, replace Shut Down Cell Traffic with Shut Down RSL Resource (WTC = 3 min.) on each TRE of this sector (cell traffic is still supported by the main sector).
Lock BSC or BTS Functions (RA) for the selected sector(s).
OMC-R
1 min.
-
Lock BTS O&M Capability of the selected BTS and of downstream BTSs (if any).
OMC-R
1 min.
-
Inform BTS site team they can start modules change.
OMC-R / BTS
1 min.
-
INPUT C2 C4 EXCH
28 / 33
3BK 17430 0803 RJZZA Ed.06
2 Scenario
2.4.2 Change Modules Inside the BTS Note
Task Description
Site
To do
Outage
C1
When possible, from the BTS NEM, Start HW Modification .
BTS
1 min.
-
C1
Remove cables and extract Evolution TREs (TRAs)/TWIN TRAs.
BTS
4 min.xTRE
-
C1
Install and cable previous TREs.
BTS
3 min./board
-
C3 C4
Restore initial configuration. C2
Remove cables and extract the new SUM. Install previous SUM and reconnect all cables.
C3 C4
BTS
4 min.
-
Restore initial configuration.
Remove cables and extract ANCs or/ and ANBs and/or AGX / AGY / AGCs / AGC9Ps.
BTS
5 min. to 30 min.
Remove cables, move SUM board, and connect all cables again (if C3).
Restore initial configuration.
-
C4: add 3 min.
Perform Move Rail (Section 2.5), if needed, then install and cable previous ANXs (and previous ANYs, if necessary) to antennas, and to TREs or ANYs.
3BK 17430 0803 RJZZA Ed.06
29 / 33
2 Scenario
2.4.3 Unlock Impacted Cells or Modules Note
Task Description
Site
To do
Outage
C2
Check Alarm Reporting on Abis TP of the selected BTS, and acknowledge the alarms of Abis and downstream BTSs (if any).
OMC-R
1 min.
-
When the Abis connection is done (Abis link no longer in alarm state), Unlock BTS O&M Capability of the selected BTS, and of the downstream BTSs (if any).
OMC-R
1 min.
-
Unlock Cell Traffic for cells of downstream BTSs (if any).
OMC-R
1 min.
-
Wait for end of software downloading into the selected BTS, and automatic ’Hardware and Alarm Audit’. The BSS Equipment View is updated with previous and moved modules.
OMC-R
6 min.
-
C4 C2 C4 C2 C4 C2 C4
Note:There is a short outage (ongoing calls stopped) on Slave BTSs, when the synchronization clock from the Master BTS comes back.
Acknowledge alarms (MCL-XCLK) on Slave BTSs, if any. C3 C4 INPUT
When previous ANXs (just reinstalled) are detected by the BTS, Edit Sector Mapping and update the table.
BTS
Stop HW Modification .
BTS
C3
C3
1 min.
-
Note:Perform this task only if C2 was not performed.
C4 C1
-
Note:If the removed ANCs or / and ANBs or/and AGX / AGY / AGCs / AGC9Ps are still displayed, do not change their sector values.
Then, click on [ SAVE ]. Wait for the EEPROM update and ’cabling detection’ to finish.
C1
1 min.
The OMC-R automatically triggers a ’Hardware and Alarm Audit.’. The BSS Equipment View is updated with previous and moved modules.
C4
-
4 min.
-
On the: BTS site, wait for the config result: success / Boot source:
Abis
message and "SBL Module States" window update OMC-R site, wait for ’Hardware Audit’ to end and previous hardware to be displayed on the ’BSSUSM Main View’ (Equipment View). C3 C4
30 / 33
Unlock BSC or BTS Function (RA) for the disabled sector.
OMC-R
3 min.
-
3BK 17430 0803 RJZZA Ed.06
2 Scenario
Note
Task Description
Site
To do
Outage
C1
Init (TRE) for disabled TREs.
BTS
1 min.
-
If all TREs of a cell are impacted, replace "Initialize TRE" with Init (RA). C1
-
When TRE initialization is finished in BSSUSM Functional, View, Unlock RSL Resources of the disabled TREs.
OMC-R
Unlock Cell Traffic for disabled cells of the selected BTS.
OMC-R
-
1 min.
If all TREs of a cell are impacted, replace ’Unlock RSL’ with Unlock Cell Traffic (when RA is initialized). -
1 min.
If the BTS has secondary sectors, replace ’Unlock Cell Traffic’ with Unlock RSL Resources of the disabled TREs. Acknowledge alarms (loss of TCH) on linked cells.
2.4.4 Call Tests Note
Task Description
Site
To do
Outage
-
Call Test on the BTS.
BTS
5 min./ cell
-
This task must be done in parallel with the OMC-R tasks to save time. ’Unlock Cell’ from Call Test is not required. CHECK
Display USD Detailed Cell Information to check if calls are made on impacted cells.
OMC-R
5 min./ cell
-
2.4.5 Final Checks Note
Task Description
Site
To do
Outage
-
Perform an Audit/Alarm State for the BSS.
OMC-R
10 min.
-
CHECK
View Status of Managed Objects and Alarms for the impacted BTS.
OMC-R
10 min.
-
Compare the status of Managed Objects and alarms with the results printed in Initial Checks.
3BK 17430 0803 RJZZA Ed.06
31 / 33
2 Scenario
2.5 Move Rail For the STASR 3BK 07193 ABxx subrack, rails must be moved before the ANC or ANB installation. The ANC and ANB must not be installed into the STASR 3BK 07193 AAxx subrack (no holes for ANC and ANB screws). If the ANC is to be plugged in: On the left, in the subrack: The previous ANX uses slot number 4 The new ANC or ANB uses slot number 3 Action: Move second pair of rails (bottom and top), counting from left to right, in one step.
Note:
If the SUM module must be moved, it goes from slot 1 to slot 7. On the right, in the subrack: The previous ANX uses slot number 10 The new ANC or ANB uses slot number 11 Action: Move the two pairs of rails (bottom and top), counting from right to left, in one step.
32 / 33
3BK 17430 0803 RJZZA Ed.06