BILL OF QUANTITY PEKERJAAN STRUKTUR PEKERJAAN JASA KONSULTANSI PERENCANAAN DETAIL TEKNIS 10 PASAR RAKYAT PD. PASAR JAYA
BILL OF QUANTITY PEKERJAAN STRUKTUR GUDANG RANGKA BAJA 66 X 20 M
No
Uraian Pekerjaan
Satuan
Qty
Harga Satuan
Jumlah Harga
PEKERJAAN STRUKTUR A
Pekerjaan Persiapan
1
Pekerjaan Direksi Keet & Gudang
m2
48.00
750,000
2
Air Kerja & Listrik Kerja
Bln
3.00
1,500,000
4,500,000
3
Mobilisasi Peralatan Dan Pekerja
Ls
1.00
15,000,000
15,000,000
4
Keselamatan Kerja K3 dan Rambu rambu
ls
1.00
5,000,000
5,000,000
B
36,000,000
Pekerjaan Galian & Pondasi
1
Galian tanah biasa sedalam 1 m
m3
24.19
65,000
1,572,480
2
Buang tanah sejauh ±15 m
m3
14.52
45,000
653,184
3
Urug kembali tanah galian
m3
9.68
25,000
241,920
4
Urugan pasir urug
m3
1.45
275,000
399,300
5
Lantai kerja beton tumbuk 1:3:5; t. 50 mm
m2
1.45
42,500
61,710
Pilecap P1 uk. 300/1000/1000 6
-Beton Readymix K-300
m3
6.00
975,000
5,850,000
7
-Bekisting Pondasi
m2
28.80
245,000
7,056,000
kg
370.00
11,500
4,255,000
-Tulangan besi U-24 8
-dia. 10 mm Kolom uk. 1000/1440/1000
9
-Beton Readymix K-300
m3
1.98
975,000
1,930,500
10
-Bekisting Kolom
m2
26.40
245,000
6,468,000
-Tulangan besi U-24 11
-dia. 8 mm
kg
85.32
11,500
981,180
12
-dia. 10 mm
kg
153.92
11,500
1,770,080
C
Pekerjaan Tie Beam
1
Galian tanah biasa sedelam 1 m
m3
44.64
65,000
2,901,600
2
Buang tanah sejauh ±15 m
m3
17.86
45,000
803,520
3
Urug kembali tanah galian
m3
26.78
25,000
669,600
4
Urugan pasir urug
m3
4.65
275,000
1,278,750
5
Lantai kerja beton tumbuk 1:3:5; t. 50 mm
m2
93.00
42,500
3,952,500
Tiebeam TB1 uk. 200/400 6
-Beton Readymix K-300
m3
29.76
975,000
29,016,000
7
-Bekisting Pondasi
m2
297.60
245,000
72,912,000
-Tulangan besi U-24 8
-dia. 8 mm
kg
979.60
11,500
11,265,400
9
-dia. 12 mm
kg
1,990.20
11,500
22,887,300
D
Pekerjaan Plat lantai dasar
1
Pemadatan tanah
m2
1,320.00
7,500
9,900,000
2
Urugan pasir urug
m3
66.00
275,000
18,150,000
3
Lantai kerja beton tumbuk 1:3:5; t. 50 mm
m2
1,320.00
42,500
56,100,000
PT ARTEFAK ARKINDO
PARAF:
1
BILL OF QUANTITY PEKERJAAN STRUKTUR PEKERJAAN JASA KONSULTANSI PERENCANAAN DETAIL TEKNIS 10 PASAR RAKYAT PD. PASAR JAYA
No
Uraian Pekerjaan
Satuan
Qty
Harga Satuan
Jumlah Harga
4
Beton Readymix K-300
m3
264.00
975,000
257,400,000
5
Tulangan wiremesh M8-150
m2
1,320.00
71,000
93,720,000
Sub jumlah Rp.
672,696,024
I. PEKERJAAN PONDASI & PERSIAPAN
II. PEKERJAAN ATAP A
Pekerjaan Struktur Baja
1
Kolom KB1 WF 250x125X5X8
kg
8,131.20
18,500
150,427,200
2
Rangka Kuda-kuda WF 250X125X5X8
kg
4,065.60
18,500
75,213,600
3
Rangka Kuda-kuda WF 125x60x6x8
kg
475.20
18,500
8,791,200
3
Rangka Ikatan antar Kuda Kuda
kg
660.00
18,500
12,210,000
4
Gording C 125x50x20x3,2
kg
12,880.56
22,000
283,372,320
5
Trekstang Besi beton Ø 12
kg
510.03
18,500
9,435,617
6
Ikatan angin Besi beton Ø 12
kg
470.80
18,500
8,709,800
7
Besi siku L 40x40x4
kg
217.88
18,500
4,030,854
8
Baud Ø 12
bh
520.00
22,500
11,700,000
9
- Base Plate t.16 mm
kg
233.13
24,500
5,711,563
10
- Stiffener t.10 mm
kg
609.84
24,500
14,941,080
- Angker Baut Ø19 p.600 mm
11
bh
144.00
45,000
6,480,000
12
Cat meni Besi
kg
28,918.24
3,000
86,754,727
13
Atap Zinkalum Spandex 0,35 mm
kg
1,632.00
59,000
96,288,000
14
Nok ZinKalum
m
68.00
45,000
3,060,000
15
Talang Air
m1
136.00
65,000
8,840,000
16
Plat Penutup Talang Rangka L 40x40x4
m1
136.00
45,000
6,120,000
17
Atao Canopy 6000x3000
m2
144.00
650,000
93,600,000
B
Pekerjaan Penggantian Atap Bangunan Lama
1
Bongkar Atap
m2
966.00
25,000
24,150,000
2
Atap Zinkalum Spandex 0,35 mm
m2
966.00
59,000
56,994,000
3
Nok ZinKalum
m
42.00
45,000
1,890,000
4
Talang Air
m
42.00
65,000
2,730,000 -
II. PEKERJAAN ATAP
Sub jumlah Rp.
971,449,960
III. PEKERJAAN LANTAI DAN DINDING 1
Pas. Batako 40x20x10
m3
873.20
87,500
76,405,000
2
Plesteran + Acian Dinding
m3
1,746.40
56,400
98,496,960
3
Kolom Praktis 10x10
m1
1,364.00
45,000
61,380,000
4
Pasangan Keramik Lantai 30x30 cm
m2
1,320.00
185,000
244,200,000
5
Pintu Besi Plat D1
m2
18.00
750,000
13,500,000
6
Pintu Besi Plat D2
m3
43.20
750,000
32,400,000
7
Kusen Jendela Alumunium
Bh
34.00
1,450,000
49,300,000
8
Pekerjaan Cat Dinding
m2
3,492.80
22,500
78,588,000
9
Ventilasi Wiremesh Rangka Siku 80x585
Unit
22.00
1,624,000
35,728,000
10
Rabat Beton Tritisan Keliling Bangunan
m1
176.00
245,000
43,120,000
PT ARTEFAK ARKINDO
PARAF:
2
BILL OF QUANTITY PEKERJAAN STRUKTUR PEKERJAAN JASA KONSULTANSI PERENCANAAN DETAIL TEKNIS 10 PASAR RAKYAT PD. PASAR JAYA
No
Uraian Pekerjaan
Satuan
III.PEKERJAAN LANTAI DAN DINDING
Qty
Harga Satuan Sub jumlah Rp.
Jumlah Harga 733,117,960
IV. PEKERJAAN INSTALASI LISTRIK & AIR HUJAN A
Pekerjaan Listrik ttk
22.00
185,000
4,070,000
Lampu Kap Industri
Bh
22.00
145,000
3,190,000
Instalasi Stop Kontak NYM 3x2,5 mm
Ttk
11.00
245,500
2,700,500
4
Saklar seri
bh
8.00
45,000
360,000
5
Saklar Engkel
bh
4.00
32,500
130,000
6
Instalasi Penangkal Petir (Lightening Protection)
Unit
2.00
4,500,000
9,000,000
7
Box MCB
Unit
2.00
7,500,000
15,000,000
8
Kabel Toefoer
m1
32.00
87,500
2,800,000
Sub jumlah Rp.
37,250,500
1
Instalasi Titik Lampu NYM 2x2,5 mm
2 3
IV. PEKERJAAN INSTALASI LISTRIK & AIR HUJAN
REKAPITULASI I. PEKERJAAN PONDASI & PERSIAPAN
672,696,024
II. PEKERJAAN ATAP
971,449,960
III.PEKERJAAN LANTAI DAN DINDING
733,117,960
IV. PEKERJAAN INSTALASI LISTRIK & AIR HUJAN
37,250,500
1.8 - PASAR BIDADARI
PT ARTEFAK ARKINDO
SUB TOTAL.....Rp.
PARAF:
2,414,514,444
3