ANALISA HARGA SATUAN PEKERJAAN PEKERJAAN PEMBANGUNAN RUMAH PRASARANANNYA DI LOKASI BUMI PALIR SEJAHTERA PERUM PERUMNAS CABANG SEMARANG I
NO. 1 1
2
KOEF.
SAT
U R A I A N.
2
3
4
1 M1 NORMALISASI SALURAN 1.0000 Ls Alat Bantu 0.0750 Uph Mandor 0.5000 Uph Tukang batu 0.7500 Uph Pekerja
1 M2 PAS.BATU BATA KOSONG 80.0000 Bh Batu bata 0.0100 Uph Mandor 0.0500 Uph Tukang batu 0.1000 Uph Pekerja
H. SATUAN BAHAN/UPAH ( Rp ) 5
HARGA BAHAN ( Rp ) 6
1,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
1,000.00 1,000.00
350.00 40,000.00 37,000.00 35,000.00 JUMLAH
28,000.00 28,000.00
UPAH TENAGA ( Rp ) 7
3,000.00 18,500.00 26,250.00 47,750.00 Dibulatkan
400.00 1,850.00 3,500.00 5,750.00 Dibulatkan
3
1 M3 BATU KOSONG (Memasukkan ke Sumur Resapan) 1.1000 M3 Batu kali bulat 0.1250 Uph Mandor 0.2500 Uph Pekerja
4 1 M3 URUGAN SIRTU & PEMADATAN 1.20 M3 Sirtu 1.0000 Ls Gilas Pemadatan 0.0250 Uph Mandor 0.25 Upah Pekerja
120,000.00 40,000.00 35,000.00 JUMLAH
72,500.00 10,000.00 40,000.00 35,000.00 JUMLAH
132,000.00
132,000.00
6 1 M' PEKERJAAN JALAN PAVING DMJ 6(lebar Perkerasan 3 m) 0.6000 m3 Galian Tanah 2.8000 m2 Urugan Sirtu t = 20 cm 2.8000 m2 Paving tebal 6 cm 4.0000 Bh Beton Kanstein uk. 20 x 30 x 50 cm 1.0000 Ls Pembersihan & Perataan
7 1 M2 PEKERJAAN JALAN PAVING TEBAL 8 CM 0.0600 m3 Pasir Urug & pengisi 1.0000 m2 Paving tebal 8 cm 1.0000 Ls Upah Pasang
60,000.00 35,000.00 3,000.00 JUMLAH
15,600.00 21,350.00 41,600.00 12,000.00 12,000.00 JUMLAH
10,000.00 1,000.00 8,750.00 19,750.00 Dibulatkan
87,000.00 10,000.00 1,000.00 8,750.00 106,750.00 106,750.00
60,000.00 45,000.00 3,000.00 JUMLAH
Dibulatkan
21,350.00 21,350.00
Dibulatkan
3,600.00 35,000.00 3,000.00 41,600.00 41,600.00
3,600.00 35,000.00 3,000.00 3,000.00
38,600.00
9,360.00 59,780.00 116,480.00 48,000.00 224,260.00
12,000.00 21,360.00 Dibulatkan
3,600.00 45,000.00 3,000.00 3,000.00
48,600.00 Dibulatkan
7 1 M' PEKERJAAN JALAN PAVING DMJ 7 (lebar Perkerasan 4 m) 0.6000 m3 Galian Tanah 3.1000 m2 Urugan Sirtu t = 20 cm 3.1000 m2 Paving tebal 8 cm 4.0000 bh Beton Kanstein uk. 20 x 30 x 50 cm 0.0000 Ls Pembersihan & Perataan
15,600.00 21,350.00 51,600.00 12,000.00 5,000.00 JUMLAH
28,000.00 400.00 1,850.00 3,500.00 33,750.00 33,750.00
132,000.00 5,000.00 8,750.00 145,750.00 145,750.00
1 m2 Urugan Sirtu tebal 20 cm =
5 1 M2 PEKERJAAN JALAN PAVING TEBAL 6 CM 0.0600 m3 Pasir Urug & pengisi 1.0000 m2 Paving tebal 6 cm 1.0000 Ls Upah Pasang
1,000.00 3,000.00 18,500.00 26,250.00 48,750.00 48,750.00
5,000.00 8,750.00 13,750.00 Dibulatkan
87,000.00
87,000.00
JUMLAH H. SATUAN ( Rp ) 8
9,360.00 66,185.00 159,960.00 48,000.00 9,360.00
274,145.00 Dibulatkan
9,360.00 59,780.00 116,480.00 48,000.00 12,000.00 245,620.00 245,620.00
3,600.00 45,000.00 3,000.00 51,600.00 51,600.00
9,360.00 66,185.00 159,960.00 48,000.00 283,505.00 283,500.00
1
2 3 4 8 1 M' PEKERJAAN JALAN PAVING DMJ 8 (lebar Perkerasan 4 m) 0.8000 m3 Galian Tanah 3.8000 m2 Urugan Sirtu t = 20 cm 3.8000 m2 Paving tebal 8 cm 4.0000 bh Beton Kanstein uk. 20 x 30 x 50 cm 1.0000 Ls Pembersihan & Perataan
9 1 M' PEKERJAAN JALAN PAVING DMJ 10 (lebar Perkerasan 5 m) 1.0000 m3 Galian Tanah 4.8000 m2 Urugan Sirtu t = 20 cm 4.8000 m2 Paving tebal 8 cm 4.0000 bh Beton Kanstein uk. 20 x 30 x 50 cm 1.0000 Ls Pembersihan & Perataan
10 1 M' PEKERJAAN JALAN PAVING DMJ 12 (lebar Perkerasan 6 m) 1.2000 m3 Galian Tanah 5.8000 m2 Urugan Sirtu t = 20 cm 5.8000 m2 Paving tebal 8 cm 4.0000 bh Beton Kanstein uk. 20 x 30 x 50 cm 1.0000 Ls Pembersihan & Perataan
11 1 M' PEK. SALURAN TYPE S.1 ( Pas. Dinding. 15 Cm ) 0.3450 M3 Galian Tanah 0.0200 M3 Urugan Pasir 0.2100 M3 Pas Batu belah kali 1 : 4 0.3400 M2 Plesteran Ban-banan 1:3 0.1000 M' Sulingan Pipa PVC 1" pj. 25 Cm 0.0000 Ls Perapihan berm
5 15,600.00 21,350.00 51,600.00 12,000.00 12,000.00 JUMLAH
15,600.00 21,350.00 51,600.00 12,000.00 12,000.00 JUMLAH
6
7
8
12,480.00 81,130.00 196,080.00 48,000.00 325,210.00
12,000.00 24,480.00 Dibulatkan
15,600.00 102,480.00 247,680.00 48,000.00 398,160.00
15,600.00 21,350.00 51,600.00 12,000.00 4,000.00 JUMLAH
471,110.00
15,600.00 60,000.00 439,870.00 24,480.00 12,500.00 1,000.00 JUMLAH
5,382.00 1,200.00 92,372.70 8,323.20 1,250.00 108,527.90
12,000.00 27,600.00 Dibulatkan
18,720.00 123,830.00 299,280.00 48,000.00 4,000.00 22,720.00 Dibulatkan
Dibulatkan
12,480.00 81,130.00 196,080.00 48,000.00 12,000.00 349,690.00 349,690.00
15,600.00 102,480.00 247,680.00 48,000.00 12,000.00 425,760.00 425,760.00
18,720.00 123,830.00 299,280.00 48,000.00 4,000.00 493,830.00 493,830.00
5,382.00 1,200.00 92,372.70 8,323.20 1,250.00 108,527.90 108,520.00
` 12 1 M' PEK. SALURAN TYPE S.2 ( Pas. Dinding. 15 Cm ) 0.5063 M3 Galian Tanah 0.0275 M3 Urugan Pasir 0.2355 M3 Pas Batu belah kali 1 : 4 0.6000 M2 Plesteran Ban-banan 1:3 0.4000 Ls Sulingan Pipa PVC 1" pj. 25 Cm 1.0000 Ls Perapihan berm
15,600.00 60,000.00 439,870.00 24,480.00 12,500.00 1,000.00 JUMLAH
7,897.50 1,650.00 103,589.39 14,688.00 5,000.00 1,000.00 125,927.39
7,897.50 Dibulatkan
13 1 M' PEK. SALURAN TYPE S.3 ( Pas. Dinding. 15 Cm ) 0.6588 M3 Galian Tanah 0.0325 M3 Urugan Pasir 0.2925 M3 Pas Batu kali 1 : 4 0.5000 M2 Plesteran Ban-banan 1:3 0.2500 Ls Sulingan Pipa PVC 1" pj. 25 Cm 1.0000 Ls Perapihan berm
14 1 M' PEK. SALURAN TANAH TYPE S.3 0.6588 M3 Galian Tanah 1.0000 Ls Perapihan galian & Berm
15,600.00 60,000.00 439,870.00 24,480.00 12,500.00 1,000.00 JUMLAH
1,950.00 128,661.98 12,240.00 3,125.00 1,000.00 146,976.98
10,276.50
15,600.00 3,500.00 JUMLAH
3,500.00 3,500.00
10,276.50 Dibulatkan
10,276.50 10,276.50 Dibulatkan
7,897.50 1,650.00 103,589.39 14,688.00 5,000.00 1,000.00 133,824.89 133,820.00
10,276.50 1,950.00 128,661.98 12,240.00 3,125.00 1,000.00 157,253.48 157,250.00
10,276.50 3,500.00 13,776.50 13,770.00
1
2 3 4 15 1 M' PEK. TERJUNAN SALURAN TYPE S.3 (Pas didnding 20 cm ) 0.9000 M3 Galian Tanah 0.0500 M3 Urugan Pasir 0.6100 M3 Pas Batu kali 1 : 4 1.0800 M2 Plesteran Ban-banan 1:3 0.2500 Ls Sulingan Pipa PVC 1" pj. 25 Cm 1.0000 Ls Perapihan berm
16 1 M' PEK. SALURAN TYPE S.4 ( Pas. Dinding. 15 Cm ) 0.8750 M3 Galian Tanah 0.0600 M3 Urugan Pasir 0.4600 M3 Pas Batu kali 1 : 4 0.6000 M2 Plesteran Ban-banan 1:3 0.2500 Ls Sulingan Pipa PVC 1" pj. 25 Cm 1.0000 Ls Perapihan berm
17 1 M' PEK. TERJUNAN SALURAN TYPE S.5 ( Pas. Dinding. 20 Cm ) 1.2000 M3 Galian Tanah 0.0600 M3 Urugan Pasir 0.7100 M3 Pas Batu kali 1 : 4 1.0800 M2 Plesteran Ban-banan 1:3 0.2500 Ls Sulingan Pipa PVC 1" pj. 25 Cm 1.0000 Ls Perapihan berm
18 1 M' PEK. GORONG-GORONG TYPE GR.1 1.1480 M3 Galian Tanah 0.0700 M3 Urugan Pasir 0.5500 M3 Pas Batu kali 1 : 4 1.3000 M2 Pleteran 1:3 0.2520 M2 Urugan Tanah Kembali 0.0960 M3 Plat Cor Beton bertulang 1:2:3 1.0000 Ls Perapihan berm
19 1 M' PEK. GORONG-GORONG TYPE GR.2 1.3500 M3 Galian Tanah 0.0750 M3 Urugan Pasir 0.6300 M3 Pas Batu kali 1 : 4 1.5000 M2 Pleteran 1:3 0.2940 M2 Urugan Tanah Kembali 0.0900 M3 Plat Cor Beton bertulang 1:2:3 1.0000 Ls Perapihan berm
27 1 M'. PEK. GORONG-GORONG TYPE GR.3 1.6320 M3 Galian Tanah 0.0800 M3 Urugan Pasir 0.7100 M3 Pas Batu kali 1 : 4 1.9000 M2 Pleteran 1:3 0.3360 M2 Urugan Tanah Kembali 0.1200 M3 Plat Cor Beton bertulang 1:2:3 1.0000 Ls Perapihan berm
5
6
15,600.00 60,000.00 439,870.00 24,480.00 1,000.00 1,000.00 JUMLAH
3,000.00 268,320.70 26,438.40 250.00 1,000.00 299,009.10
15,600.00 60,000.00 439,870.00 24,480.00 1,000.00 1,000.00 JUMLAH
3,600.00 202,340.20 14,688.00 250.00 1,000.00 221,878.20
15,600.00 60,000.00 439,870.00 24,480.00 1,000.00 1,000.00 JUMLAH
3,600.00 312,307.70 26,438.40 250.00 1,000.00 343,596.10
15,600.00 60,000.00 439,870.00 24,480.00 7,480.00 3,008,750.00 2,000.00 JUMLAH
4,200.00 241,928.50 31,824.00 1,884.96 288,840.00 2,000.00 570,677.46
15,600.00 60,000.00 439,870.00 24,480.00 7,480.00 3,008,750.00 2,000.00 JUMLAH
4,500.00 277,118.10 36,720.00 2,199.12 270,787.50 2,000.00 593,324.72
15,600.00 60,000.00 439,870.00 24,480.00 7,480.00 3,008,750.00 2,000.00 JUMLAH
4,800.00 312,307.70 46,512.00 2,513.28 361,050.00 2,000.00 729,182.98
7 14,040.00
14,040.00 Dibulatkan
13,650.00
13,650.00 Dibulatkan
18,720.00
18,720.00 Dibulatkan
17,908.80
17,908.80 Dibulatkan
21,060.00
21,060.00 Dibulatkan
25,459.20
25,459.20 Dibulatkan
8 14,040.00 3,000.00 268,320.70 26,438.40 250.00 1,000.00 313,049.10 313,040.00
13,650.00 3,600.00 202,340.20 14,688.00 250.00 1,000.00 235,528.20 235,520.00
18,720.00 3,600.00 312,307.70 26,438.40 250.00 1,000.00 362,316.10 362,310.00
17,908.80 4,200.00 241,928.50 31,824.00 1,884.96 288,840.00 2,000.00 588,586.26 588,580.00
21,060.00 4,500.00 277,118.10 36,720.00 2,199.12 270,787.50 2,000.00 614,384.72 614,380.00
25,459.20 4,800.00 312,307.70 46,512.00 2,513.28 361,050.00 2,000.00 754,642.18 754,640.00
1
2
3
4
5
6
7
8
20 1 BH PEK. GORONG-GORONG TYPE GR.1 DMJ 5 M' 3.6000 BH Pekerjaan GR 1
588,580.00
2,118,000.00
2,118,000.00
21 1 BH PEK. GORONG-GORONG TYPE GR.2 DMJ 5 M' 3.4000 BH Pekerjaan GR 2
754,640.00
2,565,000.00
2,565,000.00
22 1 BH PEK. GORONG-GORONG TYPE GR.1 DMJ 6 M' 4.3000 BH Pekerjaan GR 1
588,580.00
2,530,000.00
2,530,000.00
23 1 BH PEK. GORONG-GORONG TYPE GR.2 DMJ 6 M' 4.6000 M' Pekerjaan GR 2
614,380.00
2,826,000.00
2,826,000.00
24 1 BH PEK. GORONG-GORONG TYPE GR.2 DMJ 7 M' 5.0000 M' Pekerjaan GR 2
614,380.00
3,071,000.00
3,071,000.00
26 1 BH PEK. GORONG-GORONG TYPE GR.2 DMJ 8 M' 6.0000 M' Pekerjaan GR 2
614,380.00
3,686,000.00
3,686,000.00
27 1 BH PEK. GORONG-GORONG TYPE GR.2 DMJ 12 M' 7.5000 M' Pekerjaan GR 2
614,380.00
4,607,000.00
4,607,000.00
27 1 BH PEK. GORONG-GORONG TYPE GR.3 DMJ 8 6.2000 M' Pekerjaan GR 3
754,640.00
4,678,768.00
4,678,768.00
3,008,750.00
134,792.00
28 1 BH. JEMBATAN MASUK PLAT BETON BERTULANG 1:2:3 (S1) 0.0448 M3 Plat Cor Beton bertulang 1:2:3
29 1 BH. JEMBATAN MASUK PLAT BETON BERTULANG 1:2:3 (S2) 0.0512 M3 Plat Cor Beton bertulang 1:2:3
30 1 BH. JEMBATAN MASUK PLAT BETON BERTULANG 1:2:3 (S3) 0.0648 M3 Plat Cor Beton bertulang 1:2:3
31 1 M2. PEK. GEBALAN RUMPUT 0.1800 M3 Urugan Tanah digemburkan 1.0000 M2 Gebalan rumput gajah 1.0000 Ls Pemupukan 1.0000 Ls Perapihan berm
32 1 BH SUMUR RESAPAN t = 1,5 m 1.9311 M3 Galian Tanah 0.4760 M3 Urugan Tanah kembali 3.2000 m2 Pas. batu-bata ad. 1 : 5 9.0000 Bh Suling 2 PVC Ø 1 1/4" 0.7041 M3 batu kali kosong 1.0000 kg Pas. lapisan ijuk 0.0471 M3 Tutup Beton Bertulang
3,008,750.00
3,008,750.00
69,750.00 7,500.00 2,000.00 500.00 JUMLAH
15,600.00 7,480.00 56,380.00 17,500.00 145,750.00 7,500.00 3,008,750.00 JUMLAH
Dibulatkan
134,792.00 134,790.00
Dibulatkan
154,048.00 154,040.00
Dibulatkan
194,967.00 194,960.00
Dibulatkan
12,555.00 7,500.00 2,000.00 500.00 22,555.00 22,550.00
154,048.00
194,967.00
12,555.00 7,500.00 2,000.00 500.00 22,555.00
-
30,125.16 3,560.48 180,416.00 157,500.00 102,629.13
440,545.13
7,500.00 141,712.13 182,897.77 Dibulatkan
30,125.16 3,560.48 180,416.00 157,500.00 102,629.13 7,500.00 141,712.13 623,442.90 623,440.00
1
2 3 4 33 1 BH. PEK . PENANAMAN POHON PELINDUNG 0.1250 M3 Galian Tanah 0.0750 M3 Urugan Tanah Kembali 0.0250 M3 Pupuk Kandang 1.0000 Bh. Pohon Angsana t. 1,5 m' 1.0000 Ls Steger / Pengaman 1.0000 Ls Upah
5 15,600.00 7,480.00 75,000.00 25,000.00 2,000.00 2,200.00 JUMLAH
6
7
8 1,950.00 561.00
1,875.00 25,000.00 2,000.00 2,200.00 4,711.00
28,875.00 Dibulatkan
34 1 BH. PEK . PAPAN NAMA JALAN 0.0450 M3 Galian Tanah 0.0030 M3 Urugan pasir 0.0720 M3 Cor beton 1:3:5 0.0145 M3 Urugan Tanah Kembali 1.0000 Bh. Papan Nama Jalan
35 1 M3 PEKERJAAN CUT TANAH KERAS 0.0386 Jam Boldozer D5 0.0634 Jam Excavator PC 200 0.0096 Jam Mandor 0.0386 Jam Pekerja 1.0000 Ls Alat bantu
36 1 M3 PEKERJAAN FILL 0.0193 Jam 0.0843 Jam 0.0386 Jam 0.0096 Jam 1.0000 Ls
Boldozer D5 Dump Truck Pekerja Mandor Alat bantu
15,600.00 60,000.00 469,200.00 7,480.00 200,000.00 JUMLAH
250,000 225,000 40,000 35,000 75 JUMLAH
702.00
Dibulatkan
702.00 180.00 33,782.40 108.46 200,000.00 234,772.86 234,770.00
Dibulatkan
9,638.55 14,267.60 385.54 1,349.40 75.00 25,716.09 25,710.00
180.00 33,782.40 108.46 200,000.00 233,962.40
810.46
9,638.55 14,267.60 385.54 1,349.40 75.00 1,809.94
23,906.15
250,000 60,000 35,000 40,000 50 JUMLAH
9,879.52
4,819.28 5,060.24
50,000 JUMLAH
60,000.00 69,879.52
1,349.40 385.54 50.00 1,784.94 Dibulatkan
1.2000 m3
Tanah Urug
1,950.00 561.00 1,875.00 25,000.00 2,000.00 2,200.00 33,586.00 33,580.00
2,220.48 Dibulatkan
\\vboxsrv\conversion_tmp\scratch_4\[146701492.xls.ms_office.xls]RS 36 Cempaka Semarang,
Maret 2011
Ass Man Produksi & PLPP
AMAT IMRON
4,819.28 5,060.24 1,349.40 385.54 50.00 11,664.46 11,660.00 60,000.00 71,660.00 71,660.00
ANALISA HARGA SATUAN PEKERJAAN PEKERJAAN PEMBANGUNAN RUMAH PRASARANANNYA DI LOKASI BUMI PALIR SEJAHTERA PERUM PERUMNAS CABANG SEMARANG I
NO.
KOEF.
SAT
U R A I A N.
1
2
3
4
1
PASANGAN BOUWPLANK / M'. 0.0054 M3 Kayu Kaso 4/6 & 2/3 0.0250 Kg Paku biasa uk. 2" - 5" 0.0070 Uph Mandor 0.0700 Uph Tukang Kayu
H. SATUAN BAHAN/UPAH ( Rp ) 5
900,000.00 9,000.00 40,000.00 37,000.00 JUMLAH
M' Pas. Bouplank (Bahan 2 x pakai)
HARGA BAHAN ( Rp ) 6
UPAH TENAGA ( Rp ) 7
4,860.00 225.00 5,085.00 5,085.00
280.00 2,590.00 2,870.00
4,860.00 225.00 280.00 2,590.00 7,955.00
2,870.00
6,520.00 6,520.00
200.00 1,750.00 1,950.00
200.00 1,750.00 1,950.00 1,950.00
Dibulatkan 2
1 M2 PEKERJAAN STRIPPING 0.0050 Uph Mandor 0.0500 Uph Pekerja
40,000.00 35,000.00 JUMLAH
Dibulatkan
3
4
5
6
7
1 M3 GALIAN TANAH BIASA SEDALAM 1 M 0.0400 Uph Mandor 0.4000 Uph Pekerja
1 M3 GALIAN TANAH KERAS SEDALAM 1 M 0.0625 Uph Mandor 0.6250 Uph Pekerja
1 M3 GALIAN TANAH CADAS SEDALAM 1 M 0.1250 Uph Mandor 1.2500 Uph Pekerja
1 M3 GALIAN TANAH LUMPUR SEDALAM 1 M 0.0823 Uph Mandor 0.8230 Uph Pekerja
1 M3 URUGAN TANAH KEMBALI. 0.0192 Uph Mandor 0.1920 Uph Pekerja
40,000.00 35,000.00 JUMLAH
-
1,600.00 14,000.00 15,600.00 Dibulatkan
1,600.00 14,000.00 15,600.00 15,600.00
40,000.00 35,000.00 JUMLAH
-
2,500.00 21,875.00 24,375.00 Dibulatkan
2,500.00 21,875.00 24,375.00 24,370.00
40,000.00 35,000.00 JUMLAH
-
5,000.00 43,750.00 48,750.00 Dibulatkan
5,000.00 43,750.00 48,750.00 48,750.00
40,000.00 35,000.00 JUMLAH
-
3,292.00 28,805.00 32,097.00 Dibulatkan
3,292.00 28,805.00 32,097.00 32,090.00
40,000.00 35,000.00 JUMLAH
-
768.00 6,720.00 7,488.00
768.00 6,720.00 7,488.00 7,480.00
1,000.00 8,750.00 9,750.00 Dibulatkan
60,000.00 1,000.00 8,750.00 69,750.00 69,750.00
1,376.00 12,040.00 13,416.00 Dibulatkan
1,376.00 12,040.00 13,416.00 13,410.00
Dibulatkan 8
9
1 M3 URUGAN TANAH DARI LUAR 1.2000 M3 Tanah urug 0.0250 Uph Mandor 0.2500 Uph Pekerja
1 M3 PEMBUANGAN TANAH SEJAUH 100 M 0.0344 Uph Mandor 0.3440 Uph Pekerja
JUMLAH H. SATUAN ( Rp ) 8
50,000.00 40,000.00 35,000.00 JUMLAH
40,000.00 35,000.00 JUMLAH
60,000.00 60,000.00
-
1 10
2
3
4
1 M2 PERATAAN TANAH 1.0000 Unit Alat bantu 0.0125 Uph Mandor 0.0400 Uph Pekerja
5 500.00 40,000.00 35,000.00 JUMLAH
6
7
8
500.00 500.00 1,400.00 1,900.00
500.00 Dibulatkan
11
1 M3 URUGAN SIRTU BAWAH LANTAI 1.1000 M3 Sirtu 0.0250 Uph Mandor 0.2500 Uph Pekerja
72,500.00 40,000.00 35,000.00 JUMLAH
79,750.00 79,750.00
1,000.00 8,750.00 9,750.00
79,750.00 1,000.00 8,750.00 89,500.00 89,500.00
10,000.00 1,000.00 8,750.00 19,750.00 Dibulatkan
87,000.00 10,000.00 1,000.00 8,750.00 106,750.00 106,750.00
Dibulatkan 12
1 M3 URUGAN SIRTU & PEMADATAN 1.2000 M3 Sirtu 1.0000 Ls Gilas Pemadatan 0.0250 Uph Mandor 0.2500 Upah Pekerja
0.2000
m3
1 M2 URUGAN SIRTU TEBAL 20 Cm
72,500.00 10,000.00 40,000.00 35,000.00 JUMLAH
87,000.00 87,000.00
106,750.00
21,350.00 21,350.00
Dibulatkan 13
14
15
16
17
1 M3 URUGAN PADAS BAWAH LANTAI 1.2000 M3 Padas urug 0.0250 Uph Mandor 0.2500 Uph Pekerja
1 M3 URUGAN PASIR BAWAH LANTAI & PONDASI 1.2000 M3 Pasir urug 0.0100 Uph Mandor 0.3000 Uph Pekerja
1 M3 PAS.BATUKALI AD. 1 Pc : 5 Ps 3.4000 Zak PC (Portland Cement ) 40 kg 1.1000 M3 Batu kali 0.5440 M3 Pasir pasang 0.0750 Uph Mandor 0.6000 Uph Tukang batu 1.5000 Uph Pekerja
1 M3 PAS.BATUKALI AD. 1 Pc : 4 Ps 4.0750 Zak PC (Portland Cement ) 40 kg 1.1000 M3 Batu kali 0.5200 M3 Pasir pasang 0.0750 Uph Mandor 0.6000 Uph Tukang batu 1.5000 Uph Pekerja
1 M3 PAS. BATU KALI ad. 1 Pc : 3 Kp : 10 Ps 1.5250 Zak PC (Portland Cement ) 40 kg 1.1000 M3 Batu kali 0.4920 M3 Pasir pasang 0.1470 M3 Kapur 0.0750 Uph Mandor 0.6000 Uph Tukang batu 1.5000 Uph Pekerja
45,000.00 40,000.00 35,000.00 JUMLAH
500.00 500.00 1,400.00 2,400.00 2,400.00
54,000.00 54,000.00
1,000.00 8,750.00 9,750.00 Dibulatkan
54,000.00 1,000.00 8,750.00 63,750.00 63,750.00
60,000.00 40,000.00 35,000.00 JUMLAH
72,000.00 72,000.00
400.00 10,500.00 10,900.00 Dibulatkan
72,000.00 400.00 10,500.00 82,900.00 82,900.00
45,000.00 120,000.00 90,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
153,000.00 132,000.00 48,960.00 333,960.00
3,000.00 22,200.00 52,500.00 77,700.00 Dibulatkan
153,000.00 132,000.00 48,960.00 3,000.00 22,200.00 52,500.00 411,660.00 411,660.00
45,000.00 120,000.00 90,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
183,375.00 132,000.00 46,800.00 362,175.00
3,000.00 22,200.00 52,500.00 77,700.00 Dibulatkan
183,375.00 132,000.00 46,800.00 3,000.00 22,200.00 52,500.00 439,875.00 439,870.00
45,000.00 120,000.00 90,000.00 220,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
68,625.00 132,000.00 44,280.00 32,340.00 277,245.00
3,000.00 22,200.00 52,500.00 77,700.00 Dibulatkan
68,625.00 132,000.00 44,280.00 32,340.00 3,000.00 22,200.00 52,500.00 354,945.00 354,940.00
1 18
19
20
21
22
23
24
2
3
4
1 M3 PAS. PONDASI BATU KALI KOSONG 1.1000 M3 Batu kali 0.3000 M3 Pasir Urug 0.0390 Uph Mandor 0.3900 Uph Tukang batu 0.7800 Uph Pekerja
5
6
7
8
120,000.00 60,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
132,000.00 18,000.00 150,000.00
1,560.00 14,430.00 27,300.00 43,290.00 Dibulatkan
132,000.00 18,000.00 1,560.00 14,430.00 27,300.00 193,290.00 193,290.00
45,000.00 350.00 90,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
16,166.25 24,500.00 3,870.00 44,536.25
600.00 3,700.00 11,200.00 15,500.00 Dibulatkan
16,166.25 24,500.00 3,870.00 600.00 3,700.00 11,200.00 60,036.25 60,030.00
45,000.00 350.00 90,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
12,060.00 24,500.00 4,320.00 40,880.00
600.00 3,700.00 11,200.00 15,500.00 Dibulatkan
12,060.00 24,500.00 4,320.00 600.00 3,700.00 11,200.00 56,380.00 56,380.00
1 M' PAS. PONDASI TERAS ROLAAG BATU BATA TEBAL ½ BATA AD. 1 Pc : 3 Ps 0.0330 M3 Galian Tanah 15,600.00 0.2000 M2 Pas. Batu Bata Ad. 1 Pc : 3 Ps 60,030.00 JUMLAH
12,006.00 12,006.00
514.80
Dibulatkan
514.80 12,006.00 12,520.80 12,520.00
1 M2 PAS. BATU BATA TEBAL ½ BATA AD. 1 Pc : 3 Ps 0.3593 Zak PC (Portland Cement ) 40 kg 70.0000 Bh Batu bata uk. 5 x 11 x 22 cm 0.0430 M3 Pasir pasang 0.0150 Uph Mandor 0.1000 Uph Tukang batu 0.3200 Uph Pekerja
1 M2 PAS. BATU BATA TEBAL ½ BATA AD. 1 Pc : 5 Ps 0.2680 Zak PC (Portland Cement ) 40 kg 70.0000 Bh Batu bata uk. 5 x 11 x 22 cm 0.0480 M3 Pasir pasang 0.0150 Uph Mandor 0.1000 Uph Tukang batu 0.3200 Uph Pekerja
1 M2 PAS.BATUBATA TEBAL ½ AD. 1 Pc : 3 Kpr : 10 Ps 0.1125 Zak PC (Portland Cement ) 40 kg 70.0000 Bh Batu bata uk. 5 x 11 x 22 cm 0.0500 M3 Pasir pasang 0.0150 M3 Kapur 0.0250 Uph Mandor 0.1000 Uph Tukang batu 0.3200 Uph Pekerja
1 M2 PAS. DINDING CONBLOCK 1:5 0.0816 zak PC (Portland Cement ) 40 kg 12.5000 bh Conblock 0.0150 m3 Pasir pasang 0.0150 upah Mandor 0.1650 upah Tukang batu 0.1500 upah Pekerja
1 M' PAS. PONDASI TERAS ROLAAG CONBLOCK AD. 1 Pc : 5 Ps 0.0330 M3 Galian Tanah 0.2000 M2 Pas. Conblock Ad. 1 Pc : 5 Ps
514.80
45,000.00 350.00 90,000.00 220,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
5,062.50 24,500.00 4,500.00 3,300.00 37,362.50
1,000.00 3,700.00 11,200.00 15,900.00 Dibulatkan
5,062.50 24,500.00 4,500.00 3,300.00 1,000.00 3,700.00 11,200.00 53,262.50 53,260.00
45,000.00 2,800.00 90,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
3,672.00 35,000.00 1,350.00 40,022.00
600.00 6,105.00 5,250.00 11,955.00 Dibulatkan
3,672.00 35,000.00 1,350.00 600.00 6,105.00 5,250.00 51,977.00 51,970.00
15,600.00 51,970.00 JUMLAH
10,394.00 10,394.00
514.80 514.80
514.80 10,394.00 10,908.80 10,900.00
-
44,374.18 21,811.68 66,185.86 66,180.00
Dibulatkan 25
1 BH PAS. BAK KONTROL 30X30 0.7392 M2 Pas. Bt. Bata ad. 1 Pc : 3 Ps 0.8910 M2 Pleteran ad. 1 Pc : 3 Ps
60,030.00 24,480.00 JUMLAH
44,374.18 21,811.68 66,185.86 Dibulatkan
1 26
27
28
29
30
2
3
4
1 M2 PLESTERAN DINDING AD. 1 Pc : 3 Ps, TEBAL 15 MM 0.1620 Zak PC (Portland Cement ) 40 kg 0.0190 M3 Pasir pasang 0.0120 OH Mandor 0.1100 OH Tukang batu 0.1200 OH Pekerja
1 M2 PLESTERAN DINDING AD. 1 Pc : 4 Ps, TEBAL 15 MM 0.1300 Zak PC (Portland Cement ) 40 kg 0.0200 M3 Pasir pasang 0.0200 OH Mandor 0.1500 OH Tukang batu 0.2000 OH Pekerja
1 M2 PLESTERAN DINDING AD. 1 Pc : 5 Ps, TEBAL 15 MM 0.1080 Zak PC (Portland Cement ) 40 kg 0.0220 M3 Pasir pasang 0.0200 OH Mandor 0.1500 OH Tukang batu 0.2000 OH Pekerja
1 M2 PLESTERAN DINDING AD. 1 Pc : 3 Kp : 10 Ps, TEBAL 15 MM 0.0460 Zak PC (Portland Cement ) 40 kg 0.0060 M3 Kapur 0.0140 M3 Pasir pasang 0.0200 OH Mandor 0.1500 OH Tukang batu 0.2000 OH Pekerja
1 M2 PLESTERAN DINDING AD. 1 Pc : 3 Ps, TEBAL 20 MM 0.2700 Zak PC (Portland Cement ) 40 kg 0.0260 M3 Pasir pasang 0.0075 Uph Mandor 0.1200 Uph Tukang batu 0.1500 Uph Pekerja
5 45,000.00 90,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
6
7 7,290.00 1,710.00 9,000.00
8 480.00 4,070.00 4,200.00 8,750.00
Dibulatkan
7,290.00 1,710.00 480.00 4,070.00 4,200.00 17,750.00 17,750.00
45,000.00 90,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
5,850.00 1,800.00 7,650.00
800.00 5,550.00 7,000.00 13,350.00 Dibulatkan
5,850.00 1,800.00 800.00 5,550.00 7,000.00 21,000.00 21,000.00
45,000.00 90,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
4,860.00 1,980.00 6,840.00
800.00 5,550.00 7,000.00 13,350.00 Dibulatkan
4,860.00 1,980.00 800.00 5,550.00 7,000.00 20,190.00 20,190.00
45,000.00 220,000.00 90,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
2,070.00 1,320.00 1,260.00 4,650.00
800.00 5,550.00 7,000.00 13,350.00 Dibulatkan
2,070.00 1,320.00 1,260.00 800.00 5,550.00 7,000.00 18,000.00 18,000.00
45,000.00 90,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
12,150.00 2,340.00 14,490.00
300.00 4,440.00 5,250.00 9,990.00
12,150.00 2,340.00 300.00 4,440.00 5,250.00 24,480.00 24,480.00
300.00 4,440.00 5,250.00 9,990.00
9,765.00 2,520.00 300.00 4,440.00 5,250.00 22,275.00 22,270.00
300.00 4,440.00 5,250.00 9,990.00
8,201.25 2,520.00 300.00 4,440.00 5,250.00 20,711.25 20,710.00
Dibulatkan 31
1 M2 PLESTERAN DINDING AD. 1 Pc : 4 Ps, TEBAL 20 MM 0.2170 Zak PC (Portland Cement ) 40 kg 0.0280 M3 Pasir pasang 0.0075 Uph Mandor 0.1200 Uph Tukang batu 0.1500 Uph Pekerja
45,000.00 90,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
9,765.00 2,520.00 12,285.00 Dibulatkan
32
1 M2 PLESTERAN DINDING AD. 1 Pc : 5 Ps, TEBAL 20 MM 0.1823 Zak PC (Portland Cement ) 40 kg 0.0280 M3 Pasir pasang 0.0075 Uph Mandor 0.1200 Uph Tukang batu 0.1500 Uph Pekerja
45,000.00 90,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
8,201.25 2,520.00 10,721.25 Dibulatkan
1 33
34
35
2
3
4
1 M2 PLESTERAN DINDING AD. 1 Pc : 3 Kp : 10 Ps, TEBAL 20 MM 0.0818 Zak PC (Portland Cement ) 40 kg 0.0080 M3 Kapur 0.0187 M3 Pasir pasang 0.0075 Uph Mandor 0.1200 Uph Tukang batu 0.1500 Uph Pekerja
1 M2 PLESTERAN BAN-BANAN AD. 1 Pc : 5 Ps, LEBAR 10 CM 0.0125 Zak PC (Portland Cement ) 40 kg 0.0013 M3 Pasir pasang 0.0030 Uph Mandor 0.3800 Uph Tukang batu 0.0570 Uph Pekerja
1 M2 ACIAN 0.0813 0.0075 0.0750 0.0500
Zak Uph Uph Uph
PC (Portland Cement ) 40 kg Mandor Tukang batu Pekerja
5 45,000.00 220,000.00 90,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
6
7 3,678.75 1,760.00 1,683.00 7,121.75
8 300.00 4,440.00 5,250.00 9,990.00
Dibulatkan
3,678.75 1,760.00 1,683.00 300.00 4,440.00 5,250.00 17,111.75 17,110.00
45,000.00 90,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
562.50 117.00 679.50
120.00 14,060.00 1,995.00 16,175.00 Dibulatkan
562.50 117.00 120.00 14,060.00 1,995.00 16,854.50 16,850.00
45,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
3,656.25 3,656.25
300.00 2,775.00 1,750.00 4,825.00
3,656.25 300.00 2,775.00 1,750.00 8,481.25 8,480.00
3,200.00 9,250.00 57,750.00 70,200.00 Dibulatkan
245,250.00 62,400.00 91,350.00 3,200.00 9,250.00 57,750.00 469,200.00 469,200.00
Dibulatkan 36
37
38
39
40
41
1 M3 MEMBUAT BETON AD. 1 Pc : 3 Ps : 5 KrL 5.4500 Zak PC (Portland Cement ) 40 kg 0.5200 M3 Pasir beton 0.8700 M3 Koral beton 0.0800 Uph Mandor 0.2500 Uph Tukang batu 1.6500 Uph Pekerja
1 M2 PAS. LANTAI BETON AD. 1 Pc : 3 Ps : 5 KrL Tbl. 5 Cm (DI ACI) 0.0500 M3 Beton Rabat ad. 1 Pc : Ps : 5 Krl 1.0000 M2 Acian
1 M2 PAS. BETON AD. 1 Pc : 3 Ps : 5 KrL Tbl. 6 Cm 0.0800 M3 Beton Rabat ad. 1 Pc : Ps : 5 Krl
1 M2 PAS. BETON AD. 1 Pc : 3 Ps : 5 KrL Tbl. 8 Cm 0.0800 M3 Beton Rabat ad. 1 Pc : Ps : 5 Krl
1 M3 MEMBUAT BETON BERTULANG AD. 1 Pc : 2 Ps : 3 KrL 8.4000 Zak PC (Portland Cement ) 40 kg 0.5400 M3 Pasir beton 0.8100 M3 Koral beton 1.0000 Uph Mandor 0.3500 Uph Tukang batu 2.0000 Uph Pekerja
PEKERJAAN PEMBESIAN 1 KG DENGAN BESI POLOS/ULIR 1.0500 KG Besi beton (polos/ulir) 0.0150 KG Kawat beton 0.0003 Uph Mandor 0.0100 Uph Tukang besi 0.0100 Uph Pekerja
45,000.00 120,000.00 105,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
245,250.00 62,400.00 91,350.00 399,000.00
469,200.00 8,480.00 JUMLAH
23,460.00 8,480.00 31,940.00
469,200.00
469,200.00
Dibulatkan
23,460.00 8,480.00 31,940.00 31,940.00
Dibulatkan
37,536.00 37,530.00
Dibulatkan
37,536.00 37,530.00
-
37,536.00
37,536.00
45,000.00 120,000.00 105,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
378,000.00 64,800.00 85,050.00 527,850.00
40,000.00 12,950.00 70,000.00 122,950.00 Dibulatkan
378,000.00 64,800.00 85,050.00 40,000.00 12,950.00 70,000.00 650,800.00 650,800.00
13,000.00 12,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
13,650.00 180.00 13,830.00
12.00 370.00 350.00 732.00
13,650.00 180.00 12.00 370.00 350.00 14,562.00 14,560.00
Dibulatkan
1 42
2
3
4
PEKERJAAN PEMBESIAN SLOOF 120 KG BESI (Ø 8 mm & Ø 6 mm) 120.0000 KG Besi beton (polos/ulir)
5 14,560.00 JUMLAH
6
7
1,747,200.00 1,747,200.00
8 -
1,747,200.00 1,747,200.00 1,747,200.00
-
1,747,200.00 1,747,200.00 1,747,200.00
-
2,038,400.00 2,038,400.00 2,038,400.00
-
582,400.00 582,400.00 582,400.00
-
582,400.00 582,400.00 582,400.00
Dibulatkan 43
PEKERJAAN PEMBESIAN RING BALK 120 KG BESI (Ø 7 mm & Ø 4 mm) 120.0000 KG Besi beton (polos/ulir)
14,560.00 JUMLAH
1,747,200.00 1,747,200.00 Dibulatkan
44
PEKERJAAN PEMBESIAN KOLOM 140 KG BESI (Ø 7 mm & Ø 4 mm) 140.0000 KG Besi beton (polos/ulir)
14,560.00 JUMLAH
2,038,400.00 2,038,400.00 Dibulatkan
45
PEKERJAAN PEMBESIAN JEMBATAN MASUK RUMAH 40 KG BESI (Ø 8 mm & Ø 6 mm) 40.0000 KG Besi beton (polos/ulir) 14,560.00 JUMLAH
582,400.00 582,400.00 Dibulatkan
46
PEKERJAAN PEMBESIAN TUTUP BEERPUT 40 KG BESI (Ø 8 mm & Ø 6 mm) 40.0000 KG Besi beton (polos/ulir) 14,560.00 JUMLAH
582,400.00 582,400.00 Dibulatkan
47
1 M2 PAPAN BEGESTING 0.1000 Ltr Minyak Bekesting 0.3000 Kg Paku biasa uk. 2" - 5" 0.0440 M3 Kayu Bekisting 0.0260 OH Mandor 0.2600 OH Tukang Kayu 0.3000 OH Pekerja Biasa
Pasangan Bekisting untuk 1 M3 Beton 5.0000 x Bekisting
4,500.00 9,000.00 900,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
450.00 2,700.00 39,600.00
42,750.00
1,040.00 9,620.00 10,500.00 21,160.00 Dibulatkan
63,910.00
319,550.00 319,550.00
Dibulatkan 48
1 M3 PEK. BETON TULANG 100 kg 1.0000 M3 PAS. COR BETON AD. 1:2:3 1.0000 Ls PEMBESIAN 140 KG 1.0000 Ls PAPAN BEGESTING 1M3 BETON JUMLAH
Rp. Rp. Rp. Rp.
650,800.00 2,038,400.00 319,550.00 3,008,750.00 3,008,750.00
Rp. Rp. Rp. Rp.
650,800.00 2,038,400.00 319,550.00 3,008,750.00 3,008,750.00
Rp. Rp. Rp. Rp.
650,800.00 1,747,200.00 319,550.00 2,717,550.00 2,717,550.00
Rp. Rp. Rp. Rp.
650,800.00 582,400.00 319,550.00 1,552,750.00 1,552,750.00
Dibulatkan 49
1 M3 PEK. BETON TULANG 110 kg 1.0000 M3 PAS. COR BETON AD. 1:2:3 1.0000 Ls PEMBESIAN 110 KG 1.0000 Ls PAPAN BEGESTING 1M3 BETON JUMLAH Dibulatkan
50
1 M3 PEK. BETON TULANG 125 kg 1.0000 M3 PAS. COR BETON AD. 1:2:3 1.0000 Ls PEMBESIAN 125 KG 1.0000 Ls PAPAN BEGESTING 1M3 BETON JUMLAH Dibulatkan
51
` 1 M3 PEK. BETON TULANG 160 kg 1.0000 M3 PAS. COR BETON AD. 1:2:3 1.0000 Ls PEMBESIAN 160 KG 1.0000 Ls PAPAN BEGESTING 1M3 BETON JUMLAH Dibulatkan
450.00 2,700.00 39,600.00 1,040.00 9,620.00 10,500.00 63,910.00 63,910.00
1 52
2
3
4
5
6
7
1 M3 PEK. BETON BERTULANG 70 kg 1.0000 m3 PAS. COR BETON AD. 1:2:3 1.0000 LS PEMBESIAN 70 KG 1.0000 LS PAPAN BEGESTING 1 m3 BETON JUMLAH
8 Rp. Rp. Rp. Rp. Rp.
650,800.00 1,747,200.00 319,550.00 2,717,550.00 2,717,550.00 156,530.88
Dibulatkan 1 BH PLAT JEMBATAN MASUK RUMAH UK. 09 X0.8 X 0.008 : 53
54
55
56
57
58
1 M2 LANTAI KERAMIK WARNA 30/30 0.2845 Zak PC (Portland Cement ) 40 kg 0.0360 M3 Pasir Pasang 1.0500 M2 Keramik 30/30 (Motif) 0.0375 Kg PC Warna u/ Naad 0.0450 Uph Mandor 0.1500 Uph Tukang batu 0.3000 Uph Pekerja
1 M2 LANTAI KERAMIK POLOS 30/30 0.2845 Zak PC (Portland Cement ) 40 kg 0.0360 M3 Pasir Pasang 1.0500 m2 Keramik 30/30 0.0375 Kg PC Warna u/ Naad 0.0300 Uph Mandor 0.1500 Uph Tukang batu 0.3000 Uph Pekerja
1 M2 LANTAI KERAMIK POLOS / WARNA 20/20 0.2845 Zak PC (Portland Cement ) 40 kg 0.0360 M3 Pasir Pasang 1.0500 m2 Keramik 20/20 0.0375 Zak PC Warna u/ Naad 0.0300 Uph Mandor 0.1500 Uph Tukang batu 0.3000 Uph Pekerja
1 M2 DINDING KERAMIK 10/20 & 20/25 0.2325 Zak PC (Portland Cement ) 40 kg 0.0180 M3 Pasir Pasang 1.0250 m2 Keramik 10/20 1.0500 Zak PC Warna u/ Naad 0.0350 Uph Mandor 0.1750 Uph Tukang batu 0.3500 Uph Pekerja
1 M2 DINDING BATU ALAM 0.2938 Zak PC (Portland Cement ) 40 kg 0.0350 M3 Pasir Pasang 1.0500 m2 Batu Paros/Palimanan 0.0500 Uph Mandor 0.2500 Uph Tukang batu 0.5000 Uph Pekerja
1 M3 PEKERJAAN KOZEN KAYU 1.2000 M3 Kayu lokal Keras 6/12 1.2500 kg Paku 0.3000 Uph Mandor 18.0000 Uph Tukang kayu 6.0000 Uph Pekerja
1.0000
m'
1 m3 = 138.89 m' Kozen jadi
45,000.00 120,000.00 29,000.00 6,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
12,802.50 4,320.00 30,450.00 225.00 47,797.50
1,800.00 5,550.00 10,500.00 17,850.00 Dibulatkan
12,802.50 4,320.00 30,450.00 225.00 1,800.00 5,550.00 10,500.00 65,647.50 65,640.00
45,000.00 90,000.00 45,000.00 6,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
12,802.50 3,240.00 47,250.00 225.00 63,517.50
1,200.00 5,550.00 10,500.00 17,250.00 Dibulatkan
12,802.50 3,240.00 47,250.00 225.00 1,200.00 5,550.00 10,500.00 80,767.50 80,760.00
45,000.00 90,000.00 35,000.00 6,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
12,802.50 3,240.00 36,750.00 225.00 53,017.50
1,200.00 5,550.00 10,500.00 17,250.00 Dibulatkan
12,802.50 3,240.00 36,750.00 225.00 1,200.00 5,550.00 10,500.00 70,267.50 70,260.00
45,000.00 45,000.00 40,000.00 45,000.00 6,000.00 40,000.00 37,000.00 JUMLAH
10,462.50 810.00 41,000.00 47,250.00 99,522.50
210.00 7,000.00 12,950.00 20,160.00 Dibulatkan
10,462.50 810.00 41,000.00 47,250.00 210.00 7,000.00 12,950.00 119,682.50 119,680.00
45,000.00 90,000.00 130,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
13,218.75 3,150.00 136,500.00 152,868.75
2,000.00 9,250.00 17,500.00 28,750.00 Dibulatkan
13,218.75 3,150.00 136,500.00 2,000.00 9,250.00 17,500.00 181,618.75 181,610.00
3,800,000.00 9,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
4,560,000.00 11,250.00 4,571,250.00
12,000.00 666,000.00 210,000.00 888,000.00 Dibulatkan
4,560,000.00 11,250.00 12,000.00 666,000.00 210,000.00 5,459,250.00 5,459,250.00
39,306.29 Dibulatkan
39,306.29 39,300.00
1 59
60
2
3
4
1 BH PEKERJAAN KOZEN - KOZEN P.1 0.0350 M3 Kayu lokal Keras 6/12 6.0000 bh Angkur 0.0088 Uph Mandor 0.3500 Uph Tukang kayu 0.0875 Uph Pekerja
1 BH PEKERJAAN KOZEN - KOZEN P.2 0.0343 M3 Kayu lokal Keras 6/12 6.0000 bh Angkur 0.0088 Uph Mandor 0.3500 Uph Tukang kayu 0.0875 Uph Pekerja VOLUME DISESUAIKAN DG
61
62
63
64
65
66
1 BH PEKERJAAN KOZEN - KOZEN PJ.1 0.0491 M3 Kayu lokal Keras 6/12 6.0000 bh Angkur 0.0113 Uph Mandor 0.4500 Uph Tukang kayu 0.1125 Uph Pekerja
1 BH PEKERJAAN KOZEN - KOZEN PJ.2 0.0870 M3 Kayu lokal Keras 6/12 6.0000 bh Angkur 0.0800 Uph Mandor 0.4000 Uph Tukang kayu 0.4000 Uph Pekerja
1 BH PEKERJAAN KOZEN - KOZEN J.2 0.0419 M3 Kayu lokal Keras 6/12 4.0000 bh Angkur 0.0563 Uph Mandor 0.4500 Uph Tukang kayu 0.1125 Uph Pekerja
1 BH PEKERJAAN KOZEN - KOZEN J.1 0.0308 M3 Kayu lokal Keras 6/12 4.0000 bh Angkur 0.0400 Uph Mandor 0.3200 Uph Tukang kayu 0.0800 Uph Pekerja
1 BH PEKERJAAN KOZEN - KOZEN BV. 1 0.0173 M3 Kayu lokal Keras 6/12 4.0000 bh Angkur 0.0256 Uph Mandor 0.1000 Uph Tukang kayu 0.1563 Uph Pekerja
1 BH PEKERJAAN KOZEN - KOZEN BV. T.36. (Teras) 0.0144 M3 Kayu lokal Keras 6/12 4.0000 bh Angkur 0.0063 Uph Mandor 0.0400 Uph Tukang kayu 0.0625 Uph Pekerja
5
6
7
8
5,459,250.00 3,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
191,030.08 18,000.00 209,030.08
350.00 12,950.00 3,062.50 16,362.50 Dibulatkan
191,030.08 18,000.00 350.00 12,950.00 3,062.50 225,392.58 225,390.00
5,459,250.00 3,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
187,099.42 18,000.00 205,099.42
350.00 12,950.00 3,062.50 16,362.50 Dibulatkan
187,099.42 18,000.00 350.00 12,950.00 3,062.50 221,461.92 221,460.00
5,459,250.00 3,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
268,071.01 18,000.00 286,071.01
450.00 16,650.00 3,937.50 21,037.50 Dibulatkan
268,071.01 18,000.00 450.00 16,650.00 3,937.50 307,108.51 307,100.00
5,459,250.00 3,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
474,954.75 18,000.00 492,954.75
3,200.00 14,800.00 14,000.00 32,000.00 Dibulatkan
474,954.75 18,000.00 3,200.00 14,800.00 14,000.00 524,954.75 524,950.00
5,459,250.00 3,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
228,764.41 12,000.00 240,764.41
2,250.00 16,650.00 3,937.50 22,837.50 Dibulatkan
228,764.41 12,000.00 2,250.00 16,650.00 3,937.50 263,601.91 263,600.00
5,459,250.00 3,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
168,232.25 12,000.00 180,232.25
1,600.00 11,840.00 2,800.00 16,240.00 Dibulatkan
168,232.25 12,000.00 1,600.00 11,840.00 2,800.00 196,472.25 196,470.00
5,459,250.00 3,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
94,335.84 12,000.00 106,335.84
1,025.00 3,700.00 5,468.75 10,193.75 Dibulatkan
94,335.84 12,000.00 1,025.00 3,700.00 5,468.75 116,529.59 116,520.00
5,459,250.00 3,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
78,613.20 12,000.00 90,613.20
250.00 1,480.00 2,187.50 3,917.50
78,613.20 12,000.00 250.00 1,480.00 2,187.50 94,530.70 94,530.00
Dibulatkan
1 67
2
3
4
1 BH PEKERJAAN KOZEN - KOZEN BV.1 ( T.70 ) 0.0162 M3 Kayu lokal Keras 6/12 4.0000 bh Angkur 0.0063 Uph Mandor 0.0400 Uph Tukang kayu 0.0625 Uph Pekerja
5
5,459,250.00 500.00 40,000.00 37,000.00 35,000.00 JUMLAH
6
7
88,204.01 2,000.00 90,204.01
8
250.00 1,480.00 2,187.50 3,917.50
88,204.01 2,000.00 250.00 1,480.00 2,187.50 94,121.51 94,120.00
Dibulatkan 68
69
70
71
72
73
1BH.PAS.DAUN PINTU DBL TRIPLEK. ( P.1 ) uk. 82 x 201 cm 0.0240 M3 Kayu lokal Keras 4/10 2.0000 lb Triplex 3 mm 0.0500 KG Paku 0.1000 KG Lem 1.0000 set Engsel 4" 0.0750 Uph Mandor 1.5000 Uph Tukang kayu 0.7500 Uph Pekerja
1BH.PAS.DAUN PINTU DBL TRIPLEK. ( P.2 ) uk. 72 x 201 cm 0.0211 M3 Kayu lokal Keras 6/12 2.0000 lb Triplex 0.0500 KG Paku 0.1000 KG Lem 1.0000 set Engsel 4" 0.0875 Uph Mandor 1.7500 Uph Tukang kayu 0.8750 Uph Pekerja
1 BH. PAS. DAUN PINTU PANIL TRIPLEK 6 MM ( P1) UK. 82 X 201 Cm 0.0360 M3 Kayu lokal Keras 6/12 0.5000 lb Triplex 6 mm 0.0500 KG Paku biasa uk. 2" - 5" 1.0000 set Engsel 4" 0.1000 Uph Mandor 2.0000 Uph Tukang kayu 1.0000 Uph Pekerja
1 BH. PAS. DAUN PINTU PANIL KAYU LOKAL (P1) UK. 82 X 201 Cm 1.0000 bh Daun Pintu Panil kayu lokal 1.0000 set Engsel 4" 1.0000 bh Grendel 1.0000 bh Handel Pintu 0.0417 Uph Mandor 1.2500 Uph Tukang kayu 0.4167 Uph Pekerja
1 BH. PAS. KUNCI 2 SLAAG SETARA YALE/BELUCI 1.0000 bh Kunci 2 slaag 0.0050 Uph Mandor 0.5000 Uph Tukang kayu 0.0100 Uph Pekerja
1 BH. PAS. KUNCI 2 SLAAG SETARA ROYAL 1.0000 bh Kunci 2 slaag 0.0035 Uph Mandor 0.3500 Uph Tukang kayu 0.0100 Uph Pekerja
3,500,000.00 32,500.00 9,000.00 7,500.00 7,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
83,947.54 65,000.00 450.00 750.00 7,000.00 157,147.54
3,000.00 55,500.00 26,250.00 84,750.00 Dibulatkan
83,947.54 65,000.00 450.00 750.00 7,000.00 3,000.00 55,500.00 26,250.00 241,897.54 241,890.00
3,500,000.00 32,500.00 9,000.00 7,500.00 7,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
73,941.00 65,000.00 450.00 750.00 7,000.00 147,141.00
3,500.00 64,750.00 30,625.00 98,875.00 Dibulatkan
73,941.00 65,000.00 450.00 750.00 7,000.00 3,500.00 64,750.00 30,625.00 246,016.00 246,010.00
3,500,000.00 65,000.00 9,000.00 7,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
126,152.95 32,500.00 450.00 7,000.00 166,102.95
4,000.00 74,000.00 35,000.00 113,000.00 Dibulatkan
126,152.95 32,500.00 450.00 7,000.00 4,000.00 74,000.00 35,000.00 279,102.95 279,100.00
320,000.00 7,000.00 2,500.00 3,500.00 40,000.00 37,000.00 35,000.00 JUMLAH
320,000.00 7,000.00 2,500.00 3,500.00 333,000.00
1.00 1,666.67 46,250.00 14,583.33 62,501.00 Dibulatkan
320,000.00 7,000.00 2,500.00 3,501.00 1,666.67 46,250.00 14,583.33 395,501.00 395,500.00
60,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
60,000.00 60,000.00
200.00 18,500.00 350.00 19,050.00 Dibulatkan
60,000.00 200.00 18,500.00 350.00 79,050.00 79,050.00
30,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
30,000.00 30,000.00
140.00 12,950.00 350.00 13,440.00 Dibulatkan
30,000.00 140.00 12,950.00 350.00 43,440.00 43,440.00
1 74
75
76
77
2
3
4
1BH.PAS.DAUN PINTU PVC KM/WC ( LENGKAP) 1.0000 Set Daun Pintu PVC lengkap 0.0150 Uph Mandor 0.7500 Uph Tukang kayu 0.1500 Uph Pekerja
1 BH. PAS. DAUN JENDELA. Uk. 0.62 x 1,02 ( J1 ) 0.0105 M3 Kayu lokal Keras 6/12 0.0600 kg Paku biasa uk. 2" - 5" 0.8000 M2 Kaca polos tbl. 3 mm 1.0000 set Engsel 3" 1.0000 bh Grendel 2.0000 bh Hak angin 0.0225 Uph Mandor 0.9000 Uph Tukang kayu 0.2250 Uph Pekerja
1 BH. PAS. DAUN JENDELA. Uk.0,62 x 1,40 ( PJ2) 0.0125 M3 Kayu lokal Keras 6/12 0.0600 kg Paku biasa uk. 2" - 5" 1.0000 M2 Kaca polos tbl. 3 mm 1.0000 set Engsel 3" 1.0000 bh Grendel 2.0000 bh Hak angin 0.0250 Uph Mandor 1.0000 Uph Tukang kayu 0.2500 Uph Pekerja
1 M2 PASANG KACA POLOS t = 3 mm 4.0000 M' List kaca kayu lokal 1.0000 M2 Kaca polos tbl. 3 mm 0.0500 set Paku triplek 0.0050 Uph Mandor 0.1000 Uph Tukang kayu 0.0500 Uph Pekerja
5
6
7
8
140,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
140,000.00 140,000.00
600.00 27,750.00 5,250.00 33,600.00 Dibulatkan
140,000.00 600.00 27,750.00 5,250.00 173,600.00 173,600.00
3,800,000.00 9,000.00 40,000.00 4,500.00 2,500.00 3,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
39,995.76 540.00 32,000.00 4,500.00 2,500.00 6,000.00 85,535.76
900.00 33,300.00 7,875.00 42,075.00 Dibulatkan
39,995.76 540.00 32,000.00 4,500.00 2,500.00 6,000.00 900.00 33,300.00 7,875.00 127,610.76 127,610.00
3,800,000.00 9,000.00 40,000.00 4,500.00 2,500.00 3,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
47,369.28 540.00 40,000.00 4,500.00 2,500.00 6,000.00 100,909.28
1,000.00 37,000.00 8,750.00 46,750.00 Dibulatkan
47,369.28 540.00 40,000.00 4,500.00 2,500.00 6,000.00 1,000.00 37,000.00 8,750.00 147,659.28 147,650.00
1,500.00 40,000.00 350.00 40,000.00 37,000.00 35,000.00 JUMLAH
6,000.00 40,000.00 17.50 46,017.50
200.00 3,700.00 1,750.00 5,650.00
6,000.00 40,000.00 17.50 200.00 3,700.00 1,750.00 51,667.50 51,660.00
200.00 3,700.00 1,750.00 5,650.00
6,000.00 40,000.00 17.50 200.00 3,700.00 1,750.00 51,667.50 51,660.00
Dibulatkan 78
1 M2 PASANG KACA BURAM/ES t = 3 mm 4.0000 M' List kaca kayu lokal 1.0000 M2 Kaca Es tbl. 3 mm 0.0500 set Paku triplek 0.0050 Uph Mandor 0.1000 Uph Tukang kayu 0.0500 Uph Pekerja
1,500.00 40,000.00 350.00 40,000.00 37,000.00 35,000.00 JUMLAH
6,000.00 40,000.00 17.50 46,017.50 Dibulatkan
79
1 M3 PASANG BALOK GORDING / NOCK / JURAI / SOPI 6/12 1.1000 M3 Kayu lokal Keras 6/12 15.0000 kg Besi Strip 3.0000 kg Paku biasa uk. 2" - 5" 0.2000 Uph Mandor 7.9000 Uph Tukang kayu 2.4000 Uph Pekerja
1.0000
m'
1 m3 = 138.89 m' Balok Gording/Nock/Jurai/Sopi uk. 6/12 cm
3,500,000.00 10,000.00 10,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
3,850,000.00 150,000.00 30,000.00 4,030,000.00
8,000.00 292,300.00 84,000.00 384,300.00 Dibulatkan
31,782.71 Dibulatkan
3,850,000.00 150,000.00 30,000.00 8,000.00 292,300.00 84,000.00 4,414,300.00 4,414,300.00 31,782.71 31,780.00
1 80
81
2
3
4
1 M' PAS. LISTPLANK KAYU 3/20 0.0072 M3 Kayu Papan lokal Keras 0.0375 Kg. Paku biasa uk. 2" - 5" 0.0050 Uph Mandor 0.2000 Uph Tukang Kayu 0.1000 Uph Pekerja
1 M' PAS. LISTPLANK KAYU 2/20 0.0044 M3 Kayu Papan lokal Keras 0.0500 Kg. Paku biasa uk. 2" - 5" 0.0500 Uph Mandor 0.1000 Uph Tukang Kayu 0.1000 Uph Pekerja
5
6
7
8
2,200,000.00 9,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
15,840.00 337.50 16,177.50
200.00 7,400.00 3,500.00 11,100.00 Dibulatkan
15,840.00 337.50 200.00 7,400.00 3,500.00 27,277.50 27,270.00
2,200,000.00 9,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
9,680.00 450.00 10,130.00
2,000.00 3,700.00 3,500.00 9,200.00
9,680.00 450.00 2,000.00 3,700.00 3,500.00 19,330.00 19,330.00
100.00 925.00 437.50 1,462.50
12,500.00 100.00 100.00 925.00 437.50 14,062.50 14,060.00
300.00 1,850.00 875.00 3,025.00 Dibulatkan
9,240.00 225.00 300.00 1,850.00 875.00 12,490.00 12,490.00
Dibulatkan 82
1 M' PAS. LISTPLANK CEMENT SILICA UK. 0.8/20 1.0000 M' Kalsiplank/Woodplank 0.0100 Kg. Paku biasa Triplek 0.0025 Uph Mandor 0.0250 Uph Tukang Kayu 0.0125 Uph Pekerja
12,500.00 10,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
12,500.00 100.00 12,600.00 Dibulatkan
83
84
85
86
1 M' PASANG PAPAN NOK 4/6 0.0026 M3 Kayu Kaso lokal uk 4/6 0.0250 kg Paku biasa uk. 2" - 5" 0.0075 Uph Mandor 0.0500 Uph Tukang Kayu 0.0250 Uph Pekerja
1 M' PASANG PAPAN NOK 3/20 0.0066 M3 Kayu lokal Keras 0.0250 kg Paku biasa uk. 2" - 5" 0.0050 Uph Mandor 0.2000 Uph Tukang Kayu 0.1000 Uph Pekerja
1 M' PASANG PAPAN TALANG 2 X 2/20 LAPIS SENG BJLS 20 0.0088 M3 Kayu Papan lokal Keras 0.5000 M' Seng BJLS 22 0.0500 kg Paku biasa uk. 2" - 5" 0.0500 Uph Mandor 0.1500 Uph Tukang Kayu 0.1000 Uph Pekerja
3,500,000.00 9,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
9,240.00 225.00 9,465.00
2,200,000.00 9,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
14,520.00 225.00 14,745.00
200.00 7,400.00 3,500.00 11,100.00 Dibulatkan
14,520.00 225.00 200.00 7,400.00 3,500.00 25,845.00 25,840.00
900,000.00 17,500.00 9,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
7,920.00 8,750.00 450.00 17,120.00
2,000.00 5,550.00 3,500.00 11,050.00 Dibulatkan
7,920.00 8,750.00 450.00 2,000.00 5,550.00 3,500.00 28,170.00 28,170.00
12,705.00 27,720.00 450.00 450.00 41,325.00
200.00 3,700.00 3,500.00 7,400.00
12,705.00 27,720.00 450.00 450.00 200.00 3,700.00 3,500.00 48,725.00 48,720.00
1 M2 PAS.RANGKA ATAP KY. LOKAL 4/6 & 2/3 U/ GENTENG PALENTONG 25 BH/M2 0.0036 M3 Reng Kayu Lokal 2/3 3,500,000.00 0.0079 M3 Kaso Kayu Lokal 4/6 3,500,000.00 0.0500 kg Paku biasa uk. 2" - 5" 9,000.00 0.0500 kg Paku 1,5 " 9,000.00 0.0050 Uph Mandor 40,000.00 0.1000 Uph Tukang Kayu 37,000.00 0.1000 Uph Pekerja 35,000.00 JUMLAH
Dibulatkan
1 87
2
3
4
5
1 M2 PAS.RANGKA ATAP KAYU Uk. 5/7 & 3/4 UNTUK GENTENG BETON 12 BH./ M2 0.0046 M3 Reng Kayu Lokal 3/4 3,500,000.00 0.0096 kg Kaso Kayu Lokal 5/7 3,500,000.00 0.0500 kg Paku biasa uk. 2" - 5" 9,000.00 0.0500 kg Paku 1,5 " 9,000.00 0.0050 Uph Mandor 40,000.00 0.1000 Uph Tukang Kayu 37,000.00 0.1000 Uph Pekerja 35,000.00 JUMLAH
6
7
16,170.00 33,687.50 450.00 450.00 50,757.50
8 200.00 3,700.00 3,500.00 7,400.00
16,170.00 33,687.50 450.00 450.00 200.00 3,700.00 3,500.00 58,157.50 58,150.00
200.00 3,700.00 3,500.00 7,400.00
12,012.00 26,950.00 360.00 360.00 200.00 3,700.00 3,500.00 47,082.00 47,080.00
320.00 2,775.00 5,250.00 8,345.00 Dibulatkan
15,000.00 320.00 2,775.00 5,250.00 23,345.00 23,340.00
Dibulatkan 88
1 M2 PAS.RANGKA ATAP KAYU Uk. 5/7 & 3/4 UNTUK GENTENG METAL 1,62 LB/M2 0.0034 M3 Reng Kayu Lokal 3/4 3,500,000.00 0.0077 kg Kaso Kayu Lokal 5/7 3,500,000.00 0.0400 kg Paku biasa uk. 2" - 5" 9,000.00 0.0400 kg Paku 1,5 " 9,000.00 0.0050 Uph Mandor 40,000.00 0.1000 Uph Tukang Kayu 37,000.00 0.1000 Uph Pekerja 35,000.00 JUMLAH
12,012.00 26,950.00 360.00 360.00 39,682.00 Dibulatkan
89
90
91
92
93
1 M2 PAS.GENTENG PALENTONG 25 BH/M2 25.0000 Bh. Genteng Palentong 0.0080 Uph Mandor 0.0750 Uph Tukang Batu 0.1500 Uph Pekerja
1 M' PAS.NOK GENTENG PALENTONG 5 BH/M' 5.0000 Bh. Nok Genteng Palentong 0.1250 Sak PC (Portland Cement ) 40 kg 0.0325 M3 Pasir 0.0020 Uph Mandor 0.2000 Uph Tukang Batu 0.2000 Uph Pekerja
1 M2 PAS.GENTENG MORANDO GLAZUR 12 BH/M2 12.0000 Bh. Genteng Marando glazur 0.0075 Uph Mandor 0.0600 Uph Tukang Batu 0.1500 Uph Pekerja
1 M' PAS.NOCK GENTENG MORANDO GLAZUR 4 BH/M' 4.0000 Bh. Nock Genteng Morando glazur 0.2000 Sak PC (Portland Cement ) 40 kg 0.0325 M3 Pasir 0.0020 Uph Mandor 0.2000 Uph Tukang Batu 0.2000 Uph Pekerja
1 M2 PAS.GENTENG METAL 1.62 LB/M2 1.6200 lb Genteng Metal 0.0250 kg Paku genteng metal 0.0075 Uph Mandor 0.0600 Uph Tukang Batu 0.1500 Uph Pekerja
600.00 40,000.00 37,000.00 35,000.00 JUMLAH
15,000.00 15,000.00
3,500.00 45,000.00 90,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
17,500.00 5,625.00 2,925.00 26,050.00
80.00 7,400.00 7,000.00 14,480.00 Dibulatkan
17,500.00 5,625.00 2,925.00 80.00 7,400.00 7,000.00 40,530.00 40,530.00
2,800.00 40,000.00 37,000.00 35,000.00 JUMLAH
33,600.00 33,600.00
300.00 2,220.00 5,250.00 7,770.00 Dibulatkan
33,600.00 300.00 2,220.00 5,250.00 41,370.00 41,370.00
4,000.00 45,000.00 90,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
16,000.00 9,000.00 2,925.00 27,925.00
80.00 7,400.00 7,000.00 14,480.00 Dibulatkan
16,000.00 9,000.00 2,925.00 80.00 7,400.00 7,000.00 42,405.00 42,400.00
25,000.00 22,500.00 40,000.00 37,000.00 35,000.00 JUMLAH
40,500.00 40,500.00
562.50 300.00 2,220.00 5,250.00 8,332.50
40,500.00 562.50 300.00 2,220.00 5,250.00 48,832.50 48,830.00
Dibulatkan
1 94
95
96
2
3
4
1 M' PAS.NOCK GENTENG METAL 1 LB/M' 1.0000 Lb Nock Genteng Metal 0.0100 kg Paku genteng metal 0.0020 Uph Mandor 0.2000 Uph Tukang Batu 0.2000 Uph Pekerja
1 M2 PAS. ATAP ASBES GELOMBANG (2.1 x 1.05 x 4 mm) 0.5100 Lbr Asbes Gelombang mini 4.0000 bh Paku asbes ulir 0.0070 Uph Mandor 0.1400 Uph Tukang Batu 0.1400 Uph Pekerja
1 M' PAS. NOK STEL ASBES GELOMBANG 1,05 M' 2.1000 Lbr Nok Asbes Gelombang 4.0000 bh Paku asbes ulir 0.0040 Uph Mandor 0.1250 Uph Tukang Kayu 0.0840 Uph Pekerja
5
6
7
20,000.00 22,500.00 40,000.00 37,000.00 35,000.00 JUMLAH
20,000.00 225.00 20,225.00
27,500.00 350.00 40,000.00 37,000.00 35,000.00 JUMLAH
14,025.00 1,400.00 15,425.00
22,000.00 350.00 40,000.00 37,000.00 35,000.00 JUMLAH
46,200.00 1,400.00 47,600.00
8
80.00 7,400.00 7,000.00 14,480.00 Dibulatkan
20,000.00 225.00 80.00 7,400.00 7,000.00 34,705.00 34,700.00
280.00 5,180.00 4,900.00 10,360.00 Dibulatkan
14,025.00 1,400.00 280.00 5,180.00 4,900.00 25,785.00 25,780.00
160.00 4,625.00 2,940.00 7,725.00 Dibulatkan
97
1 M2 PAS.PENUTUP ATAP GENTENG TILUX 1.2500 Lbr Genteng tiluk 4.0000 Bh Paku asbes ulir 0.0004 0.0350 0.0035
Uph Uph Uph
Mandor Tukang Kayu Pekerja
22,000.00 350.00 40,000.00 37,000.00 35,000.00 JUMLAH
27,500.00 1,400.00 28,900.00
14.00 1,295.00 122.50 1,431.50 Dibulatkan
98
1 M' PAS.NOK PENUTUP ATAP GENTENG TILUX 1.1000 Lbr Nok Genteng tiluk 3.0000 Bh Paku asbes ulir 0.0003 0.0250 0.0025
Uph Uph Uph
Mandor Tukang Kayu Pekerja
18,000.00 350.00 40,000.00 37,000.00 35,000.00 JUMLAH
19,800.00 1,050.00 20,850.00
1 M2 PAS.RANGKA PLAFOND 4/6 0.0108 M3 Kayu 0.1000 kg Paku biasa uk. 2" - 5" 0.0025 Uph Mandor 0.1000 Uph Tukang kayu 0.0500 Uph Pekerja
3,500,000.00 9,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
10.00 925.00 87.50 1,022.50
37,632.00 900.00 38,532.00
1 M' LIST PLAFOND 1.1000 m' 0.0250 kg 0.0010 Uph 0.0210 Uph 0.0210 Uph
3 x 3 Cm Kayu List uk. 3 x 3 cm Paku biasa uk. 2" - 5" Mandor Tukang kayu Pekerja
2,000.00 9,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
2,200.00 225.00 2,425.00
100.00 3,700.00 1,750.00 5,550.00
37,632.00 900.00 100.00 3,700.00 1,750.00 44,082.00 44,080.00
40.00 777.00 735.00 1,552.00
2,200.00 225.00 40.00 777.00 735.00 3,977.00 3,970.00
360.00 3,330.00 1,995.00 5,685.00
11,375.00 100.00 360.00 3,330.00 1,995.00 17,160.00 17,160.00
Dibulatkan 101
1 M2 PAS.PLAFOND TRIPLEX 0.3500 LB Triplex 0.0100 kg Paku triplek 0.0090 Uph Mandor 0.0900 Uph Tukang kayu 0.0570 Uph Pekerja
32,500.00 10,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
11,375.00 100.00 11,475.00 Dibulatkan
19,800.00 1,050.00 10.00 925.00 87.50 21,872.50 21,870.00
Dibulatkan 100
27,500.00 1,400.00 14.00 1,295.00 122.50 30,331.50 30,330.00
Dibulatkan 99
46,200.00 1,400.00 160.00 4,625.00 2,940.00 55,325.00 55,320.00
1 102
2
3
4
1 M2 PAS.PLAFOND ETERNIT 1.1000 LB Eternit 0.0100 kg Paku triplek 0.0025 Uph Mandor 0.0750 Uph Tukang kayu 0.0375 Uph Pekerja
5
6
12,000.00 10,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
13,200.00 100.00 13,300.00
JENIS TANAH DISESUAIKAN DG KONDISI DI LAPANGAN 103
104
105
106
SEPTICTANK LENGKAP REMBESAN/BH 2.7700 m3 Galian tanah 0.2400 m3 Urugan tanah kembali 2.0000 bh Buis beton Ø 100 cm 0.0628 m3 Beton bertulng 1:2:3 (Ttp. Septick.) 0.0628 m3 Cor Beton 1:2:3 ( Dsr. Septick.) 0.3600 m3 Koral 0.6000 m3 Batu kali 4.0000 ikat Ijuk 1.0000 ls Pipa hawa PVC Ø 1.1/4" + Accesssories 0.7500 btg Pipa rembesan PVC Ø 4" 1.0000 bh Pipa Tee PVC Ø 4" 0.0750 Uph Mandor 0.7200 Uph Tukang Batu 1.5000 Uph Pekerja
PEK. PEMBUATAN 1 Bh BEERPUT/CUBLUK ( Dalam 1.5 m) 1.4248 m3 Galian Tanah 0.2475 m3 Urugan tanah kembali 0.3825 Sak PC (Portland Cement ) 40 Kg 3.0000 bh buis beton Ø 100 x 50 CM 0.0563 m3 tutup beton bertulang 1 : 2 : 3 1.0000 ls Pipa hawa PVC Ø 1.1/4" + Accesssories 0.0450 Uph Mandor 0.4500 Uph Tukang batu 0.9000 Uph Pekerja
PEK. PEMBUATAN 1 Bh BEERPUT/CUBLUK ( Dalam 2 m) 1.8997 m3 Galian Tanah 0.2475 m3 Urugan tanah kembali 0.5100 Sak PC (Portland Cement ) 40 Kg 4.0000 bh buis beton Ø 100 x 50 CM 0.0563 m3 tutup beton bertulang 1 : 2 : 3 1.0000 ls Pipa hawa PVC Ø 1.1/4" + Accesssories 0.0500 Uph Mandor 0.5000 Uph Tukang batu 1.0000 Uph Pekerja
1 BH MEMBUAT CETAKAN BEERPUT COR SETEMPAT 0.4222 M3 Kayu bekisting 6.7000 M' Seng Plat BJLS 22 lbr. 90 cm 2.0000 Kg Paku biasa uk. 2" - 5" 0.0800 Uph Mandor 1.3250 Uph Tukang kayu 0.8000 Uph Pekerja
0.1000
Bh
1 Bh Cetakan dipakai 10 x
7
8 100.00 2,775.00 1,312.50 4,187.50
Dibulatkan
24,370.00 7,480.00 105,000.00 2,717,550.00 650,800.00 115,000.00 120,000.00 3,500.00 11,500.00 40,000.00 5,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
24,370.00 7,480.00 45,000.00 105,000.00 30,625.00 11,500.00 40,000.00 37,000.00 35,000.00 JUMLAH
24,370.00 7,480.00 45,000.00 105,000.00 30,625.00 11,500.00 40,000.00 37,000.00 35,000.00 JUMLAH
900,000.00 32,000.00 9,000.00 40,000.00 37,000.00 35,000.00
67,504.90 1,795.20 210,000.00 170,662.14 40,870.24 41,400.00 72,000.00 14,000.00 11,500.00 30,000.00 5,000.00 664,732.48
3,000.00 26,640.00 52,500.00 82,140.00 Dibulatkan
67,504.90 1,795.20 210,000.00 170,662.14 40,870.24 41,400.00 72,000.00 14,000.00 11,500.00 30,000.00 5,000.00 3,000.00 26,640.00 52,500.00 746,872.48 746,870.00
34,721.77 1,851.30
34,721.77 1,851.30
1,800.00 16,650.00 31,500.00 86,523.07 Dibulatkan
315,000.00 1,724.19 11,500.00 1,800.00 16,650.00 31,500.00 414,747.25 414,740.00
46,295.69 1,851.30
46,295.69 1,851.30
2,000.00 18,500.00 35,000.00 103,646.99 Dibulatkan
420,000.00 1,724.19 11,500.00 2,000.00 18,500.00 35,000.00 536,871.18 536,870.00
17,212.50 315,000.00 1,724.19 11,500.00
345,436.69
22,950.00 420,000.00 1,724.19 11,500.00
456,174.19
379,980.00 214,400.00 18,000.00 3,200.00 49,025.00 28,000.00
JUMLAH
612,380.00
692,600.00
69,260.00
13,200.00 100.00 100.00 2,775.00 1,312.50 17,487.50 17,480.00
80,225.00 Dibulatkan
379,980.00 214,400.00 18,000.00 3,200.00 49,025.00 28,000.00 692,605.00 692,600.00 69,260.00
Dibulatkan
69,260.00
1 107
108
109
110
111
112
2
3
4
1 BH BEERPUT BETON 1:3:5 (COR SETEMPAT) 1.1775 M3 Galian tanah dalam 2 m 1.1775 M3 Perataan tanah kembali 0.4239 M3 Cor beton tumbuk 1:3:5 1.0000 Ls Cetakan beerput 0.0785 M3 Beton Bertulang Ad.1:2:3 1.0000 Ls Pipa Hawa PVC O 11/2" + Accessories
5 15,600.00 7,480.00 469,200.00 69,260.00 3,008,750.00
BAK MANDI PAS. BATU-BATA DIPLESTER BAG. DLM LAPIS KERAMIK/BH 1.6000 M2 keramik 20x20 1.0000 M2 Pas Bata Merah 1 Pc : 5 Ps + dudukan 1.2000 M2 Plesteran 1.0000 bh Afur Bak Mandi 0.3000 org Mandor 2.0000 org tukang batu 1.0000 org Pekerja
BAK MANDI FIBERGLASS 120 LITER TANAM LENGKAP DUDUKAN / BH 1.0000 Bh Fiber glas uk. 53 x 58 cm 62.0000 Bh Batu bata miring 0.3000 zak PC (Portland Cement ) 40 kg 0.0273 M3 Pasir pasang 0.8400 M2 Plesteran 1 Pc : 5 Ps 0.1500 org Mandor 1.0000 org tukang batu 0.5000 org Pekerja
11,500.00 JUMLAH
70,260.00 56,380.00 20,710.00 5,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
100,000.00 350.00 45,000.00 90,000.00 20,710.00 40,000.00 37,000.00 35,000.00 JUMLAH
BAK MANDI FIBERGLASS 120 LITER TANAM LAPIS KERAMIK + DUDUKAN / BH 1.0000 Bh Fiber glas uk. 53 x 58 cm 100,000.00 62.0000 Bh Batu bata miring 350.00 0.8400 M2 Pas Keramik didnding uk. 20 x 20 cm 70,260.00 0.3000 zak PC (Portland Cement ) 40 kg 45,000.00 0.0273 M3 Pasir pasang 90,000.00 0.8400 M2 Plesteran 1 Pc : 5 Ps 20,710.00 0.1500 org Mandor 40,000.00 1.0000 org tukang batu 37,000.00 0.5000 org Pekerja 35,000.00 JUMLAH
BAK MANDI FIBERGLASS OVAL 100 LITER LENGKAP DUDUKAN/BH 1.0000 bh Bak mandi fiberglass Oval 0.2500 zak PC (Portland Cement ) 40 kg 0.0344 m3 pasir pasang 30.0000 bh batubata 0.0375 org Mandor 0.3750 org tukang batu 0.1875 org Pekerja
PASANG BAK MANDI TERASO 50 x 50 CM LENGKAPAN DUDUKAN / BH 1.0000 bh Bak Teraso 0.3000 zak PC (Portland Cement ) 40 kg 0.0344 m3 pasir pasang 30.0000 bh batubata 0.0750 org Mandor 0.3750 org tukang batu 0.3750 org Pekerja
6
7
18,369.00 8,807.70 198,893.88 69,260.00 236,186.88 11,500.00 543,017.46
112,416.00 56,380.00 24,852.00 5,000.00
198,648.00
8
Dibulatkan
18,369.00 8,807.70 198,893.88 69,260.00 236,186.88 11,500.00 543,017.46 543,010.00
12,000.00 74,000.00 35,000.00 121,000.00 Dibulatkan
112,416.00 56,380.00 24,852.00 5,000.00 12,000.00 74,000.00 35,000.00 319,648.00 319,640.00
6,000.00 37,000.00 17,500.00 60,500.00 Dibulatkan
100,000.00 21,700.00 13,500.00 2,457.00 17,396.40 6,000.00 37,000.00 17,500.00 215,553.40 215,550.00
6,000.00 37,000.00 17,500.00 60,500.00 Dibulatkan
100,000.00 21,700.00 59,018.40 13,500.00 2,457.00 17,396.40 6,000.00 37,000.00 17,500.00 274,571.80 274,570.00
-
100,000.00 21,700.00 13,500.00 2,457.00 17,396.40
155,053.40
100,000.00 21,700.00 59,018.40 13,500.00 2,457.00 17,396.40
214,071.80
155,000.00 45,000.00 90,000.00 350.00 40,000.00 37,000.00 35,000.00 JUMLAH
155,000.00 11,250.00 3,096.00 10,500.00 179,846.00
1,500.00 13,875.00 6,562.50 21,937.50 Dibulatkan
155,000.00 11,250.00 3,096.00 10,500.00 1,500.00 13,875.00 6,562.50 201,783.50 201,780.00
70,000.00 45,000.00 90,000.00 350.00 40,000.00 37,000.00 35,000.00 JUMLAH
70,000.00 13,500.00 3,096.00 10,500.00 97,096.00
3,000.00 13,875.00 13,125.00 30,000.00 Dibulatkan
70,000.00 13,500.00 3,096.00 10,500.00 3,000.00 13,875.00 13,125.00 127,096.00 127,090.00
1 113
114
115
2
3
4
CLOSET JONGKOK PORSELIN SETARA INA LENGKAP DUDUKAN/BH 1.0000 bh closet jongkok poselin 0.0900 m3 pasir urug 0.1760 zak PC (Portland Cement ) 40 kg 0.0288 m3 pasir pasang 20.0000 bh batubata 0.1500 org Mandor 1.5000 org tukang batu 1.0000 org Pekerja
CLOSET JONGKOK TERASO LENGKAP DUDUKAN/BH 1.0000 bh closet jongkok teraso 0.0900 m3 pasir urug 0.1760 zak PC (Portland Cement ) 40 kg 0.0288 m3 pasir pasang 20.0000 bh batubata 0.1500 org Mandor 1.5000 org tukang batu 1.0000 org Pekerja
1 M' PIPA PEMBUANGAN KE SEPTIKTANK PVC Ø 10 CM/M' 0.2750 bt pipa PVC Ø 10 CM' 0.2500 bh Knee/Sock PVC Ø 10 CM' 0.2500 tb lem pipa PVC 0.0021 org Mandor 0.0850 org tukang batu 0.0213 org Pekerja
5
6
7
8
75,000.00 60,000.00 45,000.00 90,000.00 350.00 40,000.00 37,000.00 35,000.00 JUMLAH
75,000.00 5,400.00 7,920.00 2,592.00 7,000.00 97,912.00
6,000.00 55,500.00 35,000.00 96,500.00 Dibulatkan
75,000.00 5,400.00 7,920.00 2,592.00 7,000.00 6,000.00 55,500.00 35,000.00 194,412.00 194,410.00
1,000.00 60,000.00 45,000.00 90,000.00 350.00 40,000.00 37,000.00 35,000.00 JUMLAH
1,000.00 5,400.00 7,920.00 2,592.00 7,000.00 23,912.00
6,000.00 55,500.00 35,000.00 96,500.00 Dibulatkan
1,000.00 5,400.00 7,920.00 2,592.00 7,000.00 6,000.00 55,500.00 35,000.00 120,412.00 120,410.00
40,000.00 5,000.00 5,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
11,000.00 1,250.00 1,250.00 13,500.00
85.00 3,145.00 743.75 3,973.75
11,000.00 1,250.00 1,250.00 85.00 3,145.00 743.75 17,473.75 17,470.00
85.00 2,960.00 700.00 3,745.00 Dibulatkan
8,937.50 1,000.00 1,250.00 85.00 2,960.00 700.00 14,932.50 14,930.00
Dibulatkan
25,000.00 660.00 1,125.00 187.20 700.00 120.00 1,110.00 1,050.00 29,952.20 29,951.00
Dibulatkan 116
117
118
1 M' PIPA SALURAN BAWAH LANTAI PVC Ø 7.5 CM/M' 0.2750 bt pipa PVC Ø 7.5 CM' 0.2500 bh Knee/Sock PVC Ø 7.5 CM' 0.2500 tb lem pipa PVC 0.0021 org Mandor 0.0800 org tukang batu 0.0200 org Pekerja
SALURAN AIR BUIS BETON 1/2 Ø 20 CM/M' 1.0000 bh Buis beton 1/2 Ø 20 cm 0.0110 m3 Pasir urug 0.0250 zak PC (Portland Cement ) 40 kg 0.0021 m3 Pasir pasang 2.0000 bh Batubata 0.0030 org Mandor 0.0300 org tukang batu 0.0300 org Pekerja
MEMASANG PIPA LEIDING PVC / M' 0.2750 bt Pipa PVC Ø 1/2" AW 0.4000 bh Knee Siku PVC Ø 1/2" 0.1000 bh Lem PVC 0.4000 bh Socket PVC Ø 1/2" 0.0015 org Mandor 0.0600 org Tukang leiding 0.0300 org Pekerja
32,500.00 4,000.00 5,000.00 40,000.00 37,000.00 35,000.00 JUMLAH
25,000.00 60,000.00 45,000.00 90,000.00 350.00 40,000.00 37,000.00 35,000.00 JUMLAH
12,500.00 1,500.00 5,000.00 1,500.00 40,000.00 37,000.00 35,000.00 JUMLAH
8,937.50 1,000.00 1,250.00 11,187.50
25,000.00 660.00 1,125.00 187.20 700.00 120.00 1,110.00 1,050.00 2,160.00
27,672.20
3,437.50 600.00 500.00 600.00 5,137.50
60.00 2,220.00 1,050.00 3,330.00 Dibulatkan
3,437.50 600.00 500.00 600.00 60.00 2,220.00 1,050.00 8,467.50 8,460.00
1 119
2
3
MEMASANG KRAN 1.0000 BH 0.1000 rol 0.0008 org 0.0750 org 0.0075 org
4 AIR KUNINGAN / BH. Kran Air Kuningan Ø 1/2" Siltip Mandor Tukang leiding Pekerja
5 10,000.00 2,500.00 40,000.00 37,000.00 35,000.00 JUMLAH
6
7
10,000.00 250.00 10,250.00
8 30.00 2,775.00 262.50 3,067.50
10,000.00 250.00 30.00 2,775.00 262.50 13,317.50 13,310.00
30.00 2,775.00 262.50 3,067.50
17,000.00 250.00 30.00 2,775.00 262.50 20,317.50 20,310.00
Dibulatkan 120
MEMASANG KRAN 1.0000 BH 0.1000 rol 0.0008 org 0.0750 org 0.0075 org
AIR VERNEKEL / BH. Kran Air Vernekel Ø 1/2" Siltip Mandor Tukang leiding Pekerja
17,000.00 2,500.00 40,000.00 37,000.00 35,000.00 JUMLAH
17,000.00 250.00 17,250.00 Dibulatkan
121
PAS LOCIS KUSEN / BH 0.0011 m3 Beton tak betulang 1:2:3 pakai cetakan 1.0000 Ls Finishing / Acian
970,350.00 1,500.00 JUMLAH
1,047.98 1,500.00 2,547.98
Dibulatkan
122
1 M2 PEKERJAAN CAT KAYU (1 lapis plamir, 1 lapis cat menie & 2 lapis cat penutup) 0.2000 kg Cat menie 16,000.00 0.0750 kg Plamur 7,000.00 0.2600 kg Cat Kayu 26,000.00 0.0200 BH Kwas 3" 5,000.00 0.1000 Ltr Minyak cat 7,000.00 0.0400 lbr Amplas 2,000.00 0.0025 Uph Mandor 40,000.00 0.0900 Uph Tukang Cat 37,000.00 0.0700 Uph Pekerja 35,000.00 JUMLAH
3,200.00 525.00 6,760.00 100.00 700.00 80.00 11,365.00
100.00 3,330.00 2,450.00 5,880.00
3,200.00 525.00 6,760.00 100.00 700.00 80.00 100.00 3,330.00 2,450.00 17,245.00 17,240.00
100.00 875.00 975.00
1,500.00 250.00 100.00 875.00 2,725.00 2,720.00
252.00 2,331.00 700.00 3,283.00
1,500.00 250.00 630.00 100.00 252.00 2,331.00 700.00 5,763.00 5,760.00
252.00 2,331.00 700.00 3,283.00
6,500.00 250.00 700.00 100.00 252.00 2,331.00 700.00 10,833.00 10,830.00
Dibulatkan 123
1 M2 PEKERJAAN CAT GENTENG (2 lapis cat penutup dg Cat Genteng/Kolam) 0.2500 kg Cat Genteng/Kolam 6,000.00 0.0500 bh Kwas 3" 5,000.00 0.0025 Uph Mandor 40,000.00 0.0250 Uph Pekerja 35,000.00 JUMLAH
1,500.00 250.00 1,750.00 Dibulatkan
124
1 M2 PEKERJAAN CAT DINDING KM (1 lapis plamur & 2 lapis cat penutup dg Cat Genteng/Kolam) 0.2500 kg Cat Genteng/Kolam 6,000.00 1,500.00 0.0500 bh Kwas 3" 5,000.00 250.00 0.0900 kg Dempul Tembok 7,000.00 630.00 0.0500 lbr Amplas 2,000.00 100.00 0.0063 Uph Mandor 40,000.00 0.0630 Uph Tukang Cat 37,000.00 0.0200 Uph Pekerja 35,000.00 JUMLAH 2,480.00 Dibulatkan
125
1 M2 PEKERJAAN CAT TEMBOK & PLAFOND (1 lapis plamur & 2 lapis cat penutup) 0.2600 kg Cat tembok 25,000.00 0.0500 bh Kwas 3" 5,000.00 0.1000 kg Dempul Tembok 7,000.00 0.0500 lbr Amplas 2,000.00 0.0063 Uph Mandor 40,000.00 0.0630 Uph Tukang Cat 37,000.00 0.0200 Uph Pekerja 35,000.00 JUMLAH
6,500.00 250.00 700.00 100.00 7,550.00
1,047.98 1,500.00 2,547.98 2,540.00
Dibulatkan
srv\conversion_tmp\scratch_4\[146701492.xls.ms_office.xls]RS 36 Cempaka
Semarang, Maret 2011 Ass Man Produksi & PLPP
AMAT IMRON
DAFTAR HARGA BAHAN DAN UPAH TAHUN 2010 DI LOKASI BUMI PALIR SEJAHTERA PERUM PERUMNAS CABANG SEMARANG I NO. A
UPAH DAN BHN BANGUNAN
SATUAN
HARGA SATUAN
UPAH TENAGA KERJA. 1 Mandor
1 Org./Hr
40,000
2 Tukang Aspal
1 Org./Hr
37,000
3 Tukang Batu
1 Org./Hr
37,000
4 Tukang Besi
1 Org./Hr
37,000
5 Tukang Cat
1 Org./Hr
37,000
6 Tukang Kayu
1 Org./Hr
37,000
7 Tukang Las
1 Org./Hr
37,000
8 Tukang Listrik
1 Org./Hr
37,000
9 Operator
1 Org./Hr
35,000
10 Pekerja / Laden
1 Org./Hr
35,000
11 Pembantu Operator
1 Org./Hr
35,000
12 Penjaga api aspal
1 Org./Hr
35,000
13 Penjaga Malam
1 Org./Hr
35,000
14 Tukang Gali
1 Org./Hr
35,000
1 Afur bak mandi
Bh
5,000
2 Ampelas (Kertas Gosok)
Lbr
2,000
3 Asbes Gelombang uk. 105 x 210 cm
Lbr
27,500
4 Asbes Gelombang Nok. Stel uk. 1,05 cm
Lbr
22,000
4 Asbes Tilux uk. 0.8 x 1,05 cm
Lbr
22,000
5 Asbes Tilux Nok Paten
Lbr
18,000
B.
HARGA BAHAN-BANGUNAN.
6 Aspal
Kg
5,000
7 Bak Mandi fibreglass Tanam uk. 53 x 55 cm
Bh
100,000
8 Bak Mandi fibreglass Oval kap. 100 liter uk. 53 x 58 cm
Bh
155,000
9 Bak Mandi Terazo 50 x 50
Bh
70,000
10 Besi angkur ( kusen )
Bh
3,000
11 Batu Koral
M3
105,000
12 Batu Bata
Bh
350
13 Batu Bata Press
Bh
2,500
14 Batu Kali
M3
120,000
15 Batu Kali Belah
M3
90,000
16 Batu pecah 3/5
M3
75,000
17 Batu pecah 5/7
M3
75,000
18 Batu pecah 0,5/1
M3
135,000
19 Batu pecah 1/1
M3
125,000
20 Batu pecah 2/3
M3
105,000
21 Beerput (RSS)
Unit
300,000
Kg
13,000
22 Besi Beton
NO.
UPAH DAN BHN BANGUNAN
SATUAN
HARGA SATUAN
23 Besi klaam ( kuda-kuda )
Kg
10,000
24 Beton Kanstein 10 x 20 x 50 cm
Kg
12,000
25 Buis Beton 1/2 O 0.15
Bh
20,000
26 Buis Beton 1/2 O 0.20
Bh
25,000
27 Buis Beton O 0.15 ;L 1.00 M
Bh
45,000
28 Buis Beton O 0.20 ;L 1.00 M
Bh
55,000
29 Buis Beton O 0.30 ;L 1.00 M
Bh
65,000
21 Buis Beton O 0.50 ;L 1.00 M
Bh
55,000
22 Buis Beton O 0.80 ;L 1.00 M
Bh
130,000
23 Buis Beton O 1.00 ;L 50 cm
Bh
105,000
24 Buis Beton O 1.00 ;L 1.00 M
Bh
215,000
22 Cat Genteng
Kg
6,000
23 Cat Kayu
Kg
26,000
24 Cat Menie
Kg
16,000
25 Cat Tembok
Kg
25,000
26 Closet Jongkok Porselein
Bh
75,000
27 Alat Bantu
Bh
1,000
28 Conblock 9,5x19.5x39
Bh
2,800
27 Dempul/Plamur Kayu
Kg
7,000
28 Dempul/Plamur Tembok
Kg
7,000
29 Engsel - H dia. 3"
Ps
4,500
30 Engsel - H dia. 4"
Ps
7,000
31 Eternit Plaat uk.1x1 M
Lb
12,000
32 Genteng Morando
Bh
2,800
33 Genteng Morando Nok
Bh
4,000
34 Genteng Plentong
Bh
600
35 Genteng Plentong Nok
Bh
3,500
36 Genteng Metal
Lb
25,000
37 Genteng Metal Nock
Lb
20,000
38 Grendel
Bh
2,500
39 Hak Angin
Bh
3,000
40 Handel Pintu
Bh
3,500
41 Ijuk
Kg
7,500
42 Kaca Biasa tebal 3 MM
M2
40,000
43 Kaca Biasa tebal 5 MM
M2
-
44 Kaca Buram tebal 3 MM
M2
68,000
45 Kaca Buram tebal 5 MM
M2
-
46 Kapur
M3
220,000
47 Kawat Beton
Kg
12,000
48 Kayu Bakar aspal
M3
-
49 Kayu Balok 2/3,3/4,4/6 & 5/7 Lokal
M3
3,500,000
50 Kayu Balok Lokal 6/12 Gording/Kuda-kuda
M3
3,500,000
NO.
UPAH DAN BHN BANGUNAN
SATUAN
HARGA SATUAN
51 Kayu Balok Lokal Uk. 6/12 untuk Kusen
M3
3,800,000
51 Kayu Bekisting
M3
900,000
52 Kayu Papan Bekisting
M3
900,000
53 Kayu Papan Lisplank 2/20
M3
2,200,000
54 Keramik Tile 20/20
M2
35,000
55 Keramik Tile 30/30 Motif
M2
29,000
56 Keramik Tile 30/30 polos
M2
45,000
57 Knie GIP Ø 1/2"
Bh
2,500
58 Knie PVC Ø 1/2" AW
Bh
1,500
59 Knie PVC Ø 1"
Bh
1,750
60 Knie PVC Ø 2"
Bh
2,500
61 Knie PVC Ø 3"
Bh
4,000
62 Knie PVC Ø 4"
Bh
5,000
63 Kran air dia 1/2" kuningan
Bh
10,000
64 Kran air dia 1/2" vernekel
Bh
17,000
65 Krikil / Split
M3
115,000
65 Kunci-2 Slaag Setara Yale/Beluci
Bh
60,000
66 Kunci-2 Slaag setra Royal/Kuda Terbang
Bh
30,000
67 Kuwas
Bh
5,000
68 Lem Kayu
Kg
7,500
69 Lem PVC
Tube
5,000
70 Lis kaca kayu uk. 1 x 3 cm
M'
1,500
71 Lis plafond kayu 3 x 3 cm
M'
2,000
72 Lisplank Cement Silica uk. 0.8x20 cm
M'
12,500
73 Minyak Bikesting
Kg
4,500
74 Minyak cat
Kg
7,000
75 Padas Urug
M3
45,000
76 Paku Biasa
Kg
9,000
77 Paku ulir + ring Karet
Bh
350
78 Paku Triplek
Kg
10,000
79 Paku Genteng Metal
Kg
22,500
80 Papan Nama Jalan Lengkap
Unit
200,000
81 Pasir Urug
M3
60,000
82 Pasir Batu (Sirtu)
M3
72,500
83 Pasir Beton
M3
120,000
84 Pasir Pasang
M3
90,000
85 Paving Block tb 6 cm Cetak Mesin
M2
35,000
86 Paving Block tb 8 cm Cetak Mesin
M2
45,000
87 PC (Portland Cement) berat 40 kg
Zak
45,000
88 PC (Portland Cement) berwarna untuk nuud
Kg
6,000
89 Pengukuran,Pematokan Lapangan
M2
500
91 Pintu doubel triplex
Bh
250,000
90 Pintu Panil kayu lokal
Bh
320,000
NO.
UPAH DAN BHN BANGUNAN
SATUAN
HARGA SATUAN
92 Pintu PVC lengkap
Bh
140,000
91 Pipa GIP Medium Ø ½ "
Bt
82,000
93 Pipa PVC Ø 1/2" AW
Bt
12,500
92 Pipa PVC Ø 1" 94 Pipa PVC Ø 1 1/4"
Bt Bt
12,500 17,500
93 Pipa PVC Ø 2"
Bt
22,500
95 Pipa PVC Ø 3"
Bt
32,500
96 Pipa PVC Ø 4"
Bt
40,000
97 Pipa Hawa PVC 1 1/4 " + Accessories
Bh
11,500
98 Pohon Penghijauan (Angsana t : 1,5 m)
Bt
25,000
99 Pupuk Kandang
M3
75,000
100 Rooster/lubang angin (terpasang)
Bh
15,000
101 Saringan Air Mangkok
Bh
12,000
102 Saringan air plat kuningan
Bh
-
103 Seltipe
Roll
2,500
104 Semen Putih
Zak
80,000
Lb
17,500
106 Seng Plaat BJLS.22 lb. 90 cm
Lb
32,000
106 Soket Gip Ø 1/2
Bh
2,500
107 Soket PVC Ø 1/2
Bh
1,500
107 Tanah U r u g
M3
50,000
108 Tee Pipa PVC Ø 1¼ "
Lb
2,250
109 Triplex t.3 MM uk.0,9 x2,10M
Lb
32,500
110 Triplex t.4 MM uk.0,9 x2,10M
Lb
45,000
111 Triplex t.6 MM uk.1.22x2.44M
Lb
65,000
112 Pek. Sumur Pantek + lengkap dengan pompa listrik & Accessories
Lb
1,550,000
105 Seng Plaat BJLS.22 lb. 40 cm
C.
DAFTAR HARGA SEWA ALAT :
112 Sewa Alat (Bulldozer)
1/ Per Jam
250,000
113 Sewa Alat (Concrete Mixer)
1/hari
175,000
114 Sewa Alat (Concrete Vibrator)
1/hari
225,000
115 Sewa Alat (Dump Truck)
1/hari
60,000
116 Sewa Alat (Escavator)
1/ Per Jam
225,000
117 Sewa Alat (Motor Grader)
1/ Per Jam
200,000
118 Sewa Alat (Sheep Roller)
1/ Per Jam
175,000
119 Sewa Alat (Stamper)
1/hari
45,000
120 Sewa Alat (Stone Walles) 121 Sewa Alat (Wheel Loader)
1/hari 1/hari
110,000 225,000
Semarang,
Maret 2011
Ass Man Produksi & PLPP
AMAT IMRON
RENCANA ANGGARAN BIAYA Pekerjaan : Pembangunan Rumah Lokasi : Bumi Palir Sejahtera Type Rumah : RSh 27 Melati
NO.
URAIAN PEKERJAAN
1.
2.
SA TU AN 3.
KOPEL 4.
TUNGGAL 5.
VOLUME
(Dinding Bataco diplester depan, Atap genteng). HARGA JMLH HARGA JMLH HARGA SATUAN KOPPEL TUNGGAL ( Rp. ) ( Rp. ) ( Rp. ) 6. 7. 8.
I 2. 3. 4. 5.
PEKERJAAN PERSIAPAN : Air Kerja Pengukuran, Pemat.& Pembers. Lapangan. Pemasangan Bouwplank 2 x pakai Keamanan
Ls Ls M' Ls
1.000 1.000 28.500 1.000
1.000 1.000 32.500 1.000
100,000.00 100,000.00 6,520.00 50,000.00
100,000.00 100,000.00 185,820.00 50,000.00 435,820.00
100,000.00 100,000.00 211,900.00 50,000.00 461,900.00
II 1. 2. 3. 4. 5.
PEKERJAAN PONDASI : Galian tanah pondasi Urugan tanah kembali & pemadatan bekas galian pondasi Urugan pasir bwh pondasi & lantai. Pas.pondasi Umpak batu kali t. 45 cm & menerus t. 25 cm Pas.pond. rolak teras Conblock ad. 1 Pc : 5 Ps
M3 M3 M3 M3 M'
4.627 1.667 0.907 2.054 4.700
4.857 1.724 0.964 2.169 4.700
15,600.00 7,480.00 82,900.00 411,660.00 10,900.00
72,181.20 12,467.29 75,169.58 845,343.81 51,230.00 1,056,391.88
75,769.20 12,897.39 79,936.33 892,684.71 51,230.00 1,112,517.63
III
PEKERJAAN DINDING A. DINDING MASIF :
1. 2.
Pasangan Dinding Conblock ad. 1Pc : 5 Psr Pasangan beton bertulang ad. 1 Pc: 2 Ps : 3 Krl - Sloof beton 10/15 cm - Sloof beton teras 10/15 cm (Besi Ø 7 mm) - Ring Balk uk 10/12 cm - Ring Balk sopi uk 10/12 cm - Balk Sofi uk 10/10 cm - Kolom tiang teras uk.12/12 cm - Kolom Praktis 10/10 cm - Beton Teras t = 7 cm - Beton Kantilever = 6 cm (diatas pintu belakang) Pekerjaan Plesteran ad. 1 Pc : 5 Psr - Plesteran dinding depan luar Pekerjaan Plesteran ad. 1 Pc : 5 Psr - Plesteran ornamen minimalis - Plesteran Tiang Teras - Plesteran dinding KM/WC tinggi 1.60 m - Plesteran Ban-banan diatas genteng batas unit Pasang Roster beton : - uk.15 x 25 cm Pas. locis kusen 1:2:3
M2
76.905
85.930
51,970.00
3,996,752.85
4,465,782.10
M3 M3 M3 M3 M3 M3 M3 M3 M3
0.471 0.053 0.377 0.225 0.078 0.037 0.393 0.187 0.048
0.534 0.053 0.427 0.250 0.094 0.037 0.445 0.187 0.048
3,008,750.00 3,008,750.00 3,008,750.00 3,008,750.00 2,717,550.00 2,717,550.00 2,717,550.00 3,008,750.00 3,008,750.00
1,417,121.25 157,959.38 1,133,697.00 676,427.18 212,512.41 101,745.07 1,067,453.64 563,914.97 145,773.94
1,606,672.50 157,959.38 1,285,338.00 750,984.00 256,264.97 101,745.07 1,208,766.24 563,914.97 145,773.94
M2
14.060
14.060
17,070.00
240,004.20
240,004.20
Ls M2 M2 M'
1.000 1.248 7.120 6.000
1.000 1.248 7.120 6.000
17,070.00 17,070.00 17,070.00 17,070.00
17,070.00 21,303.36 121,538.40 102,420.00
17,070.00 21,303.36 121,538.40 102,420.00
Bh Bh
19.000 10.000
19.000 10.000
15,000.00 1,650.00
285,000.00 16,500.00 10,277,193.65
285,000.00 16,500.00 11,347,037.13
BH BH BH BH
1.000 3.000 2.000 1.000
1.000 3.000 2.000 1.000
524,950.00 225,390.00 196,470.00 116,520.00
524,950.00 676,170.00 392,940.00 116,520.00
524,950.00 676,170.00 392,940.00 116,520.00
BH M2 Bh Bh BH BH
6.000 0.185 1.000 3.000 4.000 1.000
6.000 0.185 1.000 3.000 4.000 1.000
127,610.00 51,660.00 279,100.00 246,010.00 43,440.00 173,600.00
765,660.00 9,546.77 279,100.00 738,030.00 173,760.00 173,600.00 3,850,276.77
765,660.00 9,546.77 279,100.00 738,030.00 173,760.00 173,600.00 3,850,276.77
3.
4 5
1.
2. 3. 4. 4. 6. 7.
B. DINDING KOMPONEN : Pas. Kusen Kayu lokal keras 5/11 bersih - Kusen Type PJ - 2 (0.0846 M³/bh) - Kusen Type P - 1 (0.0377 M³/bh) - Kusen Type J - 2 (0.0469 M³/bh) - Kusen Type BV-1 Pas. Daun Jendela +kaca polos tebal 3 mm lengkap - ukuran : 1.02 x 0.52 m' ( J.2 ) Pas. Kaca Es tebal 3 mm pada kusen BV-1 Pas. Daun Pintu panil triplek lengk. engsel+grendel Pas. Daun Pintu doubel triplek 3 mm lengk. engsel+grendel Pas. Kunci tanam 2 slaag (Pintu dpn) Pas. Kusen & daun pintu PVC lengkap (KM/WC)
IV 1. 2. 3. 4. 5.
PEKERJAAN RANGKA ATAP. Pas Gording Kayu lokal ukuran 6/12 Pas & Balok Nok Kayu lokal ukuran 6/12 Pas. Kayu Ruiter ukuran 4/6 Pas Kasau 4/6 dan Reng 2/3 Pas. Papan Lisplang Cemen Silica 0.8/20
V 1. 2. 3.
PEK.PENUTUP ATAP DAN PLAFON Pas. Penutup atap genteng palentong Pas. Nok/bubungan genteng Pas.Rangka Plafond kayu lokal ukuran 4/6 : -Bagian luar -Bagian Dalam Penutup Plafond Eternit tebal 4 mm : - Bagian luar - Bagian Dalam
4.
VI 1.
2. VII 1. 2. 3.
4. 5. 6. 7.
PEKERJAAN LANTAI. Pas. Lantai Keramik uk. 30 x 30 cm : - R.Tamu + R.Kel / R.Makan + K. tidur + Dapur - Teras Belakang - Teras depan Lantai KM / WC ,Keramik Mulia KW.I 20x20 PEKERJAAN SANITAIR. Pas. Pipa Leiding PVC dia 1/2" + Accessories Pas. Kran Leiding 0 1/2" Pas. Pipa pembuangan : - Sal Tinja pipa PVC dia 4" - Sal air kotor bawah lantai PVC dia 3" Pas. Bak Mandi Fiberglass + dudukan Pas. Closet jongkok Porselin + dudukan Pas. beerput lengkap Pas. Saringan air plastik
M' M' M' M2 M'
32.000 5.500 5.500 40.496 18.830
32.000 5.500 5.500 40.496 18.830
31,780.00 31,780.00 12,490.00 48,720.00 14,060.00
1,016,960.00 174,790.00 68,695.00 1,972,965.12 264,749.80 3,498,159.92
1,016,960.00 174,790.00 68,695.00 1,972,965.12 264,749.80 3,498,159.92
M2 m'
40.496 5.500
40.496 5.500
23,340.00 42,400.00
945,176.64 233,200.00
945,176.64 233,200.00
M2 M2
9.235 24.174
9.235 24.174
44,080.00 44,080.00
407,078.80 1,065,572.29
407,078.80 1,065,572.29
M2 M2
9.235 24.174
9.235 24.174
17,480.00 17,480.00
161,427.80 422,554.53 3,235,010.06
161,427.80 422,554.53 3,235,010.06
M2 M2 M2 M2
22.749 0.720 2.500 1.640
22.749 0.720 2.500 1.640
80,760.00 80,760.00 80,760.00 70,260.00
1,837,225.39 58,147.20 201,900.00 115,226.40 2,212,498.99
1,837,225.39 58,147.20 201,900.00 115,226.40 2,212,498.99
M' BH
7.000 1.000
7.000 1.000
8,460.00 13,310.00
59,220.00 13,310.00
59,220.00 13,310.00
M' M' BH BH BH Bh
5.500 7.000 1.000 1.000 1.000 1.000
5.500 7.000 1.000 1.000 1.000 1.000
22,380.00 17,470.00 201,780.00 194,410.00 543,010.00 12,000.00
123,090.00 122,290.00 201,780.00 194,410.00 543,010.00 12,000.00 1,269,110.00
123,090.00 122,290.00 201,780.00 194,410.00 543,010.00 12,000.00 1,269,110.00
VIII 1. 2. 3. 4.
PEKERJAAN PENGECATAN. Pengecatan Kayu pada Kusen, daun pintu, daun jendela & Lisplank Pengecatan Metrolite pada dinding luar Pengecatan Metrolite pada dinding KM/WC Pengecatan Metrolite pada plafond luar & dalam
M2 M2 M2 M2
30.368 14.060 7.120 33.409
30.368 14.060 7.120 33.409
17,240.00 10,830.00 10,830.00 10,830.00
523,544.32 152,269.80 77,109.60 361,815.14 1,114,738.86
523,544.32 152,269.80 77,109.60 361,815.14 1,114,738.86
IX 1. 2.
PEKERJAAN LAIN-LAIN. Pembersihan lapangan setelah selesai pembangunan Jl. Masuk Rumah, Rabat Beton ad. 1 Ps : 3 Ps : 5 Krl uk. 80x300x8 cm
Ls M2
1.000 2.400
1.000 2.400
100,000.00 26,190.00
100,000.00 62,856.00 162,856.00
100,000.00 62,856.00 162,856.00
REKAPITULASI RENCANA ANGGARAN BIAYA PEKERJAAN PEMBANGUNAN RUMAH TYPE RSh. 27/72 Melati DI LOKASI BUMI PALIR SEJAHTERA PERUM PERUMNAS CABANG SEMARANG I (Dinding Bataco diplester depan, Atap genteng). URAIAN PEKERJAAN
NO.
2
1 I
PEKERJAAN PERSIAPAN :
II
PEKERJAAN PONDASI :
III
PEKERJAAN DINDING
JMLH HARGA
JMLH HARGA
KOPPEL
TUNGGAL
( Rp. )
( Rp. )
3.
4.
435,820.00
461,900.00
1,056,391.88
1,112,517.63
10,277,193.65
11,347,037.13
B. DINDING KOMPONEN :
3,850,276.77
3,850,276.77
IV
PEKERJAAN RANGKA ATAP.
3,498,159.92
3,498,159.92
V
PEK.PENUTUP ATAP DAN PLAFON
3,235,010.06
3,235,010.06
VI
PEKERJAAN LANTAI.
2,212,498.99
2,212,498.99
VII
PEKERJAAN SANITAIR.
1,269,110.00
1,269,110.00
VIII
PEKERJAAN PENGECATAN.
1,114,738.86
1,114,738.86
162,856.00
162,856.00
27,112,056.13
28,264,105.36
2,711,205.61
2,826,410.54
JUMLAH TOTAL
29,823,261.74
31,090,515.90
DIBULATKAN
29,823,000.00
31,090,000.00
HARGA / M2
1,104,555.56
1,151,481.48
A. DINDING MASIF :
X
PEKERJAAN LAIN-LAIN. JUMLAH SUB TOTAL JASA KONTRAKTOR 10 %
Mengetahui/Menyetujui Manager Cabang
Semarang, Maret 2011 Ass Man Produksi & PLPP
AKHMAD RUKHIMAN
AMAT IMRON
RENCANA ANGGARAN BIAYA (RAB) PEKERJAAN LOKASI TYPE RUMAH
: PEMBANGUNAN RUMAH RSh. 29 : BUMI PALIR SEJAHTERA PERUM PERUMNAS CABANG SEMARANG I : RSh. 29 (Pelana)
NO.
URAIAN PEKERJAAN
1.
2.
SA TU
(Dinding Conblock, Atap genteng Palentong). VOLUME
HARGA SATUAN
JMLH HARGA KOPPEL
AN
KOPEL
TUNGGAL
( Rp. )
( Rp. )
3.
4.
5.
6.
7.
I 1. 2. 3. 4.
PEKERJAAN PERSIAPAN : Air Kerja Pengukuran, Pemat.& Pembers. Lapangan. Pemasangan Bouwplank 2 x pakai Keamanan
Ls m2 M' Ls
1.000 1.000 22.000 1.000
1.000 1.000 30.000 1.000
100,000.00 100,000.00 6,520.00 50,000.00
100,000.00 100,000.00 143,440.00 50,000.00 393,440.00
II 1. 2. 3. 4. 5.
PEKERJAAN PONDASI : Galian tanah pondasi Urugan tanah kembali & pemadatan bekas galian pondasi Urugan pasir bwh pondasi & lantai. Pas.pondasi menerus batu kali Ad.1 Pc :5 Ps t. 45 cm Pas.pond. rolak teras conblock ad. 1 Pc : 5 Ps
M3 M3 M3 M3 M'
2.243 0.702 1.976 1.780 5.200
3.044 0.838 2.056 2.732 5.200
15,600.00 7,480.00 82,900.00 411,660.00 10,900.00
34,990.80 5,250.96 163,810.40 732,754.80 56,680.00 993,486.96
III
PEKERJAAN DINDING A. DINDING MASIF :
1. 2.
Pasangan Dinding Conblock ad. 1 Pc : 5 Ps Pasangan beton bertulang ad. 1 Pc: 2 Ps : 3 Krl - Sloof beton 10/15 cm - Ring Balk uk 10/12 cm - Balk Sofi uk 10/12 cm - Kolom tiang teras uk.12/12 cm - Kolom Praktis 10/10 cm Pekerjaan Plesteran ad. 1 Pc : 5 Psr - Plesteran dinding luar - Plesteran Tiang Teras - Plesteran dinding KM/WC tinggi 1.60 m Pasang Roster beton : - uk.20 x 20 cm / 15 x 25 cm Pas. locis kusen 1:2:3
M2
80.000
87.000
51,970.00
4,157,600.00
M3 M3 M3 M3 M3
0.453 0.366 0.210 0.038 0.345
0.517 0.407 0.327 0.038 0.417
3,008,750.00 3,008,750.00 3,008,750.00 2,717,550.00 2,717,550.00
1,362,963.75 1,101,202.50 631,837.50 103,266.90 937,554.75
M2 M2 M2
10.716 1.699 7.680
10.716 1.699 7.680
17,070.00 17,070.00 17,070.00
182,922.12 29,001.93 131,097.60
Bh Bh
16.000 10.000
16.000 10.000
15,000.00 1,650.00
240,000.00 16,500.00 8,893,947.05
BH BH BH BH
3.000 1.000 2.000 1.000
3.000 1.000 2.000 1.000
225,390.00 524,950.00 196,470.00 116,520.00
676,170.00 524,950.00 392,940.00 116,520.00
BH BH
2.000 1.000
2.000 1.000
127,610.00 127,610.00
255,220.00 127,610.00
M2 M2 Bh Bh BH BH
0.840 0.273 1.000 3.000 2.000 1.000
0.840 0.273 1.000 3.000 2.000 1.000
127,610.00 51,660.00 279,100.00 246,010.00 43,440.00 173,600.00
107,192.40 14,092.85 279,100.00 738,030.00 86,880.00 173,600.00 3,492,305.25
M' M' M' M2 M'
34.800 5.800 5.800 52.200 21.000
34.800 5.800 5.800 52.200 21.000
31,780.00 31,780.00 12,490.00 48,720.00 14,060.00
1,105,944.00 184,324.00 72,442.00 2,543,184.00 295,260.00 4,201,154.00
3.
4 5
4. 5. 6. 7. 8.
B. DINDING KOMPONEN : Pas. Kusen Kayu Lokal keras 5/11 bersih - Kusen Type P - 1 (0.038 M³/bh) - Kusen Type PJ-2 (0.087 M³/bh) - Kusen Type J - 1 (0.030 M³/bh) - Kusen Type BV-1 Pas. Daun Jendela +kaca polos tebal 5 mm lengkap - ukuran : 1.02 m' x 0.62 m' ( J.1 ) - ukuran : 1.02 m' x 0.62 m' ( PJ.2 ) Pasang Kaca mati polos tebal 5 mm : - ukuran : 0.8 m' x 1.02 m' = 1 bh ( PJ.2 ) Pas. Kaca Es tebal 3 mm pada kusen BV-1 Pas. Daun Pintu panil triplek lengk. engsel+grendel Pas. Daun Pintu doubel triplek 3 mm lengk. engsel+grendel Pas. kunci tanam 2 slaag (Pintu dpn & Blk) Pas. Kusen & daun pintu PVC lengkap (KM/WC) - P2
IV 1. 2. 3. 4. 5.
PEKERJAAN RANGKA ATAP. Pas Gording Kayu lokal ukuran 6/12 Pas Balok Nok Kayu lokal ukuran 6/12 Pas. Kayu Ruiter ukuran. 4/6 Pas Kasau 4/6 dan Reng 2/3 Pas. Papan Lisplang Cemen Silica 0.8/20
1.
2. 3.
V 1. 2. 3. 4.
VI 1.
2. VII 1. 2. 3.
PEK.PENUTUP ATAP DAN PLAFON Pas. Penutup atap genteng palentong Pas. Nok/bubungan genteng Pas.Rangka Plafond kayu lokal ukuran 4/6 : -Bagian Dalam -Bagian Luar Penutup Plafond Eternit tebal 4 mm : -Bagian Dalam -Bagian Luar PEKERJAAN LANTAI. Pas. Lantai Keramik uk. 30 x 30 cm (polos) - R.Tamu + R.Kel / R.Makan + K. tidur + Dapur - Teras Belakang - Teras depan Lantai KM / WC ,Keramik Mulia KW.I 20x20
M2 m'
52.200 5.800
52.200 5.800
1,218,348.00 245,920.00
25.300 18.980
23,340.00 42,400.00 44,080.00 44,080.00 17,480.00 17,480.00
M2 M2
25.300 18.980
25.300 18.980
M2 M2
25.300 18.980
M2 M2 M2 M2
23.340 0.720 2.500 1.780
23.340 0.540 2.500 1.780
80,760.00 80,760.00 80,760.00 70,260.00
1,884,938.40 58,147.20 201,900.00 125,062.80 2,270,048.40
M' BH
10.000 1.000
10.000 1.000
84,600.00 13,310.00
M' M' BH BH BH Bh
9.000 11.000 1.000 1.000 1.000 1.000
9.000 11.000 1.000 1.000 1.000 1.000
8,460.00 13,310.00 22,380.00 17,470.00 201,780.00 194,410.00 543,010.00 12,000.00
1,115,224.00 836,638.40 442,244.00 331,770.40 4,190,144.80
4. 5. 6. 7.
PEKERJAAN SANITAIR. Pas. Pipa Leiding PVC dia 1/2" + Accessories Pas. Kran Leiding 0 1/2" Pas. Pipa pembuangan : - Sal Tinja pipa PVC dia 4" - Sal air kotor bawah lantai PVC dia 3" Pas. Bak Mandi Fiberglass Oval 100 ltr + dudukan Pas. Closet jongkok Porselin + dudukan Pas. beerput lengkap sedalam 1,5 m Pas. Saringan air plastik
VIII 1. 2. 3. 4.
PEKERJAAN PENGECATAN. Pengecatan Kayu pada Kusen, daun pintu, daun jendela & Lisplank Pengecatan Metrolite pada dinding luar Pengecatan Metrolite pada dinding KM/WC Pengecatan Metrolite pada plafond luar & dalam
M2 M2 M2 M2
31.284 12.415 7.680 44.280
31.284 12.415 7.680 44.280
17,240.00 10,830.00 10,830.00 10,830.00
539,336.16 134,454.45 83,174.40 479,552.40 1,236,517.41
IX 1. 2.
PEKERJAAN LAIN-LAIN. Pembersihan lapangan setelah selesai pembangunan Pek. Jalan masuk rumah beton ad. 1:3:5 ( 5 x 0.06 x 0,90 m)
Ls M2
1.000 4.500
1.000 4.500
100,000.00 26,190.00
100,000.00 117,855.00 217,855.00
201,420.00 192,170.00 201,780.00 194,410.00 543,010.00 12,000.00 1,442,700.00
REKAPITULASI RENCANA ANGGARAN BIAYA PEKERJAAN PEMBANGUNAN RUMAH RsH. 29 DI LOKASI BUMI PALIR SEJAHTERA PERUM PERUMNAS CABANG SEMARANG I
NO.
URAIAN PEKERJAAN
1
2
JMLH HARGA KOPPEL ( Rp. ) 3.
I
PEKERJAAN PERSIAPAN :
393,440.00
II
PEKERJAAN PONDASI :
993,486.96
III
PEKERJAAN DINDING A. DINDING MASIF :
8,893,947.05
B. DINDING KOMPONEN :
3,492,305.25
IV
PEKERJAAN RANGKA ATAP.
4,201,154.00
V
PEK.PENUTUP ATAP DAN PLAFON
4,190,144.80
VI
PEKERJAAN LANTAI.
2,270,048.40
VII
PEKERJAAN SANITAIR.
1,442,700.00
VIII
PEKERJAAN PENGECATAN.
1,236,517.41
IX
PEKERJAAN LAIN-LAIN.
217,855.00
JUMLAH SUB TOTAL
`
JASA KONTRAKTOR 10 %
27,331,598.87 2,733,159.89
JUMLAH TOTAL
30,064,758.76
DIBULATKAN
30,064,000.00
HARGA / M2
1,036,689.66 Mengetahui/Menyetujui Manager Cabang
Semarang, Maret 2011 Ass Man Produksi & PLPP
AKHMAD RUKHIMAN
AMAT IMRON
(Dinding Conblock, Atap genteng Palentong). JMLH HARGA TUNGGAL ( Rp. ) 8. 100,000.00 100,000.00 195,600.00 50,000.00 445,600.00 47,486.40 6,268.24 170,442.40 1,124,655.12 56,680.00 1,405,532.16
4,521,390.00 1,555,523.75 1,224,561.25 983,861.25 103,266.90 1,133,218.35 182,922.12 29,001.93 131,097.60 240,000.00 16,500.00 10,121,343.15
676,170.00 524,950.00 392,940.00 116,520.00 255,220.00 127,610.00 107,192.40 14,092.85 279,100.00 738,030.00 86,880.00 173,600.00 3,492,305.25 1,105,944.00 184,324.00 72,442.00 2,543,184.00 295,260.00 4,201,154.00
1,218,348.00 245,920.00 1,115,224.00 836,638.40 442,244.00 331,770.40 4,190,144.80
1,884,938.40 43,610.40 201,900.00 125,062.80 2,255,511.60 84,600.00 13,310.00 201,420.00 192,170.00 201,780.00 194,410.00 543,010.00 12,000.00 1,442,700.00 539,336.16 134,454.45 83,174.40 479,552.40 1,236,517.41 100,000.00 117,855.00 217,855.00
I RsH. 29 (Pelana) JMLH HARGA TUNGGAL ( Rp. ) 4. 445,600.00 1,405,532.16 10,121,343.15 3,492,305.25 4,201,154.00 4,190,144.80 2,255,511.60 1,442,700.00 1,236,517.41 217,855.00 29,008,663.37 2,900,866.34 31,909,529.71 31,909,000.00 1,100,310.34
RENCANA ANGGARAN BIAYA (RAB) Pekerjaan Lokasi Type Rumah
: PEMBANGUNAN RUMAH RS 36 : BUKIT BERINGIN LESTARI : RS 36 Type Cempaka
NO.
URAIAN PEKERJAAN
1.
2.
SA TU AN 3.
KOPEL 4.
TUNGGAL 5.
VOLUME
(Dinding Bata Merah diplester, Atap genteng). HARGA JMLH HARGA JMLH HARGA SATUAN KOPPEL TUNGGAL ( Rp. ) ( Rp. ) ( Rp. ) 6. 7. 8.
I 1 2 3 4
PEKERJAAN PERSIAPAN : Air Kerja Pengukuran, Pemat.& Pembers. Lapangan. Pemasangan Bouwplank 2 x pakai Keamanan
Ls m2 M' Ls
1.000 1.000 34.000 1.000
1.000 1.000 36.700 1.000
100,000.00 100,000.00 6,520.00 50,000.00
100,000.00 100,000.00 221,680.00 50,000.00 471,680.00
100,000.00 100,000.00 239,284.00 50,000.00 489,284.00
II 1. 2. 3. 4. 5.
PEKERJAAN PONDASI : Galian tanah pondasi Urugan tanah kembali & pemadatan bekas galian pondasi Urugan pasir bwh pondasi & lantai. Pas.pondasi umpak batu kali t. 45 cm & menerus t. 25 cm Pas.pond. rolak teras bata merah ad. 1 Pc : 3 Ps
M3 M3 M3 M3 M'
4.940 1.745 0.985 2.210 6.200
5.170 1.803 1.043 2.325 6.200
15,600.00 7,480.00 82,900.00 411,660.00 10,900.00
77,064.00 13,052.60 81,656.50 909,768.60 67,580.00 1,149,121.70
80,652.00 13,482.70 86,423.25 957,109.50 67,580.00 1,205,247.45
III
PEKERJAAN DINDING A. DINDING MASIF :
1.
Pasangan Dinding Bata Merah ad. 1Pc : 6 Psr - Pas. Bata Tiang teras Pasangan beton bertulang ad. 1 Pc: 2 Ps : 3 Krl - Sloof beton 10/15 cm - Sloof beton teras 10/15 cm - Ring Balk uk 10/12 cm - Ring Balk Sopi uk 10/12 cm - Balk Sofi uk 10/12 cm - Kolom tiang teras uk.12/12 cm - Kolom Praktis 10/10 cm - Dak Beton Teras t = 7 cm - Balk Pengaku Dak Teras 10/12 cm - Dak Beton Kantilever t : 5 cm (diatas pintu belakang & Jendela) Pekerjaan Plesteran ad. 1 Pc : 5 Psr - Plesteran dinding luar - Plesteran dinding dalam Pekerjaan Plesteran ad. 1 Pc : 5 Psr - Plesteran ornamen minimalis - Plesteran Tiang Teras - Plesteran dinding KM/WC tinggi 1.60 m Pasang Roster Beton : - uk.15 x 35 cm Pas. locis kusen 1:2:3
M2 M3
98.326 0.840
114.058 0.840
56,380.00 56,380.00
5,543,619.88 47,359.20
6,430,590.04 47,359.20
M3 M3 M3 M3 M3 M3 M3 M3 M3 M3
0.681 0.060 0.402 0.257 0.103 0.040 0.391 0.381 0.054 0.118
0.678 0.060 0.470 0.257 0.123 0.040 0.447 0.381 0.054 0.118
3,008,750.00 3,008,750.00 3,008,750.00 3,008,750.00 3,008,750.00 3,008,750.00 2,717,550.00 3,008,750.00 3,008,750.00 3,008,750.00
2,048,657.88 180,525.00 1,209,517.50 773,369.10 310,051.69 121,312.80 1,062,562.05 1,145,732.00 162,472.50 355,634.25
2,039,932.50 180,525.00 1,415,316.00 773,369.10 369,474.50 121,312.80 1,214,744.85 1,145,732.00 162,472.50 355,634.25
M2 M2
64.463 115.765
94.013 115.765
17,070.00 17,070.00
1,100,380.00 1,976,105.14
1,604,798.50 1,976,105.14
Ls M2 M2
1.000 3.360 7.120
1.000 3.360 7.120
250,000.00 17,070.00 17,070.00
250,000.00 57,355.20 121,538.40
250,000.00 57,355.20 121,538.40
Bh Bh
19.000 10.000
19.000 10.000
25,000.00 1,650.00
475,000.00 16,500.00 16,957,692.57
475,000.00 16,500.00 18,757,759.97
BH BH BH BH
1.000 3.000 3.000 1.000
1.000 3.000 3.000 1.000
524,950.00 225,390.00 196,470.00 116,520.00
524,950.00 676,170.00 589,410.00 116,520.00
524,950.00 676,170.00 589,410.00 116,520.00
BH M2 Bh Bh BH BH BH
6.000 0.185 1.000 3.000 1.000 3.000 1.000
6.000 0.185 1.000 3.000 1.000 3.000 1.000
127,610.00 51,660.00 395,500.00 279,100.00 79,050.00 43,440.00 173,600.00
765,660.00 9,546.77 395,500.00 837,300.00 79,050.00 130,320.00 173,600.00 4,298,026.77
765,660.00 9,546.77 395,500.00 837,300.00 79,050.00 130,320.00 173,600.00 3,773,076.77
2. 1.10
3.
4. 5. 6.
1.
2. 3. 4. 5. 6. 7. 8.
B. DINDING KOMPONEN : Pas. Kusen Kayu Meranti 5/11 bersih - Kusen Type P - Utama (0.0377 M³/bh) - Kusen Type P - 1 (0.0377 M³/bh) - Kusen Type J - 2 (0.0469 M³/bh) - Kusen Type BV-1 Pas. Daun Jendela +kaca polos tebal 5 mm lengkap - ukuran : 1.25 x 0.52 m' ( J.2 ) Pas. Kaca Es tebal 3 mm pada kusen BV-1 Pas. Daun Pintu panil kayu Suren/Johar + lengk. engsel+grendel Pas. Daun Pintu Panil Triplex lengk. engsel+grendel Pas. Kunci tanam 2 slaag (Pintu dpn) Setara beluci/yale Pas. Kunci tanam 2 slaag Pas. Kusen & daun pintu PVC lengkap (KM/WC) (P2)
IV 1. 2. 3. 4. 5.
PEKERJAAN RANGKA ATAP. Pas Gording Kayu lokal ukuran 6/12 Pas & Balok Nok Kayu lokal ukuran 6/12 Pas. Kayu Ruiter kayu ukuran 4/6 Pas Kasau 4/6 dan Reng 2/3 Pas. Papan Lisplang Cemen Silica 0.8/20
V 1. 2. 3.
PEK.PENUTUP ATAP DAN PLAFON Pas. Penutup atap genteng Mantili Besar Pas. Nok/bubungan genteng Mantili Pas.Rangka Plafond kayu lokal ukuran 4/6 : -Bagian Luar -Bagian Dalam Penutup Plafond Eternit tebal 4 mm : - Bagian Luar - Bagian Dalam
4.
VI 1. 2.
3. VII 1. 2. 3.
PEKERJAAN LANTAI. Urugan Pasir bawah lantai tebal 5 cm Pas. Lantai Keramik uk. 30 x 30 cm (polos) - R.Tamu + R.Kel / R.Makan + K. tidur + Dapur - Teras Belakang Pas. Lantai Keramik uk. 30 x 30 cm (Warna) - Teras depan Lantai KM / WC ,Keramik Mulia KW.I 20x20
M' M' M' M2 M'
48.500 6.500 6.500 50.974 19.400
48.500 6.500 6.500 50.974 19.400
31,780.00 31,780.00 12,490.00 48,720.00 14,060.00
1,541,330.00 206,570.00 81,185.00 2,483,453.28 272,764.00 4,585,302.28
1,541,330.00 206,570.00 81,185.00 2,483,453.28 272,764.00 4,585,302.28
M2 m'
52.974 6.500
54.974 6.500
41,370.00 42,400.00
2,191,534.38 275,600.00
2,274,274.38 275,600.00
M2 M2
9.425 30.724
9.425 30.724
44,080.00 44,080.00
415,454.00 1,354,296.29
415,454.00 1,354,296.29
M2 M2
9.425 30.724
9.425 30.724
17,480.00 17,480.00
164,749.00 537,048.53 4,938,682.20
164,749.00 537,048.53 5,021,422.20
M³
1.800
1.800
9,750.00
17,550.00
17,550.00
M2 M2
32.299 1.000
32.299 1.000
80,760.00 80,760.00
2,608,483.39 80,760.00
2,608,483.39 80,760.00
M2 M2
3.750 1.780
3.750 1.780
80,760.00 70,260.00
302,850.00 125,062.80 3,134,706.19
302,850.00 125,062.80 3,134,706.19
M' BH
7.000 1.000
7.000 1.000
8,460.00 13,310.00
59,220.00 13,310.00
59,220.00 13,310.00
M' M' BH BH BH Bh
5.500 7.000 1.000 1.000 1.000 1.000
5.500 7.000 1.000 1.000 1.000 1.000
22,380.00 17,470.00 201,780.00 194,410.00 543,010.00 12,000.00
123,090.00 122,290.00 201,780.00 194,410.00 543,010.00 12,000.00 1,269,110.00
123,090.00 122,290.00 201,780.00 194,410.00 543,010.00 12,000.00 1,269,110.00
4. 5. 6. 7.
PEKERJAAN SANITAIR. Pas. Pipa Leiding PVC dia 1/2" + Accessories Pas. Kran Leiding 0 1/2" Pas. Pipa pembuangan : - Sal Tinja pipa PVC dia 4" - Sal air kotor bawah lantai PVC dia 3" Pas. Bak Mandi Fiberglass oval + dudukan Pas. Closet jongkok Porselin + dudukan Pas. Beerput lengkap sedalam = 2 m Pas. Saringan air plastik
VIII 1. 2. 3. 4. 5.
PEKERJAAN PENGECATAN. Pengecatan Kayu Kusen, dn pintu, dn jendela & Lisplank Pengecatan Metrolite pada dinding luar Pengecatan Metrolite pada dinding dalam Pengecatan Metrolite pada dinding KM/WC Pengecatan Metrolite pada plafond luar & dalam
M2 M2 M2 M2 M2
30.368 76.463 115.765 7.120 40.149
32.368 94.013 115.765 7.120 40.149
17,240.00 10,830.00 10,830.00 10,830.00 10,830.00
523,551.22 828,092.12 1,253,732.78 77,109.60 434,809.34 3,117,295.06
558,031.22 1,018,158.62 1,253,732.78 77,109.60 434,809.34 3,341,841.56
IX 1. 2.
PEKERJAAN LAIN-LAIN. Pembersihan lapangan setelah selesai pembangunan Pek. Jalan masuk rumah beton ad. 1:3:5 ( 6 x 0.06 x 0,90 m)
Ls M2
1.000 5.400
1.000 5.400
100,000.00 38,500.00
100,000.00 207,900.00 307,900.00
100,000.00 207,900.00 307,900.00
REKAPITULASI RENCANA ANGGARAN BIAYA PEKERJAAN PEMBANGUNAN RUMAH RS 36 DI LOKASI BKIT BERINGIN LESTARIA PERUM PERUMNAS CABANG SEMARANG I (Dinding Bata Merah diplester, Atap genteng).
NO.
URAIAN PEKERJAAN
1
2
I
PEKERJAAN PERSIAPAN :
II
PEKERJAAN PONDASI :
III
PEKERJAAN DINDING
JMLH HARGA
JMLH HARGA
KOPPEL
TUNGGAL
( Rp. )
( Rp. )
3.
4.
471,680.00
489,284.00
1,149,121.70
1,205,247.45
16,957,692.57
18,757,759.97
B. DINDING KOMPONEN :
4,298,026.77
3,773,076.77
IV
PEKERJAAN RANGKA ATAP.
4,585,302.28
4,585,302.28
V
PEK.PENUTUP ATAP DAN PLAFON
4,938,682.20
5,021,422.20
VI
PEKERJAAN LANTAI.
3,134,706.19
3,134,706.19
VII
PEKERJAAN SANITAIR.
1,269,110.00
1,269,110.00
VIII
PEKERJAAN PENGECATAN.
3,117,295.06
3,341,841.56
A. DINDING MASIF :
IX
PEKERJAAN LAIN-LAIN. JUMLAH SUB TOTAL JASA KONTRAKTOR 10 % JUMLAH TOTAL PPN 10 %
307,900.00
307,900.00
40,229,516.77
41,885,650.42
4,022,951.68
4,188,565.04
44,252,468.45
46,074,215.46
-
JUMLAH TOTAL
-
44,252,468.45
46,074,215.46
DIBULATKAN
44,252,000.00
46,074,000.00
HARGA / M2
1,229,222.22
1,279,833.33
Mengetahui/Menyetujui Manager Cabang
AKHMAD RUKHIMAN
21,741,000.00 23,071,000.00 Semarang, Maret 2011 Ass Man Produksi & PLPP
AMAT IMRON
RENCANA ANGGARAN BIAYA (RAB) PAKET I #REF! DI LOKASI BUMI PALIR SEJAHTERA PERUM PERUMNAS CABANG SEMARANG I URAIAN PEKERJAAN
NO 1 I. 1 2 3
2 PEKERJAAN PERSIAPAN Air Kerja / Alat bantu Keamanan Pengukuran, Pematokan & Pembersihan lapangan
VOLUME
SAT
3
4 1.00 1.00 1.00
Ls Ls Ls
HARGA SATUAN ( Rp ) 5 1,000,000.00 1,500,000.00 1,000,000.00
Jumlah
II. 1 1 2 3 4
III. 1 2 3 4
PEKERJAAN PERBAIKAN JALAN & SALURAN Pek. Pembuatan Saluran Type S.1 Pek. Pembuatan Saluran Type S.2 Pek. Pembuatan Jalan DMJ 6 Pek. Pembuatan Jalan DMJ 8 Pekerjaan Normalisasi Saluran Jumlah PEKERJAAN LAIN-LAIN Pek. Jembatan Masuk Rumah Uk. 0.8*0.7*0.08 m Pek. Pembuatan Sumur Resapan Pek. Sumur Pantek + lengkap dengan pompa listrik & Accessories Plat Nomor Rumah Jumlah
\\vboxsrv\conversion_tmp\scratch_4\[146701492.xls.ms_office.xls]RS 36 Cempaka
JUMLAH HARGA ( Rp ) 6 1,000,000.00 1,500,000.00 1,000,000.00 3,500,000.00
194.00 108.00 87.00 112.00 70.00
m' m' m' m' m'
108,520.00 133,820.00 245,620.00 349,690.00 48,750.00
21,052,880.00 14,452,560.00 21,368,940.00 39,165,280.00 3,412,500.00 99,452,160.00
34.00 34.00 34.00 34.00
bh unit unit bh
134,790.00 623,440.00 1,550,000.00 20,000.00
4,582,860.00 21,196,960.00 52,700,000.00 680,000.00 79,159,820.00
REKAPITULASI RENCANA ANGGARAN BIAYA (RAB) PAKET I #REF! DI LOKASI BUMI PALIR SEJAHTERA PERUM PERUMNAS CABANG SEMARANG I NO.
URAIAN PEKERJAAN
1
2
JUMLAH HARGA ( Rp. ) 3
I
PEKERJAAN PERSIAPAN
3,500,000.00
II.
PEKERJAAN PERBAIKAN JALAN & SALURAN
99,452,160.00
III.
PEKERJAAN LAIN-LAIN
79,159,820.00
JUMLAH SUB TOTAL
182,111,980.00
JASA KONTRAKTOR 10 %
18,211,198.00
JUMLAH
200,323,178.00
DIBULATKAN
200,323,000.00
Mengetahui/Menyetujui Manager Cabang
Semarang, Maret 2011 Ass Man Produksi & PLPP
AKHMAD RUKHIMAN
AMAT IMRON
URAIAN ANALISA HARGA SATUAN ( METODE PELAKSANAAN )
NO
PEKERJAAN
: PEKERJAAN CUT/FILL DAN PERBAIKAN JALAN
LOKASI
:
U R A I A N
KODE
KOEF.
SATUAN
A. I 1 2 3 4 5
PEKERJAAN PENGERUKAN SLAURAN ASUMSI Pekerjaan pengerukan saluran dilakukan secara manual Lokasi pekerjaan sepanjang jalan komplek perumahan Kondisi existing jalan sedang/baik Jam kerja efektif per hari Faktor pengembangan bahan
Tk Fk
7.0000 1.1000
Jam -
II 1 2 3
URUTAN KERJA Saluran yang dikeruk saluran induk Penggalian dilakukan dengan manual Truck Bak Pendek membuang bekas galian tersebut ke luar Site dengan jaeak pembuangan sejauh
L
5.0000
Km
V Fa v1 v2 Ts2 T1 T2 T3 Ts2
2.0000 0.8300 30.0000 40.0000
M3 Km/Jam Km/Jam
10.0000 7.5000 35.0000 52.5000
Menit Menit Menit Menit
Q2
4.3117 0.2319
M3/Jam Jam
III 1
PEMAKAIAN BAHAN, ALAT DAN TENAGA BAHAN Tidak ada bahan yang dipakai
2
ALAT - TRUCK BAK PENDEK Kapasitas bak Faktor efesien alat Kecepatan rata-rata bermuatan Kecepatan rata-rata kosong Waktu siklus - Waktu tempuh isi = (L/v1) x 60 - Waktu tempuh kosong = (L/v2) x 60 - Lain-lain ( bongkar muat)
Kapasitas produksi / jam = (V x Fa x 60 ) / ( Fk x Ts2 ) Koefisien alat / m3 = 1/Q2
NO
U R A I A N
KODE
- ALAT BANTU Diperlukan alat bantu kecil-kecil : Sekop, keranjang, cangkul dii - TENAGA Produksi menentukan : Manual Produksi per hari = Tk x Q1 Kebutuhan tenaga - Mandor - Pekerja
KOEF.
SATUAN
1.0000
Lumpsum
Q1 Qt
2.0000 14.0000
M3/Jam M3
M P
0.5000 2.0000
Orang Orang
0.2500 1.0000
Jam Jam
Koefisien tenaga / m3 - Mandor = ( Tk x M ) / Qt - Tenaga = ( Tk x P ) / Qt
B. I 1 2 3 4 5
PEKERJAAN GALIAN TANAH KERAS (PADAS) ASUMSI Pekerjaan galian dilakukan secara mekanis Lokasi pekerjaan dalam komplek perumahan Kondisi existing jalan sedang/baik Jam kerja efektif per hari Faktor pengembangan bahan
Tk Fk
7.0000 1.2000
Jam -
II 1 2
URUTAN KERJA Tanah yang digali berada dalam lokasi perumahan KONDISI padas berbatu Penggalian dilakukan denganBoldozer dan Excavator sekaligus menuangkan material kedalam Dump Truck Dump Truck membuang bekas galian tersebut ke lokasi Blok A dan C dengan jarak pembuangan sejauh
L
1.0000
Km
3
III 1
PEMAKAIAN BAHAN, ALAT DAN TENAGA BAHAN Tidak ada bahan yang dipakai
2
ALAT - BOLDOZER Jarak operasi Panjang efektif Blade Faktor efesiensi alat Total potongan / galian Kecepatan Jumlah lintasan Waktu siklus = ((( n x Lh ) / c ) x 1 jam)/1000 Kapasitas produksi / jam ( Lh x b x V x Fa ) / ( Fk x Ts x n ) Koefisien alat / M3 = 1/Q1
Lh b Fa V c n Ts Q1
25.00000 2.00000 0.83000 0.15000 2.00000 4.00000 0.05000 25.93750 0.03855
M M M Km/Jam PP Jam M3/Jam Jam
NO
U R A I A N
- EXCAVATOR PC 200 Kapasitan bucket Faktor bucket Faktor efesiensi alat Waktu siklus - Mengisi / memuat - Lain-lain
Kapasitas produksi / jam = (V x Fa x Fb x 60 ) / ( Fk x Ts1 ) Koefisien alat / m3 = 1/Q1 - DUMP TRUCK Kapasitas bak Faktor efesien alat Kecepatan rata-rata bermuatan Kecepatan rata-rata kosong Waktu siklus - Waktu tempuh isi = (L / v1 ) x 60 - Waktu tempuh kosong = (L / v2 ) x 60 - Lain-lain Kapasitas produksi / jam = (V x Fa x 60 ) / ( Fk x Ts2 ) Koefisien alat / m3 = 1/Q2
KODE
Kebutuhan tenaga - Mandor - Pekerja
01
0 0. .
0.50 0.70 0.63 0.70 0.60 0.70 0.80 0.62 0.50 2.73 1.80 3,00
= ( Tk x M ) / Qt = ( Tk x P ) / Qt 0
00 ,, 43 0 0
Koefisien tenaga / m3 - Mandor - Tenaga
SATUAN
V Fb Fa Ts1 T1 T2 Ts1
0.8000 0.9500 0.8300
M3 -
1.5000 0.5000 2.0000
Menit Menit Menit
Q1
15.7700 0.0634
M3/Jam Jam
V Fa v1 v2 Ts2 T1 T2 T3 Ts2
4.0000 0.8300 10.0000 20.0000
M3 Km/Jam Km/Jam
6.0000 3.0000 5.0000 14.0000
Menit Menit Menit Menit
Q2
11.8571 0.0843
M3/Jam Jam
1.0000
Lumpsum
- ALAT BANTU Diperlukan alat bantu kecil-kecil : Sekop, keranjang, cangkul dii - TENAGA Produksi menentukan : Buldozer Produksi per hari = Tk x Q1
KOEF.
Q1 Qt
25.9375 181.5625
M3/Jam M3
M P
0.2500 1.0000
Orang Orang
0.0096 0.0386
Jam Jam
URAIAN ANALISA HARGA SATUAN ( METODE PELAKSANAAN )
KETERANGAN
KETERANGAN
KETERANGAN
00 01,, 0 0
SLOOF 12/15 Ø 15
Ø
11 Ø
Ø
8.00 12.00
Ø 8 Tulang Pokok
1 M'
Ø8x4
=
4 m
Ø 6 Beugel
1 M'
Ø 6 - 20
=
6 bh
1 bh beugel uk. 8 x 11 cm
: (11*2)+(8*2)+(2*2) : 22 + 16 + 4 : 42.00 cm
Berat Besi / M' Sloof ( Bd baja x D² x panjang ) 1 m' besi beugel Ø 6 1 buah beugel
: :
0.006165 x 0.10 kg
6 x
6 x
1 m' besi Pokok Ø 8
:
0.006165
8 x
8 x
Syarat minimal beton salut 2 cm
Besi Tulangan Pokok Besi beugel 6 bh / m'
: : :
x
1.62 kg 0.57 Kg 2.19 kg
1 m' konstruksi sloof 1 m³
1 0,12 x 0.15
x 2.14 kg
:
121.72
kg
KALAU PAKAI BESI POKOK Ø 7 & BEUGEL Ø 4 1 m' besi beugel Ø 4 : 0.006165 x 1 buah beugel : 0.04 kg 1 m' besi Pokok Ø 7
:
Besi Tulangan Pokok 4 bh Besi beugel
: : :
1 m' konstruksi sloof 1 1 m³ 0,12x 0.15
x 2.14 kg
:
0.006165
x
MAKA 4 x 4 x
7 x
7 x
1.24 kg 0.25 Kg 1.49 kg 82.96
kg
RING BALK/SOPI 10 X 12 CM
12
Ø
Ø
Ø
Ø
Ø 7 Tulang Pokok
1 M'
Ø 7x 4
=
4 m
Ø 5 Beugel
1 M'
Ø 5 - 20
=
6 bh
8
1 bh beugel uk. 6 x 8 cm
: (6*2)+(8*2)+(2*2) : 12 + 16 + 4 : 32.00 cm
6 10
Berat Besi / m' Ring Balk ( Bd baja x D² x panjang ) 1 m' besi beugel Ø 4 1 buah beugel
: :
0.006165 x 0.03 kg
4 x
4 x
1 m' besi Pokok Ø 7
:
0.006165
7 x
7 x
Besi Tulangan Pokok Besi beugel
: : :
x
1.24 kg 0.19 Kg 1.43 kg
1 m' konstruksi Ring Balk 1 m³
1 0,1 x 0.12
KOLOM 10 X 10 CM
x
1.43
Kg
:
119.39
kg
10
Ø
Ø
Ø 7 Tulang Pokok
1 M'
Ø7x4
=
4 m
Ø
Ø
Ø 4 Beugel
1 M'
Ø 4 - 20
=
6 bh
6
1 bh beugel uk. 6 x 6 cm
: (6*2)+(6*2)+(2*2) : 12 + 12 + 4 : 28 cm
6 10
Berat Besi / m' besi kolom ( Bd baja x D² x panjang ) 1 m' besi beugel Ø 4 1 buah beugel
: :
0.006165 x 0.03 kg
4 x
4 x
1 m' besi Pokok Ø 6
:
0.006165
7 x
7 x
Besi Tulangan Pokok Besi beugel
: : :
x
1.24 kg 0.17 Kg 1.41 kg
1 m' konstruksi kolom 1 m³
1 0,1 x 0.1
x
1.41
kg
:
140.84
kg
PLAT JEMBATAN 100 X 100 CM Ø 8 Tulang Pokok
1 M'
Ø 8x 4
=
7 m
Ø 6 Tulang Pembagi
1 M'
Ø 6 - 20
=
7 bh
: :
0.006165 x 0.07 kg
6 x
6 x
:
0.006165
8 x
8 x
Berat Besi / m' Plat Jembatan ( Bd baja x D² x panjang ) 1 m' besi pembagi Ø 6 1 buah pembagi 1 m' besi Pokok Ø 8 Besi Tulangan Pokok Besi beugel
: : :
x
2.83 kg 0.51 Kg 3.34 kg
1 m' konstruksi kolom 1 m³
1 0,08 x 1
x
3.34
kg
:
41.76
kg
1.025 =
0.23 kg
1.025 =
0.40 kg
1.025 =
0.10 kg
1.025 =
0.31 kg
1.025 =
0.10 kg
1.025 =
0.31 kg
1.025 =
0.10 kg
1.025 =
0.31 kg
6.67
1.025 =
0.23 kg
1.025 =
0.40 kg