Saudi Binladin Group King Abdulaziz International Airport Development Packages 421 and 422 Mechanical, Electrical, Plumbing and Fire Protection for Facilities. Model Basis of Design Report 421-422 -A000-DF-G-RPT-00020-D
March 2012
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
2
Notice This document and its contents have been prepared and are intended solely for Saudi Binladin Group’s information and use in relation to the MEP design of Packages 421 and 422 of the new King Abdulaziz International Airport Development. Atkins assumes no responsibility to any other party in respect of or arising out of or in connection with this document and/or its contents.
Document History
JOB NUMBER: Purpose Revision Description
DOCUMENT REF: 421-422-A000-DF-G-RPT-00020 421-422-A000-DF-G-RPT-00020-D -D Originated
D
Fourth Richard Smith/ Submission Paul Martin
C
Third Richard Smith/ Submission Paul Martin
B
Second Richard Smith/ Submission Paul Martin
A
First Submission
Paul Martin
421-422-A000-DF-G-RPT-00020-D
Checked
Mike Pyle Mike Pyle Mike Pyle Mike Pyle
Reviewed
Authorised
Date
Lee Hall
Stuart Downey
06 Mar 12
David Crowder
Richard Schunter
21 Jan 12
David Crowder
Richard Schunter
20 Nov 2011
Richard Smith
Richard Schunter
19 Sept 2011
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
Overview This report has the following objectives: •
To communicate and amplify the basis of the MEP contract requirements and design criteria for the building facilities defined under packages 421 and 422 of the project;
•
To summarize the scope of works, define defi ne the relevant design standards and codes of practice to be followed and confirm the design criteria;
•
To be the template for all facility Design Criteria 70% submissions
421-422-A000-DF-G-RPT-00020-D
3
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
4
Table of contents Chapter
Page
1. 1.1.
Introduction Scope
2. 2.1. 2.2. 2.3. 2.4.
Codes and Standards Codes and Standards Units Specified Standards Adopted Standards
13 15 15 15 16
3. 3.1. 3.2. 3.3. 3.4.
Design Software Mechanical Design Plumbing Systems Design Fire Protection Systems Design Electrical Systems Design
19 21 21 21 22
4. 4.1.
General Design Parameters General Design Parameters
23 25
5. 5.1. 5.2. 5.3. 5.4. 5.5.
Mechanical Systems General Basis of Design – External Design Temperatures Basis of Design – Heat Rejection Basis of Design – Internal Conditions General Areas Basis of Design – Internal Conditions Laboratories/ Special Equipment Rooms Basis of Design – Internal Conditions Computer and Communication Rooms Basis of Design – All Rooms Not Covered by MEP Basis of Design 6.4 to 6.6 inclusive Basis of Design – Emergency Chilled Water, Room Temperature Cooling Load Computation Chilled Water Basis of Design – Chilled Water Networks In Facilities (1) Fresh Air Ventilation Dedicated Exhaust Air Systems Dedicated Supply and Exhaust Air Systems Refrigerant Ventilation Management Kitchen Ventilation Car-park Ventilation Cold Smoke/Gas Removal Battery Room Ventilation Road Tunnels and Underpasses Ventilation Air Conditioning / Comfort Cooling Basis of Design – Cooling and Ventilation Fire and Motorised Fire & Smoke Dampers Special Systems – Central Vacuum Cleaning Systems - PTB Stairwell Pressurisation Systems Aircraft Systems - Pre-Conditioned Air
27 29 29 29 29
5.6. 5.6.1. 5.7. 5.8. 5.9. 5.10. 5.11. 5.12. 5.13. 5.14. 5.15. 5.16. 5.17. 5.18. 5.19. 5.20. 5.21. 5.22. 5.23. 5.24. 5.25.
421-422-A000-DF-G-RPT-00020-D
8 9
30 30 30 31 31 33 34 35 35 35 35 36 36 37 37 37 38 39 41 41 41 42
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
5.26. 5.27. 5.28. 5.29. 5.30. 6. 6.1. 6.2. 6.3. 6.4. 6.5. 6.6. 6.7. 6.8. 6.9. 6.10. 6.11. 6.12. 6.13. 6.14. 6.15. 6.16. 6.17. 6.18. 6.19. 6.20. 7. 7.1. 7.2. 7.3. 7.4. 7.5. 7.6. 7.7. 7.8. 7.9. 7.10. 7.11. 7.12.
8. 8.1. 8.2. 8.3. 8.4. 8.5. 8.6. 8.7. 8.8.
Seismic Restraint of Mechanical, Plant, Equipment and Systems Acoustic and Vibration – Mechanical Systems Diesel Oil Systems Air-Conditioning Condensate Ventilation of Hazardous Areas
5
43 45 46 47 48
Plumbing and Drainage Systems General Potable Water Supply Grey Water Hot Water Supply Legionnaire’s Disease Prevention Sanitary and Waste Drainage Vacuum Plumbing Systems Rain/Storm Water Drainage Decorative Pools and Fountains Compressed Air System Basis of Design – Sanitaryware and Fitting Load Values Assigned to Fixtures Basis of Design – Water Distribution System Design Criteria Required Capacity at Fixture Supply Pipe Outlets Basis of Design – Gravity Drainage Fixture Units Basis of Design – Sump Pumps Aircraft Systems - Potable and Blue Water Aircraft Systems – Vacuum Waste Seismic Support of Plumbing, Plant, Equipment and Systems Irrigation Liquefied Petroleum Gas Acoustic and Vibration – Plumbing Systems
50 52 52 53 55 56 57 57 58 58 59
Fire Protection General Code and Standards Water Supply Sprinkler Systems Standpipe and Hose Systems Portable Fire Extinguishers Foam Systems. Wet Fire Suppression System Control and Instrumentation Wet Fire Suppression System Pressure Regimes Dry Chemical System. Clean Agent System. Seismic Support of Fire Suppression, Plant, Equipment and Systems
64 66 66 67 67 67 68 68 69 69 70 70
Electrical Systems General Definitions, Abbreviations and Acronyms Codes and Standards - MV Supply Basis of Design – Standards Basis of Design – Substations Basis of Design – Local LV Generators Basis of Design – LV Distribution. Basis of Design – UPS
72 74 74 74 75 75 79 80 81
421-422-A000-DF-G-RPT-00020-D
59 59 60 60 61 61 62 62 62 63
71
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
8.9. 8.10. 8.11. 8.12. 8.13. 8.14. 8.15. 8.16. 8.17. 8.18. 8.19. 8.20. 8.21. 8.22. 8.23. 8.24. 8.25.
Basis of Design – Lighting Installation Basis of Design – Lighting Levels Emergency Lighting Systems Road Tunnel Lighting Control Voltages Control System Power Supply (125 V DC POWER SUPPLY) Lighting Management System (LMS) Raceways and Conduits Disturbance and Interference Protection Ratings Basis of Design – Seismic Restraints Identification and Labelling Mounting Heights Tenanted Areas – Electrical Systems Basis of Design – Aircraft Services Audio Frequency Induction loop System (AFILS) Grounding and Lightning Protection
6
84 85 87 88 89 89 89 91 92 93 94 95 96 97 97 100 100
9. 9.1. 9.2. 9.3.
LEED Compliance General Electrical Mechanical
102 104 104 104
10.
Structural, Electrical, Mechanical (SEM) Opening Requirements Ventilation Ductwork Chilled Water Condensate Refrigerant Floor Drains Drainage and Fire Service Drainage and Fire Service Electrical
105 107 107 108 108 108 109 109 110
10.1. 10.2. 10.3. 10.4. 10.5. 10.6. 10.7. 10.8.
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
Appendices Note:- The original design criteria appendices have been transferred to f acility design reports
421-422-A000-DF-G-RPT-00020-D
7
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
1.
Introduction
421-422-A000-DF-G-RPT-00020-D
8
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
9
Introduction 1.1.
Scope
Atkins have been appointed by Saudi Bin Laden Group (SBG) to carry out the detailed design of the MEP services for Packages 421 and 422 of the King Abdulaziz International Airport (KAIA) project. The facilities covered are identified in the table below in terms of their respective Facility Code references under the contract and the Atkins design delivery centre by geographic location. The purpose of this document is to establish general project wide criteria and basis of design for the facilities Mechanical, Electrical, Plumbing and Fire Systems. The systems covered in this report include; • • • • • • • • • • • • • • • • •
Air conditioning & ventilation systems BMS control, monitoring and automation system Chilled water systems Smoke extract systems Electrical power supply Normal & emergency lighting (internal) Normal & emergency lighting (external) Earthing and lightning protection Hot & cold water supply systems Rain ,surface and foul drainage systems Fire suppression systems Special aircraft systems Central vacuum cleaning system Water Feature hydraulics and water treatment systems Seismically qualified supports and restraints for MEP equipment Support structures for hydronic piping and ductwork Diesel oil systems
Fire alarm system design is within the scope of Special Airport S ystems (SAS) and is described in a separate document. This report is based on the requirements stipulated in the contract documentation and in particular Special Specification (Part-D1), tender (Part-D1), tender addendum and tender questions and answers, all relevant design reports included in the 421 and 422 Exhibit H1 - Technical. This document covers common MEP basis of design criteria for building facilities and in Appendix 1, facility specific design criteria is provided. This Basis of Design (BoD) document forms part of a family of BoD’s covering the design of the MEP systems. Other MEP related BoD’s are listed in the table below.
BoD Title
Document Number
Design Delivery Centre
MEP Systems in Facilities
421-422-A000-DF-G-RPT-00020
Dubai UAE
Kitchens and Laundries
421/422-A000-DF-X-DSG-0003-A 421/422-A000-DF-X-DSG-0003 -A
Humble Arnold
Front of house lighting
421/422-A000-DF-X-DSG-0004-A 421/422-A000-DF-X-DSG-0004 -A
MBLD & LAPD
Vertical & horizontal conveying
421-422-A000-DF-M-RPT00024-A
Barker Mohandas
Building cleaning systems
421/422-A000-DF-X-DSG-0006-A 421/422-A000-DF-X-DSG-0006 -A
Lerch Bates
Baggage handling systems
421/422-A000-DF-X-DSG-0007-A 421/422-A000-DF-X-DSG-0007 -A
BNP
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
10
BoD Title
Document Number
Design Delivery Centre
Façade Lighting
421/422-A000-DF-X-DSG-0008-A 421/422-A000-DF-X-DSG-0008 -A
Light Cibles
Landside Utilities
422-C200-DF-G-RPT-0001-A
Atkins UK
Fuel farm process
422-A000-DF-X-DSG-0002-A
Atkins Sharjah UAE
I2BS
421-DCS-M-GRP-0003
Atkins-Comms, UK
422-A000-DF-X-DSG-0003-A
Atkins Bahrain
Special Airport Systems
421-A000-00-Y-RPT-0001 to 0057 inclusive and 422-A000-00-Y-RPT0001 to 0006 inclusive
Atkins – SAS Team, UK
Fire Alarm and Detection Systems
421-A000-00-Y-RPT-0031
Atkins – UK and Dubai
SCADA
To be issued
Atkins Bahrain and UK
BMS*
421/422-DCS-GRP-G-0001-00
Atkins UAE
APM Tunnel Ventilation
421/422-DCS-GRP-G-0001-00 421/422-DCS-GRP-G-0001-00
Atkins
Site Wide Seismic Restraints Design Report
421-422-000-002-A000-DF-M-RPT0001
Atkins UK
422-C220-DF-C-RPT-001.
Atkins UK
Load centre power and process
2)
1)
Utilities, Grey Water Network Landscape Irrigation
1)
1)
422-C220-DF-L-RPT-001.
Atkins UK
1) Design report that includes includes the basis basis of design. 2) Water treatment, water quality, make up water and blow down disposal are addressed in this document Each of the above systems has a particular BoD detailing their specific requirements. The facilities covered are identified in the table below in terms of their respective Facility Code references under the contract and the Atkins Atk ins design delivery centre by geographic location.
Facility Code Reference
Facility Description
Atkins Design Delivery Centre
C110
Load Centre A
Bahrain
C120
Load Centre B
Bahrain
C130
Load Centre C
Bahrain
C140
Load Centre CN (Airport City)
Bahrain
J100
Mosque
UAE
J150
Fire and Rescue Center
UAE
J250
Tree Nursery
Bahrain
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
Facility Code Reference
11
Atkins Design Delivery Centre
Facility Description
Sharjah, UAE
J400
Fuel Farm
B100
Radio Sites Relocation + Dismantling
UAE
B360
Saudi Airlines MCC (interim)
UAE
B160
Temporary GSE Facility (interim)
UAE
H110 and H120
Data Centres
Bahrain
F100
Passenger Terminal Building
UK
F102
Pedestrian Bridges from Viaduct
UAE
F160
First and Business Class Parking
UAE
F200
Curbside Viaduct
UAE
F170
VIP and CIP Parking
UAE
F300
Transportation Centre
UAE
F400
Multi-Storey Car Park
UAE
F500
Railway Station
UAE
F155
APM Maintenance Depot
UAE
G100
Air Traffic Control Complex
USA
J600
Crisis Management Center
USA
G300
Meteorological Observation Building
USA
G200
West Support Tower
USA
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
421-422-A000-DF-G-RPT-00020-D
12
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
2.
Codes and Standards
421-422-A000-DF-G-RPT-00020-D
13
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
421-422-A000-DF-G-RPT-00020-D
14
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
15
Codes and Standards 2.1.
Codes and Standards
As detailed in contract documents documents J-10-421-PF-0 and J-10-422-PF-0 Exhibit D-Special specifications, specifications, PartD1 , clause 2.5.2 Codes and Standards, the following codes, specifications, regulations, and industry standards, where applicable, shall cover design, material, and construction of the MEP systems.
2.2.
Units
The Metric SI system will be used throughout the project unless otherwise stated.
2.3.
Specified Standards
The following codes and standards are as specified in contract document No. J-10-421-PF-0 Exhibit DSpecial specifications, Part-D1 , clause 2.5.2.+ 2.6.2. The same standards are referenced in contract document No J-10-422-PF-0 Exhibit D-Special specifications, Part-D1 , clause 2.5.2.+ 2.6.2.
Reference General Civil Defence Administration Kingdom of Saudi Arabia Kingdom of Saudi Arabia Saudi Arabian Standards Organization (SASO) Kingdom of Saudi Arabia
Publication Title
Safety Guidelines
The Saudi Building Code Relevant Standards Airport “Basis of Design” and “Standard Specifications”
ASPE
American Society Society of Plumbing Plumbing Engineers
IPC
International Plumbing Code
IMC
International Mechanical Code
NFPA
National Fire Protection Association
NPC
National Plumbing Code Handbook
ASHRAE
American Society of Heating, Refrigeration and Air conditioning Engineers
ANSI
ANSI American National Standard Institute
ASTM
American Society for Testing and Materials
ASME
American Society of Mechanical Engineers
AMCA
Air Movement and Control Association
ARI
Air-conditioning and Refrigeration Institute
AWS
American Welding Society
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
Reference
Publication Title
UL
Underwriters Laboratories
SMACNA
Sheet Metal and Air Conditioning Contractors National Association
FM
Factory Mutual
HI
Hydraulic Institute
AWWA
American Water Works Association
ICAO
International Civil Aviation Organization
ISA
International Society of Automation
EN
European Norm
IEE
Institute of Electrical Engineers
CIE
International Commission on Illumination
CIBSE
Chartered Institute of Building Services Engineers
ASME
The American Society of Mechanical Engineers
IEC
International Electrotechnical Commission
BSI
IEE Requirement for Electrical Installations British Standard institution
TIA 942
Telecommunications Infrastructure Standard for Data Centres
2.4.
16
Adopted Standards
The following codes and standards are an amplified list of the standards defined in 2.3, above and have been adopted by Atkins and are listed below. These codes and standards amplify and support those mentioned in the contract documents. In the event of a contradiction between the standards listed below and those given in the contract the t he contract documents shall take precedence.
Publication Reference
Publication Title
SBC
Saudi Building Code, Section 401, Electrical
SBC
Saudi Building Code, Section 501, Mechanical
SBC
Saudi Building Code, Section 601, Energy Conservation
SBC
Saudi Building Code, Section 701, Sanitary
SBC
Saudi Building Code, Section 801, Fire Protection
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
Publication Reference
Publication Title
ASHRAE
Handbook H - 2008 - HVAC Systems and Equipment
ASHRAE
Handbook F - 2009 - Fundamentals
ASHRAE
Handbook R - 2010 - Refrigeration
ASHRAE
Handbook A - 2011 - Applications
ASHRAE
SF-98-14-3 -- Seismic Codes, HVAC Pipe Systems, and Practical Solutions
LEED-NC v 2.2 with errata 1, 2 & 3
Leadership in Energy and Environmental Design
IFC
International Fire Code
IBC
International Building Code
IFGC
International Fuel Gas Code Code
IPC
International Plumbing Code
NEMA
National Electrical Manufacturer’s Association
IEEE
Institute of Electrical and Electronics Engineers
IESNA
Illuminating Engineering Society of North America
TIA/EIA
Telecommunication Industry Association / Electronic Industries Alliance
ICAA
International Civil Airports Association,
NFPA 10
Standard for Portable Fire Extinguishers
NFPA 11
Standard for Low, Medium and high-expansion foam
NFPA 13
Standard for the Installation of Sprinkler Systems
NFPA 14
Standard for the installation of Standpipe, Private Hydrant and Hose Systems
NFPA 15
Standard for Water Spray Fixed Systems for Fire Protection
NFPA 16
Standard for the Installation of Foam-Water Sprinkler and Foam –Water Spray Systems
NFPA 20
Standard for the Installation of Stationary Pumps for Fire Protection
NFPA 24
Standard for the Installation of Private Fire Service Mains and Their Appurtenances
NFPA 30
Flammable and Combustible Liquids Code
NFPA 54
Storage and Handling of Liquefied Petroleum Gas
421-422-A000-DF-G-RPT-00020-D
17
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
Publication Reference
NFPA 70
18
Publication Title
National Electrical Code (MV Design only)
NFPA 72
National Fire Alarm and Signalling Code
NFPA 90A
Standard for the Installation of Air-Conditioning and Ventilating
NFPA 91
Standard for Exhaust Systems for Air Conveying of Vapors, Gases, Mists, and Non-combustible Particulate Solids
NFPA 92
Standard for Smoke Management Systems
NFPA 92A
Standard for Smoke-Control Systems Utilizing Barriers and Pressure Differences
NFPA 92B
Standard for Smoke Management Systems in Malls, Atria, and Large Spaces
NFPA 96M
Standard for Ventilation Control and Fire Protection of Commercial Cooking Operations
NFPA 101A
Guide on Alternative Approaches to Life Safety
NFPA 101B
Code for Means of Egress for Buildings and Structures
NFPA 110
Standard for Emergency and Standby Power Systems
NFPA 130
Standard for Fixed Guideway Transit Systems
NFPA 170
Standard for Fire Safety and Emergency Symbols
NFPA 497
Recommended Practice for the Classification of F lammable Liquids, Gases, or Vapors and of Hazardous ( Classified ) Locations for Electrical Installations in Chemical Process Areas
NFPA 502
Standard for Road Tunnels, Bridges, and Other Limited Access Highways
NFPA 2001
Standard on Clean Agent Fire Extinguishing Systems
As noted in SC-7 of Contract Document Exhibit B t he latest version of the standards and codes (at the start of design (08 Jan 2011)) are applicable.
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
3.
Design Software
421-422-A000-DF-G-RPT-00020-D
19
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
421-422-A000-DF-G-RPT-00020-D
20
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
Design Software 3.1.
Mechanical Design
The following software will be used for the design of m echanical services;
Appendix A Calculation Type
Appendix B Applicable Software/Ca Software/Calculation lculation Methodology
Heat gain calculations and energy modelling to ASHRAE 90.1
Carrier E2-11 HAP v4.5
Duct system pressure loss
Excel spreadsheet (procedure as per ASHRAE)
Pipework system pressure loss
Excel spreadsheet (procedure as per ASHRAE)
Attenuator calculations
Trane TAP and Excel spreadsheet (procedure as per ASHRAE)
CFD internal environmental modelling
Star CCM+ (Adapco)
3.2.
Plumbing Systems Design
The following software shall be used for the design of plumbing systems;
Appendix C Calculation Type
Appendix D Applicable Software/Calcu Software/Calculation lation Methodology
Pipework system pressure loss
Excel spreadsheet (procedure as per IPC)
Drainage systems
Excel spreadsheet (procedure as per IPC)
3.3.
Fire Protection Systems Design
The following software shall be used for the design of fire protection systems;
Appendix E Calculation Type
Appendix F Applicable Software/Ca Software/Calculation lculation Methodology
Sprinkler system design
HASS
421-422-A000-DF-G-RPT-00020-D
21
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
3.4.
22
Electrical Systems Design
The following software shall be used for the design of electrical systems;
Calculation Type
Applicable Software/Calcula Software/Calculation tion Methodology
Lighting calculations – back of house areas
Dialux / Relux
Lighting calculations – Front of house areas
Dialux / Relux/AGi32
Lighting calculations - External
Dialux
High mast lighting ; BS5489
‘Visual’
Tunnel Lighting
LITESTAR 10
Cable size calculations
AMTECH (to BS 7671, IEE 17 with Amendment 1) code requirements)
Earthing calculations
Excel spreadsheet (procedure as per IEE + BS7430)
Generator Sizing
Caterpillar software + 30%
Short Circuit calculations LV
AMTECH (to BS 7671, IEE 17 with Amendment 1) code requirements)
Volt Drop
AMTECH (to BS 7671, IEE 17 with Amendment 1) code requirements)
UPS sizing calculation
Excel Spreadsheet (Connected load + spare 30% (load schedule))
ECBS Sizing calculation
Excel Spreadsheet (Connected load + spare 30% (load schedule))
th
th
th
PFC Sizing Calculation / Magnetizing KVAr of the fixed step of the capacitor Electrical load calculations and equipment sizing (Transformer sizing)
421-422-A000-DF-G-RPT-00020-D
Spreadsheet (kW {tan (cos-1 (pf1)) – tan (cos-1 (pf2))}) Excel spreadsheet. Excel spreadsheet
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
4.
General Design Parameters
421-422-A000-DF-G-RPT-00020-D
23
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
421-422-A000-DF-G-RPT-00020-D
24
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
25
General Design Parameters 4.1.
General Design Parameters
The following weather data shall be used for the design of the building services;
Parameter
Value
Latitude
21º 30’ N
Longitude
39º 12’ E
Altitude
2 to 6m above mean sea level
GACA KAIA Basis for Design 2.2
Mean annual rainfall
63.2mm
Maximum 100 year 24 hour rainfall
109.5mm
BLP Report S23-REP-04, Issue 2 dated 30 Nov 2010, Appendix 1, issued under DAR letter 1) DAR/SBG421/0140 BLP Report S23-REP-04, Issue 2 dated 30 Nov 2010, Issued under DAR letter DAR/SBG421/0140
Max design rainfall
100 year IDF curve
DAR/SOL (see 6.8)
49ºC
KAIA Basis for Design 2.3
44.4 ºC
Exhibit D Special Specification D2
29.4 ºC
Exhibit D Special Specification D2
11ºC
GACA KAIA Basis for Design 2.3
Absolute maximum ambient (external) temperature Design maximum dry bulb temperature Design maximum wet bulb temperature Absolute minimum ambient temperature Relative Humidity Relative Humidity average monthly maximum Relative Humidity average monthly minimum Relative Humidity average monthly mean
100% max 3% min 100% except February which is 90%
Data Source
GACA KAIA Basis for Design 2.3 GACA KAIA Basis for Design Table 1
4% to 10%
GACA KAIA Basis for Design Table 1
50% to 67%
GACA KAIA Basis for Design Table 1
Maximum wind speed
93kph
GACA KAIA Basis for Design 2.3
Max wind pressure at ground level on flat surface
48kg/m²
Exhibit D Special Specification D2
Daily average wind speed
5.9m/s
ASHRAE Fundamentals
Prevailing wind direction
North
GACA KAIA Basis for Design 2.3
Seismic Zone
2A
Exhibit D Special Specification D2
Weather Phenomena Occurrence
Table 2
GACA KAIA Basis for Design
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
Parameter
Value
26
Data Source
Building Weight for cooling Various, but mainly lightweight ATKINS load calculations Electrical tariff for LEED/ASHRAE 90.1 Flat, local rates ATKINS calculations 1) Summated from appendix appendix 1. This report is of very poor reprographic quality, however, however, value is in line with other sources and is only for information as this parameter is not used by design calculations.
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
5.
Mechanical Systems
421-422-A000-DF-G-RPT-00020-D
27
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
421-422-A000-DF-G-RPT-00020-D
28
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
5.1.
29
General
Refer to contract documents No. J-10-421-PF-0 Exhibit D-Special Specifications, Part-D1, clause 2.5. Mechanical Requirements and J-10-422-PF-0 Exhibit D-Special Specifications, Part-D1, clause 2.5. Mechanical Requirements. The following contains extracts from the above referenced document and additional design data sourced by Atkins. This section should be read in conjunction with specific building criteria in Appendix A and general parameters in section 5.1. In the event of a discrepancy, this section supersedes 5.1 and Appendix A supersedes this section.
5.2.
Basis of Design – External Design Temperatures
Parameter
Value
Data Source
Dry bulb design temperature
44.4ºC (1)
Exhibit D
Wet bulb design temperature
29.4ºC (1)
Exhibit D
Winter dry bulb
11.1 ºC
Exhibit D
Weather year used by the cooling and heating load and energy model
As Carrier HAP weather data
ATKINS
(1) These values are in excess of the non coincident 0.4% peaks quoted in the appendix of ASHRAE F14 and will lead to increased plant sizes.
5.3.
Basis of Design – Heat Rejection
Parameter
Value
Data Source
Wet bulb design temperature
29.8ºC
ASHRAE Fundamentals
Dry bulb design temperature (all condensing units to operate, albeit at reduced capacity at a maximum temp of 55 ºC)
44.4ºC
Exhibit D
5.4.
Basis of Design – Internal Conditions General Areas
Parameter
Value
Data Source
Dry bulb design temperature
21ºC ±1ºC
Exhibit D (1)
Relative Humidity
55% RH (peak)
Exhibit D
Internal noise level
Refer to Appendix A room data sheets
ASHRAE Applications A47 Table 42
(1) Exhibit D omits to provide the tolerance, but this is required.
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
5.5.
30
Basis of Design – Internal Conditions Laboratories/ Special Equipment Rooms
Parameter
Value
Data Source
Dry bulb design temperature
21ºC ± 1ºC
Exhibit D
Relative Humidity
50% ± 5% RH
Exhibit D
Internal noise level
Refer to Appendix A room data sheets
ASHRAE Applications A47 Table 42
5.6.
Basis of Design – Internal Conditions Computer and Communication Rooms
Parameter
Value
Data Source
Dry bulb design temperature
No less than 20ºC
Exhibit D
Relative Humidity
No less than 50% RH
Exhibit D
Maximum dry bulb design temperature
25 ºC
Exhibit H
Maximum Relative Humidity
60%
Exhibit H
Internal noise level
Refer to Appendix A room data sheets
ASHRAE Applications A47 Table 42
Data Hall design condition
20°C to 25°C 40% to 55% RH Max dew point poi nt 21.0°C 21.0°C Max rate of change: 5°C per hour
TIA-942
5.6.1.
Basis of Design – All Rooms Not Covered by MEP Basis of Design 6.4 to 6.6 inclusive
Parameter
Value
Data Source
Dry bulb design temperature
As noted in design condition tables and scheduled in Appendix A
Exhibit H
Relative Humidity
As noted in design condition tables and scheduled in Appendix A
Exhibit H
Internal noise level
Refer to Appendix A room data sheets
ASHRAE Applications A47 Table 42
APM tunnel maximum design dry bulb temperature
33°C +2K
Exhibit D (1)
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
31
(1) Exhibit D states 35°C and does not set a tolerance. The tolerance has been added so that designers can assess and identify the air-movement regimes in this non temperature critical space. This tunnel space will be provided with mechanical cooling to achieve the design temperature
5.7.
Basis of Design – Emergency Chilled Water, Room Temperature
In the event of a general power failure, the Load Centre generators will operate and a reduced capacity of chilled water will be generated. Buildings or parts of buildings that are not eligible to receive emergency chilled water will have a close down sequence where all motorised control valves stroke to the closed position. Buildings eligible for emergency chilled water will have air temperature set points adjusted to 27°C.(Source: ATKINS). The regime for achieving this w ill vary according to the type t ype of plant to be controlled and the criticality of continuing to provide cooling in such a circumstance. A strict adherence to a lower air supply rate together with the rescheduling of the space temperature may be applicable. A detailed assessment of how to use the available load load to each facility will need to be made. A loading schedule and control regime will be put in place.
Parameter
Value
Data Source
Emergency room temperature and basis of emergency load computation
27°C
Exhibit D, 2.5.3.5
Building facilities that will receive emergency chilled water
Tables 4, 5 and 6
Exhibit H CP08-C100-SD-M-RPT0100-B, page 12
5.8.
Cooling Load Computation
Introduction
This section sets out the methodology for the presentation of cooling load calculations. Individual building cooling loads are fundamental to correctly sizing plant equipment and site utility provisions. By adopting a common approach, the quality of design information can be better assured so as to: Ensure buildings are provided with sufficient cooling and ventilation to meet the internal environmental requirements as set out in the basis of design. Provide value in the selection of size and duty of mechanical mechanical plant and site wide cooling infrastructure, with secondary benefit to supporting electrical and water services.
•
•
The submission of information is to be provided in six stages. Each building team will submit information for every stage with increasing level of detail for progressive stages. This approach has been adopted so that the calculations carried out for a particular stage can be used to validate the loads derived in future stages and allow other members of the project teams to progress with their work packages. The stages are summarised as follows: Stage 1. Overview 1. Overview loads, to be derived from the designer's initial assessment of the building, based on its intended usage and information provided to date from the previous documentation (Exhibits D&H). Only total building loads are required at this stage. Stage 2. Sample 2. Sample calculations, to be derived by calculation of typical building areas. The calculations shall be sufficiently detailed to assess the major contributing factors to the loads and then be multiplied to derive an overall building load. Stage 3. Full 3. Full building loads, to be derived from a complete assessment of the building, as calculated using approved software and submitted according to the procedure defined in this document. These final loads shall be used for the basis of plant selection and submitted in full to the client. Stages 4 & 5. As 5. As Stage 4, but capturing all facilities that have lagged behind schedule (e.g. Rail Station) and other final information such as confirmed process loads. 421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
32
Stage 6.Annual 6.Annual load assessment, to be derived using Hourly Analysis software (in accordance with ASHRAE 90.1) and submitted according to the procedure defined within this document. The purpose shall be to illustrate typical annual energy consumption and provide evidence in support of the building LEED assessment credit EAC1. The format and procedure for submitting load information is defined below:. Stage 1. The stage 1 building assessment will consist of an initial summary of each building's cooling requirement as determined by each building design team's initial assessment of cooling loads. These will mainly be a repeat of the ADPI calculated loads given in exhibit H technical reports and verified by the design teams. Where additional information is available from other early assessments then this will also be included. Stage 2. The stage 2 building assessment shall provide a summary breakdown of each building's cooling load. The basis of calculation shall be to carry out detailed calculations on discrete building areas which can be scaled up to give a total for the building as a whole. Where this is not possible (due to the size and complexity of the building and level of architectural information available) a further breakdown of the stage 1 building assessment will be permitted. The intention of the stage 2 calculations will be to inform the utility infrastructure team of the likely loads from each building so that they can progress with the design of the piped site wide Chilled Water distribution network. At this and subsequent stages all loads will be broken down into the following categories: Environmental Casual Outdoor Air Fan/Pump Process Stages 3, 4 & 5 The stage 3 building assessment will contain full detailed cooling load / chilled water calculations for each building. The calculations shall be carried out using the approved software and provide a full and detailed assessment of the building loads. The overall load will be used as the basis of selection for main chiller plant within the load centres hence the figures provided must be for maximum simultaneous cooling load. The definition of which is the peak load from all buildings served by a load centre and is obtained by the summation of all the building load profiles. It is not the summation of each building’s peak load as these will occur during different times of the day and would lead to an over assessment. In terms of occupant and process loads, these shall be diversified according to the maximum allowable simultaneous occupancy / process requirement of the building (not the total of maximum allowable occupancies of each space). The environmental conditions shall also be considered in terms of their net peak effect on the building (e.g. the peak gains arising from the combined effect of both solar gain and external air temperature). No further margins or safety factors shall be included unless stated to fulfil a specific unknown quantity such as air leakage from ductwork which cannot be accurately determined until installation / commissioning. The approach to thermal modelling and load calculations can vary between engineers. The following text will act as guidelines for continuity b etween engineering teams: 1.
All calculations calculations should should be carried out using steady steady state state analysis, analysis, backed backed up by thermal models for verification where appropriate and where helpful in determining environmental load diversity.
2.
Treatment of infiltration - an allowance shall be made where background ventilation rates are insufficient to over pressurise the building. For example where an over pressurisation equivalent t o 0.7 ACH (air changes per hour) is required, but not met purely by occupant fresh air requirements, then additional air flow rates shall be included in the calculation to meet the 0.7 requirement. Equally where over pressurisation is not overtly mentioned in the contract documents, then
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
33
infiltration rates shall be included (depending on facade leakage specification) and expected in the region of 0.2 to 0.3 ACH, gross of any contribution from fresh air supply. 3.
Building weights weights should should be be input input as lightweight as the majority majority of of buildings will have have very very little exposed concrete/ thermal mass.
4.
Air system system types types should should be selected selected appropriate to the ventilation strategy. In the majority of cases cases this shall be structured so that the designers may distinguish between supply air ventilation load and building load.
5.
Assumptions shall be listed for internal gains where they are in addition to the contract contract documents, documents, with reference to the appropriate ASHRAE document.
6.
The temperature profiles of unconditioned spaces (corridors, toilets, basements basements etc), which are a function of outside temperatures, shall be d etermined, on a case by case basis and documented.
7.
Solar gains gains shall take cognisance of natural natural shading shading from building building overhangs overhangs and recesses as well as the properties of the building fabric.
8.
Reporting shall be in a standardised standardised format as determined by the central project team.
Stage 6. Full building energy models will need to be provided to satisfy LEED credits and all buildings within the LEED boundary will need to be modelled according to ASHRAE 90.1 App G. For further information refer to the section in this document which covers LEED assessments. In line with the ASHRAE 90.1 protocol the computed energy consumption will not reflect the actual energy consumption, because under the protocol some loads such as process are ignored.
5.9.
Chilled Water
Load Centres shall provide chilled water for cooling purposes to all the airport 421 and 422 buildings, with the exception of remote buildings like the radio sites, lighting vaults, etc.. All secondary and tertiary pumps will have variable speed drives. As part of the chilled water utility design, differential pressure valve sets will be provided at chilled water entry points to maintain a constant differential pressure. Control to all cooling coils, etc. will be by 2-way pressure independent control valves. The chilled water system will be variable flow to reduce pumping energy and to t o ensure maximum chilled water return temperatures are achieved. The total chilled water requirement shall be based on maximum cooling load calculation for all the served buildings with 20% spare capacity. (source: Exhibit D) Loads shall be calculated utilising Carrier E2-11 HAP v4.5 software. (source: ATKINS) BMS monitored chilled water energy meters will be provided at the point of entry to core and shell areas. (source: Exhibit D, 2.5.3.5). Critical buildings are provided with local chiller(s) that back up the site-wide chilled water system to achieve the required level of resilience. Important buildings will receive emergency chilled water from the site-wide chilled water network. The proportion of chilled water load met by the emergency chilled water is as defined in 5.7, above and as detailed in the load center load schedules. When there is a power outage at the load centers the MV generators will provide power to the cooling plant so that it can generate the required amount of chilled water. Given that the generators take up to 10 minutes to take up the load and other loads will take priority over the chillers the chilled water will not be available immediately. Since rooms with high heat gains (e.g. comms rooms) will suffer fairly rapid temperature spikes, the chilled water pumps will operate in the load center within 60 seconds of the power outage to give continuity of supply and prevent high temperature trips on critically im portant equipment.
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
5.10.
34
Basis of Design – Chilled Water Networks In Facilities (1)
Parameter
Value
Data Source
Temperature of water delivered to each facility
5.0ºC (2)
Exhibit D
Temperature of water returned from each facility
14.0ºC
Exhibit D
Spare capacity
20% (at inlet headers)
Atkins
Maximum temperature rise and pressure drop through pressure break heat exchanger on both hot and cold fluids.
1K 50 kPa
ATKINS (based on industry normal practice)
Method to allow the 20% spare capacity in buildings
Spare valved branches in plant rooms or building entry points.
ATKINS
Pipework specification
Steel, Sch 40
Exhibit D (interpreted by ATKINS on pressure)
Assumed fill/standing temperature
38ºC
ATKINS (derived by ATKINS from ASHRAE F14 and field experience)
Imposed static head
Refer to the pressure study in the Chilled Water Utility design report
ATKINS Utility Designer
Minimum static pressure at high point
1.0 bar (g)
ATKINS
Average pipe pressure drop
200 Pa/m (index)
ATKINS (derived from ASHRAE F09)
Max pipe pressure drop
400 Pa/m
ASHRAE F22
Max water velocity
1.2m/s ≤50mm, 3m/s >50mm
ASHRAE F22
Two port valve minimum authority
0.30
ASHRAE S46
Two port valve maximum design authority
0.50
ATKINS (derived from ASHRAE S46)
Pipe Sizing Standard
ASHRAE F22
ATKINS/ Exhibit D
Differential pressure at building point of entry
350kPa (3) (PTB) 250kPa (other buildings)
Exhibit H CP04-C255-SD-M-RPT0100-C page 15
Chilled water pump margin
5% (flow), 10% (pressure)
ATKINS
Acoustic and vibration requirements
Refer to Atkins’ acoustics reports and ASHRAE noise targets referenced in this documents
ATKINS/ASHRAE
Plate Heat Exchanger (PHEX) Locations
ATCT, data center redundant supply
ATKINS/Exhibit D
PHEX Provision
2 x 100% (facilities) 1 x 100% (generator cooling tower)
ATKINS
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
Parameter
Value
PHEX Temperature Difference
1K (ATCT)
2K(Data Centers) (1) Refer to Utilities BoD for external external utility information.
35
Data Source
(4)
ATKINS
(2) Will be 4.5° 4.5°C C in load centres (3) This value may be be reduced to 250kPa 250kPa as part of of an initiative to reduce pipework pipework pressure rating. (4) Due to 7°C chilled water supply temperature due to high proportion of of sensible loads
5.11.
Fresh Air Ventilation
The ventilation rates shall be based on the recommendations of ASHRAE Standard 62.1-2007 and LEED NC v 2.2 EQ PreReq 1, whichever is the greater. In rooms that are in contact with the building envelope the supply rate shall exceed the extract rate by 5% to achieve a positive pressure within the building as required by Exhibit D. All outdoor air handling units with a duty above 1.0m3/s will be equipped with purged, enthalpy rotary wheels with a ‘total heat’ recovery efficiency target of 80%. This target is defined on the basis of an exhaust airflow rate of 90% of the supply air rate. A 25% fouling degradation in heat recovery efficiency shall be assumed for the purpose of outdoor cooling/dehumidification coil sizing. Load and energy calculation shall assume an average 10% energy fouling degradation reduction. [source: ATKINS based on industry best practice for Middle Eastern environments] In some parts of some facilities there are many natural and mechanically forced leakage paths. These include: pressurisation air leaking through the envelope, air escaping down air bridges & BHS apatures, , remote local extract systems, remote toilet extract systems, etc.. This combined with in some cases the reuse of secondary air results in a situation where there is little or no exhaust at the location of the outdoor air air handling unit. In these cases, enthalpy wheel will not be applied if the volumetric flow balance defined in ASHRAE 90.1 clause 6.5.6 is not met..
5.12.
Dedicated Exhaust Air Systems
Dedicated mechanical exhaust air ventilation systems with make up from central systems will be provided to garbage rooms, battery charging rooms, toilets lavatories and kitchens and any other areas noted as requiring such in ASHRAE 62.1-2007. Explosion proof fans will be provided to rooms such as garbage, UPS and battery charging. Anti-back flow dampers shall be provided on makeup air to potentially contaminated rooms such as those used for garbage.(source garbage.(source:: Exhibit D). Exhaust air rates will be as defined in the above standard, however, for process areas such as kitchens and laundries extract rates will be based on the equipment requirements and ventilation rates will be provided by the specialist kitchen consultant.
5.13.
Dedicated Supply and Exhaust Air Systems
The same requirements as those described for dedicated exhaust air systems but shall also be provided wit h a dedicated supply system that does not supply air to any other area. Supply and exhaust systems are required for storage rooms, technical rooms and chemical rooms. (source: Exhibit D) Refer to individual building ‘Criteria for Design’ for actual requirements. Where general unspecified store rooms are identified and located within areas containing rooms such as offices these may be supplied with air from the same system that serves the offices. The extract from the store rooms will not be recirculated.
5.14.
Refrigerant Ventilation Management
In enclosed rooms that contain refrigeration plant and equipment ventilation shall be provided to purge escaped refrigerant gas. (source: Exhibit D) 421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
36
Refrigerant gas leak detection will be provided and the ventilation will be designed in accordance with ASHRAE Standard 15-2007
5.15.
Kitchen Ventilation
Kitchens will be served by dedicated fresh air AHUs and extract fans. Sufficient air will also be supplied to the kitchen to provide adequate ventilation for occupants and to offset heat gains. This air will be supplied by an air handling plant with filtration, and cooling functions. No heat recovery will be provided on kitchen AHUs due to the risk of fouling. Canopies will be a design that incorporates an energy saving feature where untreated fresh air is injected into the canopy to reduce the exhaust requirement by 40% (i.e. "Capture Jet" by Halton) The untreated fresh air for injection will be supplied by a separate air handling unit that will comprise a fan and filter. In the case of small kitchens (less than 100m2) or remote canopies, consideration will be given to deploying a solution where capture jet air is provided by a local fan (part of canopy) that takes air from the kitchen. Air will be extracted from the canopy by dedicated extract fans via fire proof ductwork. The fans will be zoned so that specific canopies or sections of canopies can be activated during the night period when the kitchen is used for room service alone or just stock pots are simmering. No fire dampers will be provided within kitchen extract ductwork. Ductwork shall be accessible for manual cleaning throughout its entire length. Access doors for this purpose shall be provided at every 1.5m centres. Kitchens will be designed so that they operate at a negative pressure. Dishwasher extracts will initially be in insulated and of welded stainless steel ductwork which will be water tight and graded back to the dishwasher to avoid problems with condensation. Where there is a risk of odours recycling to sensitive areas, consideration will be given to the need to reduce fumes from the kitchen exhaust with fume scrubber which will comprise a water wash / electrostatic filter type)or canopy integrated UV scrubbers. Kitchen exhausts will be at high level where possible and jetted vertically upwards. Where this is not achievable the need to consider fume scrubbing may take on greater significance. Make up air) will be supplied by dedicated AHUs . In larger kitchens (>75m2) a chefs control panel will be provided in the chef’s office to control ventilation.
Parameter
Value
Data Source
Kitchen canopy extract rates
To be advised by the kitchen consultant
ATKINS
Minimum velocity for canopy exhaust
8 m/s
ASHRAE A31
Make up air supply temperat temperature ure
25°C 25° C
ATKINS
5.16.
Car-park Ventilation
In accordance with NFPA 88A Standards for Parking Structures 2007, A mechanical ventilation system is not required for open parking structures on this project. NFPA 88A identifies an open parking structure as:
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report •
•
•
37
Each parking level shall have wall openings open to the atmosphere, atmosphere, for an area of not less than 0.4 m2 for each linear meter of its exterior perimeter Such openings shall shall be distributed over over 40 percent of the building perimeter or uniformly over over two opposing sides Interior wall lines and column lines shall be at least 20 percent percent open, with openings distributed to provide ventilation.
5.17.
Cold Smoke/Gas Removal
Priority 1 Critical buildings will be provided with dedicated smoke extract systems in room that are provided with clean agent fire suppression systems. The system will comprise an extract only system designed to clear smoke in 15 minutes. A motorised smoke and fire damper will be provided in the wall of t he room and shall be normally closed. A dedicated cold extract system will be provided and it is permissible to connect several rooms. The design will only allow for one room to be evacuated at any one time and the fan and damper will be controlled from the fire/smoke damper panel or the BMS/i2BS head end. Other buildings will use the primary ventilation system to exhaust cold smoke and here the extract grille will be located at the opposite end of the room. However, it must be ensured that air extracted by this method is not recirculated to other rooms when used in the cold smoke exhaust mode.
5.18.
Battery Room Ventilation
Battery rooms shall be mechanically ventilated to prevent the accumulation of Hydrogen gas reaching dangerous levels. The airflow required shall be based upon the emission of gas during charging or overcharging and limit the concentration of Hydrogen to 2% (ASHRAE Application Handbook). A factor of safety of 1.5 will be applied when selecting fans and sizing ductwork. Extracted air shall be removed from the room at high level via a dedicated system of fan and ductwork exhausting directly to outside. Make up air shall be via a ducted system direct from outside. Fans shall be explosion proof with operation initiated by a hydrogen detector (set point 1%) located at ceiling level in the battery charging room. No unventilated voids above ceilings in battery rooms will be provided. Fan operation shall be interlocked with the battery charger to prevent charging if the fan operation is not verified by an airflow detector located in the extract ductwork.
5.19.
Road Tunnels and Underpasses Ventilation
The ventilation for the tunnels and underpass shall be designed in accordance with NFPA 502 Standard for Road Tunnels, Bridges, and Other Limited Access Highways and will be based on the critical velocity method.
Parameter
Value
Data Source
CO under all free flowing and congested conditions CO under all standstill conditions
70 ppm, free flowing to congested traffic, 100ppm, standstill condition
PIARC 2004
100ppm
PIARC 2004
NO2
1 ppm
PIARC 2004
Visibility
Free flowing traffic 0.005/m Congested traffic 0.007/m
PIARC 2004
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
Parameter
Value
38
Data Source
Standstill traffic 0.009/m Traffic Design Speed
70 km/h
Exhibit D
Percentage of Heavy Truck
20%
Table 2.02.2 of Highway Design Manual Volume 1
Oil Tanker in Tunnel
No
ATKINS
Design Fire Size
70 MW
NFPA 502 2011
Tunnel Air Velocity
8 m/s
Exhibit D
Emergency Ventilation type
Longitudinal
Exhibit D
5.20.
Air Conditioning / Comfort Cooling
All spaces will be cooled to the requirements for the particular room or space. Generally, central air handling units will be utilised to provide cooling and ventilation and will incorporate energy recovery wheels where these units are not supplied with conditioned outdoor air by an outdoor air AHU. Constant air volume (CAV) systems will be provided to public spaces and variable air volume (VAV) for grouped offices. VAV Air handling units shall be furnished with variable speed control. The use of Fan coil units will be kept to a minimum subject to room/space application. (source: Exhibit D, 2.5.3.5). All air handling units and fans shall be supplied with power via a variable speed drive (VSD). Many plant although operating at fixed speeds will operate at different fixed speeds through the operating period. This will be part of the control philosophy for each system. The VSD also allows the system to be commissioned more quickly and more accurately to the installed conditions. It provides flexibility for future changes and promotes efficient operation of the systems. Cooling and ventilation air to core and shell areas will be provided with capped ductwork with metering systems connected to the BMS. (source: Exhibit D, 2.5.3.5) In the data centres the design basis using CRAC, PAU and CDU units shall be deployed as described in Exhibit H, document CP10-19-H100-SD-RPT-0100-B. (source: ATKINS). Water pipework and valve trains shall be kept out of the rooms wherever possible. Secondary Sub-station rooms are mechanically cooled when MV and /or LV switchgear is located in the same room. This is to be achieved achieved by utilising re-circulating re-circulating air handling units units or large double skinned fan coil units which re-circulate cooled air to the room via a system of ductwork. Each individual sub-station room is served by 2 No. re-circulating air handling units both rated at 100% of the cooling load and both shall operate at once, at 50% capacity each. The units are controlled by temperature within the space. Both units are monitored by the BMS system and in the event of a fault in one of the units the BMS shall automatically switch over to the other unit to provide the full cooling load. In case of a power failure the air conditioning shall remain operational in these rooms to maintain a maximum temperature of 27°C 27°C db. The re-circulating r e-circulating air handling units cooling coils utilise the on-site chilled water system. Where transformers are located in dedicated rooms, mechanical cooling can be avoided and dissipated heat dealt with by ventilation alone using natural ‘cross flow’ or high level mechanical extract with low level air intake. This does not apply to data centers given the very high availability requirements. Comms rooms are air conditioned, by utilising ‘Computer Room Air Conditioning’ (CRAC) type units within the room to monitor and regulate the temperature and humidity. Each Comms room will have a minimum of 2 No. CRAC units both rated at 100% of the cooling load and shall both operate at once at 50% capacity each. They shall be down-flow down-flow air units, wherever possible. The units are controlled by integral temperature and humidity sensors. Both units are monitored by the BMS system and in the event of a fault in one of the units the BMS shall automatically switch over to the other unit 421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
39
to provide the full cooling load. In case of a power failure the air conditioning shall remain operational in these rooms to maintain a maximum temperature of 27°C db. The CRAC units cooling coils utilise the on-site chilled water system. Cooling to each facility is provided by chilled water pipe connections from the airport wide piped chilled water distribution system. At each connection there is located a differential pressure valve to ensure a constant pressure is achieved. This is designed by the utility team under package 422. Each facility designer is then responsible for the control of chilled water to each terminal unit within the facility. The terminal units might be air handling cooling coils, fan coil units or plate heat exchangers. The branch pipework will vary in length and complexity of distribution. Each terminal unit will be controlled by a 2-port motorised control valve, CV. Differential pressure valves, DPVs, are used at sub-branches within the facility to provide constant pressure control to groups of terminals within a reasonably close proximity of each other. A number of air handlers in a single plantroom may constitute a branch for a DPV. A string of fan coils, perhaps 10 number maximum, or a number within 20m of each other may constitute a branch for a DPV. This allows the chilled water system to be divided into smaller sub-circuits for the purposes of sizing the CVs associated with the terminals on that circuit and allows each sub-circuit to be commissioned independently of other sub-circuits. Each CV is to then be sized to give an authority of N=0.5 based on the resistance of the sub-circuit under the pressure control of the sub-circuit DPV. The design incorporates separate DVPs and CVs to suit the configuration described above. Procurement of valves may determine that DVPs and CVs are combined in a Pressure Independent Valve, PIV, associated with each terminal. Perhaps a combination of DPVs and CVs with some PIV would be of benefit. These valve selection scenarios would be based on the range of valves offered by manufacturers. A number of scenarios is possible to meet the strategy explained.
5.21.
Basis of Design – Cooling and Ventilation
Parameter
Value
Data Source
Minimum fresh air rate
ASHRAE Standard 62.1-2007
Exhibit D
Pressure with respect to adjacent areas
ASHRAE A7.6 Table 3
ASHRAE Applications handbook
AHU/FCU cooling output margin
10%
DAR Reply to Submittal 421-DDT-G00174 dated 11 Sept11
VAV box output margin
10%
ATKINS
VAV system diversity
Calculate on a system by system basis
ASHRAE A37.5
Diffuser terminal velocity (in occupied zone)
0.15 to 0.25 m/s
ASHRAE F20 and Standard 55
Max ductwork pressure drop
1Pa/m
ATKINS (derived from ASHRAE F21 Duct Friction Charts)
Max ductwork velocity – trunk mainIn Shaft (Supply)
NC45 NC35
17.8m/s 12.7m/s
ASHRAE Applications 2011 A48Table 8
Max ductwork velocity – trunk mainAbove Ceiling (Supply)
NC45 NC35
12.7m/s 8.9m/s
ASHRAE Applications 2011 A48Table 8
Max ductwork velocity – branch In Shaft (Supply)
NC45 NC35
14.2m/s 10.2m/s
ASHRAE Applications 2011 A48Table 8
Max ductwork velocity – branch
NC45
10.2m/s
Above Ceiling (Supply)
NC35
7.1m/s
ASHRAE Applications 2011 A48Table 8
Max ductwork velocity – trunk mainIn Shaft (Return)
NC45 NC35
17.8m/s 12.7m/s
ASHRAE Applications 2011 A48Table 8
Max ductwork velocity – trunk mainAbove Ceiling (Return)
NC45 NC35
12.7m/s 8.9m/s
ASHRAE Applications 2011 A48Table 8
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
Parameter
Value
Max ductwork velocity – branch
NC45
14.2m/s
In Shaft (Return)
NC35
8.9m/s
Max ductwork velocity – branch
NC45
10.2m/s
Above Ceiling (Return)
NC35
7.1m/s
Max ductwork velocity – trunk mainIn Shaft (Exhaust)
NC45
17.8m/s
NC35
12.7m/s
Max ductwork velocity – trunk mainAbove Ceiling (Exhaust)
NC45
12.7m/s
NC35
8.9m/s
Max ductwork velocity – branch
NC45
14.2m/s
In Shaft (Exhaust)
NC35
10.2m/s
Max ductwork velocity – branch
NC45
10.2m/s
Above Ceiling (Exhaust)
NC35
7.1m/s
Maximum ductwork velocity – flexible duct (Supply)
NC45 NC35
3.2 m/s 2.5 m/s
Maximum ductwork velocity – flexible duct (Extract)
NC45
3.8 m/s
NC35
3.0 m/s
Maximum ductwork velocity –
NC45
3.8 m/s
Return Plenums
NC35
3.0 m/s
Maximum ductwork velocity – Exhaust Plenums
NC45 NC35
3.8 m/s 3.0 m/s
AHU fan volume / pressure margin
Data Source
5 % (volume) 10% (pressure) ASHRAE S28 Table 2 or
AHU filtration requirements
MERV 13 as LEED NC v2.2 EQ5, whichever is greater
Kitchen hood exhaust
NFPA 96
Duct sizes and design Maximum air velocity through cooling coils
40
ASHRAE F21 SMACNA 2.5m/s- No eliminator 3.0m/s – with eliminator
ASHRAE Applications 2011 A48Table 8 ASHRAE Applications 2011 A48Table 8 ASHRAE Applications 2011 A48Table 8 ASHRAE Applications A47.8 ASHRAE Applications A47.8 ASHRAE Applications A47.8 ASHRAE applications 2011 Table 9 ASHRAE applications 2011 Table 9 ASHRAE applications 2011 Table 9 ASHRAE applications 2011 Table 9 Exhibit H ASHRAE Applications handbook LEED Action Plan Exhibit D Exhibit D, 2.5.3.5 ASHRAE F21 and Exhibit H
Not to exceed code values for ‘main fan’ that include:
Maximum specific fan power (SFP)
<9.44 m3/s: 1.9 W per l/s (CAV) 2.7 W per l/s (VAV) >=9.44m3/s:
ASHRAE 90.1 (2010)
1.7 W per l/s (CAV) 2.4 W per l/s (VAV) Sand Trap Intake Louvre face velocity and pressure drop
1.5m/s (max) (η ≥ 80%) (1) 0.75m/s (min) (η ≥ 90%) (1) 75 Pa (max)
ATKINS (based on TROX data)
Maximum exhaust louvre face velocity and pressure drop.
2.5m/s
ASHRAE F21
Maximum anti-backflow damper
<200l/s per m2 at 500Pa
ATKINS (based on TROX low
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
Parameter
Value
leakage rate
41
Data Source leakage data)
Transformer room natural ventilation
Two louvres each with 4m2 (free area) per MVA of located to provide cross flow ventilation
Atkins (from DEWA data)
Airflow rate determined from a 5.5K temperature difference. Transformer room forced ventilation
Intake louvre to be located at low level in the external wall.
Atkins (from DEWA data)
Extract air intake to be located at high level in the room
(1) Based on a particle size of 200 to 700 microns
5.22.
Fire and Motorised Fire & Smoke Dampers
Fire dampers will be provided in all fire compartment walls and barriers and shall be of the same fire rating, however, fire dampers with a rating below 2 hours will not be used. Motorised Fire and Smoke dampers shall be provided in locations as defined in NFPA 90A. Motorised Fire and Smoke damper groups will be split into zones and hard wired to a local MFSD control panel that shall annunciate damper status, annunciate an alarm if a damper is not correctly positioned and allow manual over-ride and resetting of MFSDs. Additionally, the local panel shall be interfaced with t he fire alarm system, the BMS and/or the I2BS.
5.23.
Special Systems – Central Vacuum Cleaning Systems - PTB
A Central Vacuum Cleaning System includes a powerful vacuum unit fixed in a suitable location (such as a mechanical plant room). It is connected by a run of pipework to a number of hose connection points strategically placed throughout the facility to be cleaned. To clean an area, the operator plugs a hose into a convenient connection point. When the end of the flexible hose is inserted into the socket the vacuum unit automatically switches on. Using an appropriate collection tool the operator cleans the accessible area, before moving the hose to another connection point. Entrained material is conveyed through the pipe system, where it separates from the air stream in the filter unit and is collected for future disposal The vacuum unit is sited indoors, preferably in a plant room, where it is ventilated. It is mounted on a wall at a height which allows the dust container to be removed easily. Exhibit “D” Special Specification states: The vacuum system shall be designed based on providing a vacuum outlet at an interval of 15m by means of inlet valves distributed throughout the building.
The sockets can be installed either in the walls or the fl oor.
5.24.
Stairwell Pressurisation Systems
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
42
Stairwell pressurisation systems will be provided where indicated in the facility fire report. These systems will be designed in accordance with ASHRAEA52 and ASHRAE Principle of Smoke Management (Klot and Mike: 2002) with single high level injection for 3 levels and below and multiple injection for 4 levels and above. These systems will comprise run and standby fans each rated at full duty discharging untreated outdoor air into the stairwell. Multiple injection systems will deploy a vertical builder’swork shaft within the stairwell with one outlet at least every two levels . The fans will be variable speed and designed to overcome stairwell leakage so that pressure differential across closed doors do not exceed the maximum and minimum values stipulated in NFPA92A. Additionally, fans shall be selected so that protection is provided to three open doors per stairwell.
Parameter
Value/Description
Stairwell Design Pressure (doors closed)
12.5 Pa (min)
Protected open doors
Ground and 2 others
BS 5588 (not directly addressed in US codes) based on phased evacuation
Air velocity through an open door
0.75m/s
BS 5588 (not directly addressed in US codes)
5.25.
40 Pa (max)
Data Source NFPA101 – 7.2.3.9
Aircraft Systems - Pre-Conditioned Air
Pre-conditioned air will be supplied to each aircraft stand to provide a very cold pre-conditioned air (PCA) supply for aircraft cooling. PCA AHUs will be located in the bridge nodes of the PTB and these will deliver PCA to the aircraft via under apron double skin insulated ducts to pop up pits. Each PCA AHU will be provided with chilled water and ethylene glycol (GL) that will be sourced from networks in the PTB. GL chilling plants will be provided in the PTB with heat rejection to chilled water. Basis of design information is included in Exhibit D,2.5.3.6, section F and amplified below:.
Parameter
Value/Description
Data Source
Coolant
Chilled Water (primary) Ethylene Glycol (secondary)
Exhibit D
Ethylene glycol temperatures
-7°C supply -2°C return
Exhibit D
Ethylene glycol freezing point
-19.5°C
ASHRAE F31
Ethylene glycol concentration
30%w/w
ASHRAE F31
Ethylene glycol dynamic viscosity (for pipe sizing)
5.4mPa-s (13.01 ft/lb-s)
ASHRAE F31
Ethylene glycol heat capacity (for pipe sizing)
3.57 kJ/kgK (0.853 btu/lb° bt u/lb°F) F)
ASHRAE F31
Ethylene glycol density (for pipe sizing)
1,055kg/m 3 (65.85lb/ft )
ASHRAE F31
Ethylene glycol chiller condenser water temperatures (uses injection mixed chilled water)
18.3°C entering 18.3°C ent ering 23.9°C 23.9° C leaving l eaving
Exhibit D
421-422-A000-DF-G-RPT-00020-D
3
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
43
Parameter
Value/Description
Data Source
PCA delivery temperature
-4°C
Exhibit D
PCA aircraft cooling capability
Refer 2.5.3.6 E
Exhibit D
PCA system load diversity
80%
Exhibit D
Availability
95% at gate
Exhibit D
External PCA Ductwork Construction
Class 125, stainless steel with welded flanges, close cell insulation and plastic outer casing with waterproof closures. (see contract documents for full details)
Exhibit D
External PCA Ductwork design life
25 years
Exhibit D
External PCA Ductwork Test Pressure
1.5x working pressure
Exhibit D
External ductwork fall (for condensation drainage)
0.5 to 1.0%
Exhibit D
PCA ductwork diameters
To suit aircraft
Exhibit D
Pop up pit details
Refer 2.5.3.6 F
Exhibit D
Noise
<85dBA at 5m from any equipment
Exhibit D
Safety
IATA compliant
Exhibit D
5.26.
Seismic Restraint of Mechanical, Plant, Equipment and Systems
Seismic restraints for mechanical and electrical services The design of the seismic restraints will be based upon UBC 1997, with a site class of zone 2A, and the FEMA and SMACNA publications. •
•
•
•
• • • •
Building Seismic Safety Council, NEHRP NEHRP Recommended Recommended Provisions for Seismic Regulations for New Buildings and Other Structures, Part 1: Provisions (FEMA 368) Building Seismic Safety Council, NEHRP NEHRP Recommended Recommended Provisions for Seismic Regulations for New Buildings and Other Structures, Part 2: Commentary (FEMA 369) Building Seismic Safety Council, NEHRP NEHRP Recommended Recommended Provisions Design Examples (FEMA 451) Applied Technology Council, Reducing Risks of of Non Structural Earthquake Earthquake Damage – A Practical Guide (FEMA E-74) FEMA – Installing Seismic Seismic Restraints for Mechanical Mechanical Equipment (FEMA 412) 412) FEMA – Installing Seismic Restraints for Electrical Equipment (FEMA 413) FEMA – Installing Seismic Seismic Restraints for Duct Duct and and Pipe (FEMA 414) SMACNA Seismic Restraint Manual, Guideline for Mechanical Mechanical Systems (ANSI/SMACNA 0010012000)
Section 1632 of UBC 1997 determines determines the lateral force on equipment equipment supported by structures. Based on this lateral force the SMACNA manual defines seismic restraints that provide lateral and longitudinal support 421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
44
for ductwork, ductwork, pipework and and conduits. conduits. The SMACNA seismic restraints restraints are comparable comparable to those specified in FEMA E-74 which additionally includes arrangements for wall mounted pipes, pipe risers and cable trays. Seismic restraints will be addressed by the design teams in the following three categories: A – Repetitive and Linear: Linear: Repetitive support and restraint details largely associated with single or multiple service runs in both horizontal and vertical attitude. B – Unique: Unique: Support and restraint for large/heavy objects that are not covered by categories A and C C- Plant, Equipment and Apparatus Apparatus - Design of plant, equipment and apparatus by the maker so that it can withstand an earthquake Specific Design Methodologies A – Repetitive and Linear Project structural engineer determine seismic hazard level for each building zone. Seismic designer prepare a series of standard details based on FEMA 414 and an Exhibit D2 compliant ‘pre-approved’ restraint system such as that b y SBG preferred supplier Cooper B-Line. Project MEP engineers identify restraint locations and types from guidance provided by the Seismic Designer. Contractor assemble support and restraint system from ‘pre-approved’ and certified components components in accordance with maker’s instructions.
• •
•
•
B – Unique Project MEP engineers identify items requiring restraint with loads, etc.. Services requiring restraint to be clearly indicated on the 100% drawings with seismic hazard level that prevails in that part of the building. The Contractor to retain a certified seismic engineer to design restraints in accordance with FEMA approved codes and the process defined in the various sections of Exhibit D2. Obtain approval of support from an approved agency (signed and sealed)
• •
•
•
C- Plant, Equipment and Apparatus Seismic designer review review Exhibit D2 specifications and identify any shortfalls shortfalls in seismic requirements Seismic designer prepare additional seismic notes for technical schedules. Seismic designer prepare standard details to c ompliment FEMA 412 and 413 recommendations and specified Exhibit D2 seismic requirements
• • •
General Notes The seismic restraints are additional to those required for supporting the services under self weight. The sizes of the support restraints are based upon the seismic hazard level ( SHL ) which relates to the magnitude of the seismic acceleration. acceleration. The SHL is dependent dependent on the height of the service within the building. The SMACNA procedure for the design of the seismic restraint is as follows: 1. 2. 3. 4. 5. 6.
Establish location of the service within the building. Identify the SHL based on the height of the service within the building building Select an appropriate support support arrangement arrangement for the layout of the services. Determine the support member member sizes based based on the SHL and the weight of of the services. Determine spacing of the lateral and longitudinal supports based based on the route of the service and the specified spacing defined in the SMACNA guidance. Determine the size of the structural structural connection. connection.
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
45
The standard restraints included in the SMACNA guidance are: • • • • • • • •
Side bracing for rectangular ducts Side bracing for rectangular ducts with rod hangers Centre bracing for rectangular ducts Floor supported ducts Bracing for round ducts Bracing for pipes and conduit Bracing pipes on trapeze Floor supported pipes
Member sizes for non standard supports can be d esigned on the basis of the SHL. The design of the seismic restraints needs to consider: •
• • •
Where services are subject subject to significant thermal thermal expansion expansion or or contraction contraction then the restraint restraint location must consider both the seismic and thermal af fects. Providing adequate flexibility in services where they span movement joints All in line equipment equipment must be braced independently of the service. Inclusion of a factor of safety of 4 on the limit load for for anchorages. anchorages.
The services need to meet the following requirements: • •
Duct construction to conform to SMACNA Pipework construction conforms to ANSI/ASME B31.9
Spring mounts supporting rotating equipment will include seismic snubbers. Seismic restraints will be provided for all free standing equipment such as electrical panels and switchgear, water tanks etc. General arrangement drawings will be provided based upon the FEMA requirements. Final calculations, sizing and detail drawings will be provided by a specialist supplier.
5.27.
Acoustic and Vibration – Mechanical Systems
Refer to Exhibit D1 clause 2.1.2.2 and 2.1.3.2 for general requirements. Refer to the Atkins acoustic reports for further details.
Parameter
Value/Description
Data Source
Grilles, diffusers and registers
Selected so that catalogue NC rating does not exceed that of the room NC target
ATKINS (based on ASHRAE F09)
AHU attenuator selection
Use Trane TAP
based on ASHRAE F09
AHU attenuator siting
Site attenuators in locations with a uniform (1 dimensional) air-flow. Place at point of exit from plant rooms to avoid noise break in. If this is not possible clad ductwork with a sound barrier mat between attenuator and the point the ductwork passes through the plantroom wall.
ASHRAEA47
VAV box
Use Trane TAP
based on ASHRAE F09
VAV attenuator siting
Site attenuator as close to the VAV box outlet as possible and clad interconnecting ductwork with acoustic
ASHRAE A47
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
Parameter
Value/Description
46
Data Source
barrier mat.
Attenuator max resistance
50 Pa (AHUs) 25 Pa (VAV boxes) Deploy bullnoses and evasies, if required.
ATKINS
FCU attenuation
Select FCU with low noise output and provide inlet plenum with acoustic duct lining. Provide sound acoustic duct lining to all ductwork and if possible include one bend. Use Trane TAP to demonstrate noise target is met with FCU on medium speed.
ASHRAE A47
Diffuser, register and grille plenum boxes
Line with acoustic duct liner if room NR target is below NR40
ATKINS
Acoustic duct liner specification
Division 233113
Exhibit D2
Crosstalk attenuation
Provide where interconnecting ductwork joins private rooms together.
ASHRAE A47
Contaminated exhaust attenuation.
Fabricate attenuator from same material as the ductwork and line acoustic media with an impervious film such as melinex.
ATKINS
Duct mounted fans
Mount on anti-vibration mounts and where possible include attenuators in the sprung load. Provide ductwork flexible connections
ASHRAE A47
AHU Fans
Mount on anti-vibration mounts and provide a flexible duct connection within the AHU casing
ATKINS
Extent of resiliently mounted ductwork
To be assessed by Atkins-Acoustics on a case by case basis
ATKINS
Base mounted - Mount on inertia bases and provide flexible connections to pipework
Pumps
Pipeline mounted – Mount on antivibration mounts and provide flexible connections to pipework.
Extent of resiliently mounted pipework
5.28.
To be assessed by Atkins-Acoustics on a case by case basis
D2-Division 230548
ATKINS
Diesel Oil Systems
Diesel fuel oil is required for the electrical generations and incinerators comprising under or above ground ground bulk fuel oil storage tanks located near the serviced areas. The systems will include Daily fuel tank, fuel oil pumps, piping, control and accessories.
Parameter
Value/Description
Data Source
Fuel Type
Fuel Oil to ASTM D 975
D2 Division 231113
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
47
Parameter
Value/Description
Data Source
Fuel Grade
Grade No 2-D, general purpose, high volatility
D2 Division 231113
Fuel Densit Density y
0.816-0.0876 0.816-0. 0876 g/cc at 15° 15°C C
ASTM D287
Fuel Viscosity
1.3-1.5 centisokes (mm/s) at 40°C
ASTM D613
Bulk Tank Storage
7 days at peak conditions for critical buildings 2 days at peak conditions for non critical buildings
DAR/SBG 421-422/0199
Day Tank Storage
8 hours at peak conditions
D2 Division 263213
Indoor Storage Tank Standard
UL 142 single wall
D2 Division 231113
Outdoor Storage Tank Standard
UL 142 & STI F921 double Wall
D2 Division 231113
Consumption
0.26 litres /hr/kW (Approximate value to be confirmed by manufacturer)
Manufacturer’s information (Cummings Power Generation)
Transfer Pump
Duplex Fuel Oil Transfer Pump Set
D2 Division 231113
Max pump suction
Not to exceed 34 kPa
ASHRAE Fundamentals 2009 22.19
Pipe sizing
Table 28 ‘Recommended Nominal Size for Fuel Oil Suction Lines from Tank to Pump’
ASHRAE Fundamentals 2009 22.19.
Pipework specification Outdoor
Rigid Double containment piping ASTM D 2996 or ASTM D 2997
D2 Division 231113
Pipework specification Indoor
Black Steel ASTM A 53/A 53M Schedule 40 Type E or S Grade B
D2 Division 231113
5.29.
Air-Conditioning Condensate
Air conditioning condensate will be designed using materials and physical layouts (falls, cleaning access, support, etc.) in the same manner and to the same codes as the waste pipework in Section 6 of this Basis of Design. Condensate pipework will be continuously insulated to prevent formation of condensate and nuisance dripping on and from the outside of the condensate pipes. Condensate pipe will be sized in accordance with the following table.
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report ���� ��� ����
200
��� / 1/�"
��� �� �� ����
10�� 10�� / �/�" �/�"
��� �� �� ����
1��� 1��� / 1/2" 1/2"
��� �� �� ����
�00
20�� / �/�" /�"
���� ���� ���
2��� / 1"
���� 1���
�2�� �2�� / 1 1/�" /�"
�00
48
�������� ���� ���� �00 100 1000 1200 1�00
1�00
1�00
2000
2200
2�00
1� �� 100 100��
�0�� / 1 1/2" /2"
�0 �� 1����
�0�� / 2"
1�0 �� ��0��
���� / 2 1/2"
�00 �� �00��
�0�� / �"
��0 �� 1,000� �
100�� / �"
��0 �� 1,�00��
1,��0 �� 2,�00��
12��� / �" ����� ���������� ���� ���� ���� � ���� �� �� �� ���� 1% 1% ���� �������� �� ��� ���� �� ��.
Based on data provided by McQuay and validated by Atkins
5.30.
Ventilation of Hazardous Areas
5.30.1 Car Parks Refer to 5.16. 5.30.2 Battery Charging Rooms Refer to 5.18 5.30.3 Road Tunnels and Underpasses Underpasses Refer to 5.19 5.30.4 Chemical Areas All areas where hazardous chemicals are stored or used will be provided with a dedicated supply and extract 2 system that ensure a continuous background ventilation rate of 1 0 air-changes per hour or 8 l/s per m , whichever is the greater. Make up air shall be treated so that the room conditions remain within in t he limits defined in 5.6.1. Ventilation design will be developed in accordance with ASHRAE Applications A29 Additionally, local extract systems with hoods, etc will be provided to scavenge locally released gaseous emissions. Local extract systems will be developed in accordance with ASHRAE Application A30 Chemically polluted exhausts from buildings will be designed in accordance with ASHRAE Applications A44 5.30.5 Laboratories Laboratory ventilation and local extract systems (fume cupboards) will be designed in accordance with ASHRAE Applications A14 Chemically polluted exhausts from buildings will be designed in accordance with ASHRAE Applications A44 421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
49
All exhaust ductwork and associated fans, etc shall be fabricated from welded plastic material.
5.30.6 Liquefied Petroleum Gas (LPG) Areas Areas Storage areas will all be externally located and storage tanks will be freely ventilated and separated from each other and adjacent structures in accordance with Suadi Building Code (SBC) 801, table 36.4.3 Vapourisers, etc will be located externally and freely ventilated. External distribution equipment that requires protection from weather will be accommodated a ccommodated in lightweight ‘shelter’ structures with in accordance with NFPA 58 with i nlet and outlet vents on opposite walls at both high and low level (within 150mm of finished floor level). The vents shall be designed for general ventilation and to relieve explosion and shall comply with the requirements set out in NFPA 58. If mechanical ventilation is used in areas that accommodate LPG distribution equipment then explosion venting will be provided as NFPA 58 and the mechanical ventilation rate shall achieve a rate of at least 5 l/s 2 per m as NFPA 58. Fans and a nd associated equipment shall be hazardous hazardous classified in accordance with NFPA 70 and NFPA 497 Pipework distribution within building will be designed to comply with NFPA 58 and be located in ventilated spaces wherever possible. Where pipework is located in ceiling voids or risers or basements, it, along with it’s accessories such as valves will be double contained using a proprietary containment system. Gas detection will be provided to the void between the carrier pipe and the containment to provide early warning of a gas escape. Where LPG serves appliances such as kitchen ranges, etc, local gas detection will be provided at low level behind the appliances along with automatic isolation valves at the point of entry into the room, emergency knock offs and hard wired interface to the fire alarm system. SBC801 and NFPA 58 – LPG Gas Code will be used as the reference codes for the design of services associated with LPG areas. 5.30.7 Diesel Oil Stores Under SBC801 the grade 2-D diesel / fuel oil i s not classified as hazardous because it’s flashpoint is 52�C and exceeds 35 �C value for which special measures are required. Even with the elevated temperatures in this region the storage of this fuel is not regarded as a special hazard. There are three instances on this project where diesel oil is stored: 1. 2. 3.
In day tank of generator generator rooms – here there is ample natural and mechanical mechanical ventilation. In external external fuel tank – no ventilation ventilation measures measures required. required. In underground underground tank chambers – a background background ventilation rate equating equating to 2 air-changes air-changes per hour will be provided in these areas.
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
6.
Plumbing and Drainage Systems
421-422-A000-DF-G-RPT-00020-D
50
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
421-422-A000-DF-G-RPT-00020-D
51
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
6.1.
52
General
Ref: Contract document No. J-10-421-PF-0 Exhibit D-Special specifications, Part-D1, clause 2.5.3.3 and J10-422-PF-0 Exhibit D-Special specifications, specifications, Part-D1, clause 2.5.3.3 2.5.3.3 Plumbing systems.
6.2.
Potable Water Supply
All buildings shall be supplied with potable water for its domestic water supply requirement. The water supply to the buildings shall be obtained directly from the external airport main network. Service connections will be provided with water meter, pressure reducing valve assembly and back flow prevention as required by IPC. High buildings such as the air traffic control tower wil l be provided with pressure boosting.
Parameter or Strategy
Data or Description
Source
Static pressure at inlet to each facility (at outlet of PRV)
5.0 bar(g) – minimum for PTB 4.0 bar(g) – minimum for other buildings Boosting to be provided to high circuits, if required.
ATKINS Utility team using network modelling to determine minimum pressures for several scenarios.
Design dynamic hydraulic pressure drop in internal PWS main
0.75 bar
ATKINS (using methodology in IPC Appendix E)
Maximum water velocity
2 m/s
Exhibit D
Demand assessment (sanitary fixtures)
Fixture unit method from IPC handbook (see 6.11, below)
Exhibit D
14mm/d (peak) external Water feature make up for evaporation and backwash losses
5mm/d (peak) internal 3,000mm/m2/y external
ATKINS (based on Data published by Estidama/UPC)
1,000mm/m2/y internal As required by equipment with diversity applied. Undiversified demands provided by the Kitchen and Laundry Consultant
Exhibit D
Peak temperature of potable water
42°C
ATKINS (based on ME experience and review of storage and aeration process)
Temperature of chilled potable water in the hotel and to aircraft.
20°C
ATKINS (based on ASHRAE and HSE legionella design codes)
Internal potable water pipework type and rating
CPVC
Exhibit D (Division 23)
Ablution Spray (shataf) water source
Potable water
ATKINS
Ablution Spray (shataf) location
LHS of WC when facing it and so that nozzle cannot be immersed below the water line.
ATKINS (derived from IPC and SBC)
Ablution Spray (shataf) backflow protection
Spring loaded, lever valve and located so that nozzle cannot be immersed.
ATKINS (derived from IPC and SBC)
Kitchen and Laundry demand assessment
The minimum pressures close to potable water pumping stations may be higher. If a faci lity is sited close to a station AND a higher pressure is desirable the facility plumbing designer shall contact the utility designers and agree a revised pressure on a case by case basis. This pressure shall be listed in the facility design report as an exception to this document. 421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
6.3.
53
Grey Water
The grey water (i.e. treated sewage effluent (TSE)) supply to the buildings shall be obtained directly from the National Water Company (NWC) Sewage Treatment plant that is located on site. Grey water shall be supplied to water closet and urinal flushing systems and irrigation systems. In the event of failure in the grey water system, potable water make up has been provided with appropriate back flow device. (source: Exhibit D). Service connection will be provided with water meter and pressure reducing valve assembly. As required by Exhibit D a cross connection between potable and grey water supplies is to be provided at building entry points. This is so that in the event of there being insufficient grey water the potable water will top up. The grey water service cross connection with the potable water will be designed in accordance with the DAR letter DAR/SBG 421-422/0243 dated 18 May 2011, Exhibit D and Saudi Building Code SBC 701 complying with the most onerous requirement for a direct connection requiring protection against over-pressure backflow. The basis of design for this cross connection is defined below. The Treated Sewage Effluent has to be chlorinated and have UV disinfection to achieve a compliance standard of <100 cfu/100ml cfu/100ml prior to its transfer to the airport. As part of our project scope, scope, additional chlorination is provided to the grey water to maintain the residual within the network (this prevents re-growth of bacteria). The potable water will also be chlorinated and so will also maintain residual chlorine. The back flow preventers are to be installed with isolation valves both upstream and downstream (V2 and V3 on schematic). These will be normally open. open. To increase security and to prevent prevent unnecessary potable potable flows to grey (which would otherwise happen whenever the potable pressure is greater that the grey water pressure), on the potable water upstream side an automatically initiated motorised butterfly valve will also installed (V1 on schematic). The back flow preventer will be installed above above ground with a type AA air gap (Plus 200mm) between the drain vent and the ground level. The exception to this will be for t he PTB where the connection will need to either be in the service tunnel or in the P TB basement. This is due to the configuration of the tunnel in this location.
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
54
In the event of a grey water system failure the site SCADA/BMS will detect low pressure in the grey water network and sound an alarm. alarm. An authorised person will then decide whether whether or not to instigate potable water back up. If so, that person will push a control control button that will open open all the motorised butterfly valves (SV). In the back ground the SCADA/BMS will be monitoring the relative pressure between the grey water main and the potable water main and if there is not a sufficient differential pressure (preset and adjustable) this will prevent SV opening and an alarm will be generated. Once SV opens the potable water will flow under pressure into the grey water lateral. If the SCADA/BMS detects the grey grey water main depressurising depressurising the butterfly valve SV will close. Also if at any time the authorised person wants to close all the valves, they will be able to do this by pushing a button. When grey water pressure returns to normal SV will close and the operation will r eturn to normal. The area of the back flow preventer preventer between the two non return valves valves will drain, providing an air gap. In the heat of the day the air gap chamber will dry and heat up which will reduce any risk of the survival of any bugs that could have migrated to that area.
Parameter or Strategy
Data or Description
Source
Static pressure at inlet to each facility (at outlet of PRV)
4.0 bar(g) – minimum, all facilities Boosting of grey water is not required for tall buildings with low demand at high level (i.e. ATCT and WST), however, grey water will be distributed to low level outlets within reach of the pressure constraints.
ATKINS Utility team using network modelling to determine minimum pressures for several scenarios.
Design dynamic hydraulic pressure drop in the internal grey water main
0.75 bar
ATKINS (using methodology in IPC Appendix E)
Maximum water velocity
2 m/s
Exhibit D
Demand assessment (sanitary fixtures)
Fixture unit method from IPC handbook (see 7.11, below)
Exhibit D
Peak temperature of grey water
45°C
ATKINS (based on ME experience and review of STP process)
Internal grey water pipework type and rating
CPVC
Exhibit D (Division 23)
WC and urinal water source
Grey water (treated sewage effluent)
WC flushing method
Flush tanks (6 litre) (1) – (hotel rooms, quiet areas and single WC cubicles) Flushometer Valves (1) - (other areas)
ATKINS
Urinal flushing method
Flushometer Valves (1)
D2-Division 224000
Internal irrigation water source
Grey water (treated sewage effluent)
Exhibit D
10mm/m2/day over 2x 20 min
ATKINS –Landscape Refer to Landscape Irrigation Design Report 422-C220-DF-L-RPT-001 for further details
Internal grey water irrigation
(1) As Division 224000 224000
421-422-A000-DF-G-RPT-00020-D
Exhibit D (WCs) ATKINS (Urinals)
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
55
The minimum pressures close to grey water pumping stations may be higher. If a building is sited close to a station AND a higher pressure is desirable the building plumbing designer shall contact the utility designers and agree a revised pressure on a case by case basis. This pressure shall be listed in the facility design report as an exception to this document.
6.4.
Hot Water Supply
Either centralised or decentralised storage type electrical water heaters shall be utilized to supply hot water requirements in all the buildings. The system will be designed in accordance with ASHRAE A49 and the International Plumbing Code. Centralised units shall be plant room located. All kitchens shall have dedicated hot water systems.(source: Exhibit D, 2.5.3.3) Centralised systems will be used where there is a high density of outlets that require a combined storage in excess of 300 litres when calculated with a 2 hour recovery rate. Additionally, a shunt pump will be provided to circulate the hot water within the cylinder or calorifier to ensure that sections of the stored water do not continuously remain at a temperature in t he range of 20-45°C, 20-45°C, where legionella colonies could t hrive. Excessive dead legs shall be avoided and either trace heating or hot water circulation shall be adopted, as required. Outlets in areas that are accessible to the general public and all bidets shall be provided with terminal blending to avoid scalding. Hot water storage units will be insulated, direct fed and suitably rated for the maximum possible pressure, provided with pressure/temperature relief and vacuum relief all as IPC Section 504 with pressure temperature relief discharging through an air-gap. Hot water vessels shall be insulated as IPC Section 505. Hot water pipework shall be insulated in accordance with the SBC Section 601 – Energy Conservation. Ranges of faucets on counter lavatories in public restrooms are defined as being served by thermostatic blending valves in the contract documents. However, with operational issues associated with the elevated cold water temperatures and temperature lockout, this concept has been changed to the provision of hot and cold water to each faucet with a discreet mixing lever for public use.
Parameter or Strategy
Data or Description
Source
Make up water source
Potable cold water system
Exhibit D
Hot water storage tempera temperature ture
60°C
ASHRAE ASHRA E A49
Trace heating set-poi set-point nt
55°C
ATKINS ATKIN S
Hot water return temperat temperature ure
57°C
ATKINS ATKIN S
Minimum cold feed temperature
15°C
A TKINS ATKIN S
Hot water storage unit sizing method and recovery period
2 hours
ASHRAE A49
Method of heating water
Staged electrical resistance heaters
Exhibit D
Terminal blended water temperature
43°C
IPC AND SBC 701
Maximum water velocity in building
2 m/s
Exhibit D
Demand assessment (sanitary fixtures)
Fixture unit method from IPC handbook (see 6.11, below)
Exhibit D
Kitchen and Laundry demand assessment
As required by equipment with diversity applied. Undiversified demands provided by the Kitchen and Laundry Consultant
Exhibit D
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
56
Parameter or Strategy
Data or Description
Source
Internal hot water pipework type and rating
CPVC
Exhibit D (Division 23)
Bidet water source
Potable and HWS
ATKINS
Bidet backflow protection
Air gap
ATKINS (derived from IPC)
Lavatory faucet water source
Potable and HWS
Exhibit D
Lavatory and sink faucet type
Division 224000
Exhibit D2
Countertop Lavatories Faucets in public restrooms
Automatic proximity controlled, electrical with battery back-up to provide nozzle hot and cold supply.
D2-Division 224000
6.5.
Legionnaire’s Disease Prevention
Designers shall make every measure when designing systems to ensure that the risk of harbouring and spreading legionella and pneumophila are eliminated. Guidance in ASHRAE handbooks shall be adhered to, as follows: Fundamentals: F10.6 Applications: A 48.7, A48.6, A48.7, A49.9 Systems and Engineering: S31.12/13, S40.9, Additionally and given this subject is not covered in SBC701 or the IPC, the requirements of UK Health and Safety Executive (HSE) Approved Code L8 shall apply for items not covered by the ASHRAE references listed above. Designers should note that in the Middle East it is not possible to avoid water temperatures in the range of 20 - 45°C 45°C as recommended by international codes. This is i s because of the t he very high ambient temperatures and the ground heating effect on water in buried pipelines. This risk is offset by a more stringent water treatment regime by utility companies, often involving shock dosing with chlorine and other chemicals. Given that in line with normal practice facilities will not be provided with chemical treatment the design has to be executed so that: •
Long dead legs legs where infrequently drawn water can accumulate and age are avoided; avoided;
•
Oversized pipes with very low velocities (<0.6m/s) are avoided;
•
Testing points at at remote sections of the networks are are provided provided with clear instructional signage; signage;
•
Hot water water is stored and and distributed distributed at temperatures in excess excess of 55°C;
•
Systems are designed designed and installed installed so so that that they can be completely completely drained;
•
Full instructions on on how to maintain system cleanliness are included in the Operating and Maintenance instructions
Inherent in this basis of design and the Exhibit D2 specifications are philosophies and parameters that comply with good practice with respect to legionnaires disease and they are not repeated in this section.
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
6.6.
57
Sanitary and Waste Drainage
All sanitary and waste water from building plumbing fixtures shall be collected through drainage pipe work (modified single stack, to include separate vent) and discharged by gravity to manholes connected to the site sewer network. The systems will be designed in accordance with IPC Chapters 7, 8, 9 and 10. Drainage from sumps and bottom of lift shafts below external ground levels or lowest fitting to prevent surcharge shall be provided with sump pumps. Drainage from kitchens shall be connected to grease interceptors that shall have capacities as IPC Section 1003. Drainage from car parks and oily areas shall be connected to oil interceptors. Drainage from laundries shall be connected to lint interceptors. The above requirements are sourced from Exhibit D The maximum length of grease contaminated drain shall not exceed 8m before the grease is intercepted. However, longer lengths are allowed if the drain is insulated and trace heated. On large kitchens centralised grease interceptors will be favoured on environmental health grounds. (source: ATKINS) There may be a requirement for starch traps in laundry areas. This is to be investigated with the Kitchen and Laundry Consultant when the brief is finalised for these areas.
6.7.
Vacuum Plumbing Systems
Vacuum drainage systems will only be used where gravity drainage systems are not viable. Vacuum drainage systems shall be designed in accordance with BS EN 12109 (IPC not adequate) and the manufacturers’ recommendations. The systems will comprise duplex or more vacuum pumps, receiver, valves and all necessary accessories and controls. The system layout including the piping layouts, receivers, vacuum pumps and all the components shall be installed as per the manufacturers’ recommendations. The vacuum systems will collect the discharged water where it will be held in the collecting tank until it reaches a predetermined level in the tank, it will then utilise automatically forwarding pumps to discharge the wastewater into the nearest gravity drainage s ystem. The system shall be capable of receiving the wastewater from all connected appliances, transporting it to the vacuum station receiver and forwarding it to the sanitation and wastewater system. Its capacity shall be sufficient to serve the system under all conditions, low flow as well as design flow, or as specified by the system specification. The prescribed minimum vacuum level shall be maintained during normal operational conditions at every interface unit except momentarily during vacuum recovery. The system controls shall be designed, as a minimum, to maintain the system vacuum within the prescribed range and protect the equipment from flooding or running dry. The pipework shall be designed to w ithstand the expected forces, pressures and temperatures. The design shall include means of isolating lengths of vacuum drainage pipes or sub-systems to permit repair or trouble-shooting. The design shall provide for the possibility of removing one vacuum generator and, if employed, one forwarding pump for maintenance or repair, without the loss of system capacity. The vacuum station shall have stand-by power capability. 421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
58
The piping network should be both supported and braced. Support is necessary, to maintain the piping profile required for proper function. Bracing is necessary to resist thrusting and reaction forces occurring when slugs move within the piping. Thrusting and reaction forces occur wherever there is a change in direction within any plane of reference. Similarly, these forces can be expected to occur wherever piping intersects. Vacuum drainage piping should be supported using bi-directional braces. Expansion and contraction of pipework should be taken into consideration.
6.8.
Rain/Storm Water Drainage
All building roof drainage will be collected and piped to the storm water drainage system. No free discharges are permitted. Storm water collected by roof drainage systems shall consist of roof drains connected to vertical drain pipes to discharge rain and surface water to the site storm water utility. Rainwater drainage will include drains for flowerbeds and plantation areas. The system will be design in accordance with IPC Chapter 11 (Storm Drainage). Pipework will be designed to achieve a minimum a 0.75m/s self cleaning velocity. Oil interceptors followed by sand traps will be provided to parking and oil y areas (source: Exhibit D) These IDF curves shall be used to determine storm water flow rates:
This data is based the KAIA SE Tunnel study document produced by SOL document reference DARSBG421-422/0140 dated 05 April 2011. Roof drains will be designed using the 100-year recurrence interval rainfall using the IDF data indicated above. Roof drainage designs have to accommodate the peak 5 minute intensity of 302mm/h but flows to stormwater systems may be reduced to take account of roof and gutter retention, permeability and other flow control systems that may be introduced in to the roof drainage design. This shall be in accordance with section 1106 of the International Pl umbing code 2006.
6.9.
Decorative Pools and Fountains
Wherever required, decorative pools and fountains shall be provided with automatic filtration systems. Filtration systems shall include filter pumps, sand filters and chlorination equipments. The system will be designed in accordance with ASHRAE A 4.6 421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
59
Water supply for initial fill and make-up water shall be connected from the potable water distribution site utility, designed to IPC requirements complete with appropriate backflow prevention.
6.10.
Compressed Air System
The compressed air system shall be designed in accordance with ASME 31.9 for systems operating at pressure of 860 kPa (125 psig) or higher. Each compressed air system shall comprise a packaged compressed air plant having air receiver served by duplex or more air compressors complete with refrigerated type air dryer, safety devices, oil and moisture separators.
Parameter or Strategy
Data or Description
Source
Workshop Outlets
1.7m³/h
Special Specification (Part D1)
Laundries
Manufacturers Recommendations
Special Specification (Part D1)
Other Facilities
Manufacturers Recommendations
Special Specification (Part D1)
6.11.
Basis of Design – Sanitaryware and Fitting Load Values Assigned to Fixtures
Parameter or Strategy
Load Values, on Water Supply Units
Source
Lavatory Basin
1.5 cold, 1.5 hot, 2.0 total
IPC Appendix E Table E103.3(2)
Shower
3.0 cold, 3.0 hot, 4.0 total
IPC Appendix E Table E103.3(2)
Bath
3.0 cold, 3.0 hot , 4.0 total
IPC Appendix E Table E103.3(2)
WC Flush (Cistern)
5.0 cold
IPC Appendix E Table E103.3(2)
WC Flush (Valve)
10.0 cold
IPC Appendix E Table E103.3(2)
Kitchen Sink
3.0 cold, 3.0 hot, 4.0 total
IPC Appendix E Table E103.3(2)
Laundry/Cleaners Laundry/Cleane rs Sink
2.25 cold, 2.25 hot, 3.0 total
IPC Appendix E Table E103.3(2)
Washing Machine
3.0 cold, 3.0 hot, 4.0 total
IPC Appendix E Table E103.3(2)
Urinal
5.0 cold
IPC Appendix E Table E103.3(2)
Refer to IPC Appendix E Table E103.3(3) for flow rates corresponding to loading values.
6.12.
Basis of Design – Water Distribution System Design Criteria Required Capacity at Fixture Supply Pipe Outlets
Fixture Supply Outlet Serving
Flow Rate USgpm (l/s)
Flow Pressure psi (kPa)
Source
Lavatory Basin
2 (0.13)
8 (55)
IPC Table 604.3
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
60
Fixture Supply Outlet Serving
Flow Rate USgpm (l/s)
Flow Pressure psi (kPa)
Source
Shower
3 (0.19)
8 (55)
IPC Table 604.3
Bath
4 (0.25)
8 (55)
IPC Table 604.3
WC Flush (Cistern)
3 (0.19)
8 (55)
IPC Table 604.3
WC Flush (Valve)
35 (2.2)
25 (172)
IPC Table 604.3
Laundry/Cleaners Laundry/Cleane rs Sink
3 (0.19)
8 (55)
IPC Table 604.3
Urinal, valve
15 (0.95)
15 (103)
IPC Table 604.3
6.13.
Basis of Design – Gravity Drainage Fixture Units
Fixture Type
Drainage Fixture Unit Value as Load Factors
Source
Lavatory Basin
1
IPC Table 709.1
Shower
2
IPC Table 709.1
Bath
2
IPC Table 709.1
WC Flush (1.6 USgpm)
4
IPC Table 709.1
WC Flush (>1.6 USgpm)
6
IPC Table 709.1
Kitchen Sink
2
IPC Table 709.1
Laundry/Cleaners Laundry/Cleane rs Sink
2
IPC Table 709.1
Washing Machine
3
IPC Table 709.1
Urinal
2
IPC Table 709.1
6.14.
Basis of Design – Sump Pumps
Parameter or Strategy Combined Sump pump flowrate (line pumps)
Data or Description 1 l/s per 20m2 (plant rooms) 1 l/s per 75m2 (elsewhere)
Source
ATKINS
6 l/s in tank rooms
Maximum dynamic back pressure in discharge main
30kPa one pump running
ATKINS
Minimum height of electrical control gear for flood protection
1400mm AFFL
ATKINS
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
6.15.
61
Aircraft Systems - Potable and Blue Water
Comply with the requirements of Exhibit D1 – 2.5.3.6.G
Potable Water. The potable water supplied by the airport utilit y network will be fed into an interim tank with a useable volume of 30 m3. The tank is equipped with a circulation pump with UV reactor for w ater disinfection and conservation. From the potable water tank the treated water is supplied via pressure pressure booster pump system system through a pipeline network up to the pit systems on on the apron. In order to avoid avoid stagnation inside the pipe pipe network, a recirculation pipe with UV disinfection is provided. In case post-chlorination is required, required, in addition to the UV disinfection a station for for quantity-proportional dosage of a sodium hypochlorite solution is designed. The process is operated automatically. Merely in the dosing station planned for a probable chemical disinfection, in certain time intervals the dosing solution has to be prepared manually. The potable water system is controlled and visualized at the central control panel. The plant conditions for operation and alarms shall be transmitted to the I2BS. The potable water shall be chilled before it is delivered to the air crafts via an Apron mounted Pop-up.
Blue Water After vacuum sewerage evacuation, the airplane wastewater toilet tanks have to be flushed with disinfectant solution (blue water). For the subsequent use of the toilet during the flight, after each flushing - according to toilet construction and airplane type - a certain quantity of blue water is filled into the wastewater tank of the airplane toilet. The production of blue water is carried out by using a concentrate and fresh water. The concentration for the use of the blue water solution is in the range of 2 %. The blue water system consists of two chemical batching tanks which work in alternating operation. The ready for use solution is withdrawn from one tank by means of the pressure controlled delivery pumps and then pumped via the pipe network on the apron up to the t he individual pop-up pit systems. The second vessel is ready for operation or in stand by position respectively the blue water is produced in automatic operation according to the following steps: -Filling in of fresh water -Stirring unit ON -Addition of concentrate After the end of the stirring time the solution is ready for use. All work steps are controlled by monitoring time and filling level. The control of the ready to use concentration of the blue water is done by metering the conductivity. The blue water system is controlled and visualized at the central control panel. The plant conditions for operation and alarms shall be transmitted to the central building management system.
6.16.
Aircraft Systems – Vacuum Waste
The vacuum wastewater, during during evacuation of the airplane toilet tanks, is carried by means of gravity (i.e. difference of level toilet tanks in the plane up to the hose drum system in the apron pit chamber) as well as by means of the additional vacuum pressure (0.5 - 0.6 bar) in the apron pipeline system. To safeguarding the pressure in the vacuum system various metering devices shall be located on the apron as well as in the vacuum station i.e. in case of a possible pressure shortfall different safety valves open for aeration of the systems respectively due to safety criteria t he vacuum pumps are switched off.
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
62
The transport of the toilet sewage is carried out from the pit chambers via a vacuum main pipeline up to the vacuum station installed inside the wet services plantroom. The vacuum station consists mainly of a vacuum wastewater tank with two discharge pumps as well as two vacuum pumps. The vacuum station is automated i.e. the switching of the discharge pumps for transporting the wastewater quantities into the local wastewater net is done via a level metering point in the vacuum tank - the vacuum pumps for the production of the necessary vacuum pressure in the system are controlled via a pressure gauge point. The strong odour exhaust air produced during this evacuation procedure is fed into an exhaust air cleaning unit. The two-step exhaust cleaning consists of a biologically active filter and a downstream activated carbon filter. The vacuum sewerage system is controlled and visualized at the central control panel. The plant conditions for operation and alarms can be transmitted to the central building management system.
6.17.
Seismic Support of Plumbing, Plant, Equipment and Systems
Refer to section 5.25 of this document.
6.18.
Irrigation
Refer to Exhibit D, 2.5.3.3 section H for the basis of design for irrigation inside buildings. Separate connection off the grey water utilities will be provided. For the systems external to buildings, refer to the landscape Irrigation Design Report 422-C220-DF-L-RPT001 and Grey Water Utilities Design Report 422-C220-DF-C-RPT-001
6.19.
Liquefied Petroleum Gas
Liquefied Petroleum Gas (LPG) will be provided to the various commercial kitchens which will be scheduled by the kitchen consultant – Humble Arnold. The systems shall be designed by a specialist gas contractor certified by Civil Defence in accordance with the requirements of NFPA 54 ‘Storage and Handling of Liquefied Petroleum Gases’ and the local Civil Defence Authority. A minimum of 2no bulk storage tanks shall be provided for 2 weeks continuous operation. Pressure regulation valve will be provided at 3no stages as follows: • • •
First stage regulation at tank manifold(s) Second stage regulation at kitchen main feeding pipe(s) Third stage regulating at equipment.
Distribution pipework external to the building will be yellow MDPE plastic . Pipework between LPG tanks and regulators/vaporisers will be welded steel w ith special corrosion protection measures. Distribution pipework within buildings wil l be seamless welded steel tubes painted yellow. Where pipes run in basements or unventilated voids a secondary containment system will be provided and a gas detection system will detect if gas has escaped from the primary carrier pipe by sensing the containment void. The system will be as made by George Fisher. For definition purposes unventilated voids will include the utility tunnels, chases, basements, ceiling voids and risers. Gas detection will be provided at low level behind all ranges with gas appliances. It will be of a type that has a perforated sensing pipe through which air is constantly circulated to ensure, that no gas pockets have built up that would not be detected by a point source detector. An automatic shut off valve will be provided to each room where gas is consumed which will close in the event of a fire alarm in the same zone, gas being detected in the room or gas being detected in the containment pipe void..
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
63
An automatic shut off valve will be provided for each equipment range that will shut off in the event of a gas escape being detected at the range. Strategically placed zone valves will automatically close if a fire is detected in an area through which a gas pipe is routed or if gas has been detected in the containment void. Annunciation will be provided in a central location with means of resetting alarms and valves A fireman’s gas valve will be b e provided external the building. An earthquake shut off valve shall be provided at the point of entry to each building.
Parameter or Strategy
Data or Description
Source
Number of bulk storage tanks
2
Exhibit D
Storage period
2 weeks taking into account diversity and margin, but 24x7 demand.
ATKINS
Gas type
Propane
TBC
LPG storage pressure @ 55 C
19.5 bar(g)
NFPA 58
Pressure after first stage regulator (max)
140 kPa
IFGC 402.6.1
Maximum pressure drop between first stage regulator and second stage regulator
7 kPa
IFGC Table 402.4(22)
Maximum pressure after second stage regulator
34 kPa
IFGC 402.6
Maximum pressure drop between second stage regulator and third stage regulator
6.8 kPa
IFGC Table 402.4(23)
Pressure after third regulator
To suit appliances (nominally 2.7 kPa (11”w.g.))
IFGC Table 402.4(24)
Diversity factors
60% - kitchens 90% - laundries
ATKINS
Design margin
50%
ATKINS
o
6.20.
Acoustic and Vibration – Plumbing Systems
Applicable to pumps only. Refer to section 5.27.
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
7.
Fire Protection
421-422-A000-DF-G-RPT-00020-D
64
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
421-422-A000-DF-G-RPT-00020-D
65
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
66
Fire Protection 7.1.
General
Ref: Contract document No. J-1X-421 and 422-PF-0 Exhibit D-Special specifications, Part-D1, clause 2.5.3.4 Fire Protection systems. Comply with applicable laws, regulations and standards regarding fire prevention as stipulated in SC-57 of Exhibit B. Obtain approval of all fire f ire protection system design documentation from the appropoaite AHJ.
7.2.
Code and Standards
The following codes and standards will be used in the design of the fire protection systems:
Publication Reference
Publication Title
---
KAIA Fire Protection Manual (only design related sections)
NFPA 10
Standard for Portable Fire Extinguishers
NFPA 13
Standard for the Installation of Sprinkler Systems
NFPA 14
Standard for the installation of Standpipe, Private Hydrant and Hose Systems
NFPA 17
Standard for Dry Chemical Extinguishing Systems
NFPA 170
Standard for Fire Safety and Emergency Symbols
NFPA 20
Standard for the Installation of Stationary Pumps for Fire Protection
NFPA 2001
Standard on Clean Agent Fire Extinguishing Systems
NFPA 24
Standard for the Installation of Private Fire Service Mains and Their Appurtenances
NFPA 72
National Fire Alarm and Signalling Code
NFPA 780
Standard for the Installation of Lightning Protection Systems
NFPA 90A
Standard for the Installation of Air-Conditioning and Ventilating
NFPA 91
Standard for Exhaust Systems for Air Conveying of Vapors, Gases, Mists, and Non-combustible Particulate Solids
NFPA 92
Standard for Smoke Management Systems
NFPA 92A
Standard for Smoke-Control Systems Utilizing Barriers and Pressure Differences
NFPA 92B
Standard for Smoke Management Systems in Malls, Atria, and Large Spaces
NFPA 101A
Guide on Alternative Approaches to Life Safety
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
NFPA 101B
Code for Means of Egress for Buildings and Structures
NFPA 110
Standard for Emergency and Standby Power Systems
7.3.
67
Water Supply
Fire water supply to all the buildings shall be connected to the external fire fighting distribution site wide ut ility network. The supply pipe shall be sized hydraulically to meet building fire fighting flow requirements.
7.4.
Sprinkler Systems
A fully automated sprinkler system shall be provided to all buildings according to NFPA 13 requirements. The system design shall be based on hazard classifications that are provided in the contract document CPF100-SP-F-RPT-0200 Rev B. Hazard classifications are listed in Appendix A. Sprinkler system shall be designed in accordance with Exhibit "D2" 211313 - WET-PIPE SPRINKLER SYSTEMS The minimum pressure available at each sprinkler shall be designed in such a way that the required design density is achieved or the required flow at each sprinkler is achieved based on the application of the area whichever is higher. But in any case the minimum pressure requirement stated in NFPA 13 & recommendation of the sprinkler manufacturer are met. Each sprinkler riser shall be connected with an alarm check valve & isolation valve. Each alarm check valve shall not serve a portion of floor exceeding 4831sq.m. In any case if the floor area exceeds 4831 sq. m additional alarm check valve with riser shall be provided. The zoning of the sprinkler system shall comply with the requirements of NFPA 13. Non return valves shall be installed in the breeching inlet piping to avoid back flow of water from the system. Each sprinkler riser shall be connected with a breeching inlet. Breeching inlet piping shall be connected to the downstream of the alarm check valve. The sprinkler system shall be zoned & each zone shall be provided with an isolation valve supervised electrically, flow switch (connected to the fire alarm system) test and drain valve, pressure gauge, etc to comply with NFPA 13. The outlet of the drain valve shall be connected to the nearest floor drain. Sprinkler system shall be provided to all the enclosed portion of the building except the areas where other specialised systems are used. Automatic air release valves shall be installed at the elevated level of each riser with an isolation valve and end cap. All the isolation valves shall be provided with a supervisory switch which shall be electrically supervised in the Main fire alarm panel. There shall be an individual address for each isolation valve. All controls and alarms' requirements shall be connected to the fire alarm system. BMS monitoring will be provided as described in the BMS design report.
7.5.
Standpipe and Hose Systems
Standpipe and hose systems will be provided in accordance with NFPA 14 Standard for the Installation of Standpipe, Private Hydrant and Hose Systems. Stand pipe and hose system shall be designed in accordance with Exhibit "D2" –211200 - FIRESUPPRESSION STANDPIPES 421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
68
A Class I/Class III standpipe system shall be provided as per NFPA 14 requirements. A Class I standpipe system shall be provided with Fire hose cabinets with approved finish shall be placed near each hose outlet which shall contain 1 no. of 65mm diameter landing valve with 65 x 40 mm diameter reducer, 4.5kg carbon dioxide type fire extinguisher and 4.5kg dry powder type fire extinguishers. A Class III standpipe system shall be provided with Fire hose cabinets with approved finish shall be placed near each hose outlet which shall contain 1 no. of 65mm diameter landing valve, 1 no. of 40mm Hose rack, 4.5kg carbon dioxide type fire extinguisher and 4. 5kg dry powder type fire extinguishers. As part of the CRS process the CM has repeatedly instructed that only Class III standpipes be deployed, therefore this will be the basis of design. Minimum pressure available at each outlet shall be 6.9 bar (100 psi) as required by NFPA 14. The installation height of the outlets shall comply with NFPA 14. Water for the wet risers shall be tapped from the main header in mechanical plant room. An approved pressure regulating device (PRV) shall be provided to limit static and residual pressures at the riser inlet t o 175 psi (12.1 bar). Fire brigade breeching inlets with check valve shall be located around the Mosque. The location of the fire brigade breeching inlet shall be in such a way that it shall be within 30.5m of fire brigade vehicular access in accordance with NFPA 14. Siamese connections are to be provided for the fi re fighting system in each buildi ng. The Fire fighting system shall be designed in such a way that the water supply from the fire brigade trucks will reach all portions of any served building. All controls’ and alarms’ requirements shall be connected to the fire alarm system BMS monitoring will be provided as defined in the BMS design report. Pressure reducing valves or other restricting devices shall be used to control the maximum pressure and maximum flow for each water outlet point.
7.6.
Portable Fire Extinguishers
Portable fire extinguishers will be provided in accordance with NFPA 10 Standards for Portable Fire Extinguishers. Extinguishers will be provided at all hazard areas such as kitchens, electrical rooms, chemical rooms, garbage rooms and generators. Extinguisher types to be provided are: • • •
Carbon Dioxide ( provide in kitchens, electrical, communication rooms) Dry Chemical ( provide in mechanical plant and garbage rooms) Foam ( provide in chemical and paint storage room)
In rooms protected by FM-200 type, ABC and CO2 fire extinguishers will be provided in accordance with NFPA requirements.
7.7.
Foam Systems.
Pre action Foam water Sprinkler System shall be provided for generator room and system shall be of Double knock type confirming to the requirements of NFPA 11, NFPA 13 & NFPA 16. Foam system shall be designed in accordance with Exhibit "D2" N 211339 - FOAM-WATER SYSTEMS Water for the foam system is drawn from the bladder type foam tank and extinguishing panel are located within the generator room. 421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
69
Foam concentrate shall be of 3% AFFF. Water for the foam water sprinkler system shall be drawn from the fire fighting network. Pre-action valve shall be provided with electric & pneumatic head trim assembly. Isolation valves shall be provided at downstream & upstream of the pre-action valve. Appropriate capacity Vertical mounted air compressor shall be selected for the pre-action system. Bladder type Foam tank shall be located near the pre-action valve with foam proportioner. The foam proportioner shall be suitable for proportioning 3% of foam concentrate. A foam concentrate sensing line shall be there in the foam proportioner to monitor the flow of foam concentrate & to avoid the flow of water alone into the area being protected. Downstream of the pre-action valve shall be normally filled with compressed air. Foam concentrate carrying pipe shall be of stainless steel SS 316. All fittings & valves used in foam concentrate network shall be of stainless steel SS 316 Double knock system shall be with (1) sensing of heat (bulb fuses) by the sprinkler & (2) detection of smoke / fire through detectors Bladder tank size & foam concentrate quantity shall be as referred by NFPA 11 & shall include 100% standby reserve for operation of the system. In addition to that the suitable quantity of foam concentrate shall be made available for testing & commissioning of the system All the components use for the system including but not limited to bladder tank, foam concentrate, pre action valves, isolation valves, sprinklers, foam proportioner, etc shall shall be UL listed / FM approved approved and shall be approved by local authority.
Technical particulars are defined below:
Parameter or Strategy
Data or Description
Source
Foam Concentration
3% AFFF
NFPA 11/16
Design Density
6.5 lpm/m .(loading bay) and 4.1 lpm/m2 ( tanks )
NFPA 11/16
Discharge Duration
10 minutes
NFPA 11/16
2
7.8.
Wet Fire Suppression System Control and Instrumentation
To comply with NFPA 13, 14, 20 and 72 including: Pressure Gauges. Gauges. A listed pressure gauge conforming to 4- 15.3.2 shall be installed in each system riser. Pressure gauges shall be installed above and below each alarm check valve where such devices are present. Waterflow Detecting Devices. Devices. The alarm apparatus for a wet pipe system shall consist of a listed alarm check valve or other listed waterflow detecting alarm device with the necessary attachments required to give an alarm. Relief Valves. Valves. A gridded wet pipe system shall be provided with a relief valve not les s than 1/4 in. (6.4 mm)
7.9.
Wet Fire Suppression System Pressure Regimes
The fire main pressure at the point of entry to the bui lding is as detailed from the fire main utilit y hydraulic model outputs in the 70% fire main utility report. 421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
70
The residual pressure and flow rates at discharge points are as defined in NFPA 13 and 14. Pipework will be sized hydraulically in accordance with NFPA 13 to optimise pipe sizes as far as possible.
7.10.
Dry Chemical System.
Dry chemical suppression systems shall be provided within kitchen hoods. The dry chemical fire suppression systems will be performance specified for development and certification by an AHJ approved specialist contractor in accordance with NFPA 17 and Master Format and Specification Division 212400
7.11.
Clean Agent System.
Gaseous Fire Suppression System
FM200 Gaseous fire suppression is provided for the electrical and ITC equipment rooms to comply with the requirements of NFPA 2001 FM200 Gaseous fire suppression system in accordance with Exhibit "D2" 212200 - CLEAN-AGENT FIREEXTINGUISHING SYSTEMS, except the activation sequence as explained in 2.1 C. It is difficult to ensure the air tightness (Room integrity) within the voids i. e. ceiling void, room void and raised floor. Here the design considered as total flooding and extinguishing agent shall be discharged to all zones in case of fire in any zone. The design concentration for the gas will comply with the requirements of NFPA 2001, and will comply with the requirements of the authority having jurisdiction. The discharge duration of the gas will be within 10 seconds. Design concentration for FM200 will be 7.19 %. Each system will comprise of the following primary components: • • • • • • •
• •
Gas storage bottles Distribution pipework Solenoid head Solenoid actuator Pneumatic actuator Local manual actuator Supervisory low pressure switch for each cylinder Discharge pressure switch Abort switch
• • • • • •
• • •
Auto / Manual selector switch Manual release sign Entrance warning sign Gas extinguishing panel Smoke detectors Horn Strobe Flashers Alarm Bell Main/standby selector switch
All the above equipments & system will be listed for the purpose it is used. The same will be UL listed, FM approved, NFPA compliance and approved by the authority having jurisdiction. A fire detection, actuation & alarm system will be provided for each individual gas suppression system. A minimum of 2 Nos. detectors with a combination of ionisation & optical type smoke detectors will be provided with actuation for gas release and be achieved by cross zoning of the detectors (double knock). Detector allocation is based on a maximum of 23 sq/m per detector. Heat detectors are provided in the battery room with cross zoning. There shall be a time delay of 30 seconds for the discharge of gas from the time of double knock of detectors. The following annunciations will be made available at the main alarm panel from the gas release panel: • •
Gas release panel fault Fire indication, Stage 1 & Stage 2
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report • • • •
71
Gas discharge Low pressure in the gas storage cylinder AC power failure to Gas Release Panel System in Manual mode
Each room protected with a gas suppression system will be provided with a suitable Horn Strobe at each entrance of the room, controlled to activate in the event of gas discharge and to prevent personal entering the room. FM200 control panels will be located external to the rooms adjacent to the main entrance door. All ventilation system supply and/or extract ductwork to these rooms are fitted with motorized dampers to ensure air seal of the protected room in the event of gas discharge. All critical room served by gas suppression system is provided with a suitable extract ventilation system for gas clearance (purging) after discharge.
7.12.
Seismic Support of Fire Suppression, Plant, Equipment and Systems
Support, brace and provide flexible couplings for all fire suppression, plant, equipment and systems in accordance with the requirements of NFPA 13, 14 and 20. Refer also to section 5.26 of this document.
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
8.
Electrical Systems
421-422-A000-DF-G-RPT-00020-D
72
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
421-422-A000-DF-G-RPT-00020-D
73
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
74
Electrical Systems 8.1.
General
This section of the BoD should be read in conjunction with contract documents No. J-10-421-PF-0 and J-10422-PF-0, Exhibit D-Special specifications, Part-D1, Section 2.6 and the associated sections in Part D2.
8.2.
Definitions, Abbreviations and Acronyms
The following definitions and acronyms and abbreviations apply to this section
Acronym /Abbreviation
Definition
SEC
Saudi Electricity Company
EMT
Electrical metallic tubing.
IMC
Intermediate metal conduit.
RMC
Rigid metal conduit.
RNC
Rigid non-metallic conduit.
GRC
Galvanized rigid steel conduit.
Trough or Ventilated Cable Tray: Ladder Cable Tray:
A fabricated structure consisting of integral or separate longitudinal rails and a bottom having openings sufficient for the passage of air and using 75 Percent or less of the plan area of the surface to support cables. A fabricated structure consisting of two longitudinal side rails connected by individual transverse members (rungs).
Basket Cable Tray:
A fabricated structure consisting of wire mesh bottom and side rails.
Transformer K-Factor
This measures the transformer's ability to withstand the heating effects of nonsinusoidal harmonic currents produced by electronic equipment.
IBC
International Building Code.
OSHPD:
Office of State-wide Health Planning and Development for the State of California
UBC
Uniform Building Code.
ICC-ES:
ICC-Evaluation Service.
8.3.
Codes and Standards - MV Supply
The following codes and standards shall be used when designing the MV cable connections to SEC Substations.
Publication Reference Saudi Arabian Distribution Code Saudi Arabian Grid code SEC standards and specifications
Publication Title The Saudi Arabian Distribution Code The Saudi Arabian Grid Code As applicable to MV cable design for connection to SEC primary substations
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
8.4.
75
Basis of Design – Standards
The Electrical works shall be designed in accordance with the following codes and standards:-
Publication Reference
Publication Title
BS 7671
Requirements for Electrical installations 17 with Amendment 1
NFPA 72
National Fire Alarm and Signalling Code
NFPA 110
Standard for Emergency and Standby Power Systems
NFPA 780(delete) BS EN 62305
Standard for the Installation of Lightning Protection Systems(delete) Protection against lightning Part 1: General principles
NFPA 780
Standard for the Installation of Lightning Protection Systems
NEMA
National Electrical Manufacturers Association.
ANSI
American National Standards Institute.
IEEE
Institute of Electrical and Electronics Engineers.
ATSM
American Society for Testing and Materials.
UL
Underwriters laboratories, Inc
IEE
Institute of Electrical enginee engineers rs
BSI
British Standard institution
EN
European Norm
CIE
International Commission on Illumination
IEC
International Electrotechnical commission
CIBSE
Chartered Institute of Building Services Engineers
8.5.
th
Basis of Design – Substations
Parameter
Description
Source
MV and LV cables generally
Copper conductors cables only, aluminium conductors are not acceptable. Single core cables only (specified in 2 mm CSA), Multicore cables will not be acceptable. This applies to main, sub-main and final circuit cables.
Exhibit D
MV cables
IEC 60502 15/4.16 kV Single core XLPE/ MDPE water block jacket
Exhibit D2 - Part 2
MV cables and terminations
Cable joints are to be as D2-260513 MEDIUM-VOLTAGE CABLES Part
Exhibit D2-260513
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
Parameter
Description
76
Source
2.2.C and 3.3.B IEC60502 & BS6387 LV Cables
600/1000V Single core 6181 2 XLPE/LSZH Metric Cables (mm )
Exhibit D1 - 2.6.3.5
Standards: Electrical Installation generally
BS 7671 IEE 17 with Amendments 1
Exhibit D1 - 2.6.2
MV Power Supply Type
13.8 kV , 60 Hz, 3 x 1 core + E ( Earth in separate conduit)
Exhibit D2 - Part2
MV Power Factor Correction System
Automatic/manual controlled. Double star configuration at 13.8kV and in Delta configuration at 4.16kV
Exhibit D1 - 2.6.3.17
MV cable connection
Radial circuit(s) from load centre to secondary substation. Tee-off connection or Loop-in, loop-out ( whichever is more appropriate) from one MV CB to next in same secondary substation
Exhibit D
LV Power supply Type – generally
400/230 Volts, 60 Hz, TN-S 3-phase 4 wire, solidly earthed.
Exhibit D1 - 2.6.3.2
LV supply supply – receptacles small power
230 Volts, 60 Hz.
Exhibit D1 - 2.6.3.2
Substation switchgear
Integrated metal clad substation as per 2.6.3.3 – designed for 100% redundancy.
Exhibit D1 - 2.6.3.3
th
Electrical substation(s) in fire rated room. Electrical Substation
Outdoor unit substations
The agreed “rules of segregation’ are being used for the determination of the substation room orientation. See appendix... Outdoor unit substations maybe provided for outdoor applications only (e.g. for the Landside Roads). Designed to IEC Standards
Exhibit D1 - 2.6.3.3
Exhibit D1 – 2.6.3.3
30% - transformers, LV MDBs, switchboards and LV sub main cables. Spare capacity
30% spare breakers are to be provided in the distribution levels starting from Panel boards, switchboards, MCCs, MDB, etc
Exhibit D1 - 2.6.3.3
MV selection
2 x interlocked dual primary motorized circuit breakers (connected to normal and alternative radial feeders), outgoing tee-off circuit breaker to transformer.
Exhibit D1 - 2.6.3.3
LV selection
2 x transformers normally on line, feeding two separate sections of MDBs, interconnected via normally open tie CB. If one transformer fails,
Exhibit D /Atkins
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
Parameter
Description
77
Source
its feeder ACB opens and the tie ACB closes. (controlled by integral PLC in LV MDB and interface to SCADA)
Transformer type
Transformer configuration in substation
Transformer ratings
Transformer K-Factor
MV Switchgear
Cast coil/encapsulated coil type, insulation insulati on class cl ass B 150° 150°C C (80° (8 0°C temperature rise). ). Indoor type, low loss, Class F winding insulation. Basic Protection provided by provision of barriers or placing out of reach. Designed to IEC 60076 Each transformer is to be connected to two separate feeders through circuit breaker to provide a normal and an alternate source. Upon failure of the normal source, the transformer is to be switched to the alternate source. Each transformer is to be fed from lines/feeders via tapping (Tsection) as per the contract requirements. including 30% spare capacity. Standard MV/LV transformer sizes to be used are 500, 1000, 1500, & 2000 kVA only, naturally ventilated. Forced cooling will not be considered unless directed by CM.
Minimum 13. K-Factor for dry type LV transformers Metal enclosed switchgear with withdrawable Arc resistant Vacuum circuit breakers type 2B Integral Interlocked Earthing Switch. Integrated Control Section Dedicated Closing battery system Top or bottom Entry cables MV surge Arrester Designed to IEEE C37. Metalclad floor standing cubicle type main switchboards, fitted with withdrawable ACBs or motorised MCCBs to IEC 60947
Exhibit D1 - 2.6.3.3 Exhibit D2 - 261200 Atkins
Exhibit D1 - 2.6.3.3
Exhibit D1 – 2.6.3.3 Letter DAR/SBG 421422/0477; and Exhibit D2 – 261200, 2.2/Q/3 Tender Q&A – 283 and 285 shall be in accordance with ANSI/IEEE C57.110 & UL 1561.
Exhibit D2 - 261300
Form 4b (type 6).
LV Switchgear (MDB)
Front and rear accessible. Rear connected cable chambers. Side connected cable chambers where split board is required to meet spatial constraints. Copper busbars,
421-422-A000-DF-G-RPT-00020-D
Exhibit D1 – 2.6.3.3 Exhibit D2 - 262413
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
Parameter
Description
78
Source
Fully sized neutral, half sized earth. Internal PLC for process control. Integral Control voltage supply and battery charger, remote batteries. Transient Voltage surge suppression units to BS6651. Ingress protection of IP31 (indoor type) Control section with dedicated field wiring terminal blocks separated from power wiring. Electronic Trip units (Harmonic measurement type) on outgoing circuit breakers 400A and above Thermo-Magnetic trip units units on outgoing circuit breakers below 400A MDBs shall contain filters as necessary to prevent any harmonics produced “down-stream” from traveling “upstream” within the IEC recommendations as per Contract requirements, Extension of structure and busbars is to be possible at either end of switchboard for form 3 and form 4 type switchboards.
LV Switchgear incomers
Diversity Factors for electrical loads
MV Surge arrestors
421-422-A000-DF-G-RPT-00020-D
Switchboards: Circuit Breaker SMDB’s: Circuit Breaker MCC: Circuit breaker Final Panelboards: MCCB (non-auto)
In accordance with BS7671 IEE wiring regulations. UPS and Life Safety Loads to be undiversified MV surge arresters are to be provided for typical MV incomers, MV cables, MV motors and MV transformers feeders.
Exhibit D2 – 262413Exhibit D2 – 262413 Exhibit D2 – 262419 Exhibit D2 – 262416
Atkins
Exhibit D2 – 261300 / 2.6/G
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
8.6.
79
Basis of Design – Local LV Generators
Parameter
Emergency power Supply – diesel generators
Description Provided to buildings as specified. Provided to buildings as specified. Upon failure of both A and B 13.8 kV incoming lines, the central emergency generators will start and energise the 13.8 kV feeders from the central generators. Load shedding will be provided to ensure that only essential loads are connected to the central generators. At the same time, the SCADA will open 13.8 kV CB’s for feeders to buildings with local LV generators.
Source
Exhibit D – Appendix 1
In the case of building with local LV Generators, the local LV generators will start and provide power to the essential LV services in the associated building via automatic changeover transfer switch arrangement. Fuel tanks
Bulk fuel tank type
Day Tank Type
8 hour day tank 7 day bulk tank(s); 2 days bulk tank for support facilities B Above Ground double skin or bunded single skin, where possible. Install at a height to provide gravity feed to the day tank, where possible. Below ground storage tank subject to agreement with SBG. Double skinned and built into generator skid, where possible. Otherwise single skinned and bunded.
Exhibit D and DAR response to RFI
ATKINS
ATKINS
Air intake / air exhaust
Front and back of generator room respectively. It is acceptable to use turning vanes or equivalent to turn air through 90°where louvers are not opposite each other.
Exhibit D1 – 2.6.3.4
Load banks
250 A receptacles, with isolator for connection of load banks. Quantity as required to allow full load testing on generator ( example 3 No. for 500 kVA generator)
Exhibit D1 – 2.6.3.4
Parallel operation to grid
Not required
SEC regulations (Distribution code)
Minimum size
As required by load calculations.
Essential loads connected to generator
As per list in exhibit D. The load priorities in relation to available power sources: This information will be contained within the SCADA report 421-422-C100-FD-E-RPT00001-A
Exhibit D1 – 2.6.3.4
Noise attenuation
85dB at 3m from generator room wall
Exhibit D
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
Vibration isolation to adjacent floor slabs
8.7.
0.04 mm total amplitude through the frequency range down to 63Hz
80
ATKINS (TBA)
Basis of Design – LV Distribution.
Parameter
Description
Electrical installation generally
BS 7671 IEE 17 with Amendments 1
Exhibit D1 - 2.6.2
Underground conduits and ducts
Fully encased in CONCRETE throughout their entire length – due to high water table.
Exhibit D and Post Tender Clarifications ( Q 34)
Circuit breakers
800A and above – with-drawable ACB’s ( 3 or 4 pole type)
Exhibit D1 - 2.6.3.6
Meters
Multifunction meters on all main incoming feeders linked to SCADA; Analogue voltmeters, ammeters and indication lights on each incoming phase.
Exhibit D1 - 2.6.3.6
Emergency Central battery System
Modular design with all modules encapsulated plug-in type
Exhibit D1 - 2.6.3.8 / D2 263323
LV Cables
XLPE Single core only – specified in mm2
Exhibit D2 - Part 2
LV Final circuits
Minimum CSA; Lighting 2.5 mm2, Power 4 mm2
Letter DAR/SBG 421422/0477
LV Power factor correction.
PFC required to achieve 0.95
Exhibit D ( 2.6.3.6)
Sub-distribution board
Max number of outgoing ways shall be 14 ( SMDB’s)
Exhibit D1 - 2.6.3.6
Final panel boards
Totally enclosed, dead front type,IP31 for indoor, IP55 for outdoor. IEC 60529
Exhibit D2-262416
MCC’s
Source th
Metalclad free standing, sectionalized type, modular, compartmented, Form 4b (type 6) to IEC 60439, fully withdrawable. Front accessible. Copper busbars,
Exhibit D2-262419
Ingress protection of IP42 (indoor type). IP65 for outdoor / Wet areas ( eg. Pump rooms ) Voltage drop
Maximum Voltage drop shall not exceed 5% from point of supply to end circuit.
Exhibit D
Spare Capacity -30%
Generators, transformers, MDB, MCCs sub-circuit DB’s, panel boards, sub-main cables – generally throughout distribution system.
Exhibit D
Transient Voltage Surge Suppression
TVSS devices are to be provided in compliance with Section 264313
Tender - Q& A 282
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
8.8.
81
Basis of Design – UPS
Parameter
Description
Source
UPS units
Required for ICT systems, s ystems, computers, life safety loads, All I2BS components. . Adequate line stabilisers/ regulators (static electronic type, complying with relevant IEC Standards) shall be provided in the by-pass connection line of the UPS units.
Exhibit D1 – 2.6.3.7
SAS/ICT loads
All SAS/ICT loads are dual fed via UPS
Exhibit D1 – 2.6.3.7
Type ( not data centre)
Three-phase, on-line, doubleconversion, static-type.
Exhibit D1 – 2.6.3.7
Configuration
Dual/ fully redundant and hot standst andby. (System is to be externally redundant which implies 2 complete UPS units with 2 sets of batteries operating in parallel.
Exhibit D1 – 2.6.3.7
Battery autonomy
60 minutes full load, 4 hours for radio sites
Exhibit D1 – 2.6.3.7
Maintenance bypass.
Manually operated (EMBS) to ensure removal of UPS without disturbing the UPS load.
Exhibit D1 – 2.6.3.7
Single point of failure elimination
Applicable to data centres and where explicitly called for in Exhibit D
Exhibit D1 – 2.6.3.7
Battery type
Premium Valve-Regulated, Leadcalcium Batteries
Exhibit D2 - 263353
UPS-Battery room ventilation
421-422-A000-DF-G-RPT-00020-D
In addition to the A/C system; UPSbatteries charging rooms and the like shall be provided with dedicated exhaust system by means of explosion proof fans. Make up air shall be directly supplied by means of fresh air duct to these spaces.
Exhibit D1 section 2.5.3.5
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
UPS scheme layout
421-422-A000-DF-G-RPT-00020-D
82
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
8.9
83
Basis of Design – General Power Outlets
Parameter
Description
Source
Type
British standard type 3 pin 230 volts BS 1363
Exhibit D – 2.6.3.10
Duplex outlets
Adequate number in office areas, control / operations rooms. ( Typically 1 X double outlet per workstation and similar
Exhibit D / Atkins
ICT outlets
Outlets fro ICT as shown on drawings. All unswitched. For Comms rooms rack supply, see below sketch
ICT requirement
Single outlets
Corridors, public areas and technical rooms. Spacing along corridors shall be 15m maximum between outlets.
Exhibit D
Special Purpose Transformers ( for 120 Volt outlets – example in hotel suites where travellers plugs may be required)
Dry type transformer – 400/230 volts to 208/120 Volts.
Exhibit D1 – 2.6.3.10
Special purpose outlets
Outlets for fixed equipment, workshops and special equipment where required
Exhibit D1 – 2.6.3.10
400/230volts 3 phase, phase, 4 wire: Lighting (230V); and Motors larger than 3/4hp (400V). Voltage – equipment, appliance and fittings criteria
Motors larger than 500 hp (4.16kV) 400/230 Volts 3 phase, 4 wire: Small power (230V receptacles, small appliances, incandescent lighting, and small exhaust fans).
Exhibit D1 – 2.6.3.9
Motors up to 3/4 HP will be single phase 230 volts unless otherwise required specifically” RCDs
Ground Fault Circuit interrupters as per BS 7671
Exhibit D1 – 2.6.3.10
RCDs Location:
Exterior, Electric Water Cooler (EWC), Break Room (counter area outlets and next to sinks), sink s), Janitors Closet, Locker Rooms, Garage, Restrooms, Kitchens (counter area outlets and next to sinks.), Water features, Elevator pits, Escalators, Moving Walks, Chair Lifts, and electric signs.
IEC / Atkins
Technical rooms
Dedicated outlets connected to UPS supply dedicated to DDC panels for connection to BMS.
Exhibit D – 2.6.3.10
Wiring
Routed in rigid steel conduits for exposed locations subject to mechanical damage.
Exhibit D
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
8.9.
84
Basis of Design – Lighting Installation
Parameter
Description
Source
Lamp Type
T5 fluorescent lamps, equipped with electronic ballasts, will be used in the control rooms, offices, and other functional/technical spaces (mechanical, electrical rooms, toilets, corridors)
Exhibit D2-265100 and addendum 1
Standards
Comply with CIBSE
Exhibit D1 – 2.6.3.11
LMS
Luminaires 421-422-A000-DF-G-RPT-00020-D
A State of the Art Lighting Management System (LMS) is to be provided including lighting controls, dimming, energy saving methods and techniques and the exploitation of natural light, etc. Standard products Comply with CIBSE and BS 4533 (BS EN 60598)
Exhibit D and addendum 1
Exhibit D1 - 2.6.3.11
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
85
Parameter
Description
Source
External luminaires
Full cut-off type. Comply with BS 5489, CIE 115and MOT standards.
Exhibit D1 - 2.6.3.11
Lighting Levels - internal
Refer to basis of design – Lighting Levels
CIBSE
The illumination levels shall conform to BS 5489, CIE 115 and MOT MOT (Ministry of transportation) requirements for exterior areas & road ways but at a higher uniformity of 0.4 minimum
Lighting Levels -exterior areas & road ways
All General Area - 0.8 0. 8 Car Park and workshop workshop - 0.7 External Area (exposed) - 0.6
Maintenance Factor
Ceiling -70% Wall – 50% Floor - 20%
Reflectance Factor
Working Plane
Atkins
Corridor and general circulation area: at finished floor level.
Atkins
Offices etc: 750mm from finished level.
Atkins
Communication Rooms: 1000mm from finished floor level
8.10.
Atkins
Atkins
maximum 500mm from the wall/boundary
Boundary Zone
Exhibit D1 - 2.6.3.11
Exhibit D2-270400
Basis of Design – Lighting Levels
Parameter
Normal Horizontal Illuminance (lux)
Working Plane Height Metres
ECBS Horizontal Illuminance (lux)
Source
INTERNAL AREAS Ablution room
150
0
10
CIBSE
Airfield lighting vaults
300
0
100
CIBSE
Baggage handling
400
0
10
CIBSE
Break room
150
0.75
10
CIBSE
Circulation area
200
0
10
CIBSE
Detention room
300
0.75
10
CIBSE
Doctors/nurses office
500
0.75
10
CIBSE
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
Parameter
Normal Horizontal Illuminance (lux)
Working Plane Height Metres
86
ECBS Horizontal Illuminance (lux)
Source
CIBSE
Fire safety & alarm rooms (?)
800
0.75
10
Goods Inwards
300
0.75
10
Interview room
300
0.75
10
Janitors room
100
0
10
CIBSE
Commercial Kitchen
750
0.75
10
CIBSE
Residential type kitchens
400
0.75
10
Locker room
100
0
10
Maintenance access areas exterior
10
0
10
Maintenance access areas interior
50
0
10
Medical centre waiting area
300
0.75
10
Meeting room
300
0.75
10
Office
500
0.75
10
Office reception
300
0.75
10
Plant room
300
0
10
Prayer room
100
0
10
Reprography
500
0.75
10
Shower room
100
0
10
CIBSE
Smoking room
100
0
10
CIBSE
Staff canteen
300
0.75
10
CIBSE
Store room
150
0.75
100
CIBSE
Toilet
200
0
10
CIBSE
Refuse Area/Room
100
0
10
CIBSE
Electrical Room
300
0.5
100
Exhibit D2-263323
Substation
300
0.5
100
Exhibit D2-263323
Comms Room
500
1.0
100
CIBSE
Control Room
500
1.0
100
CIBSE
Car Parking
75
0
10
CIBSE
EXTERNAL AREAS
421-422-A000-DF-G-RPT-00020-D
CIBSE CIBSE
CIBSE CIBSE CIBSE CIBSE CIBSE CIBSE CIBSE CIBSE CIBSE CIBSE
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
Normal Horizontal Illuminance (lux)
Parameter
Working Plane Height Metres
87
ECBS Horizontal Illuminance (lux)
Source
BS 5489
Car Parking
20
0
Junctions to arterial roads (1, 3, 4, 9 )
30
0
Expressway & interchange
20
0
Junctions Roads
20
0
Junctions to Arterial Roads(2)
20
0
Aircraft stands
50
0
D1-2.6.12
With
BS 5489 BS 5489
Collector
BS 5489
BS 5489
CCTV perimeter fencing
10
0
Air Force manual. TM5-811-1/AFJMAN 32-1080
Perimeter fencing
4
0
Air Force manual. TM5-811-1/AFJMAN 32-1080
STREET LIGHTING
Average Luminance over the evaluated roadway
Collector Roads
1 Cd m2
0.4
0.7
BS 5489
Arterial Road 2
1 Cd m2
0.4
0.7
BS 5489
.Arterial Roads 1,3,4 & 9
1.5 Cd m 2
0.4
0.7
BS 5489
Passenger Access Roads
1.5 Cd m 2
0.4
0.7
BS 5489
8.11.
overall uniformity over the entire roadway
longitudinal uniformity of each driving lane
Emergency Lighting Systems
Parameter
Emergency Lighting Systems (self contained)
421-422-A000-DF-G-RPT-00020-D
Description Internal Type: Self-contained, modular, batteryinverter unit, factory mounted within lighting fixture body and compatible with ballast. Battery: Sealed, maintenance-free, nickel-cadmium type.
Source
Exhibit D2 –Part D2 – 263323 - 2.2
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
88
Parameter
Description
Source
Emergency Lighting System (Central Battery Systems)
Central battery inverters with the following features: Output distribution section. Emergency-only circuits.
Exhibit D2 - 263323
Remote monitoring provisions. As BS EN 50171
Demarcation – CBS / Self Contained.
CBS units are generally available in ratings above 800 watts. Emergency load load < 1000 VA, use self contained system. Emergency load => 1000VA 1000VA use CBS
Atkins
Standards
Comply with DIN VDE 0108 and NFPA 101.
Exhibit D2 - 263323
Input 230 Volt single phase or 400/230 Volt 3 phase . 230 Volt DC single phase output to distribution board / load. AC output to Airfield lighting and PTB only
Configuration
Exhibit D2 - 263323
CBS -Battery autonomy
Capable of sustaining full-capacity output of inverter unit for minimum of 90 minutes.
Exhibit D2 - 263323
Battery type
Maintenance free, sealed, leak-proof lead acid, gas recombination type
Exhibit D2 – 263323 –clause 2.9
Safety Luminaires
Where hazards are encountered by the occupants of the facility; facilit y; provide minimum lighting level to 10 Lux
Exhibit D2 – 263323 – 2.11D
Exit signs
Comply with EN 60598
Exhibit D2 - 263323
Apron floodlighting system installations
Emergency Lighting (Halogen lamps)
Exhibit D1 2.6.3.12
Interface to I2BS CBS Battery Battery Room Ventilation Ventilation
8.12.
The ECBS Contractor shall provide a interface to the BMS Identical to that for UPS battery room ventilation.
Exhibit D2 - 263323 Exhibit D1 section 2.5.3.5
Road Tunnel Lighting
Parameter
Description
Traffic Design Speed
70 km/h
Exhibit D - 265600
Stopping Sight Distance
110 m
Highway Design Manual
Maintenance Factor
0.7
ATKINS
Base Lighting
Fluorescent Lighting
BS 5489
Reinforcement Lighting Entrance Zone Luminance
High Pressure Sodium (SON) 1/10 to 1/15 of Ambient Luminance
ATKINS BS 5489
421-422-A000-DF-G-RPT-00020-D
Source
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
Level Minimum Luminance Level on Road Night Time Illuminance Level
8.13.
89
50 Lux
BS 5489
Not more than two times of adjacent road
BS 5489
Control Voltages
The following control voltages are applicable to MEP services for this project.
Parameter
Description
Source
LV Circuit breakers / Switchgear
Control voltage shall be 120 Volts DC
Tender – Q/A 78
MV Circuit breaker / switchgear
Control voltage shall be 125 Volts DC
Tender – Q/A 78
LV switchgear accessories
Accessory Control Power Voltage: Integrally mounted, self-powered; 230-V AC
Exhibit D – part 2
8.14. Control System Power Supply (125 V DC POWER POWER SUPPLY) Parameter
Lead Calcium in sealed clear plastic or glass containers. Battery sizing calculation shall be done by the medium voltage switchgear manufacturer
Battery Type
Charger
Battery Rack Battery Rack restraints DC Power Supply Battery Room Ventilation ( Where applicable )
8.15.
Description
Static-type silicon rectifier equipped with automatic regulation and provision for manual and automatic adjustment of charging rate. Two-step rack with electrical connections between battery cells and between rows of cells Rate battery rack, cell supports, and anchorage for seismic requirements. Identical to that for UPS battery room ventilation.
Source
Exhibit D2- section 261300, clause 2.7 Also (Tender – Q/A - 78)
Exhibit D2- section 261300, clause 2.7 Exhibit D2- section 261300, clause 2.7 Exhibit D2- section 261300, clause 2.7 Exhibit D1 section 2.5.3.5
Lighting Management System (LMS)
Refer to LMS design report ATK002-421-A000-DF-E-RPT-0001 for full information.
Parameter LMS General
421-422-A000-DF-G-RPT-00020-D
Description State of the Art system
Source Tender Addendum 1
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
Parameter LMS Scope / extent
LMS functionality [see matrix below and lighting management system design report for full details for full details]
I2BS interface
Utilities Tunnel
421-422-A000-DF-G-RPT-00020-D
90
Description Provided in every building a BACnet, LonWorks, OPC or Modbus interface to the NIU. a) Soft, intelligent intelligent switching switching b) Vacancy detection c) Daylight linking with and without dimming d) Scene dimming e) A-V intelligent intelligent interaction f) Burn hour monitoring g) Zonal power power and energy monitoring a) Lighting relay status for each individual relay. b) Lighting load (kW) for each each zone. c) Lighting consumption (kWh) for each zone. d) Zone lighting levels e) Status (healthy/fault) of LCS components Energy Saving Switching Scheme
Source D2 255000
Industry best practice and inferred from Exhibit D
D2 255000
Exhibit D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
91
Input data for the above matrix has been provided by Vision
8.16.
Raceways and Conduits
Parameter Cables in return air plenums Main and Sub-main cables (Indoor)
Description LSZH cables are to be routed on cable trays / ladderack. All Low voltage distribution and sub-distribution Cables (specified in mm2) shall be XLPE (90°C) (90°C) insulated insul ated single core copper co pper conductors fixed to cable trays / cable ladder
421-422-A000-DF-G-RPT-00020-D
Source
Exhibit D1 – 2.6.3.5
Interpreted from Exhibit D – 2.6.3.5
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
Parameter
92
Description
Source
Final Sub-circuit cables for lighting and small power
Insulated copper conductor (PVC 85 deg C) drawn in conduits/cable trays as per the specification.
Exhibit D1 -2.6.3.5
Exposed installations subject to mechanical damage.
All wiring/cables are to be routed in rigid steel conduits
Exhibit D1 – 2.6.3.10
Cable installation generally
Conceal cables in finished walls, ceilings, and floors, unless otherwise required.
Exhibit D 2 – 260519, Clause 3.3
Raceway application outdoors
Underground Conduit: Rigid heavy gauge PVC conduit concrete encased.
Exhibit D 2, 260533, Clause 3.3
Exposed, Not Subject to Physical Physical Damage: EMT .
Raceway applications – indoor
Exposed and Subject to Severe Physical Damage: IMC. Raceway locations include the following: a. Loading dock. b. Corridors used for traffic of mechanized carts, forklifts, and pallet-handling units. c. Mechanical rooms.
Exhibit D 2, 260533, Clause 3.3
Damp or Wet Locations: GRC. Raceway applications – Internal concealed wiring
Concealed in Ceilings Partitions: EMT.
Cable tray installation
Comply with recommendations in NEMA VE 2.
Cable tray type Cable tray grounding
Underground Duct type
and
Interior
Walls
and
Exhibit D2, 260533, Clause 3.3 Exhibit D2 - 260536 clause 3.1
Cable tray system design must comply with NEC Article 392, NEMA VE1. Ground cable trays according to manufacturer's written instructions. RNC; NEMA TC2, Type EPC-40-PVC rated for 90 C conductors for both in underground and above ground applications , UL 651 with matching fittings b y the same manufacturer as the conduit, complying with NEMA TC 3 and UL 514B.
Tender Q&A - 404 Exhibit D2 260536, Clause 3.3
Tender Q&A - 120
Underground Duct accessories
a) Duct Separators: Factory Fabricated rigid PVC interlocking spacers. b) Warning tape. c) Concrete Warning planks (red) 600x300x75mm.
Tender Q&A - 120
Underground conduit applications
a) Ducts for MV, LV and ELV Cables: Cables: RNC, NEMA Type EPC-40 –PVC, in concrete encased duct bank. b) Underground ducts crossing paved paths, driveways, roadways, and railroads: RNC, NEMA Type EPC-40 –PVC, encased in reinforced concrete
Tender Q&A - 120
8.17. Disturbance and Interference Parameter Lightning Protection 421-422-A000-DF-G-RPT-00020-D
Description Comply with IEC/BS EN 62305
Source Exhibit D1 – 2.6.3.13
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
Parameter
93
Description
Source
Surge Protection devices
Comply with IEC 61643
Exhibit D1 – 2.6.3.13
Separation from EMI Sources:
Comply with BICSI TDMM and TIA/EIA569-A recommendations.
Exhibit D2 : CONTROLVOLTAGE ELECTRICAL POWER CABLES 260523
EMI Filters (within Luminaires)
EMI – Luminaires
EMI – induced voltages
EMI-Screening
EMI – Cable screens EMI/RFI Filtering (MCC’s) EMI Emissions (UPS) Transient Frequency Performance (generators)_ Transient Voltage Performance ( generators)
Harmonic content of output waveform ( generators)
Standards ( general)
8.18.
Factory installed to suppress conducted electromagnetic interference as required by MIL-STD-461E. Fabricate lighting fixtures with one filter on each ballast as required. Ballasts for Low ElectromagneticE lectromagneticInterference Environments: Comply with 47 CFR 18, Ch. 1, Subpart C, for limitations on electromagnetic and radio-frequency interference for consumer equipment. Provide adequate grounding on all equipment to prevent the build-up of electromagnetic voltage potentials. Provide screening of panels, enclosures, devices, or components that emit interferences. All monitoring and control and Communication cables shall shall be screened with one end grounded. CE marked; certify compliance with IEC 61800-3 for Category C2. Comply with FCC Rules and Regulations and with 47 CFR 15 for Class A equipment. Less than 5 percent variation for 50 percent step-load increase or decrease. ( frequency recovery within 5 seconds) Not more than 10 percent variation for 50 percent step load increase or decrease (voltage recovery within 0.5 secs) At no load, harmonic content measured line to line or line to neutral shall not exceed 5 percent total and 3 percent for single harmonics. I2BS and all individual electrical equipment, devices and components shall comply with the requirements of the applicable UL/NEMA/IEEE/ANSI standards regarding general emissions.
Exhibit D2 - INTERIOR LIGHTING - 265100
Exhibit D
Exhibit D2 - (I2BS) 255000 Exhibit D2 - (I2BS) 255000 Exhibit D2 - (I2BS) 255000 Exhibit D2 – 262419; 2.7 Exhibit D2 – 263353; CLAUSE 2.2 Exhibit D2 - ENGINE GENERATORS - 263213 Exhibit D2 - ENGINE GENERATORS - 263213
Exhibit D2 - ENGINE GENERATORS - 263213
Exhibit D 2 (I2BS) 255000
Protection Ratings
Parameter IP –Ingress Protection Ratings – Components generally IP –Ingress Protection Ratings – Interior enclosures 421-422-A000-DF-G-RPT-00020-D
Description All components shall be IP 2X finger protected such that live components cannot be accidentally touched. Interior enclosures shall be a minimum of IP 31 unless specifically noted otherwise within Exhibit D.
Source Exhibit D2 – Division 25 – I2BS section. Exhibit D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
Parameter IP –Ingress Protection Ratings – Outdoor enclosures
Fungus proofing
General (for exterior Luminaires)
8.19.
94
Description Exterior enclosures shall be weather proof IP 55 unless specifically noted otherwise within Exhibit D. Permanent fungicidal treatment for switchgear interiors, transformer coils and cores, cores, overcurrent protective devices, instruments and instrument transformers and fungus inserts for cable ties etc. Select Luminaires that do not:Fail in materials or workmanship; corrode; fade, stain, perforate, erode, or chalk due to effects of weather or solar radiation within specified warranty period.
Source
Exhibit D
Tender Q&A -225, and Exhibit D2 Division 26 generally.
Exhibit D2 – Division 26 – Exterior Luminaires – clause 1.11
Basis of Design – Seismic Restraints
Parameter Seismic Standards.
Switchboards
Typical equipment to be retrained shall include the following;
Mounting and Anchorage of Surface-Mounted Electrical Equipment and Components:
Description Comply with seismic force force based on on the 1997 Uniform Building Code zone 2A Fabricate and test switchboards according to IEEE 344 to withstand seismic forces defined in Division 26 Section "Vibration and Seismic Controls for Electrical Systems." - Battery Racks, UPS & ECB’s. - Generators. - Cable Trays. - Unit substations. - Distribution boards, Panelboards & MCCs. - Conveying systems...etc. Anchor and fasten electrical items and their supports to building structural elements by the following methods described in HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS
Source Exhibit D1
Exhibit D
Exhibit D
Exhibit D2– 260529- clause 3.2. See also section 6.25.
.
Strength of support system
Steel Slotted Support Systems: Raceway and Cable Supports:
421-422-A000-DF-G-RPT-00020-D
Adequate in tension, shear, and pullout force to resist maximum loads with a minimum structural safety factor of five times the applied force Comply with MFMA-4, factoryfabricated components for field assembly. As described in NECA 1 and NECA 101.
Exhibit D 2 – 260529 -1.4
Exhibit D 2 – 260529 -2.1 Exhibit D 2 – 260529 -2.1
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
95
Parameter
Description
Source
Multiple Raceways or Cables:
Install trapeze-type supports fabricated with steel slotted or other support system, sized so capacity can be increased by at least 30 percent in future without exceeding specified design load limits Secure raceways and cables to these supports with two-bolt conduit clamps.
Exhibit D 2 – 260529 -3.1
Comply with seismic requirements defined in 6.24 and note the following Contract Document requirements. Refer also to the site-wide MEP seismic restraint report
8.20.
Identification and Labelling
Parameter
Description
Source
The following shall be provided with identification in accordance with Exhibit D2:Identification for raceways. Identification of power and control cables. Identification for conductors. Underground-line warning tape. Exhibit D2 - 260553 Warning labels and signs. Instruction signs. Equipment identification labels. Miscellaneous identification products. Colour coding for different voltage levels Comply with ANSI A13.1 for minimum size of letters for Exhibit D2 – 260553 legend, colour and requirements of Exhibit D 2 – Clause 2.2 • • •
Identification generally:
• • • • • •
Power Raceway Identification Materials Power And Control Cable Identification Materials
Equipment Identification Labels:
Locations of Underground Lines:
Warning Tape: Buried Concrete Warning planks
Comply with ANSI A13.1 for minimum size of letters for Exhibit D2 – 260553 legend, colour and and requirements of Exhibit D2 clause – Clause 2.2 2.2 On each unit of equipment, install unique designation label that is consistent with wiring diagrams, Exhibit D2 – 260553 schedules, and the Operation and Maintenance – Clause 2.2 Manual. Specific requirements as per exhibit D2 - 260553. Identify with underground-line warning tape for power, lighting, communication, and control wiring and optical fibre cable. Exhibit D2 – 260553 Use multiple tapes where width of multiple lines – Clause 2.2 installed in a common trench or concrete envelope exceeds 16 inches (400 mm) overall. Bury warning tape approximately 12 inches (300 mm) Exhibit D2 -– above all concrete-encased ducts and duct banks. 260543 – clause 3.4 Not applicable (only conduits/raceways)
421-422-A000-DF-G-RPT-00020-D
required
for
direct
buried
Exhibit D2 – 260543 60543 -3.4 -H9
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
8.21.
96
Mounting Heights
Parameter
Description
Source
Mounting heights generally
Comply with ADA Regulations 2010( Americans with Disabilities Act)
ADA - Refer note below)
Light switch plates – Plant / Technical areas
1200m to underside edge from finished floor level.
Specification D2
Light switch plates – Public / Office areas
1100m to underside edge from finished floor level.
ADA Regulations
Fused spur units / Disconnect switches
1200m to underside edge from finished floor level.
Specification D2
Handriers
1500 mm to centre of back box to finished floor level. Spur 300 mm from ceiling height height to centre of box.
Specification D2
General wall mounted Socket outlets / receptacles – Plant / Technical areas
Generally 300m to underside edgefrom finished floor level.
Specification D2
General wall mounted Socket outlets / receptacles – Public / Office areas
Generally 400m to underside (bottom edge of p late) from finished floor level.
ADA Regulations
Above counters / worktops
Generally 200mm above worktop or counter.
Atkins / ADA Regulations
Note 1: ADA – extract with respect to mounting heights The 2010 version of the ADA states the following: Forward Approach If access is by a forward approach and the controls can be accessed with a forward reach, the outlet or switch must be at least 15 inches above floor level. If the user does not need to reach over any obstruction or if the depth of the obstruction is no more than 20 inches, the maximum height is 48 inches above floor level. Should an obstruction have a depth of more than 20 inches but less than 25 inches, the maximum height is 44 inches above floor level. Parallel Approach A parallel approach is one that requires the occupant of the wheelchair to reach to his side to access the switch or outlet. The controls must be at least nine inches above floor level and no more than 54 inches above floor level. If the user must reach across an obstruction, which can be no more than 24 inches deep and 34 inches high, the maximum height of the control is 46 inches. Exceptions ADA guidelines provide for exceptions to the height requirements if the controls are not intended for normal use or if special equipment requires a different configuration. Outlets that do not receive regular, frequent use, such as those dedicated to wall clocks, are exempt from the guidelines. Receptacles for appliances such as refrigerators or kitchen ranges are al so exempt.
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
8.22.
97
Tenanted Areas – Electrical Systems
The shell and core areas (Tenanted areas) shall be provided with the following basic services with capped connections and metering systems as applicable.
Parameter
Description
Power supply to tenanted areas
Power supply for fresh air supply and exhaust systems.
Emergency Lighting
Basic Fire detection and alarm systems
Connection / Interface to BMS
Interface to I2BS
Basis Lighting
Basic General power outlets Emergency (generator) power.
Metering facilities
8.23.
Via an appropriate local isolator based on Watt per sq metre. This should be located in the nearest location in the back of house areas. From a local distribution panel/board to be provided by the tenant, if required. Basic temporary self contained emergency luminaries to be provided within the project. This will be fed from the adjacent Landlord’s distribution board. The temporary installation will be replaced by the prospective tenant at a later date. Minimum temporary fire alarm provision to be provided. This will be replaced when the fit-out works are provided by the prospective tenant at a later date. The permanent installation should be connected to a local fire alarm interface unit in the back of house areas which links to the house system. A junction box/ terminal box with relays to provided by the tenants for connection to the BMS house system ( Details to be defined ) A junction box/ terminal box with relays to provided by the tenants for connection to i2BS house system ( Details to be defined ) Basic temporary lighting utilising batten luminaries to be provided within the project. This will be fed from the adjacent Landlord’s distribution board. The temporary installation will be replaced by the prospective tenant at a later date. By the tenants Not provided (note: only a single normal supply to be provided). Local sub meter to be provided by the tenant. It should have facility to connect to the remote BMS house system for remote monitoring
Basis of Design – Aircraft Services
421-422-A000-DF-G-RPT-00020-D
Source
Atkins
Atkins
Atkins
Atkins
Atkins
Atkins
Atkins
Atkins Atkins
Atkins
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
98
400Hz Supplies All aircrafts will require 400 Hz power supply during the time parked at the gates. Low voltage power supply of 60 Hz is converted to 400 Hz via solid state converters located in the technical plantroom within each node building. 400Hz power cables connect via duct and manhole system from the converter to a pop up pits buried within apron located strategically localised to the aircrafts. Rating for each converter is 90 k VA. 2 Units for a non code F Node - 4 units for code F Node)
Socket for mobile GPU: 3 phase 60Hz 125A
Passenger boarding bridges Roof top equipment:40kVA per set Retrievers: 30 kVA Aircraft stands type of aircraft
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
99
�������� ���� � � � � � � � � � 0 / 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 � 2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 � � � � 2 2 1 2 � 2 � � � � 2 � � � � � � � � � 2 � 2 � � 2 � 1 1 � � � � � � � � � � � � � � � � � � � � � � � � � � � � 1 � 0 � 0 0 � � 0 1 0 0 0 0 0 0 0 � � � � � � � � � � � � � � � � � � � � � 1 � 0 1 1 1 2 2 � � � � � � � 2 � � � � � � � � � � � � � � � � � � � � ����� � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � �
1�.01 1�.02 1�.0� 1�.0� 1�.0� 1�.0� 1�.0� 1�.0� 1�.0� 1�.10 1�.11 1�.12 1�.1� 1�.1� 1�.1� 1�.1� 1�.1� 1�.01 1�.02 1�.0� 1�.0� 1�.0� 1�.0� 1�.0� 1�.0� 1�.0� 1�.10 1�.11 1�.12 1�.01 1�.02 1�.0� 1�.0� 1�.0� 1�.0� 1�.0� 1�.0� 1�.0� 1�.10 1�.11 1�.12 1�.1� 1�.1� 1�.1� 1�.1� 1�.1�
� � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � �
� � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � �
� � � � � �
� � � � � �
� � � � � �
� � � � � �
� � � �
� � � �
� � � �
� � � �
� � � � � � � �
� � � � � � � �
� � � � � � � � � �
� � � � � � � � � �
� � � � � � � � � �
� � � � � � � � � �
� � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � �
421-422-A000-DF-G-RPT-00020-D
� � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � �
� � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � �
� � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � �
� � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � �
� � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � �
� � � � � � �
� � � � � �
� � � � � �
� � � � � �
� � � � � �
� � � � � �
� � � � � �
� � � � � �
� � � �
� � � �
� � � �
� � � �
� � � �
� � � �
� � � �
� � � �
� � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � �
� � � � � � � � � � �
� � � � � � � � � �
� � � � � � � � � �
� � � � � � � � � �
� � � � � � � � � �
� � � � � � � � � �
� � � � � � � � � �
� � � � � � � � � �
� � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � �
� � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � �
� � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � �
� � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � �
� � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � �
� � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � �
� � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � �
� � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � �
� � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � �
� � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � �
� � � � � �
� � � � � �
� � � �
� � � �
� � � �
� � � �
� � � � � � � � � �
� � � � � � � � � �
� � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � �
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
8.24.
100
Audio Frequency Induction loop System (AFILS)
In order to provide high quality intelligible sound for the hard of hearing, audio frequency induction loop systems (AFILS) will be provided at the locations and areas as follows: -
Area
Description
VIP Departures First Class Car Park
Counter type system capable of one to one conversations at dedicated Customs, Immigration and Security desks Counter type system capable of one to one conversations at the Parking Control Kiosks
The systems provided will comply with IEC 60118-4:2006 – Induction Loop Systems for Hearing Aid Purposes.
8.25.
Grounding and Lightning Protection
The system shall be designed and installed to provide a safe and effective earthing system in accordance th with BS 7430, IEE 17 edition including Amendments 1 and applicable local regulations and to meet with the following requirements. •
•
•
•
•
Provide sufficiently sufficiently low impedance impedance path, path, which shall ensure ensure the satisfactory operation operation of protective devices under fault conditions. Retain system voltages within reasonable limits under fault fault conditions (such as lightning, switching surges or inadvertent contact with higher voltage systems), and ensure that insulation breakdown voltages are not exceeded. Limit the voltage voltage to earth on conductive conductive materials which enclose electrical electrical conductors or equipment. Ensure the operation of the primary protective devices devices when a fault occurs occurs between the high and low voltage windings of a transformer Provide an alternative path for induced current and and thereby minimize the electrical “noise” “noise” in cables.
The overall resistance of the grounding grounding system to the mass of earth shall be less than than 5.0 ohms. Clean earths shall have an earth impedance of less than 1 ohm. The LV grounding system is comprised of earth mats / rods, riser conductors; earth terminals located in plant rooms and are interconnected using copper conductors and bonding conductors from earth terminals to all electrical equipment, metallic enclosures, steel cable containment, structural steel members and steel reinforcement of the building. Grounding system for SAS-ICT shall provide a clean earth via single point of earthing as shown on drawings. Grounding system for medium voltage power supply system is comprised of earth mats / rods and shall be separated from low voltage power supply grounding within the building structure. Any interconnection will be external to the building. The earthing design including depth, size and quantity of ground shall be based on a provisional figure of 500 Ohms.m for load / DATA centres and 200 Ohms.m for all other buildings. The actual soil resistivity test results and re-calculation will be provided by the specialist sub-contractor to determine the required number of earth rods to achieve the required resistance to earth. The MEP installation contractor shall install any required number of earth rods to achieve the required resistance to earth. 421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
101
The Lightning Protection system is designed to IEC/Bs EN 62305 and to meet with the following requirements. The lightning protection system can include the following: •
•
•
•
•
Roof mounted air terminals and/or metallic tape network.. External down down conductors conductors along along building column structures structures and bonding bonding connection connection to building structure reinforcement at selected points and/or steel columns bonded to metallic roof framework act as down conductors. Bonding connections connections between down down conductors conductors and building re-bars at upper upper and lower level of the building when the re-bars are used as down conductors. Lightning ground pits consisting consisting of ground electrodes and pit covers. Disconnecting facility at lower portion of the down conductor conductor or lightning protection protection ground pits themselves for necessary periodic testing of ground el ectrodes.
•
Perimeter conductor electrically linking all lightning lightning protection ground pits together.
•
Any cross bonding conductor that may be be required required by pylon pylon installation installation contractor. contractor.
The entire lightning system earth resistance shall not exceed 10 ohms. The lightning protection system (LPS) earth pits shall be distinctively identified from grounding system earth pits while maintaining a suitable clearance allowed by the code. All LPS earth pits shall be lined by a copper ground ring conductor directly buried at a minimum depth of 600mm. The metallic enclosures of mechanical equipment and steel cable containment at roof top are cross bonded to the lightning protection system to avoid side flashing during a lightning discharge.
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
9.
LEED Compliance
421-422-A000-DF-G-RPT-00020-D
102
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
421-422-A000-DF-G-RPT-00020-D
103
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
104
LEED Compliance 9.1.
General
Refer to the Atkins LEED Action Plan (Ref: 421/422-A000-DF-G-RPT-0012-A) and LEED Coordination Matrix (Ref: 421/422-A000-DF-G-RPT-0013-A).
9.2.
Electrical
In particular, the electrical design shall comply with the following references: • • • •
• • • • • • • •
ASHRAE 90.1 – not not exceeding exceeding lighting power density density for internal space space lighting and light sources; LEED Manual – reductions in lighting power density density for external lighting and light sources; sources; IES/LEED Manual – limiting upwards facing light sources; LEED Manual Manual – Limit light pollution pollution from building and light spill form site boundary boundary (site Dialux model required); ASHRAE 90.1 – limit circuit voltage drop; ASHRAE 90.1 – Adequate external lighting controls; ASHRAE 90.1 – Zoning/Switching for internal lighting; ASHRAE 90.1 – Automatic lighting shut-off in buildings larger than 5000ft2; ASHRAE 90.1 – Provisions for tandem wiring of lamps; ASHRAE 90.1 – Exit signage watt/face limits; LEED Manual/IPMVP – sub metering (if pursuing pursuing this credit); credit); and Commissioning of lighting control systems.
9.3. •
•
• • • • • • • • • • • • • • • • • • • •
Mechanical
ASHRAE 90.1 – Building Building envelope minimum performance, performance, but superceded superceded by architectural architectural design design that has to equal or exceed the ASHRAE performance. LEED – the annual annual energy of the building shall shall be 17.5% 17.5% less than the benchmark building building when modelled under ASHRAE 90.1 2004 Section 11 ASHRAE 90.1 - Provision Provision of economizers where indicated in table 6.5.1 ASHRAE 90.1 90.1 – Minumum equipment efficiencies shall be be achieved achieved and certified. ASHRAE 90.1 90.1 and and LEED LEED EQc6.2 – Controllability Controllability of systems for thermal comfort. comfort. ASHRAE 90.1 – General control of systems. ASHRAE 90.1 – Ventilation controls for high occupancy areas ASHRAE 90.1 – Building services insultation. ASHRAE 90.1 – Ductwork airtightness ASHRAE 90.1 – O&M manuals ASHRAE 90.1 – System balancing ASHRAE 90.1 – Limitation of water temperature to public faucets ASHRAE 90.1 – Swimming pool heating and covers ASHRAE 90.1 – Minimum motor efficiency LEED WEc1.1 and 1.2 – water for irrigation LEED WEc2 – reduce water sed for sewage conveyance LEED WEc3.2 and 3.2 – reduce potable water used used for taps taps EAp3 and EAc4 – Fundamental and Enhanced Refrigerant Management LEED EQp1 and ASHRAE 62.1 62.1 – comply comply with minimum minimum ventilation requirements LEED EQc1 – Outdoor air monitoring LEED EQc5 - Indoor pollutant control LEED EQc7.1 – Thermal comfort design
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
10. Structural, Electrical, Mechanical (SEM) Opening Requirements
421-422-A000-DF-G-RPT-00020-D
105
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
421-422-A000-DF-G-RPT-00020-D
106
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
107
SEM Opening Requirements The dimensions of these opening are minimum sizes required from an MEP standpoint. All openings will have to be accepted and designed by the structural engineers, where applicable.
10.1.
Ventilation Ductwork
Description
Width of Wall/Floor Opening (mm)
Height of Wall/Length of Floor Opening (mm)
Fire Damper (FD)
Damper Width + 25mm on left & right side
Damper Height +25mm on top & bottom side
Fire & Smoke Damper
Damper Width
Damper Height
G.I. air duct with and without insulation
Duct Width + 50 mm on left & right side
Duct Height + 50 mm on top & bottom side
Fire Rated Air Duct
Internal Air Duct Width + 150 mm on left & right side
Internal Air Duct Height + 150 mm on top & bottom side
Grille/Louver at wall
Neck size of grille/louver + 25mm on left & right side
Neck size of grille/louver + 25mm top & bottom side
10.2.
Remarks
Approved dampers are mounted on either side of wall.
Chilled Water
A pair of supply and return pipes complete with insulation
Description
Width of Wall/Floor Opening (mm)
Height of Wall/Length of Floor Opening (mm)
Remarks
25mm dia.
350mm
200mm
Block work wall-Post drilled 200mm hole
32mm dia.
350mm
200mm
Block work wall-Post drilled 200mm hole
40mm dia.
400mm
200mm
50mm dia.
500mm
200mm
65mm dia.
600mm
250mm
80mm dia.
600mm
250mm
100mm dia.
700mm
300mm
150mm dia.
800mm
350mm
200mm dia.
900mm
400mm
250mm dia.
1100mm
500mm
300mm dia.
1250mm
550mm
350mm dia.
1450mm
650mm
400mm dia.
1450mm
650mm
421-422-A000-DF-G-RPT-00020-D
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
450mm dia.
1600mm
700mm
500mm dia.
1700mm
750mm
10.3.
108
Condensate
Single pipe complete with insulation
Description
Width of Wall/Floor Opening (mm)
Height of Wall/Length of Floor Opening (mm)
25mm dia.
200mm
200mm
32mm dia.
200mm
200mm
40mm dia.
200mm
200mm
50mm dia.
200mm
200mm
10.4.
Remarks
Refrigerant
A pair of liquid and gas pipes complete with insulation
Description
Width of Wall/Floor Opening (mm)
Height of Wall/Length of Floor Opening (mm)
All sizes.
300mm
150mm
10.5.
Remarks
Floor Drains
Floor drain, Roof drain or Vertical grating
Description
Width of Wall/Floor Opening (mm)
Height of Wall/Length of Floor Opening (mm)
50mm Drain
200mm
200mm
80mm Drain
200mm
200mm
100mm Drain
250mm
250mm drain
150mm Drain
350mm
350mm
200mm Drain
400mm
400mm
80mm VG
250mm
250mm + (100 Depth)
100mm VG
250mm
250mm + (100 Depth)
150mm VG
350mm
350mm + (100 Depth)
200mm VG
350mm
350mm + (100 Depth)
250mm VG
350mm
350mm + (100 Depth)
421-422-A000-DF-G-RPT-00020-D
Remarks
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
10.6.
109
Drainage and Fire Service
Single pipe
Description
Width of Wall/Floor Opening (mm)
20mm dia
Height of Wall/Length of Floor Opening (mm)
80mm dia sleeve opening
25mm dia.
100mm
100mm
32mm dia.
100mm
100mm
40mm dia.
100mm
100mm
50mm dia.
150mm
150mm
65mm dia.
150mm
150mm
80mm dia.
150mm
150mm
100mm dia.
200mm
200mm
150mm dia.
250mm
250mm
200mm dia
300mm
300mm
250mm dia
400mm
400mm
300mm dia
450mm
450mm
350mm dia
550mm
550mm
400mm dia
550mm
550mm
450mm dia
600mm
600mm
10.7.
Remarks
Drainage and Fire Service
Single pipe
Description
Width of Wall/Floor Opening (mm)
20mm dia
Height of Wall/Length of Floor Opening (mm)
80mm dia sleeve opening
25mm dia.
100mm
100mm
32mm dia.
100mm
100mm
40mm dia.
100mm
100mm
50mm dia.
150mm
150mm
65mm dia.
150mm
150mm
80mm dia.
150mm
150mm
421-422-A000-DF-G-RPT-00020-D
Remarks
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
10.8.
110
Electrical
Description
Width of Wall/Floor Opening (mm)
Height of Wall/Length of Floor Opening (mm)
Cable Tray
50 mm bet’ Tray & 100mm from edge
250mm per layer (MIN)
Cable Ladder
50 mm bet’ Ladder & 100mm from edge
300mm per layer (MIN)
Cable Trunking
50 mm bet’ Trunking & 100mm from edge
Trunking + 100mm (MIN)
Remarks
KAIA Package 421 and 422 – MEP Basis of MEP Basis of Design Report
421-422-A000-DF-G-RPT-00020-D
111
© Atkins Ltd except where stated otherwise.