HEAT-RECOVERY STEAM GENERATORS SPECIAL ISSUE: OUTAGE HANDBOOK
Learn the basics of HRSG inspection
T
he global economic downturn be the best program in the industry will impose new challenges on for teaching plant personnel the funplant operations. It’s difficult to damentals of heat-recovery steam believe that you will be asked generators. A graduate who later to do more with a smaller budget, becomes his or her plant’s resident but you will. However, approaching “expert” on HRSGs is likely to attend Stanley opened the online segment of these new challenges with a positive the Academy a second time—to dig the program by stating its goals: mindset can yield significant ben- into specifics. Think of Shakespeare n Identify poor operating practices. efits. One might be that your junior here: You can’t possibly understand n Identify areas requiring attention staff is forced to learn more about and absorb everything in one pass, or when plant operation permits an power-generation processes, equip- even two. offline inspection and/or during ment, and systems, thereby increasThe segment of the academy prothe next maintenance outage. ing the level of expertise onsite. gram dealing with HRSG inspec An area of possible cost-cutting tion was “taught” by Lester Stanley, Data review tasks at some gas-turbine-based cogen- Scott Wambeke, and Amy Sieben, eration and combined-cycle plants all licensed professional engineers The best place to begin your inspecis in heat-recovery steam generator with a wealth of experience in HRSG tion, the three instructors agreed, is (HRSG) inspection. Developing on- design, inspection, and trouble- in the control center where you have staff capability to conduct base-level shooting. Their course covered both access to personnel familiar with the HRSG inspections saves both money online and offline inspection. The plant’s operational idiosyncrasies as and the need to schedule yet another first encompassed data review tasks well as to historical data. This invesservice organization into an already conducted in and around the control tigative work generally is done while complex outage matrix. room and field tasks requiring a u nit the unit is operating to be sure it does Most plants have considerable gas- walk-down. Offline inspection was not impact outage duration. HRST and steam-turbine expertise but many divided into gas-side, exterior, and uses a basic 10-point checklist for do not have on-staff experts for HRSGs drums. Also included was a primer the data-review task, but items may and generators. Developing HRSG on nondestructive examination be added and/or deleted depending know-how begins with understanding (NDE) techniques and on sampling of on plant design and other considerthe types of degradation/damage that deposits and pressure parts. ations. 1. Feedwater control. Three can occur and where to look for each. of the many questions you To compile the checkshould ask operations perLearned at HRST Inc’s list that follows, the editors sonnel are these: attended the HRSG Acadn Do you see large flucemy conducted by HRST tuations in feedwater flow Inc, Eden Prairie, Minn. during “steady-state” operaThe engineering services tion? firm focuses on inspection, n Does feedwater flow start training, O&M, and redesign and stop frequently during projects for this special class startup? of steam generators. It conn During overnight shutducts two “academies” annudowns, is there frequent ally in North America and “topping-off” of the drum to periodically in international maintain level? locations. Each hosts up to A “yes” answer to one or 50 to 60 “students,” the maxmore of the questions means imum practical class size to there’s risk of thermal-shock assure constructive interacdamage—especially in the Next session: Jan 27-29, 2009 tion among lecturers and coldest tube panel. These attendees while allowing all actions cause thermal-stress Marco Polo Beach Resort, Miami an opportunity to have their events to economizers and questions answered. feedwater heaters within Details at www www.hrstinc.com .hrstinc.com The HRSG Academy may the HRSG. The number and 2
Online inspection
COMBINED CYCLE
JOURNAL, Third Quarter 2008
4M022008D
Count On Powerful Relationships Relationships At Shaw, we build more than state-of-the-art power plants. We also build win-win working relationships with our clients that focus on one thing: successful project completion. As the industry turns to natural gas for clean, reliable power, you can turn to Shaw for on-target project project execution. We deliver deliver what you expect. expect. You can count on it.
www.shawgrp.com ENGINEERING • DESIGN • PROCUREMENT • CONSTRUCTION • COAL • GAS GEOTHERMAL • AIR QUALITY QUALIT Y CONTROL • POWER GENERATION SERVICES SHAW POWER GROUP, GROUP, FOSSIL DI VISION
_
_
_
HEAT-RECOVERY STEAM GENERATORS SPECIAL ISSUE: OUTAGE HANDBOOK
duration of events influences how every HRST presentation on boiler lower than the upstream one, water quickly tube leaks and cracking will health. Poor design, leaking valves, probably is leaking by the “closed” occur. ineffective spray nozzles, a lack of valve. 2. Steam drums. First thing to instrumentation, and other factors Give this immediate attention. investigate is the consistency among can wreak havoc at cogeneration Concern is that during startups and drum-level transmitters, level gages, and combined-cycle plants, putting shutdowns, water can dribble into the and probe indicators. personnel safety at risk and causing steam piping, collect along the botIf all are not in agreement, con- equipment damage that should never tom of the pipe, migrate downstream sider checking the calibration meth- occur. to superheater and/or reheater upper od and the pressure and headers, and then run down temperature compensation a few tubes. Cooling effect of settings for the level transthe water causes those tubes Control Block mitter. to contract. Resulting stress TC valve TC Spray water inlet valve Don’t overlook asking can cause tube bowing and Desuperheater if the “agreement” among tube-to-header weld cracks. nozzle assembly level indicators differs at Also check plant data to high and low steam loads identify times when spraying and/or high and low drum to less than the saturation levels. Stanley said that temperature of steam in the HRST often inspects highpipe plus 30 deg F. Do a thor1 pressure (HP) drums with ough review: startup, steadywater-level marks that are High-temperature steam state full load with and withDesuperheated steam several inches too high, yet out duct firing, steady-state the operators say they are controlling One of the first things to inves- low load (less than about 120 MW to the OEM’s guidelines. This means tigate is spray-valve behavior. Is for an F-class gas turbine), and durthere is disagreement between the spray-valve position near constant ing transients. Desuperheating to indicated and actual drum levels. at steady load or does it fluctuate— near-saturation temperature creates Concern here is that if the opera- sometimes closing entirely? If your the potential for damage like that tors experience a high-drum-level spray valve is continually hunting— described above for a leaking sprayevent, they may think they’re operat- that is, opening and closing dozens of water valve. ing below the “high-high” level (HHL) times each hour—the hot/cold cycles If your data review reflects the but are actually above it and drum eventually will stress desuperheater possibility of desuperheater probwater may be carrying-over into the nozzles to failure and possibly create lems and you are unfamiliar with the HP superheater. other damage as well. Control-logic attemperation station, walk it down Wambeke mentioned, “You now see adjustments generally can rectify while the plant is operating to see if that the value of a thorough annual this condition. design/installation deficiencies exist. inspection goes well beyond identiIf your desuperheating stations Fig 2 shows a poor desuperheater fying wear and tear that requires are properly designed and equipped arrangement. When Stanley flashed repair. It enables the operations with thermocouples (TCs) upstream this picture up on the screen, he noted team to see what’s really going on in and downstream, verify that both the following: the HRSG and suggests fine-tuning are reporting about the same steam n The thermocouple is so close to the of controls and procedures to avoid temperature when the control sysdesuperheater it gets quenched by incidents that can damage equip- tem indicates that the spray valve is water droplets, thereby providment unnecessarily.” closed (Fig 1). If this is not the case ing erroneous data. Specifically, Stanley continued, “Ask if the and the downstream TC is reading operators don’t know how close to rates of pressure increase and/or decrease during startup and shutdown exceed OEM guidelines.” If “yes,” you should be concerned about Desuperheater the possibility of fatigue damage at manways and thick nozzles and carefully check those locations when the unit is out of service. Thermocouple Upstream elbows HRST engineers are seeing more and more HRSGs with crack indications on downcomer nozzle welds, supporting what many in the industry have been saying for years: HPdrum nozzles are high on the list of components most susceptible to cycling stresses. Sieben added that spin cooling is hard on the HRSG too. “Most operations personnel don’t seem to approach shutdowns as carefully as they do startups,” she said, “and a fast cool-down can be just as damagNo drain or drip leg at low point ing as a fast start.” 3. Desuperheaters get a significant 2 amount of podium time in virtually 4
COMBINED CYCLE
JOURNAL, Third Quarter 2008
HEAT-RECOVERY STEAM GENERATORS SPECIAL ISSUE: OUTAGE HANDBOOK
saturation temperature that the plant is operating. An improved 300 Tube flow instability pipe location for the TC is needed. caused by low load n The desuperheater is too close and original tube-panel design to both the upstream and downThermal shock caused stream pipe elbows. Problems creby “topping-off” drum prior ated: Steam flow to the attemperato warm start tor is not uniform and spray water is not fully evaporated before 250 impinging on the downstream F , e r elbow. Latter causes fatigue dam- t u a age to the elbow. r e n There is no drain at the low point, p m allowing water to pool and to cre e T ate “water events” during startup. 4. Stack temperature. Recall that 200 high stack temperature is indicative of inefficient operation. Compare the actual readings at high and low loads and compare to known benchmarks. A large difference between the actual 3 and known signals a problem. Check common causes—such as debris 0 30 60 90 120 150 180 Time, min accumulation on finned-tube surfaces—and take corrective action. 5. Water temperature at economizer Don’t be surprised if the data you When the pump starts, listen for outlet. Compare the water tempera- seek are not available. Sometimes audible signs of cavitation. HRST ture at the economizer outlet to the permanent TCs are located in places engineers have been in several plants saturation temperature of water in that don’t indicate what actually is where poor design of the recirc systhe steam drum at the exact same happening in the tube panel and test tem has caused recurring cavitation time. If the two are within a couple of TCs must be installed. Fig 3 shows and pump damage—in some cases so degrees, Wambeke said, then water what an inspection team learned severe that the plants no longer use exiting the economizer contains about temperatures during startup their recirc pumps. However, this is steam. Avoid this condition with when test TCs were installed at stra- not a solution because the economizstartups that are as short as possible tegic locations within an LP econo- er can be damaged by thermal shock and maintain economizer feedwater mizer. and/or dewpoint corrosion. 7. Economizer recirculation pump. 8. Superheater and reheater drains. flow. Venting appropriatedly during filling and startup also is important. Verify during your inspection that the Proper drain operation is critical for Keep in mind that air pockets recirculation pump is operating early protecting superheaters and reheatblock water flow and once a circuit in startup and before new feedwater ers from large thermal shocks caused is blocked it will steam up, making is added to the LP economizer. This by the failure to remove condensate it even more difficult to “clear” dur- allows the recirc flow to buffer the prior to startup. Stanley stressed ing startup. If the temperature of the temperature difference between the that your inspection should, at a minwater at the economizer outlet makes hot tube panels and the relatively cold imum, confirm the following: several sudden jumps upward during water being injected into the circuit. n Low-point drains are open during startup from a lower-than-expected startup to purge water/condenvalue, this generally means a vapor sate prior to admitting steam to pockets are being cleared and normal tube panels (harps). It’s relatively operation is being restored. However, easy to check the timing of motorsuch clearing events, similar to water operated drain valves; for manuhammer, stress the economizer ally operated valves, verify that unnecessarily. proper procedures are in place and Stanley also suggested that you followed. compare an operating point to a n Drains are open sufficiently early known benchmark. A large difference in the startup process to ensure is cause for concern. Check for steamthat all condensate actually will be ing, gas-side fouling, vapor locking drained prior to steam admission. from trapped air, gas bypass, etc, and Operators at some plants where take corrective action. drains open to a funnel verify drains 6. Water temperature at economizer are clear of water by sound: A drain inlet. Review data to identify any incidischarging steam makes more dences of rapid temperature change noise. A more scientific approach (30 deg F/min, plus or minus) when is to install TCs on the drain pipe the unit is in operation or offline. and monitor for a reading above the Such rapid change is viewed as a saturation temperature. thermal shock to the economizer. n Drains are open during a trip, Also verify that the inlet temperarestart, and purge. ture doesn’t drop below 120F. Low n Panels do indeed drain completely temperature is the cause of dewpoint when drains are open. The ele4 condensation and tube wastage. vated drain tank in Fig 4 requires 6
COMBINED CYCLE
JOURNAL, Third Quarter 2008
SM
ADVANCED FLUID ASSESSMENT
IT GENERATES ENOUGH POWER FOR A CITY AND ENOUGH PROBLEMS FOR A CRISIS. It’s no secret—along with power, your turbines generate serious problems. Fortunately, our engineers have a SM
serious solution. It’s called VitalPoint —the first fluid assessment program designed exclusively for power generati on companies. With VitalPoint, you get the most advanced condition monitoring tools in the industry. If there’s a problem that threatens your equipment or an opportunity to extend your oil’s lifespan, our diagnostics will find it. To learn more, simply call 800-655-4473 and ask for a VitalPoint specialist. VitalPoint—cleaner energ y, from the inside out.
IT’S
BETTER
TO
KNOW
L O S A N G E L E S , C A | C H I C A G O , I L | L O U I S V I L L E, K Y | A T L A N T A , G A | H O U S T O N , T X | M O N T E R R E Y , M E X I C O | T O K Y O , J A P A N
HEAT-RECOVERY STEAM GENERATORS SPECIAL ISSUE: OUTAGE HANDBOOK
sufficient pressure in the drain system to push condensate up into the vessel. Drain tanks located in a pit are better because they allow gravity draining. Also check to see that HP, IP, and LP drains are not combined in a common collection pipe upstream of the blowdown tank. Reason: Flow through the HP drains could force water back into the IP or LP system if all the drains are open at the same time. Guidelines for proper drain system design can be found in the “HRSG Users Handbook,” published by the HRSG User’s Group (details at www.hrsgusers.org). 9. Selective catalytic reduction system. Compare historical ammonia consumption and outlet NO x readings. Rapid changes to NOx emissions or ammonia flow may identify catalyst plugging or poisoning or ammonia supply issues. Catalyst can be plugged by insulation released by way of transition-duct failure; ammonia injection nozzles can be plugged by contaminants in the reagent or by rust in lances; in oil-fired turbines, unburned fuel sprayed on catalyst during failed start attempts can ignite later and sinter the catalyst. 10. Gas-side backpressure. Does overall HRSG backpressure compare with OEM predictions? If not, what sections have more backpressure than predicted? If you can determine where backpressure is high, then the boiler inspection can investigate more carefully during the next outage. Gas-side cleaning of finned-tube sections is one solution. More proactive inlet-duct liner and insulation maintenance may be another if fouling by insulation fibers is to blame.
Online field tasks Some key inspection tasks only can be done while the HRSG is operating—identification of casing hotspots, for example. Here are five things Wambeke suggested that you should be sure to accomplish during your online walk-down: 1. Check the supplementary firing system. Look through all view ports to determine flame health and ductburner condition. Bullet points below provide some guidance for this activity based on HRST’s experience. n A flame length in excess of 12 ft for an F-class HRSG is too long. Reason: Long flames, typically caused by low exhaust flow and/or poor distribution of exhaust flow across the burner, can “lick” tubes in the first panel and cause localized overheating. n A bushy flame is desirable—that 8
is, unless it is angled upward or downward, which indicates a problem with exhaust flow to that portion of the burner. n A bright yellow flame is good; dull orange indicates too little exhaust flow. n Monitor CEMS data as supplemental firing is initiated and shut off. Noticeable step changes in NOx and CO levels may indicate a burner problem. n Check the integrity of burner elements and baffles. If breakage occurs, there is the possibility of damage to firing-duct walls and floors and to downstream tube bundles. 2. Watch for deflection of superheater and reheater floor pipe penetrations during startup and shutdown. Temperature differentials across superheater and reheater tube bundles can cause the panels to bow, exacerbating drain-line lateral movement. Drains that collide with the floor liner or casing often suffer stress-induced cracking. Stainless-steel bellows have difficulty moving laterally, while fabric seals in high-temperature locations typically stiffen-up. The extra motion created by panel bowing often causes bellows to crack and tear. On fabric seals, bands pull lose and the fabric kinks. Latter creates small holes
5
6
and leaks that propagate into fabric blowouts. Fig 5 shows a superheater drain seal that has ripped loose from the floor casing because of excess lateral movement combined with the expected axial motion. Stanley urged all attendees to also look for “stick and slip” of pipes during startup—a sign of hard interference with the floor. He said what happens is that drain lines don’t move much as the superheater warms up and then suddenly—bang—the pipe drops an inch or so. A little while later there’s another bang and another drop. Such hard c ontact/expansion interference obviously places unnecessary stresses on drain lines. 3. Stop, look, listen—for vibration. Listen carefully during your online walk-down. When standing alongside the transition duct connecting the GT outlet to the HRSG, do you hear any rattling or flapping sounds? They can emanate from loose and vibrating (a) internal liner sheets on walls, floor, or ceiling, (b) flow distribution plates, and/or (c) superheater baffles. Recall that the perforated flow distribution plates even out flow across the transition piece just upstream of the duct burner; superheater baffles prevent gas bypass around the tube bundle. Do you hear and/or see the casing pulsing or vibrating? Pay particular attention to the inlet duct to the HRSG, SCR cavity, and stack breeching. Vibration can fatigue internal liner support studs; if they fail, the liner and insulation may be lost. Sometimes a casing vibrates simply because it doesn’t have a sufficient number of stiffeners. The inlet-duct sidewall panel in Fig 6 has 10 horizontal stiffeners. But looking closely, note that the second, fourth, seventh, and ninth stiffeners (moving upward from the ground) were added after startup to address repeat liner failures attributed to casing vibration. The new stiffeners are larger and painted a different color than the originals. Vibration of walkways and platforms may be more obvious than casing vibration. If noted, look closely to determine if the source of the vibration is the HRSG. Stanley said to also check largebore piping for steady motion. If piping entering or exiting the HRSG is constantly rocking, the source of the disturbance could be the tube panels vibrating in the “breeze” of the GT exhaust stream. Repetitive motion can cause fatigue damage. When the unit is offline, push hard on tube panels to see if they swing or sway. If so,
COMBINED CYCLE
JOURNAL, Third Quarter 2008
HEAT-RECOVERY STEAM GENERATORS SPECIAL ISSUE: OUTAGE HANDBOOK
7
8
cially in areas where the casing is stiff—such as floors and roofs. Don’t forget to point the infrared gun at pipe penetrations, expansion joints, casing doors, field joints, and duct corners. The stainless-steel bellows seal under the HP superheater in Fig 8 reveals a hot spot where the seal attaches to the floor casing. Probable cause is a lack of insulation inside the bellows. High-temperature areas of the economizer drain-pipe penetration seals in Fig 9a pinpoint leakage through torn fabric. R is the reference temperature of 142F; Point 2 is at 519F, Point 3 at 390F, and Point 4 at 589F. Wear and tear on the seals is evident in Fig 9b. 5. Check pipe supports. First step is a visual survey to confirm that all
supports are connected and not at maximum travel in the “hot” condition. Record locations of all supports for comparison purposes during later inspections. Also note damage to hangers, supports, insulation, and/or lagging that may indicate transient phenomena— such as water hammer. Fig 10 shows a guide for a reheater pipe that was bent by a water-hammer event. Spring hanger indicator in Fig 11 should be surveyed in both the “hot” and “cold” positions. The red (hot) and white (cold) diamonds indicate as-designed conditions.
Offline inspection
9a
install better tube-panel restraints and guides. In some cases, sophisticated analysis is needed to determine the root cause of vibration. A noise signature often can help in this regard. Occasionally, vortex shedding in the tube bundles can create acoustic resonance problems. These may be noticed near the HRSG and/or in nearby buildings. Comparing calculated and measured shedding frequencies can give clues. 4. Identify hotspots. Begin with a visual survey of the casing for burned or discolored paint—for example, the pink area in Fig 7 at the lower portion of the inlet-duct sidewall. Then use an infrared gun to measure metal temperature; next, map temperatures and prioritize corrective action. Stanley said that casing temperatures above 350F are especially problematic if several square feet of casing are affected. Such high temperatures combined with the affected area cause restrained expansion which, in turn, results in cracking of casing steel—sometimes severe. Most paint will discolor above 350F and cracking is a possibility, espe10
9b
10
The HRST instructors divided the offline inspection module into four parts: gas side, exterior, drums, and so-called “extended scope” focusing on nondestructive examination (NDE). Stanley handled the first two; Sieben and Wambeke handled the remaining two. Stanley began by stating four primary goals of offline inspection: n Document equipment condition. n Identify items requiring immediate maintenance. n Note emerging problems, thereby allowing time for analysis. n Begin planning and budgeting maintenance activities for future outages.
Gas side
11
Key to an effective gas-side inspection, the HRST instructors told the group, are the following: n Dedicated, meticulous inspectors. They recommended a mixed team consisting mainly of in-house personnel and some outside experts with broad industry perspective. Also stressed was that any inspection worthwhile undertaking should be done properly; good
COMBINED CYCLE
JOURNAL, Third Quarter 2008
ALLIED POWER GROUP PUTS SALES AND SERVICE IN SYNCHRONICITY.
ALLIED POWER GROUP IS YOUR ONE TRUSTED SOURCE FOR FAST REPAIRS AND HIGH-QUALITY REPLACEMENT PARTS. WE HAVE ONE OF THE LARGEST GE AND WESTINGHOUSE INVENTORIES IN THE WORLD AND CAN PROVIDE FAST, HIGH QUALITY REPAIRS FOR IGT COMPONENTS SUCH AS HOT GAS PATH AND COMBUSTION COMPONENTS FOR MAJOR OEMS. WITH FLEXIBLE OPTIONS LIKE E XCHANGE AND LOANER PROGRAMS, CONSIGNMENT, SALES AND LEASE, INVENTORY MANAGEMENT AND POOLING, ALLIED POWER GROUP IS YOUR ONE-STOP SHOP. BEST OF ALL, WE PROVIDE AN UNMATCHED LEVEL OF SERVICE WHEREVER AND WHENEVER YOU NEED IT TO KEEP YOUR BUSINESS RUNNING.
1 5 0 0 5 M i n t z L a n e, H o u s t o n, T X 7 70 1 4
1.888.830.3535
alliedpg.com
UNITED FOR PERFORMANCE.
Product names, logos, brands, and other trademarks mentioned herein are the property of their respective trademark holders. These trademark holders are not affiliated with Allied Power Group, nor do they sponsor or endorse any of the products, services or methods supplied or used by Allied Power Group.
HEAT-RECOVERY STEAM GENERATORS SPECIAL ISSUE: OUTAGE HANDBOOK
n
n
n
inspections, Stanley continued, take days, not hours. A detailed record of observations and other facts. Take plenty of photos and measurements; describe observations in detail using a digital recorder and transcribing/editing your voice notes. Critical measurements might include material thickness in areas experiencing FAC (flow accelerated corrosion) attack, length of any cracks identified, distances across any cracks found, etc. Organize facts logically. Link every fact to a specific location in the HRSG. Editor’s note: Perhaps this goal can be facilitated through use of software customized for your specific boilers. To learn more, access www.combinedcyclejournal.com/archives.html, click 3Q/2007, click “Knowledge retention: New software tools help improve plant reliability, reduce maintenance cost” on issue cover. Your ultimate goal should be to provide a comprehensive followup checklist with detailed notes so someone else can conduct next year’s inspection having the same knowledge you possess—that is, to pick up where you left off without missing a beat. Recommend a follow-up NDE program for areas where problems are suspected. This might include one or more of the following: borescope examination, ultrasonic (UT) surveys, dye-penetrant (PT) testing,
magnetic-particle (MT) examina- a liner plate moves and a gap is cretion, hardness testing (particu- ated between it and adjacent plates, larly where P91/T91 materials are insulation can be sucked into the flow used), etc. stream. This creates a hot spot in the For inspection purposes, Stanley seg- transition duct skin and allows liberments the HRSG into three areas: ated insulation to blind a portion of the SCR catalyst. n Access lanes—including inlet duct, firing duct, SCR, between Be aware that problems often are tube bundles, and stack. experienced with flow distribution plates. Also, check harps for corron Crawl spaces under and above tube headers. sion, warped tubes, and vibration wear from tubes contacting—that is, n Exterior—including roof casing, floor casing, walls. banging into or rubbing against— Your inspection should go beyond each other when the unit is in serwhat HRST would do under its vice. Baffles and tube ties should standard HRSG contract. Engage be inspected for vibration damage, other experts to examine your steam wear, expansion interferences, and valves, safety valves, silencers, weld cracks. Figs 13, 14 show failed tube-fin tab instrumentation, piping to/from the HRSG, etc. welds that caused “rattling.” Some Inlet-duct checklist. Inspect the failed tabs rub directly on tubes. liner system for loose plates, spinning Although no gouges were identified washers, exposed insulation, and in this case, if condition is left uncorfailed studs. Fig 12 is typical of what rected, tube wear will continue (tubeyou might find. Here studs failed and tie components are harder than the washers were liberated leaving liner tube material). Such wear often is plates with minimal support. Once worst at lower elevations, which is convenient because they are easier to access for inspection. Note that the Studs broken; inlet-duct superheater panel in Fig 15 washers missing is missing center baffles. Firing-duct checklist has five focal points for your inspection: n Liner system. Inspect the same way you did for the inlet duct. n Duct burner. Look for sag in elements or baffles, nozzle plugging, and coke buildup; verify that burner “wing” condition is satis12 factory.
13
14
16
12
15
17
COMBINED CYCLE
JOURNAL, Third Quarter 2008
“
The system allows us to respond quickly to changes in component performance, before they impact plant heat rate. — Chung Liu, Massachusetts Municipal Wholesale Electric Company
”
Energy EtaPRO ™ Performance Monitoring and Optimization System saves money while reducing emissions. With 600+ generating units worldwide, General Physics Corporation’s real-time monitoring helps plants achieve a
1% or better heat rate improvement
and typically provides a 100% ROI in less than 12 months. From installation to operation, our power plant experts partner with you and respond quickly whenever you need them. Put our experience to work for you.
www.etaproefficiency.com 800.803.6737
EtaPRO
™
REMOTE I
Offices in:
I
I
North America • Latin America • Europe • Asia
Visit us at POWER-GEN International, #2112. Visit us at HRSG,Booth Booth 716 IT
I G
E
ICE
I
HEAT-RECOVERY STEAM GENERATORS SPECIAL ISSUE: OUTAGE HANDBOOK
Tubes and fins. Inspect the same way you did for the inlet duct. But also check for evidence of flame impingement or local hot spots as well as for tubes bowed because of desuperheater issues. n Baffles and supports. Look for loose or missing baffles, plus overheated tube ties and baffles. n Firing-duct TCs. Be aware that most thermocouples are too short to read representative temperatures. Also, that TCs typically have no radiation shield and they are influenced by cool tubes and burner shine. Figs 16-21 illustrate what to look for when inspecting the firing duct. Bowed reheater tubes in Fig 16 are downstream of the desuperheater, which probably allowed wet steam to enter the tubes. A Sky Climber or scaffolding is needed to perform a good duct-burner inspection (Fig 17) and repair any cracking identified (Fig 18). Burner coking sometimes is found when alternative fuels are burned. Fig 19 shows coking on a duct burner firing refinery gas. Olefins reportedly were the cause in this case. Coking can occur when burning natural gas if there is poor mixing of air and fuel at the burner. An overheated liner protecting the sidewall of a firing duct is shown in Fig 20. Hot-spot indications on tubes downstream of duct burners are illustrated in Fig 21. Tube-bundle access-lane checklist. n
18a
This list begins, like the inlet- and firing-duct checklists above, with the liner system. Same principles apply. Next, tubes and fins should be inspected for corrosion, warping, and fouling. Warping of superheater and reheater tubes caused by poor control of the desuperheating process is relatively common (refer back to Fig 16). Warping is also indentified with LP and IP economizers that share common headers with HP economizers (for more detail, access www.combinedcyclejournal.com/archiveshtml, click 1Q/2008, click “Module, header replacement. . . .” on issue cover. Look carefully for tube-to-header weld cracking (Fig 22). It can accompany tube bowing, but often is found as well on tubes that have not bowed. Tube bowing and cracking usually
18b
are caused by the same problem: Wet steam entering the tube field. Tubes downstream of the SCR are susceptible to fouling by ammonia salts and by rust that flakes off carbon-steel fin and tube surfaces (Fig 23). The amount of sulfur in the fuel, and in the inlet air, impacts the rate of fouling; so does the amount of time the unit is offline, particularly in a humid environment. Inspect bundles for wear caused by tube vibration. This will be found most often where tube-tie welds are broken and tubes are free to rattle around (refer back to Fig 14). Fig 24 shows where baffles are located to avoid bypass of gas around heat-transfer surfaces. If metal deterioration is identified, make a note for maintenance follow-up. Also iden-
20
19
21
14
22 COMBINED CYCLE
23
JOURNAL, Third Quarter 2008
HEAT-RECOVERY STEAM GENERATORS SPECIAL ISSUE: OUTAGE HANDBOOK Sidewall baffles
Exhaust flow is into page Upper header
Lower header Center (laning) baffles
Header (bulkhead) baffles
Tubes
25
24
26
27
28
29
30a
30b
tify and correct areas where expan- bricks to settle. This can create gaps sion/contraction adversely impact between blocks, especially in the top baffle function (Fig 25) and where baf- row of each module (Fig 27). Insulafles have slipped down tubes (often tion then is free to blow downstream because fins have broken off) and cre- and plug LP heat-transfer surfaces. Crawl-space checklist. Inspecting ated openings for gas bypass. As you move back through the unit, the upper and lower crawl spaces in Stanley said, look over the upstream an F-class HRSG may not be much face of the SCR catalyst for fouling— fun, but it certainly is where an typically caused by rust and/or insu- inspector proves his or her value. lation fiber entrained in the hot gas Virtually everyone on the plant staff (Fig 26). Gas bypass around the cata- can hear casing vibration or see dislyst limits its effectiveness and could colored paint at a hotspot, but only a possibly put the plant out of com- well-trained and physically fit inspecpliance on NOx. Be sure to look for tor can slither around a cramped, poorly installed baffling, open space dirty crawl space and identify existaround the perimeter of the catalyst ing and possible future problems. bed, and gaps between baffling and Inspectors examine floor debris for catalyst frames. evidence of problems, the liner, liner Finally, look for openings between fit-up around piping and hanger pencatalyst blocks and between the etrations, baffles, bent piping, header b l o c k s a n d f r a m e s . I n s u l a t i o n corrosion, header/tube joint condition between blocks has been known to where visible, dripping water or corcompress over time, allowing catalyst rosion/rust stains from tube leaks, 16
etc. The photos in Figs 28 to 35 show some of the things you can expect to encounter. n A bent (and binding) liner donut around a pipe penetration in the floor liner is shown in Fig 28. A donut in such poor condition allows insulation to migrate upward, thereby creating a hotspot in the floor casing and limiting penetration seal life. It also allows debris to enter the seal underneath, accelerating damage to it and increasing corrosion risk. n Fig 29 is a reheater pipe penetration with no liner donut, a condition that hastens degradation of insulation. A hotspot is created around the stainless steel bellows below because there is no thermal barrier between the 1050F reheat pipe and the bellows. n Insulation slips down and out of stainless-steel bellows located
COMBINED CYCLE
JOURNAL, Third Quarter 2008
COMBINED CYCLE
JOURNAL, Third Quarter 2008
17
HEAT-RECOVERY STEAM GENERATORS SPECIAL ISSUE: OUTAGE HANDBOOK
31a
31b
32a
32b
33a
33b
Opening
be looking for when inspecting an HRSG. The checklist presented for this module had a familiar ring: n Casing hotspots and cracking. n Piping penetration seals. n Access-door condition. n Pipe hangers. n Expansion joints at the round-tosquare transition and between the HRSG and stack. n HRSG foundations. Of course, this isn’t all you should be inspecting on the exterior of your HRSG. Time limitations in the classroom and space limitations in the magazine militate against covering everything. When developing an inspection program customized to your plant, don’t forget such things as burner hardware, valves, safety valves and silencers, drum instrumentation, ammonia vaporizer, ammonia injection grid and associated piping and nozzles, etc. Once again, photos taken during inspections conducted by HRST engineers give you a good sense of what’s important: n Fig 36 shows hotspot on access door and adjacent casing caused by leaking door seal and/or problems with the internal insulation pillow. n Rust that accumulates in a fabric seal impedes its ability to flex and eventually the material splits (Fig 37). Liner donuts that are maintained in good condition help prevent rust from dropping into the seal. n Cracked stainless-steel bellows in Fig 38 is a casualty of excessive drain movement as discussed ear-
Gap
34
n
n
n
18
above roof casing because no liner donut is present (Fig 30a). Roof-top photo reveals casing rust and blue tint to bellows indicative of operational hotspots (Fig 30b). Drain pipes under HP superheaters and reheaters are notorious for developing stress cracks— especially at the drain pipe-to jumper weld (Fig 31a). Inspector’s finger points to what he believes is a crack (Fig 31b), later confirmed with dye-penetrant test. Debris accumulation on roof allows rainwater to pool (Fig 32a), leading to corrosion problems inside the HRSG. The result of long periods offline and water leakage is shown in (Fig 32b). Poor condition of drain line serving an LP economizer was found
35
n
n
during an inspection of the lower crawl space below this HRSG (Fig 33a). HRST engineers recommended removing the stainlesssteel bellows expansion joint around this drain, which had lost about 25% of its wall thickness in five years of service (Fig 33B). Gas bypass: Rust is swept away in region of high gas velocity downstream of the small square dark opening in Fig 34. Oversize gaps, which proper baffling should prevent, may avoid interference problems but they adversely impact performance (Fig 35).
36
Exterior inspection By this point in the session, attendees were catching on to what they should COMBINED CYCLE
37
JOURNAL, Third Quarter 2008
GE Energy
Worldwide service is in your reach. GE Energy’s aeroderivative services arelocated where youneed them— anywhere in the world. Our service centers arepositionedaroundthe globe, ready to provide a full array of services forindustrial andmarine customers. We also have an established network of international field service teams who can deliver the technological expertise you expect from GE right to your site. No matter where you are, the aero energy service team is there to help you reach your goal. Visit us at ge.com/energy and findout more.
Service capabilities include contractual service agreements, engine and module exchange programs, spare parts, modules and engines, repair and overhaul capability and engineering services both in the field and from the factory.
HEAT-RECOVERY STEAM GENERATORS SPECIAL ISSUE: OUTAGE HANDBOOK
n
lier. Mechanical seals are an alternative to fabric seals and bellows. Large casing hotspots can cause walls and/or floors to expand more than anticipated. Inflexible support columns can create stress points, cracks, and hot gas leaks at locations shown in Fig 39. One example is foundation cracking in Fig 40, caused by restrained expansion of the inlet-duct support column. Such cracking can be caused by hotspots or by improper bolting of the column to the foundation base plate.
Drums Amy Sieben took over for Lester Stanley at the podium. First thing she mentioned: Steam drums provide the only non-intrusive access to the water/
38
Expansion
Stress point (typical)
39
40
20
steam side of an F-class HRSG. That’s an important point. All boiler water eventually passes through one or more steam drums in a triple-pressure unit, so a great deal can be learned from a proper inspection. Sieben’s checklist included the following: n Inspect the drum internal surface. n Investigate any signs of distress on steam separation equipment and the belly pan which are caused by thermal stress (cracks) or flow-accelerated corrosion (FAC). If components are worn, measure metal thickness to quantify the extent of material loss. n Verify mechanical integrity. n Determine if the actual waterline is at the level designers intended. n Scoop-up and carefully examine drum debris. Run tests to characterize the debris if necessary. n Check the manway ring to see if machining is necessary to restore it to the desired flat condition. A thorough examination of the drum internal surface demands that you get up close to the metal and look for pits, nicks, cracks, tubercles, corrosion, erosion, etc. Take notes and pictures of anything that looks out of the ordinary, Wambeke suggested from the back of the room. Begin with a color assessment: Red is good in an oxidizing environment (Fig 41), bad in a reducing environment. Next, assess overall drum condition, tracking surface defects from manufacture—such as those created while rolling steel for the HP drum pictured in Fig 42. Scaling and lack of passivation during operation is illustrated in Fig 43. Has smoothness/roughness of the drum surface changed during the inspection interval? For example, perhaps tubercles have formed (Fig 44) . It is particularly important to identify any pitting attack and to inspect what the pits look like underneath. Keep in mind that pits may corrode under pits, resulting in pits larger than those at the surface. Signs of distress to look for on steam separators and the belly pan include the following: n Cracks in the belly pan (or baffle plate), as shown in Fig 45. n Cracks in the corners of the final separator (Fig 46). n Thinning caused by FAC, as evidenced by the loss of material on the belly pan in Fig 47a and the hole in the LP belly pan in Fig 47b. Also, early FAC attack on the LP cyclone in Fig 48a and advanced attack (huge hole) on the Fig 48b cyclone.
41
42
43
44
Ultrasonic (UT) thickness measurements are useful for documenting the condition of drum internals, as well as of tubes and piping. Keep meticulous records to enable rateof- wear calculations and timely maintenance planning. Standard UT measurements are all that’s needed to quantify material loss. Thickness testing of internals compares original specifications of drum components to data collected during your inspection. More sophisticated UT—such as shear-wave and phasedarray—are used to identify cracking. The software described in last year’s Outage Handbook (see italicized editor’s note above) allows direct capture electronically of thickness measurements as the UT probe
COMBINED CYCLE
JOURNAL, Third Quarter 2008
Turbine Lube Oil & EHC Solutions When gas turbines fall casualty to unit trips and fail-to-start conditions, lube oil varnish is the usual suspect . . . So how do you solve the problem? Electrostatic oil cleaners and depth filter systems alone yield little or no long term success. While your unit is on-line and the oil is warm, the majority of varnish-causing contaminants are in solution and cannot be removed by electrostatic or depth filtration systems.
Hy-Pro has the solution to make varnish vanish . . . And it doesn’t require electrostatic oil cleaning! Patent-pending Ion Charge Bonding technology removes varnish-causing contaminants while they are still in solution whether your turbine is on-line or standing by. Hy-Pro’s soluble varnish removal system is the proven solution to restore and maintain the health of your turbine oil!
before
after
Achieve & Maintain Target Varnish Potential Numbers in Days not Months! Dedicated Off-Line Gearbox Filtration
Duplex Filter, auto kleen upgrade
Vacuum Dehydration & Turbine Oil Coalescence
EHC & Lube Oil Filter Element Upgrades. Non-spark & static dissipating elements.
Fluid Contamination Under Control with . . . Innovative Filtration Products, Support and Solutions Make Hy-Pro a part of your lube team and arm yourself with tools and industry expertise to maximize reliability from your hydraulic & Lube assets. Hy-Pro will help you develop and implement strategies to achieve and maintain target fluid cleanliness levels and extend useful fluid life.
www.hyprofiltration.com Fishers, Indiana USA. +1.317.849.3535
FILTRATION
HEAT-RECOVERY STEAM GENERATORS SPECIAL ISSUE: OUTAGE HANDBOOK
45
46
47a
48a
47b
48b
is moved across the surfaces of affected components. Data are stored in a manner that allows retrieval by clicking on a particular tube, header, etc, on drawings of your unit incorporated into the software package. Mechanical integrity. Look for the obvious: Broken “U” bolts, missing nuts and other hardware, plugged chemical-feed lines and separators, etc. Fig 49 shows a fractured chemical-feed line found in the HP drum of one boiler inspected by HRST engineers; Fig 50 reveals a bolt missing from a secondary separator; Fig 51a is of a mesh separator failure; Fig 51b shows a mesh-separator pad resting at the bottom of the steam drum. Water level. The primary cause of faulty level indication is instrumentation that is out of calibration. Sometimes, however, water level falsely appears lower than actual because the level transmitter is located too near a downcomer or pump intake. Their suction effect “pulls” on the level sensing lines (Fig 52). Plugging of sensing lines is another possible cause of false readings or sluggish response. Fig 53 shows a pencil-type magnet with debris pulled from a lower-level tap for an HP drum. Debris volume, if large, suggests possible rethinking of blowdown procedures and/or the need to check for iron transport caused by FAC. Fig 54 is a photo of iron debris found in a stagnant area of an HP drum at an end beyond the baffle. Also check for this material in the blowdown tank.
NDE basics
22
49
50
51a
51b
52
53
Sieben suggested, “Depending on the HRSG’s age, number and severity of cycles, and past issues, intrusive inspection techniques should be considered to more accurately assess boiler condition.” This might include one or more of the following: n Ultrasonic testing (UT) of tubes and piping beyond spot checks; select optimum technology from among A-scan, phased-array, or shearwave as specific tasks dictate. n Dye-penetrant (PT) or magnetic-
COMBINED CYCLE
54
JOURNAL, Third Quarter 2008
Our solutions revolve around a single point: You.
Wood Group Gas Turbine Services: Ì
Covers the world – where you work, we work
Ì
Gives you OEM-equivalent MRO, cost-effectively
Ì
Knows ongoing customer satisfaction is the real meaning of “service”
Ì
Delivers on its promises from beginning to end
We are centered on solving your rotating equipment challenges – and make sure your world keeps on turning.
www.woodgroup.com/gts
Ì
[email protected]
HEAT-RECOVERY STEAM GENERATORS SPECIAL ISSUE: OUTAGE HANDBOOK
particle (MT) testing of suspect areas. n Removal and inspection of desuperheaters. n Borescope examination. n Sampling and analysis of pressure-part materials. Ultrasonic testing. Recall how UT works: An ultrasound transducer connected to a diagnostic machine is passed over the object being inspected. The transducer typically is separated from the test object by a couplant. Reflection off the back wall or imperfection records the wall thickness or depth of the discontunity. A-scan UT typically is selected for thickness testing, especially where FAC or external corrosion has been identified. It’s easy to use, fast, and accurate. Sieben offered an inspection plan that’s easy to customize for your HRSGs. She stressed that inspections should be prioritized based on risk. n Examine LP evaporator circuits (plus IP circuits up to 400-psig saturated) and HP, IP, and LP economizer tubes that operate between 280F and 340F, the temperature range that exacerbates FAC attack. Wall thinning generally is experienced first after tube bends near the upper headers. However, the risk of two-phase FAC is just slightly higher than single-phase FAC, so the lowerheader inlets may be more convenient to check. To access the tubebend area, remove header baffles as necessary. n Check pipe elbows (jumpers) at the apex of the elbow; and straight runs downstream of control valves and orifice plates, especially where temperatures are more than 280F and less than 340F. n Examine headers on HRSGs with “stick-through” welds on the headers directly across from the tube inlet. To review basics of tube-toheader joints, access www.combinedcyclejournal.com/archives. html, click 3Q/2004, click article title on cover. Phased-array UT makes use of multiple fixed-angle transducers in a single probe to quickly and accurately characterize flaws to provide the depth of indications, which show up as echo blips on the instrument’s screen (Fig 55). It has become the instrument of choice in GT inspections for its ability to identify even small flaws in complicated geometries—such as compressor airfoils, blade platforms, disks, etc. Leading technology has its price. 24
Phased-array instruments and probes are more complex and expensive than conventional UT and technicians require more experience and training to use it. However, compared to radiography (RT), the old standard in boiler work, phased-array UT offers several advantages, including: n No work stoppage or welder relocation is required to check work because there are no safety hazards with UT as there are with RT (radiation). n Inspections are conduct-
ed faster. Better suited for the detection of planar, crack-like indications— such as lack of fusion—which are conducive to premature failure. n The exact depth of a defect is revealed, facilitating its removal and rework. Digital RT is making great strides to eliminate or minimize this list. Shear-wave UT is about two to three times less expensive, but does not give depth of indication. Best applications for it are straight pipe, elbows, and circumferential welds. PT and MT methods are used to identify cracks at the surface of the base tube material at or near a weld. They also are used for regular checking of tube/header joints at the economizer water inlet when more than 500 start/ stop cycles have been accumulated; to verify the integrity of superheater and reheater tube/header joints where warped tubes have gotten worse over time; and to pinpoint suspect leaks in vent and drain lines. PT is a low-cost and widely applied inspection method for locating surface-breaking defects in all non-porous materials (metals, plastics, and ceramics). For inspection of ferrous components, however, MT often is preferred because of its subsurface detection capability. Dye-penetrant inspection is used to detect casting and forging defects, cracks, and leaks in new products, as well as cracks on in-service components not visible to the naked eye. It is simple to use: Penetrant is applied to the surface, excess penetrant is removed, and developer is applied to make the crack visible. Little trainn
ing is required to develop proficiency in conducting PTs. The red dye used most often offers a high visual contrast against a white developer background. The developer draws out the penetrant from the flaw over a wider area than the real flaw, enhancing its visibility. Perhaps the biggest concern in conducting a dye-penetrant inspection is surface cleanliness, offered Wambeke. But keep in mind that some cleaning methods are detrimental to test sensitivity. Occasionally, acid etching is required to remove metal smearing and to reopen the defect. Magnetic particle inspection processes make use of an externally applied magnetic field or dc current through the material. They are based on the principle that the magnetic susceptibility of 55 a defect in a ferrous material is markedly poorer—that is, the magnetic resistance is greater— than that of the surrounding material. The most common MT method relies on finely divided iron or magnetic iron oxide particles held in suspension in a suitable liquid (often kerosene). This fluid is referred to as the “carrier.” The particles often are colored and usually coated with fluorescent dyes that are made visible with a handheld ultraviolet (UV) light. The suspension is sprayed or painted over the magnetized specimen to localize areas where the magnetic field has protruded from the surface. The magnetic particles are attracted by the surface field in the area of the defect and hold on to the
COMBINED CYCLE
56
57
JOURNAL, Third Quarter 2008
edges of the defect and define it by a build-up of particles. MT is used to inspect machined parts before they are placed in service and also to inspect parts in service for fatigue cracking (Fig 56). The testing method is easy to apply and takes less time than UT and PT, but it does not work well with complex geometries. Attemperators in cycling service should be inspected annually. Look for cracking or distress on the desuperheater assembly; check nozzles for plugging; confirm liner integrity (see liner crack in Fig 57), and the absence of pitting/wear at the downstream elbow. If data suggest overspray, inspect piping for cracks. Borescope inspections commonly associated with GTs, steam turbines, and generators also find application in some sections of HRSGs. The most likely areas of use include the following: n Economizer, cold end, when pitting or cracking of the tube internal surface is of concern because of cyclic stresses and/or waterquality issues. n Economizer, hot end, if damage or deposits are suspected from water-quality excursions in con junction with excessive steaming.
26
HP evaporator, hot end, if waterchemistry excursions make internal deposits a risk or iron levels are above 1 ppm. n LP evaporator tube rows most susceptible to FAC damage based on a circulation analysis or failure history. n First tube bundle of the superheater downstream of the steam drum, if deposits from carryover are suspected because of a steamseparator failure. Tube samples are taken to characterize both hard scales that form in LP boilers and magnetite and copper deposits in HP boilers. Such deposits reduce heat transfer and efficiency and make the HRSG more susceptible to overheating and tube failures. Tubes are sampled only when available NDE methods are not able to meet expectations. Tube sampling is difficult, expensive, and has obvious inherent risks. Laboratory analysis will suggest corrections to water chemistry and operating procedures and the most efficient method for removing deposits. Base metal analysis will advise on the condition of boiler tubes and whether expectations of service life must be revised downward. ccj n
COMBINED CYCLE
JOURNAL, Third Quarter 2008