Penta-Ocean Construction Co., Ltd.
Ref.: MS/C/024
Shatin to Central Link Contract 02 02 ! "in #en$ Station and %&&roach Structures
Re'ision ion : -
Metho Method d Stat State+ e+en entt for for Con Constr struc uctio tion n of of (rain (raina$ a$ee and and Manh Manhol oles es
Pa$e Pa$e:: of )
(ate: te: )--20*
Method Statement For Construction of Drainage and Manholes For Hin Keng Station & Approach Structures, Contract No. 11!
This document contains confidential information of Penta-Ocean Construction Co., Ltd. and shall not be copied or amended without approval of the Project Manager "e#
%
$ssue Date
Status
Prepared b "ngineer # Construction Manager
!eviewed b
!eviewed b
$% Manager
&afet Manager
'oe (ong
)elen Tong
%le* Lam
!%1%!1' Su(mission
+ate
+ate
!eviewed b &enior Construction Manager
+ate
%pproved b Project Manager
Penta-Ocean Construction Co., Ltd.
Ref.: MS/C/024
Shatin to Central Link Contract 02 ! "in #en$ Station and %&&roach Structures
Re'ision : -
Method State+ent for Construction of (raina$e and Manholes
Pa$e: 2 of )
(ate: )--20*
Colbert Cheung +ate
(ilson Chu +ate
Content
)age
.
The &cope of (ors //////////////////////// 0
1.
(or methodolog and Testing Procedure ././//////////.//
0.
Material, Plants and Labour !esources ///////////////... 2
3.
Construction Programme ////////////////////// 2
4.
&afet and "nvironmental Mitigation Measures ///////////../.. 2
5.
6lood Protection Measures ///////////////////// 7
8.
6ire +etection and Protection Measures //////////////../ 7
9.
Contingenc Plan /////////////////////////..
0
%ppendices %ppendi* % : Laout plan ;71#(#)<=#&(L#C3#7 to 79 and &uggested +rainage Laout in )in Tin Plaground> %ppendi* ? : Tpical section for drainage construction and manhole construction. %ppendi* C :
2
Penta-Ocean Construction Co., Ltd.
Ref.: MS/C/024
Shatin to Central Link Contract 02 ! "in #en$ Station and %&&roach Structures
Re'ision : -
Method State+ent for Construction of (raina$e and Manholes
Pa$e: * of )
1.
(ate: )--20*
*he Scope of +ors
This method statement is purposed to establish and illustrate the construction method for both pipewors ;&torm and &ewerage> and manholes for &hatin to Central Lin ;Contract 71 : )in =eng &tation and %pproach &tructures> Project as specified in project specification. This method statement outlines the procedure for constructing drainage pipes to fulfill the oncoming needs of )in =eng &tation.
The proposed alignment and location of pipewors and manholes please refers to the enclosed drawings in %ppendi* %.
!.
+or Methodolog- and *esting )rocedure
Anderground &ervices location plans made available b the Client# "ngineer will be viewed. % Cable %voidance Tool ;C%T> will be used to identif the location of underground services before e*cavation.
!.1 )rocedures of pipe la-ing
1.. &tormwater pipes : Precast Concrete Pipe
i>
&et out the alignment on site according to approved shop drawings.
ii>
6ence off the woring area and plants.
iii>
.
iv>
"*cavate a trench between sheet piles to appro*imate 477mm below st laer of wailing and strut.
v>
.
vi>
6urther e*cavate the ground down to appro*imate 477mm below 1 nd laer of wailing and strut.
vii>
Penta-Ocean Construction Co., Ltd.
Ref.: MS/C/024
Shatin to Central Link Contract 02 ! "in #en$ Station and %&&roach Structures
Re'ision : -
Method State+ent for Construction of (raina$e and Manholes
Pa$e: 4 of )
(ate: )--20*
section 3-3 and 4-4>. viii>
!epeat &tep vi> and vii> for remaining strut and wailing if reBuired.
i*>
"*cavate the ground down to final formation level. ;Please refer to the section 5-5>.
*>
*i>
Place concrete blinding to the formation level to provide suitable woring environment if necessar.
*ii>
Construct the bedding for the pipe. 6or the bedding of storm water drains which is divided into Tpe % bedding and Tpe ? bedding. ;> 6or Tpe % bedding, plain concrete cradle will be constructed to support the pipes. ;Please refer to the section 8-8a> ;1> 6or Tpe ? bedding, the bottom of trenches will be filled with compacted filling materials. ;Please refer to the section 8-8b>.
*iii>
Cut pipe into appropriate length for installation if reBuired.
*iv>
La the pipes directl on the plain concrete cradle ;Tpe % bedding> or compacted soils ;Tpe ? bedding>.
*v>
&eal e*ternall and internall with cement mortar for the joint between the cut pipe and the pipe to which it is connected. %nd the cement mortar shall consist of cement and sand in the proportions 0 b mass.
*vi>
Carr out air test or water test for the installed pipeline.
*vii>
Clean the pipeline b pigging, high pressure water jetting or other method approved b the "ngineer.
*viii>
Carr out st laer of bacfilling from the proposed formation level to 077mm above the top of the pipe with lightl compact b hand rammers or manuall operated power eBuipment. 6ill material within st laer of bacfilling shall be compacted to at least 94D of the ma*imum dr densit and it shall be deposited in laers not e*ceeding 77mm. .
*i*>
Carr out 1nd laer of bacfilling from 077mm above the top of the pipe to 477mm below the lowest laer of strut and wailing. 6ill material shall be compacted b vibrating roller to at least 4
Penta-Ocean Construction Co., Ltd.
Ref.: MS/C/024
Shatin to Central Link Contract 02 ! "in #en$ Station and %&&roach Structures
Re'ision : -
Method State+ent for Construction of (raina$e and Manholes
Pa$e: of )
(ate: )--20*
24D of the ma*imum dr densit and it shall be deposited in laers not e*ceeding 147mm. %nd then the lowest laer of strut and wailing will be removed. ;Please refer to the section 2-2>. **>
Carr out 0rd laer of bacfilling from 477mm below the lowest laer of strut and wailing to 477mm below st laer of strut and wailing. 6ill material shall be compacted b vibrating roller to at least 24D of the ma*imum dr densit and it shall be deposited in laers not e*ceeding 147mm. %nd then st laer of strut and wailing will be removed. ;Please refer to the section 77>. ;
rd
laer of bacfilling should onl fill from 477mm below the lowest laer of strut and wailing to 477mm below 1 nd laer of strut and wailing, and then repeat step *i*> till 477mm below the e*isting ground level>. **i>
Carr out 3th laer of bacfilling from 477mm below st laer of strut and wailing to the e*isting ground level. 6ill material shall be compacted b vibrating roller to at least 24D of the ma*imum dr densit and it shall be deposited in laers not e*ceeding 147mm. ;Please refer to the section ->.
**ii>
!emove the sheet piles and reinstate the ground surfaces as per original. ;Please refer to the section 1-1>.
**iii>
Carr out CCTE inspection before the pipeline is handed over.
1..1 &ewer pipes : Eitrified Cla Pipe
i>
&et out the alignment on site according to approved shop drawings.
ii>
6ence off the woring area and plants.
iii>
iv>
"*cavate a trench between sheet piles to appro*imate 477mm below st laer of wailing and strut.
v>
vi>
6urther e*cavate the ground down to appro*imate 477mm below 1 nd laer of wailing and strut.
vii>
viii>
!epeat &tep vi> and vii> for remaining strut and wailing if reBuired.
Penta-Ocean Construction Co., Ltd.
Ref.: MS/C/024
Shatin to Central Link Contract 02 ! "in #en$ Station and %&&roach Structures
Re'ision : -
Method State+ent for Construction of (raina$e and Manholes
Pa$e: of )
(ate: )--20*
i*>
"*cavate the ground down to final formation level.
*>
*i>
Place concrete blinding to the formation level to provide suitable woring environment if necessar.
*ii>
Cut pipe into appropriate length for installation if reBuired.
*iii>
La the pipes.
*iv>
&eal e*ternall and internall with cement mortar for the joint between the cut pipe and the pipe to which it is connected. %nd the cement mortar shall consist of cement and sand in the proportions 0 b mass.
*v>
Carr out air test or water test for the installed pipeline.
*vi>
Clean the pipeline b pigging, high pressure water jetting or other method approved b the "ngineer.
*vii>
Construct concrete surround for the laid pipes for pipes protection.
*viii>
Carr out st laer of bacfilling from the proposed formation level to 077mm above the top of the pipe with lightl compact b hand rammers or manuall operated power eBuipment. 6ill material within st laer of bacfilling shall be compacted to at least 94D of the ma*imum dr densit and it shall be deposited in laers not e*ceeding 77mm.
*i*>
Carr out air test or water test for the installed pipeline.
**>
Carr out 1nd laer of bacfilling from 077mm above the top of the pipe to 477mm below the lowest laer of strut and wailing. 6ill material shall be compacted b vibrating roller to at least 24D of the ma*imum dr densit and it shall be deposited in laers not e*ceeding 147mm. %nd then the lowest laer of strut and wailing will be removed.
**i>
Carr out 0rd laer of bacfilling from 477mm below the lowest laer of strut and wailing to 477mm below st laer of strut and wailing. 6ill material shall be compacted b vibrating roller to at least 24D of the ma*imum dr densit and it shall be deposited in laers not e*ceeding 147mm. %nd then st laer of strut and wailing will be removed. ;
Penta-Ocean Construction Co., Ltd.
Ref.: MS/C/024
Shatin to Central Link Contract 02 ! "in #en$ Station and %&&roach Structures
Re'ision : -
Method State+ent for Construction of (raina$e and Manholes
Pa$e: of )
(ate: )--20*
from 477mm below the lowest laer of strut and wailing to 477mm below 1 nd laer of strut and wailing, and then repeat step *i*> till 477mm below the e*isting ground level>. **ii>
Carr out 3th laer of bacfilling from 477mm below st laer of strut and wailing to the e*isting ground level. 6ill material shall be compacted b vibrating roller to at least 24D of the ma*imum dr densit and it shall be deposited in laers not e*ceeding 147mm.
**iii>
!emove the sheet piles and reinstate the ground surfaces as per original.
**iv>
Carr out air test or water test. %nd carr out infiltration test not more than 8 das before the pipeline is handed over.
**v>
Carr out CCTE inspection before the pipeline is handed over.
!.! Construction seuences of manhole/
1.1. Manhole : Ma*. depth more than 0.4m
i>
&et out the location on site according to approved shop drawings.
ii>
6ence off the woring area and plants.
iii>
.
iv>
"*cavate verticall between sheet piles to appro*imate 477mm below st laer of wailing and strut. ;Please refer to the section 3-3>.
v>
vi>
6urther e*cavate the ground down to appro*imate 477mm below 1 nd laer of wailing and strut.
vii>
.
viii> i*>
!epeat step vi> and vii> for remaining strut and wailing. "*cavate the ground down to final formation level, and 0 rd laer of wailing and strut will be installed, if reBuired. ;Please refer to the section 9-9>
*>
Penta-Ocean Construction Co., Ltd.
Ref.: MS/C/024
Shatin to Central Link Contract 02 ! "in #en$ Station and %&&roach Structures
Re'ision : -
Method State+ent for Construction of (raina$e and Manholes
Pa$e: ) of )
(ate: )--20*
*i>
Place 84mm thic blinding laer under the manhole. ;Please refer to the section 2-2>.
*ii>
Carr out surve to locate the level of connection points.
*iii>
"rect formwor and fi*ing reinforcement bars. ;Please refer to the section 17-17>.
*iv>
st pour ?edding and haunching will be constructed and it will onl be cast within one time provided with a longitudinal C.'. ;Please refer to the section 1-1>. 1nd pour . 4m of manholes wall will be cast within one time provided with a longitudinal C.'.
*v>
;Please refer to the section 11-11>. 0rd pour !educing slab and wall below 7.4m high of ground level will be cast in one time.
*vi>
;Please refer to the section 10-10>. *vii>
.
*viii>
Carr out air test.
*i*>
Clean the manhole.
**>
Carr out st laer of bacfilling from the proposed formation level to 477mm below the lowest laer of strut and wailing. 6ill material shall be compacted b vibrating roller to at least 24D of the ma*imum dr densit and it shall be deposited in laers not e*ceeding 147mm. %nd then the lowest laer of strut and wailing will be removed. ;Please refer to the section 14-14>. Carr out 1nd laer of bacfilling from 477mm below the lowest laer of strut and wailing to
**i>
477mm below st laer of strut and wailing. 6ill material shall be compacted b vibrating roller to at least 24D of the ma*imum dr densit and it shall be deposited in laers not e*ceeding 147mm. %nd then remove st laer of strut and wailing. ;Please refer to the section 15-15>. Carr out 0rd laer of bacfilling from 477mm below st laer of strut and wailing to e*isting
**ii>
ground level. 6ill material shall be compacted b vibrating roller to at least 24D of the ma*imum dr densit and it shall be deposited in laers not e*ceeding 147mm. ;Please refer to the section 18-18>. **iii>
!emove the sheet pile and reinstate the ground surfaces as per original.
1.1.1 Manhole : Ma*. depth less than 0.4m
i>
&et out the location of site according to the approved shop drawings.
ii>
6ence off the woring area and plants.
iii>
Penta-Ocean Construction Co., Ltd.
Ref.: MS/C/024
Shatin to Central Link Contract 02 ! "in #en$ Station and %&&roach Structures
Re'ision : -
Method State+ent for Construction of (raina$e and Manholes
Pa$e: of )
(ate: )--20*
"*cavate verticall between sheet piles to appro*imate 477mm below st laer of wailing and
iv>
strut st laer of wailing and strut will be installed about .7m below the ground surface. v>
"*cavate the ground to the proposed formation level.
vi>
vii>
Place 84mm thic blinding laer under the manhole.
viii>
Carr out surve to locate the level of connection points.
i*>
"rect formwor and fi*ing reinforcement bars.
*>
st pour ?edding and haunching will be constructed and it will onl be cast within one time provided with a longitudinal C.'.
*i>
1nd pour .84m of manholes wall will be cast within one time provided with a longitudinal C.'.
*ii>
0rd pour !educing slab and wall below 7.4m high of ground level will be cast in one time.
*iii>
*iv>
Carr out air test.
*v>
Clean the manhole.
*vi>
Carr out st laer of bacfilling from the proposed formation level to 477mm below the lowest laer of strut and wailing. 6ill material shall be compacted b vibrating roller to at least 24D of the ma*imum dr densit and it shall be deposited in laers not e*ceeding 147mm. %nd then the lowest laer of strut and wailing can be removed. Carr out 1nd laer of bacfilling can be carried out from 477mm below the lowest laer of strut
*vii>
and wailing to e*isting ground level. 6ill material shall be compacted b vibrating roller to at least 24D of the ma*imum dr densit and it shall be deposited in laers not e*ceeding 147mm. The sheet pile can be removed and then the ground surfaces should be reinstated as per original.
!.' *esting procedure
1.0. &eBuence of air test
i>
!emove all obstructions, debris and superfluous matter from the pipelines.
Penta-Ocean Construction Co., Ltd.
Ref.: MS/C/024
Shatin to Central Link Contract 02 ! "in #en$ Station and %&&roach Structures
Re'ision : -
Method State+ent for Construction of (raina$e and Manholes
Pa$e: 0 of )
ii>
(ate: )--20*
&eal the end of all the pipelines and associated branches under test b e*panding drain plugs or inflatable canvas or rubber test bags.
iii>
Connect a A-tube manometer to the pipelines.
iv>
Pump air into the pipeline until a test pressure of slightl more than 77 mm of water is registered on an A-tube manometer connected to the pipeline. 4 minutes shall be allowed for stabiliFation of the air temperature and the air pressure shall then be adjusted to 77 mm of water.
v>
!ead the pressure from the A-tube at the end of a 4 minutes period without further pumping.
vi>
Measure the air pressure inside the pipelines upon test start.
vii>
Measure the loss of air pressure inside the pipelines.
1.0.1 &eBuence of water test
i>
!emove all obstructions, debris and superfluous matter from the pipelines.
ii>
&ecure all drain stoppers and# or bags in the end of the pipelines and all associated branches under test.
iii>
6ill water to the pipelines at least 1 hours before the test to allow for water absorption.
iv>
% test pressure of .1m head of water above the soffit of the pipe at the high end shall be applied at the standpipe and maintained for 07 minutesG the test pressure applied shall not e*ceed 5m head of water at the invert the low end of the pipe.
v>
The head of water at the standpipe shall be topped up at 4 minutes intervals during the test and shall be filled to the specified head at the end of the test period b adding measured Buantities of water to the standpipe.
vi>
The leaage of water from the pipeline shall be measured as the amount of water added to maintain the specified test pressure.
1.0.0 &eBuence of infiltration test
The procedure for the infiltration test shall be accordance with ?&9774 Part Clause 0.5.
0
Penta-Ocean Construction Co., Ltd.
Ref.: MS/C/024
Shatin to Central Link Contract 02 ! "in #en$ Station and %&&roach Structures
Re'ision : -
Method State+ent for Construction of (raina$e and Manholes
Pa$e: of )
'
(ate: )--20*
Material, )lants and 0a(our "esources
4 - 7 worers at pea time,
(oring and lifting platform with Certificate,
?achoe,
(elding machine,
Eibrator,
!igger,
&teel stairwas,
Henerator,
Pumps and concrete pump,
(ooden chutes, and
&mall hand tools and# or other tools necessar for in-situ concrete casting wor.
Construction )rogramme
Tentative &tart Mid-October 174G Tentative 6inish Mid-March 175.
2
Safet- and 3n#ironmental Mitigation Measures
i>
%ll worers are reBuired to attend pre-wor health chec b &ite Iurse before attending &afet
ii>
%ll worers are reBuired to wear safet helmet, safet shoes and reflective vest.
iii>
Temporar shoring sstem shall be properl designed.
Penta-Ocean Construction Co., Ltd.
Ref.: MS/C/024
Shatin to Central Link Contract 02 ! "in #en$ Station and %&&roach Structures
Re'ision : -
Method State+ent for Construction of (raina$e and Manholes
Pa$e: 2 of )
(ate: )--20*
the construction of temporar wors construction before carring out an soil in-site test. iv>
(eel regularl inspection and checing will be carried out b Competent Person.
v>
Lifting appliances should be eBuipped with safe load indicator. The lifting appliances and lifting gears should be certified b !P" with valid testing and e*amination certificates. Operator should also enter the result of weel checing into the prescribed inspection 6orm .
vi>
Io load should be allowed to be carried out outside the site boundar and no worer is allowed to wor below the lifting route.
vii>
(aste water sedimentar tan shall be provided on site. %ll water shall be properl discharged to "P+s approved water discharge points.
viii>
Permit to Operate, Permit to Move, Permit to +ig and )ot (or Permit should be strictl implemented.
i*>
%ll bodil injur, accident incident or near miss should be reported to foreman or &afet Officer immediatel.
*>
%ll mobile crane and generator shall be silent tpe.
*i>
!egularl chec the generator and electrical tools b registered electrician. Provide proper earth-rodG provide emergenc stop buttonG &top the generator when refuelling.
4
Flood )rotection Measures
Temporar soa awa pit and temporar pump pit should be provided at low-point area to avoid water flooding.
5
Fire Detection and )rotection Measures
&moing is prohibited on site
Provide sufficient fire e*tinguishers in good conditions at woring place.
6
Contingenc- )lan
2
Penta-Ocean Construction Co., Ltd.
Ref.: MS/C/024
Shatin to Central Link Contract 02 ! "in #en$ Station and %&&roach Structures
Re'ision : -
Method State+ent for Construction of (raina$e and Manholes
Pa$e: * of )
(ate: )--20*
The movement monitoring on tracs and adjacent Operational !ailwa 6acilities shall be conducted concurrentl to review an impact caused b construction of pipelines and manholes.
*
Penta-Ocean Construction Co., Ltd.
Ref.: MS/C/024
Shatin to Central Link Contract 02 ! "in #en$ Station and %&&roach Structures
Re'ision : -
Method State+ent for Construction of (raina$e and Manholes
Pa$e: 4 of )
(ate: )--20*
%ppendi* %
Laout plan ;+rawing Iumber 71#(#)<=#&(L#C3#7 to 79>.
4
Penta-Ocean Construction Co., Ltd.
Ref.: MS/C/024
Shatin to Central Link Contract 02 ! "in #en$ Station and %&&roach Structures
Re'ision : -
Method State+ent for Construction of (raina$e and Manholes
Pa$e: of )
(ate: )--20*
%ppendi* ?
Tpical
section
for
drainage
construction
construction
and
manhole
Penta-Ocean Construction Co., Ltd.
Ref.: MS/C/024
Shatin to Central Link Contract 02 ! "in #en$ Station and %&&roach Structures
Re'ision : -
Method State+ent for Construction of (raina$e and Manholes
Pa$e: of )
%ppendi* C
(ate: )--20*
Penta-Ocean Construction Co., Ltd.
Ref.: MS/C/024
Shatin to Central Link Contract 02 ! "in #en$ Station and %&&roach Structures
Re'ision : -
Method State+ent for Construction of (raina$e and Manholes
Pa$e: of )
%ppendi* +
!is %ssessment
(ate: )--20*
Penta-Ocean Construction Co., Ltd.
Ref.: MS/C/024
Shatin to Central Link Contract 02 ! "in #en$ Station and %&&roach Structures
Re'ision : -
Method State+ent for Construction of (raina$e and Manholes
Pa$e: ) of )
)
(ate: )--20*