Symposium on Innovation and Challenges in Asian Tunneling SICAT 2017 7 & 8 September 2017
By
Er.. Dr Er Dr.. Chew Chew Soon Soon Hoe Assistant Professor, National University of Singapore of Singapore Council Member – Member – Institute of Engineers, of Engineers, Singapore (IES) President, Singapore Chapter of ASCE of ASCE
Prof. CHEW SH (NUS)
1
FOCUS of of THIS THIS PAPER • Singapore is small in size (a small red
)
and yet see a wide variation of soil/rock of soil/rock profile.
• It ranges from “thick layer of very of very soft clays” to “fractured hard rock”, as well as “mixture of soft of soft soils and hard rock within the same tunnelling face” (so called “mixed soil” condition). • In many station construction and tunnelling works associated with MRT and HSR construction, some of these of these soil/rock profiles encountered will need some form of improvement or treatment for : (a) construction safety, (b) limiting ground movement, (c) limiting water seepage, (d) limiting ground lost, (e) Prof. CHEW SH (NU S) better construction rate and better productivity.
4
FOCUS of of THIS THIS PAPER of various traditional ground improvement • The principle of various techniques are available for various type of soil of soil profiles to satisfy various design criterion. Yet,
innovative application and/or careful modification modification are needed to implement at site for the project to be successful. of these improvement • This papers will discuss some of these techniques and their innovative implementation with reference to Singapore contact. Special reference will be paid on the proposed HSR station at Jurong East and the proposed tunnel towards Tuas. Prof. CHEW SH (NUS)
5
1. Introduction Introduction of of SG SG‐KL HSR project Singapore side 2. History and Geology of Jurong of Jurong East Site 3. Geotechnical Challenges Challenges – – Geotechnical Geotechnical Condition at Jurong East Area, Singapore Formation – including limestone cavity ‐‐ Jurong Formation – Formation – Soft clay, Peaty Soil and F1 Sand ‐‐ Kallang Formation – 4. Challenges 4. Challenges in Vertical shaft and tunneling works 5. Ground Improvement Techniques for Confronting above Challenges – Grouting, Suitable Chemical and continuous progressive soil investigation while tunneling etc 6. Conclusion Prof. CHEW SH (NUS)
6
FOCUS of of THIS THIS PAPER of various traditional ground improvement • The principle of various techniques are available for various type of soil of soil profiles to satisfy various design criterion. Yet,
innovative application and/or careful modification modification are needed to implement at site for the project to be successful. of these improvement • This papers will discuss some of these techniques and their innovative implementation with reference to Singapore contact. Special reference will be paid on the proposed HSR station at Jurong East and the proposed tunnel towards Tuas. Prof. CHEW SH (NUS)
5
1. Introduction Introduction of of SG SG‐KL HSR project Singapore side 2. History and Geology of Jurong of Jurong East Site 3. Geotechnical Challenges Challenges – – Geotechnical Geotechnical Condition at Jurong East Area, Singapore Formation – including limestone cavity ‐‐ Jurong Formation – Formation – Soft clay, Peaty Soil and F1 Sand ‐‐ Kallang Formation – 4. Challenges 4. Challenges in Vertical shaft and tunneling works 5. Ground Improvement Techniques for Confronting above Challenges – Grouting, Suitable Chemical and continuous progressive soil investigation while tunneling etc 6. Conclusion Prof. CHEW SH (NUS)
6
[Channel NewsAsia, 19 Jul 2016] A Memorandum of Understanding of Understanding (MoU) on the Singapore ‐Malaysia High‐Speed Rail (HSR) project was signed on 19 July 2016. It is expected to reduce travel time between Singapore and Kuala Lumpur to around 90 minutes. Prof. CHEW SH (NUS)
7
Key Facts Total Length
350km
Number of Stations
8
Operating Speed
300km/h
Train
10 car train
Number of Services
3
Express International
KL‐SG
Shuttle International
KL‐SG
Domestic Service
Malaysia only
Prof. CHEW SH (NUS)
8
Prof. CHEW SH (NUS)
9
This is in line with plans to transform Jurong East into Singapore's second Central Business District Prof. CHEW SH (NUS)
[The Straits Times, 6 May 2015]
10
[Straits Times, 12 May 2015]
The Jurong Country Club, which was founded in 1975, has a land lease for the site until 2035. The club completed an 18‐hole renovation in July 2012, which about $24 million. Prof. CHEW cost SH (NUS)
11
• located within the 67 hectares of plot currently occupied by the Jurong Country Club. • Land for the terminal = 13 hectares. • The remaining 54 ha will be comprehensively developed into “Jurong Lake District” ‐ include office space, hotels, retail and entertainment facilities.
Prof. CHEW SH (NUS)
12
Prof. CHEW SH (NUS)
13
Prof. CHEW SH (NUS)
14
Tunnel
15km
• Tunnel lilely below AYE • Total Length = 15km
Prof. CHEW SH (NUS)
Jurong Country Club
15
One Artist Impression – for illustration only Shopping ,Roof Garden
Carpark
Shopping Area, F & B
Drop off area, coach area, shops
Custom, ticketing etc
Arrival & Departure
Prof. CHEW SH (NUS)
19
Symposium on Innovation and Challenges in Asian Tunneling SICAT 2017 7 & 8 September 2017
2. History and Geology of Jurong East Site
Prof. CHEW SH (NUS)
20
Location with Geological Outcrop
Prof. CHEW SH (NUS)
21
Location with Geological Outcrop
Prof. CHEW SH (NUS)
22
• Before large‐scale development, the Jurong Country Club site, which is seated around Sungei Jurong, Jurong lake and Sungei Pandan area, used to occupied by mangrove forests with an outer line of mud and sand.
Prof. CHEW SH (NUS)
24
Water Channel
In the Year of 1872 Prof. CHEW SH (NUS)
25
Peng Kang
Prof. CHEW SH (NUS)
Mangrove Forest Area
In the Year of 1911
Pandan
26
1954
Prof. CHEW SH (NUS)
1972
1961
27
Golf course built Water channel shape formed
Prof. CHEW SH (NUS)
In the Year of 1975
28
Landfill to divert water channel
Prof. CHEW SH (NUS)
In the Year of 1984
29
Jurong country clubhouse was still a single storey building
Prof. CHEW SH (NUS)
In the Year of 1995
30
Jurong country clubhouse reconstructed Man‐made water feature
Prof. CHEW SH (NUS)
In the Year of 2007
31
Proposed HSR Terminal
Prof. CHEW SH (NUS)
In the Year of 2017
32
[NewLaunch101, 11 May 2015]
Prof. CHEW SH (NUS)
4040
[Straits Times, 14th May 2015]
Prof. CHEW SH (NUS)
41
[The Business Times, 13 May 2015]
Prof. CHEW SH (NUS)
43
Prof. CHEW SH (NUS)
44
Prof. CHEW SH (NUS)
47
Geology of Singapore – DSTA, 2009
Kallang Formation
Prof. CHEW SH (NUS)
Jurong Formation
48
Geology of Singapore of Singapore – – DSTA, DSTA, 2009 Kallang Formation, Alluvial member (Ka)
Jurong Formation, Tengah Facies (Jt) Ayer Chawan Facies (Jac) Queenstown Facies(Jq)
Kallang Formation
Jurong Formation
Prof. CHEW SH (NUS)
49
Central Belt Eastern Belt Prof. CHEW SH (NUS)
50
‘recent deposits’ (Scrivenor, 1924)
‘Recent Alluvium and related deposits’ (Alexander, 1950)
5 members recognized (DSTA, 2009)
• Alluvial Member (Ka): of the Kallang and Jurong • valley fills & thin veneer on the floor of the River basins vary – pebble beds through sand, muddy sand, and • deposits vary – clay to peat • Locally we call it F1 ‐‐ Loose sand and E – Estuary Peaty soil • Prof. CHEW SH (NUS)
‘Shale & Sandstone’ (Scrivenor, 1924)
Prof. CHEW SH (NUS)
52
‘Older Sedimentary Rocks’ (Alexander, 1950)
Presence of limestone (since 1987)
Jurong Formation with 7 Facies (DSTA, 2009)
53
• Ayer Chawan Facies (Jac) • Well‐bedded tuffaceous muddy sandstone & mudstone
• Tengah Facies (Jt) • muddy fine to medium grained poorly lithified sandstone • weathered material that has developed in‐ situ, possibly in marine environment
• Queenstown Facies(Jq) • consists predominantly of thinly of thinly bedded red and purple mudstone mudstone with some red to purple shale
Prof. CHEW SH (NUS)
54
Prof. CHEW SH (NUS)
55
Prof. CHEW SH (NUS)
56
Prof. CHEW SH (NUS)
59
Inferred fault Thrust fault Strike/dip Syncline Anticline
Project is located within 2 inferred faults (NE‐SW) and 1 thrust fault (NW‐SE)
Prof. CHEW SH (NUS)
Expected Fault Types Within Project Area Thrust Fault: Reserve fault in respond to compressional forces by pushing up a rock block over the other – Murai Thrust fault, DSTA, 2009 Rock around this fault line, tends to be Schist/slate and easier to break into sheet like
60
Mudstone = Schist/Slate
Tends be a weak zone and slide along the cleavage / easier to be broken into sheets
Low angle thrust, close to horizontal, but the Fault zone (highly fractured zone) will be shallower and conceptually rock quality in hanging wall will be poorer than footwall Mudstone been pressed – cleavage parallel to sub‐ parallel to bedding
Tear Fault : Fault occurring in the rocks above a low‐angle thrust fault and striking approximately at right angles to the strike of the low angle thrust fault. The rock blocks are displaced horizontally. Tear fault normally cut vertically.
Flower structure is expected to encountered.
Northeasterly trending fault in Jurong Formation are considered to be tear fault, (DSTA 2009)
Normal faults
Normal faults due to tran‐tension
What about Limestone??
Prof. CHEW SH (NUS)
68
Litho‐stratigraphy of Jurong Formation
Dark grey Limestone, Pandan Facies, fossils can be observed, NUS, near to Sport Drive, Ayer Rajah Expressway Source: Geology of Singapore, 2nd edition, DSTA, 2009
Reef ? Fossil
Colonial coral (?) in growth position but distorted
Brachiopods fossil
Site investigation borehole data from Jurong West N1 C29/C32 project
Prof. CHEW SH (NUS)
72
• Borehole depth varies from 40m to 67m
Typical soil profile from adjacent site development.
• 4 distinct layers – Fill, Organic clay (E), Residual Soil (SVI), Completely weathered Sedimentary Rock (SV)
• Possible cavities found at depth from 26.5m to 40m. Prof. CHEW SH (NUS)
73
Yung Ho Rd Proposed site Tukang Innovation Drive
Penjuru Rd
Prof. CHEW SH (NUS)
74
74
All adjacent site reference borelogs show similar soil profile: Fill > KF > JF (S‐VI, S‐V) No bedrock were found up to 67m depth.
Show possible limestone formation
Prof. CHEW SH (NUS)
75
Cavity – possible Borehole 4 Borehole 7 & 8
Prof. CHEW SH (NUS)
76
76
Cavity ‐‐ need to identify and treat them..
Prof. CHEW SH (NUS)
For Illustration only
77
Jurong Lake Garden Area Proposed site
Prof. CHEW SH (NUS)
78
N=0
12m
M 15m
N=0
M
N=0
N=0‐14
N=9
RL88.4
E 15m
F2 RL85.5
N=16
N=9‐12
N=10‐12
RL85.3 N=16
S(VI) silty sand
Prof. CHEW SH (NUS)
1.5m
79
1m bgl N=4 N=2
1m bgl FILL 3m N=2
M
15m
F2 N=5‐17 RL83.4
Prof. CHEW SH (NUS)
N=9
N=2
E 16.5m
3m
RL83.7 S(VI) Silty sand N=18‐22
1.5m
10.5m M
1m bgl
N=2‐4
15m N=3‐8
RL89.3 N=9‐16
RL83.5 N=27 N=23
S(V) N=100 Silty sand
S(VI) Silty sand
N=100
sandstone
N=5‐12
N=100
80
BH1
BH5
BH7 BH11 BH31
~300m Prof. CHEW SH (NUS)
BH1 RL104.12 1.5m
1m bgl
8181
BH5 RL104.24
BH7 RL104.4 1.5m
BH11 RL104.44 1m bgl 1.5m
BH31 RL104.59 1.5m
24m 34m 34.5m
27.5m
38.5m
RL75.6
[Cross‐Section BH1‐BH5‐BH7‐BH11‐BH31] Subsoil lies within the geological demarcation of Jurong Formation. Widely distributed with thick layers of sandy clay, sandy silt, clayey sand and silty sands soils) Prof. CHEW SH(residual (NUS)
82
BH1
BH3
2m bgl N=4‐7 8.3m
RL89.4 3.3m
2m bgl
Fill 2.4m bgl RL74.9 7.4m N=4‐11 Silty Clay with Sand 9.6m
N=4 8.8m N=6‐8
N=100
Prof. CHEW SH (NUS)
BH2
14.4m
N=4‐6
N=7‐8
Clayey Silt N=33‐47
N=59‐100
Clayey Silt with Sand N=81‐100
[Cross‐Section BH1‐BH3‐BH2]
85
2‐3 Floors Basements
E
D
C
Reference Soil Profile (SI report of Jurong East RC1)
Prof. CHEW SH (NUS)
89
Reference Soil Profile (SI report of Jurong Lake) Prof. CHEW SH (NUS)
90
Symposium on Innovation and Challenges in Asian Tunneling SICAT 2017 7 & 8 September 2017
3. Geotechnical Challenges – and Comforting Geotechnical Condition at Jurong East Area, Singapore
‐‐ Jurong Formation ‐‐ Kallang Formation – Soft clay and Peaty Soil
Prof. CHEW SH (NUS)
91
1. Highly varied in soil/rock profile at this site 2. Present of peaty soft soils long term Settlement to be considered 3. Discontinuous layers 4. Presence of cavities / underground streams 5. Mixed phase soil/rock may be encountered when tunnelling Prof. CHEW SH (NUS)
92
Highly varied soil profile
Geological Cross Section A‐A Site 5
Jurong Country Club
Site 3
0m Sandy Silt (FILL) SPT N = 9
6m 9m
Very Sot Clay (KALLANG FORMATION) SPT N = 0‐2
Firm Sandy Silt (JURONG FORMATION) SPT N = 2
26m
Sandy Silt (FILL) SPT N=16
Sandy Silt (FILL)
Sandy Silt (JURONG FORMATION S‐V) SPT N=31‐37
KALLANG FORMATION Soft Clay JURONG FORMATION Sandy Silt/Clay Cavity
Sandy Silt (JURONG FORMATION S‐V) SPT N=67 Sandy Silt (JURONG FORMATION S‐V) SPT N=100
JURONG FORMATION Sandy Silt
Cavity
30m 36m 40m 46m
Weak to moderately Strong Sandstone (JURONG FORMATION S‐III) SPT N=100
Sandy Clay (JURONG FORMATION SPT N = 3 Hard Silt (JURONG FORMATION) SPT N = 30 Hard Silt (JURONG FORMATION) SPT N = 100
Prof. CHEW SH (NUS)
0m 3.5m
8.1m 10m 15m
30m
JURONG FORMATION Sandstone
95
95
Problem with Jurong Formation Bedrock profile
Features of Jurong Formation: Limestone interbedded with mudstone, siltstone and sandstone
Steeply inclined bedding planes
●
Top of rock level is undulating – Need for closer boreholes spacing
●
Piles cannot rest on Mudstone – easily soften with water
●
Limestone karstic feature – may need ground improvement
Prof. CHEW SH (NUS)
96
Problem with Kallang Formation – Thick soft soils
Prof. CHEW SH (NUS)
99
99
Problem with Kallang Formation – Thick soft soils
FILL PEAT S(IV) JF (V. SOFT)
S(V) JF (HARD) CAVITIES
Prof. CHEW SH (NUS)
100
Problem with Kallang Formation – Soft soils
Soft soil –
‐‐ will give rise to excessive settlement issue. Peaty soils in particular ‐‐ High secondary consolidation settlement ‐‐ will continue to settle over many many years without increase in load.
Prof. CHEW SH (NUS)
101
Problem in tunneling in mixed soils condition Classification of Mixed Ground A mixed ground is usually defined as occurrence at excavation face of two or more type of soils with significantly different properties that affect TBM operation. They can be: (a) Layered or banded ground formed by rock beddings, dykes, faults or shear zones. (b) Interface ground of soil and rock, typically weathered materials above bedrock. (c) Mixed ground with locked corestones mixed with soil materials. Prof. CHEW SH (NUS)
102
Problem in tunneling in mixed soils condition Classification of Mixed Ground
Prof. CHEW SH (NUS)
103
Problem in tunneling in mixed soils condition In Jurong
Tuas Area
Prof. CHEW SH (NUS)
104
Problem in tunneling in mixed soils condition In Jurong
Tuas Area
‐‐ > Tunnelling in these varied soil profile has to be carefully planned..
Prof. CHEW SH (NUS)
105
Problem in encountering limestone
Prof. CHEW SH (NUS)
106
Symposium on Innovation and Challenges in Asian Tunneling SICAT 2017 7 & 8 September 2017
4. Challenges in vertical shaft and tunneling works
Prof. CHEW SH (NUS)
108
Next, let me summarize some
Challenges in Vertical Shaft/Station Box Vertical Shaft ‐‐ for Launching shaft and receiving shaft as well as Station Box construction
Challenges in Tunneling works
Prof. CHEW SH (NUS)
109
Challenges in Vertical Shaft/Station Box
Prof. CHEW SH (NUS)
110
Challenges in Vertical Shaft/Station Box
Prof. CHEW SH (NUS)
111
Challenges in Tunneling works
Prof. CHEW SH (NUS)
112
Challenges in Tunneling works
Prof. CHEW SH (NUS)
113
Challenges in Tunneling works
Prof. CHEW SH (NUS)
115
Challenges in Tunneling works
Prof. CHEW SH (NUS)
117
Challenges in Tunneling works
Prof. CHEW SH (NUS)
118
Challenges in Tunneling works
Prof. CHEW SH (NUS)
119
Symposium on Innovation and Challenges in Asian Tunneling SICAT 2017 7 & 8 September 2017
5. Ground Improvement needed to confront the geotechnical issues above
Prof. CHEW SH (NUS)
120
Here, We have to consider the following two structures:
• Vertical Shaft ‐‐ for Launching shaft and receiving shaft as well as Station Box construction ‐‐ Earth retaining structure needed. • Tunneling In the above mentioned difficult ground conditions. Prof. CHEW SH (NUS)
121
Vertical Shaft / Station Box Due to present of thick soft soil, and the closed proximity to neighbor high‐rise building, the retaining structure has to be rigid and strong.. Typical using Contiguous bored piles or secant pile wall or Diaphragm wall.. Need many layers of struts or internal JGPs strut.
Prof. CHEW SH (NUS)
122
Vertical Shaft / Station Box
Prof. CHEW SH (NUS)
123
Vertical Shaft / Station Box
Prof. CHEW SH (NUS)
124
Vertical Shaft / Station Box
Prof. CHEW SH (NUS)
125
Vertical Shaft / Station Box
Prof. CHEW SH (NUS)
126
Vertical Shaft / Station Box Diaphragm wall
Anchoring
Strutting
Prof. CHEW SH (NUS)
127
General Ground Improvement Methods
Ground improvement methods Not suitable here
Mechanical Modification Methods
Compaction
Hydraulic Modification
Vertical Drains
(Source: Hayward Baker) Prof. CHEW SH (NUS)
Physical & Chemical Modifications
Grouting, )DCM r e k a B d r a w y a H : e c r u o S (
(Stapelfeldt, 2006) 130
Cement treatment methods Ground Improvement Methods
131 Prof. CHEW SH (NUS)
131
Cement treatment methods Ground Improvement Methods
Jet Grouting
132SH (NUS) Prof. CHEW
Jet Grouting “Jet”
132
Compaction grouting Ground Improvement Methods Application of Compaction grouting
134SH (NUS) Prof. CHEW
134
Settlement control by Compaction grouting
Prof. CHEW SH (NUS)
135
135
Cavity filling by Compaction grouting
136SH (NUS) Prof. CHEW
136
Cavity filling by Compaction grouting
137SH (NUS) Prof. CHEW
137
Jet Grouting – Types
138SH (NUS) Prof. CHEW
138
Jet Grouting – Super Large diameter
Or other equivalent products – e.g. SuperJet etc
Minimum diameter is 4.2m and the maximum 139 Prof. CHEW SH (NUS) is 5.0m. diameter
139
Jet Grouting – Super Large diameter Need it in corners with full of underground services • SonicJet columns constructed to form into a retaining wall, for the closing of the gap.
Prof. CHEW SH (NUS)
140
Jet Grouting – Super Large diameter Need it in corners with full of underground services • SonicJet columns constructed to form into a retaining wall, for the closing of the gap.
Prof. CHEW SH (NUS)
141
Jet Grouting – Super Large diameter Need it in corners
The diameter was determined -- the minimum Prof. CHEW SH (NUS) diameter is 4.2m and the maximum diameter is 5.0m.
142
Jet Grouting – Super Large diameter
Prof. CHEW SH (NUS)
Icsge 2015 – “large diameter sonicjet pile”, Chew et al
143
Jet Grouting – Super Large diameter
Prof. CHEW SH (NUS)
Prof. CHEW SH (NUS)
Icsge 2015 – “large diameter sonicjet pile”, Chew et al
Icsge 2015 – “large diameter ”
145
144
145
Prof. CHEW SH (NUS)
Icsge 2015 – “large diameter ”
146
146
Jet Grouting – Super Large diameter
Movement at 3 m away form SonicJet < 3mm
Prof. CHEW SH (NUS)
Icsge 2015 – “large diameter ”
147
147
Tunneling in Soft Soil Ground • Tunneling in Soft soils in highly build‐up area will cause excessive ground settlement issues.. • Soft ground needed to be treated – Commonly using Jet Grouting or DCM • Sometime, grouting has to be done at the congested area with limited ground surface available.
Inclined grouting super large diameter JGPs Prof. CHEW SH (NUS)
150
Tunneling in Mixed Soil Condition Solution for Mixed Soil Tunneling Either Option A. Make TBM machine to ‘s uit ’ the ground. Convertible TBM Or Option B . Ground tr eatment (improvement) to make the ground to ‘s uit’ the machine. Prof. CHEW SH (NUS)
151
Tunneling in Mixed Soil Condition Option A. Make TBM machine to ‘suit’ the gro und.
Prof. CHEW SH (NUS)
152
Tunneling in Mixed Soil Condition Option A. Make TBM machine to ‘suit’ the gro und.
Prof. CHEW SH (NUS)
153
Tunneling in Mixed Soil Condition Option A. Make TBM machine to ‘sui t’ the gro und.
What are the Challenges ?
• Timely characterization of soil and weathered rocks as the tunnel progresses.. • Possible exploration by geophysical methods above ground or probing ahead of tunnel face • How to measure and model mixed face behaviour?
Prof. CHEW SH (NUS)
154
Tunneling in Mixed Soil Condition Option B. Ground t reatment (imp rovement) to make the groun d to ‘s uit’ the machine. • Condi tioning of t he grades S(III/IV) and S(V) materials: Use make gr ade S(III/IV) with less p ermeable Permeation Grouting and make grade S(V) more stable. Use Jet Grouting/DCM • Temporarily lowering down ground water table to reduce water pressure and water infl ow. • Watch out for sand lenses – use TAM Grouting/Chemical Grouting Prof. CHEW SH (NUS)
155
Tunneling in Mixed Soil Condition Option B. Ground t reatment (imp rovement) to make the groun d to ‘s uit’ the machine. • Tunnel face can also inj ect special flui d to “ condit ion the soil” ahead of cutting or during cutting. use of special cement+ bentonite + chemical mi x.. • Function:
-- dispersed the clay to reduce plastici ty -- harden faster -- better flow c haracteristic f or easy excavating.
Prof. CHEW SH (NUS)
156
Tunneling in Mixed Soil Condition
Prof. CHEW SH (NUS)
157