Vol. 2 Trading Operations in the Philippine WESM AUGUST 2015
WESM Handbook
A Guide to All Members and Applicants of the Philippine Wholesale Electricity Spot Market (WESM)
The Philippine Electricity Market Corporation (PEMC) provides this document (the “Document”) for general information purposes only. The information contained in this Document is correct to the best of PEMC’s knowledge at the time of publishing but may change over time. The Document is reviewed and updated from time to time. If you have further inquiries regarding this Document, please contact PEMC’s Participant Support Section via e-mail at
[email protected], or through telephone at (+632) 631.8734 loc. 229/239. Disclaimer/Waiver: All information in this document may still be subject to change after final verification by the PEMC. This publication is meant to provide a timely overview of the trading operations in the WESM. As such, PEMC does not make any representation or warranties as to the completeness or accuracy of the information. PEMC, likewise, accepts no responsibility or liability whatsoever, for any loss or costs incurred by the reader arising from, or in relation to, any contributions or assumptions derived from the information.
Editorial Team
CONTRIBUTORS
Phillip C. Adviento Josephine C. Corpuz Cerise M. Cabactulan Eric Niño U. Louis Menachem Reykarl B. Loyola Katrina A. Garcia-Amuyot Daisy Jane C. Alfafara Arnesh Y. Inostro Theresse Joy V. Calo
Edwin N. Mosa Arthur P. Pintado Edward I. Olmedo
Layout Artist Rhlee B. Amojilar
Adviser Robinson P. Descanzo
Table of contents
WESM Operations
2
Introduction
2
Scheduling and Dispatch in the WESM
2
WESM Timetable
4
During Normal Conditions
7
During Emergency Conditions
7
Sample Cases of Market Interventions
8
Market Suspension
9
Sample Normal Dispatch Process
9
Load Forecasting
10
Introduction
10
Demand Forecasting for Market Projections
11
Demand Forecast for the Real-time Dispatch Runs
12
Operational Market Reports
13
Introduction
13
Procedure
13
Daily Operation Reports
15
Market Participant Interface
17
Scheduling and Pricing
19
WESM OPERATIONS
INTRODUCTION • • •
A clear definition and delineation of responsibilities are necessary to ensure the reliable operation of the grid, especially with the Market Operator (MO) and the System Operator (SO) being two separate entities. As a result, the WESM Manual on the Dispatch Protocol was formulated after rigorous discussions between MO and SO. The Dispatch Protocol ○○ Clearly establishes the WESM Timetable for the execution of specific processes (WESM Rules 3.4.2 and 10.4.8.1) ○○ Establish scheduling and dispatch procedures to be followed in -- Normal Conditions -- Emergency Conditions that should be consistent with the WESM Timetable and features of the MMS
Scheduling and Dispatch in the WESM • • • •
WESM was established as the trading platform of energy transactions. WESM was also established as the central platform for the dispatch scheduling of generating facilities. SO is still responsible in the dispatch of generating units at real-time. MO has the responsibility of forecasting demand, and prepares a Security Constrained Economic Dispatch (SCED) schedule of generators and loads based on the hourly demand bids and generation offers. ○○ MO also maintains a Market Network Model (MNM) which shall be used by the Market Dispatch Optimization Model (MDOM), which shall be able to consider transmission constraints and losses.
Responsibilities in WESM’s Scheduling and Dispatch The MO, SO, and Trading Participants (TPs) are the three entities involved in the scheduling and dispatch of generating facilities in WESM MO Responsibilities in Scheduling and Dispatch • • •
2 2
Maintenance of the MNM in coordination with the SO Generation of dispatch schedules using the MDOM Transmittal of dispatch schedules to the SO for implementation
SO Responsibilities in Scheduling and Dispatch •
• •
Submission of overriding constraints to ensure the reliable operation of the grid ○○ Outage Schedule - List of Equipment (e.g. generators, lines, transformers, breakers, etc.) that will be out of service for a certain defined period. ○○ Contingency List - List of Equipment enlisted for contingency analysis (as per Grid Code: N-1 Contingency Requirement). ○○ Security Limits - List of Generators and Branch Groups that will have its limits overridden for security purposes (e.g. MRU/testing/commissioning). ○○ Transmission Limits - list of transmission capacities of lines and transformers to be consider in the scheduling process Implementation of the dispatch schedules provided by MO Issuance of deviation report to MO (actual vs. schedule)
TP Responsibilities in Scheduling and Dispatch • •
Submission of bids and offers to WESM consistent with the WESM Timetable Comply to the dispatch instructions of SO Figure 1. Scheduling and Dispatch in the WESM
3 3
WESM Timetable •
Trading activities in WESM operate at different time frames ○○ Week Ahead Projection (WAP) ○○ Day Ahead Projection (DAP) ○○ Hour-Ahead or Real-Time Dispatch (RTD) ○○ Real-Time Ex-post (RTX)
WESM Timetable: WAP •
The Week-Ahead Projection (WAP) gives indicative hourly dispatch schedules and spot prices for the next seven days. • Its results serve as a guide to the following entities: ○○ Participants when bidding transactions in the market for the next seven days ○○ SO in the determination of the cost impact of planned outages • It considers the following information, which shall be used by the Market Management System (MMS) to generate schedules: ○○ Demand bids and energy offers from Trading Participants ○○ Demand forecasts ○○ Outage Schedules ○○ Security Limits ○○ Latest available system snapshot • WAP executed every day today produce results for theresults next seven days. WAP is isexecuted every to produce for the next seven days
WESM timetable: WAP
•
Figure 2. WESM Timetable: WAP Execution of WAP at Day D
D-1
•
D
D+1
Study Period of WAP at Day D (From D+1 to D+7) D+2 D+3timetable: D+4 D+5 D+6WAP D+7 WESM
D+8
D+9
TRADING DAYS
WAP at 0900H each • WAPis is executed executed at 0900H of each of trading day trading
day
trAdiNG dAyS …
4
5
6
7
Prior to 0900H, the following activities are made for D+1 to D+7 • Gathering of weather forecasts • Preparation of demand forecasts • Submission or revision of bids and offers
4 4
8
9
10
11
12
13
14
15
WAP Results and Analysis Coordination with SO WAP Execution
16
17
18
19
…
Basic WESM 2014
Publish WAP Results in WEB The latest information provided by SO prior to 0900H shall be used • System Snapshot • Outage Schedule • Security Limit • Transmission Limit • Contingency List Basic WESM 2014
WESM Timetable: DAP • • •
•
•
The Day-Ahead Projection (DAP) gives indicative hourly dispatch schedules and spot prices covering the succeeding hours of the day up to the end of the following day. It allows the SO to prepare a more accurate contingency plan for the relevant intervals. It considers the following information, which shall be used by the Market Management System (MMS) to generate schedules ○○ Demand bids and energy offers from Trading Participants ○○ Revisions of bids and offers for consideration in the DAP run can be done until a cut-off time (four hours prior to the trading hour) ○○ Demand forecasts ○○ Outage Schedules ○○ Security Limits ○○ Latest available system snapshot DAP is executed every four hours to produce results for the succeeding hours until the end of the following day.
WESM timetable: dAP
DAP is executed every four hours to produce results for the succeeding hours until the end of the Figure 3. WESM Timetable: DAP following day trAdiNG dAyS …
4
5
6
7
8
0800H DAP
0400H DAP
DAP Results Analysis Coordination with SO
9
10
11
12
13
14
1200H DAP
15
16
17
18
19
…
1600H DAP
DAP Results Analysis Coordination with SO is done up until 1 hour after the DAP execution
• The latest information provided by SO prior to each DAP run shall be used • The latest bids and offers shall be used. Submission or revision of bids and offers relevant to the succeeding hours can be made prior to the execution of the DAP run. • Demand forecasts for each of the succeeding hours evaluated by the DAP run should be provided prior to its execution. Revisions may still be implemented prior to the DAP run
•
DAP Study Period
Basic WESM 2014
Table 1. DAP Study Period Study Horizon
DAP Run at Current Day “D”
From
To
0400H
0500H of D
2400H of D
0800H
0900H of D
2400H of D
1200H
1300H of D
2400H of D+1
1600H
1700H of D
2400H of D+1
2000H
2100H of D
2400H of D+1
2400H
0100H of D+1
2400H of D+1
5 5
WESM Timetable: RTD • • • •
The Hour-Ahead or Real-Time Dispatch (RTD) publishes schedules that shall be implemented by SO, and spot prices that shall be used in the settlement of market transactions. The RTD schedules are subject to the final screening of SO before a dispatch instruction is issued to a Trading Participant. The dispatch schedule is the target MW loading of all Trading Participants at the end of a trading interval. RTD is executed every 55th minute of the hour.
WESM timetable: rtd
•
RTD is executed every 55th minute of the hour
Figure 4. WESM Timetable: RTD RTD Execution for Trading Hour HH
The latest information provided by SO prior to each RTD run shall be used Gate Closure for bids and offers
40
50
00
10
20
Trading Interval HH
30
HH-2 • •
Trading Interval HH
40
50
0
0
10
20
30
HH-1
40
50
00
10
HH
Transmit RTD Schedules and MOT to SO Publish results in WEB
20
30
40
HH+1
Dispatch Implementation for HH to meet Target Schedule Basic WESM 2014
WESM Timetable: RTX • • • •
The Real-Time Ex-Post (RTX) represents the duration of the trading interval. It is not used by the SO in the dispatch implementation since it is merely used for “price discovery”, in which its results represent the actual events that transpired for the duration of the trading interval Its results are used to settle imbalances in the market (schedule vs. actual) RTX is executed every 1st minute of the hour
•
WESM timetable: rtX
RTD is executed every 55th minute of the hour Figure 5. WESM Timetable: RTX RTX Execution for Trading Hour HH
The latest information provided by SO prior to each RTX run shall be used
Trading Interval HH
40
50 HH-2
6 6
00
10
20
30
40 HH-1
50
0
0
10
20
30
40
HH
50
00
10
20
30
HH+1
Basic WESM 2014
40
During Normal Conditions Majority of the day-to-day activities in the market fall under the category of normal conditions Table 2. WESM Tasks During Normal System Conditions Procedure in the Dispatch Protocol
Activities
Responsible Group MO
SO
Bids and Offers
Appendix A.1
x
Demand Forecasting
Appendix A.2
x
Outage Scheduling
Appendix A.3
x
Contingency Planning
Appendix A.4
x
Pre-Dispatch Market Projections
Appendix A.5
x
Real-Time Dispatch Schedule
Appendix A.6
x
Dispatch Implementation
Appendix A.7
x
System Status Report
Appendix A.8
x
Post Dispatch Report
Appendix A.9
x
Market Information Publication
Appendix A.10
x
Daily Operational Report
Appendix A.11
x
x
During Emergency Conditions •
WESM Rules 6.3.1.1 states that an emergency condition is a situation which has an adverse effect on electricity supply or which poses a significant threat to system security Table 3. Clasification of Emergency Events Activities Procedure in the Dispatch Protocol Market Failure
MMS Failure
System Operations SO
MO
Medium-term supply deficiency
Communication network Breakdown
Total system Collapse
Communication network Breakdown
Effects of force majeure events
Computer systems failure
Grid Islanding or Isolation
Computer systems failure
Site-related Emergencies
Multiple forced Outages
Site-related Emergencies
Threat to system Security
7 7
•
WESM Rules 6.3.1.1 states that an emergency condition is a situation which has an adverse effect on electricity supply or which poses a significant threat to system security Table 4. WESM Tasks During Emergency System Conditions Procedure in the Dispatch Protocol
Activities
Responsible Group MO
SO x
System Emergency and Restoration
--
x
Market Suspension and Intervention
Appendix B.2
x
EMS Disaster Recovery Procedures
--
MMS Disaster Recovery Procedures
--
x
Report and Documentation of Events
--
x
x
x
Sample Cases of Market Intervention (06 February 2012: 1200H to 1400H)
Figure 6. Sample Case: Market Intervention
Emergency – Market intervention was declared due to tripping of several power plants affected by magnitude 6.9 earthquake in the Visayas Region. The intervention was initiated by the Visayas System Operator. The Market Intervention Report prepared by the National Grid Corporation of the Philippines (NGCP) is attached. (WESM Rules clause 6.3.1.2 (c))
8 8
Market Suspension (14 July 2010)
Figure 7. Sample Case: Market Suspension
Pursuant thereto and by reason of the power system disturbance brought by typhoon “BASYANG”, the commission has suspended the operations of the WESM effective on 14 July 2010 at 1200H, as contained in the notice of Market Suspension issued by this commission which is attached hereto and made an integral part hereof as Annex A
Sample Normal Dispatch Process
FOR THE 0900H TARGET TRADING INTERVAL (08:01 AM UNTIL 09:00 AM) Figure 8. Sample Normal Dispatch Process
FOR THE 0900H TARGET TRADING INTERVAL (08:01 AM UNTIL 09:00 AM)
9 9
LOAD FORECASTING
INTRODUCTION Forecasting is a process of predicting market condition using historical data. In the WESM, we predict the energy to be consumed in a certain area for a specific trading interval incorporating historical data, real time grid system status, weather condition and events.This process is known as Load Forecasting. The provision of load demand is necessary for the calculation of market prices and dispatch schedules. It is an integral requirement of the market dispatch optimization model. The WESM Rules provide the calculation of market projections and real-time schedules which require accurate load demand forecast information. The load forecasting in the market has three time frames; namely hour-ahead, day-ahead and week-ahead forecasting. Hour-Ahead Forecast The process of forecasting the load energy demand for next top of the hour. It is conducted every hour and uses the latest real time grid system status, weather condition and events. The Ex-ante (Real-Time Dispatch or RTD) utilizes this forecast. Day-Ahead Forecast The process of forecasting the load energy demand for the next day and is being updated every four hours to accurately reflect the near real time load energy demand. The Day-Ahead Projection (DAP) utilizes this forecast. Week-Ahead Forecast The process of forecasting the load energy demand for the next seven days. It is being updated daily. The forecast output is an indicative figure for Market Participant bidding strategy and generator maintenance scheduling. The Week-Ahead Projection (WAP) utilizes this forecast.
10 10
DEMAND FORECAST FOR MARKET PROJECTIONS Week-Ahead and Day-Ahead Demand Forecasts •
Hourly Demand Forecasts for each Forecast Area from the current day to the next seven days shall be determined by the Market Operator using the Similar Day Load Forecast (SDLF) module of the Market Management System (MMS).
•
The Demand Forecasts obtained in the week ahead forecast shall be used as Input Demand Forecasts to obtain the WAP and the DAP.
•
The summation of the Net Load Forecast plus the losses computed for a Forecast Area after the optimization process in the relevant market run (i.e. WAP or DAP) constitutes the Final Demand Forecast for that Forecast Area.
Figure 9. SDLF Methodology Load Forecasting
11 11
DEMAND FORECAST FOR THE REAL-TIME DISPATCH RUNS
Hour-Ahead Forecasts •
Demand Forecasts for the next hour in each Forecast Area shall be determined by the Market Operator using the Load Predictor (LDP) module of the Market Management System.
•
The Demand Forecasts obtained in the hour-ahead forecast shall be used as Input Demand Forecasts to obtain the Real-Time Dispatch (RTD).
•
The summation of the Net Load Forecast plus the losses computed for a Forecast Area after the optimization process in the relevant RTD run constitutes the Final Demand Forecast for that Forecasted Area.
Figure 10. LDP Methodology Load Forecasting
12 12
Operational Market Reports
INTRODUCTION The Market Operator (MO) regularly publishes operational market reports to the public required by the WESM Rules in accordance with the WESM Timetable. Using a web-based report system, operational market reports are easily made available online to the trading participants and the general public.
PROCEDURE Market Participant Interface (MPI) Registered Trading Participants (TPs) shall have access to the Market Management System (MMS) or WESM through a Market Participant Interface (MPI). The MPI is connected to the MMS through the worldwide web. The MPI shall be used by all TPs to bid and retrieve market information from the WESM-MMS. The MPI may be accessed through: www.mms.wesm.ph •
Information to be Published ○○ System Messages The System Messages display is the primary link between the Trading Participant and the WESM Market Operator. The TP is notified of all kinds of system events such as report publication and availability, market suspension or re-activation, and the like. System Messages are classified as: ----
Normal: These are generally system-generated messages displayed in GREEN Urgent: Urgent Messages are displayed in BLUE Emergency: Emergency Messages are displayed in RED
○○ Market Status Display The Market Status Display shows the status of Hourly Energy Markets e.g. if the Market is still Open or had already Closed. ○○ Market Participant Interface Data Using MPI, the Trading Participants will be able to access the following information: ---------
Market Participant Registration Bids and Offers Data Market and System Advisories Updates on Market Prices, Dispatch and Pre-dispatch schedules Demand Forecasts Real-Time Ex-post (RTX) Prices Market Participant Specific, All Market Participants, and ADHOC Reports Settlement (Prudential Requirements)
13 13
WESM Website The WESM website contains technical information on the WESM as well as all recent WESM development and announcements. The WESM website is: www.wesm.ph •
Information to be Published All Market information required to be published by the Market Operator under the WESM rules shall be made accessible to the WESM members, DOE, ERC and the general public through the WESM website. Access to the Market information other than the WESM website shall be the responsibility of the parties concerned. ○○ Systems and Procedures The following are standard operating procedures that are to be observed during WESM operation: ------
WESM Timetable WESM Operating Procedures during Normal System Condition Emergency Procedures jointly developed by System Operator and Market Operator. Detailed procedures developed by the System Operator in relation tocompetitive tendering process for Ancillary Services. Dispatch and pricing procedures in the event of load shedding and excess generation developed in consultation with the System Operator.
○○ Other WESM Reports The following are the relevant reports that are to be prepared as required by the different provisions of the WESM rules: ----
14 14
Findings and recommendation of the PEM auditor regarding changes in WESM rules consequent to annual audit, review, check, or otherforms of review. Suspension notice issued to a WESM participant. It shall also be published in a newspaper of general circulation, as soon as practicable. Revocation of suspension issued to a WESM Participant. It shall also be published in a newspaper of general circulation, as soon as practicable.
Operational Market Reports DAILY OPERATIONS REPORT The Market Operator shall closely monitor Market Operations on an hourly basis within the trading day. Likewise, the MO shall record and verify all significant events that are not recorded in the MMS. The MODOR shall be reviewed and approved by the Operations Unit Head. At the end of every trading day, the Market Operator shall prepare a report containing the summary of its operations on an hourly basis of the previous day which includes the contents of the Post Dispatch Report. The following are the daily Operations report being published by the Market Operator: WESM WEB SITE (https://www.wesm.ph) • • • • • • • •
WAP_DAY_LUZON WAP_DAY_VISAYAS NEXT_DAY_LUZON NEXT_DAY_VISAYAS PREVIOUS_DAY_LUZON PREVIOUS_DAY_VISAYAS RTD Marginal Plant RTX Marginal Plant
Market Participant Interface (MPI) • • • • •
RTD OUTAGE SCHEDULE RTX OUTAGE SCHEDULE PEN REPORT DAP Pmin PSM REPORT-Hourly Price Substitution occurrence if any for RTD and RTX
Next Week Summary (NWS) A summary of the results of WESM´s Week-Ahead Projection (WAP). The Next Week Summary (NWS) report contains a daily summary of the following results for each of the trading days included in the relevant WAP workflow run. 1. 2. 3. 4.
Demand and Reserve Requirement Market Participant Bids and Offers Summary Energy and Reserve Schedules Market Price Summary
The WAP is executed daily to project the hourly results for the next seven days (e.g. Monday WAP run contains hourly results from the next day (Tuesday) up to the following Monday).
15 15
Next Day Summary (NDS) A summary of the results of WESM´s Day-Ahead Projection (DAP). The NDS report contains a summary of the following results projected for the following day as obtained in the relevant DAP workflow run. 1. 2. 3. 4.
Demand and Reserve Requirement Market Participant Bids and Offers Summary Energy and Reserve Schedules Market Price Summary
The DAP is executed every four hours to project the hourly results from the next hour of the same day, up until the end study period of a particular run (some DAP runs end at 2400H of the same day while other DAP runs end at 2400H of the next day). The following table shows the study periods of the different DAP runs. Table 5. DAP Runs DAP RUN
FROM
TO
0400H
0500H of DAY ´D´
2400H of DAY ´D´
0800H
0900H of DAY ´D´
2400H of DAY ´D´
1200H
1300H of DAY ´D´
2400H of DAY ´D+1´
1600H
1700H of DAY ´D´
2400H of DAY ´D+1´
2000H
2100H of DAY ´D´
2400H of DAY ´D+1´
2400H
0100H of DAY ´D+1´
2400H of DAY ´D+1´
Previous Day Summary A summary of the results of WESM´s Hour-Ahead or Real-Time Dispatch (RTD) and Real-Time Ex-Post (RTX) The Previous Day Summary (PDS) report contains a summary of the following results that transpired during the previous day involving the RTD and RTX workflows in the market. 1. 2. 3. 4.
Demand and Reserve Requirement Market Participant Bids and Offers Summary Energy and Reserve Schedules Market Price Summary
The information contained herein are those obtained at real-time for the RTD and RTX workflows, and it does not reflect any pricing corrections that may be involved in cases of pricing errors. The Market Operator regularly publishes market reports to the public that contains a summary of the market´s results, primarily involving the RTD and RTX.
16 16
Operational Market Reports Marginal Plants The Marginal Plant (MP) data presents information on the hourly Marginal Plants and their corresponding price offers in the market. The MP is the generating unit or plant whose price offer corresponds to the system marginal price for a given trading interval. In an unconstrained system, the market price is set by one MP (i.e., the system marginal price). This price is adjusted for each node to consider transmission losses and/or congestion costs to come up with a resulting value called the Locational Marginal Price (LMP). Where the system is constrained, the relevant flows of electricity are affected as the line limitations arising from the congestion may impede the supply of cheaper electricity from one area to another. In such cases, there may be more than one MP setting the marginal price for the different nodes on either side of the constraint. Available Market Data in the WESM Website The following list shows a variety of market information made available to the general public in the WESM public website. 1. Market Bids and Offers 2. Market Prices and Schedules 3. Ex-ante and Ex-post LWAP 4. Market Re-Run Results 5. Marginal Plants 6. Administered Price 7. HVDC Schedule 8. Net Settlement Surplus 9. Must-Run Unit Generation Price Index 10. Price Substitution Methodology for Congestion 11. Daily PEN-MRR-PSM-AP Summary 12. Final Market Prices
MARKET PARTICIPANT INTERFACE The results of the Real Time Dispatch (RTD and RTX) shall be published in the Market Participant Interface (MPI). The following information shall be published (for each Resource of a Trading Participant) Table 6. RTD & RTX Results Published in the MPI Information
RTD
RTX
Energy
Dispatch Target
Actual Energy / Delivered / Consumed
Nodal Price
Ex-Ante Price
Ex-Post Price
Other system data that will be published includes the following: • • • •
Total energy dispatched Total dispatchable load Total system losses Locational Marginal Prices 17 17
Publication of Results The results of the Real Time Dispatch shall be published in accordance with the WESM timetable. The results of the Real Time Dispatch shall be published in the Market Participant Interface (MPI) and correspondingly submitted to the System Operator on the following schedules: Table 7. RTD & RTX Results Schedule in the MPI Process
Study Horizon
Execution Frequency
RTD Results Publication
1 Hour-ahead
Hourly, at the start of Trading Interval
RTX Results Publication
24 Hours of the previous Day
1200H of the following Day
RTD Outage Schedule The RTD Outage Schedule data presents information on the hourly Outage Schedules for the RTD run for the 24-hour interval within a trading day. RTX Outage Schedule The RTX Outage Schedule data presents information on the hourly Outage Schedules for the RTX run for the 24-hour interval within a trading day. PEN Report The PEN Report data presents information on the summary of all the Pricing Error Notice (PEN) issued within the trading day. DAP Pmin The DAP Pmin data presents information on the computation of the total Pmin of the generators resulted from the 1600H DAP run of the trading Day. It aims to see whether there shall be a possibility of an over generation for the next trading day. PSM Report The PSM Report data presents information on the hourly price substitution occurrence if any for RTD and RTX.
18 18
SCHEDULING OperationalAND Market PRICING Reports
Scheduling and Dispatch upon Establishment of WESM Operations •
WESM was established as the central trading platform for the scheduling, dispatch, and net settlement of generating facilities and loads in grids with WESM operations.
•
The Market Operator (MO), System Operator (SO), and Trading Participants (TPs) are the three entities involved in the scheduling and dispatch of generating facilities in WESM.
•
The SO is responsible for the dispatch of generating units at real-time.
•
The MO has the responsibility of forecasting demand and the scheduling of generators and loads based on hourly generation offers and demand bids through a Security-Constrained Economic Dispatch (SCED). ○○ The SCED of generators and loads are obtained using WESM’s MDOM, which utilizes the MNM maintained by the MO. As such, pricing and scheduling calculations are able to consider transmission losses and constraints.
•
TPs are responsible for the following: ○○ Submission of generation offers and/or demand bids. ○○ Comply with the dispatch instructions.
19 19
USEFUL CONTACTS Philippine Electricity Market Corporation Participant Support Section 9F Robinsons Equitable Tower, ADB Avenue Ortigas Center, Pasig City, Philippines 1600 Tel. No.: (+632) 631.8734 loc. 239 / 229 / 220 / 302 Facsimile: (+632) 636.0802 / 634.0985 Email:
[email protected]
Department of Energy DOE Information Center Information Technology & Management Services Energy Center, Merritt Road Fort Bonifacio, Taguig, Philippines 1201 Tel. No.: (+632) 840.2120 Email:
[email protected] National Electrification Administration 57 NEA Building, NIA Road, Government Center Diliman, Quezon City, Philippines 1001 Tel No.: (+632) 929.1909 local 124 Facsimile: (+632) 929.2171
National Grid Corporation of the Philippines Quezon Avenue corner BIR Road Diliman, Quezon City, Philippines Trunk-line (connecting all Departments): (+632) 981.2100
Energy Regulatory Commission Pacific Center Building, San Miguel Avenue Ortigas Center, Pasig City, Metro Manila, Philippines 1600 Tel. No.: (+632) 914.5000 local 114 Facsimile: (+632) 631.5816 Email:
[email protected]