Construction Method Statement for the new WELCOME BUILDING at the City of Bath College
City Of Bath College Welcome Building
Construction Method Statement
INTRODUCTION Cowlin have been awarded the contract for the Welcome Building, City of Bath College, a prestigious project in the Centre of Bath, at the corner of Avon Street and James Street West. The project will start in March 2011 and is due to be completed in October 2011. The purpose of this Construction Method Statement is t o demonstrate our intended method of carrying out this task under close consideration of all relevant aspects, i.e. adjoining public footpaths, traffic flow for both Avon Street and James Street West and a live College environment. Upon Cowlin starting on site, we will take over an existing site compound from the Enabling Works Contractor (Emery Bros), who will have demolished the existing Kings building. The crushed material from the demolition works will be used for the piling mat to reduce the amount of stone that has to be imported to site. Key operations for the superstructure of the project will be PILING, GROUNDWORKS, STEELFRAME, COMPOSITE CONCRETE SLABS AND BLOCKWORK.
Site Set Up The extent of the site compound will be as shown on APPENDIX 1. Full protective hoardings and screens will be put in place to the full perimeter of the site. We have been granted permission by Highways to extend the site compound along James Stre et West to the demarcation of old and new paving slabs, leaving app. 2m of footpath open. However, at present we do not envisage utilizing this area, other than for t he Entrance gate. Should this area be required at a later stage we will liaise with both, Highways and the Tree Officer before extending the compound. We do understand the importance of prote ction to the Willow Tree at the corner of Avon Street / James Street West and will therefore arrange any access and egress in a way to ensure that the 2No gullies that are feeding the Willow Tree remain unobstructed and that no potential damage or contamination can occur.
Access / Egress Following discussions with the BANES Highways supervisor we will set up 2No main delivery entrances as described below. During the superstructure works the main entrance will be via Avon Street, where we intend to utilize the current footpath as a lay by for deliveries. This lay by will be equipped with 2No gates
Page 2
City Of Bath College Welcome Building
Construction Method Statement
that will allow driving in and out with the flow of traffic to ensure the continuation of the one way-bus-route in Avon Street. To achieve the above we will remove the existing bollards and ramp down the kerbstones as necessary. Furthermore we will establish a second site entrance in James Street West, which will be the main access and egress point for the second part of the project.
Deliveries The main delivery to and from site will be Lower Bristol Road A36 and the 2No afore mentioned entrances in Avon Street and James Street West (APPENDIX2). Whilst we cannot completely eliminate the use of articulated lorries during the superstructure phase, we will encourage all suppliers and subcontractors to use smaller delivery vehicles to reduce the need for extensive manoeuvring in and around site. In addition we will endeavour to time major deliveries either before or after the peak of rush hour traffic. We fully accept the priority for buses in Avon Street and for pedestrians on t he footpath of James Street West. All vehicles entering or leaving site will therefore be supervised by a banksman / traffic warden. Frequent visits of a Road-sweeper will ensure that footpaths and roads are kept clean throughout the project.
Contractors Parking There will be no subcontractor parking on site or on the City of Bath College property. All subcontractors will have to park in public car park or pay and display areas. We will include this condition in all our subcontracts and encourage public transport and/or shared transport to and from site. The lay-by in Avon Street will be used as an offloading area for small items and tools during the fitout-stage of the building. We will assist our contractors by giving them the opportunity of setting up small lockable containers on site for safe storage overnight.
Demolition & Enabling Works This is not part of Cowlin’s scope of works and will be carried out by Ohters.
Page 3
City Of Bath College Welcome Building
Construction Method Statement
Piling We propose to carry out the piling in 2 stages. Starting at the lower level along Avon Street and then providing a higher piling mat with battered e dge to overcome the level difference of app. 1200mm. The piling mat will be designed by our P iling contractor and checked and approved by our temporary works department. All Piling will be carried out in accordance with the Avon Act. On completion, the piling mat will remain in place and will be trimmed appropriately to form the working platform to carry out the ground works, drainage and ultimately the ground floor slab (NB the ground floor slab is designed as being suspended and therefore does not rely upon the substrate for support).
Ground works The ground beams will be constructed by site excavation through the fill material and then ‘Pecafill’ permanent shutters placed as necessary to minimise the amount of concrete required.
Similarly, the drainage and various service ducts will be e xcavated through the site fill and positioned prior to final trimming of the stone to form the ground floor slab. The drainage design will be developed in conjunction with Wessex Water to provide any necessary attenuation storage in the area defined by gridlines C, E, 1 & 2.
Frame Upon completion of the pilecaps and groundbeams the steelframe will be de livered to site. The erection sequence will be established based on stability criteria ’. The frame construction would be facilitated by use of a self erec ting tower crane positioned on the East side of the building footprint. The various deliveries of the steel frame, the composite decking sheets, reinforcements and the ready-mix concrete, will be via Avon Street and off loaded and positioned by use of the crane.
Page 4
City Of Bath College Welcome Building
Construction Method Statement
Cladding & Roofing The various specification cladding elements on the building (Masonry, render, curtain walling, Zinc etc) will be undertaken by use of a traditional full height independent scaffold to the perimeter of the building. The materials for inner leaf and internal wall construction will be distributed by forklift from the small storage area to the East of the building footprint. Because of the limitations on size of storage area the materials will be procured and delivered on a ‘just in time’ basis. Similarly, roofing materials will be loaded to the roof by us e of the telescopic forklift. Loading bays will be constructed at each floor level. The vertical Brise Soleil to the Western – Avon street – elevation will be installed by use of powered access equipment after the scaffold has been dismantled.
Liason / Communication Throughout the project Cowlin will maintain a high level of liaison and communication to all relevant parties to ensure that the project can be delivered with the least amount of disruption to neighbouring buildings and the public in general. Our Site Manager S tefan Thiel is looking forward to this project and will be happy to discuss any issues that may arise during the c onstruction. We will issue contact details for the site compound immediately after completion of the set up.
Page 5
City Of Bath College Welcome Building
Construction Method Statement
APPENDIX 1:
SITE COMPOUND PLAN
Access & Egress for Vehicles During Super structure Works
Deliveries through Avon Street
Existing College Blue shaded area not part of inital set up but may be used later for egress gate
Access & Egress for Vehicles Works. Pavement Priority to Pedestrians
Pedestrian Entrance
Contractors Compound Site Boundary Hoarding
Page 6
City Of Bath College Welcome Building
Construction Method Statement
APPENDIX 2:
City Of Bath College – Welcome Building Proposed Delivery Routes
Site DeliveryAccess DeliveryEgress
Avon Street St James’s Parade
Lower Bristol Road – A36 A 367
Page 7