Ultrasite BTS Installation Hand Book (GSM 900 – DCS 1800) Telecom Implementation On this document you can find: - UltraSite BTS Outdoor Installation On this document you can find the following slides: - Generic Location of the BTS Cabinets and Eltek Power Supply - Grounding and Bridge Kit - Location of the Plug In Units - TRX Cabling for 900 and 1800 BTS Cabinets - Entry Cable Standard - DC and AC Cables - Synchronization Between Cabinets (Master and Slave) - Transmission and Cross-Connection Between Cabinets - Transmission Cable
Slide 1 of 20 – 25.Feb.2007 – by Stevan Picolli – DN607140 TI.04
TELECOM IMPLEMENTATION
Generic Location of the Cabinets Case 1 Feeder cables going to the left side
Case 2 Feeder cables going to the right side
ATTENTION: 1800 CABINET MIGHT NOT BE APPLICABLE FOR SOME CONFIGURATIONS (ROAD SITES)
Slide 2 of 20 – 25.Feb.2007 – by Stevan Picolli – DN607140 TI.04
TELECOM IMPLEMENTATION
Fixing the Cabinets Ensure the Eltek Cabinet and BTS 900 has a distance (gap) of 1cm. This gap is needed because the Eltek cabinet has some screws blocking the opening of the 900 cabinet roof.
Slide 3 of 20 – 25.Feb.2007 – by Stevan Picolli – DN607140 TI.04
TELECOM IMPLEMENTATION
Grounding BTS Grounding MUST be installed immediately after fixing the cabinets in the base frame.
Slide 4 of 20 – 25.Feb.2007 – by Stevan Picolli – DN607140 TI.04
TELECOM IMPLEMENTATION
Bridge Kit
ATTENTION: TWO CABINETS MIGHT NOT BE APPLICABLE FOR SOME CONFIGURATIONS (ROAD SITES) Slide 5 of 20 – 25.Feb.2007 – by Stevan Picolli – DN607140 TI.04
TELECOM IMPLEMENTATION
Location of the Plug-In Units (6+6+6 Configuration) Plug-In Units can be installed only after BTS Grounding.
Slide 6 of 20 – 25.Feb.2007 – by Stevan Picolli – DN607140 TI.04
TRX 12 – SPACE AVAILABLE
TELECOM IMPLEMENTATION
TRX Cabling for 900 Sectors – Example This picture is applicable only for 6+6+6 Configuration
Slide 7 of 20 – 25.Feb.2007 – by Stevan Picolli – DN607140 TI.04
TELECOM IMPLEMENTATION
Location of the Plug-In Units (2+2 or 2+2+2 Configuration) Plug-In Units can be installed only after BTS Grounding.
Slide 8 of 20 – 25.Feb.2007 – by Stevan Picolli – DN607140 TI.04
TELECOM IMPLEMENTATION
TRX Cabling for 900 Sectors
Slide 9 of 20 – 25.Feb.2007 – by Stevan Picolli – DN607140 TI.04
TELECOM IMPLEMENTATION
TRX Cabling for 1800 Sectors
Slide 10 of 20 – 25.Feb.2007 – by Stevan Picolli – DN607140 TI.04
TELECOM IMPLEMENTATION
Entry Cable Standards
Slide 11 of 20 – 25.Feb.2007 – by Stevan Picolli – DN607140 TI.04
ATTENTION: 1800 CABINET MIGHT NOT BE APPLICABLE FOR SOME CONFIGURATIONS (ROAD SITES)
TELECOM IMPLEMENTATION
Entry Cable Kit – How to Use 1 – When installing ’’ Feeder cable, layer 1 must be cut off 2 – When installing MW Cable (RG223) DO NOT cut any layer 3 – When installing metal pipe, layer 1 or 1 and 2 can be cut 4 – Never leave a hole if there is no cable or pipe
1
2
3
Slide 12 of 20 – 25.Feb.2007 – by Stevan Picolli – DN607140 TI.04
WRONG
TELECOM IMPLEMENTATION
DC Cable
Cover must be installed Slide 13 of 20 – 25.Feb.2007 – by Stevan Picolli – DN607140 TI.04
TELECOM IMPLEMENTATION
AC Cable for Heater
Slide 14 of 20 – 25.Feb.2007 – by Stevan Picolli – DN607140 TI.04
TELECOM IMPLEMENTATION
Synchronization Cable – UUHA Not applicable when only one cabinet is in use OUTPUT INPUT
BTS 1800 – SLAVE
Slide 15 of 20 – 25.Feb.2007 – by Stevan Picolli – DN607140 TI.04
BTS 900 - MASTER
TELECOM IMPLEMENTATION
Synchronization Cable – UUHA During the commissioning, in the “Hardware Configuration”, for Cabinet Properties, select “Use autodetected Clock Synchronization between BTS Cabinets”. Not applicable when only one cabinet is in use
Slide 16 of 20 – 25.Feb.2007 – by Stevan Picolli – DN607140 TI.04
TELECOM IMPLEMENTATION
Transmission and Cross-Connection Between Cabinets Not applicable when only one cabinet is in use
BTS 1800 – SLAVE
Slide 17 of 20 – 25.Feb.2007 – by Stevan Picolli – DN607140 TI.04
BTS 900 - MASTER
TELECOM IMPLEMENTATION
Transmission Cable 1 – Organize MW Cable inside of the BTS 2 – 1 or 2 loops are allowed and recommended inside of the BTS 3 – Labels must be fixed on the cables (Far End Site Code) 4 – Dummy plates must be installed when TX cards are not.
WRONG
Slide 18 of 20 – 25.Feb.2007 – by Stevan Picolli – DN607140 TI.04
TELECOM IMPLEMENTATION
Commissioning Cable
BTS End – D9 Male
PC End – D9 Female
Pin No. 2, LMP In
Pin No. 3, Transmitted Data
Pin No. 3, LMP Out
Pin No. 2, Received Data
Pin No., Ground
Pin No. 5, Ground
Slide 19 of 20 – 25.Feb.2007 – by Stevan Picolli – DN607140 TI.04
TELECOM IMPLEMENTATION
EDGE ACTIVATION For EDGE Activation, the only thing to be done is to set the ABIS ALLOCATION PROPERLY Abis allocation for 1 3 0 1 1 2 1 3 2 4 2 5 3 6 3 7 4 8 4 9 5 10 5 11 6 12 6 13 14 15 16 17 18 19 20 21 22 23 EDAP 2, 4 24 EDAP 2, 4 25 1 26 3 27 28 29 30 31