Re-farming Planning process Request for re-farming Step1: 2G spectrum allocation to 3G Step2: 2G and 3G zone setup
Step3: 2G network analysis Step4: 2G network re-planning Step5: Project Implementation Step6: Prelaunch and Optimization Step7 :Reporting Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 2
© Nokia Siemens Networks 2012
If 2G network replanning results are not acceptable, then Step1 and/or Step2 can be repeated
Spectrum Carving
Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 3
© Nokia Siemens Networks 2012
Spectrum Allocation (Sandwich Model) recommended for efficient frequency re-farming • Closest frequencies at both sides of the WCDMA carrier can be optimally utilized for GSM frequencies • Guard bands can be minimized with Flexi BTS 4.2 MHz filter and coordinated network deployment 4.2 MHz
Other operator’s band
WCDMA/HSPA
2.2 MHz 2.4 MHz 2.6 MHz = WCDMA/HSPA = Non-BCCH GSM, coordinated deployment = BCCH GSM, coordinated deployment = GSM, uncoordinated deployment Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 4
© Nokia Siemens Networks 2012
Other operator’s band
Spectrum Allocation (Sandwich Model) recommended for efficient frequency re-farming • Spectrum Carving scenario Guard band / Joker
G900 BCCH - TCH
G900 TCH
U900
U900 center freq.
GSM UMTS 900 GSM 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 • GSM spectrum allocation strategy : • Ad-Hoc ( non group BCCH-TCH)
Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 5
© Nokia Siemens Networks 2012
2.2 MHz 2.4 Mhz 2.6 Mhz
Zone Setup
Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 6
© Nokia Siemens Networks 2012
Zone setup GSM900 (with U2100 zone), Buffer zone, GSM900 with U900 zone
• Core Zone - Limited GSM900 band area (re-farming area) - The limited GSM900 band is used together with 3G on U900 band. • Buffer zone - Buffer zone is having limited band for GSM900 (after re-farming) with UMTS on 2100 band. It is required to provide enough separation between the same frequencies of GSM900 (full band) and UMTS900 (co-channel IF) • Common Zone - Full GSM900 band area - The whole available 900 band is used for GSM, UMTS and U2100 band.
GSM Limited band + U900 4.2 MHz must be re-farmed and 2 Channels on the border should be used for non BCCH only
Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 7
© Nokia Siemens Networks 2012
GSM (Limited band) + U900 4.2 MHz must be re-farmed and 4 Channels on the border should be used for non BCCH only
GSM (Whole band) + UMTS 2100
UMTS900 Interference Scenarios Interference Main Scenarios UMTS900 site GSM site cosite UMTS900 site (Coordinated Scenario) GSM site in Buffer Area (Uncoordinated Scenario with Adjacent Channels) GSM site in GSM Network Area (Uncoordinated Scenario Co-Channels)
UMTS900 Area Buffer Area GSM900 Network Area Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 8
© Nokia Siemens Networks 2012
Network Analysis
Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 9
© Nokia Siemens Networks 2012
Network Analysis (Planning inputs and outputs) Inputs from current network :
• • • • •
Re-farming strategy (site coordination, UMTS 900 site list, planning area etc..) Configuration analysis (Capacity) Performance analysis Parameter/feature analysis Traffic analysis and Traffic forecast (traffic increase/decrease due to UMTS 900)
Outputs :
• • • • •
New configuration plan (max configuration on re-farmed band) New capacity plan (add 1800 sectors/move traffic to UMTS900/2100) New frequency plan (Optimizer)
New HOC&POC plan New feature implementations to maintain QoS of network Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012
10
© Nokia Siemens Networks 2012
Step by Step GSM capacity Analysis List cells in core and buffer
A
Calculate traffic to be off Loaded
No GSM cell > 3 TRXs
End yes
Any collocated DCS
Downgrade to 3 TRXs
No
yes
Is 3 TRXs enough to handle existing traffic
yes
End
Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 11
© Nokia Siemens Networks 2012
Upgrade DCS TRX
No
A
End
New Collocated DCS
Capacity planning - example Traffic increase (forecast) Half rate ratio ave. # of TSLs used for (E)GPRS # of TCHs on BCCH / TRX # of TCHs on nonBCCH / TRX
# of required TSLs with FR and HR
# of required TSLs with GSM FR and HR and for ave. (E)GPRS traffic
# of required DCS TSLs - 1 TRXs on GSM
# of required DCS TRXs - 1 TRXs on GSM
or traffic volume needed to be reallocated to U900/U2100
# of required DCS TSLs - 2 TRXs for GSM
# of required DCS TRXs - 2 TRXs for GSM
or traffic volume needed to be reallocated to U900/U2100
UMTS2100_COLOCATED
2 TRXs/cell on GSM 25542 6232 15979
BH traffic forecast (Erl.)
1 TRX/cell on GSM 52740 9495 32654
BH traffic (Erl.)
Calculations based on inputs 53368 70872 79938
# of DCS TRXs
48516
# of GSM TRXs
BT200321 BT200461 BT200462 BT200463 BT200561 BT200562
Inputs on BTS level 14428 11869 2559
The same Effective Frequency Load is assumed after re-farming
# of TRXs
4533
Cell name
Sum:
10% 40% 2 6 7
1 2 2 2 3 3
1 2 2 2 2 2
0 0 0 0 1 1
0.64 9.98 10.59 1.86 10.37 5.52
0.71 10.98 11.65 2.05 11.40 6.07
3 15 16 5 16 10
5 17 18 7 18 12
-1 11 12 1 12 6
0 2 2 1 2 1
0.00 6.51 7.05 0.00 6.85 2.58
-7 5 6 -5 6 0
0 1 1 0 1 0
0.00 1.38 1.92 0.00 1.72 0.00
0 0 0 0 1 1
Aim to ensure that excessive GSM 900 traffic (due to max configuration after refarming) will be planned to move either 1800 band or UMTS Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 12
© Nokia Siemens Networks 2012
Network re-planning
Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 13
© Nokia Siemens Networks 2012
Why Network re-design Objectives : • To Modernize the network • Common standard • Expansion readiness • Feature readiness • Simplify network, easy to control. • High quality, secure, save • Nice esthetics
Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 14
© Nokia Siemens Networks 2012
Re-design activities Massive site evaluation is takes time to evaluate the design manually. Using Automatic Cell Planning tool to evaluate the network NSN uses ACORN as ACP tool. ACP tools mainly supports for Network configuration & optimization services - outcome:
-
Heights Tilts (mechanical, electrical) Antenna Types Azimuth Power Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012
15
© Nokia Siemens Networks 2012
Automated Configuration & Optimization of Radio Networks
Frequency re-planning / GFP Implementation use Optimizer tool
Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 16
© Nokia Siemens Networks 2012
Step by Step Optimizer (1)
Recommended Time frame A - B -Minimum 14 days -Maximum 20 days
A
Define Frequency Allocation
Analyze OSS measurement duration
Define cells in core and buffer
Measurement > 14 days ? Any co-BCCH and co BSIC problem ? yes
No
No
yes yes Retune co-BCCH and coBSIC
A
Neighbor optimization
OSS measurement
B Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 17
© Nokia Siemens Networks 2012
Step by Step Optimizer (2) C B Plan approved by Isat ?
Create Interference Matrix
No
yes Upload main KPI
Time frame B - C - Minimum 7 days
A
GFP implementation
Neighbor Optimization KPI Evaluation
Create Frequency Plan KPI achieve ?
No
Verify optimization result yes
C Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 18
© Nokia Siemens Networks 2012
END
A
Pre Launch and Optimization (Layering Strategy)
Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 19
© Nokia Siemens Networks 2012
Optimization - Traffic steering GSM DCS Objectives : Is to reduce interference on GSM 900 layer, due to limited GSM 900 spectrum after spectrum carve for UMTS900. Applying traffic steering strategy to offload GSM traffic into DCS, it reduces the usage of GSM spectrum. Parameter Control and performance monitoring must be check closely.
Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 20
© Nokia Siemens Networks 2012
Optimization - Layering GSM - U900 – U2100 Objectives : The strategy is to use U900 sharing the traffic from U2100, where U2100 coverage and quality is poor. U900 is aiming for Deep Indoor Coverage and Cell border. U900: Cell Border and Deep Indoor Coverage (Coverage Layer)
U2100 : Access and Main Data Layer (Capacity Layer)
Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 21
© Nokia Siemens Networks 2012
Multicarrier Layering Overview Cell Reselection Idle Mode, CELL_PCH, • URA_PCH •
Hierarchical Cell Structure (HCS) Measurement Power Offsets
3G System
Re-direction Transition to CELL_DCH
• •
Directed RRC Connection Setup Common Channel Layering
• • • •
HSPA Capability based Handover Load and Service based Handover Inter-Frequency Handover Inter-System Handover
UMTS 2100 (F1/F2)
Handover Within CELL_DCH
UMTS 900
UMTS 900
Intersystem Hand Over 2G System
• • •
Requirement to balance traffic between network layers While UMTS900 device penetration is relatively low then all UMTS900 devices should be pushed to UMTS900 layer Traffic management can be applied in both Idle and Connected Mode states Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012
22
© Nokia Siemens Networks 2012
GSM
DCS
Multicarrier Layering Strategic
Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 23
© Nokia Siemens Networks 2012
Generic parameter
Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 24
© Nokia Siemens Networks 2012
GSM 900 re-farming and UMTS 900, 2100 NSN Solution
Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 25
© Nokia Siemens Networks 2012
Roll out, Modernization and Re-farming Project Scope (Implementation): 1. Rollout and Modernization
2.
Swap / Modernization BTSs with Feeder less Swap Antennas (new triple bands antenna) and Aerial redesign (high, panning) TRX Upgrade – Downgrade ( GSM & DCS) New site (DCS) Implementation Band Pass Filter*
Re-farming
3.
Spectrum re-arrangement (GFP with Optimizer)
WCDMA Integration
U900 & U2100
* High Rejection for Co-site CDMA, Low Rejection Non Co-site CDMA. Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 26
© Nokia Siemens Networks 2012
Roll out, Modernization and Re-farming Project Scope (KPI Monitoring): 1. Rollout and Modernization
2.
Swap / Modernization BTSs with Feeder less KPI Maintain Swap Antennas (new triple bands antenna) and Aerial redesign (high, panning) TRX Upgrade – Downgrade ( GSM & DCS) New site (DCS) KPI basic Implementation Band Pass Filter for Co-site CDMA and Non Co-site CDMA.
Re-farming
3.
Spectrum re-arrangement (GFP with Optimizer) KPI Maintain
WCDMA Integration
4.
U900 & U2100 KPI basic
Cluster optimization :
Scope : Under Core Zone, Buffer Zone, and Common Zone KPI Methodology and KPI baseline & target : TBD
Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 27
© Nokia Siemens Networks 2012
Implementation process Site audit on refarming area
Zone setup (Core – Buffer)
NetAct Planner analysis
Antenna Optimization with ACP tool Amount of Antenna changes = SMALL
Maintain using current parameters (bcch, bsic, neighbor, sc, etc)
Final Plan Site release & BSS – RAN Parameter update
1 . Define mini cluster (for implementation strategy, performance monitoring) 2. Create Drive route
Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 28
© Nokia Siemens Networks 2012
KPI Baseline taken
Project implementation Using mini Cluster Base
Reporting
Amount of Antenna changes = BiG
Run AFP on NetAct Planner for ARFCN, neighbor, etc
Implementation Validation, Performance Monitoring and Optimization
B
Implementation process B
Incase the mini cluster Performance experience severe degradation, then run optimizer tool
Spectrum Carving by Optimizer tool
Performance Monitoring and Fine Tuning
Performance Monitoring and Fine Tuning
Continue Project Implementation for next mini Cluster
Spectrum Scanning 900 Mhz on CORE Zone
GSM TRX D/G
Spectrum Clean on refarming area
No
Yes
U900 Integration
Performance Monitoring and Fine Tuning
U900 Spectrum Scanning on Buffer zone
Spectrum Overshooting
No
Yes Continue Optimization and Performance stabilization Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 29
© Nokia Siemens Networks 2012
Final Acceptance
Clustering Semarang area
Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 30
© Nokia Siemens Networks 2012
Dept. / Author / Date
Clustering Semarang + Jogjakarta
Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 31
© Nokia Siemens Networks 2012
Dept. / Author / Date
Clustering Jogjakarta
Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 32
© Nokia Siemens Networks 2012
Dept. / Author / Date
Roll out, Modernization and Re-farming Project Activities: 1. Spectrum Allocation Plan for 2G
A part of available GSM frequency band is reallocated to U900.
2. Zone area setup
Core Zone : The limited GSM900 band is used together with 3G on U900 band. Buffer Zone : Having limited band of GSM900 after re-farming together with 3G on U2100 bands. It is required to provide enough separation between the same frequencies of GSM900 (full band) and UMTS900
Common Zone : Full 900 band used together
3. Site Audit
TSSR report Update site database on Tools (NetAct Planner, NetAct Optimizer)
4. GSM + DCS +U2100 Analysis (Coverage, Capacity)
ACP tool to evaluate the antenna optimization Comparison Coverage plot prediction (G900, G1800, U2100) Identify coverage risk, and give solutions Check Radio resource, & Transport capacity dimensioning Ensure GSM 900 capacity dimensioning per site is 3/3/3
Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 33
Ensure NO Live REPEATER / MCPA integrated at “CORE & Buffer Zone Area”
© Nokia Siemens Networks 2012
Roll out, Modernization and Re-farming 5. Site data plan and BSS Plan
Final site configuration (BTS Capacity, aerial setting, etc) Final Site drawing Propose new sites incase existing site could not absorb the traffic BSS feature for Capacity and performance enhancement if available
6. Define mini clusters on Core zone, and Buffer Zone
Mini cluster defined is for project controlling (integration, performance monitoring and KPI benchmark) Each cluster contain 10 – 15 sites (resources dependency) Define Drive Test route, and OSS KPI baseline time frame agreed between NSN – Indosat
7. KPI Performance Baseline For acceptance Cluster base is preference
Mini cluster Drive test and OSS performance baseline report (mini cluster base) Drive test and KPI baseline report
Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 34
© Nokia Siemens Networks 2012
Roll out, Modernization and Re-farming 8. Provide BSS - RAN data Parameter (PES)
PES shall be deliver to Project team 5 days before implementation date. PES shall be complete and Correct before Integration date ,Incase any error during integration due to unproper parameter value, correction shall be made on Immediate basis. BSS - RAN parameter update (BCCH, SC, Handover..etc) U900 sites “must not on service”
9. Capacity expansions implementation (HW & SW)
at this phase (NO PES for U900 send to project team)
Ensure BSS- RAN PES implemented as Plan Ensure the scope KPI basic for new DCS Update Network Performance reporting (main KPI, Quality statement, SSV, DT reporting)
10. Swap and replaced to new antenna system (triple bands with feeder less)
Ensure Aerial Setting, RET Calibrated, Filter are implemented as plan, as well as radio parameter update. Ensure the scope activity on swap modernization (DT) Update Network Performance and Capacity Report (main KPI, Quality statement, SSV, DT reporting). NetAct Optimizer site Database Update Running NetAct Optimizer for new Frequency, SC allocation, if optimization is required. The process will be done when each cluster execution is completed.
Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 35
© Nokia Siemens Networks 2012
Roll out, Modernization and Re-farming 11. Swap / Modernization + Upgrade BTS plus / Ultrasite
Ensure PES implemented as Plan Ensure the scope activity on swap modernization (DT, KPIs) Update Network Performance reporting (main KPI, Quality statement, SSV, DT reporting)
12. New DCS implementation
Ensure PES implemented as Plan Ensure the scope KPI basic for new DCS Update Network Performance reporting (main KPI, Quality statement, SSV, DT reporting)
13. Traffic steering Management (GSM DCS)
Containment on DCS as much as possible, obtain the cell performance with no degrading the KPI Urban area: drive the traffic into DCS band in idle and dedicated mode Suburban and rural area where: drive to GSM band in idle mode only DT is to ensure RX level and Quality
14. Performance and Capacity Monitoring :
Main KPIs, Traffic (Voice and data), Capacity resources (Traffic and signaling)
Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 36
© Nokia Siemens Networks 2012
Roll out, Modernization and Re-farming 15. Provide BSS data Parameter (PES)
PES for Down Grading GSM 900 Capacity with detail HW Identification
16. Downgrading G900
Ensure Capacity downgrading as plan Ensure quality and resource utilization
17. Network Performance stabilization
Network Performance Monitoring and Fine tuning Define the KPI baseline
18. GFP (G900 + G1800) preparation use OPTIMIZER tool
Optimizer Data Collection & measurement Post processing GFP plan review (sanity check, Netact Planner C/I, C/A coverage plot) Interference matrix GFP Proposal to Indosat to obtain the approval
19. Drive test (idle & dedicated for GSM only) before GFP Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 37
© Nokia Siemens Networks 2012
Roll out, Modernization and Re-farming 20. GSM 900 & GSM 1800 GFP (Optimizer)
GFP Implementation (automatic by network or Manual) TBD Ensure parameter implemented as plan DT verification (functionality test) Performance monitoring and parameters fine tuning
21. Drive test (idle & dedicated for GSM only) after GFP 22. Spectrum scanning 900 MHz (allocated for U900)
Scan (GSM ARFCN) focus at CORE ZONE, by using Scanner box (SEEGULL) not Mobile Phone (UE) Scan report GSM per ARFCN in core zone with limit Level -155 dB (U900 Isolation) Template TBD Analysis & Reporting Physical tuning if necessary Submit scanning Report to Indosat
23. Fine tuning cell by cell (parameter & Physical)
HOC - POC parameter tuning optimization
Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 38
© Nokia Siemens Networks 2012
Note: • Data for analysis and performance monitoring must be use from “Busy Hour Busy Day” • Any performance issue due to congestion or high utilization, implementation of capacity expansion is a must
Roll out, Modernization and Re-farming 24. RAN data Parameter (PES) 25. U900 on service
Ensure parameter, feature implemented as plan Update Network Performance reporting (main KPI, Quality statement, SSV, DT reporting) Ensure the scope activity (DT, KPI basic, included Intersystem HO, Inter Freq HO) Ensure Load balance capacity among multiband technology (GSM 900 – DCS 1800 – UMTS 2100)
26. Spectrum scanning 900 MHz
Scan UARFCN focus at BUFFER ZONE, by using Scanner box (SEEGULL) not Mobile Phone (UE) Scan report GSM per ARFCN in core zone with limit Level -155 dB (U900 Isolation) Template TBD Analysis & Reporting Submit scanning Report to Indosat
27. Performance Monitoring:
GSM 900 Interference band check U900 KPI basic (included Intersystem HO, Inter Freq HO)
28. Final KPI Acceptance Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 39
© Nokia Siemens Networks 2012
Note: • Data for analysis and performance monitoring must be use from “Busy Hour Busy Day” • Any performance issue due to congestion or high utilization, implementation of capacity expansion is a must
Pre Launch and Optimization Optimization Strategy and Process
Customer CustomerConfidential Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 40
© Nokia Siemens Networks 2012
Optimization Strategy Optimization Strategy
Accessibility Improvement
Traffic & Capacity Management
Signaling Analysis and Improvement
Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 41
© Nokia Siemens Networks 2012
Transport Network Audit
Retain-ability Improvement
(E)GPRS/R99 / HSDPA Analysis and Improvement
Frequency Optimization
System Integrity Improvement
Coverage Assessment
Handover Optimization
Optimization Strategy
NETWORK AUDIT - Parameter & Neighbor audit - Site Configuration - Capacity audit
WORST PERFORMANCE CELL CBCCH & ANTENNA GRID ALLIGNMENT TRAFFIC MANAGEMENT
PARAMETER OPTIMIZATION TRANSPORT OPTIMIZATION CAPACITY OPTIMIZATION FEATURE OPTIMIZATION (E)GPRS, R99, HSDPA OPTIMIZATION AMR OPTIMIZATION
COVERAGE ASSESMENT & OPTIMIZATION HARDWARE FAULT MONITORING & ESCALATION STRATEGIC FREQUENCY PLANNING & OPTIMIZATION VIP CUSTOMER COMPLAINT HANDLING
2G & 3G RADIO NETWORK PERFORMANCE & OPTIMIZATION Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 42
© Nokia Siemens Networks 2012
KPI EVALUATION - ACCESSIBILITY Background
Accessibility Performance in Wireless Network is the Key Factor as Accessibility Performance is an indication of the Ability of the Network to serve it’s subscriber for all offered services. Accessibility is measured as the successful Signalling (RRC) Establishment and RAB Establishment.
Objective
By Delivering this activities : Improve the Network Accessibility as per Our KPI Commitment Detail Investigate of All Resources that impacting Network Accessibility to find the root cause of Congestion Issue. Review the process and Methodology of Network Capacity Monitoring
Main Activities
Regional RNC Accessibility Performance Review Accessibility Performance Drops Distribution Analysis & Investigation Accessibility Performance Drops Improvements and Resolution Accessibility Performance Parameters Optimization
Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 43
© Nokia Siemens Networks 2012
KPI EVALUATION - RETAINABILITY Background
Objective
By Delivering this activities : Improve the Network Retain-ability Performance as per Our KPI Commitment Detail Investigate of All Macro Areas that impacting to performance to find the root cause of Drop Call Issue. Review the impact of current Network Strategy to the Retain-ability Performance.
Main Activities
Regional BSC/RNC Accessibility Performance Review Retainability Performance Drops Distribution Analysis & Investigation Retainability Performance Drops Improvements and Resolution Retainability Performance Parameters Optimization Handover and Soft Handover performance analysis
Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 44
Retaianability Performance is also the Key Factor as Retainability is the indication of the Network Ability to serve the user to retain the requested service to the desired duration. Reatainability is measured per Service or RAB (CS, PS, CS Voice, CS Video, PS Interactive, PS Streaming, PS R99 or PS HS)
© Nokia Siemens Networks 2012
KPI EVALUATION - MOBILITY Background
Another important aspect in Wireless Network Service is System Integrity Performance as This KPI is an indication of Quliaty Level of Offered Service. In This Activity, 3 Main KPI are used to measured the 3G Network Integrity Performance i.e. Soft Handover Success Rate Performance Inter Radio Access Technology Handover Success Rate and HSDPA Cell Throughput Performance.
Objective
By Delivering this activities : Improve the Network Integrity Performance as per Our KPI Commitment Detail Investigate of all the issue that impacting to Network Integrity Performance to find the root cause of Low Network Integrity Performance. Review the impact of current Network Strategy to the Network Integrity Performance
Main Activities
SHO Success Rate Improvement IRAT Success Rate Improvement HSDPA Cell Throughput Improvement
Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 45
© Nokia Siemens Networks 2012
Pre Launch and Optimization (Network Statistic)
Customer CustomerConfidential Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 46
© Nokia Siemens Networks 2012
Network Statistics Network statistics is one of the tool to monitoring and that is the one of indicator from network performance. Deliverable shall be delivered to indosat representative as : OSS Data Nokia Siemens Networks collect and ensure the availability of OSS data which is accessible via OMC. Provision of tools arranged in chapters Tool. Daily Statistic Reports Weekly Performance Reports Monthly Executive Performance Report
KPI Achievement At the end of each stage and project, Nokia Siemens Networks provides a complete and comprehensive Performance report in the form of Executive Summary Report and Technical Report. The report is part of the acceptance requirement.
Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 47
© Nokia Siemens Networks 2012
KPI Acceptance KPI Acceptance Method The following methods are applied on acceptance process: Acceptance will be based on KPI Achievement Week of KPI Achievement is one week of the last optimization stage week. KPI Achievement week shall be agreed by Indosat and Nokia Siemens Networks. KPI Achievement is measured by accumulate used counters of 1 week data (7x24 hours) from Monday
to Sunday. The measurement data is based on hourly data. If any different data between Vendor and Indosat, the value will be verified using hourly data. KPI formula to be used in the calculation are based on KPI formula defined by Indosat Acceptance will be based on “Reward or Deduction” Scoring Systems. Nokia Siemens Networks shall submit a complete and comprehensive acceptance report as defined in Reporting chapter before the acceptance. Indosat will issue the acceptance certificate if the target score is achieved.
Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 48
© Nokia Siemens Networks 2012
Pre Launch and Optimization (Drive Test)
Customer CustomerConfidential Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 49
© Nokia Siemens Networks 2012
Drive Test Drive Test is performed for the following circumstance: Verification Drive Test due to Project implementation activities Verification Drive Test after the global parameter change Verification Drive Test for RF troubleshooting The following rules apply in performing Drive Test: The Drive Test data shall be recorded All problems occured during drive test shall be logged for further analysis The scope of drive test is limited for outdoor site The drive test route shall be proposed to Indosat prior the execution
Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 50
© Nokia Siemens Networks 2012
Reporting
Customer CustomerConfidential Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 51
© Nokia Siemens Networks 2012
Project Progress & reporting RF Planning (AOP): Weekly progress AOP Weekly progress KPI Basic (PLO) Monthly progress AOP
Optimization: Weekly Report (activity & KPI performance) Monthly Report (activity & KPI performance) Quarterly Report (KPI Achievement & ATP)
Customer Confidential Indosat 2012 / Version 2-0 / Re-farming Project 2012 52
© Nokia Siemens Networks 2012
Activities RF Planning (AOP): Detail coverage & capacity planning Parameter planning Abis Mapping Review of RNP Criteria (Swap/modernization) RNP Translation (Swap/modernization) Databuild creation for RF (PES, NDB)