DE S
PROYEK HOTEL SANTIKA PALEMBANG
DOKUMEN HITUNGAN AKHIR PAKET P.05A - PAKET INTERIOR
untuk PT. CITRA CHRISTOPHINDO MULIA
MEI 2017
PQS.02_2013: Hotel Santika - Palembang P.05A - Pekerjaan Interior
PT. Danata Estima Sarana
DAFTAR ISI
BAGIAN 01
-
PERNYATAAN HITUNGAN AKHIR
BAGIAN 02
-
DAFTAR SERTIFIKAT PEMBAYARAN YANG TERDAHULU
BAGIAN 03
-
PERNYATAAN SISA PEMBAYARAN
BAGIAN 04
-
PERNYATAAN PERSETUJUAN TERHADAP DOKUMEN HITUNGAN AKHIR
-
PERSETUJUAN PERUBAHAN PEKERJAAN.
LAMPIRAN LAMPIRAN "A"
PQS.02_2013: Hotel Santika - Palembang P.05A - Pekerjaan Interior
PT. Danata Estima Sarana
BAGIAN 01 - PERNYATAAN HITUNGAN AKHIR.
Harga Kontrak asli (tidak termasuk PPN, 10%)
Rp.
7,272,727,273
Perubahan terhadap Harga Kontrak Asli : Tambahan
Kurangan
Rp.
Rp.
Persetujuan Perubahan Pekerjaan (Hanya indikasi, Aspek legal belum dipenuhi)
315,517,710
315,517,710
(565,890,000)
(565,890,000)
(250,372,290)
Total Harga Kontrak termasuk Persetujuan Perubahan Pekerjaan
Rp.
7,022,354,983
Ditambah PPN, 10%
Rp.
702,235,498
Total Hitungan Akhir (termasuk PPN, 10%)
Rp.
7,724,590,481
Setuju untuk dan atas nama Kontraktor PT. Citra Christophindo Mulia
PT. Citra Christophindo Mulia (saksi)
-----------------------------------------------------
-----------------------------------------------------
Tanda Tangan .
Tanda Tangan saksi.
Nama
: _____________________
Nama
: _____________________
Jabatan
: Direktur
Jabatan
: _____________________
Tanggal
: _____________________
Tanggal
: _____________________
PQS.02_2013: Hotel Santika - Palembang P.05A - Pekerjaan Interior
PT. Danata Estima Sarana
BAGIAN 02 - DAFTAR SERTIFIKAT PEMBAYARAN YANG TERDAHULU.
Rujukan Pembayaran
Tanggal Terbit
Nilai Pembayaran Tercatat (Termasuk PPN, 10%)
1
Uang Muka (Dibayar Langsung)
Rp.
1,200,000,000
2
Sertifikat No. 01
Rp.
773,952,000
3
Sertifikat No. 02
Rp.
886,912,000
4
Sertifikat No. 03
Rp.
1,295,168,000
5
Sertifikat No. 04
Rp.
1,723,520,000
6
Sertifikat No. 05
Rp.
1,151,168,000
7
Sertifikat No. 06
Rp.
57,400,950
Rp.
7,088,120,951
Total pembayaran tercatat sampai dengan hari ini (termasuk PPN, 10%)
Setuju untuk dan atas nama Kontraktor
PT. Citra Christophindo Mulia
PT. Citra Christophindo Mulia (saksi)
-----------------------------------------------------
-----------------------------------------------------
Tanda Tangan .
Tanda Tangan saksi.
Nama
: _____________________
Nama
: _____________________
Jabatan
: Direktur
Jabatan
: _____________________
Tanggal
: _____________________
Tanggal
: _____________________
PQS.02_2013: Hotel Santika - Palembang P.05A - Pekerjaan Interior
PT. Danata Estima Sarana
BAGIAN 03 - PERNYATAAN SISA PEMBAYARAN
Total Hitungan Akhir, termasuk PPN, 10% (sesuai dengan Bagian 01).
Rp.
7,724,590,481
Dikurangi Total pembayaran tercatat sampai dengan hari ini (sesuai dengan Bagian 02).
Rp.
(7,088,120,951)
Total Sisa Pembayaran untuk PT. Citra Christophindo Mulia, termasuk PPN, 10%
Rp.
636,469,530
Nilai harga yang dapat dibayarkan kepada Pemborong setelah perhitungan akhir sepenuhnya ditandatangani dan dilakukan berdasarkan Syarat dan Tata Cara Pembayaran yang disepakati di dalam kontrak (Pembayaran Progress 100%)
Rp.
250,240,006
Pembayaran yang dapat dilakukan kepada Pemborong setelah masa pemeliharaan selama 12 ( dua belas ) bulan selesai (setelah Berita Acara Serah Terima Kedua ditandatangani)
Rp.
386,229,524
Terbagi atas:
Kami dengan ini menegaskan bahwa, berdasarkan Kontrak yang berlaku, kami tidak mempunyai tuntutan apapun, diluar total nilai tersebut di atas dan setuju untuk menerima Total sisa pembayaran sebesar Rp. 636.469.530 ,- ( Enam Ratus Tiga Puluh Enam Juta Empat Ratus Enam Puluh Sembilan RIbu Lima Ratus Tiga Puluh ; termasuk PPN, 10%) sebagai penyelesaian akhir sepenuhnya Kontrak Paket P.05A - Pekerjaan Interior, dan semua hal - hal yang timbul dari Kontrak ini.
Setuju untuk dan atas nama Kontraktor
PT. Citra Christophindo Mulia
PT. Citra Christophindo Mulia (saksi)
-----------------------------------------------------
-----------------------------------------------------
Tanda Tangan .
Tanda Tangan saksi.
Nama
: _____________________
Nama
: _____________________
Jabatan
: Direktur
Jabatan
: _____________________
Tanggal
: _____________________
Tanggal
: _____________________
PQS.02_2013: Hotel Santika - Palembang P.05A - Pekerjaan Interior
PT. Danata Estima Sarana
BAGIAN 04 - PERNYATAAN PERSETUJUAN TERHADAP DOKUMEN HITUNGAN AKHIR
Rujukan
: DOKUMEN KONTRAK PAKET SAP, YANG DISETUJUI DAN DITANDA TANGANI OLEH PT. GRAHA UTAMA DEVELOPMENT DAN PT. CITRA CHRISTOPHINDO MULIA.
Merujuk kepada Kontrak tersebut di atas, kami telah meneliti dengan seksama Bagian 01 - Pernyataan Hitungan Akhir, Bagian 02 - Daftar Sertifikat Pembayaran yang Terdahulu, Bagian 03 - Pernyataan Sisa Pembayaran dan mengerti sepenuhnya dan setuju dengan isi yang tercantum di sana. Setuju untuk dan atas nama Kontraktor
PT. Citra Christophindo Mulia
PT. Citra Christophindo Mulia (saksi)
-----------------------------------------------------
-----------------------------------------------------
Tanda Tangan .
Tanda Tangan saksi.
Nama
: _____________________
Nama
: _____________________
Jabatan
: Direktur
Jabatan
: _____________________
Tanggal
: _____________________
Tanggal
: _____________________
Setuju untuk dan atas nama Pemberi Tugas PT. GRAHA UTAMA DEVELOPMENT
PT. GRAHA UTAMA DEVELOPMENT (saksi)
-----------------------------------------------------
-----------------------------------------------------
Tanda Tangan
Tanda Tangan saksi
Nama
: Johannes Suriadjaja
Nama
: _____________________
Jabatan
: Direktur
Jabatan
: _____________________
Tanggal
: _____________________
Tanggal
: _____________________
PQS.11_2013 : Hotel Batiqa Cirebon P.05 - Interior Final Account
PT. Danata Estima Sarana
LAMPIRAN PERSETUJUAN PERUBAHAN PEKERJAAN
PROYEK HOTEL SANTIKA PALEMBANG DAFTAR PERSETUJUAN PERUBAHAN BIAYA PEKERJAAN INTERIOR (Kontraktor : PT. Citra Cristophindo Mulia)
NO. PPB
NO. SITE INSTRUCTION
KETERANGAN
TOTAL HARGA (Belum termasuk PPN 10%)
Date
Rp. Tambah
01/PPB/SANTIKA-PLBG/INT/IX/16
Rp. Tambah
Rp. Kurang
22 Juli 2016
SI No. 081/HS/CCM/07-16
Pekerjaan kurang Decorative Panel di Lift Lobby Lt.2
22 Juli 2016
SI No. 032/HS/CCM/03-16
Pekerjaan kurang Dekorative Panel Meeting Room di Lt.3 dan pekerjaan gawangan Pintu Meeting Room Lt. 5
16 Maret 2016
SI No. 036/HS/CCM/03-16
Pekerjaan kurang Decorative Panel Doof Shaft Koridor Guest Room Lt. 5-13
19 Maret 2016
SI No. 085/HS/CCM/07-16
Pekerjaan kurang Decorative Panel Kamar Premier A & C di Lt. 6-11
22 Juli 2016
(51,159,000)
100%
-
(51,159,000.00)
SI No. 086/HS/CCM/07-16
Pekerjaan kurang Decorative Panel Kamar Premier A & C di Lt. 12-13
22 Juli 2016
(19,453,000)
100%
-
(19,453,000.00)
(145,890,000)
031/HS/CCM/03-16
Penambahan Pintu (P7 W & P1 W) , Wallpaper di Function Room dan Meeting Room
100%
57,800,000.00
-
058/HS.CCM/03-16
Penambahan lebar Counter
18 Juni 2016
6,500,000
100%
6,500,000.00
-
061/HS.CCM/07-16
Penambahan Box Apar
23 Juni 2016
38,822,010
100%
38,822,010.00
-
062/HS.CCM/06-16
Penambahan Penutup Curtain
23 Juni 2016
3,150,000
100%
3,150,000.00
-
062/HS.CCM/07-16
Penambahan Kubus
23 Juni 2016
5,400,000
100%
5,400,000.00
-
(16,350,000)
-14748000
15 Maret 2016
088/HS/CCM/08-16
Penambahan Ambalan Kaca Toilet
04 Agustus 2016
091/HS/CCM/08-16
Pemasangan Hood Egg Corner
04 Agustus 2016
093/HS/CCM/08-16
Pemasangan Screen Motorize
08 Agustus 2016
099/HS/CCM/08-16
Pekerjaan Cove Lampu panel dinding tangga Utama
103/HS/CCM/09-16
Penambahan Panel HPL di Kolom & Balok, dan
(44,180,000)
1,893,000
1,893,000
100%
-
(16,350,000.00)
100%
-
(14,748,000.00)
100%
-
(44,180,000.00)
1,893,000.00
100%
57,800,000
-
(145,890,000.00)
111,672,010
-
-
27,125,000
100%
27,125,000.00
-
1,700,000
100%
1,700,000.00
-
1,700,000
100%
1,700,000.00
-
25 Agustus 2016
4,200,000
100%
4,200,000.00
-
26 Se pt em be r 2016
26, 410, 000
100%
26,410,000.00
-
Total Penjumlahan PPB No. 03/PPB/SANTIK A-PLBG/INT/V/17 - Rp. 04/PPB/SANTIKA-PLBG/INT/V/17
%
Pekerjaan kurang Meja Pantry, dan Kamuflase di Area Lounge - Lt.2
Total Penjumlahan PPB No. 02/PPB/SANTIK A-PLBG/INT/V/17 - Rp. 03/PPB/SANTIKA-PLBG/INT/V/17
Rp. Kurang
TOTAL HARGA PRESTASI (Belum termasuk PPN 10%)
SI No. 080/HS/CCM/07-16
Total Penjumlahan PPB No. 01/PPB/SANTIKA-PLBG/INT/IX/16 - Rp. 02/PPB/SANTIKA-PLBG/INT/V/17
Prestasi Kemajuan
106/HS/CCM/10-16
Cover Kolom dan Balok
10 Oktober 2016
107/HS/CCM/10-16
Pemasangan HPL Pintu Janitor
11 Oktober 2016
112/HS/CCM/11-16
Penambahan partisis movable, sekat partisi, triplek
114/HS/CCM/11-16
Penambahan sekat partisi 2 muka dan pintu kasir
114/HS/CCM/02-17
Penambahan Panel HPL dan Wallpaper Restauran
61,135,000
-
-
72,150,000
100%
72,150,000.00
-
1,500,000
100%
1,500,000.00
-
28 N ov emb er 2016
50, 200, 500
100%
50,200,500.00
-
28 November 2016
2,716,000
100%
2,716,000.00
-
28 N ov emb er 2016
14, 251, 200
100%
14,251,200.00
-
Total Penjumlahan PPB No. 04/PPB/SANTIK A-PLBG/INT/V/17 - Rp.
140,817,700
-
-
8
05/PPB/SANTIKA-PLBG/INT/V/17
Pekerjaan Provisional Sum
(200,000,000)
Total Penjumlahan PPB No. 05/PPB/SANTIKA-PLBG/INT/V/17 - Rp. 06/PPB/SANTIKA-PLBG/INT/V/17
Denda Keterlambatan
(220,000,000)
Total Penjumlahan PPB No. 06/PPB/SANTIKA-PLBG/INT/V/17 - Rp.
100%
-
(200,000,000.00)
100%
-
(220,000,000.00)
(200,000,000)
(220,000,000)
(145,890,000)
(200,000,000)
(620,000,000)
Ringkasan 01/PPB/SANTIKA-PLBG/INT/IX/16
1,893,000
02/PPB/SANTIKA-PLBG/INT/V/17
111,672,010
111,672,010.00
1,893,000.00
(145,890,000.00) -
03/PPB/SANTIKA-PLBG/INT/V/17
61,135,000
61,135,000.00
-
04/PPB/SANTIKA-PLBG/INT/V/17
140,817,700
140,817,700.00
-
05/PPB/SANTIKA-PLBG/INT/V/17
(200,000,000)
-
(200,000,000.00)
06/PPB/SANTIKA-PLBG/INT/V/17
(220,000,000)
-
(220,000,000.00)
Total Penambahan / Pengurangan terhadap Harga Kontrak (Tidak termasuk PPN)
3 15 ,5 17 ,7 10
( 5 65 ,8 90 ,0 00 )
1 ,8 93 ,00 0
( 14 5, 89 0, 00 0)
PPn 10%
31,551, 771
(56, 589,000)
189, 300
( 14,589, 000)
3 47 ,0 69 ,4 81
( 62 2, 47 9, 00 0)
2 ,0 82 ,30 0
( 16 0, 47 9, 00 0)
Total - Dialihkan ke Bagian 01 - Pernyataan Hitungan Akhir (dengan PPn 10%)
9
05/PPB/SANTIKA-PLBG/INT/V/17
Pekerjaan Provisional Sum
(200,000,000)
Total Penjumlahan PPB No. 05/PPB/SANTIKA-PLBG/INT/V/17 - Rp. 06/PPB/SANTIKA-PLBG/INT/V/17
Denda Keterlambatan
(220,000,000)
Total Penjumlahan PPB No. 06/PPB/SANTIKA-PLBG/INT/V/17 - Rp.
100%
-
(200,000,000.00)
100%
-
(220,000,000.00)
(200,000,000)
(220,000,000)
(145,890,000)
(200,000,000)
(620,000,000)
Ringkasan 01/PPB/SANTIKA-PLBG/INT/IX/16
1,893,000
02/PPB/SANTIKA-PLBG/INT/V/17
111,672,010
111,672,010.00
1,893,000.00
(145,890,000.00) -
03/PPB/SANTIKA-PLBG/INT/V/17
61,135,000
61,135,000.00
-
04/PPB/SANTIKA-PLBG/INT/V/17
140,817,700
140,817,700.00
-
05/PPB/SANTIKA-PLBG/INT/V/17
(200,000,000)
-
(200,000,000.00)
06/PPB/SANTIKA-PLBG/INT/V/17
(220,000,000)
-
(220,000,000.00)
Total Penambahan / Pengurangan terhadap Harga Kontrak (Tidak termasuk PPN)
3 15 ,5 17 ,7 10
( 5 65 ,8 90 ,0 00 )
1 ,8 93 ,00 0
( 14 5, 89 0, 00 0)
PPn 10%
31,551, 771
(56, 589,000)
189, 300
( 14,589, 000)
3 47 ,0 69 ,4 81
( 62 2, 47 9, 00 0)
2 ,0 82 ,30 0
( 16 0, 47 9, 00 0)
Total - Dialihkan ke Bagian 01 - Pernyataan Hitungan Akhir (dengan PPn 10%)
9
PROYEK HOTEL SANTIKA - PALEMBANG PERSETUJUAN PERUBAHAN BIAYA
Kontrak/SPK Ref No.
010/SPK/GUD/Kontraktor Interior/XI/2015 tanggal 18 November 2105
Persetujuan Perubahan Pekerjaan No.
02/PPB/SANTIKA-PLBG/INT/V/17
Tanggal
09 Mei 2017
Instruksi Lapangan No.
031/HS/CCM/03-16 - 15 Maret 2016
Instruksi Lapangan No.
058/HS.CCM/03-16 - 18 Juni 2016
Instruksi Lapangan No.
061/HS.CCM/07-16 - 23 Juni 2016
Instruksi Lapangan No.
062/HS.CCM/06-16 - 23 Juni 2016
Instruksi Lapangan No.
062/HS.CCM/07-16 - 23 Juni 2016
Pekerjaan Tambah Kurang 1 SI No. 031/HS/CCM/03-16 - 15 Maret 2016 Penambahan Pintu (P7 W & P1 W) , Wallpaper di Function Room dan Meeting Room
Rp.
57,800,000
2 SI No. 058/HS.CCM/03-16 - 18 Juni 2016 Penambahan lebar Counter
Rp.
6,500,000
Rp.
38,822,010
3 SI No. 061/HS.CCM/07-16 - 23 Juni 2016 Penambahan Box Apar
PROYEK HOTEL SANTIKA - PALEMBANG PERSETUJUAN PERUBAHAN BIAYA
Kontrak/SPK Ref No.
010/SPK/GUD/Kontraktor Interior/XI/2015 tanggal 18 November 2105
Persetujuan Perubahan Pekerjaan No.
02/PPB/SANTIKA-PLBG/INT/V/17
Tanggal
09 Mei 2017
Instruksi Lapangan No.
031/HS/CCM/03-16 - 15 Maret 2016
Instruksi Lapangan No.
058/HS.CCM/03-16 - 18 Juni 2016
Instruksi Lapangan No.
061/HS.CCM/07-16 - 23 Juni 2016
Instruksi Lapangan No.
062/HS.CCM/06-16 - 23 Juni 2016
Instruksi Lapangan No.
062/HS.CCM/07-16 - 23 Juni 2016
Pekerjaan Tambah Kurang 1 SI No. 031/HS/CCM/03-16 - 15 Maret 2016 Penambahan Pintu (P7 W & P1 W) , Wallpaper di Function Room dan Meeting Room
Rp.
57,800,000
2 SI No. 058/HS.CCM/03-16 - 18 Juni 2016 Penambahan lebar Counter
Rp.
6,500,000
Rp.
38,822,010
4 SI No. 062/HS.CCM/06-16 - 23 Juni 2016 Penambahan Penutup Curtain
Rp.
3,150,000
5 SI No. 062/HS.CCM/07-16 - 23 Juni 2016 Penambahan Kubus
Rp.
5,400,000
3 SI No. 061/HS.CCM/07-16 - 23 Juni 2016 Penambahan Box Apar
+ Total Penambahan terhadap Harga Kontrak (Tidak termasuk PPN)
Rp.
111,672,010
Rp.
111,672,010
Dampak terhadap biaya Perubahan Terhadap Nilai Kontrak (Tidak termasuk PPN) Dampak Terhadap Rencana Dampak Terhadap Rencana Awal
Hari Kalender + (xx hari)
Catatan :
PPB-02 / 1
Pemberi Tugas PT. Graha Utama Development
Tanggal : Menyetujui PT. Citra Christophido Mulia (Kontraktor)
Direktur Tanggal :
Mengetahui(Aspek Mutu)
Mengetahui(Aspek Biaya)
PT. Dinamika Teknik Selaras (Manajemen Kontruksi)
PT. Danata Estima Sarana (Quantity Surveyor)
Tanggal :
Dhaya Parna Direktur Utama Tanggal :
PPB-02 / 2
PROYEK HOTEL SANTIKA - PALEMBANG PERSETUJUAN PERUBAHAN BIAYA
Kontrak/SPK Ref No.
010/SPK/GUD/Kontraktor Interior/XI/2015 tanggal 18 November 2105
Persetujuan Perubahan Pekerjaan No.
03/PPB/SANTIKA-PLBG/INT/V/17
Tanggal
09 Mei 2017
Instruksi Lapangan No.
088/HS/CCM/08-16 - 04 Agustus 2016
Instruksi Lapangan No.
091/HS/CCM/08-16 - 04 Agustus 2016
Instruksi Lapangan No.
093/HS/CCM/08-16 - 08 Agustus 2016
Instruksi Lapangan No.
099/HS/CCM/08-16 - 25 Agustus 2016
Instruksi Lapangan No.
103/HS/CCM/09-16 - 26 September 2016
Pekerjaan Tambah Kurang 1 SI No. 088/HS/CCM/08-16 - 04 Agustus 2016 Penambahan Ambalan Kaca Toilet
Rp.
27,125,000
2 SI No. 091/HS/CCM/08-16 - 04 Agustus 2016 Pemasangan Hood Egg Corner
Rp.
1,700,000
Rp.
1,700,000
4 SI No. 099/HS/CCM/08-16 - 25 Agustus 2016 Pekerjaan Cove Lampu panel dinding tangga Utama
Rp.
4,200,000
5 SI No. 103/HS/CCM/09-16 - 26 September 2016 Penambahan Panel HPL di Kolom & Balok, dan Planter Box
Rp.
26,410,000
3 SI No. 093/HS/CCM/08-16 - 08 Agustus 2016 Pemasangan Screen Motorize
+ Total Penambahan terhadap Harga Kontrak (Tidak termasuk PPN)
Rp.
61,135,000
Rp.
61,135,000
Dampak terhadap biaya Perubahan Terhadap Nilai Kontrak (Tidak termasuk PPN) Dampak Terhadap Rencana Dampak Terhadap Rencana Awal
Hari Kalender + (xx hari)
Catatan :
PPB-03 / 1
Pemberi Tugas PT. Graha Utama Development
Tanggal : Menyetujui PT. Citra Christophido Mulia (Kontraktor)
Direktur Tanggal :
Mengetahui(Aspek Mutu)
Mengetahui(Aspek Biaya)
PT. Dinamika Teknik Selaras (Manajemen Kontruksi)
PT. Danata Estima Sarana (Quantity Surveyor)
Tanggal :
Dhaya Parna Direktur Utama Tanggal :
PPB-03 / 2
PROYEK HOTEL SANTIKA - PALEMBANG PERSETUJUAN PERUBAHAN BIAYA
Kontrak/SPK Ref No.
010/SPK/GUD/Kontraktor Interior/XI/2015 tanggal 18 November 2105
Persetujuan Perubahan Pekerjaan No.
04/PPB/SANTIKA-PLBG/INT/V/17
Tanggal
09 Mei 2017
Instruksi Lapangan No.
106/HS/CCM/10-16 - 10 Oktober 2016
Instruksi Lapangan No.
107/HS/CCM/10-16 - 11 Oktober 2016
Instruksi Lapangan No.
112/HS/CCM/11-16 - 28 November 2016
Instruksi Lapangan No.
114/HS/CCM/11-16 - 28 November 2016
Instruksi Lapangan No.
114/HS/CCM/02-17 - 28 November 2016
Pekerjaan Tambah Kurang 1 SI No. 106/HS/CCM/10-16 - 10 Oktober 2016 Cover Kolom dan Balok
Rp.
72,150,000
2 SI No. 107/HS/CCM/10-16 - 11 Oktober 2016 Pemasangan HPL Pintu Janitor
Rp.
1,500,000
Rp.
50,200,500
4 SI No. 114/HS/CCM/11-16 - 28 November 2016 Penambahan sekat partisi 2 muka dan pintu kasir
Rp.
2,716,000
5 SI No. 114/HS/CCM/02-17 - 28 November 2016 Penambahan Panel HPL dan Wallpaper Restauran
Rp.
14,251,200
3 SI No. 112/HS/CCM/11-16 - 28 November 2016 Penambahan partisis movable, sekat partisi, triplek pada ceiling dan bongkar partisi
+ Total Penambahan terhadap Harga Kontrak (Tidak termasuk PPN)
Rp.
140,817,700
Rp.
140,817,700
Dampak terhadap biaya Perubahan Terhadap Nilai Kontrak (Tidak termasuk PPN) Dampak Terhadap Rencana Dampak Terhadap Rencana Awal
Hari Kalender + (xx hari)
Catatan :
PPB-04 / 1
Pemberi Tugas PT. Graha Utama Development
Tanggal : Menyetujui PT. Citra Christophido Mulia (Kontraktor)
Direktur Tanggal :
Mengetahui(Aspek Mutu)
Mengetahui(Aspek Biaya)
PT. Dinamika Teknik Selaras (Manajemen Kontruksi)
PT. Danata Estima Sarana (Quantity Surveyor)
Tanggal :
Dhaya Parna Direktur Utama Tanggal :
PPB-04 / 2
PROYEK HOTEL SANTIKA - PALEMBANG PERSETUJUAN PERUBAHAN BIAYA
Kontrak/SPK Ref No.
010/SPK/GUD/Kontraktor Interior/XI/2015 tanggal 18 November 2105
Persetujuan Perubahan Pekerjaan No.
05/PPB/SANTIKA-PLBG/INT/V/17
Tanggal
09 Mei 2017
Instruksi Lapangan No.
Pekerjaan Tambah Kurang 1 SI No. ____ Pekerjaan Provisional Sum
Rp.
(200,000,000) +
Total Penambahan terhadap Harga Kontrak (Tidak termasuk PPN)
Rp.
(200,000,000)
Rp.
(200,000,000)
Dampak terhadap biaya Perubahan Terhadap Nilai Kontrak (Tidak termasuk PPN) Dampak Terhadap Rencana Dampak Terhadap Rencana Awal
Hari Kalender + (xx hari)
Catatan :
PPB-05 / 1
Pemberi Tugas PT. Graha Utama Development
Tanggal : Menyetujui PT. Citra Christophido Mulia (Kontraktor)
Direktur Tanggal :
Mengetahui(Aspek Mutu)
Mengetahui(Aspek Biaya)
PT. Dinamika Teknik Selaras (Manajemen Kontruksi)
PT. Danata Estima Sarana (Quantity Surveyor)
Tanggal :
Dhaya Parna Direktur Utama Tanggal :
PPB-05 / 2
PROYEK HOTEL SANTIKA - PALEMBANG PERSETUJUAN PERUBAHAN BIAYA
Kontrak/SPK Ref No.
010/SPK/GUD/Kontraktor Interior/XI/2015 tanggal 18 November 2105
Persetujuan Perubahan Pekerjaan No.
06/PPB/SANTIKA-PLBG/INT/V/17
Tanggal
09 Mei 2017
Instruksi Lapangan No.
Pekerjaan Tambah Kurang 1 SI No. ___________ Denda Ketelambatan
Rp.
(220,000,000) +
Total Penambahan terhadap Harga Kontrak (Tidak termasuk PPN)
Rp.
(220,000,000)
Rp.
(220,000,000)
Dampak terhadap biaya Perubahan Terhadap Nilai Kontrak (Tidak termasuk PPN) Dampak Terhadap Rencana Dampak Terhadap Rencana Awal
Hari Kalender + (xx hari)
Catatan :
Pemberi Tugas PT. Graha Utama Development
Tanggal : Menyetujui PT. Citra Christophido Mulia (Kontraktor)
Direktur Tanggal :
Mengetahui(Aspek Mutu)
Mengetahui(Aspek Biaya)
PT. Dinamika Teknik Selaras (Manajemen Kontruksi)
PT. Danata Estima Sarana (Quantity Surveyor)
Tanggal :
Dhaya Parna Direktur Utama Tanggal :
PPB-06 / 1