Analisa Harga Satuan Pekerjaan Sanitasi Diposkan : 04 Juni 2014 Oleh : Endang Kusman
No. URAIAN
SAT VOLUME
HARGA SAT
HARGA
(Rp)
(Rp)
M01 1 Buah Closet jongkok Porselen Standar
Closet jongkok
bh
1.00
188,200.00
188,200.00
P.C (50 gk)
Kg
6.00
1,406.00
8,436.00
Pasir pasang
m3
0.01
233,400.00
2,334.00
Pekerja
org
1.0000
42,000.00
42,000.00
Tukang batu
org
1.5000
65,000.00
97,500.00
Kepala Tukang
org
1.5000
75,000.00
112,500.00
Mandor
org
0.1600
80,000.00
12,800.00
Jumlah
463,770.00
Dibulatkan
463,770.00
M02 1 Buah Urinoir
Urinoir
bh
1.00
1,773,400.00
1,773,400.00
P.C (50 gk)
Kg
6.00
1,406.00
8,436.00
Pasir pasang
m3
0.01
233,400.00
2,334.00
Pekerja
org
1.0000
42,000.00
42,000.00
Tukang batu
org
1.0000
65,000.00
65,000.00
Kepala Tukang
org
0.1000
75,000.00
7,500.00
Mandor
org
0.0010
80,000.00
80.00
Perlengkapan 30 % harga urinoir
lot
0.3000
1,773,400.00
532,020.00
Jumlah
2,430,770.00
Dibulatkan
2,430,770.00
M03 1 Buah Wastafel
wastafel standar
unit
1.00
1,012,700.00
1,012,700.00
P.C (50 gk)
Kg
6.00
1,406.00
8,436.00
Pasir pasang
m3
0.01
233,400.00
2,334.00
Pekerja
org
1.2000
42,000.00
50,400.00
Tukang batu
org
1.4500
65,000.00
94,250.00
Kepala Tukang
org
0.1500
75,000.00
11,250.00
http://www.softwarerab.com/analisahargasatuanpekerjaansanitasi.htm
1/7
5/28/2017
Analisa Harga Satuan Pekerjaan Sanitasi Software RAB
Mandor
org
0.1000
80,000.00
8,000.00
Perlengkapan 12 % harga wastafel
lot
0.1200
1,773,400.00
212,808.00
Jumlah
1,400,178.00
Dibulatkan
1,400,178.00
M04 1 Buah bak Mandi Fibreglass Volume 0,30 m3
Bak fibreglass 0.60m x 0.60m
bh
1.00
255,300.00
255,300.00
Pekerja
org
1.8000
42,000.00
75,600.00
Tukang batu
org
2.7000
65,000.00
175,500.00
Kepala Tukang
org
0.5400
75,000.00
40,500.00
Mandor
org
0.1100
80,000.00
8,800.00
Perlengkapan 18 % harga bak
lot
0.1800
255,300.00
45,954.00
Jumlah
601,654.00
Dibulatkan
601,654.00
M05 1 M' Saluran Air Limbah Buis beton d = 30 cm 60 cm
Buis beton Ø 30 cm
bh
1.10
61,700.00
67,870.00
Bata merah
bh
25.00
775.00
19,375.00
P.C (50 gk)
Kg
10.300
1,406.00
14,481.80
Pasir pasang
m3
0.061
233,400.00
14,237.40
Pasir urug
m3
0.069
175,300.00
12,095.70
Pekerja
org
0.3800
42,000.00
15,960.00
Tukang batu
org
0.1900
65,000.00
12,350.00
Kepala Tukang
org
0.0190
75,000.00
1,425.00
Mandor
org
0.0190
80,000.00
1,520.00
Jumlah
159,314.90
Dibulatkan
159,315.00
M06 1 Buah Bak Kontrol Pas Bata Merah Uk (60 x 60) cm
Bata merah
bh
186.00
775.00
144,150.00
P.C (50 gk)
Kg
114.000
1,406.00
160,284.00
Pasir pasang
m3
0.184
233,400.00
42,945.60
Batu pecah 2/3
m3
0.033
211,100.00
6,966.30
Besi beton
m3
4.850
16,500.00
80,025.00
Pasir beton
m3
0.120
255,400.00
30,648.00
Pekerja
org
2.1600
42,000.00
90,720.00
Tukang batu
org
0.7200
65,000.00
46,800.00
Kepala Tukang
org
0.0720
75,000.00
5,400.00
Mandor
org
0.1080
80,000.00
8,640.00
Tukang gali
org
0.1000
42,000.00
4,200.00
Jumlah
620,778.90
Dibulatkan
620,779.00
M07 1 Buah Bak Kontrol Pas Bata Merah Uk (30 x 30) cm
Bata merah
bh
53.00
775.00
41,075.00
P.C (50 gk)
Kg
44.000
1,406.00
61,864.00
Pasir pasang
m3
0.070
233,400.00
16,338.00
http://www.softwarerab.com/analisahargasatuanpekerjaansanitasi.htm
2/7
5/28/2017
Analisa Harga Satuan Pekerjaan Sanitasi Software RAB
Batu pecah 2/3
m3
0.070
211,100.00
14,777.00
Besi beton
m3
1.600
16,500.00
26,400.00
Pasir beton
m3
0.060
255,400.00
15,324.00
Pekerja
org
3.2000
42,000.00
134,400.00
Tukang batu
org
1.0150
65,000.00
65,975.00
Kepala Tukang
org
0.0015
75,000.00
112.50
Mandor
org
0.0160
80,000.00
1,280.00
Jumlah
377,545.50
Dibulatkan
377,546.00
M08 1 M' Pipa PVC Ø 1/2" (AW)
Pipa pvc Ø 1/2"
m'
1.2000
10,025.00
12,030.00
Pekerja
org
0.0360
42,000.00
1,512.00
Tukang batu
org
0.0600
65,000.00
3,900.00
Kepala Tukang
org
0.0060
75,000.00
450.00
Mandor
org
0.0018
80,000.00
144.00
Perlengkapan 35 % harga pipa
lot
0.3500
12,030.00
4,210.50
Jumlah
22,246.50
Dibulatkan
22,247.00
M09 1 M' Pipa PVC Ø 1" (AW)
Pipa pvc Ø 1"
m'
1.2000
15,800.00
18,960.00
Pekerja
org
0.0360
42,000.00
1,512.00
Tukang batu
org
0.0600
65,000.00
3,900.00
Kepala Tukang
org
0.0060
75,000.00
450.00
Mandor
org
0.0018
80,000.00
144.00
Perlengkapan 35 % harga pipa
lot
0.3500
18,960.00
6,636.00
Jumlah
31,602.00
Dibulatkan
31,602.00
M10 1 M' Pipa PVC Ø 11/2" (AW)
Pipa pvc Ø 11/2"
m'
1.2000
26,475.00
31,770.00
Pekerja
org
0.0360
42,000.00
1,512.00
Tukang batu
org
0.0600
65,000.00
3,900.00
Kepala Tukang
org
0.0060
75,000.00
450.00
Mandor
org
0.0018
80,000.00
144.00
Perlengkapan 35 % harga pipa
lot
0.3500
31,770.00
11,119.50
Jumlah
48,895.50
Dibulatkan
48,896.00
M11 1 M' Pipa PVC Ø 2" (AW)
Pipa pvc Ø 2"
m'
1.2000
27,675.00
33,210.00
Pekerja
org
0.0360
42,000.00
1,512.00
Tukang batu
org
0.0600
65,000.00
3,900.00
Kepala Tukang
org
0.0060
75,000.00
450.00
Mandor
org
0.0018
80,000.00
144.00
Perlengkapan 35 % harga pipa
lot
0.3500
31,770.00
11,119.50
http://www.softwarerab.com/analisahargasatuanpekerjaansanitasi.htm
3/7
5/28/2017
Analisa Harga Satuan Pekerjaan Sanitasi Software RAB
Jumlah
50,335.50
Dibulatkan
50,336.00
M12 1 M' Pipa PVC Ø 4" (AW)
Pipa pvc Ø 4"
m'
1.2000
86,975.00
104,370.00
Pekerja
org
0.0810
42,000.00
3,402.00
Tukang batu
org
0.1350
65,000.00
8,775.00
Kepala Tukang
org
0.0135
75,000.00
1,012.50
Mandor
org
0.0041
80,000.00
328.00
Perlengkapan 35 % harga pipa
lot
0.3500
104,370.00
36,529.50
Jumlah
154,417.00
Dibulatkan
154,417.00
M13 1 M' Pipa PVC Ø 3/4" (AW)
Pipa pvc Ø 3/4"
m'
1.2000
13,050.00
15,660.00
Pekerja
org
0.0810
42,000.00
3,402.00
Tukang batu
org
0.1350
65,000.00
8,775.00
Kepala Tukang
org
0.0135
75,000.00
1,012.50
Mandor
org
0.0041
80,000.00
328.00
Perlengkapan 35 % harga pipa
lot
0.3500
15,660.00
5,481.00
Jumlah
34,658.50
Dibulatkan
34,659.00
M14 1 Buah Bak Cuci piring Stainless steel
Bak cuci stainless steel + asesoris
bh
1.0000
397,800.00
397,800.00
Pekerja
org
0.0300
42,000.00
1,260.00
Tukang batu
org
0.3000
65,000.00
19,500.00
Kepala Tukang
org
0.0300
75,000.00
2,250.00
Mandor
org
0.0015
80,000.00
120.00
Jumlah
420,930.00
Dibulatkan
420,930.00
lengkap
M15 1 Buah Kran Ø 1/2" 3/4"
Kran air
bh
1.0000
40,900.00
40,900.00
Seal tape
bh
0.0250
4,200.00
105.00
Pekerja
org
0.0100
42,000.00
420.00
Tukang batu
org
0.1000
65,000.00
6,500.00
Kepala Tukang
org
0.0100
75,000.00
750.00
Mandor
org
0.0050
80,000.00
400.00
Jumlah
49,075.00
Dibulatkan
49,075.00
M16 1 Buah Floor Drain
Floor drain
bh
1.0000
66,600.00
66,600.00
Pekerja
org
0.0100
42,000.00
420.00
Tukang batu
org
0.1000
65,000.00
6,500.00
Kepala Tukang
org
0.0100
75,000.00
750.00
http://www.softwarerab.com/analisahargasatuanpekerjaansanitasi.htm
4/7
5/28/2017
Analisa Harga Satuan Pekerjaan Sanitasi Software RAB
Mandor
org
0.0050
80,000.00
400.00
Jumlah
74,670.00
Dibulatkan
74,670.00
M17 1 M' Grafel beton U 20 cm 60 cm
Pipa beton U
bh
1.1000
44,300.00
48,730.00
Bata merah
bh
12.0000
775.00
9,300.00
P.C (50 gk)
zak
0.1030
1,406.00
144.82
Pasir pasang
m3
0.0305
233,400.00
7,118.70
Pasir urug
m3
0.0345
175,300.00
6,047.85
Pekerja
org
0.0100
42,000.00
420.00
Tukang batu
org
0.1000
65,000.00
6,500.00
Kepala Tukang
org
0.0100
75,000.00
750.00
Mandor
org
0.0050
80,000.00
400.00
Jumlah
79,411.37
Dibulatkan
79,411.00
M18 1 M' Pasang Talang Plastik PVC U 15 cm (AW)
Talang plastik PVC
m'
1.05000
60,000.00
63,000.00
Perlengkapan 35 % harga talang
lot
0.3500
63,000.00
22,050.00
Pekerja
org
0.1500
42,000.00
6,300.00
Tukang batu
org
0.4000
65,000.00
26,000.00
Kepala Tukang
org
0.0250
75,000.00
1,875.00
Mandor
org
0.0013
80,000.00
100.00
Jumlah
119,325.00
Dibulatkan
119,325.00
M19 1 M' Saluran Air Limbah Buis Beton Ø 60 cm
Buis beton Ø 60 cm
bh
1.10
130,900.00
143,990.00
Bata merah
bh
25.00
775.00
19,375.00
P.C (50 gk)
zak
0.206
1,406.00
289.64
Pasir pasang
m3
0.061
233,400.00
14,237.40
Pasir urug
m3
0.069
175,300.00
12,095.70
Pekerja
org
0.3800
42,000.00
15,960.00
Tukang batu
org
0.1900
65,000.00
12,350.00
Kepala Tukang
org
0.0190
75,000.00
1,425.00
Mandor
org
0.0190
80,000.00
1,520.00
Jumlah
221,242.74
Dibulatkan
221,243.00
M20 1 M' Pasang Talang Seng Datar
Seng pelat 3" x 6"
lbr
0.50000
20,801.00
10,400.50
Paku
kg
0.01500
23,400.00
351.00
Kayu kelas II
m3
0.00960
2,850,000.00
27,360.00
Meni besi
kg
0.2500
30,400.00
7,600.00
Pekerja
org
0.1500
42,000.00
6,300.00
Tukang batu
org
0.4000
65,000.00
26,000.00
http://www.softwarerab.com/analisahargasatuanpekerjaansanitasi.htm
5/7
5/28/2017
Analisa Harga Satuan Pekerjaan Sanitasi Software RAB
Kepala Tukang
org
0.0250
75,000.00
1,875.00
Mandor
org
0.0013
80,000.00
100.00
Jumlah
79,986.50
Dibulatkan
79,987.00
M21 1 Buah Closet Duduk
Closet duduk
bh
1.00
1,724,700.00
1,724,700.00
Pekerja
org
3.3000
42,000.00
138,600.00
Tukang batu
org
1.1000
65,000.00
71,500.00
Kepala Tukang
org
0.0010
75,000.00
75.00
Mandor
org
0.1600
80,000.00
12,800.00
Perlengkapan 6 % harga closet
lot
0.0600
1,724,700.00
103,482.00
Jumlah
2,051,157.00
Dibulatkan
2,051,157.00
M22 1 Buah Tangki Air fibreglass Volume 1 m3
Bak fibreglass kapasitas 1 m3
bh
1.00
1,316,400.00
1,316,400.00
Pekerja
org
3.3000
42,000.00
138,600.00
Tukang batu
org
1.1000
65,000.00
71,500.00
Kepala Tukang
org
0.0010
75,000.00
75.00
Mandor
org
0.1600
80,000.00
12,800.00
Perlengkapan 6 % harga bak
lot
0.0600
1,316,400.00
78,984.00
Jumlah
1,618,359.00
Dibulatkan
1,618,359.00
M23 1 Unit Septictank 2x1,50x1,50 m + Rembesan
Galian tanah
m3
4.500
26,252.00
118,134.00
Pasir urug
m3
0.214
175,300.00
37,514.20
lantai kerja
m3
2.250
716,798.00
1,612,795.50
Pas bata adk 1pc : 3ps
m2
15.000
220,267.10
3,304,006.50
Pelat beton K225
m3
0.300
6,438,864.00
1,931,659.20
Plesteran adk 1pc : 3ps
m2
15.000
41,301.82
619,527.30
Pipa PVC 4" jenis AW
m'
5.400
256,800.00
1,386,720.00
Pipa GIP 1 1/2"
m'
5.000
46,750.00
233,750.00
Galian tanah untuk rembesan
m3
3.375
20,000.00
67,500.00
Pas ijuk
kg
5.400
23,400.00
126,360.00
Urugan kerikil 3/5
m3
1.050
205,000.00
215,250.00
Pipa PVC 4" berlubang jenis AW
m'
9.000
36,700.00
330,300.00
Urugan dan perataan tanah
m3
1.125
34,584.00
38,907.00
Jumlah
10,022,423.70
Dibulatkan
10,022,424.00
M24 1 Unit Septictank 1x1,50x1,50 m + Rembesan
Galian tanah
m3
2.250
20,000.00
45,000.00
Pasir urug
m3
0.107
175,300.00
18,757.10
lantai kerja
m3
1.125
716,798.00
806,397.75
Pas bata adk 1pc : 3ps
m2
7.500
220,267.10
1,652,003.25
http://www.softwarerab.com/analisahargasatuanpekerjaansanitasi.htm
6/7
5/28/2017
Analisa Harga Satuan Pekerjaan Sanitasi Software RAB
Pelat beton K225
m3
0.150
6,438,864.00
965,829.60
Plesteran adk 1pc : 3ps
m2
7.500
41,301.82
309,763.65
Pipa PVC 4" jenis AW
m'
9.000
256,800.00
2,311,200.00
Pipa GIP 1 1/2"
m'
2.500
46,750.00
116,875.00
Galian tanah untuk rembesan
m3
1.688
20,000.00
33,760.00
Pas ijuk
kg
2.700
23,400.00
63,180.00
Urugan kerikil 3/5
m3
0.525
205,000.00
107,625.00
Pipa PVC 4" berlubang jenis AW
m'
9.000
36,700.00
330,300.00
Urugan dan perataan tanah
m3
0.563
34,584.00
19,470.79
Jumlah
6,780,162.14
Dibulatkan
6,780,162.00
Kembali ke Analisa SNI
Copyright © 2015 Software RAB Rumah | XHTML | G1 | G2 | Valid RSS | Privacy Policy | Disclaimer | Contact
www.softwarerab.com
http://www.softwarerab.com/analisahargasatuanpekerjaansanitasi.htm
7/7