HMS Directive No. 34 - Management of Change
Prepared by:
Verified by:
Approved by:
Livar Haga
Kjetil Serigstad
Anne Myhrvold
Revision number: 3 Classification:
Issue date: 2009-12-30
Next review date: 2010-12-31
Public /unc las sif ied
BP int ernal
Conf ident ial
Sec ret
HMS Directive No. 34 - Management of Change
Doc.no: [n.nn.nnn]
[Subtitle/Chapter title]
Rev. no: 3
Authority: En E ngineering Authority
Issue date: 2009-12-30
Page 2 of 15
Document control sheet Docu Docume ment nt owner ner Review period Deviation management
Liva Livarr Ha Haga ga 1 Year Ref. HSE-Directive No. 35
Revision history
3
2010
02
2009
01
2008
Rev.no
Issue date
HMS Directive No. 34 - Management of Change HMS Directive No. 34 - Management of Change HMS Directive No. 34 - Management of Change Description
Livar Ha Haga L.Haga
Kjetil Serigstad L.Haga
Anne Myhrvold H.Halvorsen
L.Haga
L.Haga
H.Halvorsen
Prepared by
Verified by
Approved by
Attention: Paper copies of governing documents are uncontrolled. This copy is valid at time of printing only. The controlled document is available at the Governing Documents Triangle at BP Norway Intranet.
HMS Directive No. 34 - Management of Change
Doc.no: [n.nn.nnn]
[Subtitle/Chapter title]
Rev. no: 3
Authority: En E ngineering Authority
Issue date: 2009-12-30
Page 3 of 15
Table of content 1 2 3
General........ General.............. ........... ........... ........... ........... ............ ............ ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ............ ............ ........... ........... .......4 .4 Responsibi Responsibility.......... lity................ ............ ............ ............ ........... ........... ........... ........... ............ ............ ........... ........... ........... ........... ............ ............ ........... ........... ........... ........... ........... ........... .......6 .6 Processes Processes ........... ................. ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ............ ............ ........... ........... ........... ........... ............ ............ ........... ........... .......8 .8 3.1 Plant/Equi Plant/Equipment pment Change........... Change................ ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ...........8 ......8 3.2 Process/Sys Process/System tem Change................ Change...................... ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ...........9 ......9 3.3 People/Org People/Organisa anisational tional Change Change ........... ................ ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ............ ............ .......9 .9 4 Demand Demand Analysis Analysis ........... ................. ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ............ ............ ........... ........... ........... ........... ............ ...........10 .....10 5 Risk Evaluation....... Evaluation............. ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... ........... .........11 ....11
Attention: Paper copies of governing documents are uncontrolled. This copy is valid at time of printing only. The controlled document is available at the Governing Documents Triangle at BP Norway Intranet.
HMS Directive No. 34 - Management of Change
Doc.no: [n.nn.nnn]
[Subtitle/Chapter title]
Rev. no: 3
Authority: En E ngineering Authority
1 Purpose
Issue date: 2009-12-30
Page 4 of 15
General The purpose of this directive is to ensure that all proposed temporary and permanent changes within BPN are systematically evaluated to ensure that the risk related to people, plant or processes are assessed, communicated and controlled to an acceptable level. The mindset is that the responsible person has intent to make a change. This directive and attached forms will be used to identify and document the risks related to the change and any steps necessary to mitigate those risks. If remaining risks are unacceptable, the change must not be implemented. This directive meets the expectations set forth in Getting HSSE Right, Element 7 Management of Change (MoC) and Integrity Management Standard element 7: Management of Change.
Scope
The directive applies to changes within BPN related to plant, process and/or people. All changes will be managed by utilizing utilizing a risk based&controlled decision-making decision-making process. The level of rigor involved should be commensurate with the level of risk. The directive applies to any temporary or permanent physical alteration that deviates from the design intent, any deviation from the documented safe operating limits or procedures, any change in process outside the design specification, any change in management systems, or a significant change in organization or personnel that leads to a loss or transfer of people with particular knowledge or experience. This directive lists factors for each type of change, to consider whether the change requires requires a MoC. MoC. Consult relevant change with your supervisor. If in doubt whether the change requires MoC contact person with adequate experience/expertise. (I.e. HSSE representatives, lead discipline engineer, technical authority, etc.) The directive applies to all parts of BPN activities - onshore and offshore. The directive and its appendices should be used for generic MOC. In situations for which dedicated processes and procedures have been prepared satisfying the key requirements of MOC, namely robustly documented risk management process, such should be used for managing changes fitting their scope.
References
The framework regulations The PSA regulations The Management Regulations The PSA regulations BP “Getting HSSE right” BP “Integrity Management Standard”
Attention: Paper copies of governing documents are uncontrolled. This copy is valid at time of printing only. The controlled document is available at the Governing Documents Triangle at BP Norway Intranet.
HMS Directive No. 34 - Management of Change
Doc.no: [n.nn.nnn]
[Subtitle/Chapter title]
Rev. no: 3
Authority: En E ngineering Authority
Issue date: 2009-12-30
Page 5 of 15
BP Golden Rules for Safety – “Management of Change”
BPN Directive 35 “Processing unwanted events and exemptions”
BPN Directive 36 “Risk analysis and acceptance criteria”
BPN Projects & Modification Procedure 1.70.005
BPN Control of Temporary Equipment 1.70.007.
BPN “Handover document - Transition of Roles and Responsibilities.” Acceptance criteria are criteria used to express an acceptable level of risk in activities ALARP (As Low As Reasonably Practicable) -means that the risk level has been reduced through a documented and systematic process to such a level that it is no longer possible to identify cost-ef fective measures that can further reduce the risk Critical work process includes work processes where lack of control of changes may lead to moderate or high risk (combination of consequence and probability) of: accidents, harm to people and/or damage to the environment economic loss, and/or impairment of BP's reputation HAZID (HAZard IDentification) is a method used used to identify potential elements elements of risk HSSE (Health, (Health, Safety, Security and the Environment) The term also includes emergency preparedness, working environment and security MoC implies a documented Management of Change process as described in this directive. Plant Is in this directive related to plant, facilities and equipment such as buildings, structure, piping, safety equipment, escape routes, tie-ins, by-passes, etc. Process Is in this directive related to work processes or systems such as procedures, software, conditions or requirements (work-flow) People Is in this directive related to organizational change processes Risk - Expression of the combination of probability and consequences of one or more accident/incidents happening Risk analysis - An analysis covering systematic mapping and description of risk to personnel, the environment and material assets. Work Work aris arisin ing g from from temp tempor orar ary y and and perm perman anen entt chan change ges s to orga organi niza zati tion on,, pers person onne nel, l, systems, process, procedures, equipment, products, materials or substances, and laws and regulations cannot proceed unless a Management of Change
Definitions and abbreviations
Gold Golden en Rule Rule
process is completed, where applicable, to include: a risk assessment conducted by all impacted by the change development of a work plan that clearly specifies the timescale for the change
Attention: Paper copies of governing documents are uncontrolled. This copy is valid at time of printing only. The controlled document is available at the Governing Documents Triangle at BP Norway Intranet.
HMS Directive No. 34 - Management of Change
Doc.no: [n.nn.nnn]
[Subtitle/Chapter title]
Rev. no: 3
Authority: En E ngineering Authority
Issue date: 2009-12-30
Page 6 of 15
and any control measures to be implemented regarding: equipment, facilities and process operations, maintenance, inspection procedures training, personnel and communication documentation authorization of the work plan by the responsible person(s) through completion Evaluation of the need for MoC should be done in all phases from the planning stage and all the way through the actual execution. It is a duty of everyone involved in the planning, approval and execution of work to evaluate the need for MoC. A generic MoC process is required when change introduce risk factors that are not sufficiently identified, documented and controlled through other relevant procedures/directives, exemplified in chapter 3. E.g. Safe Job Analysis (Directive #11), Projects & Modification (Procedure 1.70.005) etc. Detailed descriptions of changes requiring and not requiring documented MoC process are specified in chapter 3 (Plant, Process and People). For changes repeated frequently it may be worthwhile to establish described work processes which are reused and robustly documented. This will probably be more effective than to use this generic method each time such change is to be managed.
Identify need for MoC
Appendices
Terms Of Reference (TOR) Plant / equipment change checklist Process / system change checklist People / organisation change checklist Risk assessment table MOC Report
Records
MOC Poster The following should be registered in Traction: Terms of Reference MoC Report with attachments
2
Responsibility
Attention: Paper copies of governing documents are uncontrolled. This copy is valid at time of printing only. The controlled document is available at the Governing Documents Triangle at BP Norway Intranet.
HMS Directive No. 34 - Management of Change
Doc.no: [n.nn.nnn]
[Subtitle/Chapter title]
Rev. no: 3
Authority: En E ngineering Authority
Issue date: 2009-12-30
Type of Change People People - Organization Organization
Responsibility table
Proc Process ess - Syste Systems ms or or Dire Directi ctive ves s Plant – Eq E quipment Chemica Chemicals/S ls/Subs ubstan tance/M ce/Mater aterial ials s
Codes and Regulatory Requirements
Emer Emerge genc ncy y Prep Prepar ared edne ness ss Logistics an and Co Contracts
Managers
Page 7 of 15
Accountability/ Approver Manager of the new organization or Line supervisor of the position affected Work Work Proces Process s owner owner Equipment owner (OIM, area responsible, , etc.) Appropri Appropriate ate Plant, Plant, produ product ct or Proces Process s owner (incl. Directive owner, Industrial hygienist). Directive Owner, Technical Requirements Authority (TA) (TA) or HSSE Manager OIM, OIM, Emer Emerge genc ncy y Cont Contro roll ller er and/ and/or or Security & Emergency Advisor Logistics- an and PS PSCM Ma Manager
have accountability for: knowing the legal compliance requirements related to the operations and assets for which they are responsible and for ensuring that changes in legal and regulatory requirements affecting their accountabilities are monitored, communicated and implemented effectively. is responsible for verifying that the risk evaluations carr ied out are in accordance with BP's expectations and that adequate risk-reducing measures have been identified ensuring management systems are in place for monitoring changes to health, safety, security and environmental laws and regulations, communicating the changes, assessing the impact assuring that implementation plans and monitoring methods are put in place to assure compliance. is the person requesting and approving the final MoC. shall ensure that the directive is followed and that the MoC team is familiar with the directive. shall ensure that identified measures are implemented prior to making the actual change. The client shall assess whether the MoC shall be led by an independent party. is responsible for Establishing a MoC team which will identify risks and risk-reducing measures. Prepare MoC report and record actions in Traction.
HSSE Manager
Client/Approver
MoC leader
The person who is appointed to plan and lead a MoC process shall have the relevant background from similar analyses, e.g. HAZOP, HAZID, etc. Engineering Authority
shall ensure that logged MoCs are reviewed annually to assess the cumulative impact of all changes.
MoC team's HSSE representative
is responsible for
making sure that the risk evaluation reflects BP's requirements and HSSE expectations
Attention: Paper copies of governing documents are uncontrolled. This copy is valid at time of printing only. The controlled document is available at the Governing Documents Triangle at BP Norway Intranet.
HMS Directive No. 34 - Management of Change
Doc.no: [n.nn.nnn]
[Subtitle/Chapter title]
Rev. no: 3
Authority: En E ngineering Authority
Issue date: 2009-12-30
3
Processes
3.1
Plant/Equipment Change
Definition
Page 8 of 15
Plant/Equipment change process may include any changes in the following, but not limited to Change to the platform/building structure Change in equipment location requiring changes in piping or utilities Changes in operating conditions outside normal operating or design envelopes, such as pressures, temperatures, etc. Change to any safety equipment, safety related device, safety system, escape route or hazardous area classification Changes which could affect the capacity or design basis Changes in maintenance, inspection or testing Equipment modification (e.g., alarms, instrumentation, etc.) Addition of equipment that may contribute to greater relief requirements New projects that involve tie-ins or equipment modification on existing units Use of new technology, new materials, new equipment Change to hired or temporary equipment Bypass connections around equipment that is normally in service unless the change is covered in a normal operating procedure Change to chemical inventory and chemical use Deferral of planned major maintenance and modification activity Changes for which other robustly documented risk managing processes, procedures/directives exist should be managed using this when the situation fit the scope (e.g. modification procedures, risk analysis methods, SJA, work processes integrated in Computerized Maintenance Management System (CMMS), Maint Web, Critical Protective System Register (CPSR) process, etc.). In general, the following changes would not need a documented MoC: Changes like-for-like in kind (equipment, consumables, or parts) New equipment that has no impact on existing operations Routine maintenance of equipment Change that is consistent with the design parameters. Minor changes that do not affect HSE, personnel, or customers. (e.g. a change in supplier for materials without HSE-impact ).
Attention: Paper copies of governing documents are uncontrolled. This copy is valid at time of printing only. The controlled document is available at the Governing Documents Triangle at BP Norway Intranet.
HMS Directive No. 34 - Management of Change
Doc.no: [n.nn.nnn]
[Subtitle/Chapter title]
Rev. no: 3
Authority: En E ngineering Authority
The effects of the change
3.2
Issue date: 2009-12-30
Page 9 of 15
Based on a detailed description of the plant/equipment changes the MoC leader will, in cooperation cooperation with relevant skilled personnel, consider the effects by using Appendix 2 Checklist – Plant/equipment changes Check against other checklists attached for relevance. If the change will cause deviation from requirements, either internal or external, BPN Directive 35 Processing unwanted events and exemptions must be followed.
Process/System Ch Change
Definition
Workprocess/System change process may include any changes in the following, but not limited to Changes in legal and regulatory requirements, technical codes, standards with safety, health and environmental effects. New legislation o Changes to existing legislation o Legislation compliance issues raised by o regulatory body inspection and progress the update of outstanding inspection-related issues. Change in procedure, sequence, or change in steps Use of new or upgraded software, etc. Changes in emergency preparedness and response Changes for which other robustly documented risk managing processes, procedures/directives exist should be managed using this when the situation fit the scope (e.g. risk analysis methods, SJA, work processes integrated in Computerized Maintenance Management System (CMMS), Maint- Web process, etc.). In general, the following changes would not need a documented MoC: Minor changes that do not affect HSE, personnel, or customers
The effects of the change
3.3 Definition
Based on a detailed description of the process/system changes the MoC leader will, in cooperation cooperation with relevant skilled personnel, consider the effects changes . by using Appendix 3 Checklist – Process/system changes. Check against other checklists attached for relevance. If the change will cause deviation from requirements, either internal or external, BPN Directive 31 Exemptions must be followed.
People/Organisational Ch Change
People/Organisational change process includes any changes in the relationship between work tasks and available resources such as An established job type is removed from the
Attention: Paper copies of governing documents are uncontrolled. This copy is valid at time of printing only. The controlled document is available at the Governing Documents Triangle at BP Norway Intranet.
HMS Directive No. 34 - Management of Change
Doc.no: [n.nn.nnn]
[Subtitle/Chapter title]
Rev. no: 3
Authority: En E ngineering Authority
Issue date: 2009-12-30
Page 10 1 0 of o f 15 15
organization, or a new job type is added Changes in the organization structure and/or reporting relations Changes in competence requirements for identified roles Changes in activity activity level (changes in work work descriptions for the existing organization) Change of major supplier, including relevant subcontractors (changes in the supply chain) Changes to logistics such as significant change in transportation route, loading/ discharge location. Individuals are required to take on significantly new responsibilities demanding skills and competencies unconnected with those required previously Individuals relinquish responsibilities for tasks related to HSSE compliance or other critical business processes without those tasks being reallocated Changes to outsource a function that was previously performed by BPN personnel Changes for which other robustly documented risk managing processes, procedures/directives exist should be managed using this when the situation fit the scope (e.g. risk analysis analysis methods, SJA, Handover Document - Transition Transition of Roles and Responsibilities available via HRs intranetpage under Forms, Handover, etc.). In general, the following changes would not need a documented MoC: Change in a contractor providing an existing low risk service, subject to normal pre-qualification. Minor changes that do not affect HSE, personnel, or customers
The effects of the change
4
Based on a detailed description of the organisational changes the MoC leader will, in cooperation cooperation with relevant skilled personnel, consider consider the effects by using Appendix 4 Checklist - Organisational changes Check against other checklists attached for relevance. If the change will cause deviation from requirements, either internal or external, BPN Directive 31 Exemptions must be followed.
Demand Analysis
Intr Introd oduc ucti tion on
In conne onnect ctio ion n wit with h ma manage nagem ment ent of of cha chang nge e pro proce ces sses, ses, the the MoC MoC lead leader er sha shall make sure that the changes are described in detail in order to ensure a sufficient evaluation basis ensure that the analysis basis is documented so that the relation between the analysis basis and the results (measures) are traceable The descriptions should describe the current situation and the desired future situation.
Attention: Paper copies of governing documents are uncontrolled. This copy is valid at time of printing only. The controlled document is available at the Governing Documents Triangle at BP Norway Intranet.
HMS Directive No. 34 - Management of Change
Doc.no: [n.nn.nnn]
[Subtitle/Chapter title]
Rev. no: 3
Authority: En E ngineering Authority
Terms of reference reference
Issue date: 2009-12-30
Page 11 1 1 of o f 15 15
The indivi individual dual who is is proposin proposing g the change change shall shall complet complete e the following following sections sections of the Terms of Reference for the Management of Change (Appendix 1.) Name and the date. The description of the change. The purpose of the change. Type and Duration of change (permanent/temporary) Target date for the change MoC team Approver
Duration of change
The approver is the individual who will ultimately approve the relevant change. In emergency situation, the person in charge is authorized to execute changes to maintain the safety of the facility without following the fully documented MOC directive. After the emergency situation is cleared, properly documented MOC processes should be handled. If the change is intended to be temporary, a time limit must be set on when the original design intent (ie equipment, operational conditions, organizational structure, etc) will be restored, and the management system (Traction) should be used to ensure that the time limit and any other conditions are not violated.(Normally less than 6 months). Extension of temporary change shall be reviewed and approved by the next higher level of management before pre-authorized time-limit expire. Special precautions to maintain safe operations while a temporary change is in effect shall be periodically reviewed for effectiveness. Facilities are brought back to normal or permanent mode before a temporary MOC is closed. When evaluating the impact on critical work processes, the main focus must be on identifying changes which may lead to Related activities being completely left out due out due to lack of resources or lack of awareness of the importance of the activity Related activities being performed, but with reduced quality. This may be due to inexperienced personnel performing the work or taking "shortcuts" as a result of imbalance between the workload and available resources Losses which Losses which may occur because personnel perform activities for which they are not sufficiently skilled, thus leading to the work being done incorrectly The eval evaluat uation ion of of critic critical al work work proc process esses es must must also also inclu include de indir indirect ect effec effects. ts. Engineering Authority shall ensure that each organizational unit reviews the MoCs logged in Traction annually or more frequently if appropriate, to assess the cumulative impact of all changes.
Main focus
Creepi Creeping ng chang changes es
5
Risk Evaluation
Attention: Paper copies of governing documents are uncontrolled. This copy is valid at time of printing only. The controlled document is available at the Governing Documents Triangle at BP Norway Intranet.
HMS Directive No. 34 - Management of Change
Doc.no: [n.nn.nnn]
[Subtitle/Chapter title]
Rev. no: 3
Authority: En E ngineering Authority
Introduction
Issue date: 2009-12-30
Page 12 1 2 of o f 15 15
Risk evaluations of MOC MOC processes shall be done by a MoC team. The MoC team ought to consist of representatives of the critical work processes identified as being affected by the change personnel with HSSE competence employees' elected representative and/or safety delegate (shall be invited.) In selecting a team, the following mix of attributes must be considered: Adequate technical expertise/experience. Adequate understanding of the risks Adequate organizational and business understanding. Arrangements for employee contribution This team will propose measures, which limit any risks to an acceptable level in accordance with BPN ALARP principle (ref. Directive 36 Risk analysis and acceptance criteria). The MoC team will identify potential elements of risk using HAZID , etc or other systematic methods which stimulate creativity, i.e. which gives the participants the opportunity to identify identify circumstance circumstances s that are outside outside their their own scope of experience by using appropriate checklist (appendix 2-5) and other tools available for Hazard recognition
Identifying elements of risk
The team should consult as widely as is necessary to allow them to come to an informed decision on the risks associated with the change. Affected persons including contractors, sub-contractors, vendors, and customers may be consulted as necessary. When identifying potential elements of risk, a risk evaluation needs to be carried out in which the elements are ranked into the following categories: High potential which potential which means that risk-reducing measures need to be implemented Medium potential which potential which means that risk-reducing measures can be implemented if deemed necessary based on a cost/benefit evaluation Low potential which potential which means that no further measures are deemed necessary
Identification of risk-reducing measures
The risk of an unintended unintended incident incident occurring occurring can be estimated estimated by means of BPN risk matrix, available through directive 35 Unwanted Events, or by using the more advanced & detailed methodologies and acceptance criteria in HSSE Directive no. 36, Risk Analysis and Acceptance Criteria. Based on a systematic evaluation of the elements of risk involved in an management of change process, the MoC team is to identify probability-reducing measures intended measures intended to prevent an incident from occurring and/or
Attention: Paper copies of governing documents are uncontrolled. This copy is valid at time of printing only. The controlled document is available at the Governing Documents Triangle at BP Norway Intranet.
HMS Directive No. 34 - Management of Change
Doc.no: [n.nn.nnn]
[Subtitle/Chapter title]
Rev. no: 3
Authority: En E ngineering Authority
Issue date: 2009-12-30
Page 13 1 3 of o f 15 15
consequence-reducing measures intended measures intended to reduce the consequences of an incident that has occurred Of these two, probability-reducing measures are to be prioritized
Implementation of measures
Based on the risk and risk reducing measures the MoC team shall confirm whether or not the change should be implemented. The MoC team shall prepare a plan for implementation of the measures. The plan is to propose deadlines and the person responsible for each of the measures This should include how the change is to be effectively communicated to the workforce and other affected persons (such as contractors, sub-contractors, customers, and vendors). Special competence requirements must also be considered and completed prior to implementation of the changes. The MoC approver shall assess whether any proposed change requires a prestart up review to confirm that the MoC system has been correctly applied, that the change is safe to commission and that it meets applicable legal obligations. Records, procedures and drawings shall be updated to reflect the MoC. MoC systems shall be designed to ensure that all actions are closed out and achieves the necessary effect. The The res resul ults ts of the the rev revie iew w sho shoul uld d be be wel welll doc docum umen ented ted and and ret retai aine ned d for for futu future re verification. This is important even if the review did did not require any additional additional action to be taken. MoC report, using template in appendix 6, shall be developed describing the following sections: Participants Risk assessment method Accept criteria Actions: summary and number of identified actions/barriers. Assumptions: number of established assumptions. Drawings: summary of drawings utilized. Documents: summary of documentation utilized. References The approver shall sign completed MoC report to indicate acceptance or nonacceptance of the review findings. The MoC leader must ensure documentation of the risk evaluation in accordance with Appendix 5 Risk Assessment Table documentation of measures identified as part of the risk evaluation in Tr@ction The MoC report together with measures identified shall be recorded in Traction under Other events, Event type: MoC. The Traction shall be recorded under the specific asset or if of general nature under BUR (Business Unit Resources). Traction list of Management of Change processes shall be reviewed at least annually to assess cumulative impact of all changes.
Docu Docume ment ntat atio ion n
Logged MoCs
Performance management
The use of MoC-system shall be assessed by processes which:
Attention: Paper copies of governing documents are uncontrolled. This copy is valid at time of printing only. The controlled document is available at the Governing Documents Triangle at BP Norway Intranet.
HMS Directive No. 34 - Management of Change
Doc.no: [n.nn.nnn]
[Subtitle/Chapter title]
Rev. no: 3
Authority: En E ngineering Authority
Issue date: 2009-12-30
1.
Confir Con firm m the chang change e achieve achieve its its origin original al intent intent
2.
Confir Con firm m the cha change nges s are exe execut cuted ed correc correctly tly
Page 14 1 4 of o f 15 15
3. Co Conf nfirm irm th the e acti action ons s are are clos closed ed 4.
EA or deleg delegated ated audit MOC-p MOC-proces rocesses ses at at least least annual annually ly
Attention: Paper copies of governing documents are uncontrolled. This copy is valid at time of printing only. The controlled document is available at the Governing Documents Triangle at BP Norway Intranet.
HMS Directive No. 34 - Management of Change
Doc.no: [n.nn.nnn]
[Subtitle/Chapter title]
Rev. no: 3
Authority: En E ngineering Authority
Issue date: 2009-12-30
Page 15 1 5 of o f 15 15
Flow chart: Client identifying need for change
Client and supervisor, and person with adequate experience/expertise
he change does not require a MoC when: the change does not introduce any risk factors. the change is covered in chapter 3 stating MoC not required.
Describe the change
Does the change require a Management of Change process?
no Should you be in doubt whether the change requires MoC, please contact a person with adequate experience/ expertise (directive owner, HSE department, teamleaders etc.)
yes
Client
Complete Terms of Reference for MOC or initiate other robustly documented risk management process.
MoC team
Identify potential elements of risk using of the change by using appropriate checklist
MoC team
Identify probabilityreducing measures and/orconsequenceand/orconsequencereducing measures
Are the reducing measures sufficient?
no
yes MoC team
Establish plan for implementation of actions identified
MoC team
Complete MoC Report
MoC approver
Follow up actions in Traction
MoC approver
Engineering Auth (EA) &/ HSSE Manager
Verify implemented riskreducing measures.
Review the management of changes within their function annually to assess the cumulative impact of all changes.
Attention: Paper copies of governing documents are uncontrolled. This copy is valid at time of printing only. The controlled document is available at the Governing Documents Triangle at BP Norway Intranet.