HAZO HA ZOP P Study Study of Ba Batc tch h Plan Plants ts an and d Ope Opera ratio tions ns
Data Requirements
Definition of steps, including process conditions, agitation / mixing, charging, reacting, discharging etc.
Interlocks in operation during step (e.g. ( e.g. valves held closed)
Necessary conditions to move to next step
Details of alarms, including “watchdog” timers
© Det Norske Veritas AS. All rights rights reserved.
2
Preparations Leader and some members should prepare before study to understand:
Hazards of the process
Control scheme, including sequence control
Cycle of operations and main process steps
Study sections to be used
© Det Norske Veritas AS. All rights reserved.
3
Preparations Leader must decide how to carry out the study, after preparing the following:
A matrix showing the process steps and the study sections, and showing which section is active in which step A chart showing which valves, drives, pumps and instruments are active in each step of the process
© Det Norske Veritas AS. All rights reserved.
4
Guidewords
The standard guidewords from Process HAZOP are used
Additionally, guidewords related to the following parameters are used: - Time - Step - Action
© Det Norske Veritas AS. All rights reserved.
5
Additional Guidewords: Time
NO TIME
Event or action missed altogether
MORE TIME
Event occurs after it should or takes longer time
LESS TIME
Event occurs before it should or takes shorter time
WRONG TIME
Event or action occurs when it should not
© Det Norske Veritas AS. All rights reserved.
6
Additional Guidewords: Step
STEP TOO LATE
An input fault prevents step on
STEP TOO EARLY
Step on conditions met early
STEP LEFT OUT
Operator forgets a step
STEP BACKWARDS
Fault causes incorrect transfer to another step
© Det Norske Veritas AS. All rights reserved.
7
Additional Guidewords: Step
STEP TOO LATE
An input fault prevents step on (= MORE TIME)
STEP TOO EARLY
Step on conditions met early (= LESS TIME)
STEP LEFT OUT
Operator forgets a step (= NO TIME)
STEP BACKWARDS
Thus, guidewords associated with the parameter STEP can be addressed by TIME
© Det Norske Veritas AS. All rights reserved.
Fault causes incorrect transfer to another step (= WRONG TIME)
8
Additional Guidewords: Action
PART ACTION
One sub-action in a step is missed
EXTRA ACTION
Operator includes an action from another step
WRONG ACTION
An aberration - needs serious brain storming
© Det Norske Veritas AS. All rights reserved.
9
Procedure: Option 1 – Step by Step
Consider 1st step, for all active sections, then all inactive sections Use all guidewords for active sections, not for inactive sections, where “becomes active” is the deviation
Take each step in turn and repeat this process
Identify and study other sections not in normal operation
© Det Norske Veritas AS. All rights reserved.
10
Step by Step Method st
1 Step
st
Take 1 Active Section
Complete Logsheet
No Take next active section
Last Active Section ?
Yes Take other inactive sections
Complete Logsheet
Last Step ? Yes Finshed
© Det Norske Veritas AS. All rights reserved.
11
Next
Step
Procedure: Option 2 – Section by Section
Consider 1st section, for all steps: - First for steps when it is active - Then for others
Use all guidewords for active steps, not for inactive steps, where “becomes active” is the deviation
Take each section in turn, and repeat this process
Identify and study other sections not in normal operation
© Det Norske Veritas AS. All rights reserved.
12
Section by Section Method st
1 Section
st
Take 1 Step in which this section is active
Complete Logsheet
No Take next step in which this section is active
Last Step in which this section is active ?
Yes Take steps in which this Section is not active
Complete Logsheet
Last Section ? Yes Finshed
© Det Norske Veritas AS. All rights reserved.
13
Next
Section
Procedure: Which Option? Consider matrix showing steps and sections:
If there are fewer steps, use step-by-step
If there are fewer sections, use section-by-section
If there are equal numbers of each, it does not matter which option you choose
© Det Norske Veritas AS. All rights reserved.
14
Refrigerated Ship Loading: Batch HAZOP Example XCV4
V281
T1
P1
Q.R.C. 10” 150#
T1
V284
V282 1.5”
10” Export Line 1.5”
XCV3
V78 1”
V280
3”
V283 V80
V77
To Sea
e.g. Ammonia or LNG
© Det Norske Veritas AS. All rights reserved.
8” Vapour Return Line
15
Analysis Matrix for Refrigerated Ship Loading Steps
(1) Cool Line
(2) Connect Arm
(3) Cool Arm
Delivery Line
A
I
A
A
I
I
Recirculation Line
A
I
I
I
I
I
Loading Arm
I
A
A
A
A
A
Sections
(4) (5) (6) Load Ship Purge and Disconnect Drain Arm Arm
Which approach is recommended: section-by-section or step-by-step?
In what order should the steps be considered for each section?
© Det Norske Veritas AS. All rights reserved.
16
Open/Closed Valves etc. for Refrigerated Ship Loading Steps
(1) Cool Line
(2) Connect Arm
(3) Cool Arm
V77
O
O
C
C
C
M
V80
C
C
C
C
C
C
V78
C
C
O
O
C
C
V284
C
C
C
C
C
C
XCV3
C
C
O
O
C
C
V280
C
C
C
C
C
C
XCV4
C
C
C
C
C
C
V281
C
C
O
O
O
C
QRC
D
Conn
Conn
Conn
Conn
D
V282
C
C
O
O
O
C
V283
C
C
C
C
O
C
Valves etc.
(4) (5) (6) Load Ship Purge and Disconnect Drain Arm Arm
O = Open; C = Closed; D = Disconnected; Conn = Connected
© Det Norske Veritas AS. All rights reserved.
17
Batch Reactor HAZOP Example Distillation Column
Nitrogen Purge Solvent A
Condenser
HV-1
Reactant B
PCV-1
HV-2
Reactant C
HV-5
Coolant in TCV-2 Catalyst D
HV-3 HV-7
Stirrer AG-1
HV-4
AV-1
Vent
Receiver R2
Heating/cooling fluid TCV-1
Vacuum
Distillate Transfer
Batch Reactor R1 P-3
HV-6 Product discharge to storage P-1
P-2
PCV-2
© Det Norske Veritas AS. All rights reserved.
Excess heating/cooling fluid discharge
Slide 18
HAZOP Procedure For Batch Units VALVE/EQUIPMENT ITEM PROCESS STEP
HV-1
HV-2
HV-3
HV-4
HV-5
HV-6
HV-7
PCV1
PCV2
AV-1
TCV1
TCV2
AG-1
P-1
P-2
P-3
Before start of batch
C
C
C
C
C
C
C
C
C
C
C
C
Off
Off
Off
Off
1. Nitrogen Purge
C
C
C
C
C
C
O
C
C
O
C
C
Off
Off
Off
Off
2. Charging Solvent A
O
C
C
C
C
C
C
C
C
O
C
O
Off
Off
Off
Off
3. Charging Reactant B
C
O
C
C
C
C
C
C
C
O
C
O
On
Off
Off
Off
4. Charging Reactant C
C
C
O
C
C
C
C
C
C
C
C
O
On
Off
Off
Off
5. Charging Catalyst D
C
C
C
O
C
C
C
C
C
C
C
O
On
Off
Off
Off
6. Heating
C
C
C
C
C
C
C
C
M
C
M
O
On
On
Off
Off
7. Pull Vac on Reactor
C
C
C
C
O
C
C
M
M
C
M
O
On
On
Off
Off
8. Distillation
C
C
C
C
O
C
C
M
M
C
M
O
On
On
Off
Off
9. Break vacuum
C
C
C
C
O
C
O
C
M
C
M
O
On
On
Off
Off
10. Cooling
C
C
C
C
C
C
C
C
M
O
M
O
On
On
Off
Off
11. Discharge Distillate
C
C
C
C
C
C
C
C
M
O
M
O
On
On
Off
On
12. Discharge Product
C
C
C
C
C
O
C
C
C
O
C
C
Off
Off
On
Off
Symbols used:
C = closed O = open M = modulating
© Det Norske Veritas AS. All rights reserved.
Slide 19
HAZOP Procedure For Batch Units PROCESS STEPS STUDY SECTIONS
1
2
3
4
5
6
7
8
9
10
11
12
1. Nitrogen purge
A
I
I
I
I
I
I
I
A
I
I
I
2. Reactor
A
A
A
A
A
A
A
A
A
A
A
A
3. Jacket heating/cooling
I
I
I
I
I
A
A
A
A
A
A
I
4. Heating/cooling supply
I
I
I
I
I
A
A
A
A
A
A
I
5. Heating/cooling discharge
I
I
I
I
I
A
A
A
A
A
A
I
4. Solvent A
I
A
I
I
I
I
I
I
I
I
I
I
5. Reactant B
I
I
A
I
I
I
I
I
I
I
I
I
6. Reactant C
I
I
I
A
I
I
I
I
I
I
I
I
7. Vacuum system
I
I
I
I
I
I
A
A
I
I
I
I
8. Vent system
A
A
A
I
I
I
I
I
I
A
A
A
9. Catalyst D
I
I
I
I
A
I
I
I
I
I
I
I
10. Distillation Column & Condenser
A
A
A
A
A
A
A
A
A
A
A
A
11. Condenser coolant
I
A
A
A
A
A
A
A
A
A
A
I
12. Receiver
A
A
A
A
A
A
A
A
A
A
A
A
13. Distillate transfer system
I
I
I
I
I
I
I
I
I
I
A
I
14. Product Discharge system
I
I
I
I
I
I
I
I
I
I
I
A
circulation system
© Det Norske Veritas AS. All rights reserved.
© Det Norske Veritas AS. All ri hts
22 May
Slide 20
Batch HAZOP Logsheet Project:
Batch Reactor HAZOP Node: 001
Node Description:
Step 1 Nitrogen Purge to reactor Section Nitrogen purging line to reactor (active for this step)
GUIDEWORD/ DEVIATION
No Flow
More Pressure
Less Time
CAUSES
CONSEQUENCES
Page: 1
SAFEGUARDS
REC #
RECOMMENDATION
R1
Provide a flowmeter in the nitrogen supply line to indicate nitrogen flow to the reactor during purging.
Bursting disc system on R2 reactor set at 3 Barg. (not shown on drawing).
Ensure that the nitrogen supply pressure is below 1 Barg to prevent failure of the reactor bursting disc should the reactor become pressurised with nitrogen. Include in operating procedures for Step 1 the time the reactor must be purged with nitrogen for before proceeding to Step 2.
Manual valve closed No nitrogen supply to reactor. or line blockage. There no purging and potential No nitrogen supply. flammable atmosphere in the reactor when solvent is charged (Step 2). Potential fire or explosion if there is a source of ignition. Nitrogen supply Possible overpressure of reactor, pressure too high distillation system and receiver which could cause failure.
Operator knowledge and training. Reliable nitrogen supply.
Operator does not purge reactor for long enough.
As for ‘No Flow’ (above).
© Det Norske Veritas AS. All rights reserved.
As for ‘No Flow’ (above).
© Det Norske Veritas AS. All ri hts
22 May
R3
Slide 21
Batch HAZOP Logsheet Project:
Batch Reactor HAZOP
Node Description: Step 1 Section GUIDEWORD/ DEVIATION
CAUSES
Reverse low Reacor manway (Reactor) open
Less Flow (Vent Line)
Node: 002
Nitrogen Purge to reactor Reactor, Distillation line, condenser, receiver and vent line (all active for this step) CONSEQUENCES
SAFEGUARDS
Discharge of nitrogen around reactor area. Possible hazard to operators if they are close to the reactor
Standard pre-checks for this process are that reactor manway should be bolted closed before starting the nitrogen purge. Standard pre-checks for this process are that catalyst charge valve should be closed before starting the nitrogen purge. As before. Operating procedures.
Catalyst charge valve open.
As above.
Vent valve closed during nitrogen purging.
Inadequate purging with same consequences as for ‘No Flow’ and More Pressure in Node 1 (i.e. inadequate purging and increase in pressure in reactor system).
© Det Norske Veritas AS. All rights reserved.
Page: 1
© Det Norske Veritas AS. All ri hts
22 May
REC #
RECOMMENDATION
Slide 22
Batch HAZOP Logsheet Project:
Node: 003
Node Description: Step 1 Section GUIDEWORD/ DEVIATION
More flow (vacuum line)
Page: 1
Nitrogen Purge to reactor Other non-active sections in this step.
CAUSES
Vacuum valve PCV1 open when purging reactor with nitrogen.
© Det Norske Veritas AS. All rights reserved.
CONSEQUENCES
SAFEGUARDS
Vacuum created in reactor and increased purging flow. No hazard.
© Det Norske Veritas AS. All ri hts
22 May
REC #
RECOMMENDATION
Pressure gauge on reactor.
Slide 23
Batch HAZOP Logsheet Project:
Node: 001
Node Description: Step 2 Section GUIDEWORD/ DEVIATION
CAUSES
No flow
Operator forgets to charge solvent. Valve blocked.
More time.
Operator error. Batch meter set incorrectly.
Wrong Action
Operator error. Wrong solvent supply routed to reactor.
© Det Norske Veritas AS. All rights reserved.
Page: 2
Charging Solvent A to reactor Solvent A feed line to reactor CONSEQUENCES
SAFEGUARDS
No solvent transfer to reactor. Potential exothermic reaction when other eactants are heated during the process. This would cause loss of product (failed batch). Too much solvent added to reactor. Reactor may be overfilled when reactants are added. Possible discharge of reactants and solvent from the catalyst charging connection during Step 5. Wrong solvent transferred to reactor. Loss of product (failed batch). Potential hazard of using incorrect solvents not known.
Operator checks solvent quantity added on meter upsteam. This is entered on the batch record sheet.
© Det Norske Veritas AS. All ri hts
22 May
Operating procedures.
Operating procedures.
REC #
RECOMMENDATION
R4
Provide software interlock on batch meter for Solvent A to ensure that batch quantity cannot be exceeded.
Check what other solvent could be mistakenly added to the reactor and check whether these could create a hazard if they were used instead of Solvent A.
Slide 24
Batch HAZOP Logsheet Project:
Node: 005
Node Description: Step 2 Section GUIDEWORD/ DEVIATION Less flow
CAUSES
Reactor drain valve open
© Det Norske Veritas AS. All rights reserved.
Page: 1
Charging Solvent A to reactor Reactor (active during this step) CONSEQUENCES
SAFEGUARDS
Solvent discharged from reactor drain line. Inadequate solvent in reactor. Possible effect on reaction/product quality.
Operating procedues and pre-start checks that run out valve is closed before adding solvent. Solvent loss would be small since P2 must be used to remove material from the reactor
© Det Norske Veritas AS. All ri hts
22 May
REC #
RECOMMENDATION
Slide 25
Batch HAZOP Logsheet Project:
Node: 005
Node Description: Step 2 GUIDEWORD/ DEVIATION
Section CAUSES
Page: 1
Charging Solvent A to reactor Other non active sections CONSEQUENCES
SAFEGUARDS
REC #
RECOMMENDATION
No hazards identified.
© Det Norske Veritas AS. All rights reserved.
© Det Norske Veritas AS. All ri hts
22 May
Slide 26
Safeguarding life, property and the environment www.dnv.com
© Det Norske Veritas AS. All rights reserved.
27