UTRAN Technical Proposal
Technical Proposal for Radio Network -Build the cost effective network with fast, best, value added MBB For 2G&3G DATA NETWORK EXPANSION 2014
HUAWEI TECHNOLOGIES CO., LTD. Ethio Telecom Network Expansion Project
Huawei Confidential
TABLE OF CONTENT TABLE OF CONTENTS.........................................................................................................1 LIST OF FIGURES................................................................................................................3 LIST of TABLES....................................................................................................................4 Preface....................................................................................................................................1 1
2
Executive Summary........................................................................................................2 1.1
RAN Planning Result.................................................................................................................... 2
1.2
Benefits to Vietnamobile............................................................................................................... 2
1.3
Other Special Topics..................................................................................................................... 5
VNM’s Requirement Analysis.........................................................................................5 2.1
3
RFP Requirement......................................................................................................................... 5 2.1.1
General Requirement.............................................................................................................. 5
2.1.2
Huawei New NodeB Option 1................................................................................................. 6
2.1.3
Investment Protection............................................................................................................. 6
RAN Network Planning and Design................................................................................7 3.1
Overview of Proposed RAN Network............................................................................................. 7
3.2
RAN Product Design Criteria......................................................................................................... 7
3.3
3.2.1
New NodeB Design................................................................................................................ 7
3.2.2
Expansion RNC/BSC Design................................................................................................. 11
3.2.3
IUB IP Migration................................................................................................................. 13
OMC Design Criteria.................................................................................................................. 14 3.3.1
3.4
3.5
4
M2000 SUN M5000 Software Upgrade..................................................................................14
Site Solution Design................................................................................................................... 15 3.4.1
Antenna Design.................................................................................................................... 15
3.4.2
Power Design....................................................................................................................... 16
Gb over IP Design...................................................................................................................... 19
Huawei Customized Solution for VNM.........................................................................20 4.1
4.2
4.3
4.4
Dedicated smartphone solution to for a future oriented network.......................................................20 4.1.1
100% smartphone penetration................................................................................................ 20
4.1.2
Smartphone oriented RNC design..........................................................................................20
4.1.3
Enhanced Fast Dormancy...................................................................................................... 21
4.1.4
Layered Paging in URA_PCH............................................................................................... 21
Construct Vietnam fast MBB with cutting-edge technologies..........................................................22 4.2.1
Distributed NodeB which encompasses cutting-edge SingleRAN technologies...........................22
4.2.2
All IP transmission to break out bandwidth bottleneck..............................................................24
High NodeB Performance............................................................................................................ 25 4.3.1
Leading RF Performance....................................................................................................... 25
4.3.2
High Capacity and Integration............................................................................................... 25
All IP based Large Capacity RNC................................................................................................ 26
Vietnamobile 3G Data Expansion Project
Huawei Confidential
I
4.5
TCO Savings.............................................................................................................................. 28 4.5.1
4.6
Smooth Evolution....................................................................................................................... 29 4.6.1
5
Cost effective Platform......................................................................................................... 28 Cabinet Sharing.................................................................................................................... 29
4.7
Feature List.............................................................................................................................. 29
4.8
Roadmap.................................................................................................................................. 32
DISCLAIMER..............................................................................................................33
Abbreviations.......................................................................................................................33
Vietnamobile 3G Data Expansion Project
Huawei Confidential
II
LIST OF FIGURES Figure 3-1 Proposed Huawei SingleRAN UMTS Products...............................................................................7 Figure 3-2 Proposed Huawei IPRAN Topology............................................................................................14 Figure 3-6 Actual Site Survey..................................................................................................................... 15 Figure 3-7 Antenna Specifications............................................................................................................... 16 Figure 3-8 Huawei proposed Power Product-TP48200A................................................................................17 Figure 3-9 Huawei proposed Power Product-TP48 300B...........................................................................17 Figure 3-10 Huawei proposed Power Product-APM30 Ver.D.........................................................................18 Figure 4-2 Fast Dormancy VS Enhanced Fast Dormancy...............................................................................21 Figure 4-3 Small form factor and lightest RRU.............................................................................................23 Figure 4-4 Fast Delivery for 100% RRU...................................................................................................... 23 Figure 4-5 Huawei Co-transmission Solution...............................................................................................25 Figure 5-3 Huawei 64QAM HSPA+ solution................................................................................................26 Figure 5-6 Huawei BSC6900 Architecture................................................................................................... 27 Figure 5-7 Huawei GBR Differential Solution.............................................................................................. 28 Figure 5-12 Total Software Upgrade Base Station Architecture......................................................................29
Vietnamobile 3G Data Expansion Project
Huawei Confidential
III
LIST of TABLES Table 1-1 Output power of RRU3826............................................................................................................ 3 Table 3-1 Proposal of Module selection......................................................................................................... 7 Table 3-2 Proposal of new NodeB models Option1......................................................................................... 8 Table 3-4 Model 1....................................................................................................................................... 8 Table 3-5 Model 1 Dimension for Option1..................................................................................................... 9 Table 3-6 Model 2....................................................................................................................................... 9 Table 3-7 Model 2 Dimension for Option1 &Option2....................................................................................10 Table 3-8 Model 3..................................................................................................................................... 10 Table 3-10 Model 4.................................................................................................................................... 11 Table 3-12 Power Design Result for Option1................................................................................................ 19 Table 4-1 SPUb Capabilities....................................................................................................................... 20 Table 4-2 Power Design Result................................................................................................................... 22 Table 5-2 Benefits from Huawei’s Innovative UTRAN Solution.....................................................................28
Vietnamobile 3G Data Expansion Project
Huawei Confidential
IV
Preface As a major player in the telecommunication industry, Huawei Technologies Co., Ltd. provides robust, flexible, cost-effective and future-oriented mobile solutions to worldwide operators. With Huawei series of outstanding products, successful end-to-end solutions, experienced radio frequency planning as well as excellent services, Huawei believes that the cooperation between Vietnamobile and Huawei will be a win-win Situation for each other. This document is drafted to provide a comprehensive description of proposed radio access network solution in accordance to the requirements from Vietnamobile (hereinafter referred to as VNM), which is based on the information provided in RFP. The contents of this proposal are organized as follows: Preface Brief introduction for this proposal Chapter 1: Executive Summary Summarize VNM network expansion planning result, highlights, and special concerns Chapter 2: VNM Requirement Analysis Describe Huawei understanding of the requirements Chapter 3: RAN Network Planning and Design BTS/NodeB details, BSC/RNC, OMC and parts design and dimensioning Chapter 4: Huawei Customized Solution for VNM Detailed solution for this project, and also provide some customized solution to satisfy future network Chapter 5: DISCLAIMER Abbreviation
Vietnamobile Scenario 2000 Project
Huawei Confidential
Page 1 of 37
1
Executive Summary
1.1
RAN Planning Result Based on the existing network configuration and new purchase requirement from VNM, there are two options for 2014 3G data network expansion. Option1 is to enhance both 3G coverage and offload data from 2G hotspot. While option2 is mainly focus on 3G and 2G coverage. Huawei proposes two proposals accordingly. For Option 1: Expansion of UMTS network from the existing 573 NodeB to 806 NodeB with a total of 2418 cells after expansion Reuse live RNCs will be upgraded to support the capacity requirements of VNM in this RFP with the site locations of all the RNC being in the existing three MTSOs, leading to no additional requirement for new switching office. The existing 3G OMC will be expanded to support the capacity requirement in this RFP with software upgrade to latest version R13. However, 2G OMC platform is reaching EOS, we also provide cost effective solution to swap OSS completely with new Single OSS platform with latest version for both 2G and 3G. The new ATAE platform can simultaneously support PRS which allows MBB visibility such as terminal visibility and service visibility. The following table lists the detailed planning results for to Scenario 1 ~ 3. Stage
Scenario 1(Mandato ry)
Carrier Configura tion
Total NodeB
Total Carrier
Capacity( Subs)
Current
573
1,719
200,000
S111
233
699
256,000
Accumulat ive total
806
2418
456,000
S111>S222
164
492
57,400
Accumulat ive total
573
2,211
257,400
164 NodeB S111>S222
1.2
Total RNC
CS Capacity (Erl)
HSDPACa pability(M bps)
HSUPACa pability(M bps)
3
13621
1500
180
Benefits to Vietnamobile A competitive solution is tailored with the goal in mind of achieving cost competitiveness, increased operating efficiency and outstanding network performance for VNM. This in turn translates into long-term TCO saving and future-proof network with the best position for future expansion and evolution. The benefits to VNM are summarized below: 1)
Superior network performance with high scalability and expansion flexibility
State of the art Remote Radio Unit RRU3826 with high power, high capacity, small form factor and light weight
Maximum 1×80W TOC
Maximum four carriers per RRU3826 (capable of 20W per carrier @ S111 and upgradable to 40W per carrier @ S222)
Vietnamobile Scenario 2000 Project
Huawei Confidential
Page 2 of 37
400 mm x 300 mm x 100 mm (with the housing)
15 kg (with the housing)
Tower mounted which contributes to no feeder loss
Support LTE long term evolution without hardware change
Only three RF modules are required for 3*4 configurations with 20W TOC for each carrier. Power capacity as shown in the below table: Table 1-1 Output power of RRU3826 Number of Carriers
Output Power per Carrier (W)
1
80
2
40
3
26
4
20
Working bandwidth of 25M IBW, thus requiring no additional filter.
State of the new Universal Main Processing Transmission Board UMPTb1 with GUL three mode in one BBU, high capacity, LTE hardware ready
Support GSM/UMTS/LTE three mode in one BBU
Support upgrade easily from UMTS to UMTS & LTE dual mode
Support big high signally capacity up tp GSM 72 TRX, UMTS 1500 CNBAP,LTE 120 CAPS separately.
State of new baseband Unit WBBPf card with high capacity and new features of RAN15.0
Support high capacity up to maximum UL 512 CE and UL 768 CE on one WBBPf4 card
Support interconnected across BBUs to achieve baseband resource sharing
Support maximum 6 cells per card
Support new features such as Turbo IC
High speed Mobile Broadband Solution with HSPA+ support with easy upgrade to 42Mbps DL/ 11Mbps uplink
New nodeBs are hardware and software ready for HSPA+@21Mbps/DL and 11.5Mbps/UL starting from the first day.
Multiband and multi-carriers capability with the support of DC-HSDPA/DC-HSUPA (to support carriers in the same frequency band) as well as DB-HSDPA/DB-HSUPA (to support carriers in different frequency bands)
Ready with MIMO+DC function to support downlink peak rate of 84Mbps/user.
All IP transmission to overcome bandwidth bottleneck
100% field-proven IP RAN which is 2 years ahead of other vendors.
Hybrid IP transmission architecture to leverage on existing TDM backhaul resources which enables operator to adopt a mixed transmission scheme, for example voice service will be carried over TDM interface to guarantee high QoS whereas data service will be carried over IP interface to achieve high capacity.
Support of hybrid network clock provision: clock sync on Ethernet in NodeB can be supported by adding IP clock server base on link layer whereas Synchronous Ethernet can be supported by directly obtaining clock source from IP transmission network physical layer.
Vietnamobile Scenario 2000 Project
Huawei Confidential
Page 3 of 37
2)
Superior Mobile Broadband Experience with unsurpassed voice quality, throughput capacity, reliability and QoS
Innovative technology and features to improve voice quality, capacity and reliability
High quality crystal voice, HSPA+ no Power back off, innovative HSUPA Uplink Inteference Cancellation feature, HSUPA FDE, Anti-Interference Scheduling for HSUPA, Dual-Threshold Scheduling with HSUPA Interference Cancellation, Control Channel Parallel Interference Cancellation (CCPIC) etc.
Smartphone oriented capacity dimensioning to avoid signaling storm. 1.
Smartphone software features: Coordinate the smart UE state transition to reduce signaling Enhanced Fast Dormancy feature: at least 40% of signaling exchange can be reduced and RNC CPU resources can be saved significantly while UE battery consumption is saved as much as that in IDLE mode.
Layered Paging in URA_PCH: a large number of unnecessary paging messages (which in turn leads to PCHs being congested) can be avoided.
High capacity RNC platform: high performance BSC6900 platform that adopts flexible capacity strategy both in control plane and user plane. BSC6900 supports up to 50 SPUb boards in control plane with 5300K BHCA or 50 DPUe boards in user plane with 40Gbps throughput;
High redundancy design.
Main boards with backup mechanism;
RNC, SGSN,GGSN, MSC resource pooling;
35% Redundancy design for RNC (handling capacity, C7 signaling and trunk interfaces) and OMC (hardware for management capacity);
Storage battery system with 8 hours backup time.
QoS Guarantee Mechanism and Intelligent Management Platform
3)
Future proof solution to achieve cost competitiveness
New-built sites ready for smooth evolution to SingleRAN HSPA+/LTE
HSPA+ hardware ready for 21 Mbps downlink & 5.76 Mbps uplink from Day 1;
SingleRAN NodeB ready for smooth evolution to LTE with only software upgrade on the RF module and baseband unit and adding of a baseband processing card
1.3
Other Special Topics Huawei, being a long-term strategic partner with VNM, is capable of providing a competitive and customized solution to attain high network performance and. In order to complete the proposal, emphasis is also focused on other special topics as listed below 1
Optional u111->U222 upgrade solution for 164 existing sites
For the existing 164 sites, additional WBBP boards should be added to achieve U222;
2
VNM’s Requirement Analysis
2.1
RFP Requirement
2.1.1
General Requirement
In order to improve and extend 3G coverage and offload for 2G data network, Vietnamobile intends to purchase Node + RNC with the major scope as below:
Vietnamobile Scenario 2000 Project
Huawei Confidential
Page 4 of 37
FESA
ICWA
SAM A
2.1.2
I D
Scope
Unit
Vendor
Quantity
1
Provide new Node B & Transmission
Site
Ericsson Huawei
or
233
2
Provide new RNC (for Ericsson) or upgrade RNC (for Huawei)
Site
Ericsson Huawei
or
1
3
Provide new 2G BTS & transmission
Site
4
Provide additional equipments & transmission for 12 IBS conversion
Site
Ericsson Huawei Ericsson
8 0 12
5
Provide 130 GRFU to swap for DRFU
Broa d
Huawei
0
6
Provide backbone capacity upgrade
Links
Huawei Ericsson
or
TBD Bidders
by
1
Upgrade & Swap transmission Access for 2G & 3G
Links
Huawei Ericsson
or
TBD Bidders
by
8
Engineering Services transmission
Site
Ericsson Huawei Ericsson only Huawei only Ericsson only Huawei only Ericsson Huawei Ericsson only Huawei only
or
233
or
20 0 20 0 233
Option 1
(Full Scope): Radio &
9
Civil work for new sites
Site
10
Managed Services: Radio & transmission
Site
20 0
Huawei New NodeB Option 1
For the detailed site list with configuration, please check Annex 3.2_List of 233 new NodeB. Need to add 10 extension package for sites higher than 50 meters. Name
Region
Province
District
31906 2 31902 6 31901 8 31901 2 31901 1 31900 9 31101 0 31100
South
Dong Nai
Trang Bom
RF Antenna Height (m) 50
South
Dong Nai
Xuan Loc
58
South
Dong Nai
Thong Nhat
58
Main Road + Residential Main Road + Residential Suburban
South
Dong Nai
Long Thanh
58
Main road
South
Dong Nai
Xuan Loc
58
Suburban
South
Dong Nai
Thanh pho Bien Hoa
56
Suburban
South
Binh Thuan
Ham Thuan Nam
58
Suburban
South
Binh Thuan
Ham Thuan Bac
58
Main road
Vietnamobile Scenario 2000 Project
Huawei Confidential
Morphology
Page 5 of 37
5 31100 2 30200 4
South
Binh Thuan
Ham Thuan Nam
58
South
Ba Ria - Vung Tau
Long Dien
58
2.1.3
Main Road + Residential Urban
Investment Protection Existing Investment Protection In order to protect the investment and reduce TCO, the proposed solution should maximally reuse the existing network resources. Future Investment Protection Based on RFP, VNM requires all vendors to propose a cost effective solution in this project and the system should capable to support smooth evolution to next generation mobile technologies without any hardware change. It can be understood as below: Ready for higher throughput via HSPA+ without any hardware replacement. UMTS ready for smooth evolution to LTE in the future without any hardware replacement.
3
RAN Network Planning and Design
3.1
Overview of Proposed RAN Network The following principles will be followed in network design process: 1
Add new NodeB sites based on the scenarios identified in Section 2.1
2
Expand RNCs to support up to 13621 Erl and 1500 Mbps.
The dimensioning of NodeB strictly follows VNM’s demand in RFP. Huawei propose module selection as below. Table 3-2 Proposal of Module selection Items
3G
Module
Software version
Hardware version
Remark
Node B
DBS3900
V200R015
-
RNC
BSC6900
V900R015
HW69R11
RF
RRU3826
-
-
Distributed site
Base Band
BBU3900
-
-
UMPTb1/WBBPf3/UTRP
V200R013
SUN M5000
OSS
M2000
Distributed site
License Expansion +Software Upgrade
: All existing 3G Huawei equipment in Vietnamobile’s network will be upgraded to the latest version of RAN15, which matches with the statement in the table above.
3.2
RAN Product Design Criteria
3.2.1
New NodeB Design The proposed UMTS/LTE multimode base stations for VNM are part of Huawei SingleRAN 3900 series of BTS, comprising the DBS3900, which are based on the modular design and depicted in the figure below:
Vietnamobile Scenario 2000 Project
Huawei Confidential
Page 6 of 37
Figure 3-1 Proposed Huawei SingleRAN UMTS Products
:Detail specification of the provided basestation could be found in Product description documents provided by Huawei Based on the VNM network situation and actual network planning result, Huawei proposes the product selection and site design for the VNM according to following criteria. All Nodes B shall be collocated with existing 2G sites Node B shall support Iub over E1 (8E1 at least) and FE Battery backup time of the proposed Node B shall be at least 8 hours Based on the new NodeB sites distribution, Huawei propose 4 models as below. Table 3-3 Proposal of new NodeB models Option1 Model type
Co-site with
Existing 2G
Model 1
HW
Outdoor
DBS3900(3G,S222)
21
Model 2
HW
Indoor
DBS3900(3G,S222)
119
Model 3
E///
Outdoor
DBS3900(3G,S222)
52
Model 4
E///
Indoor
DBS3900(3G,S222)
41
Vietnamobile Scenario 2000 Project
Proposed Configuration
Huawei Confidential
Quantity
Page 7 of 37
3.2.1.1 Model 1: Indoor co-site with Ericsson- BTS2XXX(2G)+DBS(3G, S111) Scope 2G GSM with Ericsson site, 3G new build. Proposed Product According to the actual site survey, in this model, Huawei will deploy our own power system.
Table 3-4 Model 1 Model
1
Scenario
NodeB Type
Number
UMTS(3*1)
RRU3826 UMPT main control board WBBPf base band board UTRP card for 8*E1 DCDU TP48300/B 100Ah Battery
3 1 1 1 1 1 1
Description The BBU and transmission equipment will be installed in the 19” inch rack. New TP48300/B will be added for 3G and transmission. Distribute new battery for 3G and transmission. Planning Result Table 3-5 Model 1 Dimension for Option1 Mode type
Co-site with
Existing 2G
Model 1
Ericsson
Indoor
Proposed Configuration
Option 1
DBS3900(3G)
21
3.2.1.2 Model 2: Outdoor co-site with Ericsson- BTS2XXX(2G)+DBS(3G, S111) Scope 2G GSM with Ericsson site, 3G new build. Proposed Product According to the actual site survey, in this model, Huawei will deploy our own power system. Table 3-6 Model 2 Model
Scenario
NodeB Type
Number
2
UMTS(3*1)
RRU3826 UMPT main control board WBBPf base band board UTRP card for 8*E1
3 1 1 1
Vietnamobile Scenario 2000 Project
Huawei Confidential
Page 8 of 37
Model
Scenario
NodeB Type
Number
DCDU TP48200A 150Ah*1
1 1 1
Description The BBU and transmission will be installed in the TP48200A cabinet (outdoor power system). New TP48200A will be added for 3G and transmission. Distribute new battery for 3G and transmission. Planning Result Table 3-7 Model 2 Dimension for Option1 &Option2 Mode type Co-site with Existing 2G Model 2
Ericsson
Proposed Configuration
Indoor
DBS3900(3G)
Option 1 119
3.2.1.3 Model 3: Indoor co-site with Huawei- BTS3900(2G)+DBS(3G, S111) Scope 2G GSM with Huawei BTS3900, 3G new build. Proposed Product According to the actual site survey, this model needs a new TP48300/A power system for 3G deployment. Table 3-8 Model 3
Model
3
Scenario
NodeB Type
Number
UMTS(3*1)
RRU3826 UMPT main control board WBBPf base band board UTRP card for 8*E1 DCDU TP48300/B 100Ah Battery/150 Ah Battery
3 1 1 1 1 1 1~3
Description Install new UMTS BBU box and hardware ready for GUL co-BBU SingleRAN solution. New TP48300/A will be added for 3G and transmission. The BBU and transmission equipment will be installed in the 19” inch rack. Distribute new battery for 3G and transmission.
Vietnamobile Scenario 2000 Project
Huawei Confidential
Page 9 of 37
3.2.1.4 Model 4: Outdoor co-site with Huawei- BTS3900A(2G)+DBS(3G, S111) Scope 2G GSM with BTS3900A, 3G new build. Proposed Product According to the actual site survey, this model needs a new TP48200A power system for 3G deployment. Table 3-9 Model 4 Model
4
Scenario
NodeB Type
Number
UMTS(3*1)
RRU3826 UMPT main control board WBBPf base band board UTRP card for 8*E1 DCDU TP48200A 150Ah Battery
3 1 1 1 1 1 1
Description Install new UMTS BBU box and hardware ready for GUL co-BBU SingleRAN solution. New TP48200A (both power and battery cabinet) will be added for 3G and transmission. The BBU and transmission equipment will be installed in TP48200A.
3.2.2
Expansion RNC/BSC Design Current RNCs can support NodeB expansion together with traffic model change with software and hardware expansion. (1) FG2c IP Cards for IUB IP migration on each RNCs (2) IP CLK Server need to deployed in RNC central room For BSC, we also need purchase license only, as the detailed design has not been fixed. We may need to add hardware in different BSCs. According to the RFP requirement, we would use the traffic model herein below:
- CS capacity: Add 8,200 Erl - PS capacity: Add 894 Mbps - Sub/NodeB: 1,000 Subs For both Option 1, the traffic model is as below:
User plane traffic parameters
Vietnamobile Scenario 2000 Project
Input Value
Huawei Confidential
Page 10 of 37
CS voice penetration ratio
100%
CS data (Video Phone 64k) penetration ratio
50%
Voice Traffic per CS voice sub in BH(Erlang )
0.018
CS data traffic per CS data (Video Phone 64k) sub in BH (Erlang)
0.0018
CS voice call duration (sec.)
60
CS data (Video Phone 64k) call duration (sec.)
60
Handover times per CS call (Inter/Intra RNC soft&softer handover)
6
PS (Including R99 and HSPA) Penetration Ratio (% of Total Subscribers)
100%
PS throughput (Including R99 and HSPA, UL+DL) per PS sub in BH (bps)
14,775
PS Rab Data Rate (kbps)
47.284736842
Vietnamobile Scenario 2000 Project
Huawei Confidential
Page 11 of 37
Smart phone Penetration Ratio (% of Total Subscribers)
100%
(Smart phone) PS call per PS sub per BH
5
(Smart phone) Handover times per PS call (Inter/Intra RNC soft&softer handover)
2.5
(Smart phone) PS channel switch per PS call
1
(Smart phone) Cell update per PS call
0.1
(Smart phone) Mean holding time (MHT) in DCH/H/FACH state per PS call (sec)
34
(Smart phone) Mean holding time (MHT) in PCH per PS call (sec)
15
(Smart phone) PS throughput (Including R99 and HSPA, UL+DL) per PS sub in BH (bps)
3,000
Vietnamobile Scenario 2000 Project
Huawei Confidential
Page 12 of 37
RNC dimension input is as below:
Hardware Current License
RNC 100
RNC 200
RNC 300
Total
BSC6900 UMTS Basic Software, V900R015 (per Erl)
897
4844
240
5981
BSC6900 UMTS Basic Software, V900R015 (per Mbps)
94
509
25
628
HSDPA Introduction Package (per Mbps)
81
420
22
523
HSUPA Introduction Package (per Mbps)
1
4
1
6
Hardware License After Expansion
RNC 100
RNC 200
RNC 300
Total
BSC6900 UMTS Basic Software, V900R015 (per Erl)
2318
11317
546
14181
BSC6900 UMTS Basic Software, V900R015 (per Mbps)
242
1223
57
1522
HSDPA Introduction Package (per Mbps)
208
934
49
1191
HSUPA Introduction Package (per Mbps)
208
934
49
1191
3.2.2.1
Dimension procedure: Transmission Dimension:
233 NodeB Exp RNC 100 RNC 200 RNC 300 3.2.3
Current NodeB
Current Cell
Add NodeB
Add Cell
Add DC Cell
Current E1
Add E1
230 266 77
690 798 231
44 192 20
132 576 60
132 576 60
920 1064 308
1096 1832 388
IUB IP Migration Since current NodeB IUB transmission is ATM only, Huawei provide IP migration solution as below.
Vietnamobile Scenario 2000 Project
Huawei Confidential
Page 13 of 37
(1) FG2c IP Cards for IUB IP migration on each RNCs (2) IP CLK Server need to deployed in RNC central room (3) Site installation package for IP migration
Clock Source: •
On RNC sites, both BITS and CX will provides PRC input for IPCLKs;
•
During the Y1 implementation, some IPCLK which not collocated with RNC sites, will be equipped with GPS antenna for PRC input.
Resiliency: •
IPCLK will be deployed in pairs to form a active/standby configuration. The BTS/NodeB will choose the best clock according to BMC algorithms.
•
The IP RAN network will utilize the L3VPN’s protection to facilitate the sync high availability;
QoS: •
The IPCLK packet’s DSCP value will set to 46 (EF);
•
IP RAN will use PQ to schedule the IPCLK packets to avoid introduce large PDV;
Primary clock path Backup clock path
NodeB
IP RAN
Primary IPCLK Backup IPCLK
BTS
BITS RNC/BSC
No de B
Figure 3-2 Proposed Huawei IPRAN Topology
RNC/BSC Location
IPCLK Location
IPCLK Quantity
Wireless Sites Quantity
Hanoi
Hanoi
2
260
Danang
Danang
2
97
HCM
HCM
2
452
Vietnamobile Scenario 2000 Project
Huawei Confidential
Remark
1+1 backup, GPS antenna system if existing central rooms do not have.
Page 14 of 37
3.3
OMC Design Criteria
3.3.1
M2000 SUN M5000 Software Upgrade Huawei provided SUN M5000 server as hardware platform. The management capacity of M5000 8 CPU and in term of equivalent Network Elements is 340. To support additional new 233 NodeBs, only need software upgrade and license expansion. Based on RFP requirement, the OMC design will be based on following principle: Fully utilizing the existing resource, e.g. equipment room space and transmission. The redundancy of OMC should be 35%, all interfaces are configured with 1+1 redundancy. Centralized management, remote notification. Stand alone PRS system would be introduced.
: Detail specification of the provided OMC product could be found in Product description documents provided by Huawei.
3.4
Site Solution Design Site solution plays a critical role in overall network performance and at the same time comprises a significant share of the CAPEX and the OPEX. Bearing this in mind, the solution is design based on the principles of cost saving without compromising performance.
3.4.1
Antenna Design According to the actual site survey, there are some of towers with high numbers of antennas installed. This leads to difficulties in installing more new antenna on such kind of tower. Furthermore, it is also difficult to evaluate the maximum load of the tower and as a result it is risky to add more antennas on it. Figure below demonstrate two different tower scenarios with few antenna installed (enough space) and high number of antenna installed (not enough space) No Enough Space
Figure 3-3 Actual Site Survey Based on the VNM’s current network situation and actual network planning result, Huawei proposes the product fit and site design according to the following criteria. For co-site scenario, single band antenna or dual band antenna will be used according to tower condition. For tower will enough space, single band antenna will be use. For tower with not enough space, the existing antenna will be dismantled and dual band antenna will be installed. Generally, 10% of the co-sited sites will use dual band antennas. Need to update site solution and BoQ after site survey. For new-site scenario, single band antenna will be used Antenna For 1800MHz&1900MHz&2100MHz
Vietnamobile Scenario 2000 Project
Huawei Confidential
Page 15 of 37
A19451800v01
Directional Antenna,DX-1710-2200-65-18i-0F,2*7/16 DIN Female,Downtilt kit packed separately
Antenna For Dual&Triple ADU451807v0 1
Directional Antenna,DXX-790-960/1710-2180-65/65-17.5i/18.5iM/M,4*7/16 DIN Female,Downtilt kit packed separately
Figure 3-4 Antenna Specifications
3.4.2
Power Design
TP48200A
Specification
Dimension
1500(H)*650(W)*650(D) base
mm/without
100Hmm*650Wmm*650Dmm / base
Vietnamobile Scenario 2000 Project
Huawei Confidential
Page 16 of 37
Weight
≤120 kg (without battery cabinet)
AC input mode
Three phase:346Vac ~ 415Vac/200Vac ~ 240Vac or Single phase:200Vac~240Vac
Heat dissipation
850W (1500W as optional)
Environment Temperature
-40℃~+45℃ + solar radiation
Relative Humidity
5%~100% RH
Battery space
Up to 2*180AH battery inside
User space
8U space to house BBU or transmission equipment
Noise
According to ≤
[email protected]
Installation
On the concrete floor or rooftop.
GR487
,
noise
Figure 3-5 Huawei proposed Power Product-TP48200A
Battery + Battery Rack
Power Supply System
Shuangdeng
Mini TP48300B: W*H*D:442mm(W)×360mm(D)×480mm(H)
W*H*D:600mm*700mm*480mm
Figure 3-6 Huawei proposed Power Product-TP48
Vietnamobile Scenario 2000 Project
Huawei Confidential
300B
Page 17 of 37
BTS3900A Ver.D
Specification
Dimension
1400(H)*600(W)*480(D) w/o base 1600(H)*600(W)*480(D) w/i base
Weight
≤194kg (AC)
DC/AC
APM30H+RFC: 220V AC; 110V AC; TMC11H+RFC: -48V DC
APM30H dissipation
Heat
1500W(Ver.D)
Environment Temperature
-40℃~+50℃,w/ solar radiation
Relative Humidity
5%~100%RH
Height
-60~4000m
Noise
APM30H/TMC11H ( Ver.D ) thermal consumption ≤700W, or RFC cabinet use 1*80W RFU: ETS 300 753,Rural Area,Class 4.1E。
APM30H/TMC11H ( Ver.D ) thermal consumption > 700W , or RFC cabinet use 2*80W RFU: : ETS 300 753,Urban Area,Class 4.1E。
Installation
On the concrete floor or rooftop. Figure 3-7 Huawei proposed Power Product-APM30 Ver.D
TP48200A is proposed as outdoor 3G+Transmission power system;
Vietnamobile Scenario 2000 Project
Huawei Confidential
Page 18 of 37
TP48300B is proposed as indoor 3G+Transmission power system; APM30 reuse solution is provided for Huawei outdoor sites. 3.4.2.1 Planning Design Result Table 3-10 Power Design Result for Option1
Count of ID Model Model1 Model2 Model3 Model4
Power Cabinet APM30(REUSE)
20
21
Grand Total
20
140
3.5
TP48200/A
TP48300/B 21
119 52
73
Gb over IP Design GBSC traffic increased and ask for Gb over IP migration since the TDM transmission interface cards is not enough from SGSN side. Huawei provides Gb over IP solution for DNBS1/ DNBS4/ DNBS5/ DNBS6/ HCBS6. We provides Gb over IP/EDGE license as well as IP cards for expansion. For detail, please check BOQ.
BSC
Location
SGSN
Current Configured Gb Channel
Added Gb Channel
Final Gb Channel
Stage 1
Stage 2
HNSG1
50
144
194
GboFR
Transmission Protection
HNBS3
MTSO Hanoi
HNBS6
Hoa Binh
35
92
127
GboFR
HNBS7
Ha Tinh
35
80
115
GboFR
DNBS1
MTSO Danang
80
115
195
GboFR
GboF R GboF R GboF R Gb/IP
DNBS2
MTSO Danang
200
198
398
Gb/IP
Gb/IP
DNBS4
Dak Lak
150
290
440
GboFR
Gb/IP
DNBS5
Binh Dinh
67
115
182
GboFR
Gb/IP
1+0 Redundancy
DNBS6
Binh Dinh
200
345
545
GboFR
Gb/IP
1+0 Redundancy
HCBS6
Vung Tau
140
185
325
GboFR
Gb/IP
1+0 Redundancy
HCBS3
MTSO HCM
487
465
952
Gb/IP
Gb/IP
1+ 1 Redundancy
HCBS5
Dong Nai
240
428
668
GboFR
GboF R
1,684
2,457
4,141
HCSG1
Total
4
1+ 1 Redundancy 1+ 1 Redundancy 1+0 Redundancy
IP Interface Card Not required Not required Not required Required, new purchase Required, available Required, new purchase Required, new purchase Required, new purchase Required, new purchase Required, available Not required
Huawei Customized Solution for VNM Based on our understanding of the RFP requirements, Huawei will propose customized solution to build a stateof-the-art network with best users experience without compromising previous investment.
Vietnamobile Scenario 2000 Project
Huawei Confidential
Page 19 of 37
4.1
Dedicated smartphone solution to for a future oriented network
4.1.1
100% smartphone penetration In the scope of the project, Huawei takes into consideration the 100% smartphone penetration ratio stated in the RFP and this is reflected in the RNC capacity dimensioning. Besides putting emphasis on the hardware capability to handle the surge in signaling requirements, two smartphone dedicated features are also provided to counter the signaling storm problem araising from increased smartphone penetration. These two features are: “Enhanced Fast Dormancy” and “Layered Paging in URA_PCH”.
4.1.2
Smartphone oriented RNC design With the increasing penetration ratio of smartphones as a proportion of overall device, the impact of smartphones to the overall signaling traffic becomes a critical issue. According to the statistic data, the signaling traffic of smartphones is 14 times of featured phone. With the understanding of the technical requirement in RFP and business requirement in the market, Huawei here proposes a high signaling capacity system for VNM. SPUb is the signaling processing board in RNC. since RAN14.0, the signaling capacity has been greatly enhanced. For the capacity of SPUb, please refer to the table below. Table 4-11 SPUb Capabilities Boa rd SPUb
BH CA* 124 000
No deB 180
C el l 600
cNbap /s 1800
Active users
9600
Note: The BHCA capacity depends on the actual traffic.
With SPUb, RNC can be flexibly configured according to the actual capacity demands, referring to both data throughput and signaling. 4.1.3
Enhanced Fast Dormancy This feature concerns with the impact of Fast Dormancy to the RNC. To reduce the signaling processing cost in the Fast Dormancy procedure, when receiving SCRI (signaling connection release indication) message from UE or UE inactivity timer expires, RNC can transfer UE state to CELL/URA_PCH instead of IDLE mode which is in legacy Fast Dormancy processing. The picture below indicates the working principle of enhanced fast dormancy.
Vietnamobile Scenario 2000 Project
Huawei Confidential
Page 20 of 37
Figure 4-8 Fast Dormancy VS Enhanced Fast Dormancy With this feature, when receiving SCRI from UE or UE inactivity timer expires, RNC will decided to transfer the state of the UE to CELL_FACH or through Cell_FACH to CELL/URA_PCH instead of IDLE mode. When UE periodically sends heartbeat message, RNC will reconfigure UE to CELL_FACH or CELL_DCH. The signaling procedure between UE and RNC will be limited to only a few message exchanges because the RRC connection keep existing, at least 40% signaling exchange can be reduced and RNC CPU resources can be saved significantly while UE battery consumption is saved as much as that in IDLE mode. 4.1.4
Layered Paging in URA_PCH Due to the rapid rise of smart phone use in recent years, paging messages have been increasing. Conventionally, paging messages are sent to the entire UTRAN registration area (URA). Once Layered Paging in URA_PCH is activated, paging messages are first sent to the last camped-on cell of the UEs in the URA_PCH state and the neighboring cells of the last camped-on cell. When necessary, these messages will be sent to the URA. This reduces the number of paging messages and the possibility of PCH congestion, eliminates the need for manually dividing URAs, and reduces the number of URA updates.
4.2
Construct Vietnam fast MBB with cutting-edge technologies From the experienced accumulated from previous 3G project with VNM and in lights of the competition and challenges faced by VNM in expanding its 3G network, we have identified a few key challenges in 3G network deployment Space and power constraints leading to challenging sites deployment Interference complication in the border area with two operators using the same frequency
4.2.1
Distributed NodeB which encompasses cutting-edge SingleRAN technologies To overcome the challenges of existing network environment and to meet VNM’s technical requirements, Huawei proposes our matured SingleRAN solution to realize a sound and high performance 3G network The proposed DBS3900 nodeB possesses the following advantages: Multi technology nodeB which supports GSM/UMTS/LTE in the same platform High capacity basedband processing unit (BBU)
Vietnamobile Scenario 2000 Project
Huawei Confidential
Page 21 of 37
Table 4-12 Power Design Result Mode
GSM
Capacity
UMTS
A single cell supports a maximum of 24 carriers. A single BTS of a version earlier than GBSS14.0 supports a maximum of 72 carriers and 12 cells. A single BTS of GBSS14.0 supports a maximum of 126 carriers (TDM) and 32 cells. A single BBU: 24 cells, (uplink: 3072 channel elements (CEs); downlink: 4608 CEs) Two interconnected BBUs: 48 cells (uplink: 5632 CEs; downlink: 8448 CEs)
As of RAN14.0.
LTE
Maximum throughput per cell with 20 MHz bandwidth
Downlink data rate at the MAC layer: 150 Mbit/s (2x2 MIMO); uplink data rate at the MAC layer: 70 Mbit/s (2x2 MU-MIMO or 2x4 MU-MIMO)
Maximum throughput per eNodeB
Sum of uplink and downlink data rates at the MAC layer: 1500 Mbit/s (packet size: 550 bytes)
Maximum number of UEs in RRC_CONNECTED mode per eNodeB:
3024 with 1.4 MHz bandwidth
6480 with 3 MHz bandwidth
10,800 with 5 MHz/10 MHz/15 MHz/20 MHz bandwidth
Data radio bearers (DRBs): a maximum of 8 DRBs can transmit data of a UE at the same time.
Small form factor and light weight RRU3826 which is tower mounted to reduce footprint and facilitate installation Only 3 RF modules for 3*4 configurations, 20W TOC for each carrier. Working bandwidth with the support of 25M IBW, requiring no additional filter.
Figure 4-9 Small form factor and lightest RRU
Flexible capability, fast delivery
Vietnamobile Scenario 2000 Project
Huawei Confidential
Page 22 of 37
Figure 4-10 Fast Delivery for 100% RRU
Simple & fast deployment
As the normal scenarios, RRU installation need the workers climb the tower and fix near the antenna. So the weight of RRU is the key factor, the lighter the module, the quicker and simpler the engineering, the fast deployment would largely benefit to VNM to push the network time to market. Huawei field lightest module RRU3826 only owns 12L/15kg with 1*80W high integrated capacity, which 30% leading comparing to field traditional 18L/21kg modules.
Install on tower &zero feeder loss
Compare to the macro site solution, RRU allow operator to install the module close to the antenna, which help the operator save 3dB feeder loss and get more 20%~30% additional coverage with the same TOC, As the inventor of RRU solution, Huawei deeply understand the main concern of the RRU. Corresponding to the benefit, RRU solution would bring some challenges, the reliability is the most key factor, as we all know, when the RRU install on the tower it means more difficulty than macro site if RRU is down. Huawei hold the most mature design and richest delivery experience in the world, which ensure to keep the RRU failure in lowest in the field.
Easy site acquisition
Per our survey in Vietnam, most sites’ resource would need sharing with 2~3 operators, which make the site space difficult to obtain. RRU solution allow operator to install in flexible method, for example, we would install the RRU on the tower in most scenarios. In some specific scenario, such as street site, RRU would be supported to mount on the wall, Etc.
Low power consumption
Huawei DBS3900 RRU solution adopts innovative MCPA technology and intelligent power management, which can largely decrease the power consumption of base station. Furthermore, the module adopt the natural dissipation, compare to the macro site, no need additional fans which keep the lower failure rate and lower power consumption. Solution benefits: Field lightest with 15Kg, which is easier to fix on the tower, compare to other vendors’ 21Kg module. Large capacity and high integration, which no need additional footprint. Long term investment protection based on smooth evolution in future years. 4.2.2
All IP transmission to break out bandwidth bottleneck Transmission resource is one of the most valuable assets for operators in the future, and IP based unified bearer is the inevitable trend for multi-services. Demands of VNM This is a good opportunity for VNM to modernize the network to IP and optimize the network architecture parallel with the RAN expansion project, with achievements:
Vietnamobile Scenario 2000 Project
Huawei Confidential
Page 23 of 37
Unified transmission to enhance network efficiency and reduce backhaul cost; Future-oriented technology support new services fast deployment, such as LTE IP transmission enable an open & high efficient pipe for multi-services Huawei IP Co-transmission Solution As the industry leader in IPRAN field, Huawei proposes to provide the all IP transmission architecture for VNM, especially the co-transmission of GSM&UMTS <E.
Figure 4-11 Huawei Co-transmission Solution Unified transmission for all GSM/UMTS/LTE sites to enhance network efficiency and lower cost IP transmission enable an open and high efficient pipe for multi-services Leading IP compress technology in Iub & Gb interface enhancing ~30% transmission efficiency. (Note: this is the reference value) Smooth way for fast LTE deployment in the future by co-transmit with legacy networks such as GSM, UMTS for better resources utilization and OPEX reduction. Solution Benefits Compared to the traditional independent transmission, it can lower deployment cost, shorten construction period and ease the maintenance effectively, reducing the CAPEX and OPEX of operators. It will adopt All IP development trend of future transport.
4.3
High NodeB Performance
4.3.1
Leading RF Performance High Output Power All radio modules, including the 4 carriers at least, provide 20W output power. This high output power ensures better coverage and improved indoor reception. Furthermore this configuration requires one X-Polar antenna per sector which minimizes the impact on existing antenna system. High Receiver Sensitivity Huawei’s SingleRAN equipment offer receiver sensitivity of -125.8dBm. This improved receiver sensitivity, compared with -118dBm traditional legacy equipment receiver sensitivity, can improve the cell coverage range by additional 20%.
Vietnamobile Scenario 2000 Project
Huawei Confidential
Page 24 of 37
4.3.2
High Capacity and Integration Large Capacity RRU radio module supports up to 4 UMTS carriers, and max 8 grades cascaded, up to 24 carriers are supported. 100% RRU requires no footprint which could minimize space requirement, reduce site cost and offer flexible deployment options. Integration Highly integrated RRU3826 is only 12L with field lightest RF module with hardware ready for U/L dual mode or LTE mode, which bring more benefit to the closed in tower fixture, exquisite meeting the multi mode feature requirement. Key highlights of Huawei HSPA+ Higher Order Modulation (HOM) at Air Interface By using 64QAM instead of 16QAM as modulation scheme in HSPA+ downlink, the number of bits per symbol increase from 4bits to 6bits and hence the data rate of each HSDSCH code increase from 960kbps to 1.4Mbps. The HOM of 64QAM can achieve 21Mbps data throughput in the downlink.
Figure 5-12 Huawei 64QAM HSPA+ solution
4.4
All IP based Large Capacity RNC To meet high-speed and large-volume data services of HSPA era, Huawei BSC6900 of RNC introduces advanced and future oriented all-IP Platform that establish its leading position in industry. The large capacity and high density RNC greatly simplify the network architecture, thus reducing maintenance costs and saving physical space, which in turn leads to CAPEX and OPEX saving.
Common All-IP platform of advanced radio access controller
The BSC6900 uses the all-IP Platform of Advanced Radio Controller (PARC) developed by Huawei, it provides sufficient bandwidth for high-speed and large-volume data services, and reduces the cost of construction, operation, and maintenance of transport networks. Based on the Gigabit Ethernet (GE) star non-blocking switching on the Medium Access Control (MAC) sub layer, the BSC6900 achieves a central switching capacity of 120 Gbit/s.
Vietnamobile Scenario 2000 Project
Huawei Confidential
Page 25 of 37
Figure 5-13 Huawei BSC6900 Architecture
High integration and large capacity
With only 2 cabinets, Huawei RNC support up to 3,060 Node Bs, 5,100 cells, 167,500 Erlang voice traffic. Both uplink and downlink PS data capacity reach 40 Gbps.
Fully pooled processor
Due to fully pooled processor design, BSC6900 can support smooth expansion based on independent board level for signaling, user traffic, and transmission connectivity respectively.
RNC pool design to improve the reliability in maximum
Huawei support the leading RNC pool solution in the industry, which can improve the reliability of the service maximally.
Diverse transmission solution
BSC6900 supports integrated ATM & IP transmission solution. Hybrid IP transport and ATM/IP dual stack on Iub interface can be supported. Multiple types of physical transmission ports for the Iub, Iur, and Iu interfaces can be supported as well. The ATM transmission ports are the following types:
E1/T1
Unchannelized STM-1/OC-3c
Channelized STM-1/OC-3
The IP transmission ports are the following types:
E1/T1
Fast Ethernet (FE)
GE
POS/cPOS
Advanced RRM algorithms
Huawei advanced RRM algorithms of power control, handover, call admission control, load control and resource allocation effectively improve system performance.
QoS improvement solution
GBR (Guarantee Bit Rate) solution and priority control provide differentiated services experience, guarantee the VIP user’s QoS, and improving VIP users’ experiences.
Figure 5-14 Huawei GBR Differential Solution
Vietnamobile Scenario 2000 Project
Huawei Confidential
Page 26 of 37
4.5
TCO Savings
4.5.1
Cost effective Platform a)
The unified platform and modular design make network deployment very fast and easily and also reduce CAPEX and OPEX greatly.
b) High integrated and large capability modules can save footprint and rental cost for the operator. Even Huawei BBU module can be installed in any existing 2U high spare and RRU installed near the antenna, which realize zero footprint deployment. c)
Superior RX sensitivity and Higher Output Power can help operator reduce the number of the site and save equipment cost.
d) High effective digital power amplifier (up to 40%) save the power consumption more than 45% compare with the traditional solution. In DBS solution, the power consumption can be reduced further with RRU installed near the antenna. e)
Smooth evolution ability to HSPA+ and LTE can protect investment of operator maximum. Table 5-13 Benefits from Huawei’s Innovative UTRAN Solution Item
Revenue Increasing
Performance improvement
Multi-carrier technology
√
√
√
High power efficiency
√
√
√
High performance HSPA
√
√
Leading IPRAN
√
√
Mobile TV based on MBMS Smooth evolution to HSPA+ and LTE Smart phone based, large capacity RNC
4.6
TCO Saving CAPEX OPEX Saving Saving
√
√
√ √
√
√
√
√
√ √
Smooth Evolution Focused on the pressure and demand of VNM, Huawei provide industry leading, TCO saving and future oriented solution to help VNM get most benefit from SingleRAN. SDR based SingleRAN enables flexible migration between different technologies (GSM/UMTS/LTE) on same frequency, thus avoid duplicating investments and ensure smooth migration in future, which can be seen in the figure below.
Vietnamobile Scenario 2000 Project
Huawei Confidential
Page 27 of 37
Figure 5-15 Total Software Upgrade Base Station Architecture
4.6.1
Cabinet Sharing
With TP48200A and APM30 , in Huawei’s proposal, we offer 3G and transmission share same installation space for outdoor sites. Huawei’s 3900 series nodeB’s BBU is a multimode BBU which provide a common platform for GSM/UMTS/LTS. The co-exist of different technologies on the same platform contributes to increased operating efficiency.
4.7
Feature List Beside the mandatory and optional features, there are still many other features realized in the version but not adopted in the project. For detail, please check our bill of quotation.
RAN15.0 RNC Features package for 233 New NodeB WRFD-010613 WRFD-020701 WRFD-011600 WRFD-011000 WRFD-021309 WRFD-150205 WRFD-010615 WRFD-020303 WRFD-020309 WRFD-020305 WRFD-020306 WRFD-140206
Vietnamobile Scenario 2000 Project
AMR-WB (Adaptive Multi Rate Wide Band) (per Erl) AMR/WB-AMR Speech Rates Control (per Erl) TFO/TrFO (per Erl) Cell Broadcast service (per Erl) Improved Downlink Coverage (per Erl) Layered Paging in Idle Mode (per Erl) Multiple RAB Package (PS RAB >=2) (per Erl) Inter-RAT Handover Based on Coverage (per Erl) Inter-RAT Handover Based on DL QoS (per Erl) Inter-RAT Handover Based on Service (per Erl) Inter-RAT Handover Based on Load (per Erl) Layered Paging in URA_PCH (per Erl)
Huawei Confidential
Page 28 of 37
WRFD-050402
IP Transmission Interface (per Erl)
WRFD-140213 WRFD-011000 WRFD-010610 WRFD-010620 WRFD-010621 WRFD-010622 WRFD-010611 WRFD-010651 WRFD-010623 WRFD-010650
Intelligent Access Class Control (per Erl) Cell Broadcast service (per Mbps) HSDPA Introduction Package (per Mbps) HSDPA 3.6Mbps per User (per Mbps) HSDPA 7.2Mbps per User (per Mbps) 32 HSDPA Users per Cell (per Mbps) HSDPA Enhanced Package (per Mbps) HSDPA over Iur (per Mbps) 64 HSDPA Users per Cell (per Mbps) HSDPA 13.976Mbps per User (per Mbps)
WRFD-010681 WRFD-010685 WRFD-010612
HSPA+ Downlink 21Mbps per User (Per Mbps) Downlink Enhanced L2 (Per Mbps) HSUPA Introduction Package (per Mbps)
WRFD-010635
HSUPA over Iur (per Mbps)
WRFD-010614
HSUPA Phase 2 (per Mbps)
WRFD-010636 WRFD-021309
SRB over HSUPA (per Mbps) Improved Downlink Coverage (per Mbps)
WRFD-010690
TTI Switch for BE Services Based on Coverage (per Mbps)
WRFD-010634
60 HSUPA Users per Cell (per Mbps)
WRFD-010507
Rate Negotiation at Admission Control (per Mbps) Layered Paging in Idle Mode (per Mbps) Multiple RAB Package (PS RAB >=2) (per Mbps) One Tunnel (per Mbps) Inter-RAT Handover Based on Coverage (per Mbps) Layered Paging in URA_PCH (per Mbps) IP Transmission Introduction on Iub Interface (per Mbps)
WRFD-150205 WRFD-010615 WRFD-020111 WRFD-020303 WRFD-140206 WRFD-050402
Introduction
on
Iub
WRFD-140213 WRFD-140216
Intelligent Access Class Control (per Mbps) Load-based Uplink Target BLER Configuration (per Cell)
WRFD-140211
Dynamic Target RoT Adjustment (per Cell)
Vietnamobile Scenario 2000 Project
Huawei Confidential
Page 29 of 37
WRFD-140215
Dynamic Configuration of Feedback Period (per Cell)
WRFD-150236
Load Based Dynamic Adjustment of PCPICH (per Cell)
WRFD-020500 RAN15.0 NodeB Feature Package(S111) for 233 New NodeB WRFD-010614 WRFD-150242 WRFD-010691
HSDPA
CQI
Enhanced Fast Dormancy (per PS k Sub)
HSUPA Phase 2 (per NodeB) HSDPA Scheduler Pool (per NodeB) HSUPA UL Interference Cancellation (per Cell)
WRFD-020136
Anti-Interference (per Cell)
WRFD-010638
Dynamic CE Resource Management (per NodeB)
WRFD-010631
Dynamic Code Allocation Based on Node B (per NodeB)
WRFD-020118 WRFD-050501
Energy Efficiency Improved (per NodeB) Clock Sync on Ethernet in Node B (per NodeB) CE overbooking (Per NodeB) Clock Sync on Ethernet in Node B (per NodeB) Intelligent Power Management (per NodeB) HSUPA Phase 2 (per NodeB) Downlink 64 QAM (per Cell)
WRFD-140212 WRFD-050501 WRFD-020121 WRFD-010614 WRFD-010683 Optional Features Optional RAN15 RNC Features WRFD-030004
Scheduling
for
HSUPA
Adaptive Configuration of Typical HSPA Rate (per Mbps)
WRFD-020806
Differentiated Service Based on SPI Weight (Per Mbps)
WRFD-010712
Adaptive Configuration of Traffic Channel Power offset for HSUPA (per Mbps)
WRFD-140222
Adaptive Adjustment of HSUPA Small Target Retransmissions (per Mbps)
WRFD-021103 WRFD-021103
Access Class Restriction (per Erl) Access Class Restriction (per Mbps)
WRFD-020309
Inter-RAT Handover Based on DL QoS (per Mbps)
WRFD-020308
Inter-RAT Handover Phase 2 (per Mbps)
Vietnamobile Scenario 2000 Project
Huawei Confidential
Page 30 of 37
WRFD-020305
Inter-RAT Handover Based on Service (per Mbps)
WRFD-020306
Inter-RAT Handover Based on Load (per Mbps)
Optional RAN15 NodeB Feature Package(S111) WRFD-140201 WRFD-020137
Dual-Threshold Scheduling with Interference Cancellation (per Cell)
WRFD-030010
CQI Adjustment Based on Dynamic BLER Target (per Cell)
WRFD-140221
HSDPA Scheduling Based on UE Location (Per Cell)
WRFD-150206 WRFD-150222 WRFD-150235
Turbo IC (per Cell) HSUPA Time Division (per Cell) DPCH Maximum Power Restriction (per Cell) Control Channel Parallel Interference Cancellation (CCPIC) (per NodeB)
WRFD-010210 WRFD-140202
4.8
AMR Voice Quality Improvement Based on PLVA (Per Cell) HSUPA
Control Channel Parallel Interference Cancellation (Phase 2) (Per NodeB)
Roadmap For all the GSM/UMTS/LTE/OSS products Huawei provide in this proposal, we also provide the latest roadmap for your reference. With the new and powerful solution, the UTRAN can easily support long term evolution to HSPA+ and LTE. For detail, please refer to roadmap documents.
Vietnamobile Scenario 2000 Project
Huawei Confidential
Page 31 of 37
5
DISCLAIMER The solution and dimension in this proposal are subject to the business requirement and traffic model required in the RFP and any assumption herein is deemed as necessary. Notwithstanding any description in the proposal, the scope of work of Huawei's offer is strictly subject to the Bill of Quantities. In case the condition of solution and dimension varies, the Bill of Quantities and price shall be adjusted accordingly.
Abbreviations Abbreviation
A AMR ANR APN APS ARPU ASIC ATM B BG BHCA BSC BSS BSSAP C CAMEL CAP CC CDR CES CG CN CORBA CS CSCF D DCH DHCP DL DNS E EIR EMS F FDD FE FTP G GE GGSN GMLC GPRS GPS
Full Name
Adaptive Multi-Rate Automatic Noise Restrain Access Point Name Automatic Protection Switch(ing) Average Revenue Per User Application Specific Integrated Circuit Asynchronous Transfer Mode Border Gateway Busy Hour Call Attempt Base Station Controller Base Station Subsystem Base Station Subsystem Application Part Customized Applications for Mobile network Enhanced Logic CAMEL Application Part Call Control Call Detail Record Circuit Emulation Service Charging Gateway Core Network Common Object Request Broker Architecture Circuit-switched Call Session Control Function Dedicated Channel Dynamic Host Configuration Protocol Downlink Domain Name Server Equipment Identification Register Element Management System Frequency Division Duplex Fast Ethernet File Transfer Protocol Gigabit Ethernet Gateway GPRS Support Node Gateway Mobile Location Center General Packet Radio Service Global Position System
Vietnamobile Scenario 2000 Project
Huawei Confidential
Page 32 of 37
Abbreviation
GRE GSM GTP GUI GW H HLR HPLMN HSDPA HSS I ICC IM IMA IM-MGW IMS IMSI IMT-2000 IN IOT ISC ISDN ISUP ITU-T K KB L L2TP LAN LCS LI LIG LMT M MAP MGCF MGCP MM MMI MML MNC MNP MS MSC MSISDN MSRN MTBF MTP3B MVPN N NMS NPDB O
Full Name
Generic Routing Encapsulation Global System for Mobile Communications GPRS Tunneling Protocol Graphic User Interface Gateway Home Location Register Home PLMN High Speed Downlink Packet Access Home Subscriber Server Interference Canceling Combination Intensity Message Inverse Multiplexing on ATM MGW of IMS subsystem IP Multimedia Subsystem International Mobile Station Identity International Mobile Telecommunication 2000 Intelligent Network Interoperability Test IP multimedia Service Control Integrated Services Digital Network Integrated Services Digital Network User Part/ISDN User Part International Telecommunication Union - Telecommunication Standardization Sector Kilobyte Layer 2 Tunneling Protocol Local Area Network Location services Lawful Interception Lawful Interception Gateway Local Maintenance Terminal Mobile Application Part Media Gateway Control Function Media Gateway Control Protocol Mobility Management Man Machine Interface Man-Machine Language Mobile Network Code Mobile Number Portability Mobile Station Mobile Service Switching Center Mobile Station International ISDN Number Mobile Station Roaming Number Mean Time Between Failures Message transfer part (broadband) Mobile Virtual Private Network Network Management Station; Number Portability Database
Vietnamobile Scenario 2000 Project
Huawei Confidential
Page 33 of 37
Abbreviation
OMC P PCH PDP PLD PLMN POS PPS PS PSTN PTT Q QoS R RAB RADIUS RAN RANAP RNC RRM RRU S SCCP SCP SCTP SDF SDH SGSN SGW SIM SMC SMSC SMS-GMSC SMS-IWMSC SRF SS7 SSF SSP STM-1 STM-4 STP T TCAP TCO TOC TMSI U UDP UE UL UMTS URA USIM
Full Name
Operation & Maintenance Center Paging Channel Packet Data Protocol Programmable Logic Device Public Land Mobile Network Packet Over SDH Pre-Paid Service Packet Switched Public Switched Telephone Network Push To Talk Quality of Service Radio Access Bearer Remote Authentication Dial in User Service Radio Access Network Radio Access Network Application Part Radio Network controller Radio Resource Management Remote Radio Unit Signaling Connection and Control Part Service Control Point Signaling Control Transmission Protocol Service Data Function Synchronous Digital Hierarchy Serving GPRS Support Node Signaling Gateway Subscriber Identity Module Short Message Center (used for SMS) Short Message Service Center Short Message Service Gateway MSC Short Message Service Inter-working MSC Service Resource Function CCITT Signaling System No.7 Service Switching Function Service Switching Point SDH Transport Module -1 SDH Transport Module -4 Signalling Transfer Point Transaction Capability Application Part Total Cost of Ownership Top of Cabinet Temporary Mobile Subscriber Identifier User Datagram Protocol User Equipment Uplink Universal Mobile Telecommunications System User Registration Area UMTS Subscriber identity module
Vietnamobile Scenario 2000 Project
Huawei Confidential
Page 34 of 37
Abbreviation
UTRAN V VLR VMSC VPLMN W WAP
Full Name
UMTS Terrestrial Radio Access Network Visitor Location Register Visited Mobile Switching Center, Visited MSC Visited PLMN Wireless Application Protocol
Vietnamobile Scenario 2000 Project
Huawei Confidential
Page 35 of 37