Latin terms that can be used for cool tattoo ideas!Descripción completa
e tFull description
good for beginners
Full description
semester 2 year 1 terms for economics
BACKFLUSH COSTINGFull description
Project Management Department ( PMD) A company department responsible for run Projects of the Company profitably by Contract & Subcontract Management, Cost Control, Planning & Scheduling, Project Auditing & constant Monitoring over all project aspects. CONTRACTS Agreement Mutually agreed terms between two parties about proposals & acceptance on paper duly signed by both parties. Contract Mutually agreed terms between two parties about proposals & acceptance on paper duly signed by both parties bound by enforcement Law. Type of Contract Contracts fall into following categories 1) Fixed Price (Lump Sum) 2) Unit Rate Fixed Price Contracts A performing Contractor has to complete the agreed qty’ of work for an agreed fixed Contract Value. Risks of all Cost escalation rest on performing Contractor.
Lump Sum Turn Key (LSTK) Contractor is legally bound to perform the following for a fixed Contract Value against approved Rules & Credit a. Design, b. Engineering, c. Procurement, d. Construction, e. Commissioning, f. Hand over
Lump Sum Progress Basis ( Procure & Built ) (LSPB) Contractor is legally bound to perform the following for a Provisional Contract Value against Agreed Rules & Credit a. Full or Partial Procurement, b. Construction, c. Commissioning, d. Hand over
Unit Rate Contracts The buyer shall pay the contractor in accordance with the completed Qty of works against agreed unit prices & Rules & Credit
Engineering, Procurement & Construction ( EPC) Contractor is legally bound to perform the following against agreed unit prices & Rules & Credit a. Engineering, b. Procurement, c. Construction, d. Commissioning, e. Hand over
Advance Payment The Part of Payment made to Contractor by Client Initially (5% to 20 % of CV) against mobilization of Resources & Start Temporary Facilities .it shall be recovered against Each Progress Invoice submitted by Contractor by the same % Retention Payment The part of payment with held by Client against each progress payment (5% to 10 %) in order to ensure satisfactory performance completion of contract terms. Client shall release the retention upon successful completion of the works agreed Work Total amount of resources & time required to complete an activity Bill of Quantity (B.O.Q) Total Qty of the Work specified in Main Contract
Material Take OFF (M.T.O) Total Qty of the Work obtained from IFC drawings against B.O.Q General Procedure to do M.T.O MTO should be inline with the following 1) IFC Drawings 2) Method of measurement specified in Contract 3) Contract Terms & Conditions Change Order Work Works not included or beyond the Original Scope of Work / B.O.Q to be performed +ve Change Order Work Increase in Qty from Original Scope of Work / B.O.Q -ve Change Order Work Decrease in Qty and/or De-scope of work from Original Scope of Work / B.O.Q MRP (Manpower Resource Planning) / (Manpower Requirement Program) Manpower resources planned against the schedule activities to complete the project ERP (Equipment Resource Planning) / (Equipment Requirement Program) Equipment resources planned against the schedule activities to complete the project LD (Liquidate Damage) Debt imposed by the owner on the Performing Contractor against delayed work completion which Affect total project completion and/or a part of the project completion by performance wise & cost wise. Owner can impose LD to the maximum limit of 10 % of the Contract Value. COSTING Budget The planned cost for an activity or project. Revenue Income against work performed as per agreed contract terms & conditions Cost Incurred expenditure against performed work Profit Saved cost against performed work (Revenue - Cost) Gross Profit (GP) Difference between the Gross Value of Work Invoiced & Actual Cost Incurred to perform that Work Gross Profit Margin (%) Ratio between GP & ACWP (GP / ACWP %) Net Profit (NP) Profit excluding the Overhead Cost (GP – OH) Committed Cost Cost incurred to be paid against work performed GVWS (Gross Value of Work Scheduled.) The sum of the Revenue for all planned work scheduled to be accomplished within a given time period GVWP (Gross Value of Work Performed) Total Revenue to be incurred for the performed Qty of Work as of date GVWB (Gross Value of Work Budgeted) Total Revenue to be incurred for the performed Qty of Work as of date BCWP (Budget Cost of Work Performed.) Total Cost of work performed against planned (budgeted) unit rate.
GVWI (Gross Value of Work Invoiced ) Total Revenue incurred for the performed Qty of Work Invoiced ACWP (Actual Cost of Work Performed ) Total Cost incurred for the Completed Qty of Work BCWP (Budget Cost of Work Performed.) / ( Earned Value) Total Cost of work performed against planned (budgeted) unit rate. BCWS (Budget Cost of Work Scheduled.) The sum of the budgets for all planned work scheduled to be accomplished within a given time period WIP (Work in Progress) Total Revenue to be incurred for the Un-approved Qty of the Work Performed (GVWP – GVWI) Gross Value of Work Performed (GVWP) minus Gross Value of Work Invoiced (GVWI) Earned Man-hour The time in standard hours credited as a result of the completion of a given task or a group of tasks (Unit Man-hour x Completed Work Qty) Actual Man-hour Time consumed in standard hours to the completion of a given task or a group of tasks Productivity Ratio between Earned Man-hours & Actual Man-hour General Responsibilities of the Quantity Surveyors Sl
1
2
Trade / Designation
Jr.Qs
Site QS
3
Project QS
4
Sr.QS
General Responsibilities
1) Site Tracking 2) Progress Updating, 3) PC Preparation 4) Assists to Site QS for preparation of MTO . 1) MTO 2) Preparation of Monthly Progress Valuation 3) Preparation of C.O Request, 4) Costing Reports to H.O 5) Preparation of Star Rate for a Non-BOQ Items / Works 6) Verify & Certify the S/C Invoices & Process the Payments
1) Preparation & incorporate any Changes in MRP & ERP 2) Prepare Activity % Breakup for each BOQ Items & Obtain approval from client prior to prepare the progress valuation / Measurement sheet 3) Review Progress Valuation & Get approval from Client for Submission of Final Invoices 4) Claim Negotiation with Client for Star Rate ,Additional Works, 5) Mgmt’ Reports to H.O, 6) Review & Approval of MR’s / P.O against Approved Available Budget 7) Ensuring the Cost Booking according to Cost Distribution in JDE System 1) Control the Cost with in the Budget 2) Revise the Operating Budget for approved Changes in Contract Value 3) Review of MRP & ERP prior to get approval from top management 4) Claim Negotiation with Client for Star Rate ,Additional Works 5) Ensuring all Executive Mgmt’ reports prior to Sr.PM Approval 6) Maintaining & Control Over the All contract Documents 7) Co-ordinate with Execution team & H.O regarding Cost issues & Reports 8) Carry-Out the Commercial Close-out & arrange all necessary backup documents for the release of retention money from client