Introduction This eBook is a result of a 3-parts blog series which provided an overview and explanation of major steps and considerations for BW on HANA upgrade and migrations, based on a trial BW 7.5 system and HANA SPS10 • Part 1: Migrating a BW system from anyDB (any database) to HANA involves Preparatory work in the BW system • Part 2: SUM DMO Tool for SAP Upgrade and Migration • Part 3: Post processing on the migrated system Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
1
BW Migration to HANA
Part 1 of 3 Preparation in BW System By OZSoft Consulting for ITConductor.com
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
2
Introduction • This series of publication intends to provide an overview and explanation of major steps and considerations for BW on HANA migrations • Migrating a BW system from anyDB (any database) to HANA involves 1. 2. 3.
Preparatory work in the BW system DMO and Actual migration Post processing on the migrated systems
• This first part focuses on the preparation tasks on the BW system.
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
3
Preparatory work in the BW system Preparation is a collaborative work between Basis, BW support team and ABAP/development team. Create a production copy Sandbox Best practice in doing an upgrade is to create and use a production copy sandbox first before starting with the development system. It offers the following benefits: 1. Identify potential issue and get a fix ready before hitting the other systems used in development and production. 2. Allows optimization of the process to reduce the downtime and impact to the business. The update and migrate tool, SUM’s DMO, provides a special feature which allows repetition of the downtime for optimization.
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
4
Target BW and HANA DB • Recommended to always use the latest BW release/level for the target system. • The target HANA system has been installed as per SAP requirements. • The target support package should be the latest, and ideally installed with the DSP (datacenter service point). • The capacity should meet the result from the sizing report discussed at later stage.
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
5
BW Housekeeping/data clean-up Similar to preparing a BW system for upgrade and/or Unicode conversion, reduction of the data volume should be done normally referred to as BW housekeeping tasks. This will reduce the data to be exported from the source system and imported to the target DB. This will reduce the downtime of the system during the upgrade, and it also reduces the capacity requirement of the target HANA DB. The normal housekeeping/clean-up tasks involves the BW functional team, which includes • • • •
PSA reduction and change log Infocube compression Deletion of temporary objects Deletion of statistics data
In addition, the ‘SAP BW Migration Cockpit’ includes a Housekeeping section for common housekeeping tasks. Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
6
SAP BW Migration Cockpit for SAP HANA SAP provides the BW migration cockpit program, which is the main entry point to all the tools for the BW to HANA migration preparation. It also includes some post-task items (e.g. ASU, Down-sizing – Near-line Storage, extended tables)
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
7
Migration Cockpit • From the cockpit, all the tools needed for can be executed (e.g. sizing, list program codes that can be optimized for HANA). Also incorporated previous tools like ASU, normal housekeeping tasks, BW Checks. • Each tab has different tasks within it. If you hover to the right side ‘Documentation’, it provides either • OSS note which contains the ABAP program to be uploaded to perform the check, and ‘how-to-guide’, e.g. BW Checklist for SAP HANA • Link to the relevant SAP HELP page
• The cockpit is installed by creating ABAP program ZBW_HANA_MIGRATION_COCKPIT from OSS note 1909597, which also contains the guide ’SAP Migration Cockpit’. • The document SAP First Guidance - BW Housekeeping and BWPCA covers some of the major checks/tools • HANA checklist • Sizing Check • Note Analyzer Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
8
Checks tab This section has several items
Upgrade Paths • Install ABAP program from OSS note 2296693, which also contains the documentation. • Sample report below – note that DMO will be used
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
9
Checklist Tool • Install the program ZBW_HANA_CHECKLIST from OSS note 1729988 – which also contains two documents: • How to … Checklist Tool for SAP BW powered by SAP HANA • SAP BW powered by SAP HANA Checklist Tool
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
10
Sample BW Checklist Report
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
11
Other Checks The lower screen contains more checks. The Documentation tab points to the SAP Help page.
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
12
BW (consistency) Checks These are standard BW transactions/programs. • BW Object Checks – this is transaction RSRV
• BEx Query Check – this runs the ABAP program ANALYZE_RSZ_TABLES Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
13
Planning Function Check This run program RSPLS_PLANNING_HDB_ANALYSIS – it checks if a planning function can be executed in memory, with the following default screen • ‘How to check whether a Planning function or Disaggregation in PAK is executed in Memory’ ← provides very good explanation on this subject.
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
14
Sizing This tab contains several sections Sizing Tool • The tool provides an estimated size of eventual BW system in the HANA database. • Note that the figure from this report does not include other memory requirements within HANA (e.g. calculation space). • OSS note 2296290 provides more detail/guide on how the sizing program works, prerequisite, how to run it, and how to read the summary report. One of the attached guide also provide overview on HANA BW Scale Out.
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
15
Sizing Tool • Provides several options/factors/simulation • Output report is written into a file, into the work directory The report has several sections: • Source DB contents, e.g. size of different table types (e.g. infocubes, PSA)
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
16
Sizing Tool Sample Report • Minimum Sizing Requirements - with recommended number of nodes
• Sizing Details
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
17
Iterative Sizing • Run the sizing tool several times with or without selecting any option to compare results of the clean-up/data reduction activities: • Change the filename of the output result for comparison purposes. • Result of each table are shown in the report’s Table Details, broken down by row/column types, and for each table estimated ABAP and HANA size.
Author: Terry Kempis Editor: Linh Nguyen
• There is also an CSV file containing the Table Detail, for easier comparison, containing total_size, ABAP size, HANA size. • Note that some of options can only be implemented after the migration, e.g. Dynamic Tiering. However, it is a good idea to run this several times with several options to see the impact if they are done after the migration, i.e. ‘what if’. • Reference : OSS note 1736976 – Sizing Report for BW on HANA, which contains two document on sizing and Scaleout.
ITConductor.com
18
Future Growth Simulation • This option allows you to extrapolate the size based on growth factor or absolute number.
• With the example above, the report will show minimum and recommended size per year
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
19
Non-Active Data, Dynamic Tiering • This options are another ‘what-if’ scenario, e.g. what if dynamic tiering is used.
Non-Active Data • This is in relation to the new ‘multi-colored’ - refer to blog SAP BW on HANA : Data Classification (HOT/WARM/COLD) • If selected, there will be a section ‘Non-Active data’ in the report.
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
20
Dynamic Tiering • BW on HANA introduced the multi-temperature data. Briefly, data are classified as: • HOT data – accessed very often, should stay in HANA memory • WARM data – infrequent access, using HANA dynamic tiering (i.e. extended storage, extended table), e.g. data more than 2 years old • COLD data – sporadic/infrequent access, using Near-line Storage (NLS)
• PSA tables and Change Logs are considered ‘non-active automatically’ – Reference OSS Note • References: • ‘Big Data Management in HANA BW.pdf’ from OSS note 1983178
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
21
Dynamic Tiering - Brief • Dynamic Tiering (aka extended storage) is another way of reducing HANA memory footprint by moving some data into Dynamic storage server. • For example, data from an infocube which are more 12 months old can be moved to the dynamic storage, hence only the current year’s data are the only ones that occupy the HANA memory. This is done by 1. defining another table with the same definition as the current table, with additional ‘extended storage’ clause. 2. moving the data from the current table to the ‘extended table’ 3. creating a view with a join of the current table and the ‘extended table’. If an SQL issue a select SQL which include data from the extended table, then it is retrieved from the ‘extended storage’ into the Dynamic Tiering server’s memory - but still does not occupy HANA memory • References: • SAP HANA Dynamic Tiering for Using Extended Tables • OSS note 1983178 - HANA Dynamic Tiering
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
22
Memory Configurations • Allowed Memory Configurations • Down-sizing (configuration) – these are post-task activities • The document points to SAP Help portal on the subjects of NLS and Data Archiving
• Down-sizing (execution) • The ‘Move to Extended Tables’ document refers to • OSS note 2557636 – conversion of PSA and write-optimized DSO in SAP-HANA extended tables which also contains document ‘Changing the Multi-Temperature Category of BW objects’.
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
23
Housekeeping The tasks in this section are to be used in conjunction with the ASU tool (under Migration). This has 2 sections: • Housekeeping Automation this is transaction STC01
• Housekeeping Tasks
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
24
Migration ASU Toolbox: • Refer to 1000009 - ASU Toolbox 2008, upload the relevant DMO task list (ASU_BW_70x_75x_DMO_3 .zip). As in other upgrade, there are pre and posttasks. • There are other tools on this tab, but note below.
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
25
WHM • This contains the ‘Transformation Finder’. There are several options/selection on the transformation • Install ABAP program ZBC_TRANSFORMATION_FIND ER from OSS note 1908367 , which also contains the ‘SAP BW Transformation Finder’, a how-to-guide. • The following blog provides a good understanding of the transformation and links to various blogs on this subject, HANA Transformations Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
26
Optimization
• Program to scan custom ABAP codes for potential optimization for HANA. • Install the ABAP program from OSS note 1847431, which also contain the how-to-guide.
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
27
Next – SUM DMO and Migration • Now that we have prepared the source BW system, we are ready to proceed with SAP SUM (Software Update Manager) using DMO (Database Migration Option) to carry out the upgrade and migration of the BW system from anyDB to BW on HANA. • Stay tuned for the next section DMO and Migration.
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
28
BW Migration to HANA Upgrade Migrate
Any DB
Part 2 of 3 SUM DMO Tool for SAP Upgrade & Migration By OZSoft Consulting for ITConductor.com
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
29
Introduction • This is Part 2 of the series of publication which provides an overview and explanation of major steps and considerations for BW on HANA migrations • Migrating a BW system from anyDB (any database) to HANA involves 1. 2. 3.
Preparatory work in the BW system SUM DMO Tool for SAP Upgrade and Migration Post processing on the migrated systems
• This part focuses on the tool used for the migration, prerequisites, optimization and the actual migration steps.
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
30
DMO, Guides • SUM’s DMO (Database Migration Option) is the tool to update and migrate anyDB (any Database) to HANA. • HINT: It cannot be used for pure migration purposes only! If your current release/level already meet the HANA requirement and does not want to do go the latest release/level, then at least update other package (e.g. ST-PI) so that you will have stack xml which is needed by DMO. • Before embarking on doing migration using DMO, first go through the following • ‘SAP First Guidance - Using the DMO Option to Migrate BW on HANA, • ‘Database Migration Option (DMO) of SUM - Introduction’ - it provides a very good introduction of DMO and contains links to other related blog (e.g. optimization, technical background). • All notes in this document and the steps followed in this migration exercise were based on the cookbook, blogs and the references below. • The central note 2257362 for DMO with SUM 1.0 SP 17 • Update of SAP Systems using SUM 17 <— read this one to appreciate the SL Common UI, features, etc. • Database Migration Option of SUM SP17 - Target Database SAP HANA Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
31
DMO (Database Migration Option) DMO is an inplace-migration using SUM (Software Update Manager). The target PAS will replace the source PAS in the same host, using same ID, network configuration
SOURCE PAS TARGET PAS
Source and Target System for this exercise (TARGET) SID ABA BASIS 750/04 HANA DB KERNEL 745 patch 200
(SOURCE) SID ABA BASIS 750/02 SYBASE DB DMO needs two sets of kernel Target software release of the source DB – i.e. 745 patch 200 for SYBASE DB
Author: Terry Kempis Editor: Linh Nguyen
Target Target software software release release of of the the target target DB DB –– i.e. i.e. 745 745 patch 200 for HANA DB patch 200 for HANA DB
ITConductor.com
32
DMO uses memory pipe mode The export and import occurs within the same server, so data is passed through the same memory segment
EXPORT Kernel : 745/200 SYBASE
Memory PP
SOURCE SYBASE DB
Import Kernel: 745/200 HANA
TARGET HANA DB
Reference: DMO: comparing pipe and file mode for R3load
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
33
DMO - more DMO’s migration repetition for testing purposes of the downtime phase See: 4.3.4 Using the Migration Repetition Option for Testing of the DMO Guide
DMO supports MDC The target database in DMO can be a tenant database. DMO has option to create the target DB, if it does not exist yet. DMO Unicode conversion DMO can convert a non-Unicode system to Unicode – at the same downtime. Note that only single-code page is supported, not multi-code (MDMP).
DMO SQL DDL generation DMO generates the DDL in one of its phase, so there is no need to manually run this. Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
34
SLUIGUI – going around
The tab in the right hand side are Legend, More, Task List, Logs, Breakpoints. Clicking on any tab to expand, click again on the tab to hide. Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
35
SLUIGUI - MORE Under More, SUM Guide – this will take you to SAP marketplace, right to SUM guide page SUM Note – this will take you to the central note of the current SUM you are using SAP Help Portal – goes to https://help.sap.com
Log Tail – this is the log ‘tail viewer’. You can choose any log file, e.g. SAPup.log
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
36
SLUIGI – Utilities and Task List
Utilities can also be viewed directly from the ‘extended viewer’
:1128/lmsl/sumabap//doc/sluigui_ext/ Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
37
SLUIGUI – LOGS, BREAKPOINTS Breakpoints can be set from here Logs can be viewed without going to the OS V
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
38
Observer Mode
This feature allows monitoring for the update process from a mobile device or desktop. To use,
1. Prepare the observer mode (create new user obs, add a password, then add group SAPSYS to obs. 2. Start the observer monitor with the following URL, login with the obs user :1128/lmsl/sumobserver/ABA/mo nitor/index.html
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
39
Resetting DMO, source DB instance after migration RESETing the DMO After migration, the source database remains intact. It’s on the state before the shutdown. If for whatever reason, it can be used again after a reset which is provided by DMO. Note that the reset will delete data from the target HANA DB. Reference: DMO technical background Source database after migration After the migration testing, we installed another PAS pointing to the source database – so we ended up with two running systems: 1. A migrated system in HANA 2. The original source ASE system The normal steps in installing a Distributed system are: 1. ASCS instance 2. Database Instance 3. Primary Application System (PAS) But only step 1 and 3 are needed. Note that by skipping step 2, the profile parameter, environment (env.csh) and DB (dbenc.csh) variables may have some missing items. Fortunately, that DMO backup the source system versions, including the kernel for reference/re-use. This is handy for production copy sandbox – for comparison purposes, but not on production. Ensure that this is totally isolated from normal use. Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
40
DMO - Optimization During the days of Combined Upgrade and Unicode Conversion (CUUC) – downtime optimization was a challenge. You need to manually specify table split, which tables to do first, etc. With DMO, tools and features are available to reduce the downtime, including optimized table splitting • Benchmark Tool • Migration repetition
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
41
Benchmarking tool DMO’s ’benchmarking’ (migration) tool is available to simulate the export and import process to check the migration rate/speed. It has repetition option to enable optimization by adjusting the process parameters (SQL uptime, SQL downtime, R3load uptime, R3load downtime). This should be done before the DMO and against a production copy which mirrors the production setting, (i.e. capacity, network, target HANA) HINT: benchmark both export and import to simulate production run
For more details, refer to the following Optimizing DMO Performance
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
42
Migration Repetition/Optimizing downtime DMO provides ‘migration repetition’ to help reduce the system downtime. For each DMO run, the following files are created • ‘MIGRATE_UT/DT_DUR.XML’ - contains statistics for each migrated table • UPGANA.XML
These files can be use for subsequent DMO run to optimize and reduce the downtime. See DMO Guide Cookbook
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
DMO
UPGANA.XML MIGRATE_*_DUR.XML
43
Preparations/Checks - 1 Migration Key - Generate the system migration key License - Generate the license for the target migrated system (i.e. based on HANA DB). Time zone • Make sure both source system and the HANA severs have the same time zone settings and within SAP (transaction STZAC). DB Free space • As a shadow system is created, there should be at least 50Gb database free space, or more, depending on the existing components. SAPLOCALHOST/Hostname Make sure that the profile parameter SAPLOCALHOST matches the hostname in SM51. WARNING: Hostname 'XXXXXXXX' is different from hostname 'YYYYYYYY' system runs with!
If you encounter the issue in the shadow instance, stop SAPup, stop the shadow instance, edit the parameter in the SHADOW profile directory, restart the shadow instance. Resume the process. Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
44
Preparations/Checks - 2 SAP Host agent – install/update to the latest version SPAM Update to the latest SPAM, or download and extract it into /trans/EPS/in SAPCAR download the latest SAPCAR for extraction HANA Client • Download and extract the HANA client • For LINUX PAS, the DMO will install it as part of the migration • For Windows PAS, install it manually before starting the DMO. DOWNLOAD/Stack.xml • The Maintenance Planner is now used to generate the stack.xml and download the target components, including the latest SUM, ACPs, and kernel (for all platforms) Target HANA DB log mode • Set the log_mode parameter to ‘overwrite’ Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
45
Preparations/Checks - 3 Deletion of some BW objects In one of the dialog, you will enter values as per below. Discuss with your BW team.
Delete temporary BW query bookmarks older than ... days:: 99 Delete sent BW query bookmarks older than ... days:: 9 Delete BW traces older than ... days:: 99 Delete BW statistics older than ... days:: 9 SUM After extracting the SUM package, change owner to adm and the group to sapsys As root, register to host agent cd /SUM ./STARTUP confighostagent Normal upgrade preparations are not included in this document, e.g. pre-downtime tasks like queue processing, stopping jobs, locking users, etc.
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
46
Migration Steps/Screenshots - 1 Start DMO http://sid-aba-aba:/1128/lmsl/sumabap//doc/sluigui Extracts from SAPupConsole.log – note that only DMO-related phases are included here ======= This is SAPup release lmt_008 V53.000 - all engines are running ======= =========== Welcome to Software Update Manager =========== Important information for this program is included in * SAP Note 2223738* and further SAP Notes mentioned therein. The keyword is included in the relevant product-specific SAP Note. Read the current version before you start preparing the procedure and check the SAP Note again for changes before you start the procedure.
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
47
Migration Steps/Screenshots - 2 >> 2016/08/05 13:14:32 START OF PHASE PREP_INPUT/MIG2NDDB_INI =========== Database Migration Option =========== Enter the target database type: 01) - No migration 02) * SAP HANA DATABASE TYPE: SAP HANA =========== Migration Parameters =========== Select tables for table comparison checks. 01) * Do not compare table contents 02) - Operate on all tables 3) - Operate on selected tables only Provide a valid migration key for installation number "0123456789". For a detailed description of generating the key, see SAP note *317096* . Migration Key: 1W5gdEM50D001eqtdQQ011e3
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
48
Migration Steps/Screenshots - 3 SAP HANA SCALE OUT Are you running a SAP HANA Scale Out Landscape as a target for this migration? *If so, you can enable the landscape reorganization during the preprocessing of the migration.* . 01) Execute Landscape Reorg Enter a number/range/"all" to change selection or "ok" or to complete Migration Repetition Test cycle This option will stop the tool after the downtime migration phase, enabling a simple repetition of it to optimize the procedure by tuning the parameters (like R3load processes). You should in no case use this option for a productive run! NOT for 01) X Enable Migration Repetition Option production Choose an execution strategy for transaction SGEN. Select option ‘Do not start ABAP load generation during the update’. There is more flexibility when doing it as a post-task (e.g. use more servers)
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
49
Migration Steps/Screenshots - 4 PREP_CONFIGURATION/SUBMOD_MIG_INSTCLIENT/HDB_INSTCLIENT
=========== Target database client =========== The tool needs access to the target database client. Enter the following information: Path to "hdbinst" for client installation: (This is where the HANA DB Client will be installed in LINUX. For Windows, this should be installed before starting DMO) =========== Database Migration Initialization =========== You are going to migrate your system to a new database. Enter the following parameters of the target database: Target Hostname: xxxxxxxx Enter the SID and instance number of the target database instance (might be different from your SAP system): SID of the target database: A4H Target Instance Number: 00 Author: Terry Kempis Editor: Linh Nguyen
Tenant DB name. If it does not exist yet, it will be created during the process. See next slide ITConductor.com
50
Migration Steps/Screenshots - 5 Enter the path of the SAP License file for your migrated SAP system: Target System License: (License key based on HANA DB)
*Additional Information:* Specify the database connectivity data of the target database to be used for the SAP system migration. In case you are using a SAP HANA multitenant database container, specify the connectivity data of the target database tenant. In case you are using a SAP HANA multitenant database container, and want to create a new database tenant, specify the connectivity data of the database tenant to be created. Enter password for target database user "SYSTEM". Enter password for target database SYSTEMDB superuser (MultiDB).
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
51
Migration Steps/Screenshots - 6 =========== Parameters for BW-Specific reports =========== Within the next phases certain BI housekeeping tasks will be performed. Please decide which data shall be deleted in the database. **Caution:* The data deleted during the next phases as specified in the fields below cannot be restored by resetting update process.*
Enter the amount of data to be deleted: Delete temporary BW query bookmarks older than ... days:: 99 Delete sent BW query bookmarks older than ... days:: 9 Delete BW traces older than ... days:: 99 Delete BW statistics older than ... days:: 9
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
Values agreed with BW team
52
Migration Steps/Screenshots - 7 =========== Perform Scale Up (Single Node) Prerequisite on SAP HANA if necessary =========== *Action Required (if condition is met):* *You decided to NOT run the SAP HANA Landscape Reorganization. However, if you run an SAP HANA Single-Node system with scale-up, you must manually import a file with specific SQL-information to enable the optimal table partition. Carry out the following procedure:* 1. Download the appropriate file that is in the attachment of the following SAP Notes: * For SAP Business Warehouse on SAP HANA, see SAP Note 1908075. From the attachment TABLE_PLACEMENT_BW.zip, select the suitable SQL-file. * For SAP Business Suite on SAP HANA or SAP S/4HANA, see SAP Note 1899817. Choose the attachment: TABLE_PLACEMENT_ERP_* or TABLE_PLACEMENT_S4H_* according to the version and SP level of the target system. 2. Edit the downloaded file by replacing all occurrences of $$PLACEHOLDER with your SAP. 3. Import the edited files to SAP HANA using one of the following commands on OS level of the managed system: * */usr/sap/ABA/hdbclient/hdbsql -U SYSTEM -I -E 1* * */usr/sap/ABA/hdbclient/hdbsql -U SUPER -I -E 1* 4. After the import, continue with the migration procedure.
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
53
Migration Steps/Screenshots – Export/Import/Downtime Checks after phase MAIN_SWITCH/SUBMOD_MIG_SWITCH_ORG/SUBMOD_MIG_DOWNTIME_RUN/EU_CLONE_ MIG_DT_RUN were negative! Last error code set: Found 12 failed export processes REPEAT – some errors due to export and import server Found 64 failed import processes capacity (e.g. memory) << 2016/08/10 18:35:33 END OF PHASE MAIN_SWITCH/SUBMOD_MIG_SWITCH_ORG/SUBMOD_MIG_DOWNTIME_RUN/EU_CLONE_ MIG_DT_RUN
Downtime reached, migration repetition prompt =========== Testcycle =========== Downtime migration finished successfully. 01) - Yes, initialize the downtime migration phase and repeat 02) * No, continue with next phase Do you want to repeat the downtime migration phase?: No, continue with next phase Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
54
Next – Post-processing on the New System • Now that we have prepared the source BW system, and • We have completed the SAP SUM (Software Update Manager) upgrade & migration using DMO (Database Migration Option) for the BW system from anyDB to BW on HANA. • Stay tuned for the next section Post-processing on the Upgraded/Migrated System.
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
55
BW Migration to HANA Preparation
Post-processing Upgrade Migrate
Any DB
Part 3 of 3
Post-processing on the Migrated System
By OZSoft Consulting for ITConductor.com
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
56
Introduction • This is Part 3 of the series of publication which provides an overview and explanation of major steps and considerations for BW on HANA migrations • Migrating a BW system from anyDB (any database) to HANA involves 1. Preparatory work in the BW system 2. SUM DMO Tool for SAP Upgrade and Migration 3. Post processing on the migrated system
• This part focuses on post-processing, which includes standard tasks after upgrade and HANAspecific post-tasks. Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
57
Post-processing - general After migrating a BW system to HANA, there are two general groups of post-tasks 1. Standard tasks after a release upgrade or Unicode conversion 2. HANA-specific tasks
After the downtime processing AND before doing anything: 1. Create a backup of the database 2. Configure HANA parameter log_mode to ‘normal’
3. Configure HANA parameter enable_auto_log_backup to ‘YES’
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
58
Standard post tasks Below are some post tasks after a release upgrade/or Unicode conversion. The list is not exhaustive, not necessarily in sequence, and does not include site-specific process. Adapt dialog instances to the new release/kernel Run SECSTORE (OSS note 816861) Run SICK
Configure SAINT parallelism (OSS note 1309506)
For each instances, run SM51 and SM21
RZ12 – configure number of free WPs
Run SGEN (SAP_BASIS first, then the rest)
DB13 – maintain standard jobs
Reconfigure/adapt 3rd party products
RSA1 – check source systems - activate
Import profile parameters
Solution Manager configuration
Note that the DMO tool, automatically run RS_BW_POST_MIGRATION during its post-processing phase, but there maybe a case of running some steps. Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
59
HANA-specific post-tasks • The cookbook, SAP First Guidance – DMO – BW on HANA lists down the tasks and steps in detail. • OSS notes, blogs that were referenced while doing the steps, (i.e. to get more background information), are added in this document. • Some of the tasks need to be a collaborative work with the BW Administrators and Security team.
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
60
HANA-specific post-tasks - 1 Task – Activate new HANA server functions (scriptserver) • Login to the system database container to adjust the scripserver section of the daemon.ini and nameserver.ini Task – Enable ‘Dynamic Range Partitioning’ feature of DataStore objects
• Refer to OSS note 2081135 for background on this Dynamic Range Partitioning Task – Install Application Function Library (AFL) • For the brief on AFL, refer to SAP help page - AFL • For HANA Analysis Process (HAP) background, refer to First Guidance – SAP BW 7.40 powever by HANA - HANA Analysis Process Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
61
HANA-specific post-tasks - 2 Task – Configuring DBMS User Management for SAP HANA • This task need to be done in collaboration with the security team • For more detail/additional document, refer to DBMS Users in SAP NW ABAP 7.40 • Additional information – Configuring DBMS User Management for SAP HANA • SQL syntax to get the SQL_port for the connection information in DBCO select sql_port from sys.m.services where service_name = ‘indexserver’
• SQL syntax to list DBMS user’s assigned roles select * from effective_roles where user_name = ‘’
• If you remove the assigned DBMS user through SU91, the DBMS user will notbe deleted from the HANA side. Remove it through program RSUSR_DBMS_USERS
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
62
HANA-specific post-tasks - 3 • DBMS roles that are available for DBMS users
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
63
HANA-specific post-tasks - 4 Task – Install Smart Data Access (SDA) Drivers • Reference: SAP help page – SDA Task – Transaction RS3HANA_CHECK/ADMIN • This is for SAP HANA view. For background, refer to SAP First Guidance SAP BW 7.40 on HANA - View Generation Task – Create CDS views after migration
• CDS stands for ‘Core Data services’ • For brief on CDS, see Enhanced ABAP development with CDS
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
64
HANA-specific post-tasks - 5 Task – RowStore to Column conversion • In our migration, only empty, temporary tables were listed during the check Task – Check HANA with DBACOCKPIT • No issue found Task – RS_BW_POST_MIGRATION • As the source system was already on 750/02, all mentioned OSS notes were already in place and no issue found.
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
65
HANA-specific post-tasks - 6 Task – ASU Tool box • There are some follow-up post-tasks
Task – RSDU_TABLE_CONSISTENCY • For more information, refer to Table Consistency Check for BW Tables on HANA Task – RSDDB_INDEX_CREATE_MASS • For more information, refer to BWonHANA: InfoProvider column views Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
66
HANA-specific post-tasks – 7 Task - Migration Check – SHDB_MIGRATION_CHECK • Note 1785060 - Recommendations for performing the migration to SAP HANA
Task - RS_BW_POST_MIGRATION • If OSS note 2060342 has been implemented, then run step 12 ‘Create views for InfoProvider’. This was not performed since the system is already 7.50 Task - Repair inconsistent PSA tables No issue found Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
67
HANA-specific post-tasks - 8 Task - Regenerate all Transformations • For reference, see Transformation – Consistency check programs • Refer to OSS note 1408161 – Program for transformation activation The note refers to required input parameters • Transformation ID can be derived from table RSTRAN
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
68
HANA-specific post-tasks - 9 Task - Convert InfoCubes into in-memory optimized
• It is highly recommended to convert existing InfoCubes to SAP HANAoptimized Infocubes to reduce the data load. Note that after the migration to HANA, all newly created InfoCubes will be automatically be SAP HANAoptimized Infocubes. • References: Converting Standard InfoCubes to SAP HANA-Optimized InfoCubes Aspects of the HANA-optimized InfoCube • To check if an infocube is optimized, go to RSA1, under Settings Subtype = ‘SAP HANA optimized Infocube’.
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
69
HANA-specific post-tasks - 10 Task – Migrate BW Workspaces • Report RS_BW_POST_MIGRATION – steps 12 - 15
For explanation on ‘Unload Priority’, refer to SAP BW on HANA: Data Classification
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
70
HANA-specific post-tasks - 11 The following tasks were not performed in our migration, some of them maybe required to take advantage of simpler data models on BW, and especially with the new BW/4HANA, just announced by SAP in Sep-2016: • Converting DataStore Objects and Infocubes into advanced DSO • Convert MultiProvider to CompositeProvider
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
71
Summary The SAP BW upgrade and migration to SAP HANA has over 100 steps, and each environment maybe a little different based on the usage scenario and customer specific data encountered. However, these publication seek to provide an overview of the processes for planning and guidance so that you can confidently create a roadmap for BW on HANA and even next generation BW/4HANA migration involving: • Preparation of the source BW system • Carrying out the SAP SUM (Software Update Manager) upgrade & migration using DMO (Database Migration Option) for the BW system from anyDB to BW on HANA. • Finally, post-processing on the Upgraded/Migrated System. GOOD LUCK! Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
72
About OZSOFT OZSOFT CONSULTING HEADQUARTER 20660 Stevens Creek Blvd., Suite 261 Cupertino, CA 95014. USA
Email: [email protected] Worldwide: +1 (408) 416-2482 North America Toll-free: +1 (888) 876-2482 http://www.ozsoft-consulting.com
Company > Delivering IT, with Peace of Mind! Specializing in SAP since 1996 Services SAP on AWS (Amazon Web Services) Cloud-based Managed Services Plan, Practice, Perform & Perfect IT • SAP Implementation: SAP Netweaver, SAP HANA, SAP BusinessObjects architected for secure, scalable, high-performance and availability, as well as time/cost efficiencies. • SAP OS/DB Migration: Certified migrations using best practices to mitigate risks and minimize downtime. Combined Upgrade and Migration support. • Cloud Excellence Operations: IT Process Automation increases operating efficiencies, and agility best suited for cloud services. We provide partial to fully managed services while your SAP environment runs at AWS, using IT-Conductor for Cloud-based monitoring & automation.
Software Solutions Full suite of SAP systems monitoring solutions for Microsoft Systems Center Operations Manager (SCOM) focus on Availability, Alerting, and Performance Management: • SAP Management Pack • HANA Management Pack • BusinessObjects Management Pack • ASE Management Pack Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
73
About IT-Conductor IT-CONDUCTOR HEADQUARTER 20660 Stevens Creek Blvd., Suite 261 Cupertino, CA 95014. USA
Email: [email protected] Worldwide: +1 (408) 416-2565 North America Toll-free: +1 (888) 666-2899 http://www.itconductor.com
Company > Stop Guessing, Start Managing! IT-Conductor is the AMMO you need to: • Automate • Monitor • Manage & • Optimize your SAP Performance & Operations including Performance Testing/Tuning as a Service. IT-Conductor was officially founded in 2014 after more than 10 years of turning a big idea of automating IT into a practical solution. The big idea is to enable customers to "Stop Guessing, and Start Managing" their enterprise IT application environment. It's all about the integrated ability to collect vast amount of application and supporting infrastructure instrumentation data into standardized and time-synchronized intelligence that can be action upon.
> Monitor SAP WITHOUT Installation! The power of IT-Conductor lies in it's ease of access through a cloud platform to simply hook up to your environment via a secured connection and start agentlessly monitor and manage the applications, databases, hosts and related infrastructure components. Templates make application discovery fast and easy to go from monitoring to managing in minutes! ___________________________________________________________________________________________________________________________________________
© 2016 IT-Conductor, Inc. and/or its affiliates. All rights reserved. IT-Conductor is a trademark of IT-Conductor, Inc. or its affiliates. This publication may not be reproduced or distributed in any form without IT-Conductor’s prior written permission. If you are authorized to access this publication, your use of it is subject to the Terms of Service and Copyright and Trademarks posted on itconductor.com. The information contained in this publication has been obtained from sources believed to be reliable or from IT-Conductor’s own experience and research. IT-Conductor disclaims all warranties as to the accuracy, completeness or adequacy of such information and shall have no liability for errors, omissions or inadequacies in such information. This publication consists of the opinions of IT-Conductor organization and should not be construed as statements of fact. The opinions expressed herein are subject to change without notice. Although IT-Conductor may include a discussion of related legal issues, IT-Conductor does not provide legal advice or services and its research should not be construed or used as such.
Author: Terry Kempis Editor: Linh Nguyen
ITConductor.com
74
Let
itconductor.com • Any Questions? @itconductor
• Contact Info: Linh Nguyen
[email protected]
Terry Kempis
[email protected] 75