SAP2000 application of Post-tension Prestress Design
Full description
For ACI 318-08 Herein describes in detail the various aspects of the post-tensioned concrete design procedure with the American code ACI 318-08 [ACI 2008].Full description
Ribbed slabs are used for long spans with relatively light loads. They are constructed in one of the following ways as described in clause 30 of IS: 456-2000 1. As a series of concrete ribs with t...
Multi-Level Formwork Load Distribution With Post-Tensioned Slabs
design and analysis for RC Slabs
Full description
Post-Tensioning Tendon Installation and Grouting ManualFull description
Full description
void and rib slab report.Full description
Brief on Flat Slabs: introduction, types, advantages and disadvantages. Other related topics are also covered: post-tensioning, pre-stressing, in situ construction, prefab construction
Approach slab rests on Dirt walls of a any and ever Bridge.Full description
POST TENSIONED FLOORS
12/10/2009
POST TENSIONED FLOORS ■ History of PrePre-stressed Concrete
1886 First Patent for Prestressed Concrete (P.H. Jackson of San Francisco)
1928 Modern Development of Prestressed Concrete (E. Freyssinet of France )
12/10/2009
POST TENSIONED FLOORS ■ Idea of PrePre-stressed Concrete
POST TENSIONED FLOORS ■ Idea of PrePre-stressed Concrete
12/10/2009
POST TENSIONED FLOORS ■ Idea of PrePre-stressed Concrete
12/10/2009
POST TENSIONED FLOORS ■ Types of Prestressed Concrete
POST TENSIONED FLOORS ■ PRE TENSIONING
Steel tendons are stressed prior to concrete placement, usually at a precast plant remote from the construction site
12/10/2009
POST TENSIONED FLOORS ■ POST TENSIONING
Steel tendons are stressed after the concrete has been placed and gained sufficient strength at the construction site
12/10/2009
POST TENSIONED FLOORS ■ STRANDS / TENDONS
12/10/2009
POST TENSIONED FLOORS ■ BONDED TENDONS Can be more costly due to duct placement & grouting Force transmitted by anchors and bond to concrete Greater total force can be applied Strain compatibility with concrete Openings less difficult Minimizes need for nonnon-prestressed reinforcement More complex stressing equipment required
POST TENSIONED FLOORS ■ UNBONDED TENDONS Economical Greater layout flexibility Force transmitted solely by the anchors Total force limited by anchor spacing Replaceable Simple stressing equipment
POST TENSIONED FLOORS ■ Main Applications of Prestressed Concrete
POST TENSIONED FLOORS ■ Main Applications of Prestressed Concrete
12/10/2009
POST TENSIONED FLOORS ■ Main Applications of Prestressed Concrete
12/10/2009
POST TENSIONED FLOORS ■ Main Advantages of Post Tension Floors ■ Functional Large Cantilevers Long economical spans Flexibility in Column Layout Effective use of high strength materials P/T slab is typically 30% 30% thinner
POST TENSIONED FLOORS ■ Main Advantages of Post Tension Floors ■ Economical Effective use of high strength materials P/T slab is typically 30% 30% thinner Forms are removed in 2-3 days not in 21 to 28 day as for rebar Concrete Significantly reduces amount of reinforcement Typically need about 50% 50% of crew
POST TENSIONED FLOORS ■ Main Advantages of Post Tension Floors ■ Technical Deflection and vibration control Long--term creep problems are virtually Long eliminated by load balancing Moment of inertia approaches Igross Crack control and waterwater-tightness
POST TENSIONED FLOORS ■ PT Slab Vs RC Slab ■ Slab Thickness Typical Span/Depth Floor System P/T
RC
One way slabs
48
21-28
Two-way slabs
45
33
Two-way slabs with drop panels
50
36
(minimum drop panel L/6 each way)
POST TENSIONED FLOORS ■ PT Slab Vs RC Slab ■ Span – Cost Relation
POST TENSIONED FLOORS ■ PT Slab Vs RC Slab ■Cost Breakdown
12/10/2009
POST TENSIONED FLOORS ■ Common Systems of PT Slabs Solid Slab
One Way Slabs Two Way Slabs
Flat Slabs
Flat Plates Flat Slab With Drop
Waffle Slabs
One Way Joists Two Way Waffle Slab
12/10/2009
POST TENSIONED FLOORS ■ One Way Systems
POST TENSIONED FLOORS ■ Two Way Systems
POST TENSIONED FLOORS ■ Banded & Waffle Slabs
POST TENSIONED FLOORS ■ Construction of PT Slabs ■ Shuttering
12/10/2009
POST TENSIONED FLOORS ■ Construction of PT Slabs ■ Laying of Bottom Reinforcement
12/10/2009
POST TENSIONED FLOORS ■ Construction of PT Slabs ■ Laying of Tendons & Laying of Top Reinforcement
12/10/2009
POST TENSIONED FLOORS ■ Construction of PT Slabs ■ Concrete Casting
12/10/2009
POST TENSIONED FLOORS ■ Construction of PT Slabs ■ Stressing of Strands
POST TENSIONED FLOORS ■ Construction of PT Slabs ■ Stressing of Strands INITIAL
FINAL
At 25 25% % of Concrete Strength
At 70 70% % of Concrete Strength
About 24 hours from casting
About 72 hours from casting
Shutter is removed and props are installed
Anchors are finished and shutter can be removed
POST TENSIONED FLOORS ■ Construction of PT Slabs ■ Measurement of Elongation
POST TENSIONED FLOORS ■ Construction of PT Slabs ■ Stressing Report Measured elongation needs to be within 7% of calculated value Per code, for tendons outside the 7%, the EOR shall ascertain and correct the “problem”. “problem”. What to do? DeDe-Tension / Re Re--Tension? Elongation records shall be sent to the engineer by next working day after stressing Elongations shall be approved or rejected within three working days after stressing
POST TENSIONED FLOORS ■ Construction of PT Slabs ■ Finishing of Tendon Ends
12/10/2009
POST TENSIONED FLOORS ■ Outlines of Design Procedure Selection of Initial Slab Thickness
Determination of the Amount of PrePre-Stressing Serviceability Calculations (Deflection, Vibration) Limit State Calculations (Stresses) Calculation of bonded reinforcement 12/10/2009
POST TENSIONED FLOORS ■ Selection of Initial Thickness
12/10/2009
POST TENSIONED FLOORS ■ Amount of Prestressing Minimum P/A =0.9
ACI
Maximum spacing of tendons is six times the slab thickness.
Prestressing always provide an uplift to overcome 6060-90 percent of dead loads
12/10/2009
POST TENSIONED FLOORS ■ Amount of Prestressing
12/10/2009
wb L2 P= 8h
POST TENSIONED FLOORS ■ Amount of Prestressing
wbx =
Ly
αLx + Ly 4
wbx Lx Px = 8hx
Py =
wbx Lx y
8hy
12/10/2009
2
2
4
4 4
wb
Lx wby = wb 4 4 αLy + Lx
POST TENSIONED FLOORS ■ Amount of Prestressing
α =1.0 for 4 edges continuous or discontinuous =1.0 for 2 adjacent edges discontinuous =2.0 for 1 long edge discontinuous =0.5 for 1 short edge discontinuous =2.5 for 2 long and 1 short edges discontinuous =0.4 for 2 short and 1 long edges discontinuous =5.0 for 2 long edges discontinuous =0.2 for 2 short edges discontinuous