Progress Calculation Procedure for Engineering Normally in an EPC project, progress calculation procedure for engineering deliverables is developed and used to monitor project performance against man hour spent. When working with progress calculation, you should know the level of reporting. In a typical project, engineering progress is measured as level 2 (phase wise) and level 3 (engineering discipline wise) and level 4 (document wise). Refer to the following procedure to calculate engineering progress,
Online Project Management Try Project Management Software. For Free!
Lookahead Schedule Maintenance Planning Maintenance schedule Planner's Resources
1) Engineering progress for each document (Level 4) = the sum of the product of weight factor for each work step and engineering progress for each work step
Primavera P6 Primavera P6 Tutorial Progress Calculation/Measureme Calculation/Measurement nt
2) Engineering progress for each discipline (level 3) = the sum of the product of weight factor for each document and engineering progress for each document
Sample Layout Sample WBS Sample Work Activity Schedule Control schedule design Schedule development Schedule Options
3) Calculate total engineering progress (level 2) = the sum of the product of weight factor for each discipline and engineering progress for each discipline
How to Get an Engineering Drawing Progress – Level 4 The progress calculation is done based on engineering work steps and their weight factors for an engineering drawing. See the below sample work steps and weight factors.
Schedule Report Tank Construction
Sample weight factor for each work step for each engineering drawing Weight factor is calculated based on effort required for each work st ep for a particular drawing/document. The ratio of weight factor for each work step could be different depending on your project team’s expert judgment. The following work steps are required to produce an engineering drawing as minimum.
Engineering Study online.miu.edu.my/Admission-Open
100% Internship Placement & 5K RM Free Waiver for Degree Programs!
1. Start 2. Study/Preparation 3. Issue for internal review 4. Issue to client
Study Nutrition at IMU 5. Approval by client
Krygier Design, Inc. Project Management 2
6. Issue for construction The projects I involved describe the weight factors for the above work steps are as follows; 1) 5% (0.05) of total hours for “Start" work st ep
Free Download DWG CAD Project Engineer Needed Construction Management
2) 45% (0.45) of total hours for "Study and preparation" step 3) 10% (0.10) of total hours for "Issue for Internal Review" 4) 10% (0.10) of total hours for "Issue to client" 5) 15% (0.15) of total hours for to get "Approval by Client"
Mechanical Design Springtime Amsterdam
6) 15% (0.15) of total hours for "Issue for construction" The sum of total weight factors f or all work steps must be 100% (1).
Sign In
Toolbox4Planning: Progress Calculation Procedure for Engineering
Page 2 of 10
Let’s find out how a piping drawing progress is calculated. Suppose a piping isometric drawing design has been completed 50% of “Study and Preparation” work step. See the details calculation and below figure for easy understanding.
POPULAR POSTS How to Get Resource Loading Histogram/S Curve in Primavera P6
Progress for a piping isometric drawing at that stage = Weight factor for “Start” work step (0.05) x progress for “Start” work step (100%) + Weight factor for “Study and Preparation” (0.45) x progress for “Study and Preparation” work step (50%) Therefore, the actual progress for that drawing up to 50% completion of study and preparation step is 27.5 %. The actual progress would be 50% when “Study/Preparation” work is completed 100%.
Job Descriptions of Project Planner,Planning Engineer,Schedule Engineer and Primavera Planner
P6 Filters Most Used in Schedule Reporting (Activity Filtering)-Part2
► Mechanical ► Diploma
Engineering
of Engineering
► Engineering
► Piping
Drawing
Engineering
► Electrical
Engineering In
► Engineering
Design
Progress Calculation for Engineering Specification/Requisition-Level 4 Progress calculation for an engineering specification/requisition is done using the same exercise for engineering drawing. The only different is its work Step and weight factor as weight factor for each work step for each specification/requisition is required to calculate the quantity progress.
Sample weight factor for each w ork step for each engineering specification/requisition The following are work steps and weight factors for a production of engineering specification/requisition.
► Engineering ► Civil
Projects
Engineering Compa
► Engineering
1) 5% (0.05) of total hours for “St art" work step 2) 45% (0.45) of total hour for "Study and preparation" step.
Construction 3) 15% (0.15) of total hours for "Issue to client" 4) 20% (0.20) of total hours for to get "Approval by Client"
Receive updates by e-mail:
E-mail:
Subscribe
5) 15% (0.15) of total hours for "Issue for construction/Purchase” Once again, the sum of total weight factors for all work steps must be 100% (1).
How to Get Engineering Progress by Discipline -Level 3 To calculate discipline wise (level-3) engineering progress, in other word, physical progress for an engineering discipline = the sum of the product of weight factor for each document and engineering progress (quantity) for each document.
How to find weight factor for engineering document Weight factor calculation for engineering document is required to calculate engineering progress for each discipline. Engineering documents are normally categorized drawings, specifications, requisitions and information documents. P&ID drawings, isometric drawings, pump GA, foundation drawings, etc. are in drawing category. Material specification, equipment/piping fabrication and erection specification and Instrument cable specification are in specification category. REQ for piping material, REQ for pump/compressor/blower and etc. are in requisition category. Weight factor for an engineering document = budgeted man hour for a document/total budgeted man hour for all documents in each discipline, Assume the budgeted man hour for an iso metric drawing is 200 and 10,000 hours for all piping documents. Therefore, weight factor for that iso drawing is (200/10,000) 0.02.
Progress Calculation for Mechanical Engineering Discipline Progress calculation for mechanical engineering discipline = the sum of the product of weight factor for each document and the actual progress of each document in mechanical discipline for a particular project. For instance, a project includes the mechanical scope required to produce a list of drawings and documents and the work is in-progress. Suppose a table of mechanical documents are shown as the following,
Toolbox4Planning: Progress Calculation Procedure for Engineering
Page 3 of 10
Weight factor for pump data sheet is 0.0356 obtained based on 200 budgeted hours/ 5470 total budgeted hours of mechanical discipline. The progress data in “Quantity Progress (% complete)" column is referred to the document progress calculation based on work step completion and work step weight factor. For example, Quantity Progress (% complete)" for pump data sheet = 5% x 100%+45%x100%+15%x100+20% x100%+15% x33% = 90% , This is the same calculation method used for a piping isometric drawing progress as explained on above. The progress data in "Weight Progress" which also known as physical progress column is referred to the progress calculation based on document weight and Quantity Progress (% Complete). For example, Physical Progress of pump data sheet document = 0.03656 x 90% = 3.3%, Finally, the total progress for mechanical engineering section, 37.8% is the sum of weight progress for each document. Progress calculation procedure for process, piping, civil, structure, electrical and instrumentation is done using the same methodology as mechanical discipline.
How to Get Overall Engineering Phase/Stage – Level 2 Progress data for engineering phase can be obtained using the same exercise like discipline wise progress calculation. The difference is the way how you want to group it. That means weight factor for each engineering discipline is required to analyse the total progress of all disciplines. . See the below formula to get overall engineering progress. Progress for engineering phase/stage = the sum of the product of weight fact or for each discipline and progress for each discipline, see how weight factor for each engineering discipline as below.
How to find w eight factors for engineering disciplines Weight factor = budgeted hour for each discipline/Total budgeted hour for all discipline for a particular project, For example Assuming that budgeted man hour for mechanical, process, piping, civil, structure, electrical and instrumentation are listed as table below. Weight factor for mechanical engineering discipline = 5470 (Budgeted man hour) / 31370 (Overall engineering man hour) = 0.1744
Toolbox4Planning: Progress Calculation Procedure for Engineering
Page 4 of 10
Progress Calculation for Overall Engineering Mechanical engineering progress is 37.8 % as stated above and assuming that the individual progress for other disciplines is listed as below table. Then, Overall Engineering phase/stage progress = the sum of the product of weight factor for each discipline and physical progress for each discipline, = 0.1744 x 37.8% + 0.0956 x 50% + 0.2550 x 20% + 0.1020 x 30% + 0.1116 x 25% + 0.1275 x 15% + 0.1339 x 13% = 26%
Download sample progress calculation sheet to learn more.
QuickBooks® Online Accountancy Software to Save Time. Login from Mac's, PC's or Mobiles!
You might also like:
Basic concept of civil/structure engineering work flow for ...
How to Develop Procurement Progress Calculation Sheet Using ...
Progress Calculation Sample for Pump Installation Work
Linkwithin
+1 Recommend this on Google
8 comments: Anonymous February 16, 2013 at 9:17 PM but what about progress of non deliverables i.e. meetings , site coordination etc Reply
Unknown May 5, 2013 at 4:23 PM For non-deliverables (considered LOE) can be planned as a fixed 10% of overall engineering estimated? Reply Replies
Toolbox4Planning: Progress Calculation Procedure for Engineering
Min Oo
Page 5 of 10
May 7, 2013 at 6:57 PM
As LOE activities can’t be measured objectively, the planned value is always s ame as earned value. Therefore, schedule variance is always Zero. It doesn't matter 10% or 20% when schedule variance is reported. The use of LOE (Level of Effort) should be avoided when engineering progress is evaluated so as to not distort overall engineering progress.
Reply
imraank May 27, 2013 at 11:16 PM Dear Min please elaborate "% complete" column with an example as I couldn't able to f ind values mentioned in the table Reply Replies Min Oo
June 1, 2013 at 3:38 PM
Hi Imraank, Thanks for your comment. I have recently updated on this procedure. It has explained more details. Regards,
Reply
Cindy Hammerhead September 30, 2013 at 9:50 PM I personally don't believe there should be any progress claimed for activities outside of the deliverables, i.e., client approval, meetings, etc. Those items are not in the scope of work. The scope of work should only include drawing, report submissions - once the are approved. Until they are approved, they have made zero progress on their deliverables. For drawings, I would suggest using the 30%, 65%, 90%, and 100% for each design package. Once the drawings are at 100% they are IFC'd. As far as the weighting of the individual tasks of the design packages, I believe 40% for 30% drawings, 30% for 65% drawings, 25% for 90% drawings, and 5% for 100% drawings. The reasoning behinds this weighting is the fact that the earliest design activities take the longest. Any subsequent activities only add to the previously approved parts. Again, just my two cents... Reply
Anonymous April 27, 2014 at 8:09 AM This article and comments are about how to track earned value progress earned. Let's backup to the establishment of the progress plan. Generally a discipline lead puts together his plan based on the way he is going to earn progress on the deliverables without consideration of the earned rules for progress which will cause variances to the SPI and Earned Rules Established. How is the industry dealing with this?
[email protected] Reply
Anonymous June 2, 2014 at 12:45 PM Hi everybody, Anyone have productivity table(manhours/drawing) for engineering drawings like PID, Isometric, foundation drawing, materila specification etc.please share Reply
Toolbox4Planning: Progress Calculation Procedure for Engineering
Comment as:
Publish
Page 6 of 10
Select profile...
Preview
Links to this post Create a Link
Newer Post
Home
Subscribe to: Post Comments (Atom)
1
WELCOME
FOLLOWERS
Hi, my name is Min Oo. Thank you for vis iting my site and welcome to my blog. I have been working in different roles in projects, maintenance planning & scheduling and engineering in the oil & gas and petrochemical industry over the last 12 years. The gr eatest value of Toolbox4Planning is sharing ideas, tool & techniques and best practices that can be applied in industries involved in engineering, construction, manufacturing, maintenance and research. You can find tutorials and templates related to planning & scheduling and project control at Toolbox4Planning which would help you improve your planning knowledge and skills. Grab a cup of your favourite beverage, browse the blog, share y our thoughts / leave comments. Email:
[email protected]
Join this site with Google Friend Connect
Members (158) More »
Already a member?Sign in
© 2014 Toolbox4Planning. All rights reserved.. Powered by Blogger.
Older Post
Toolbox4Planning: Progress Calculation Procedure for Engineering
Page 7 of 10
Toolbox4Planning: Progress Calculation Procedure for Engineering
Page 8 of 10
Toolbox4Planning: Progress Calculation Procedure for Engineering
Page 9 of 10
Toolbox4Planning: Progress Calculation Procedure for Engineering
Page 10 of 10