This guide has been prepared to assist welding personnel with the preparation of welding procedures required as part of their company certification to CSA Standards W47.1, W47.2 and W186.Descripción completa
Full description
Tank Fabrication ProcedureFull description
procedure
WELDING PROCEDURE QUALIFICATION IMPACT TEST REQUIREMENTS
IMPACT TEST IS REQUIRED FOR MATERIALS AS PER Cl# 2.2.8 & 2.2.9
AUTOMATIC OR SEMI-AUTOMATIC PROCESS
IMPACT TEST AT HAZ Cl# 7.2.2.2
DESIGN METAL TEMP > 500F (100C)
VERTICAL WELD
IMPACT TEST ON WELD METAL Cl# 7.2.2.3
AUTOMATIC OR SEMI-AUTOMATIC PROCESS
IMPACT TEST AT HAZ ALSO Cl# 7.2.2.3
DESIGN METAL TEMP > 200F (-70C)
WELDING AT THE COMPONENT LISTED IN 2.2.9.1 (SHELL PL, SHELL REINFO PL, SHELL INSERT PL ETC) AND ATTACHMENTS OF THESE COMPONENTS