Chapter 3 COST ESTIMATION
Computerized controls, long distance control arrangements--arrangements--- less labor requires For Fluid-processing plant: (e.g. ethylene oxide plant)--- 1/3 to 2 employee hours per ton product For plant: (e.g. Solid-Fluid-processing polyethylene plant)--- 2 to 4 employee hours per ton product For Solid-processing plant: (e.g. coal briquetting plant)--- 4 to 8 employee hours per ton product Labor cost---depends on – type of worker, plant’s geographical location, prevailing wage rates, worker’s productivity productivity Table-22 (CH-6, Timmerhaus): Operating labor, fuel, steam, power & water requirement for various processes based on capacity Table-23 (CH-6, Timmerhaus): Costs for selected utilities and labor Table-24 (CH-6, Timmerhaus): Engineering news record labor index
(3) Direct supervisory & Clerical Labor: Requirement closely relates to amount of operating labor, complexity of operation, product quality standards
1
Compiled by Prof. Prasad Parulekar
The world’s largest digital library
Try Scribd FREE for 30 days to access over 125 million titles without ads or interruptions! Start Free Trial Cancel Anytime.
The world’s largest digital library
Try Scribd FREE for 30 days to access over 125 million titles without ads or interruptions! Start Free Trial Cancel Anytime.
The world’s largest digital library
Try Scribd FREE for 30 days to access over 125 million titles without ads or interruptions! Start Free Trial Cancel Anytime.
15% of operating labor cost
(4) Utilities Cost: Steam, processing & cooling water, compressed air, fuel, electricity, N2, natural gas, etc. Cost varies as per, amount of consumption, plant location, source Cost estimation---based on preliminary preliminary design Purchased or produced in company Produced by company, used for only 1 process--service cost charges as manufacturing manufacturing cost Produced by company, used by different processes, service cost apportioned among different processes based upon individual consumption Steam---consumed by manufacturing process & for auxiliary needs Electricity for lighting, motors, process — for equipments Consider allowances for radiation and other line losses
(5) Maintenance & Repairs: For efficient operation of plant Expenses — labor, labor, material, supervision supervision 2 – 20% of equipment cost depending upon light or
The world’s largest digital library
Try Scribd FREE for 30 days to access over 125 million titles without ads or interruptions! Start Free Trial Cancel Anytime.
The world’s largest digital library
Try Scribd FREE for 30 days to access over 125 million titles without ads or interruptions! Start Free Trial Cancel Anytime.
For operating rates less than plant capacity--Costs are 85% of that of 100% capacity for 75% operating rate Costs are 75% of that of 100% capacity for 50% operating rate Table-25 (CH-6, Timmerhaus): Estimation of maintenance & repair costs
(6) Operating Supplies: Miscellaneous materials needed to keep process functioning functioning efficiently Not the part of raw material or maintenance & repair materials e.g. charts, lubricants, test chemicals, etc 15% of total cost for maintenance & repair
(7) Laboratory Charges: Laboratory test for control over operation & product quality 10-20% of operating labor costs
(8) Patent & Royalties: Processes covered by patents To pay for patent rights, royalties based on amount of material produced For development and procurement of patent rights
The world’s largest digital library
Try Scribd FREE for 30 days to access over 125 million titles without ads or interruptions! Start Free Trial Cancel Anytime.
The world’s largest digital library
Try Scribd FREE for 30 days to access over 125 million titles without ads or interruptions! Start Free Trial Cancel Anytime.
(9) Catalyst & Solvents: Depends upon specific selected
manufacturing
process
(A-2) Fixed Charges: (1) Depreciation: For equipments, buildings & other material objects Invested at starting only Expenses for these should be written of as an manufacturing manufacturing expenses Different methods available for calculation For machineries and equipments--- annually 10% of FCI For buildings--- annually 3% of initial cost of buildings
(2) Local Taxes: Depends on plant locality & regional laws For highly populated areas--- annual property taxes --- 2 - 4 % of FCI For less populated areas--- 1 - 2% of FCI
(3) Insurance: Rates depends upon type of process & extent of
The world’s largest digital library
Try Scribd FREE for 30 days to access over 125 million titles without ads or interruptions! Start Free Trial Cancel Anytime.
The world’s largest digital library
Try Scribd FREE for 30 days to access over 125 million titles without ads or interruptions! Start Free Trial Cancel Anytime.
(4) Rent: For rented land & buildings 8 – 12% of value of rented property
(A-3) Plant Overhead Costs: Costs not directly related to production Non-manufacturing machineries, equipments, buildings, etc. Costs--- closely related to costs of labor directly connected with production operation For general chemical plant--- 50 – 70% of total expenses for operating labor, supervision & maintenance
(B-1) Administrative Costs: Expenses connected with top management or administrative activities Salaries & wages to administrators, secretaries, accountants, stenographers, typists & similar workers; Costs for office supplies; outside communications, administrative buildings 20 – 30% of operating labor
(B-2) Distribution & Marketing:
The world’s largest digital library
Try Scribd FREE for 30 days to access over 125 million titles without ads or interruptions! Start Free Trial Cancel Anytime.
The world’s largest digital library
Try Scribd FREE for 30 days to access over 125 million titles without ads or interruptions! Start Free Trial Cancel Anytime.
shipping charges + container’s costs + advertising + technical sales service Cost — depends upon, type of product, other products — depends of companies, location, company policies 2 – 20% of total product cost More for new product or products sold in small quantities to large no. of customers; Low costs for Large volume products such as bulk chemicals
(B-3) Research & Development Costs: For developing new methods & products 2 – 5% of every sales
(B-4) Financing Costs: Interests on borrowed capital (though interest rates are fixed, not considered as fixed charges) Annual interest rates – 5 – 10% of total borrowed capital Investment done directly from company’s existing funds — to to or not to charge interest on it as cost? (depends upon company policies) For income tax calculations--- interest on owned capital --- not charged as cost
(B-5) Gross Earning Expenses: Gross Earning = (Total Income)
(Total Production
The world’s largest digital library
Try Scribd FREE for 30 days to access over 125 million titles without ads or interruptions! Start Free Trial Cancel Anytime.
The world’s largest digital library
Try Scribd FREE for 30 days to access over 125 million titles without ads or interruptions! Start Free Trial Cancel Anytime.
The world’s largest digital library
Try Scribd FREE for 30 days to access over 125 million titles without ads or interruptions! Start Free Trial Cancel Anytime.