Fidic Timeline (Final)
Home
Fidic Timeline (Final)
FIDIC...
Author:
Asif Hameed
84 downloads
696 Views
408KB Size
Report
DOWNLOAD .PDF
Recommend Documents
Fidic Timeline (Final)
FIDICFull description
Final Progressive Timeline Copy
fidic
fidicFull description
Robotech - Timeline
timeline
RIZAL Timeline
by ALma ToledoFull description
Saxophone Timeline
Witchblade Timeline
La relación de toda la cronología de los comics de Witchblade,
Rizal Timeline
Saxophone Timeline
FIDIC 1992
Fidic General Conditions of Contract
FIDIC Clauses
Full description
Fidic Yellow
General Conditions of Fidic Yellow
FIDIC 1987
Sarwono-Fidic
Presentasi Bapak Sarwono tentang SengketaFull description
difference between fidic 1987 & fidic 1999
Timeline of Architecture Style
Deskripsi lengkap
Warhammer Timeline 2500-
A synthesis of all sources for WFRP and WB. By Jackdays
Nike Sustainability Timeline
is the bestFull description
Timeline of Muslim History
timeline, muslim, history, sirah, islam, Allah, sejarah islam,
Warhammer Timeline 2400-2499
A synthesis of all sources for WFRP and WB. By Jackdays
Vampire the Masquerade Timeline
Rough and incomplete Timeline for oWoD vampireDescripción completa
Jose Rizal Life Timeline
Full description
7th Sea - Timeline
Timeline for 7th SeaDescrição completa
Music History Timeline
Submission of Proposed Breakdown of Lump sum Amount (28 Days) (14.1)
Sign of Contract Agreement (28 Days) (8.1)
First Estimate of Payment Submission (42 Days) (14.4) No Receiving of IPC Reply (42 Days) (16.1)
Commencement of Works (28 Days) (8.1) Submission of Performance Security (28 Days) (8.1)
Agreement on Insurances (8.1)
Issuance of IPC by Engineer (28 Days) (14.6)
IPC Request (14.6) (28 Days) (1.1.3.1) Base Date of Date Submission of Tender
Receiving of Letter of Acceptance (LOA) by Contractor (4.2)
Delay in IPC by Employer (21 Days) (16.1) Request to show Employer Financials (28 Days) (2.4)
Notification to Employer for Claim (28 Days) (20.1)
Submission of Full Detail Claim by Contractor (42 Days) (20.1) Notice of Commencement (7 Days) (8.1)
Termination by the Employer (28 Days) (15.5) After Late Dates: Contractor Receives Notice Employer Return Performance Security
Programme Submission (28 Days) (8.3)
PRE-CONSTRUCTION PHASE
Engineer Replacement (42 Days) (3.4)
Engineer’s Reply (21 Days) (4.2)
Contractor Termination of Contract (21 Days) (16.1) Suspension of Work (21 Days) (16.1) Testing (24 hrs to engr.) (7.4)
Force Majeure Awareness Notification (14 Days) (19.2) Termination Notice (Force Majeure) (84/140 Days) (19.6) Submission of Statement at Completion (84 Days) (11.3) Suspension of Work (84 Days) (8.11)
Taking Over Certificate (10.1)
Decision by DAB after Receiving Reference (84 Days) (20.4)
Floating Deliverables
Contractor request to Proceed…. Engineer’s Reply Termination by (28 Days) Contractor (8.11) (8.11)
Final Statement (56 Days) (14.11)
Issuance of T.O or Rejection (28 Days) (10.1)
Issuance of Final Payment Certificate (28 Days) (14.13)
Defect Remedial (Further Tests) (28 Days) (11.6)
Notice to other Party if Dissatisfied (28 Days) (20.4) Arbitration Initiation (56 Days) (20.5)
EXECUTION PHASE
Decided Deliverables
Payment of Remaining Half of Retention Money (14 Days) Release of (14.9) Performance Certificate (10.1)
Notice by the Contractor (14 Days) (10.1) Claim after notification (28 Days) (17.5)
FIDIC General Conditions Timeline
Payment of First Half of Retention Money (14 Days) (14.9)
Maximum Defect Liability Period (02 Years) (11.3)
OPERATION & MAINTENANCE PHASE
×
Report "Fidic Timeline (Final)"
Your name
Email
Reason
-Select Reason-
Pornographic
Defamatory
Illegal/Unlawful
Spam
Other Terms Of Service Violation
File a copyright complaint
Description
×
Sign In
Email
Password
Remember me
Forgot password?
Sign In
Our partners will collect data and use cookies for ad personalization and measurement.
Learn how we and our ad partner Google, collect and use data
.
Agree & close