UPDA Exam Questions for Civil Engineers 2016 d) All of above
15.Example 15. Example for sedimentary rock? -
Sand stone
16.Moister 16. Moister content of timber used in building frames can be? a) >20% 17. Level of service on road is? a) Qualitative measure of traffic flow b) Numerical number from 1 – 5 c) Qualitative measure of traffic flow & Numerical number from 1 – 5 d) None of above 18. If you have short measuring tape the error will be (n)…error? a) Systematic
19.Undrained 19. Undrained shear strength of clay equals? a) b) c) d)
2 confined compressive strength confined compressive strength ½ confined compressive strength Not related to confined compressive strength
20. Critical path in project network is the? a) Longest sequence of activities
21.What 21. What is the value of engineering? Value engineering can be defined as an organized effort directed at analyzing designed building features, systems, equipment, and material for the purpose of achieving essential functions at the lowest life cycle cost consistent with required performance, quality, reliability, and safety
22.What 22. What are the project phases? 5 phases of project management 1. conception and initiation, 2. planning, 3. execution,
3 Edition 2
UPDA Exam Questions for Civil Engineers 2016 4. performance/monitoring, performance/monitoring, and 5. project close
23.Type 23. Type of foundations? All foundations are divided into two categories: 1. shallow foundations and – depth 1m 1. Individual footings 2. Strip footings 3. Raft or mat foundations 2. deep foundations – depth 20-60m 1. Pile foundations a) End bearing pile b) Friction pile
24.The 24. The higher hand in project requirements? 25.What 25. What is the difference between client and owner? Client is a person that purchases goods or services, under the protection and engages the professional advice / knowledge of another person/business leader. I.e. when you employ the services of a lawyer, you are his/her client Costumer is a person that purchases goods or services from another person or company. I.e. when you buy milk at the supermarket, you are a supermarket customer . Owner is the person, company or state authorities who are the real owners, and have the power to project changes, stopped or sale
26.What 26. What is LEED? Leadership in Energy and Environmental Design (LEED) is an internationally recognized green building certification system, providing third-party verification that a building or community was designed and built using strategies aimed at improving performance across all the metrics that matter most: energy savings, water efficiency, CO2 emissions reduction, improved indoor environmental quality, and stewardship of resources and sensitivity to their impacts.
27.Fire-fighting 27. Fire-fighting componen components? ts? Fire protection in buildings, offshore construction is typically achieved via all of the following: a) Passive fire protection - the installation of firewalls and fire rated floor assemblies to form fire compartments intended to limit the spread of fire, high temperatures, and smoke.
4 Edition 2
UPDA Exam Questions for Civil Engineers 2016 b) Active fire protection - manual and automatic detection and suppression of fires, such as fire sprinkler systems and (fire alarm) systems. c) Education - the provision p rovision of information regarding passive and active fire protection systems to building owners, operators, occupants, and emergency personnel so that they have a working understanding of the intent of these systems and how they perform in the fire safety plan.
28.Glazing 28. Glazing minimum ratio in high-rise building? For building glazing ratio is 50% or more. High-performance, window and glazing systems are now available that can dramatically cut energy consumption and pollution. - can reduce energy consumption from 10%-50% - reduce lighting and HVAC costs 10%-40%.
29.Span 29. Span of over-handing ratio of roof span? 30.What 30. What is officially plan? An official plan describes your upper, lower or single– tier municipal council's policies on how land in your community should be used. It is prepared p repared with input from you and others in your community and helps to ensure that future planning and development will meet the specific needs of your community
31.What 31. What is the purpose of fast track project? 1. Fast track - start construction before the design is complete. The purpose is to shorten the time to completion 2. Design–bid–build (D-B-B) - traditional method to project delivery
32.Non-bearing 32. Non-bearing wall? Non-load-bearing walls carry only their own weight. This type of wall is used to close in a steel or concrete frame building.
33.What 33. What is Sill? (klupcica ili prag) Sill is a slab of stone, wood, or metal at the foot of a window opening or doorway. - a strong horizontal beam forming a base in the frame of a timber-framed building. - each of the lower horizontal members of the frame of a cart or motor or rail vehicle.
34.What 34. What is lintel? a) a horizontal support of timber, stone, concrete, or steel across the top of a door or window b) a horizontal supporting member, installed above an opening such as a window a window or a door, a door, that that serves to carry the weight of the wall the wall above it.
5 Edition 2
UPDA Exam Questions for Civil Engineers 2016
35.Term 35. Term of member that connect between trusses to truss? Truss is - essentially a triangulated system of straight interconnected structural elements. The most common use of trusses is in buildings, where support to roofs. Some benefits: a) Long span b) Lightweight c) Reduced deflection (compared to plain members) d) Opportunity to support considerable loads.
Lateral stability provided by longitudinal wind girder and vertical bracings in the gables (blue) Longitudinal stability provided by transverse wind girder and vertical bracings (green)
36.What 36. What is type of Greek column that is shortest & studied?
6 Edition 2
UPDA Exam Questions for Civil Engineers 2016 Doric columns are shortes
37.Folded 37. Folded structure? Are three-dimensional structures. Creating with mathematical model.
38. Which architecture type that contains pointed architecture? Gothic architecture is the architecture of the late medieval period, characterized by use of the pointed arch. 39. For which purpose the architecture program is running? 40. What is the first point in project definition, to achieve costumer target? Projects are divided into 6 stages: 1. DefinitionBefore a project starts the project manager must make sure the project goals, objectives, scope, risks, issues, budget, timescale and approach have been defined 2. 3. 4. 5. 6.
Initiation Planning Execution Monitoring & Control Closure
41.Delay 41. Delay in contract due to late legal or permission?
7 Edition 2
UPDA Exam Questions for Civil Engineers 2016
42.AB 42. ABET is…? a) Engineering firm Accreditation Board for Engineering and Technology, Inc., is a non-governmental a non-governmental organization that organization that accredits post-secondary accredits post-secondary education education programs in "applied science, computing, science, computing, engineering engineering BFFS is. BFFS is. Basic Free Slow Speed Estimate
43. Dimension of common bedrooms’ door size?
44.Brick 44. Brick to concrete block? 45.Simple 45. Simple beam has les performance compared with continuous beam because of: a) It has more deflection 46. Who is designer of Alsharq Village at Doha: a) Ibrahim Aldosary b) Rasem Badran c) Jan Novel
47.In 47. In skeleton buildings, the main function of beams is to: a) Collect loads from slab and transfer it to columns
48.Wheel 48. Wheel color includes: a) 12 color 49. Which of the following columns has no base? a) Doric
50.Engineering 50. Engineering discipline between planning, architecture involved with spacing between buildings, and not buildings individual design? a) City planning b) Urban design
8 Edition 2
UPDA Exam Questions for Civil Engineers 2016 51. The high of the minarets m inarets of Ottoman arch mosque? a) 20m b) 40m c) 70m
52.Natural 52. Natural foundation strength, when it is compares by concrete foundation? a) More strength then concrete b) The same strength then concrete c) Less strength then concrete 53. Water falls villa, one of the famous works of Frank Lloyd Wright, its structural concept is? a) Cantilever
54.What 54. What is definition of the Pile Cap? A Pile Cap is a reinforced concrete structure, which allows the load from a column to be equally shared between s group of pile.
55. Which of the following can be considered as a landmark in Qatar? a) Sheraton hotel
56.Eiffel 56. Eiffel Tower is constructed from? a) Iron 9 Edition 2
UPDA Exam Questions for Civil Engineers 2016 b) Stainless steel
57.Concrete 57. Concrete is made of: a) 1 cement – 3 sand – 6 water 58. Height of Aspire tower: a) 300 m
59.A 59. A beam is having deflection, how to repair this deflection: a) Adding steel reinforcement b) Increasing depth of the beam
60.A 60. A footing is getting shear load more than the original calculations, the design must: a) Increase the plan dimension
61.Stone 61. Stone walls installation problems that may lead to cracks and failure: a) b) c) d)
Mortar erosion Lack of tie joints …. between different courses All the above
62.Function 62. Function of ground foundation: a) Carry all live and dead loads 63. City block is defined as: a) Minimum urban unit surrounding by public spaces b) Minimum urban unit surrounding by parking slots c) Minimum urban unit surrounding by parks d) Maximum rural unit
64. Population density is: a) Population /Area
65. A discipline between planning and architecture that deals with spaces between buildings without dealing with the architecture of the buildings: a) Urban design
10 Edition 2
UPDA Exam Questions for Civil Engineers 2016 b) City planning
66. The interdisciplinary nature of enginee engineering ring affects specialization specialization,, accordingly: a) All engineers must be specialized in all disciplines b) All engineers must be aware of general knowledge about all disciplines without specialization c) Specialized engineers must be aware of general knowledge about other disciplines 67. Sinan is an architect from: a) Ottoman period
68. Construction starts: a) After getting the authority approvals
69.The 69. The site must be clear: a) After end of construction
70.Cut 70. Cut & Fill for road works are calculated based on: a) Cross section
71.When 71. When a concrete beam is designed as doubly reinforced beam: a) High bending moment b) Limitation of beam depth Note: If a beam cross section is limited because of architect or other considerations, it may happen that concrete cannot develop the compression force required to resist the given bending moment; in this case, reinforcing steel bars are added in compression zone, resulting in a so-called doubly reinforced beam. Another reason for placing reinforcement in the compression zone is that when beams span more than two supports (continuous construction), both positive and negative moments will exist.
72.While 72. While lifting a precast slab, where the highest shear may happen? a) At edges (slab ends)
73.What 73. What is hydration? a) hydration is a chemical reaction in which a substance combines with water
11 Edition 2
UPDA Exam Questions for Civil Engineers 2016
74.A 74. A foundation to be constructed on a weak soil, what measures should be taken? a) Replace soil with single size sand
75.Which 75. Which type of rollers to be used for sand compaction? a) Roller with vibrator
76.Land 76. Land to be surveyed, which method to be used? a) Geodesic
77.Steel 77. Steel strength? a) 400 MP-a
78.What 78. What is density for reinforcement reinforcement concrete? a) 2400 kg/m3 And 2200 kg/m3 for normal concrete
79.QSAS is…? Qatar Sustainability Assess Assessment ment System. This T his is a green building certification system developed for the State of Qatar. Global Sustainability Assessment Assessment System (GSAS), formerly known as the Qatar Sustainability Assessment System (QSAS). The assessment criterion takes into consideration various categories related to sustainable development and its impact on environmental stress mitigation. QSAS is assessed on the following eight categories; urban connectivity, site, energy, water, indoor environment, materials, management and operations and cultural – economic values
80.Reinforcing 80. Reinforcing steel bars of T10@10cm spacing to be replaced by T12, calculate the new required r equired spacing? a) New spacing=Old spacing x (New steel diameter)2 / (Old steel diameter)2 = 10 x (12)2 / (10)2 =14.4mm
81.Increment 81. Increment of W/C ratio (water / cement) will lead to: a) Reduce the strength of concrete a) Mmax = = QL2 / 8
12 Edition 2
UPDA Exam Questions for Civil Engineers 2016
82.Required 82. Required CPI value for a project is 1.02, where actual value is 0.95. What does it indicate? Actual Cost Performance Indicator (CPI) is less than planned, which means that project actual cost is more than budget cost due to misuse of project resources.
83.Scale 83. Scale on drawing is 1:62500, what is the actual value for a distance measured on drawing of 7.25”? 7.25” x 62500 x 1ft/12” x 1yard/3ft x 1 mile/1760 yard=7.15 miles
84.What 84. What is the cement type used for concrete exposed exposed to soil? Type II: Moderated sulphate resistance *for severe sulphate attack (soil with high sulphate content), type V should be used (High sulphate resistance)
85.CPM 85. CPM used to: Calculate longest duration
86.WBS 86. WBS – OBS relationship relationship?? The OBS displays organizational relationship and them uses them for assigning work to resources in a project. WBS - is a deliverable-oriented decomposition of a project into smaller components OBS - is an intermediate level of a different chart. OBS displays organizationa organizationall relationships and then uses them for assigning work to resources in a project. Like its originator, the OBS allows complex projects to be broken down, providing a more organized representation of the work to be completed. While the WBS is used to define the project during early stages its cycle, the OBS provides an organizational structure for the project as it moves to completion. The hierarchical nature of the Organizational Breakdown Structure allows for the appropriate resources and responsibilities to be assigned.
87.If 87. If a project has CPI value of 0.91 and SPI value of 1.01, what does it mean? It means that project is ahead on schedule (time wise), but is losing (cost wise)-over budget CPI - cost performance index, SPI – schedule performance index
88.If 88. If contractor failed in delivering the project, what will be the consequences? Liquidating of the performance bond.
13 Edition 2
UPDA Exam Questions for Civil Engineers 2016
89.In 89. In pert analysis, activity is represented by? Arrow PERT - Program (or project) Evaluation and Review Technique. Is a statistical tool, used in project in project management, which was designed to analyze and represent the tasks involved in completing a given project. given project. First First developed by the United the United States Navy in the 1950s, it is commonly used in conjunction with the critical the critical path method (CPM).
90.Concrete 90. Concrete durability depends on (related to) _____and_____? Temperature, Moisture, Physical factors, Chemical factors, Biological factors
91.AASHTO is …? American Association of State Highway and Transportation Officials
92.When 92. When a bid awarded to a contractor, the client will ask the contractor to submit additional documents? 93.When 93. When design reinforced concrete, the concrete: (related to concrete under which type of stress) 94.An 94. An arch with start point of bearing1=30 o 15i, bearing 2=35o10I and radius r=200m. Calculate the arch length? Arch angle = 35o10I - 30o 15i =4o 55i Arch length = Θ* π*r/180=17.16m
95.What 95. What is the value of water molar mass? a) 18g/mol
96.Timber 96. Timber beam properties (why timber could be used in construction as structural member)? According Euro Code 5, Timber construction can be design to base on limit state design
100. Station PI =90m, calculate station PC? PC=PI-T =18259.025-90
14 Edition 2
UPDA Exam Questions for Civil Engineers 2016 =18,169.025=18+169.025
101. For simply supported beam, stresses due to flexural & shear are zero at: Support, bottom fibre
102. Pure bending (question related to strength of materials)? - is a condition of stress where where a bending a bending moment is applied to a beam without presence of axial, of axial, shear, or shear, or torsional torsional forces. Pure forces. Pure bending occurs only under a constant bending moment
103. What is proctor test is used for? To obtain maximum dry density (MDD) for backfilling material.
104. In concrete mix design, which of the following is not required? a) b) c) d)
Workability W/C Compressive strength Initial setting time
105. Forward pass in project management is used to calculate: calculate : Longest duration of project
106. One of the following is not acceptable reason of delay or non-performance of the work: a) b) c) d)
Frustration of object Death of party Destruction of deliverable Strike of labours
107. Acceptable laying temperature of asphalt: a) 135 – 175O C
108. Highway design: a) Traffic volume
15 Edition 2
UPDA Exam Questions for Civil Engineers 2016
109. Ultrasonic pulse test is: a) Destructive test b) Non-destructive test c) Use to obtain maximum strength of concrete d) B & C An ultrasonic pulse velocity test is an an in-situ in-situ,, nondestructive nondestructive test test to check the quality of concrete of concrete and natural rocks. In this test, the strength and quality of concrete or rock is assessed by measuring the velocity of an ultrasonic an ultrasonic pulse passing through a concrete structure or natural rock formation. This test is conducted by passing a pulse of ultrasonic wave ultrasonic wave through through concrete to be tested tested and measuring the the time taken by pulse to get through the structure. Higher velocities indicate indicate good quality and continuity of the material, while slower velocities vel ocities may indicate concrete with many cracks or voids. 110. Time cost analysis is related to: a) Difference between actual cost and crashed cost / Normal time b) Difference between actual cost and crashed cost / Crashed time c) Difference between actual cost and crashed cost / NT+CT
111. Lowest level in WBS: a) Deliverable
112. Fiber saturation happens when: a) No free water in cells walls
113. How many layers of concrete are performed while carrying out a concrete slump test? a) 3 layers
114. Main cause to reduce concrete durability? a) b) c) d)
Corrosion of reinforcement Sulphate and ground water Fire All of above
16 Edition 2
UPDA Exam Questions for Civil Engineers 2016
115. Why concrete needs to be cured? a) To keep water retained in concrete to complete reaction & develop full strength b) To dehydrate
116. Archimedes principle for buoyancy is based on: a) b) c) d)
Area Moment of inertia Intensity of water Weight
117. Load carrying and deflection design is known for: a) Euler – Bernoulli
118. Richter scale used to measure: a) Seismic energy
119. Using concordant cable in pre stressed concrete for beams will reduce: a) Deflection of beam
120. Choose right answer: a) The higher the cement content the higher strength of concrete b) Cracks in concrete are due to high water content
121. Strength of concrete: a) b) c) d) e)
Crushing strength Vibration Size of aggregate Workability All of above
122. Measurement in drawing near near to 100ft is: a) 1 : 1000
17 Edition 2
UPDA Exam Questions for Civil Engineers 2016
123. Line connecting the same elevation on the drawing known as: a) Contour line
124. What is the reaction in the ceiling fan? a) Tension
125. What is the meaning of Fast track project? a) Project include Design + Build b) Project starts before design completes
126. What is the benefit of design+bid+build type project? a) Duration+cost Duration+cost of the project known b) Avoid contact between tenderers c) All above
127. Air entrainin entrainingg in the concrete caused? The primary purpose of air entrainment is to increase the durability of the hardened concrete, especially in climates subject, the secondary purpose is to increase workability of the concrete while w hile in a plastic state 128. One of the below is not characteristic of the project? a) Design b) Complex activities c) Internal use d) Never done before
129. For extracting rock samples of good quality, we use? a) Standard split spoon samples
130. Limit method for design concrete beams is considered: a) Smallest area of concrete with smallest area of reinforcement
131. The factors that govern the workability of fresh concrete are: a) The quantities of cement paste and aggregate relative b) The plasticity of the paste itself
18 Edition 2
UPDA Exam Questions for Civil Engineers 2016 c) The grading of aggregate d) The shape and surface characteristic of the aggregate e) All of above
132. Admixture added to concrete for: a) b) c) d) e) f)
Increase the concrete strength Increase the initial setting of concrete Manage the workability of concrete Decrease the water content B and C A and B
133. During the project, your order can be changed to: a) Owner change the requirement
134. The most element effect in QSAS is: a) Environment
135. This question is regarding the deflection of car speed 60mile/h when it reaches the Roundabout: a) 150 feet
136. Undrained shear strength for clay: a) Unconfined compressive strength of clay b) 2x Unconfined compressive strength of clay c) Not related to unconfined compressive strength of clay
137. For very dense sand, STP (N) value: The Standard Penetration test ( SPT) is a common in situ testing method used to determine the geotechnical engineering properties of subsurface soils. It is a simple and inexpensive test to estimate the relative density of soils soils and approximate shear shear strength parameters. parameters. a) 0-20 b) 25-42 c) More than 100
19 Edition 2
UPDA Exam Questions for Civil Engineers 2016
138. Concrete cubes are usually tested at: a) 28 days
139. QCS stand for: Qatar Construction specification
140. QSAS stand for: Qatar Sustainability Assessment System
141. The following is very critical to structures: a) Differential settlement
142. Plastic behaviour of concrete: a) Shrinkage cracks b) Settlement c) A & B
143. Why steel bars are used as concrete reinforcement: reinforcement: a) Strength an low price
144. Level of service is demonstrated as: a) 1-5 b) Qualitative Analysis c) A & B Level of service (LOS) is a qualitative measure used to relate the quality of traffic service. LOS is used to analyze highways highways by categorizing traffic flow and assigning assigning quality levels of traffic traffic based on performance measure like speed, density, etc.
145. Factor affecting bearing capacity while design of foundatio foundation: n: a) b) c) d)
Shear Specific weight of soil Dimension of foundation All of above
20 Edition 2
UPDA Exam Questions for Civil Engineers 2016
146. Cause of corrosion: a) Availability of water and moisture 147. If $1,000,000 deposited, what will be the total amount after 5 years accumulated on monthly basis with annual rate of return of 9%: a) $ 1,565,681 b) $ 1,538,623 c) ………………. Solution: Present value or deposit ( P) = $ 1,000,000 Interest rate ( i)=0.09/12=0.0075 (monthly) - interest rate is required to be calculated on monthly basis – duration also as monthly Duration (n) =5x12=60 months Future value ( F) =? F=P (1+i) n=$ 1,000,000(1+0.0075)60=$ 1,565,681
148. Backfilling of utility trenches, each layer should be maximum as per QCS: a) 150mm (QCS-selection 12-part4-4.1.4)
149. WBS (Work Breakdown Structure): - is first thing to be done after project definition, it is graphical presentation of the whole project - WBS organizes and define total scope of the project - does not show activity sequence
150. CPM (Critical Path Method): a) Estimate the activity duration
151. 2-way slab sides lifting caused by: a) Torsion
152. Top of WBS: a) The project b) Deliverables
153. High W/C (water/cement) ratio leads to: a) Reduce strength
21 Edition 2
UPDA Exam Questions for Civil Engineers 2016
154. Safe design of long piles in rock based on: a) Strength of rock
155. Timber imported factor to be used as a beam member: a) Strength
156. Clayesh! a) Good for usage in road b) Bad for usage in road
157. Weaving length in roads: a) Change of position in interchanges b) Change of speed
158. Which will be placed lowest in the tranches? a) Drainage pipes b) Water pipes c) Electricity cable
159. If T-beam is supported as continuous beam, then the middle beam must be designed as: a) b) c) d)
Simply supported Rectangular section T-beam Flange
160. Modulus of Elasticity of a mass of rock compared to rock substance is: a) Equivalent to … b) Higher than … c) Lower than …
161. Arrange the following activities as to be performed at site: Pouring concrete, formwork erection, formwork removal, concrete curing Answer: formwork erection, pouring concrete, concrete curing, formwork removal
22 Edition 2
UPDA Exam Questions for Civil Engineers 2016 163. The amount of time that a schedule activity can be delayed without delaying the early start date of any immediately scheduling activities is: a) Free float
164. Asghal is: a) Public Work Authority (it is not a ministry)
165. An activity that determine determiness the start date or finish date of next activity based on a logical relationship is: a) Predecessor activity
166. What is the most important factor (which is before capacity): a) Safety
167. Uplifting of slab on grade will happen because of: a) Differences of shear at the slab ends b) Soil resistance
168. What is the most important factor for project end state? a) Accomplishing project within time frame
169. What are the best dimensions for an isolated footing with a known area of 2.25m2 if column dimensions on footing are 0.8m x 0.25m? a) 1.80m x 1.25m
0.80m
170. The following network activity means: 3 days
A
B
a) Activity B starts immediately after 3 days of activity A starts
23 Edition 2
UPDA Exam Questions for Civil Engineers 2016
171. Calculate the rotation of member AB: a) b) c) d)
0.0378 deg 0.02601 rad 0.00046 rad Zero
172. The diagram represents: represents:
4
25
4 4
a) Shear b) Moment c) Deflection
173. Qatar Buildings and Regulations Buildings 1. The The Museu m of Islamic Art is a museum located in the Qatari capital Doha and designed by architect I. M. Pei 2. Aspire Tower – The Torch, Doha, is a 300m‐ tall tall skyscraper hotel located located in the Aspire Zone, Designed by architect Hadi Simaan and AREP and structural engineer Ove Arup and Partners, currently the tallest structure and building in Doha and Qatar 3. The Burj Qatar is a skyscraper in West Bay, Doha, Qatar, Qat ar, designed by French architect Jean Nouvel, has a height of 232m Regulations 1. Stage 1: Design Control Stage 1 Approval - general overviews and strategies-DC1 2. Stage 2: Design Control Stage 2 Approval - design develops for final approval-DC2 3. Stage 3: Building Permit – after DC2 approved, process usually takes at least 90 days
174. Suinstability, according to new researches, is considered for building CO2 emission as: a) 25% b) 45% c) 75%
175. Engineering is using: a) Knowledge of Science & Mathematics
24 Edition 2
UPDA Exam Questions for Civil Engineers 2016 b) Lows of nature
176. What is the meaning of POE: Post Occupancy Evaluation (POE) has its origins in the United States. POE is process of evaluating buildings in a systematic and rigorous manner after they have been built and occupied for some time. POE provides feedback of how successful the workplace is in supporting the occupying organization and individual end ‐user requirements.
177. The proper ratio for stairs (2 raises+run): a) 60‐62.5 cm b) 50‐60 cm c) 65‐70 cm
178. What is an optimal slope in the garden? a) 8% (to be double checked)
25 Edition 2
UPDA Exam Questions for Civil Engineers 2016
179. Type of slabs
180. The strength for the nature foundation shall be: a. Stronger than the pressure from the building
26 Edition 2
UPDA Exam Questions for Civil Engineers 2016 b. Lower than the pressure from the building c. Equal pressure
181. What is rentable system for the span over 50m? a. Steel structure b. Slab concrete c. Space frame (Ramovske konstrukcije) konstrukcije)
182. What is the function of the cement in the concrete? To connect non adhesive components
183. Curtain wall? System an outer covering of a building in which the outer walls are non ‐ structural. A curtain wall is designed to resist air and water infiltration. Curtain wall systems are typically designed with extruded aluminum members. When glass is used as the curtain wall, a great advantage is that natural light can penetrate deeper within the building. Design requirements: 1. thermal expansion and contraction; 2. building sway and movement; 3. water diversion; 4. thermal efficiency for cost‐ effective heating, cooling, 5. lighting in the building.
184. In case of designing column and footing and in case of shear (poprečne sile) existing following measure should be taken: a) Enlarge footing b) Increase steel c) Increase thickness
185. In case of digging next to a wall how to protect it with? a) wall
186. What is the main structural difference between cable and tent structure: a) Tent is a surface structure but, cable is frame structure also both are tensioned
187. Disadvantage for simple beam than continues once? a) More deflecting
27 Edition 2
UPDA Exam Questions for Civil Engineers 2016
188. Function of ground footing: a) b) c) d)
Surround all the built area Resist the imposed loads and dead loads Resist different soil impact The last two? two?
189. Beams in skeleton buildings depend on: a) Transfer loads from slab to columns:
190. To start construction what is the name of the underwater tight chamber: a) Caisson or Air-lock
191. Project control: Series of processes and steps that a project manager in cooperation with other management staff carries out to control the project: a) terms of progress, b) quality, c) changes, d) products, e) commitments f) and other critical concerns The ultimate purpose of project control is to manage work during each stage and to prepare the project for the next stage.
28 Edition 2
UPDA Exam Questions for Civil Engineers 2016 Project control achieving defined objectives and expectations within a predetermined timetable, with three high‐ level processes: a) setting standards b) measuring performance corrections c) taking corrections Each of the processes can be divided into smaller steps and tasks: a) Hold meetings - every meeting starts with an agenda b) Perform quality control – starts when a project started until to the t he end of project c) Track work progress - ensure that project work is being done as scheduled d) Respond to changes - by effectively responding to changes PM is able to ensure that the scope, schedule and cost remain relevant to current situation e) Manage issues - takes a steps to identify issues, assess their impact, develop solution actions, take those actions and track progress on issues
192. Project Engineer is involved in the project during: a. Stays till project ends
193. The difference between between project and operation? Project is unique and having beginning and the end. Operation is repetitive.
194. Stakehold Stakeholder? er? A party that has an interest in an enterprise or project. The primary stakeholders in a typical corporation are its investors, employees, customers and suppliers.
195. Project charter Describes what your project is, and how you will approach it, and it lists the names of all stakeholders.
197. On relation to the use of air-entraining agents in concrete, which of the following statements are true? a. b. c. d.
Improve the workability Improving long-term durability d urability Makes a less dense mixture all the above are true
198. Right or false? What factors influence the compressive strength of concrete? a. Resistance is inversely proportional to the water-cement ratio
29 Edition 2
UPDA Exam Questions for Civil Engineers 2016 b. The resistance is proportional to the cement content c. Cracks on the surface due to excessive water content d. All others are true. 199. If a work, if the property decides to make a change in scope, what is the procedure to do? a. Change order b. Modification
200. For why steel is preferred as reinforcement reinforcement in concrete? a. b. c. d.
Because it is inexpensive and resistant Because it is easily accessible Because it adheres well to concrete Because it has the same coefficient of expansion of the concrete.
201. What is a logical sequence of activities? activities? a. 1,2,3,4 b. 3,2,4,1 c. 2,4,3,1
202. Problem: "If in a plane I measure 7 ¼ " "(inches) and is 1/62.500 scale, what is the distance between the two points in miles? Answer: 7, 25 miles 203. On Work breakdown structure relative to project which of the following statements are false? a. Breaks up the project in a " top-down " b. It breaks down the draft as "down -top " c. Used to handle large projects. 204. What of the following statements are false for a Work package? a. It should set deadlines "definitive "
205. What is the SPT for dense sand? Options: 0-20 / 20-40 / > 100. Answer: 20-40
206. How to calculate a continuous T beam? a. Supported at various points b. Simply supported 30 Edition 2
UPDA Exam Questions for Civil Engineers 2016 c. Flanged section d. Rectangular section
207. What is Degree of curve? 100 feet chord angle
208. In a beam which points of stress due to the time t ime and bearing is equal to 0? a. b. c. d.
In the neutral center In the top center fiber light l ight At lower fiber support In the neutral light support
209. Relearn the gap: The immediate _______are Necessary Necessary to Develop the Following tasks in a breaking down of a project. a. Critical activities b. predecessor activities c. successor activities d. Burst activities e. None of the above is correct Answer: Predecessor activities.
210. What is the perception and reaction time for calculating the sight distance? a. b. c. d.
1 second 2.5 s 3.5 s None of the above
211. For how cross sections are used? Answer: for cut and fill quantities.
31 Edition 2
UPDA Exam Questions for Civil Engineers 2016
212. Problem influence lines. Vocabulary: shear stress.
214. Lacing system. Doubt: Is an articulated structure? 215. Problem of a cross section of concrete. What is the moment of resistance? The moment of resistance of the concrete section is the moment of couple formed by the total tensile force (T) in the steel acting at the center of gravity of reinforcement and the total compressive force (C) in the concrete acting at the center of gravity of the compressive stress diagram.
216. Pick up the correct statement from the following: A.The A. The theory of formation of concrete is based on the phenomena of formation of voids B.The B. The bulking of sand is taken into account while volumetric proportioning of the aggregates C.T C.The dry sand and the sand completely flooded with water, have practically the same volume D.T D.The expansion and contraction joints are provided if concrete structures exceed 12 m in length E.All E. All the above
217. Initial setting time of cement for asbestos cement products should be not less than a) 90 minutes
218. Pick up the correct statement regarding regarding low heat cement from the following: a. It possesses p ossesses less compressive strength b. Its initial setting time is about one hour c. Its final setting time is about 10 hours d. Its mainly used for mass concrete work
32 Edition 2
UPDA Exam Questions for Civil Engineers 2016 e. All the above
219. Name the type of cement from the following for canal linings: a. sulphate resisting cement b. rapid hardening cement c. quick setting cement d. pozzuolana cement
220. If water required for 1 bag of cement is 30 liters, the water cement ratio is : A.0.40 A.0.40 B.0.50 B.0.50 C.0.60 C.0.60 D.None D.None of these
221. The weight of 1 m3 of brick earth, is about A. 1800 kg
222. Mastic asphalt is normally used for a) water proofing
223. Strength of cement concrete primarily depends upon a) water-cement ratio
224. Soundness of cement is tested by - Le-chatelier apparatus
225. Slump test for concrete is carried out, to determine - workability
226. In case of Raymond pile A.l A. lengths vary from 6 m to 12 m B.diameter B. diameter of top of piles varies from 40 cm to 60 cm C.d C.diameter of pile at bottom varies from 20 cm to 28 cm D. thickness thickness of outer shell depends upon pile diameter d iameter E.all E. all the above
33 Edition 2
UPDA Exam Questions for Civil Engineers 2016
227. The foundations are placed below ground level, to increase - stability of structure
228. The loose pockets in soil mass can be bridged safely by providing a raft foundation provided the soft area is smaller than A. the the column spacing B.one-third B. one-third the column spacing C.h C.half the column spacing D. three-fourth three-fourth the column spacing E.none E. none of these
229. The concrete slump recommended for beams and slabs is a. 30 to 125 mm
230. The entrained concrete is used in lining walls and roofs for making a. b. c. d.
heat insulated sound insulated neither (a) nor (b) both (a) and (b)
231. For providing a raft foundation, the following activities are involved a. b. c. d. e.
ramming the foundation bed excavation of the soil up to required depth laying the reinforcement over the foundation bed curing the cement concrete placed over reinforcement pouring the cement concrete over the reinforcement
232. Raft foundation are generally preferred to when the area required for individual footing, is more than - 50% of total area
233. Pick up the incorrect statement from the following: - to drain off water from the earth retained, weep holes are provided near the top of the retaining wall
34 Edition 2
UPDA Exam Questions for Civil Engineers 2016
234. The process of keeping concrete moist for a certain period after its finishing, is known as - curing of concrete
235. Raft foundations are used for: A.providing A. providing increased area of foundation over poor bearing capacity of soil B.spanning B. spanning over small soft or loose pockets C.c C.counter acting the hydrostatic effect D.a D.all the above
236. The foundation which consists of a thick reinforced cement slab covering whole area to support heavy concentrated structural loads, is known as - raft footing
237. For a wall carrying heavy load on low bearing capacity soil, A.l A. lean concrete bed is provided B. thick thick concrete bed is provided C.r C.r einforced einforced concrete bed is provided D.( D.(a) and (c) of the above E.( E. (b) and (c) of the above.
238. The bearing capacity of a water logged soil, may be improved by - drainage
239. Two columns 50 cm x 50 cm and 60 cm x 60 cm carry 80 tones and 120 tones of loads respectively. The center to center distance between columns is 5.00 meters. The permissible bearing capacity capacity of the soil is 20t/m2. If the footing is not to project more than 25 cm beyond the outside of the smaller column, pick up the correct design parameters of the footing from the following: A.distance A. distance of C.G. of the loads from the smaller column = 3.00 m B. the the length of the foundation slab = 7.00 m C.a C.area of footing slab = 11.00 m2 D.width D.width of the footing = 1.57 m. E.all E. all the above
240. The formwork including the props can be removed from beams, only after
35 Edition 2
UPDA Exam Questions for Civil Engineers 2016
241. The concrete slump recommend recommended ed for foundations, is a) 50 to 100mm
242. The construction joints in buildings are provided after - 40m
243. Pick up the correct statements from the following: A.cracks A. cracks appear on the plastered surface in the form of hair cracks B.i B. in brick work, the efflorescence is removed by applying a solution of zinc sulphate and water C.e C.e xcessive thermal variations variations in the the backing or plaster causes causes the plaster to fall D.a D.all the above
244. Pick up the correct statement from the following: A.Plain A. Plain cement concrete is equally strong in compression as well as in tension B.Slump B. Slump test is performed to check concrete strength C.Curing C.Curing of concrete is done for proper compaction of cement Fineness modulus is the index number expressing the relative sizes of both coarse and fine D. aggregates E.Concrete E. Concrete is a mixture of binding material, coarse aggregate and water.
245. Pick up the correct statement from the following: A.I A.Isolated footing is provided under column to transfer the load l oad safely to soil bed B.column B.column footings may have steps or projections in the concrete base C.heavily C.heavily loaded column base must be provided steel reinforcement in both directions D. the the concrete offset should be at least 15 cm on all sides E.all E. all the above
246. If h is the difference in level between end points separated by l, then the slope correction is . The second term may be neglected if the value of h in a 20 m distance is less than A.
m B.1 B. 1 m C.2 C.2 m
36 Edition 2
UPDA Exam Questions for Civil Engineers 2016 D.3 D.3 m
247. The accuracy of measurement in chain surveying, does not depend upon A.l A. length of the offset B.scale B.scale of the plotting C.i C.importance of the features D.g D.general layout of the chain lines
248. Offsets are measured with an accuracy of 1 in 40. If the point on the paper from both sources of error (due to angular and measurement measurement errors) is not to exceed 0.05 cm on a scale of 1 cm = 20 m, the maximum length of offset should be limited to A.14.14 A.14.14 B.28.28 B. 28.28 m C.2 C.200 m D.n D.none of these.
249. Ranging in chain survey means A.l A.looking at an isolated point not on the line B.establishing B.establishing an intermediate point on the line C.d C.determining the distance between end points
250. The operation of resection involves the following steps 1. 2. 3. 4.
rough orientation of the plane table the three lines form a triangle triangle of error drawing lines back through the three control points select a point in the triangle of error such that each ray is equally rotated either clockwise or anti clockwise 5. the points obtained obtained by three rays is the correct location The correct sequence is A.1, A.1, 3, 2, 4, 5 B.1, B. 1, 2, 3, 4, 5 C.1 C.1, 4, 3, 2, 5 D.1 D.1, 3, 2, 4, 5
37 Edition 2
UPDA Exam Questions for Civil Engineers 2016
251. If the length of a transition curve to be introduced between a straight and a circular curve of radius 500 m is 90 m, the maximum perpendicular perpendicular offset for the transition curve, is A.0.70 A.0.70 m B.1.70 B. 1.70 m C.2 C.2.70 m D.3 D.3.70 m E.4.70 E. 4.70 m
252. For quality control of Portland cement, the test essentially done is A.setting A.setting time B.soundness B. soundness C. tensile tensile strength D.c D.consistency E.all E. all the above
253. If 1500 g of water is required to have a cement paste 1875 g of normal consistency, the percentage of water is A.20% A.20% C.3 C.30% E.40% E. 40%
B.25% B.25% D.3 D.35%
254. Hydration of cement is due to chemical action of water with A.Tricalcium A. Tricalcium silicate and dicalcium silicate B.Dicalcium B. Dicalcium silicate and tricalcium aluminate C.T C.Tricalcium aluminate and tricalcium alumino ferrite D.All D.All the above
255. Curing A.r A. r educes educes the shrinkage of concrete B.preserves B. preserves the properties of concrete C.p C.prevents the loss of water by evaporation D.a D.all of the above
256. Curing a concrete for long period ensures better A.volume A.volume stability B.strength B. strength
38 Edition 2
UPDA Exam Questions for Civil Engineers 2016 C.water C.water resistance D.water D.water tightness and durability E.all E. all the above
257. Pick up the correct statement from the following: A.I A.Insufficient quantity of water makes the concrete mix harsh B.I B. Insufficient quantity of water makes the concrete unworkable C.E C.E xcess quantity of of water makes the concrete segregated D.E D.E xcess quantity of of water causes bleeding in concrete concrete E.All E. All the above
258. Workability of concrete is measured by Slump test
259. Shrinkage in concrete can be reduced by using A.l A. low water cement ratio B.l B. less cement in the concrete C.p C.proper concrete mix D.p D.presaturated aggregates E.all E. all the above
260. A construction joint is provided where A.bending A.bending moment is small B.shear B.shear force is small C. the the member is supported by other member D.a D.all the above
261. Pick up the correct statement from the following According to the petrologic p etrologic characteristics, concrete aggregates are classified as heavy weight, normal weight and light weight According to the shape of the particles, p articles, concrete aggregates are classified as rounded irregular, B. angular and flaky According to the surface texture of the particles, the concrete aggregates agg regates are classified as glassy, C. smooth, granular, rough, crystalline, honey combed and porous D.All D.All the above A.
262. Pick up the incorrect statement from the following: A.The A.The degree of grinding of cement, is called fineness
39 Edition 2
UPDA Exam Questions for Civil Engineers 2016 B.The B. The process of changing cement paste into hard mass, is known as setting of cement The phenomenon by virtue of which cement does not allow transmission of sound, is known as C. soundness of cement D.T D.The heat generated during chemical reaction of cement with water, is known as heat of hydration E.None E. None of these.
263. Permissible compressive strength of M 150 concrete grade is A.100 A.100 kg/cm2 B.150 B. 150 kg/cm2 C.2 C.200 kg/cm2 D.2 D.250 kg/cm2 E.300 E. 300 kg/cm2
264. Slump test of concrete is a measure of its -
Consistency ASTM (American Society for Testing and Materials) explain how the slump test should be done
265. Water cement ratio is A.volume A. volume of water to that of cement B.weight B.weight of water to that of cement C.weight C.weight of concrete to that of water D.v D.volume of concrete to that of water E.both E. both (a) and (b) of the above
266. Separation of water or water sand cement from a freshly concrete, is known a) bleeding
267. According to Water-Ceme Water-Cement nt Ratio Law, the strength of workable plastic concrete A.depends A. depends upon the amount of water used in the mix B.does B. does not depend upon the quality of cement mixed with aggregates C.d C.does not depend upon the quantity of cement mixed with aggregates D.a D.all the above
268. High temperature - decreases the strength of concrete
40 Edition 2
UPDA Exam Questions for Civil Engineers 2016
269. Allowable shear strength of concrete, depends upon A.shear A.shear strength B. tensile tensile strength C.c C.compressive strength D.n D.none of these.
270. Workability of concrete mix with low water cement ratio is determined by - slump test
271. While designing an air entrained concrete A.water A. water cement ratio is reduced B.proportion B. proportion of aggregates is reduced C.a C.an allowance for the entrained air is made D.s D.s trength of the concrete, is reduced E.all E. all the above
272. Concrete gains strength due to - hydration of cement
273. Expansion joints are provided if the length of concrete structures exceeds - 45m
274. Workability improved by adding A.f A.fly ash B.hydrated B. hydrated lime C.c C.calcium chloride D.b D.bentonite E.all E. all the above
275. If the slump of a concrete mix is 60 mm, its workability is - medium
276. Pick up the correct statement from the following: A.Construction A. Construction joints in columns are provided a few cm below the junction of beam B.Construction B. Construction joints in columns are provided at the bottom hunching C.Construction C.Construction joints in beams and slabs are provided within middle third D.Construction D.Construction joints are generally provided in positions subjected to least shear force
41 Edition 2
UPDA Exam Questions for Civil Engineers 2016 E.All E. All the above
277. The shortest distance between two places measured along the surface of the earth, is - length of the arc of the great circle passing through them
278. In the cantilever truss as shown in below figure, the horizontal component of the reaction at A, is
A.30 A.30 tones B.60 B. 60 tones C.9 C.90 tones D.1 D.120 tones E.150 E. 150 tones
279. For a simply supported beam with a central load, the bending moment is A.l A. least at the center B.l B. least at the supports C.maximum C.maximum at the supports D.maximum D.maximum at the center
280. A simply supported beam carrying a uniformly distributed load over its whole span is propped at the center of the span so that the beam is held to the level of the end supports. The reaction of the prop will be A.half A.half the distributed load B.3/8th B.3/8th the distributed load C.5 C.5 /8th the distributed load load D.Distributed D.Distributed load. E.none E. none of these.
281. The range within which a load can be applied on a rectangula rectangularr column, to avoid any tensile stress, is A.one-half A.one-half of the base
42 Edition 2
UPDA Exam Questions for Civil Engineers 2016 B.one-fifth B.one-fifth of the base C.one-fourth C.one-fourth of the base D.one-fifth D.one-fifth of the base E.one E. one sixth of the base on either side of centroid
282. The shear stress at any section of a shaft is maximum A.at A.at the center of the section B.at B. at a distance r/2 from the center C.a C.a t the top of the surface D.a D.a t a distance 3/4 r from the the center E.none E. none of these 283. The region of the cross-section of a column in which compressive load may be applied without producing any tensile stress, is known as the core of the cross-section. In circular columns the radius of the core, is - one-quarter of the radius
284. The maximum bending moment due to a moving load on a simply supported beam, occurs - under the load
285. A simply supported beam of span L carries a uniformly distributed load W. The maximum bending moment M is
286. A cantilever beam rectangular in cross-section is subjected to an isolated load at its free end. If the width of the beam is doubled, the deflection of the free end will be changed in the ratio of A.8 A.8 C.1 C.1 /2 E.3 E. 3
B.1/8 B.1/8 D.2 D.2
287. When equal and opposite forces applied to a body, tend to elongate it, the stress so produced, is called - Compressive stress
43 Edition 2
UPDA Exam Questions for Civil Engineers 2016 - Tensile stress
288. Stress in a beam due to simple bending, is - directly proportional
289. The bending moment is maximum on a section where shearing force - changes sign
290. A district road with a bituminous pavement pavement has a horizonta horizontall curve of 1000 m for a design speed of 75 km ph. The super-elevation is A.1 A.1 in 40 B.1 B. 1 in 50 C.1 C.1 in 60 D.1 D.1 in 70 E.none E. none of these. 291. The total length of a valley formed by two gradients - 3% and + 2% curve between the two tangent points to provide provide a rate of change of centrifugal centrifugal acceleration 0.6 m/sec2, m/sec2, for a design speed 100 km ph, is A.16.0 A.16.0 m
292. The advantage of providing super elevation on roads, r oads, is A.higher A.higher speed of vehicles B.i B. increased volume of traffic C.r C.r educed educed maintenance cost of the roads D.d D.draining off rain water quickly E.all E. all the above 293. For a vehicle moving m oving with a speed of 80 km per hour, the brake reaction time, in ordinary cases, is 2.5sec
294. Reynolds coefficient number is used for - Fluid mechanics close conduit
44 Edition 2
UPDA Exam Questions for Civil Engineers 2016
295. Relaxation of cable? Deflection
296. Plasticity index WC – Water content
297. Pert analysis Go to PMP
298. According to QCS, what is the initial and final set time for concrete - Initial 2h - Final 10h 299. The cost variance factor in the project is indicated for: a. the budget 300. What from the following is not considering a project? a. Submit a tender document for contractor
301. The Maximal Dry Density (MDD) shall be at: a. Optimal WC (water content)
302. What is the meaning of the PERT Analysis? - to provide graphical representation of a project p roject time line
303. The standard deviation is factor for - Pessimistic estimated value - Optimistic estimated value
304. What is the max allowable tense stress in the wooden buildings? 40 MPa
305. The steel reinforcement in the concrete is very important for: - max bending moment - max tension stress
45 Edition 2
UPDA Exam Questions for Civil Engineers 2016
306. If there in a building with shallow foundation and the soil very expensive, and as per soil report we must the replace this soil with other we can: - use same soil with good compaction up to more than 95% from MDD - excavate this soil and use the same soil for backfilling after 95% MDD
307. What is the type of cement we can use it in sub-structure reinforcement concrete? OPC
308. What is the min thickness in blinding concrete in sub-structure concrete? 75mm
309. The strength material is defined as: Ability of material to resist deformation
310. Stress means: - Internal forces developed in material m aterial due to external forces - Deformation in material caused of external forces
311. The summation of internal angels of 6 side polygon is: 5400
312. ASHGAL responsible for: Public housing -?
313. Compaction in backfilling in used for: Reducing air content in backfilled material
314. One of the following is not a gypsum board characteristic a. Low cost in construction
315. Super elevation is used at: - horizontal curves – to avoid centrifugal force at high speeds
316. The un-drained shear strength for clay is equal to: One and a half the unconfined compressive strength of clay
46 Edition 2
UPDA Exam Questions for Civil Engineers 2016
317. Project Scope Management: a. Define scope and control scope
318. lntersections WBS & OBS a. Project overlap b. Cost Account
319. Ultrasound test used to determine - ultrasonic a. b. c. d.
Cracks Position of cracks Length of of cracks All of above
320. What is the most sensitive period in the project? Initial period
321. What is least influential in projects? a. Time b. Materials c. Manpo Manpower
322. NFPA standard National Fire Protection Association The leading information and knowledge recourse of fire, electrical and related hazards Testing of Fire alarm sound according to NFPA standard – Answer: Monthly
323. Condensate water generated from which part of split unit - Evaporator
324. What Is the system used to extract the air from the basement - Ventilation system
325. What is the name of the upward force which Is equal the downward force and keep the object floating - Buoyancy (uzgon) force
47 Edition 2
UPDA Exam Questions for Civil Engineers 2016 326. At which part of project the following take place: design change, scheduling and planning - Planning & Execution part
327. Bolt size: M 33x3 means - 33 related to bolt diameter and 3 related to pitch distance
328. Water start boiling at - Saturated liquid
329. A material that makes deformation under sheer stress is: a. b. c. d.
Liquid Gas Solid Fluid
330. If you Increase the water cement ration in the concrete: a. b. c. d.
Concrete will lose its specifications Decrease the hardening time of concrete Decrease the slump Increase the slump
331. If you were awarded a project, you will start work: a. One week before the approval of the authorities b. After the approval of the authorities c. One day before the approval of the authorities
332. A moving tire on the ground will produce: a. b. c. d.
Potential energy Kinetic energy in translation Kinetic energy in rotation Kinetic energy in translation and rotation
333. One of the following is not process of the project: a. Concept
48 Edition 2
UPDA Exam Questions for Civil Engineers 2016
334. If you are are going going to start with oil pipeline construction which is the following engineer you are going to choose: a. b. c. d.
Petroleum Chemical Civil Mechanical
335. Car dashboard is made by Fiberglass
336. If you have have body moving around circle with speed, the direction of centripetal force from the center is away or toward
337. The propensity of a material to undergo permanent deformatio n under load: a. ductility b. shear stress c. plasticity
338. What is the least bothered bothered constraint on project execution: a. Performance
339. Isolated system is a system that: a. Neither mass or the energy will enter or leaves the system
340. 0ne of the below listed bonds is not considered considere d as a strong bond: a. Van-der Waals bonds b. Metallic bond c. Ionic bond
341. Classification of gravel from Largest to Smallest by a. Flakiness Index
342. Sample Collected from SPT will be used to calculate a. Liquid limit b. Sieve analysis
49 Edition 2
UPDA Exam Questions for Civil Engineers 2016 c. Hydrometer Test d. All the above
343. Product of engineeri engineering ng materials test for Reliability and Suitability will be done by: a. Testing Engineer
344. Concrete Strength is inversely proportion to Water Cement Ratio 345. Test Conducted Conducted in Sand and Gravel type soils: a. Shear BOX test
346. ………………..rule of Elasticity is…………… a. Young's Young's modulus, which is also known as the elastic modulus, is a mechanical property of linear elastic solid materials. It defines the relationship between stress (force per unit area) and strain (proportional deformation) in a material.
347. Problem a lattice? In mathematics, a lattice is one of the fundamental algebraic structures.
348. Maximum possible value of Compacting Factor for fresh (green) concrete is: a. 1.5
50 Edition 2
UPDA Exam Questions for Civil Engineers 2016
349. The pin-jointed 2-D truss is loaded with a horizontal force of 15 KN at joint S and another 15 KN vertical force at joint U, as shown. Find the force in member RS (in KN) and report your answer taking tension as positive and compression as negative.
RS =7.5 KN Tension
350. In its natural condition, a soil sample has a mass of 1.980 kg and a volume of 0.001m 3. After being completely dried in an oven, the mass of the sample is 1.800 kg. Specific gravity Gis 2.7. Unit weight of water is 10 KN/m3. The degree of saturation of the soil is: a. 0.65
351. Four columns of a building arc to be located within a plot size of 10m x 10m. The expected load on each column is 4000 KN. Allowable bearing capacity of the soil deposit is 100 kN/m2• The type of foundation best suited is a. isolated footing b. raft foundation
51 Edition 2
UPDA Exam Questions for Civil Engineers 2016 c. pile d. combined footing
352. Concrete gains strength due to: Hydration of cement
353. Before starting work at site, the major factor has to be checked is? - Approval from MMUP (Ministry (Ministry of Municipality and Urban Planning) Planning) / Civil / Defense etc.
354. Final as built drawings for what purpose - To keep record for later maintenance
Q: What are joints in concrete? Why are they necessary? A: Joints A: Joints are pre-planned cracks to accommodate the expansion and shrinkage of concrete, caused by changes in moisture and temperature. Although irregular cracks are unsightly and difficult to maintain, they generally do not affect the integrity of the concrete. Cracks in concrete can be controlled and minimized by properly designed joints. There are three types of common joints: 1. Contraction joints 2. Isolation or expansion joints 3. Construction joints Q: Why does concrete crack? A: Concrete, A: Concrete, like all other materials, will slightly change in volume when it dries out. Q: How does temperature affect concrete? A: Three factors control the set time, strength gain and overall durability of concrete: time time,, temperature and temperature and moisture moisture.. These factors are interdependent on each other. The ideal temperature for concrete is 10oC. C. If If the temperature is too high, the concrete can dry out prematurely and not reach its desired strength. It can also crack from rapid shrinkage. If the temperature is to low, the concrete set time and strength gain can be reduced and the concrete can be subjected to freezing while water i s present and have severe freeze/thaw damage. Q: Why is curing necessary for concrete? A: Concrete A: Concrete develops strength ONLY in the presence of moisture, therefore it is absolutely important that it is kept moist after casting. If concrete is allowed to dry out, it will not develop to the strength it was designed for. Q: What are the causes of Honeycombing? A: Honeycombing A: Honeycombing is caused by a number of different reasons: 1. Insufficient compacting or vibrating 2. Segregation of the concrete when it i s allowed to free-fall from heights over three feet
52 Edition 2
UPDA Exam Questions for Civil Engineers 2016 3. When the steel reinforcement is too close to the formwork (boxing) 4. When the formwork is not nailed tight and the grout from the concrete leaks out 5. When too stiff a concrete is used without the proper vibrating equipment Q: What is segregation? A: Segregation A: Segregation is the separation of coarse aggregate from cement paste. It mainly occurs due to excess water, resulting in the non-cohesiveness of concrete. Q: What is workability of concrete? A: The ease of placing, compacting and finishing of concrete in t he desired manner is its workability. Normally the workability is measured through slump; higher the slump, higher the workability
Sand stone is sedimentary rock Stainless steel contains 18% of chromium and 8% nickel Bitumen in A. solid state, is called asphalt A.solid B.semi B. semi fluid state, is called mineral tar C.ffluid state, is called petroleum C. D.aall the above. D. For the manufacture of Portland cement, the proportions p roportions of raw materials used, are - lime 63% ; silica 22% ; other ingredients 15% Initial setting time of cement for asbestos cement products should be not less than - 90 minutes A badly mixed cement concrete results in - honey combing The mixture of different ingredients(sastojci) of cement, is burnt at - 1400°C Permissible compressive strength of M 300 concrete grade is - 300 kg/cm2 The process of hardening the concrete by keeping its surface moist is known - Curing Separation of water or water sand cement from a freshly concrete, is known - Bleeding
53 Edition 2
UPDA Exam Questions for Civil Engineers 2016 Plywood is preferred as construction material because - The strength of the panel is consistent across all directions Cement stored for longer than 28 days shall be tested for “loss of ignition”
54 Edition 2