Gas and LNG Storage The Future of Modular LNG Tanks Tanks
Gas and LNG Storage | The Future of Modular LNG Tanks
1. Introduction 1.1 LNG and LNG to Power Market Overview The LNG supply market has doubled in the last decade to 301.5 MMPTA [1], and it is anticipated that the next decade will see further growth, particularly in the USA, Canada, East Africa and FLNG, increasing by 46% to 443 MMTPA by 2021 based on projects currently under construction. construction. This expansion is associated with very high and increasing LNG liquefaction costs. For those terminals coming on line by 2021 the estimated CAPEX is over $1,500/tonne. Efforts to lower the unit costs of liquefaction has seen a move away from very large scale, bespoke trains tr ains to a modular, multi-train approach, based on smaller, midscale 0.5 to 1.0 MMTPA trains, such as Energy World’s proposed plant in Sengkang, Indonesia. At the beginning of 2016 regasication capacity, or potential demand, was 757 MMTPA, including just over 10% FSRU capacity,, but from 2000 to 2015 utilization has remained capacity r emained between 30% to 40%. With With capacity only expected to expand to 810 MMTPA by 2021, utilization would need to increase to 44% to meet the estimated increase in demand. Clearly there has not been a lack of regasication capacity for the LNG supply, but some analysts have predicted an oversupply of LNG [3].
Global trade was 245 MMTPA in 2015. The average yearly growth of LNG demand since 2000 has been 6.6% pa. If this continues, demand would reach 358 MMTP MMTPA A by 2021, which would represent a utilization of 80% on the planned liquefaction capacity by 2021, without allowing for capacity taken ofine. Some recent reports [2] have suggested the so called glut in LNG has not materialized, and the numbers above could lend support to that view.
But the LNG market is changing, oil prices are lower, LNG prices are being driven down, even renegotiated, renegotiated, and buyers are seeking shorter term, more exible contracts. Despite these challenges there was 890 MMTPA of proposed new liquefaction capacity in January 2016, key regions being US, Canada, East Africa and FLNG. Clearly many of these projects will not proceed as they compete for supply contracts, but this should encourage demand side expansion. A number of factors will drive demand side expansion including conversion to cleaner cheaper fuels for power generation, to either reduce particulate pollution from coal red power stations or convert from fuel oil. In addition, those countries that seek to honor their COP21 commitments are likely to see natural gas and liqueed natural gas (LNG) as an essential transition fuel to a lower carbon future. For those countries with an established gas distribution network, large scale regasication terminals, in excess of 1.0 bcfd are appropriate, whereas archipelagoes such as the Caribbean [4], Indonesia and the Philippines need to consider a hub and spoke solution in which large scale LNG imports (7.0 MMTPA) can be distributed by smaller LNG carriers (30,000m3) directly to the power station. Some Some companies companies are now areconsidering now considering vertical integration vertical in which they provide both supply LNG asboth well as demand integration in which they of provide supply in terms of LNG to Power. According to Anatol Anatol Feygin of of LNG as well as demand in terms of LNG to Cheniere “that will be the major growth for LNG demand Power. According to Anatol Feygin Feyg in of Cheniere Chen iere going forward” and is a model it is looking to replicated “that will be theLNG major growth formaking LNGthe fuel globally [3]. Lower prices are also demand going forward” and countries is a model more attractive. However, for those thatitdoisnot have an established gas distribution the capital costs looking to replicated globallynetwork [3]. Lower LNG of receiving, storing and regasication at each power station prices are also making the t he fuel more attractive. can inhibit the development of LNG to power projects.
However, for those countries that do not have an established gas distribution network the capital costs of receiving, storing and regasication at each power station can inhibit the development of LNG to power projects.
Gas and LNG Storage | The Future of Modular LNG Tanks
Storage Tank Capacity (m3 )
Power Station Capacity(MW)
Offtaker
2018 (Conv)
2032 (New)
Total
By 2018
By 2023
Total
The Bahamas, BEC (NP)
393
320
713
70,000
90,000
160,000
The Bahamas, GBPC
240
0
240
20,000
20,000
40,000
Barbados, BL&P
60
245
305
35,000
45,000
80,000
Belize, BEL
62
40
102
5,000
15,000
20,000
1,025
1,800
2,825
370,000
460,000
830,000
Guyana, GPL
140
240
380
35,000
45,000
80,000
Haiti, EDH
238
560
798
55,000
225,000
280,000
Jamaica, JPS
621
1,320
1,941
140,000
155,000
295,000
Suriname, EBS
299
640
939
50,000
105,000
155,000
3,078
5,165
8,243
780,000
1,160,000
1,940,000
Dominican Republic, All
Total
Table 1 LNG Storage Tank Capacities for Caribbean hub and spoke scenario [4]
1.2 LNG to Power Storage Requirements For the Caribbean the IADB report [4] forecasts gas demand of 490 MMSCFD or almost 23,000m 3 of LNG per day. Assuming a hub and spoke scenario for distribution from the Dominican Republic, Table 1 summarizes the storage capacity by country required in 2018 and then expansion through to 2032 to meet the forecast demand.
For perspective a modern combined cycle gas turbine has a thermal efciency of between 45% to 55%. Therefore a 100MW power station consumes approximately 800m 3 of LNG per day or over 24,000m 3 per month. The report outlines conversion and new build forecasts for CCGT, single cycle gas turbines and reciprocating gas fueled power stations. The results highlight a key issue for development of LNG to power projects. The storage capacities at the end of each spoke are relatively small. If the capacity for the Dominican Republic is ignored the average storage capacity is approximately 50,000m3. If Belize is also ignored and a nominal tank size of 20,000m 3 is assumed, each phase of development could be based on multiples of a standard tank size. By 2018 the Caribbean market could require 20 x 20k m3 LNG storage tanks with perhaps another 40 x 20k m 3 or 20 x 40k m3 LNG tanks by 2023.
The Caribbean is only one example. Other countries, such as the Philippines and Indonesia have much greater demand for power station conversion and new build. Also, projects in Central America are being considered, but based on receiving 150,000m3 LNG carriers unloading to FSRUs or onshore LNG regasication terminals that are effectively oversized for the power station capacity.
1.3 Background to Modular LNG Tanks The authors have been involved with LNG tank design and development for almost 20 years. In that time the traditional solution for LNG storage in excess of 10,000m 3 has been a stick built 9% Ni steel single or full containment LNG storage tanks. Most LNG projects have targeted throughputs greater than 1000 MMSCFD or 7MMTPA. The storage volumes for this size of regasication or liquefaction plant have exceeded 160,000m 3. Indeed as the capacity of LNG carriers has increased up to 266,000m 3 (Q-Max) the onshore storage tank size has also increased to ensure lling or discharge can be achieved within 24 hours.
Gas and LNG Storage | The Future of Modular LNG Tanks
Figure 1 27,500 m3 ethane/ethylene/LNG carrier operated by Evergas ©
Relatively little work has been done to develop cost effective storage tank sizes for the LNG to Power market. Tank sizes greater than 160,000m3, required to receive a standard export LNG carrier, would provide 10 months of storage for a 100MW CCGT. Even for a larger power station it is clear that there is a mismatch between the storage tank and the exporting LNG carrier. Smaller carriers exist, using Type C or membrane technology, but there is a denite requirement for smaller ships to support cost effective LNG to power delivery. Ships in the range of 10,000m 3 to 30,000m3 would allow smaller marine facilities and be compatible with the required onshore storage.
Figure 2 Economies of scale- tank volume [8] or number of tanks [9]
Presentations at the Trinidad Oil and Gas Conference in 2014 [5] and Gastech 2015 [6] have highlighted the market opportunity for LNG to power and emphasized that the design and delivery of smaller LNG tanks is essential to reduce overall cost and schedule to ensure that the cost base is reasonable and the market sustainable. Another market that is expected to see signicant expansion is the LNG marine fuels business. Eagle LNG has recently completed its project in Maxville, FL, USA and Conrad Shipyard is building an LNG bunkering barge. The LNG volumes for each ship are suitable for Type C storage containers, but aggregated onshore LNG storage tank volumes in excess of 10,000m 3 are necessary.
Gas and LNG Storage | The Future of Modular LNG Tanks
1.4 The opportunities The small to midscale LNG market, supplying power stations or the marine fuels business, requires a smaller capacity LNG storage tank, in the range of 10,000m 3 to 100,000m3. The traditional solution based on 9% Ni steel technology is stick built on site. It is well known that the unit price of LNG stored reduces as the single tank size increases [8]. However economies of scale can also be achieved by production volume. The modular LNG tank seeks to reduce the unit cost for smaller LNG storage volumes by targeting offsite manufacturing productivity levels. The economies of scale are based not on the volume of a single tank but the number of units produced to achieve the required volume. A good reference case was the production of 25,000 m 3 tanks in South Carolina [9]. The estimated productivity improvements, interpolated from the stated productivity for the initial 10 tanks, are shown in Figure 2. It is noted that the rst sphere in that project experienced severe component t up and some welding issues. Since the basic tank unit can be in the range of 10k m 3 to 40k m3, larger total volumes can be achieved with multiple tanks, which can also align with project phasing goals. The following sections in this paper will provide an update on development of the modular LNG tank concept.
The key modular LNGLNG tank drivers are: The key modular tank drivers are: – –Standardize tanktank design by volume based on based site specic Standardize design by volume on seismic isolation
site specic seismic isolation
– Offsite tank pre-fabrication in parallel with foundation –construction Offsite tank pre-fabrication in parallel with
foundation construction
– Dedicated fabrication yard leading to improved productivities higher quality – Dedicated and fabrication yard leading to
improved productivities and higher quality – Offsite pre-commissioning of tank – –Reduced executed on siteof tank Offsitemanhours pre-commissioning These drivers target a “plugexecuted and play” capability – Reduced manhours on site while reducing costs and schedule compared to the stick built traditional solution.target a “plug and play” These drivers
capability while reducing costs and schedule compared to the stick built traditional solution.
Gas and LNG Storage | The Future of Modular LNG Tanks
2. Technical Development
Figure 3 Initial Modular Tank Concept [6]
2.1 Initial Concept
2.2 Current Concept
The initial concept [6] was based on either 9% Ni or membrane technology. To reduce the overall weight the modular tank provides single containment capability, thereby eliminating the concrete wall and roof. The tank was erected on a cellular concrete base which provided a robust susbstructure for subsequent transportation by water from the fabrication yard to the project site.
2.2.1 Design
At the project site the tank was supported on bearings, founded on shallow footings or piles. Trenches between the foundations allowed access for the self-propelled modular transporters (SPMTs).
After the presentations in 2014 [5] and 2015 [6], specic project opportunities focused further development.
The initial concept considered a maximum volume of 36,000m3, and this was considered to be close to the upper bound of what could, or should, be pre-fabricated and transported, before costs were negatively impacted. However, an opportunity to consider a 40,000m 3 single containment design on the US GoM coast provided the basis for the next phase of development. Technical assumptions are presented in Table 2. The updated design in shown in and Figure 5
Gas and LNG Storage | The Future of Modular LNG Tanks
Figure 4 40k m3 9%Ni Steel Single Containment Modular LNG Tank General Arrangement
Figure 5 40k m3 9%Ni Steel Single Containment Modular LNG Tank Details
Gas and LNG Storage | The Future of Modular LNG Tanks
Remark
Value
Remark
Value
Design Standards
NFPA59A, API625/620
Outer Tank
LNG Storage Tank Type
Single Containment
Material
Steel ASTM A36
Foundation Type
Piled supported, elevated
Outer tank diameter
40.000
m
Min width annular space
1.250
m
Inner Tank Material
9Ni ASTM A533 Type 1
Dome Roof
Net Capacity
40,000
m3
Material
Steel ASTM A36
Gross Capacity
42,696
m3
Spherical Radius
40.000
Inner Tank Diameter
37.500
m
Insulation Material
Height (ambient)
39.380
m
Bottom
Cellular Glass
Annular
Expanded Perlite
Suspended deck
Glass ber blanket
LNG Product
m
Seismic Design
Temperature
-170
oC
OBE (pga)
0.037
g
Density (BOG)
440
kg/m3
SSE (pga)
0.074
g
Density (max)
470
kg/m3
Wind
Latent heat of vaporization
511,000
J/kg
ASCE 7-05
63
m/s
Design boil o rate (vol)
0.05
%/day
Soils
US GoM typical
Maximum lling rate
850
m3 /hr
very soft to rm cohesive
0-30
ft
Max out pumping rate
2,250
m3 /hr
rm to sti cohesive
30-100
ft
slightly over consolidated
>100
ft
Pressures Maximum design pressure
190
mbar
Minimum design pressure
-5
mbar
Table 2 40k m3 Single Containment Tank Design Data
The key technical developments are summarized below. –
The tank is elevated above ground to provide both space for the SPMTs and also air ow to eliminate base slab heating.
–
The cellular concrete base slab is replaced with a steel grillage and concrete deck. This reduced weight which is a signicant issue for the larger tank volume.
–
9%Ni was chosen over membrane based on owner preference and concerns over permitting delays that might arise since membrane tanks have not yet been approved by FERC. This issue is discussed further in the next section 2.3.2.
–
Side wall discharge is proposed. This is consistent with NFPA 59 and if in-tank shut off valves are provided the design spill is signicantly reduced. The tank elevation also ensures that the pump does not need to be recessed below ground to achieve the minimum NPSH. Typical details were presented at LNG 12 [10] refer to Figure 6. The results of the techno-economic evaluation concluded that side wall pump discharge could reduce costs by up to $6MM for a 2 x 140k m 3 storage tanks (1998 prices). But the prize is even greater for the modular LNG tank. Not only is the pump platform signicantly reduced in size, refer to Figure 7, but the tanks can be manifolded reducing the total number of pumps. The pumps can also be located outside of the bunded areas with easy access for maintenance.
–
For larger total volumes, based on multiple units, the modular LNG tank will require individual bunded areas. This area can be optimized based on the work carried out by Coers (2005) [11].
Gas and LNG Storage | The Future of Modular LNG Tanks
Figure 6 Proposed side entry pump suction nozzle for a single integrity LNG tank [10]
Figure 7 Comparison of roof platforms with and withou t side wall discharge (courtesy Cheniere and Coers [11])
2.2.2 Execution
–
The hydrotest is not carried out at the fabrication yard. It was concluded that owners and or regulators may require proof that the 9%Ni inner tank was not damaged during transportation. Transferring the test to the project site signicantly reduces the foundation loads at the fabrication yard.
–
The inner and outer tanks are erected as complete prefabricated rings in a stepped sequence starting with the outer tank then the inner tank. A linear layout for multiple tank erection is shown in Figure 8. A heavy lift crane is used for ring installation.
–
The roof is prefabricated as one piece and lifted into position. No air lift is envisaged.
–
After roof erection the bottom insulation and inner tank bottom plate can be installed, providing weather protection to the insulation.
–
It is assumed that the fabrication yard has a bulkhead suitable for load out of 5,000 te, however temporary loading ramps can be used, founded on a piled ground beam where soil conditions are not strong enough.
Based on the design described above an execution plan was developed working with Great Basin Industries and Mammoet. The overall scope of work was divided into a number of work packages as summarized in Table 3. The following notes highlight some important issues regarding the execution plan. –
–
Fabrication yards do exist along the US GoM coast. The work to date has not undertaken a detailed evaluation of potential sites, but greeneld development is also an option. This approach will increase the initial startup costs and therefore it has been assumed an existing facility will be utilized. Fabrication facilities are not limited to the project country, indeed the modular LNG concept envisages regional fabrication yards that will support LNG storage tank in that area, thereby reducing the shipping times and costs.
Gas and LNG Storage | The Future of Modular LNG Tanks
Figure 8 Modular LNG Tank erection (courtesy of GBI and Mammoet)
Figure 9 Modular LNG Tank Transportation (courtesy of Mammoet)
Gas and LNG Storage | The Future of Modular LNG Tanks
Tank prefabrication
Tank Transportation
Project Site
Fabrication yard enabling works
Supply of all heavy lift equipment
Enabling works for receiving tank
Tank fabrication line foundations
Supply of all marine equipment
Construction of tank foundation
Material procurement
Load out at fabrication yard
Hydrotesting
Steel grillage fabrication
Tow to project site
Perlite insulation
Tank ring prefabrication
Ooad at project site
Tank hook up
Tank erection
Set down at project site on plinths
Bund construction
Tank roof prefabrication
Demobilization
Final pre-commissioning of tank
Roof Erection
Ready for cooldown
Pre-commissioning Preparation for transportation
Table 3 Execution Work Packages for 9% Ni steel single containment modular LNG tank
–
–
–
The tank will be moved on to the transportation vessel using SPMTs. Whether the SPMTs remain for the duration of the tow depends on distance. For short tows the SPMTs will travel with the tank, although the tank will be lowered on to temporary supports on the transportation vessel. For long tows (more than several days) two sets or SPMTs are require, one at the fabrication yard and one at the project site. Sea fastenings will depend on the specic tow route. For inland water way tows or sheltered water tows initial calculations indicate vessel motions will not r equire any seafastening for the inner tank. The outer tank will be fastened to the vessel deck. For longer tows or open water tows, temporary sea fastening of the inner tank will be required. Calculations have shown that the inner tank top ring stiffening and or shell thickness could be increased to cater for the inertial loading. Alternatively temporary restraints to the outer tank shell will provide resistance to the inertial loads. These restraints can be removed once the tank is installed at the project site and prior to hydrotesting.
Enabling works at the project site are relatively modest and cost effective. For load below 5,000 te temporary unloading ramps can be used. This will be founded on a piled ground beam. Temporary onshore mooring onshore points will be required for a traditional Mediterranean spread mooring pattern.
The key benets of the proposed execution plan are
1.
Tank erection is not waiting on construction of the project site tank foundation.
–
Regulatory processes normally prevent any construction on site before project permits have been secured.
–
Many LNG sites require signicant enabling works including, but not limited to, bulk earthworks before foundation construction can commence.
2.
Tank fabrication and erection can start once material is procured and delivered to the fabrication yard.
–
Many large LNG tanks have seen lead times for 9% Ni steel plate of 12 to 18 months. This is very market dependent but it has mitigated the schedule delay waiting for foundation construction and outer wall construction.
–
Material pre-ordering can reduce the lead times, and nancial commitments prior to nal regulatory approval can further reduce the schedule.
–
Tank erection commences with fabrication and erection of the steel grillage and outer tank carbon steel outer tank rings. This material is on much shorter lead times.
–
Based on an established fabrication yard, tank erection can commence well ahead of a stick built tank at the project site.
3.
Signicant, labor intensive activities are transferred from the project site to a dedicated fabrication yard.
–
Project site, stick built tanks are often remote from large resource centers, reducing productivity and or increasing labor costs.
–
Specialist welders are required for the inner 9% Ni tank which incurs a premium for remote sites. Further, in tight labor markets, the transient labor force may be difcult to secure, whereas an established fabrication yard can provide a more reliable resource.
4.
Improved productivities and quality
–
An established fabrication yard focused on tank fabrication can invest in training and equipment to increase productivities and reduce costs.
–
Prefabrication of tank parts can be done in covered areas, further increasing productivities and workmanship quality.
Gas and LNG Storage | The Future of Modular LNG Tanks
Figure 10 23m diameter tank under tow (courtesy of S mith Group)
Figure 11 Peru LNG Tank 130,000m3 with 256 Triple PendulumTM bearing (courtesy of EPS)
Figure 12 Incheon LNG Terminal founded in elastomeric bearings
Gas and LNG Storage | The Future of Modular LNG Tanks
2.3 Further Development 2.3.1 Standard Tank Design by Volume The work carried out on the 40k m 3 modular LNG tank conrmed technical feasibility and schedule advantages over a stick built solution. It also highlighted the importance of fabrication yard set up costs. When these are spread over many tanks they are not signicant, as for any pre-engineered, manufactured product. To ensure that competitive pricing is achieved from the start it was recognized that offsite pre-fabrication should not be delivered on a bespoke design basis for each project. The modular LNG tank concept would be enhanced if standard designs could be offered for any site, anywhere in the world. A standard tank design would permit the fabricator to further improve its fabrication and erection methods. Key site specic drivers for modular LNG tank design are: 1.
Soil conditions and foundation design
2.
Seismic conditions and inertial loads on tank and foundation
3.
Other environmental loading conditions (such as wind and snow loading)
4.
Temperatures and effect on insulation design
5.
Tow route, duration and storm conditions
The soil conditions will always be site specic and provided settlement criteria are satised then there is no direct impact on the modular tank design, except for seismic response. Other environmental loading conditions are not signicant drivers of tank shell and roof quantities and conservative assumptions could be made to eliminate this variation.
Preserving a standardize design is always a compromise. Perlite insulation could be maintain a constant thickness and heat leak variations addressed by changes in the roof and base insulation thicknesses. This would impact the overall height of the tank and is not necessarily the most efcient solution. Further work will be required to understand the sensitivity to this issue, but if insulation properties cannot be easily adjusted for a given thickness then conservative insulation thicknesses could be appropriate. Tank response during the tow has been investigated. It is clear that any extreme motions that would impact the basic tank design can be addressed with temporary sea fastenings and strengthening to the outside of the tank which can be ultimately removed and reused.
The key driver on tank shell design and quantities is seismic loading. This is the most signicant lateral load on the tank and in areas of moderate to high seismicity, will govern the tank geometry and shell weight. Some tank designs have adopted seismic isolation to reduce the inertial loading and shell quantities, refer to Figure 11 and Figure 12. According to Earthquake Protection Systems Inc. (EPS) [12] an 85% reduction in seismic loading was achieved, which reduced the overall cost of the tank construction. Despite the cost savings on the Peru LNG tanks, seismic isolation is not the default approach for dealing with moderate to high seismic loads. Lowering the tank aspect ratio (H:R), using inner tank straps to prevent uplift and advanced nonlinear dynamic soil structure interaction (DSSI) can be used to lower the inertial load effects on the tanks. Seismic isolation automatically elevates the tank and introduces a second foundation or base slab. This increases schedule and cost, to which the isolator cost is also added.
For the modular LNG tank these costs are already included and the elevated tank is part of the overall concept to allow for installation using SPMTs. In fact the modular LNG tank is very well suited to adopting seismic isolation because all components are included in the existing design for other reasons. Initial calculations conrm that tuning the elastomeric bearing will lower the seismic loads to those of the base design. The base design could be chosen utilizing the 33% over stress permitted under the Operating Basis Earthquake (OBE). For areas of high seismicity, friction pendulum bearings of the type provided by EPS may be required. The solution for any specic site requires a detailed analysis of the tank foundation system incorporating isolators. It is important that the foundation system (shallow or deep) is incorporated into the model, because signicant reduction in loads can arise due to non-linear response in the soil resulting in longer period response and higher levels of damping.
Gas and LNG Storage | The Future of Modular LNG Tanks
Figure 13 Effect of seismic isolation on acceleration and displacements [13]
Seismic isolation results in longer period response which is accompanied by an increase in tank transient displacements. This will impact the design of incoming pipework but experience has shown that differential movements can be accommodated in the piping design. If displacements are considered too high then viscous dampers can be added to the isolation system to reduce peak displacements. Isolation of vertical ground motions is not as common, and has not been proposed for LNG tanks to date. Vertical accelerations will increase the effective weight of the LNG and therefore the hoop stresses. In areas of high seismicity, such as the west coast of the US, peak spectral accelerations approaching 1g can occur, but careful DSSI can mitigate these effects. Long period ground motions cannot be isolated and these give rise to sloshing effects on the liquid surface. The codes are clear on the requirements for freeboard under both OBE and SSE conditions. As seismic intensity increases, the freeboard height for a given tank aspect ratio increases. To preserve a standard tank design, bafes could be installed on the underside of the roof to disrupt the sloshing wave, but this is a novel approach which might not be acceptable to owners or regulators. Alternatively, it is accepted that the tank height must be increased to address this issue. However it would require only a minor height adjustment to the standard tank design. Further work is required to understand the variations and impact that vertical and horizontal seismic accelerations have on the modular tank design, but initial results are encouraging and a standardized tank design is possible, which should translate into further reductions in cost and schedule.
2.3.2 Membrane Modular LNG Tank Membrane tanks are not new, indeed more than 100 onshore membrane tanks have been built since 1972, and over 85% of all LNG carriers utilize the membrane technology solution. Two membrane tanks are currently under construction for Energy World Corporation at Sengkang, Sulawesi, Indonesia and Pagbilao, Philippines. In addition there have been recent developments in international codes to recognize and incorporate design provisions for membrane tanks. Nevertheless, the dominant tank technology for LNG storage remains 9% Ni steel. A description of the membrane technology and comparison with above ground 9% Ni storage tanks is presented by Ezzarhouni etal (2016) [7]. Whilst this comparison was for a full integrity or full containment design there are many attributes of the system that are compatible with the objectives of the modular LNG tank and would enhance the overall concept, further lowering the costs and reducing the schedule.
Figure 14 Top view of the bottom oor showing membrane system (courtesy GTT)
Gas and LNG Storage | The Future of Modular LNG Tanks
These benets are summarized below and quantied in Section 3:
–
GTT has developed a highly modular membrane system based on pre-engineered, manufactured components. This is well aligned with the objectives of a standardized tank design.
–
There is only one structural tank and it is located on the outside. The inner 9% Ni and outer A36 shells are replaced with a 1.2mm stainless steel liner and A537 Class 2 outer shell. Total steel weight and costs reduce signicantly.
–
–
–
–
–
–
Additional benets of a membrane LNG tank are: The keydesign modular LNG tank drivers are:
–
Stainless steel and A537 Class 2 have much shorter procurement lead times and will continue to exhibit much lower price volatility. The total volume of wall insulation, based on PUF lled plywood boxes, is less. Hence, for the same overall external tank diameter and volume the corresponding tank height is reduced, further reducing the shell quantities. The tank transportation weight is lighter than the 9% Ni steel option, despite having all insulation installed prior to load out. Membrane tanks do not require hydrotesting. Leak tightness is demonstrated through the ammonia leak test. Foundation proof loading is of questionable value even for 9% Ni LNG tanks and is not required for membrane LNG tanks which use polyurethane foam (PUF) bottom insulation. No hydrotest means that the tank can leave the fabrication complete with all insulation installed and fully pre-commissioned. After installation at the project site the ammonia leak test could be rerun to satisfy the owner and regulator that no damage was sustained during the sea tow.
The design is fundamentally more robust with respect to transportation loadings. Recalling that 85% of all LNG carriers use the technology it is a well proven technology able to accommodate the strains associated with vessel motion. Further, all transportation loads can be designed into the outer tank which can easily accommodate seafastening and temporary strengthening. There is no thin walled inner shell to seafasten.
–
cycling of 9% Ni tanks is not recommended –Thermal Standardize tank design by volume based on because of the inner tank radial movements. However, site specic seismic isolation the membrane tank is not subject to the same constraints the linertank accommodates the thermal strains within –asOffsite pre-fabrication in parallel with the stainless steel corrugations. foundation construction The membrane insulation space is maintained under a
–nitrogen Dedicated yard leading to This purgefabrication which is continuously monitored. isimproved consideredproductivities a more effective and method of leak detection higher quality than temperature sensors which rely on a spill of LNG
–rather Offsite of tank thanpre-commissioning vapor.
– –The membrane liner permits the use on of sumps Reduced manhours executed site in the tank bottom thereby increasing the net useable tank volume. – These In summary, thetarget membrane modular tank takes drivers a “plug andLNG play” important steps towards the “plug andand play” objective. capability while reducing costs schedule
compared to the stick built traditional solution.
Gas and LNG Storage | The Future of Modular LNG Tanks
3. Comparison of 9% Ni Steel and Membrane Tanks Dimension
9% Ni Modular LNG Tank
Membrane Modular LNG Tank
Net LNG storage volume (m3)
40,000
Outer tank diameter (m)
40.000
Inner tank diameter (m)
37.500
38.800
Design Maximum Liquid Level (m)
38.802
36.280
Outer tank height to roof joint (m)
42.280
39.460
5.365
5.365
50.447
47.627
Roof rise (m) Overall tank height from ground (m)
Table 4 Comparison of principal dimensions for 9% Ni and membrane modular LNG tank
3.1 Quantities
3.2 Schedule and Cost
Table 4 and Figure 15 summarize the principal dimensions of the 9% Ni and membrane modular LNG tanks.
A comparison of construction schedules is shown in Table 7. The schedule is based on an EPC contract, with all design data, including soils information available at notice to proceed. The membrane tank is estimated to be ready for transportation at the same time as the 9% Ni but the overall schedule is 2 months quicker because there is no hydrotest and annular insulation to complete at the project site.
Table 5 compares the weights, and thereby the quantities, for 40k m3 9% Ni and membrane modular LNG tanks. The following notes explain the key differences. –
The outer tank shell weights are similar weight. The membrane tank is the same diameter, but is shorter because of lower wall and base insulation thicknesses. The membrane tank uses ASTM A537 Class 2 steel compared to A36 for the 9%Ni tank. This is a stronger steel and whilst more expensive per tonne, is more efcient in terms of weight and subsequent welding costs. Bottom shell thickness is 23mm compared to 16mm for the 9% Ni tank.
–
The inner tank compares the weight of ASTM A533 Type I 9% Ni steel with 1.2mm A304L stainless steel membrane. Since the membrane is not structural the weight is substantially less, saving 476te on the inner tank weight.
–
Roof insulation weights are similar, however the PUF insulation system shows a saving in weight of 336te over the perlite, resilient blanket and foam glass blocks used on the 9% Ni tank.
–
The elimination of the inner structural tank and use of PUF insulation has resulted in overall weight savings of 20%. Further the membrane transportation weight is less than the 9% Ni which excludes the perlite.
These results demonstrate that the membrane tank is a lighter design than the 9% Ni steel tank.
Costs are sensitive to local labor conditions and material costs. The costs have, therefore, been normalized and compared to a traditional stick built single containment LNG tank at 100%.
Gas and LNG Storage | The Future of Modular LNG Tanks
Figure 15 General arrangement for 9% Ni and membrane modular LNG tanks
Item
9% Ni Modular LNG Tank
Membrane Modular LNG Tank
Total (te)
Transport (te)
Total (te)
Transport (te)
Shell
504
504
544
544
Base
74
74
74
74
Roof
107
107
107
107
Shell
467
467
45
45
Base
66
66
12
12
Bottom
502
502
234
234
Wall
368
300
300
Roof
50
50
54
54
Pump Platform
350
350
350
350
Concrete
990
990
990
990
Steel
212
212
212
212
3,690
3,323
2,922
2,922
554
498
438
438
4,244
3,821
3,360
3,360
Outer Tank
Inner Tank
Insulation
Grillage
Sub-total Contingency Total
Table 5 Comparison of tank weights for 9%Ni and Membrane Modular LNG Tanks
Gas and LNG Storage | The Future of Modular LNG Tanks
9% Ni Single Containment
9% Ni Modular LNG Tank
Membrane Modular LNG Tank
100%
90%
80%
Table 6 Cost comparison of 9% Ni and Membrane Modular LNG Tank 40k m3 Activity
Months from notice to proceed 9% Ni Modular LNG Tank
Membrane Modular LNG Tank
0
0
Purchase and fabricate material
+5
+4
Grillage construction complete
+6
+5
Outer tank erection complete
+14
+10
Inner tank erection complete
+14
+16
Roof installation complete
+15
+11
Insulation complete at fab yard
+17
+17
Transport and set tank
+18
+18
Hydrotest
+19
n/a
Insulation complete at project site
+20
n/a
Final pre-commissioning
+22
+20
Ready for Cooldown
+22
+20
Notice to Proceed
Table 7 Comparison of schedules for 9% Ni and Membrane Modular LNG Tanks
Gas and LNG Storage | The Future of Modular LNG Tanks
4. Conclusions
The ongoing development work on the modular LNG tank concept has conrmed technical feasibility of both 9% Ni and membrane solutions. The membrane option will offer a more robust design for transportation and also lower costs and shorter schedules. More importantly, the concept of a cheaper and quicker prefabricated small to medium sized tank with “plug and play” capability, based on a standard design that can be installed for any site, anywhere in the world is achievable. Single containment is not appropriate for all projects and jurisdictions. Full containment options are too heavy to transport cost effectively, but initial work looking at precast wall panels and wire wound prestressing as used in the water tank industry, combined with the membrane technology should offer cost and schedule savings.
The small to mid-scale LNG and LNG to Power markets require smaller tanks. Cheaper and faster, smaller tanks will greatly assist this developing market.
Gas and LNG Storage | The Future of Modular LNG Tanks
References 1.
IGU (2016), “2016 World Energy Report”, International Gas Union
2.
Shell (2017) “Shell LNG Outlook 2017”, http://www.shell.com/ energy-and-innovation/natural-gas/liqueed-natural-gas-lng/lngoutlook.html
3.
4.
5.
Shiryaevskaya, A., Burkhardt, P., (2017), “Hottest thing in LNG is producing power as record glut looms”, Bloomberg news article 18 January 2017, https://www.bloomberg.com/news/ articles/2017-01-18/hottest-thing-in-lng-is-producing-power-asrecord-glut-looms Castalia (2015), “Natural Gas in the Caribbean – Feasibility Studies, Revised nal report (Vol I and II)”, Report to the InterAmerican Development Bank, 30 June 2015. Raine, B., (2014) “Onshore Mid-Scale LNG Terminal Storage and Modularization”, Trinidad Oil and Gas Conference, May 2014
6.
Raine, B., Powell, J., (2015), “Onshore Mid-Scale LNG Terminal Storage Modularization”, Gastech 2015, Singapore, 29 October 2015.
7.
Ezzarhouni, A., Powell, J., Elliott, S., (2016) “Why a Membrane Full Integrity Tank?” LNG 18, Perth, PO-8, 11-15 April 2016
8.
Long, B., (1998) “Bigger and Cheaper LNG Tanks? Overcoming the obstacles confronting freestanding 9% Nickel Steel Tanks up to and beyond 200,000m3”, LNG 12, Perth, 4-7 May 1998, Paper Session 5.6.
9.
Veliotis, P.T., (1977) “Solution to the Series Production of Aluminum LNG Spheres”, Society of Naval Architects and Marine Engineers Transactions, Volume 85, 1977, pp 481-504.
10. Antalffy, L. P., Aydogean, S., De la Vega, F. F., Malek, D. W., Martin, S., (1998) “Technical-economic evaluation of pumping systems for LNG storage tanks with side and top entry piping nozzles”, LNG12, Perth, 4-7 May, 1998, Poster Session B.8 11. Coers, D, (2005) “Transshipping LNG – Downscaling FieldErected Storage Tanks for Lower Prole”, 2005 (Presentation with photos provided by CB&I). 12. Peru LNG, Melchoriate, Peru, “Triple Pendulum bearings protect critical storage tanks”, Earthquake Protection Systems Inc, http:// www.earthquakeprotection.com/pdf/Peru_LNG_Dec08.pdf 13. Symans, M. D., “Seismic Protective Systems: Seismic Isolation”, FEMA, Instruction Material Complementing FEMA 451, Design Examples, Seismic Isolation 15-7-1, http://www.ce.memphis. edu/7119/PDFs/FEAM_Notes/Topic15-7-SeismicIsolationNotes. pdf
Contact us:
[email protected] Find us on Twitter and LinkedIn