Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
CTJV
OCT 2007
Mott MacDonald 1 Atlantic Quay Broomielaw Glasgow G2 8JB UK Tel: 44 (0)141 222 4500 Fax: 44 (0)141 221 8083
221661/02/B - OCT 2007/ P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Mott MacDonald CTJV
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
Mott MacDonald CTJV
List of Contents
Page
Chapters and Appendices 1 Introduction
1-1
2 Model Description and Modelling Methodology
2-1
2.1
Introduction
2-1
2.2
ETAP Software Package
2-1
2.3
System model Data 2.3.1 System Earthing 2.3.2 System Operation
2-2 2-2 2-2
3 Relay Setting Results and Discussion
3-1
3.1
Introduction
3-1
3.2
Relay Setting and Co-ordination Studies 3.2.1 Fault current matrix for relay settings 3.2.2 Guidelines for relay settings for 51, 50, 51N and 51G protection function 3.2.3 Guidelines for relay setting for 27 protection function 3.2.4 Guidelines for relay setting for 59 protection function 3.2.5 Guideline for relay setting for 49 protection function 3.2.6 Guidelines for relay setting for 46 protection function 3.2.7 Guidelines for relay setting for 66 protection function 3.2.8 Guidelines for relay setting for 37 protection function 3.2.9 Relay setting for 87 protection function / Interface with Kahramaa 3.2.10 Setting of 25 function for ATS at 33 kV and 6.6 kV levels 3.2.11 Over current protection for the LV systems
3-1 3-1 3-4 3-6 3-8 3-9 3-11 3-12 3-12 3-13 3-25 3-26
Appendix - A: Relay setting schedules
A1
A-1: LV relays setting schedule
A2
A-2: HV feeders relay setting schedule
A20
A-3: Interface with Kahramaa - Schedule for 87L and 87T protection
A25
A-3: 33/6.6 kV and 6.6/0.415 kV transformer relay setting schedule
A29
A-4: MV motor relay setting schedule
A33
Appendix - B: TCC for relay co-ordination
B1
i 221661/02/B - OCT 2007/i of i P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
Table 1-1: Main protection functions set and relay used for the protection Table 3-1: Fault levels at 132 kV main switchboard of the Kahramaa substation Table 3-2: Current matrix for various ratings of transformer Table 3-3: Fault current matrix for over current relay setting Table 3-4: Permissible time delay for over current relay co-ordination Table 3-5: Guideline for relay setting for under voltage protection Table 3-6: Guideline for relay setting for over-voltage protection Table 3-7: Setting group for REM 543 relay for thermal over load protection Table 3-8: Time constant – heating; Data assumed if not available Table 3-9: Setting of 87L protection for 33 kV feeders from SB-27101 A/B Table 3-10: Setting group for REF 542+ relay for 87T protection Table 3-11: Setting of 87M protection for MV BOG compressors Table 3-12: Direct on line starters with MCCB and INSUM-2, load up to 45kW Table 3-13: Direct on line starters with MCCB and INSUM-2, load more than 45kW
Mott MacDonald CTJV
1-1 3-1 3-2 3-3 3-4 3-6 3-8 3-9 3-10 3-14 3-21 3-24 3-27 3-28
Figure 3-1: Sample circuit diagram for relay setting guideline 3-4 Figure 3-2: Setting of 87L protection for 33 kV out going feeders from SB-27101 A/B on the relay characteristic 3-15 Figure 3-3: Representation of 87L protection for 132 kV cable 3-16 Figure 3-4: Representation of 87T protection for TR-27101 A/B 3-19 Figure 3-5: Characteristic for the differential protection of REF 542 + 3-21 Figure 3-6: Three-phase stabilized differential protection for motors 3-23
ii 221661/02/B - OCT 2007/ii of i P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
Mott MacDonald CTJV
Summary and Conclusion This report describes the results of the relay co-ordination studies performed for the QGX-CLP development Project. In this report, relay setting and co-ordination for QGX-CLP electrical distribution system (SS-2702 and SS-2701) are carried out for all voltage levels from 132 kV to 0.415 kV. Setting of protections functions such as 87L, 87T, 87M, 81U, 27, 59, 49, 46, 47, 66, 50, 51, 50N, 51N, 51G etc. (as defined in the relaying scheme documents) are covered. Down stream over-current relays are co-ordinated with the up stream relays. At 0.415 kV level, MCCBs are co-ordinated with the up-stream over-current relays. At all voltage levels the proper co-ordination of the relays and setting of various protection functions are ensured for both minimum and maximum fault currents. Time current characteristics (TCC) of the over-current relays at different voltage levels are presented in the report. TCCs shows that the protection setting adopted are in line with the selective, sensitive and fast operation of relays. Siemens relays are mainly used in the HV system at 132 kV level while ABB relays are mainly used in 33kV and below voltage levels. Relay setting schedules are presented in Appendix - A and TCCs of the over-current protection are presented in Appendix - B.
221661/02/B - OCT 2007/ P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
1
Mott MacDonald CTJV
Introduction
This report describes the relay co-ordination studies performed by Mott MacDonald on behalf of Chiyoda Technip Joint Venture (CTJV) for the QGX-CLP (Qatar Gas II – Common Lean LNG Project) development project. The electrical distribution system of the CLP network comprises of the substation SS-2701, SS-2702 and SS-2703. The substation SS-2701 is having option of power supply either from QGX system or from the SS-2702. The substation SS-2702 (Lean LNG storage tank substation-2) is connected to the Kahramaa substation through two 132 kV underground cables and the substation SS-2703 is supplied from SS-2701. For the CLP system study the substation SS-2701 is considered to be supplied from the substation SS-2702. In this report, integrated relay setting of various protection functions and co-ordination of various relays are presented. Main protection functions for which the relay settings are carried out are shown in Table 1-1.
S.No.
ANSI Number
Protection Name
Relay Type used
87-T & 87-N
Transformer differential
7UT612, REF542+
87-L
Line differential
7SD53, SOLKOR-N, REL 561
87-M
Motor differential
REM 543
2
49
Motor Thermal
REM 543
3
27
Under voltage
REF 542+, REM 534
4
59
Over voltage
REF 542+, REM 543
5
46
Unbalance current
REM 543
6
47
Phase sequence voltage
REM 543
7
66
Max. motor starts
REM 543
8
37
Under power
REM 543
9
51, 51N, 51G
Over current / EF
REF 542+, REM 543
10
50, 50N
Instantaneous O/C and E/F
REF 542+, REM 543
11
81U
Under frequency
REF 542+
1
Table 1-1: Main protection functions set and relay used for the protection
1-1 221661/02/B - 05/10/2007 /1-1 of 1 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
2
Mott MacDonald CTJV
Model Description and Modelling Methodology
2.1
Introduction
This section describes the electrical distribution system for the QGX-CLP development project, the modelling methodology adopted and the data used in performing the electrical system studies. Included within this section is a description of the following: •
Software package
•
EATP model development
The ETAP representation of the QGX-CLP electrical network is presented in electrical system studies report1 already submitted.
2.2
ETAP Software Package
Fault level and relay co-ordination studies are carried out using version 5.0.3 of ETAP PowerStation, developed by Operation Technology, Incorporated. This package uses standard models of the main components in the power system in combination with numerical techniques to solve the various electrical and mechanical equations describing the system. The system model and parameters are entered into the model using the ETAP network schematic capture facility. The main components represented in the ETAP model are as follows: Synchronous machines: A standard two-axis equivalent circuit model is used to represent synchronous machines. This model includes sub-transient, transient and synchronous reactances and their associated time constants and allows full dynamic modelling of transient events. Stator and rotor saturation are accounted for, as are the alternator and prime mover inertia. Asynchronous (induction) machines: These elements are modelled based on their per-phase equivalent circuit parameters. The equivalent circuit data is manipulated to create a two axis transient model that also includes the motor and driven load inertia and the load torque-slip curve. The dynamic simulation therefore takes account of the motor and load dynamics. The model also accounts for the momentary and decaying current contribution that asynchronous machines will make into a system short circuit. Transformers: These are modelled as equivalent pi impedance network. The zero sequence impedance, and winding connections are included in the model. This is used to assemble the correct zero sequence network representation when calculating earth fault currents. Cables: Cables (and transmission lines) are modelled by a circuit of fixed positive sequence impedance and shunt susceptance. A pi impedance network is used to represent the circuit with half of the total circuit capacitance connected as a shunt element at each end of the circuit.
1
Electrical system studies for QGX-CLP development protect; Load flow, short circuit and motor starting studies – Rev A; Mar 2007, report submitted by Mott MacDonald Ltd.
2-1 221661/02/B - OCT 2007/2-1 of 1 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
Mott MacDonald CTJV
Controllers: The prime mover turbines and voltage regulator/exciter system associated with synchronous machines are included as transfer function block diagrams and associated gains and time constants. Relays: Over current relay specific to manufacturer and model are available with all setting ranges and typical ANSI and IEC curves for inverse, very inverse and other characteristics. By selecting one particular setting of current and time delay the same can be projected on TCC (on loglog scale) to view the possible operation time for various currents.
2.3
System model Data
The ETAP single line representation of the QGX electrical system is based on CTJV General Single Line Diagram for the Electrical System2 . The system model3 used for system study is used for the relay co-ordination.
2.3.1
System Earthing
The QGX electrical system earth fault levels are generally limited by neutral earthing resistors that are organised as follows: •
132 kV
- Solidly earthed
•
33 kV
- limited to 400 A by each transformer NER
•
11 kV
- limited to 400 A by unit transformer NER (unit fed compressor motors)
•
6.6 kV
- limited to 400 A by each transformer NER;
•
0.415 kV
- limited to 10 A by each transformer NER.
2.3.2
System Operation
Various transformer configurations were considered in the studies for calculation of the minimum and the maximum fault current calculation. The following definitions are used throughout the report when referring to transformer connections: •
Dual transformers – each switchboard section is fed in isolation by its associated transformers. This is the normal operating configuration for the system.
•
Single transformers – two or more switchboard sections are fed via a single transformer. This is to consider a case where there is a single transformer outage and its load is taken up by another unit. For a switchboard fed by three or more transformers, it is not expected that one unit would be rated to supply the whole load.
2
CTJV, QATARGAS II DEVELOPMENT PROJECT General Single Line Diagram, Dwg. Nº: QGX/20/91/EL/DR/SD/001 Rev C2 3
Electrical system study for QGX-CLP development project Mar-2007 (Study report for load flow, short circuit, motor starting) submitted by Mott MacDonald Ltd.
2-2 221661/02/B - OCT 2007/2-2 of 2 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
3
Mott MacDonald CTJV
Relay Setting Results and Discussion
3.1
Introduction
Methodology used for relay setting and co-ordination of relays are presented in the various sub-section below. Based on that relay setting schedules and TCC of the over current relays are prepared.
3.2
Relay Setting and Co-ordination Studies
The relay setting and co-ordination studies are carried out for various relays and protection functions presented in the Table 1-1. Before carrying out the relay setting, a fault current matrix for various voltage levels is prepared. The current matrix gives important information for the minimum and maximum fault currents seen by each relay at various locations in the system, based on which proper discriminated, sensitive and coordinated protection can be achieved. In order to achieve the uniform relay setting for the feeders having similar rating of transformers and loads guidelines are prepared for setting of the various protection functions.
3.2.1
Fault current matrix for relay settings
Current matrix is calculated for faults at voltage levels. The following tables present the current matrices. The minimum and maximum three-phase fault levels at 132 kV main switchboard of the Kahramaa substation4 are presented below: S.No.
Fault level
Three-phase fault current (kA) at 132 kV main switchboard of the Kahramaa substation
X/R ratio
1
The minimum
10.2
12.05
2
The maximum
15.47
6.48
Table 3-1: Fault levels at 132 kV main switchboard of the Kahramaa substation
4
Email from Vincent Sauvergrain to Manoj Gupta, dated 31/08/2007, subject: QGX-CLP-MMD electrical studies-Company and KM comments
3-1 221661/02/B - OCT 2007/3-1 of 1 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
S.No
Transformer Tag Name
Primary Voltage
Secondary Voltage
Mott MacDonald CTJV
Transformer Rating Min Max MVA MVA
Full load current (FLC) (kA) I-Min I-Max I-Min I-Max Primary Primary Secondary Secondary
KV
kV
1
TR-27101 A/B
132
33
2
TR-27601
33
11
3
TR-27204 A/B
33
6.9
4
TR-27201 A/B
33
6.9
12
15
5
TR-27301 A/B
6.9
0.44
1.6
1.6
6
DTR-27302 A/B
6.9
0.44
1
1
0.084
80
0.437
1.4
1.75
Inrush Current (Multiple of FLC) 7
Type
100
0.35
Step down
25
25
0.437
0.437
1.312
1.312
7*
HV Distribution
20
25
0.350
0.437
1.674
2.092
4.75
MV Distribution
0.210
0.262
1.004
1.255
5.19
MV Distribution
0.134
0.134
2.100
2.100
7.31
LT Distribution
0.084
1.312
1.312
11.66
LT Distribution
Table 3-2: Current matrix for various ratings of transformer * Assumed data (Higher side value is considered for protection margins) Fault current matrix for fault currents at various voltage levels and associated fault current flow at higher voltage levels is presented in Table 3-2 below
3-2 221661/02/B - OCT 2007 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
Mott MacDonald CTJV
Three-phase fault current when supplied from Kahramaa S/S Minimum (kA) Maximum (kA)
Fault location
Fault current observation
0.415 kV SB-27302A
SB-27302A
21.17
22.34
Bus section
21.17
22.34
6.6 kV incomer
1.38
1.45
SB-27301A
28.12
30.22
Bus section
28.12
30.22
6.6 kV incomer
1.83
1.98
SB-27201A
10.08
16
6.6 kV incomer
10.08
11
Bus section
10.08
11
33 kV TR-27201
2.06
2.34
33 kV incomer
2.06
1.51
132 kV CLP
0.52
0.4
6.6 kV
SB-27205A
11.81
17
SB-27205A
6.6 kV incomer
11.81
11.73
Bus section
11.81
11.73
33 kV TR-27204
2.41
2.89
33 kV incomer
2.41
1.68
132 kV CLP
0.62
0.45
33 kV
33 kV TR-27603
9.02
13.92
TR-27603
Bus section
9.02
13.92
33 kV incomer
9.02
9.46
132 kV CLP
2.31
2.52
132 kV CLP
9.5
13.92
132 kV CLP
10.05
15.17
0.415 kV SB-27301A
6.6 kV SB-27201 A
132 kV TR-27101A
(LG fault current)
Table 3-3: Fault current matrix for over current relay setting For the minimum three-phase fault current calculation, the minimum fault level at Kahramaa S/S and no motor contribution are considered. For the maximum fault current calculation, the maximum fault level at Kahramaa S/S and motor contributions are considered. All faults currents are as per IEC 60909 symmetrical breaking currents. Earth fault current is restricted to the value as indicated in the Section – 2.3.1 due to the resistance grounded system.
3-3 221661/02/B - OCT 2007 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
3.2.2
Mott MacDonald CTJV
Guidelines for relay settings for 51, 50, 51N and 51G protection function
The following guidelines are adopted for the relay settings •
Time discrimination between the relays
The Circuit protection Time Interval (CTI)5 for the over current relay settings is presented below S.No.
Components
CTI with field test (s) Static / Electronics relays
1
Circuit breaker opening time 5 cycles
2
Relay over travel
3
Relay tolerance and error
0.1 0 0.12
Total CTI
0.22
Table 3-4: Permissible time delay for over current relay co-ordination Hence it is practical to have CTI for the electronics relays as low as 0.22 s. CTI provides the necessary time delay between the operations of the two relays and ensure co-ordinated operation. •
Guideline for setting of the over current relays
A sample circuit is shown below with a transformer and load. Relay locations are presented by A, B and C. Fault is presented on the primary side and secondary side of the transformer by Fp and Fs respectively. C Fp
B
.
A Fs
Figure 3-1: Sample circuit diagram for relay setting guideline
5
IEEE Std. 242-2001: Chapter 15 Over current protection
3-4 221661/02/B - OCT 2007 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
Mott MacDonald CTJV
For the over current protection following guidelines are adopted •
The characteristic of the relays at A, B and C for over current protection is normal inverse. Exception can be made for the relay at A, if associated with a motor protection, then it may be definite time or extremely inverse.
•
Relay at B and C must not operate for the maximum full load current of the transformer. The pickup is set between 115-150% of the full load current depending on the coordination with the down-stream and up-stream relays.
•
Relay at C must not operate for inrush current of the transformer, to ensure this the pickup setting of the instantaneous element must be more than the inrush current as indicated in the Table 3-1
•
For the fault Fs, the instantaneous elements of the relay at A should give protection, backup by the over-current element of the B and C. The instantaneous element of the relay at B will not be co-ordinated as the same is used for blocking of ATS (Automatic transfer system)6 in event of fault at the secondary side of the transformer. Pickup values for the instantaneous element at B are considered as follows o
At 33 kV level set pickup = 2 kA
o
At 6.6 kV level set pickup = 4 kA
o
At 0.415 kV level set pickup = 10 kA
•
The instantaneous element of C should provide protection for the fault Fp
•
In no case the minimum CTI should be violated for the maximum fault current seen by the relays
•
Because earth fault current is limited by the NGR, definite time characteristics are adopted to co-ordinate all 51N and 51G protection functions.
•
Characterise of the fuse are as per the ABB fuse manual 7 . The fuse characteristics as given on page 13 of the manual are modelled in ETAP.
The TCCs for the over current protection is presented in the Appendix – B.
6
“Secondary selective systems”, document number QGX/20/19/EL/TS/NA/026
7
“PowerIT Motor Circuit Fuses, CMF/CEF” ABB catalogue 1 YMB631051-en
3-5 221661/02/B - OCT 2007 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
3.2.3
Mott MacDonald CTJV
Guidelines for relay setting for 27 protection function
For the under voltage protection the following settings are considered
S.No. 1 2
Under voltage element U< = 0.1 - 1.2 Un t< = 40 - 30,000 ms
For Motor 0.7 500 ms
For Transformer 0.7 70 ms
Table 3-5: Guideline for relay setting for under voltage protection •
Under voltage relay at transformer secondary is used for ATS operation as shown in figure below. During the operation of 50, 50N or 27 immediate transfers of the loads to the other main bus (S1-R) should not occur otherwise that bus (S1-R) will also see the fault. For this reason operation time of the 27 and ATS should be time delayed to allow the operation of 51, 51N at each outgoing feeder to disconnect the faulty feeders from the bus (S1-L), if the fault is at the outgoing feeders. Hence the additional time delay is used for this purpose. Time delay of 2s is provided by the 27X of the ATS.
The action can be summarised as follows: •
For faults at transformer secondary side the ATS operation is blocked by the instantaneous over-current relays 50 and 50N as well as 27
•
For the low voltage at the secondary of the transformer by opening the primary CB motor under voltage operates first followed by under voltage relay on the transformer secondary with the time delay of 70 ms that activates the transfer logic of ATS. The ATS operates after a delay of 2s by opening the primary CB of the affected transformer, then opening secondary CB of the transformer and closing the bus coupler. In this way the bus S1-L is transferred to the bus S1-R.
3-6 221661/02/B - OCT 2007 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
Mott MacDonald CTJV
P1-L
P1-R
C
Time delay of the 27X is taken care by the control logic. The following time delays are suggested for the 27X operation at different voltage levels
C
"#
27X at 33kV: Time delay = 2 s 27X at 6.6kV: Time delay = 3 s 27X at 415V: Time delay = 3.5 s
! "#
% '(
B
S1-L
A
B
S1-R
Fs "#& &
Figure 3-1A: ATS operation – Interaction with over-current and under voltage relays
3-7 221661/02/B - OCT 2007 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
3.2.4
Mott MacDonald CTJV
Guidelines for relay setting for 59 protection function
For the over voltage protection the following settings are considered
S.No. 1 2
Over voltage element U> = 0.1 - 3.0 Un t = 40 - 30,000 ms
For Motor 1.15 5000
Table 3-6: Guideline for relay setting for over-voltage protection
Motor starting results reveals that the maximum post transient over voltages after the motor start are as high as 1.1 pu for less than 100 ms. Considering the result of the motor starting the low set U> of the 59 function is set to 1.15 pu with a time delay of 5s.
3-8 221661/02/B - OCT 2007 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
3.2.5
Mott MacDonald CTJV
Guideline for relay setting for 49 protection function
For the thermal over load protection (49) of the MV motors, REM 543 (ABB) is used. For the LV motors the setting of the thermal protection is presented in Appendix – A1.
3.2.5.1 49 protection function for ABB REM 543 relay
S.No.
Setting Parameter
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Ist = 0.1-10.00 In Tst = 0.1 - 120.0 s NC-st = 1-3 Device Type = 0-6 Trip Temp. = 80-120 % Alarm Temp. = 40-100% Reset Temp. = 40-100% Am Temp.= -50-100 Deg C TC-cooling = 1.0-10.0 TC-Heating = 1-999 min ST-CS = 0.0-999.0 min LT-CSS = 0.0-999.0 min p = 0.0 - 1.0 S-TR =50-350 Deg C Tmax S = 0.0-350 Deg C ST-CR = 0.0-999.0 min LT-CR = 0.0-999.0 min p = 0.0 - 1.0 R-TR =50-350 Deg C Tmax R = 0.0-350 Deg C Trip Delay = 0-86400 s
Sample Data 3.5 12 3 3 120 90 60 50 3 45 14.00 69 0.5 90 155 4 69 0.25 100 200 3600
Remarks Starting current Starting time Number of starts allowed from cold Surface cooling Trip temperature Alarm temperature Reset temperature Ambient Temp. * TC-Heating Time constant Short TC - Stator Long TC - Stator Wt. factor Stator Temp. rise at FL Stator Max. Temp Short TC - Rotor Long TC - Rotor Wt. factor Rotor Temp. rise at FL Rotor Max. Temp 60 min
Table 3-7: Setting group for REM 543 relay for thermal over load protection Explanations of the above setting parameters are presented below •
Ist is set as per the individual motor starting current
•
Tst is set as per the individual motor starting time
•
NC-st is set as per the individual motor data
•
Device type8 is set for motor rating > 500 kW and surface cooling
8
Relay technical data sheet: ABB ProtectIT Machine Terminals REM 543 and REM 545, document number: 1MRS751173-MBG
3-9 221661/02/B - OCT 2007 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
Mott MacDonald CTJV
•
Trip Temp. is set to 120% with Trip Delay of 60 min (3600s). It means that from motor temperature in the range of 100-120%, warning alarm will be generated until time delay of 60 min, for temperature more than 120%, tripping will occur instantaneously.
•
Alarm Temp. is set at 90%
•
Reset Temp. is set at 60% of the thermal capacity
•
Am. Temp. is set at 50 Deg. C
•
TC-cooling is set at 3 times the heating time constant. For motors less than 1300 kW it is taken as 6.0
•
TC – heating is set according to individual motor data. Following values are used when the data is not available
S.No.
Motor rating
Time constant – Heating (Min)
1
Less than 1300 kW
30
2
1300 kW to 2000 kW
35
3
2100 kW to 3000 kW
40
4
More than 3000 kW
45
Table 3-8: Time constant – heating; Data assumed if not available •
Settings from ST-CS to TMAX R are taken as default setting for wide range of motor ratings, except for S-TR and R-TR. The value of S-TR and R-TR for motors above 2000 kW is 90 and 100 respectively and for motors between 1000 kW to 2000 kW is 70 and 80 respectively.
3-10 221661/02/B - OCT 2007 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
3.2.6
Mott MacDonald CTJV
Guidelines for relay setting for 46 protection function
For current unbalance protection (for ABB REM 543) the following settings are considered •
Operation mode = Inverse time (2)
•
Pick up Is = 0.05
•
K is calculated for individual motor in such a manner that the tripping time of the relay is below the thermal damage curve. For motors above 2500 kW the thermal damage limit is taken as 15s and below that it is 10s. 2
Thermal damage curve is plotted using I * t = 15 (10). 2
2
And the motor tripping time is plotted for (I – Is ) * t = K For successful tripping the tripping curve must lie below the thermal damage curve. •
Operation time = Not applicable as the operation mode is not definite time
•
Start delay = 1 s
•
Minimum operation time = 7 s
•
Maximum operation time = 3600 s
•
Cooling time = 1800 s
•
For ABB make REM 543 9 relay inverse time characteristic is used for this function.
9
“Negative Phase Sequence Protection” ABB document no. 1MRS752310-MUM, Issued 10/1998, Version E/24.11.2003 3-11 221661/02/B - OCT 2007 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
3.2.7
Mott MacDonald CTJV
Guidelines for relay setting for 66 protection function
For protection function 66 (for ABB make, REM 543) the following settings a re considered •
Operation mode = 2 (Both I2t and stall protection)
•
Starting current = From the motor data sheet
•
Start time = 1.1 * motor start time (10% margin)
•
Time limit = Number of hot starts * start time
•
Countdown rate = 3 * start time
•
Stall time = From the motor data sheet
The protection function is also used to derided the 51LR protection function using the NOC3High (I>>)10 of the over- current protection. Output of the 66 protection function (using MotStart) is applied as input to NOC3High to double the setting of the NOC3High during the motor start-up duration. Once the motor reaches to its normal speed the NOC3High is returned to the actual setting (which set at 0.75 * Motor starting current). In this way 51LR is achieved during the motor start-up and the motor normal running condition. During the motor start-up the 51LR function is provided by the MotStart (66 protection function) and during the motor normal running condition the 51LR function is provided using the NOC3High of the over-current protection.
3.2.8
Guidelines for relay setting for 37 protection function
For protection function 37 (for ABB make, REM 543) the following settings a re considered Minimal load = 5%, Minimal current = 5% Op. time = 300 s (5 min)
10
Email from Toshiaki Saito to Manoj Gupta; dated 28/09/2006; subject: QGX : 51LR protection of REM543 (SL19020); attachment: Motstart_ver_0.10.pdf 3-12 221661/02/B - OCT 2007 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
3.2.9
Mott MacDonald CTJV
Relay setting for 87 protection function / Interface with Kahramaa
The differential protection as indicated in Table 1-1 is used for cables, transformers and motors protections. The differential protection is a unit protection and setting of this function required detailed analysis. The following sections present the calculation of the differential protection for various equipments using different relays.
3.2.9.1 Setting of 87L protection for 33 kV outgoing feeders Relay type: Solkor-N Setting is based on the minimum fault current basis, in this case the earth fault current, hence the differential current setting is equal to earth fault current. For the bias current setting minimum through fault is considered to be equal to two times the full load plus the earth fault. Based on these criteria the setting points are presented in Table 3-8 and on the relay characteristic by black dots in Figure 3-2. In the Figure 3-2, operating point of the relays are shown to test the stability of the relay under EF condition with relatively higher value of the restraint current (2 * FLC + EF) / 2. If for the operating point falls inside the relay selected characteristic then the relay will operates for other higher value of the phase current as well. Hence in the figures below operating points of the relays are shown by black dots to present a case in which differential current is equal to the EF current and the bias current is (2*FLC + EF)/2. The operating point will assist to select the correct value of relay setting such as B2 and Is
3-13 221661/02/B - OCT 2007 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
33 kV feeder To
Mott MacDonald CTJV
TR-27204 A/B
TR-27601 to TR-27605
TR-27201 A/B
MaxLoad Current/ Cable Rating (A)
438
438
263
CT Ratio (to 1A)
600
600
400
Primary EF Current (A)
400
400
400
Relay Bias Current (x In)
1.06
1.06
1.16
Relay Differential Current (xIn)
0.67
0.67
1.00
Minimum Differential Allowed wrt to Ic (x In)
0.1
0.1
0.1
Diff Setting Chosen
0.2
0.2
0.2
1
1
1
Bias Break point Chosen
Table 3-9: Setting of 87L protection for 33 kV feeders from SB-27101 A/B Same setting is used for both sending end and receiving end of the 33 kV feeder cables Ic: Relay bias current
3-14 221661/02/B - OCT 2007 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
Mott MacDonald CTJV
Solkor N - Bias Characteristic Is = 20%,S1=20% , S2=150%, B2= 0.5, 1, 1.5, 2 2.500
x ( t 2.000 n e r r u C l 1.500 a i t n ) N e I r e f f 1.000 i D r o e t 0.500 a r e p O
B2 = 2.5
0.000 0.00000
0.50000
1.00000
1.50000
2.00000
2.50000
3.00000
Restraint or bias Current (x I N) Figure 3-2: Setting of 87L protection for 33 kV out going feeders from SB-27101 A/B on the relay characteristic 3-15 221661/02/B - OCT 2007 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
Mott MacDonald CTJV
3.2.9.2 Interface with 132 kV Kahramaa substation - Setting of 87L protection
Relay Type: 7SD53 (Siemens) and REL 561 (ABB)
132 kV Kahramaa S/S
800/1
REL 561
800/1
7SD53
3*1C 1000 Sqmm 2850 m XLPE
800/1
7SD53
800/1
REL 561
132 kV CLP- SS2702
Figure 3-3: Representation of 87L protection for 132 kV cable Cable charging current = 20 A (Approximately) Guidelines adopted for 87L relay settings are •
Pickup for differential current (I-Diff>) should be more than 2.5 time the charging current
•
5% CT error should be added for calculation of the differential current
•
Charging current compensation is not required as the charging current is only 20A
•
Harmonic current stabilisation feature should be set to On
•
No additional time delay is required either for I-Diff> or for I-Diff>>
•
For dual slope characteristic relay, set the first slope to 50%, second slope to 100%, and intersection of slope 1 and slope 2 to 350% of I-bias.
•
Same setting of the differential protection should be adopted for both the ends of cable if CT ratios at both the ends are same.
3-16 221661/02/B - OCT 2007 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
Mott MacDonald CTJV
Calculations of relay setting parameters for 7SD53 are presented below •
Setting of I-Diff> I-Diff> = (2.5 * Charging current + 5% CT ratio error) / CT ratio = (2.5 * 20 + 0.05 * 800) / 800 = 0.1125 Adopted setting for I-Diff> = 0.12
•
Setting of I-Diff> Switch On Setting of the I-Diff> is increased to the minimum 3 times during cable energization I-Diff> Switch On = 3 * I-Diff> = 3 * 0.12 = 0.36 Adopted setting for I-Diff> Switch On = 0.36
•
Time delay for I-Diff> = 0.0s
•
Time delay for I-Diff>> = 0.0s
•
Charging current compensation = OFF
•
I-Diff>> = Min ( 3* Full load current, Line-line fault current) / CT ratio = Min ( 3 * 300 A, 7.45 kA) / 800 = 1.125 Adopted setting for I-Diff>> = 1.25
•
I-Diff>> Switch On = 4 * I-Diff>> = 4 * 1.25 =5
•
Inrush Restraint = On
•
2 Harmonic restraint = 30%
•
Cross block = No
•
Maximum Inrush Peak = 9.0 (Based on 11 * Transformer full load RMS current)
nd
3-17 221661/02/B - OCT 2007 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
Mott MacDonald CTJV
Calculations of relay setting parameters for REL 561 are presented below •
Operation = On
•
CT factor = 1 (Because CT ratio of both sides of the cable are same)
•
IminSat (Minimum current for CT saturation detection) Adopted setting = 300%
•
Iminop (Pick for differential current) I-Diff> for 7SD52 is 12%, in REL 561 the minimum setting available is 20% Adopted setting = 20%
•
IDiffLVl1 (Slope 1 of the relay characteristics) IDiffLVl1 = 50%
•
IDiffLVl2 (Slope 2 of the relay characteristics) IDiffLVl2 = 100%
•
ILV1/2Cross (Intersection of the slope 1 a nd slope 2) ILV1/2Cross = 350%
•
Evaluate = 3 of 4 (Refer relay manual for this setting)
•
Asymdelay (Asymmetrical time delay in data communication between the two ends) Asymdelay = 0.0 (Refer relay manual for this setting)
•
Diff Sync (For synchronising the operation of relays at two ends) Set Diff Sync = Master (For the relay at Kahramaa Substation) Set Diff Sync = Slave (For the relay at CLP SS-2702 substation)
•
CCom (Charging current compensation) Set CCom to Off
Complete relay setting schedule for the 87L protection is listed in Appendix – A3, for the 132 kV feeders C30 and C40.
3-18 221661/02/B - OCT 2007 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
Mott MacDonald CTJV
3.2.9.3 Interface with 132 kV Kahramaa substation - Setting of 87T protection for TR-27101A/B Relay Type: 7UT612 This relay provides the differential protection for the 80 MVA, 132/33kV transformer connecting the Kahramaa substation to SS-2702 substation. 132 kV 600/1
TR-27101 A/B 80 MVA Z = 12.5%
87 T 87N
7UT612
2000/1 33 kV
Figure 3-4: Representation of 87T protection for TR-27101 A/B
Calculations of the relay setting parameters are presented below •
Setting of differential current (Id>)
The relay should have minimum restrain for magnetising current (assumed to be 2% of full load current) , CT errors (considered to be 5%) at full loads and should consider the effects of transformer tap operations
Using the formula shown below minimum restraint current = 0.07 Minimum restraint current (Is) = (5% of Isecondary / CT ratio) + (5% of Iprimary / CT ratio) Isecondary = X * FLC (FLC: Full load current) Iprimary = X * FLC X = 1.15 (15% allowable overload is considered) Adding the differential current at full load due to CT ratio mismatch, the minimum differential current = 0.07 + 0.11 = 0.18 Considering the safety margin, CT saturation and transformer tap operation set Id> to 0.25 In 3-19 221661/02/B - OCT 2007 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
•
Mott MacDonald CTJV
Add on Stabilization Setting of the Add on Stabilization is based on the inrush current magnitude. Inrush current for TR-27101A/B = 7 * Full load current = 7 * 350 = 2450 A The inrush current seen at CT secondary = 2450 / 600 = 4.08 Adopted setting for Add on Stabilization = 75% of 4.08In = 3.0 In
•
Set Action time = 250 cycles
•
High set differential current (Id>>)
Setting of Id>> is calculated based on the formula given in the manual of 7UT612 on page 37 Id>> = (Transformer Full load current / CT primary) / Z (pu) = (350/ 600) / 0.125 = 4.7 In Adopted setting for Id>> = 4.7 •
Pickup on switch on = 1 (No shifting of the characteristic during switching)
•
TD for Id> = 0.0, TD for Id>> = 0.0
•
I2N / IfN = 30% (2 harmonic restraint ratio)
•
InfN / IfN = 30% (5 harmonic restraint ratio) Cross block = 0 Time for cross bloc = Deactivated
• •
nd
th
Calculation of setting parameters for 87N protection (Setting group of Restricted Earth Fault (64) are use for 7UT612) Secondary side Neutral CT ratio = 400/1 Line CT ratio = 2000/1 •
Set I-REF> to 100 A I-REF> = 100 / 400 = 0.25
•
Set time delay = 0
•
Slope = 0
Because earth fault current is limited to 400A hence chances of CT saturation and error due to through fault current is remote. Complete relay setting schedule for the 87T protection for the transformer TR-27101 A/B is presented in the Appendix – A3.
3-20 221661/02/B - OCT 2007 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
Mott MacDonald CTJV
3.2.9.4 Setting of 87T protection for 33/6.6 kV and 132/33 kV transformers Relay type: REF 542+ Basic setting groups for the transform differential protection for the ABB make REF 542 plus relay are presented below for the 87T protection of TR-27101A/B S.No. 1 2 3 4 5 6 7 8 9 10 11 12 13
Setting Parameter VG = 0 - 11 Earthing P: Yes / No Earthing S: Yes / No Ip = 10 - 100000 A Is = 10 - 100000 A Ith = 0.1 - 0.5 Ir URL = 0.5 - 5.0 In SBRT = 0.2 - 2.0 SBRL = 1.00 - 2.00 Ir Slope = 0.4 - 1.0 Trip Id> = 5.00-40.00 I2 Block= 0.1 - 0.3 I5 Block = 0.1 - 0.3
Sample Data 0 Yes Yes 350 1400 0.2 0.5 0.25 1 1 5 0.3 0.3
Remarks Transformer vector group
Rated primary side current Rated secondary current Threshold current Unbiased region limit Slightly biased threshold Slightly biased region limit Third region slope Upper Id threshold for trip 2nd harmonic threshold 5th harmonic threshold
Table 3-10: Setting group for REF 542+ relay for 87T protection
Id =
Id>
I1 – I2
R3
R1: Unbiased region
Trip only without nd th 2 and 5 harmonics
R2: Slightly biased region R3: Heavily biased region
SBRT It
Slope
R2
R1
URL
SBRL
Ib = (I1 + I2) / 2
Figure 3-5: Characteristic for the differential protection of REF 542 + Area above the thick black line is the trip area and below is the no trip region 3-21 221661/02/B - OCT 2007 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
Mott MacDonald CTJV
Explanation of the individual setting parameter is presented below •
VG: Vector group is set to 11 as all MV transformer as Dyn11
•
Ip and Is are set according to the individual transformer rating
•
Ith: Threshold current for the unbiased region (R1) is set to 20%, considering the maximum CT error of +5% and -5% at both ends of the transformer for through fault condition For 33/6.9 kV transformers Ith is set to 10%
•
URL: Unbiased region limit is set to 0.5In corresponding to 50% of the full load
•
SBRT: Slightly biased region threshold (R2) is set to 25% For 33/6.9 kV transformers Ith is set to 20%
•
SBRL: Slightly biased region limit is set to 1.0, corresponding to full load Slope is set to 1 so that wider area is covered under tripping zone and at the same time higher than the minimum setting to provide the sufficient bias during through fault condition and CT situation conditions. For 33/6.9 kV transformers Ith is set to 0.5
•
Trip Id> is set at 5.0, which is higher than the inrush current
•
I2 Block and I5 Block for the harmonic current is taken as to be at the default set value
3-22 221661/02/B - OCT 2007 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
Mott MacDonald CTJV
3.2.9.5 Setting of 87M protection for motor Relay Type: REM 543 Differential protection of the motors using REM 543 is based on stabilized three-phase differential protection11. Basic relay characteristic is shown below
Figure 3-6: Three-phase stabilized differential protection for motors The setting groups are as follows •
Basic setting (Id>): Pickup for the differential element (5 – 50 %)
•
Turing point 1: Value of Ib/In from where the first slope starts (0.0 – 1.0 In)
•
Starting ratio: Slope of the line after the Turning point 1 (10 - 50%)
•
Turning point 2: Value of Ib/In from where second slope starts (1.0 – 3.0 In)
•
Inst. Setting (Id>>): Instantaneous differential element pickup (5.0 – 30.0 In)
11
“Diff6G-Stabilized Three-Phase Differential Protection for Generators” ABB document number 1MRS752302-MUM, version C/18.1.2002
3-23 221661/02/B - OCT 2007 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
Mott MacDonald CTJV
Settings adopted for BOG compressor motor relay are set as under
S. No.
Motor Rating (kW) Calculation parameters
9500
1
CT ratio
700/1
2
Basic setting (Id>) [5 – 50%]
10
3
Turing point 1 [0.0 – 1.0 In]
0.5
4
Starting ratio [10 – 50%]
50
5
Turning point 2 [1.0 – 3.0 In]
1.5
6
Inst. Setting (Id>>) [5.0 – 30 In]
5.0
Table 3-11: Setting of 87M protection for MV BOG compressors
3-24 221661/02/B - OCT 2007 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
Mott MacDonald CTJV
3.2.10 Setting of 25 function for ATS at 33 kV and 6.6 kV levels Relay type: REF 542+ The relay operates when the Delta Voltage and Delta Angle are within the set limits for a specified Time Delay, based on this Delta Voltage = 0.05 pu Delta Angle = 10 Degree Time Delay = 15s Explanations of the above setting are given below Settings are as per the operating criteria described in the relay manual 12 Delta V is set as per the allowable LF voltage limits for HV and MV (5%) switchboards Delta Angle is set to 10 (More than this value may be the indicator of the overloads / faults on the switchboards). This is also supported by the load flow result under normal condition, where the buses angle were found to be near to 5 degree while in the single transformer operation exceeding 10 degree at 6.6 kV switchboards, in all these cases of LF Delta Angle is within 10 degree. Time delay is set to 15s to give enough time before Delta V and Delta Angle remain within the set values.
12
Relay REF 542+ manual “Protection functions: configuration and settings” ABB document number 1VTA10002 Rev03, en 3-25 221661/02/B - OCT 2007 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
Mott MacDonald CTJV
3.2.11 Over current protection for the LV systems LV motors and static loads protections are provided by the ABB make INSUM-2 relay. INSUM13 has an inbuilt CT which can be used for loads up to 63A, for loads more than 63 A an external CT is used to scale down the current as per the requirement of the application. ABB make MCCB with static release type PR221 and PR111 are used for the loads more than 45kW. Tables 3-11 and 3-12, presents the different type of MCCB used for different rating of LT loads and related setting of the releases. Settings of the INSUM-2 for each type of load as shown in the Tables 3-11 and 3-12 are presented in Appendix –A. TCCs of MCCBs are already reported in company approved QGX relay setting studies report14 . For the five LNG circulating pumps (415V - 104.4 kW) supplied by the LDB Siemens panels, the protection relay in use is GE multilin MM2, setting of which is provided by CTJV 15 and presented in Appendix A-1.
13
“MCU parameter description” Ver. 3.0, ABB document on the INSUM relay
14
Electrical system study for QGX, Company approved report – Relay co-ordination studies – Rev G, July 07, report submitted by Mott MacDonald Ltd. To CTJV 15
Email from Vincent to Manoj Gupta; dated 28/09/2007; subject: RE: QGXE2A4042 / CLP - LDB Relays in Satellite SS2701A, SS-2702A/B/C – Settings; Attachment: MM2 Setpoint File Information.pdf
3-26 221661/02/B - OCT 2007 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
Cub
Motor
Mott MacDonald CTJV
MCCB
S.
No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Size 6E 6E 6E 6E 6E 6E 6E 6E 6E 6E 6E 6E 6E 6E 6E 6E 6E 12E 12E
kW 0.18 0.25 0.37 0.55 0.75 1.1 1.5 2.2 3 4 5.5 7.5 11 15 18.5 22 30 37 45
I (A) 0.72 0.83 1.1 1.5 2 2.8 3.5 5 6.6 8.6 11.5 15.2 22 28.5 36 42 56 68 83
Type T2H160 MF 1 T2H160 MF 1 T2H160 MF 1.6 T2H160 MF 1.6 T2H160 MF 2 T2H160 MF 3.2 T2H160 MF 4 T2H160 MF 5 T2H160 MF 8.5 T2H160 MF 11 T2H160 MF12.5 T2H160 MA 20 T2H160 MA 32 T2H160 MA 52 T2H160 MA 52 T2H160 MA 52 T2H160 MA 80 T2H160 MA 80 T2H160 MA 100
Magnetic Tripping current (A) 13 13 21 21 26 42 52 65 110 145 163 200 288 364 468 520 800 960 1200
MCCB Setting t1 I2 t2
I1
-
-
-
-
Contactor
INSUM
Interpose
QGX Type A9 A9 A9 A9 A9 A9 A16 A26 A26 A30 A50 A50 A50 A50 A50 A63 A75 A95 A110
TYPE MCU2 0.1-3.2 A MCU2 0.1-3.2 A MCU2 0.1-3.2 A MCU2 0.1-3.2 A MCU2 0.1-3.2 A MCU2 63 A MCU2 63 A MCU2 63 A MCU2 63 A MCU2 63 A MCU2 63 A MCU2 63 A MCU2 63 A MCU2 63 A MCU2 63 A MCU2 63 A MCU2 63 A MCU2 0.1-3.2 A MCU2 0.1-3.2 A
CT KORC 1A 105/1 S KORC 1A 105/1 S
I3
13 13 13 13 13 13 13 13 13 13 13 10 9 7 9 10 10 12 12
Table 3-12: Direct on line starters with MCCB and INSUM-2, load up to 45kW
3-27 221661/02/B - OCT 2007 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
Cub Size
Motor kW I (A)
I1
MCCB Setting t1 I2 t2
I3
Contactor QGX Type
INSUM TYPE
Interpose CT
T4H250 PR221-I In 160
Tripping current (A) 1360
20
12E
55
98
-
-
-
-
8.5
A145
MCU2 0.1-3.2 A
KORC 1A 105/1 S
21
12E
75
135
T4H250 PR221-I In 250
1875
-
-
-
-
7.5
A185
MCU2 0.1-3.2 A
KORC 1A 185/1 S
22
16E
90
158
T4H250 PR221-I In 250
2000
-
-
-
-
8
A210
MCU2 0.1-3.2 A
KORC 1A 185/1 S
23
16E
110
193
T4H320 PR221-I In 320
2080
-
-
-
-
6.5
A260
MCU2 0.1-3.2 A
KORC 1A 310/1 S
24
Cub600
132
232
E2N1250In400 PR121/LI
2400
0.8
12
-
-
6
N/A
MCU2 0.1-3.2 A
SUCCESS 400/1 A
25
Cub600
FDR
630
T5H630In630 PR221-LSI
2835
1
3
-
-
4.5
26
Cub600
FDR
800
S6H800In800 PR212-LSI
6400
1
A
2
A
8
S. No.
MCCB Type
Mott MacDonald CTJV
Table 3-13: Direct on line starters with MCCB and INSUM-2, load more than 45kW
3-28 221661/02/B - OCT 2007 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
Appendix - A: Relay setting schedules
The relay setting schedule is organised as follows A1: LT relays setting schedule A2: 33 kV feeders relay setting schedule A3: 33/6.6 kV and 6.6/0.415 kV transformer relay setting schedule A4: MV motor relay setting schedule
A1 221661/02/B - OCT 2007/1 of 1 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Mott MacDonald CTJV
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
Mott MacDonald CTJV
A-1: LV relays setting schedule Setting Guideline for Auto-Restart Function
With referring to the Annexure-III (Motor Auto Restart Study) of the QGX relay setting report 13, autoRestart setting is provided for the LV motors required to be re-started as per the following guideline; Device Duty: Function 27 Setting Parameter:
•
Reset Voltage Level (RVL) Range: 50 - 100% Setting: 90%
•
Max Auto Re-closing Time (MAT) Range: 0.0 - 5.0sec Setting: 0.0sec16
•
Max. Power down Time (PDT) Range: 0 - 1200sec Setting: 5sec (Refer Note-1 below)
•
Staggered Start Time (SST) Range: 0 -1200sec Setting: Refer Note-2 below
Note-1: Referring to the Annexure-IV (Transformer Energization Study) of the QGX relay setting report13. Note-2: Setting value to be as per "Switch-In Time" for each priority group specified in Annexure-III (Motor Auto Restart Study) of the QGX relay setting report 13.
16
Email from Toshiaki Saito to Manoj Gupta dated 22/06/2007; Subject: Re: QGX : Wrap-up Comment on Relay Coordination Study (INSUM Setting)
A2 221661/02/B - OCT 2007/2 of 2 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
S.N Cub. o. Size
Rated Rated I Protection kW A Type
INSUM CT ratio TYPE
Mott MacDonald CTJV
Device Setting range Duty
Schedule for LV (0.415 kV) feeders ST
Setting
NR-DOL/RCU Starter Type
MRD
As per Motor Data
In = 0.10 - 3.20 A Ist = 1.0 - 10 In Tst = 1 - 600s 49
Function TOL TOL Type t6 = 5 - 40s CDTF = 1 - 100 AL = 50 - 100%
51 LR Stall Protection Trip Level Trip Delay 1
6E
0.18
0.72
TYPE -C
MCU2
Remark
0.72 6 5
Nominal current Startup ratio
Enable Standard As per Motor Data 10 cool down time fact. 4 Alarm level 90 Trip Only 400% 5sec
0.1 - 3.2A 51 G Function EF Method RCT Ip = 1,5,50 A AL = 0.1(0.1)
27
Function 27 Un = 230 - 690 V AL = 50 - 100% U< = 50 -100% t< = 0.2 - 5 s RVL = 50 - 100 % MAT = 0.0 - 5.0 s PDT = 0 - 1200 s SST = 0 - 1200s
Alarm Only Measure 1 Alarm level 0.3
Enable 415 Alarm level 80 Trip level 70 0 Trip delay for DOL/RCU 90 Reset Voltage Level Auto reclosing time 0 Note-1 5 As per annexure-III Of the QGX – Rev G report
A3 221661/02/B - OCT 2007/3 of 3 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
Mott MacDonald CTJV ST
NR-DOL/RCU Starter Type
MRD
As per Motor Data
In = 0.10 - 3.20 A Ist = 1.0 - 10 In Tst = 1 - 600s 49
Function TOL TOL Type t6 = 5 - 40s CDTF = 1 - 100 AL = 50 - 100%
51 LR Stall Protection Trip Level Trip Delay 2
6E
0.25
0.83
TYPE-C
MCU2
0.83 6 5
27
Function 27 Un = 230 - 690 V AL = 50 - 100% U< = 50 -100% t< = 0.2 - 5 s RVL = 50 - 100 % MAT = 0.0 - 5.0 s PDT = 0 - 1200 s SST = 0 - 1200s
ST
Enable Standard As per Motor Data 10 cool down time fact. 4 90 Alarm level Trip Only 400% 5sec
Alarm Only Measure 1 0.3 Alarm level
Enable 415 Alarm level 80 70 Trip level Trip delay for DOL/RCU 0 Reset Voltage Level 90 Auto reclosing time 0 5 Note-1 As per annexure-III NR-DOL/RCU Starter Type
MRD
As per Motor Data
In = 0.10 - 3.20 A Ist = 1.0 - 10 In Tst = 1 - 600s 49
Function TOL TOL Type t6 = 5 - 40s CDTF = 1 - 100 AL = 50 - 100%
51 LR Stall Protection Trip Level Trip Delay 6E
0.37
1.1
TYPE-C
MCU2
Startup ratio
0.1 - 3.2A 51 G Function EF Method RCT Ip = 1,5,50 A AL = 0.1(0.1)
3
Nominal current
1.1 6 5
Nominal current Startup ratio
Enable Standard As per Motor Data 10 cool down time fact. 4 90 Alarm level Trip Only 400% 5sec
0.1 - 3.2A 51 G Function EF Method RCT Ip = 1,5,50 A AL = 0.1(0.1)
27
Function 27 Un = 230 - 690 V AL = 50 - 100% U< = 50 -100% t< = 0.2 - 5 s RVL = 50 - 100 % MAT = 0.0 - 5.0 s PDT = 0 - 1200 s SST = 0 - 1200s
Alarm Only Measure 1 Alarm level 0.3
Enable 415 Alarm level 80 Trip level 70 Trip delay for DOL/RCU 0 Reset Voltage Level 90 Auto reclosing time 0 5 Note-1 As per annexure-III Of the QGX – Rev G report
A4 221661/02/B - OCT 2007/4 of 4 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
Mott MacDonald CTJV ST
NR-DOL/RCU Starter Type
MRD
As per Motor Data
In = 0.10 - 3.20 A Ist = 1.0 - 10 In Tst = 1 - 600s 49
Function TOL TOL Type t6 = 5 - 40s CDTF = 1 - 100 AL = 50 - 100%
51 LR Stall Protection Trip Level Trip Delay 4
6E
0.55
1.5
TYPE-C
MCU2
1.5 6 5
27
Function 27 Un = 230 - 690 V AL = 50 - 100% U< = 50 -100% t< = 0.2 - 5 s RVL = 50 - 100 % MAT = 0.0 - 5.0 s PDT = 0 - 1200 s SST = 0 - 1200s
ST
Enable Standard As per Motor Data 10 cool down time fact. 4 90 Alarm level Trip Only 400% 5sec
Alarm Only Measure 1 0.3 Alarm level
Enable 415 Alarm level 80 70 Trip level Trip delay for DOL/RCU 0 Reset Voltage Level 90 Auto reclosing time 0 5 Note-1 As per annexure-III NR-DOL/RCU Starter Type
MRD
As per Motor Data
In = 0.10 - 3.20 A Ist = 1.0 - 10 In Tst = 1 - 600s 49
Function TOL TOL Type t6 = 5 - 40s CDTF = 1 - 100 AL = 50 - 100%
51 LR Stall Protection Trip Level Trip Delay 6E
0.75
2
TYPE-C
MCU2
Startup ratio
0.1 - 3.2A 51 G Function EF Method RCT Ip = 1,5,50 A AL = 0.1(0.1)
5
Nominal current
2 6 5
Nominal current Startup ratio
Enable Standard As per Motor Data 10 cool down time fact. 4 90 Alarm level Trip Only 400% 5sec
0.1 - 3.2A 51 G Function EF Method RCT Ip = 1,5,50 A AL = 0.1(0.1)
27
Function 27 Un = 230 - 690 V AL = 50 - 100% U< = 50 -100% t< = 0.2 - 5 s RVL = 50 - 100 % MAT = 0.0 - 5.0 s PDT = 0 - 1200 s SST = 0 - 1200s
Alarm Only Measure 1 Alarm level 0.3
Enable 415 Alarm level 80 Trip level 70 Trip delay for DOL/RCU 0 Reset Voltage Level 90 Auto reclosing time 0 5 Note-1 As per annexure-III Of the QGX – Rev G report
A5 221661/02/B - OCT 2007/5 of 5 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
Mott MacDonald CTJV ST
NR-DOL/RCU Starter Type
MRD
As per Motor Data
In = 2.0 - 63.0 A Ist = 1.0 - 10 In Tst = 1 - 600s 49
Function TOL TOL Type t6 = 5 - 40s CDTF = 1 - 100 AL = 50 - 100%
51 LR Stall Protection Trip Level Trip Delay 6
6E
1.1
2.8
TYPE-C
MCU2
2.8 6 5
27
Function 27 Un = 230 - 690 V AL = 50 - 100% U< = 50 -100% t< = 0.2 - 5 s RVL = 50 - 100 % MAT = 0.0 - 5.0 s PDT = 0 - 1200 s SST = 0 - 1200s
ST
Enable Standard As per Motor Data 10 cool down time fact. 4 90 Alarm level Trip Only 400% 5sec
Alarm Only Measure 1 Alarm level 0.3
Enable 415 Alarm level 80 Trip level 70 Trip delay for DOL/RCU 0 90 Reset Voltage Level Auto reclosing time 0 Note-1 5 As per annexure-III NR-DOL/RCU Starter Type
MRD
As per Motor Data
In = 2.0 - 63.0 A Ist = 1.0 - 10 In Tst = 1 - 600s 49
Function TOL TOL Type t6 = 5 - 40s CDTF = 1 - 100 AL = 50 - 100%
51 LR Stall Protection Trip Level Trip Delay 6E
1.5
3.5
TYPE-C
MCU2
Startup ratio
2.0-63.0 A 51 G Function EF Method RCT Ip = 1,5,50 A AL = 0.1(0.1)
7
Nominal current
3.5 6 5
Nominal current Startup ratio
Enable Standard 10 As per Motor Data 4 cool down time fact. Alarm level 90 Trip Only 400% 5sec
2.0-63.0 A 51 G Function EF Method RCT Ip = 1,5,50 A AL = 0.1(0.1)
27
Function 27 Un = 230 - 690 V AL = 50 - 100% U< = 50 -100% t< = 0.2 - 5 s RVL = 50 - 100 % MAT = 0.0 - 5.0 s PDT = 0 - 1200 s SST = 0 - 1200s
Alarm Only Measure 1 0.3 Alarm level
Enable 415 80 Alarm level 70 Trip level Trip delay for DOL/RCU 0 Reset Voltage Level 90 0 Auto reclosing time 5 Note-1 As per annexure-III Of the QGX – Rev G report
A6 221661/02/B - OCT 2007/6 of 6 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
Mott MacDonald CTJV ST
NR-DOL/RCU Starter Type
MRD
As per Motor Data
In = 2.0 - 63.0 A Ist = 1.0 - 10 In Tst = 1 - 600s 49
8
6E
2.2
5
TYPE-C
MCU2
2.0-63.0 A
Function TOL TOL Type t6 = 5 - 40s CDTF = 1 - 100 AL = 50 - 100%
51 LR Stall Protection Trip Level Trip Delay Trip Delay 51 G Function EF Method RCT Ip = 1,5,50 A AL = 0.1(0.1)
27
Function 27 Un = 230 - 690 V AL = 50 - 100% U< = 50 -100% t< = 0.2 - 5 s RVL = 50 - 100 % MAT = 0.0 - 5.0 s PDT = 0 - 1200 s SST = 0 - 1200s
ST
5 6 5
Trip Only 400% 5sec 5sec Alarm Only Measure 1 Alarm level 0.3
Enable 415 Alarm level 80 Trip level 70 Trip delay for DOL/RCU 0 90 Reset Voltage Level Auto reclosing time 0 Note-1 5 As per annexure-III NR-DOL/RCU Starter Type
As per Motor Data
In = 2.0 - 63.0 A Ist = 1.0 - 10 In Tst = 1 - 600s Function TOL TOL Type t6 = 5 - 40s CDTF = 1 - 100 AL = 50 - 100%
51 LR Stall Protection Trip Level Trip Delay 9
6E
3
6.6
TYPE-C
MCU2
Startup ratio
Enable Standard As per Motor Data 10 cool down time fact. 4 90 Alarm level
MRD
49
Nominal current
6.6 6 5
Nominal current Startup ratio
Enable Standard 10 As per Motor Data 4 cool down time fact. Alarm level 90 Trip Only 400% 5sec
2.0-63.0 A 51 G Function EF Method RCT Ip = 1,5,50 A AL = 0.1(0.1)
27
Function 27 Un = 230 - 690 V AL = 50 - 100% U< = 50 -100% t< = 0.2 - 5 s RVL = 50 - 100 % MAT = 0.0 - 5.0 s PDT = 0 - 1200 s SST = 0 - 1200s
Alarm Only Measure 1 0.3 Alarm level
Enable 415 80 Alarm level 70 Trip level Trip delay for DOL/RCU 0 Reset Voltage Level 90 0 Auto reclosing time 5 Note-1 As per annexure-III Of the QGX – Rev G report
A7 221661/02/B - OCT 2007/7 of 7 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
Mott MacDonald CTJV ST
NR-DOL/RCU Starter Type
MRD
As per Motor Data
In = 2.0 - 63.0 A Ist = 1.0 - 10 In Tst = 1 - 600s 49
Function TOL TOL Type t6 = 5 - 40s CDTF = 1 - 100 AL = 50 - 100%
51 LR Stall Protection Trip Level Trip Delay 10
6E
4
8.6
TYPE-C
MCU2
8.6 6 5
27
Function 27 Un = 230 - 690 V AL = 50 - 100% U< = 50 -100% t< = 0.2 - 5 s RVL = 50 - 100 % MAT = 0.0 - 5.0 s PDT = 0 - 1200 s SST = 0 - 1200s
ST
Enable Standard As per Motor Data 10 cool down time fact. 4 90 Alarm level Trip Only 400% 5sec
Alarm Only Measure 1 Alarm level 0.3
Enable 415 Alarm level 80 Trip level 70 Trip delay for DOL/RCU 0 90 Reset Voltage Level Auto reclosing time 0 Note-1 5 As per annexure-III NR-DOL/RCU Starter Type
MRD
As per Motor Data
In = 2.0 - 63.0 A Ist = 1.0 - 10 In Tst = 1 - 600s 49
Function TOL TOL Type t6 = 5 - 40s CDTF = 1 - 100 AL = 50 - 100%
51 LR Stall Protection Trip Level Trip Delay 6E
5.5
11.5
TYPE-C
MCU2
Startup ratio
2.0-63.0 A 51 G Function EF Method RCT Ip = 1,5,50 A AL = 0.1(0.1)
11
Nominal current
11.5 6 5
Nominal current Startup ratio
Enable Standard 15 As per Motor Data 4 cool down time fact. Alarm level 90 Trip Only 400% 5sec
2.0-63.0 A 51 G Function EF Method RCT Ip = 1,5,50 A AL = 0.1(0.1)
27
Function 27 Un = 230 - 690 V AL = 50 - 100% U< = 50 -100% t< = 0.2 - 5 s RVL = 50 - 100 % MAT = 0.0 - 5.0 s PDT = 0 - 1200 s SST = 0 - 1200s
Alarm Only Measure 1 0.3 Alarm level
Enable 415 80 Alarm level 70 Trip level Trip delay for DOL/RCU 0 Reset Voltage Level 90 0 Auto reclosing time 5 Note-1 As per annexure-III Of the QGX – Rev G report
A8 221661/02/B - OCT 2007/8 of 8 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
Mott MacDonald CTJV ST
NR-DOL/RCU Starter Type
MRD
As per Motor Data
In = 2.0 - 63.0 A Ist = 1.0 - 10 In Tst = 1 - 600s 49
Function TOL TOL Type t6 = 5 - 40s CDTF = 1 - 100 AL = 50 - 100%
51 LR Stall Protection Trip Level Trip Delay 12
6E
7.5
15.2
TYPE-C
MCU2
15.2 6 5
27
Function 27 Un = 230 - 690 V AL = 50 - 100% U< = 50 -100% t< = 0.2 - 5 s RVL = 50 - 100 % MAT = 0.0 - 5.0 s PDT = 0 - 1200 s SST = 0 - 1200s
ST
Enable Standard As per Motor Data 15 cool down time fact. 4 90 Alarm level Trip Only 400% 5sec
Alarm Only Measure 1 Alarm level 0.3
Enable 415 Alarm level 80 Trip level 70 Trip delay for DOL/RCU 0 90 Reset Voltage Level Auto reclosing time 0 Note-1 5 As per annexure-III NR-DOL/RCU Starter Type
MRD
As per Motor Data
In = 2.0 - 63.0 A Ist = 1.0 - 10 In Tst = 1 - 600s 49
Function TOL TOL Type t6 = 5 - 40s CDTF = 1 - 100 AL = 50 - 100%
51 LR Stall Protection Trip Level Trip Delay 6E
11
22
TYPE -C
MCU2
Startup ratio
2.0-63.0 A 51 G Function EF Method RCT Ip = 1,5,50 A AL = 0.1(0.1)
13
Nominal current
22.0 6 5
Nominal current Startup ratio
Enable Standard 15 As per Motor Data 4 cool down time fact. Alarm level 90 Trip Only 400% 5sec
0.1 - 3.2A 51 G Function EF Method RCT Ip = 1,5,50 A AL = 0.1(0.1)
27
Function 27 Un = 230 - 690 V AL = 50 - 100% U< = 50 -100% t< = 0.2 - 5 s RVL = 50 - 100 % MAT = 0.0 - 5.0 s PDT = 0 - 1200 s SST = 0 - 1200s
Alarm Only Measure 1 0.3 Alarm level
Enable 415 80 Alarm level 70 Trip level Trip delay for DOL/RCU 0 Reset Voltage Level 90 0 Auto reclosing time 5 Note-1 As per annexure-III Of the QGX – Rev G report
A9 221661/02/B - OCT 2007/9 of 9 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
Mott MacDonald CTJV ST
NR-DOL/RCU Starter Type
MRD
As per Motor Data
In = 2.0 - 63.0 A Ist = 1.0 - 10 In Tst = 1 - 600s 49
Function TOL TOL Type t6 = 5 - 40s CDTF = 1 - 100 AL = 50 - 100%
51 LR Stall Protection Trip Level Trip Delay 14
6E
15
28.5
TYPE-C
MCU2
28.5 6 5
27
Function 27 Un = 230 - 690 V AL = 50 - 100% U< = 50 -100% t< = 0.2 - 5 s RVL = 50 - 100 % MAT = 0.0 - 5.0 s PDT = 0 - 1200 s SST = 0 - 1200s
ST
Enable Standard As per Motor Data 15 cool down time fact. 4 90 Alarm level Trip Only 400% 5sec
Alarm Only Measure 1 Alarm level 0.3
Enable 415 Alarm level 80 Trip level 70 Trip delay for DOL/RCU 0 90 Reset Voltage Level Auto reclosing time 0 Note-1 5 As per annexure-III NR-DOL/RCU Starter Type
MRD
As per Motor Data
In = 2.0 - 63.0 A Ist = 1.0 - 10 In Tst = 1 - 600s 49
Function TOL TOL Type t6 = 5 - 40s CDTF = 1 - 100 AL = 50 - 100%
51 LR Stall Protection Trip Level Trip Delay 6E
18.5
36
TYPE-C
MCU2
Startup ratio
2.0-63.0 A 51 G Function EF Method RCT Ip = 1,5,50 A AL = 0.1(0.1)
15
Nominal current
36.0 6 5
Nominal current Startup ratio
Enable Standard 15 As per Motor Data 4 cool down time fact. Alarm level 90 Trip Only 400% 5sec
2.0-63.0 A 51 G Function EF Method RCT Ip = 1,5,50 A AL = 0.1(0.1)
27
Function 27 Un = 230 - 690 V AL = 50 - 100% U< = 50 -100% t< = 0.2 - 5 s RVL = 50 - 100 % MAT = 0.0 - 5.0 s PDT = 0 - 1200 s SST = 0 - 1200s
Alarm Only Measure 1 0.3 Alarm level
Enable 415 80 Alarm level 70 Trip level Trip delay for DOL/RCU 0 Reset Voltage Level 90 0 Auto reclosing time 5 Note-1 As per annexure-III Of the QGX – Rev G report
A10 221661/02/B - OCT 2007/10 of 10 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
Mott MacDonald CTJV ST
NR-DOL/RCU Starter Type
MRD
As per Motor Data
In = 2.0 - 63.0 A Ist = 1.0 - 10 In Tst = 1 - 600s 49
Function TOL TOL Type t6 = 5 - 40s CDTF = 1 - 100 AL = 50 - 100%
51 LR Stall Protection Trip Level Trip Delay 16
6E
22
42
TYPE-C
MCU2
42.0 6 5
27
Function 27 Un = 230 - 690 V AL = 50 - 100% U< = 50 -100% t< = 0.2 - 5 s RVL = 50 - 100 % MAT = 0.0 - 5.0 s PDT = 0 - 1200 s SST = 0 - 1200s
ST
Enable Standard As per Motor Data 15 cool down time fact. 4 90 Alarm level Trip Only 400% 5sec
Alarm Only Measure 1 0.3 Alarm level
Enable 415 Alarm level 80 70 Trip level Trip delay for DOL/RCU 0 Reset Voltage Level 90 Auto reclosing time 0 5 Note-1 As per annexure-III NR-DOL/RCU Starter Type
MRD
As per Motor Data
In = 2.0 - 63.0 A Ist = 1.0 - 10 In Tst = 1 - 600s 49
Function TOL TOL Type t6 = 5 - 40s CDTF = 1 - 100 AL = 50 - 100%
51 LR Stall Protection Trip Level Trip Delay 6E
30
56
TYPE-C
MCU2
Startup ratio
2.0-63.0 A 51 G Function EF Method RCT Ip = 1,5,50 A AL = 0.1(0.1)
17
Nominal current
56.0 6 5
Nominal current Startup ratio
Enable Standard As per Motor Data 15 cool down time fact. 4 90 Alarm level Trip Only 400% 5sec
2.0-63.0 A 51 G Function EF Method RCT Ip = 1,5,50 A AL = 0.1(0.1)
27
Function 27 Un = 230 - 690 V AL = 50 - 100% U< = 50 -100% t< = 0.2 - 5 s RVL = 50 - 100 % MAT = 0.0 - 5.0 s PDT = 0 - 1200 s SST = 0 - 1200s
Alarm Only Measure 1 Alarm level 0.3
Enable 415 Alarm level 80 Trip level 70 Trip delay for DOL/RCU 0 Reset Voltage Level 90 Auto reclosing time 0 5 Note-1 As per annexure-III Of the QGX – Rev G report
A11 221661/02/B - OCT 2007/11 of 11 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies 0.1 - 3.2 A
Mott MacDonald CTJV
ST
NR-DOL/RCU Starter Type
Ext CT1 Ip = 10 - 6300A Ext CT Is = 0.01 - 3.20 A
105 1
MRD
As per Motor Data
In = 10.5 - 105A Ist = 1.0 - 10 In Tst = 1 - 600s 49
18
12E
37
73.5
TYPE-B
MCU2
Function TOL TOL Type t6 = 5 - 40s CDTF = 1 - 100 AL = 50 - 100%
51 LR Stall Protection Trip Level KORC 1A Trip Delay
51 G Function EF Method RCT Ip = 1,5,50 A AL = 0.1(0.1)
0.1 - 3.2 A
Function 27 Un = 230 - 690 V AL = 50 - 100% U< = 50 -100% t< = 0.2 - 5 s RVL = 50 - 100 % MAT = 0.0 - 5.0 s PDT = 0 - 1200 s SST = 0 - 1200s
ST
73.5 5.6 6
Enable Standard 15 As per Motor Data 4 cool down time fact. 90 Alarm level Trip Only 400% 5sec
Alarm Only Measure 1 0.3 Alarm level Enable 415 Alarm level 80 Trip level 70 Trip delay for DOL/RCU 0 90 Reset Voltage Level 0 Auto reclosing time Note-1 5 As per annexure-III
105 1
MRD
As per Motor Data
In = 10.5 - 105A Ist = 1.0 - 10 In Tst = 1 - 600s
19
12E
45
84
TYPE-B
MCU2
Function TOL TOL Type t6 = 5 - 40s CDTF = 1 - 100 AL = 50 - 100%
51 LR Stall Protection Trip Level KORC 1A Trip Delay
51 G Function EF Method RCT Ip = 1,5,50 A AL = 0.1(0.1)
Startup ratio
NR-DOL/RCU Starter Type
Ext CT1 Ip = 10 - 6300A Ext CT Is = 0.01 - 3.20 A
49
Nominal current
Function 27 Un = 230 - 690 V AL = 50 - 100% U< = 50 -100% t< = 0.2 - 5 s RVL = 50 - 100 % MAT = 0.0 - 5.0 s PDT = 0 - 1200 s SST = 0 - 1200s
84.0 5.9 5
Nominal current Startup ratio
Enable Standard 15 As per Motor Data 4 cool down time fact. 90 Alarm level Trip Only 400% 5sec
Alarm Only Measure 1 0.3 Alarm level Enable 415 80 Alarm level 70 Trip level Trip delay for DOL/RCU 0 90 Reset Voltage Level Auto reclosing time 0 Note-1 5 As per annexure-III Of the QGX – Rev G report
A12 221661/02/B - OCT 2007/12 of 12 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies 0.1 - 3.2 A
Mott MacDonald CTJV
ST
NR-DOL/RCU Starter Type
Ext CT1 Ip = 10 - 6300A Ext CT Is = 0.01 - 3.20 A
105 1
MRD
As per Motor Data
In = 10.5 - 105A Ist = 1.0 - 10 In Tst = 1 - 600s 49
20
12E
55
105
TYPE-B
MCU2
Function TOL TOL Type t6 = 5 - 40s CDTF = 1 - 100 AL = 50 - 100%
51 LR Stall Protection Trip Level KORC 1A Trip Delay
51 G Function EF Method RCT Ip = 1,5,50 A AL = 0.1(0.1)
0.1 - 3.2 A
Function 27 Un = 230 - 690 V AL = 50 - 100% U< = 50 -100% t< = 0.2 - 5 s RVL = 50 - 100 % MAT = 0.0 - 5.0 s PDT = 0 - 1200 s SST = 0 - 1200s
ST
105.0 5.3 6
Enable Standard 29 As per Motor Data 4 cool down time fact. 90 Alarm level Trip Only 400% 5sec
Alarm Only Measure 1 0.3 Alarm level Enable 415 Alarm level 80 Trip level 70 Trip delay for DOL/RCU 0 90 Reset Voltage Level 0 Auto reclosing time Note-1 5 As per annexure-III
185 1
MRD
As per Motor Data
In = 18.5 - 185A Ist = 1.0 - 10 In Tst = 1 - 600s
21
12E
75
129.5
TYPE-B
MCU2
Function TOL TOL Type t6 = 5 - 40s CDTF = 1 - 100 AL = 50 - 100%
51 LR Stall Protection Trip Level KORC 1A Trip Delay
51 G Function EF Method RCT Ip = 1,5,50 A AL = 0.1(0.1)
Startup ratio
NR-DOL/RCU Starter Type
Ext CT1 Ip = 10 - 6300A Ext CT Is = 0.01 - 3.20 A
49
Nominal current
Function 27 Un = 230 - 690 V AL = 50 - 100% U< = 50 -100% t< = 0.2 - 5 s RVL = 50 - 100 % MAT = 0.0 - 5.0 s PDT = 0 - 1200 s SST = 0 - 1200s
129.5 6.2 5
Nominal current Startup ratio
Enable Standard 13 As per Motor Data 4 cool down time fact. 90 Alarm level Trip Only 400% 5sec
Alarm Only Measure 1 0.3 Alarm level Enable 415 80 Alarm level 70 Trip level Trip delay for DOL/RCU 0 90 Reset Voltage Level Auto reclosing time 0 Note-1 5 As per annexure-III Of the QGX – Rev G report
A13 221661/02/B - OCT 2007/13 of 13 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies 0.1 - 3.2 A
Mott MacDonald CTJV
ST
NR-DOL/RCU Starter Type
Ext CT1 Ip = 10 - 6300A Ext CT Is = 0.01 - 3.20 A
185 1
MRD
As per Motor Data
In = 18.5 - 185A Ist = 1.0 - 10 In Tst = 1 - 600s 49
22
16E
90
166.5
TYPE-B
MCU2
166.5 5.7 6
Function TOL TOL Type t6 = 5 - 40s CDTF = 1 - 100 AL = 50 - 100%
Trip Only 400% 5sec
51 G Function EF Method RCT Ip = 1,5,50 A AL = 0.1(0.1)
0.1 - 3.2 A
Function 27 Un = 230 - 690 V AL = 50 - 100% U< = 50 -100% t< = 0.2 - 5 s RVL = 50 - 100 % MAT = 0.0 - 5.0 s PDT = 0 - 1200 s SST = 0 - 1200s
Alarm Only Measure 1 0.3 Alarm level Enable 415 Alarm level 80 Trip level 70 Trip delay for DOL/RCU 0 90 Reset Voltage Level 0 Auto reclosing time Note-1 5 As per annexure-III
ST
NR-DOL/RCU Starter Type
Ext CT1 Ip = 10 - 6300A Ext CT Is = 0.01 - 3.20 A
310 1
MRD
As per Motor Data
In = 31 - 310A Ist = 1.0 - 10 In Tst = 1 - 600s 49
23
16E
110
186
TYPE-B
MCU2
186.0 5.7 6
Function TOL TOL Type t6 = 5 - 40s CDTF = 1 - 100 AL = 50 - 100%
Startup ratio
Trip Only 400% 5sec
51 G Function EF Method RCT Ip = 1,5,50 A AL = 0.1(0.1)
Nominal current
Enable Standard 12 As per Motor Data 4 cool down time fact. 90 Alarm level
51 LR Stall Protection Trip Level KORC 1A Trip Delay
27
Startup ratio
Enable Standard 15 As per Motor Data 4 cool down time fact. 90 Alarm level
51 LR Stall Protection Trip Level KORC 1A Trip Delay
27
Nominal current
Alarm Only Measure 1 0.3 Alarm level
Enable 415 80 Alarm level 70 Trip level Trip delay for DOL/RCU 0 90 Reset Voltage Level Auto reclosing time 0 Note-1 5 As per annexure-III Of the QGX – Rev G report
A14 221661/02/B - OCT 2007/14 of 14 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
Mott MacDonald CTJV ST
0.1 - 3.2 A
NR-DOL/RCU Starter Type
Ext CT1 Ip = 10 - 6300A Ext CT Is = 0.01 - 3.20 A
400 1
MRD
As per Motor Data
In = 40 - 400A Ist = 1.0 - 10 In Tst = 1 - 600s 49
24 Cub600
132
240
TYPE-A
MCU2
Success
Function TOL TOL Type t6 = 5 - 40s CDTF = 1 - 100 AL = 50 - 100%
51 LR Stall Protection Trip Level Trip Delay
51 G Function EF Method RCT Ip = 1,5,50 A AL = 0.1(0.1)
Function 27 Un = 230 - 690 V AL = 50 - 100% U< = 50 -100% t< = 0.2 - 5 s RVL = 50 - 100 % MAT = 0.0 - 5.0 s PDT = 0 - 1200 s SST = 0 - 1200s
240.0 5.8 6
Nominal current Startup ratio
Enable Standard 18 As per Motor Data cool down time fact. 4 Alarm level 90 Trip Only 400% 5sec
Alarm Only Measure 1 0.3 Alarm level Enable 415 80 70 Trip delay for DOL/RCU 0 90 Reset Voltage Level Auto reclosing time 0 Note-1 5 As per annexure-III Of the QGX – Rev G report
For the five LNG circulating Siemens panels are presented below:
pumps
(415V
-
104.4
kW)
supplied
by
the
LDB
27-MP 7111and 27-MP 7112 at the switchboard LDB 27302 27-MP 7113 at the switchboard LDB 27305 27-MP 7114 and 27-MP 7115 at the switchboard LDB 27306 The protection relay in use is GE multilin MM2, setting of which is provided by CTJV 17 and presented below:
17
Email from Vincent to Manoj Gupta; dated 28/09/2007; subject: RE: QGXE2A4042 / CLP - LDB Relays in Satellite SS2701A, SS-2702A/B/C – Settings; Attachment: MM2 Setpoint File Information.pdf
A15 221661/02/B - OCT 2007/15 of 15 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
A16 221661/02/B - OCT 2007/16 of 16 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Mott MacDonald CTJV
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
A17 221661/02/B - OCT 2007/17 of 17 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Mott MacDonald CTJV
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
A18 221661/02/B - OCT 2007/18 of 18 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Mott MacDonald CTJV
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
A19 221661/02/B - OCT 2007/19 of 19 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Mott MacDonald CTJV
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
Mott MacDonald CTJV
A-2: HV feeders relay setting schedule
S.No.
Switch Board ID
Voltage (kV)
Panel Number
Feeder Name
Device Type / Manufacturer
CT ratio
Device Duty
Setting range
Setting
Remark
Schedule for 33 kV feeders
2000/1
1
SB27101A
33
A1 B1
Incoming A/B TR27101 A/B
51
I> = 0.05-40 Curve = NI, EI, VI, DT k = 0.05 - 1.5
50
I>> = 0.05-40
50N
t>> = 0.02 to 300s I0>> = 0.05 - 40 k = 0.05 - 1.5
0.95 Curve = NI 0.12
1
Output to ATS
0.02 0.05 0.05 (NI)
Output to ATS
REF 542 + 51N
51G 400/1
A20 221661/02/B - OCT 2007/20 of 1 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
I0>> = 0.05-40 Curve = NI, EI, VI, DT k = 0.05 - 1.5 t0>>DT = 0.04 to 300s
0.05 Curve = DT
I0> = 0.05-40 Curve = NI, EI, VI, DT k = 0.05 - 1.5
I0>0.25 Curve = DT
t0>DT = 0.04 to 300s
t0>DT = 0.72
0.42
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
S.No.
Switch Board ID
Voltage (kV)
Panel Number
Feeder Name
Mott MacDonald CTJV
Device Type / Manufacturer
CT ratio
Device Duty 51
2
3
SB27101A
SB27101A
33
33
A2 B2
A4 B4
TR-27204 A/B
TR-27604 TR-27605
REF 542 +
REF 542 +
Setting Setting range I> = 0.05-40 Curve = NI, EI, VI, DT k = 0.05 - 1.5
Remark 0.75
Curve = NI 0.15
50
I>>> = 0.05-40 t>>> = 0.015 to 300s
9.85 0.015
27
U< pickup (relay logic) Time delay
51N
I0> = 0.05-40 Curve = NI, EI, VI, DT t0>DT = 0.04 to 300s
I0>0.15 Curve = DT t0>DT = 0.12
51
I> = 0.05-40 Curve = NI, EI, VI, DT k = 0.05 - 1.5
Curve = EI
600/1 50% 4s
CB Open (Not to trip)
1.25 0.2
50
I>>> = 0.05-40 t>>> = 0.015 to 300s
10.35 0.015
27
U< pickup (relay logic) Time delay
51N
I0> = 0.05-40 Curve = NI, EI, VI, DT
I0>0.15 Curve = DT
t0>DT = 0.04 to 300s
t0>DT = 0.12
600/1
A21 221661/02/B - OCT 2007/21 of 2 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
50% 4s
CB Open (Not to trip)
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
S.No.
Switch Board ID
Voltage (kV)
Panel Number
Feeder Name
Mott MacDonald CTJV
Device Type / Manufacturer
CT ratio
Device Duty
51
4
SB27101A
33
A5 B5
TR-27603 TR-27606
REF 542 +
SB27101A
33
A6 B7
SB-27104 SB-27105
REF 542 +
Setting
Remark
I> = 0.05-40 Curve = NI, EI, VI, DT k = 0.05 - 1.5
Curve = EI
1.25 0.2
50
I>>> = 0.05-40 t>>> = 0.015 to 300s
10.35 0.015
27
U< pickup (relay logic) Time delay
51N
I0> = 0.05-40 Curve = NI, EI, VI, DT
I0>0.15 Curve = DT
t0>DT = 0.04 to 300s
t0>DT = 0.12
I> = 0.05-40 Curve = NI, EI, VI, DT k = 0.05 - 1.5
Curve = EI
600/1
51
5
Setting range
50% 4s
1.65 0.05
50
I>>> = 0.05-40 t>>> = 0.015 to 300s
6.85 0.015
27
U< pickup (relay logic) Time delay
51N
I0> = 0.05-40 Curve = NI, EI, VI, DT
I0>0.15 Curve = DT
t0>DT = 0.04 to 300s
t0>DT = 0.12
600/1
A22 221661/02/B - OCT 2007/22 of 3 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
50% 4s
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
S.No.
6
Switch Board ID
SB27101A
Voltage (kV)
33
Panel Number
A7 B6
Feeder Name
SB-27102 SB-27103
Mott MacDonald CTJV
Device Type / Manufacturer
REF 542 +
CT ratio
Device Duty
Setting range
Setting
51
I> = 0.05-40 Curve = NI, EI, VI, DT k = 0.05 - 1.5
0.75 Curve = NI 0.29
50
I>>> = 0.05-40 t>>> = 0.015 to 300s
6.85 0.15
27
U< pickup (relay logic) Time delay
50% 4s
51N
I0> = 0.05-40 Curve = NI, EI, VI, DT
I0>0.25 Curve = DT
t0>DT = 0.04 to 300s
t0>DT = 0.12
I> = 0.1-4 Curve = NI, EI, VI, DT k = 0.05 - 3.2
Curve = NI
400/1
51
7
SB27102 SB27103
33
RMU outgoing feeder to SB27201
RMU outgoing feeder
7SJ600
Remark
0.7 0.2
50
I>>> = 0.1-25 t>>> = 0.0 to 60s
6.9 0.01
27
U< pickup (relay logic) Time delay
50% 4s
51N
I0> = 0.05-25 Curve = NI, EI, VI, DT
I0>0.25 Curve = DT
t0>DT = 0.0 to 60s
t0>DT = 0.12
400/1
A23 221661/02/B - OCT 2007/23 of 4 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
S.No.
8
Switch Board ID
SB27104 SB27105
Voltage (kV)
33
Panel Number
RMU outgoing feeder BOG Compressor
Feeder Name
RMU outgoing feeder
Mott MacDonald CTJV
Device Type / Manufacturer
7SJ600
CT ratio
Device Duty
600/1
A24 221661/02/B - OCT 2007/24 of 5 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Setting range
Setting
Remark
51
I> = 0.1-4 Curve = NI, EI, VI, DT k = 0.05 - 3.2
1.6 Curve = EI 0.05
50
I>>> = 0.1-25 t>>> = 0.0 to 60s
6.9 0.01
27
U< pickup (relay logic) Time delay
50% 4s
51N
I0> = 0.05-25 Curve = NI, EI, VI, DT
I0>0.15 Curve = DT
t0>DT = 0.0 to 60s
t0>DT = 0.12
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
Mott MacDonald CTJV
A-3: Interface with Kahramaa - Schedule for 87L and 87T protection S.No.
Switch Board ID
Voltage (kV)
Panel Number
Feeder Name
Device Type / Manufacturer
CT ratio
Device Duty
Setting range
Setting
Remark
Schedule for line differential protection From up stream 400/1
A7
1A
SS-2702
33
All outgoing 33 kV feeders
SS-2702
87L
Down stream 400/1
A2-A6
From
1B
Solkor-N B6
33
All outgoing 33 kV feeders
up stream 600/1 Solkor-N B2-B5, B7
87L
Down stream 600/1
A25 221661/02/B - OCT 2007/25 of 1 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Id> = 0.1 - 2.5 In BS1 = 20 - 150 % BS2 = 30 - 150 % Ibreak = 0.5 - 20.0 In td> 0.0 - 10 s CT Ratio Cor = 0.50 - 1.0 CT Ratio Cor = 0.50 - 1.0 Internal Trip = ON, OFF External Trip = ON, OFF Delay Ex. Trip = 0.0 - 10s
0.1 20 150 1 0.05 1 1 OFF ON 0
Differential current 1st Bias slope 2nd Bias slope Bias break point Differential delay At up-stream relay At down stream relay
Id> = 0.1 - 2.5 In BS1 = 20 - 150 % BS2 = 30 - 150 % Ibreak = 0.5 - 20.0 In td> 0.0 - 10 s CT Ratio Cor = 0.50 - 1.0 CT Ratio Cor = 0.50 - 1.0 Internal Trip = ON, OFF External Trip = ON, OFF Delay Ex. Trip = 0.0 - 10s
0.1 20 150 1 0.05 1 1 OFF ON 0
Differential current 1st Bias slope 2nd Bias slope Bias break point Differential delay At up-stream relay At down stream relay
External trip delay
External trip delay
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
S.No.
2
Switch Board ID
Interface with KM 132 kV SSRLS2
Voltage (kV)
132
Panel Number
132 kV KM S/S Outgoing feeders to QGXCLP
Feeder Name
Mott MacDonald CTJV
Device Type / Manufacturer
CT ratio
Device Duty
800/1
C30
7SD53
87L
800/1
C40
C30
3
Interface with KM 132 kV SSRLS2
132
132 kV KM S/S Outgoing feeders to QGXCLP
800/1
REL 561
C40
87L
800/1
Setting range
A26
Remark
I-Diff> = 0.1 - 20.00 A
0.12
I-Diff> pickup value
I-Diff>Switch On TD I-Diff>= 0.0 - 60.0 s T310 Iphas = 0.0 to 0.5 s Ic-Com = ON, OFF IcSTAB/IcN = 2.0 - 4.0 I-Diff>> = 0.8 - 100.0 A I-Diff>>Switch On Inrush restraint = ON, OFF I2/In = 10 - 45% Cross block = NO, YES Imax-inrush = 1.1 - 25.0 A Cross B 2HM
0.36 0 0 OFF 1.25 5 ON 15 NO 9 0
I-Diff> under switch on Time delay for I-Diff
CTFactor = 0.4-1.0 IminSat = 100-1000% In IminOp = 20-150% In IdiffLvl1= 20-150% Ib IdiffLvl2= 30-150% Ib ILvl1/2Cross = 100-1000% Ib Evaluate = 2 of 4, 3 of 4 AsymDelay = 0.0 - 5.0 ms DiffSync = Mater, Slave CCComp = ON, OFF
221661/02/B - OCT 2007/26 of 2 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Setting
1 300 20 50 100 350 3 of 4 0 Master Slave OFF
Charging current comp. Ic stabilization I-Diff>> pickup value
2nd Harmonic % of In Max. inrush peak value
CT matching factor Imin for saturation detection Idiff pickup Slope 1 Slope 2 Slope 2 intersection Tripping condition Asymmetrical delay At Kahramma substation At QGX-CLP SS-2702 Charging current comp.
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
S.N o.
4
SB ID
SB27101
Voltage (kV)
33
Panel Number
A1 B1
Feeder Name
TR-27101 A/B
Device / Manufactur er
7UT612
Mott MacDonald CTJV
CT ratio
Up stream 800/1
Device Duty
87T
Down stream 2000/1
Setting range
Diff. Prot. INC. CHAR.START INRUSH 2. HARM. REST.n.HAR. I-Diff>Mon I>Curr. GUARD DIFFw.IE1-MEAS DIFFw.IE2-MEAS I-DIFF> 0.05 - 2.00 (0.01) T I-DIFF> = 0.0 - 60.00s I-DIFF>> = 0.5-35.0 (0.1) T-IDIFF>> = 0.0 - 60.00s SLOPE 1= 0.1 - 0.5 BASE Point1 = 0.0 - 2.00 SLOPE 2 = 0.25 - 0.95 BASE Point2 = 0.0 - 10.0 I-REST. STARTUP = 0.0 - 2.0 START-FACTOR = 1.0 - 2.0 T START MAX = 0 - 180s I-ADD ON STAB = 2.0 - 15.0 T ADD ON STAB = 2- 250 2. HARMONIC = 10- 80% CROSSB.2.HARM = 2-1000 n. HARMONIC = 10 - 80% CROSSB.n.HARM = 2-1000 IDIFFmax.n.HM = 0.5 - 20 I-DIFF>MON T I-DIFF>MON = 1 - 10s
A27 221661/02/B - OCT 2007/27 of 3 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Setting
ON OFF ON 5. Harm ON 0 NO NO 0.25 0 4.7 0 0.25 0.5 0.5 1 0.1 1 0 3 250 15 20 30 0 1.5 0.25 2
Remark
Increase of trip char. Inrush 2nd Harm. Restraint nth Harmonic Restraint Diff. current monitoring I> for current guard
Id> pickup Time delay for Id> Id>> pickup Time delay for Id>>
Differential relay characteristic
I-RESTRAINT for start detc. Factor for increasing Char. Starting time Pickup for ADD on Stability Cycles for ADD on stability 2nd Harmonic Content in Id> Cycles for cross block 2nd harm. nth Harmonic in Id> Cylces for cross block nth harm. Limit Id> max for nth harm. Rest. Diff current for monitoring Monitoring time delay
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
S.No.
5
Switch Board ID
SB27101
Voltage (kV)
Panel Number
A1 33
Feeder Name
Mott MacDonald CTJV
Device Type / Manufacturer
TR-27101 A/B
7UT612
33 B1
87N 2000/1
Up stream 800/1
A1
SB27101
Device Duty
400/1
B1
6
CT ratio
TR-27101 A/B
REF 542 +
87T Down stream 2000/1
Setting range
REF Prot = ON, OFF, BLOCK I-REF> = 0.05 - 2.0 In TD-IREF = 0.0 - 60.0 s Slope = 0.00 - 0.95 VG = 0 - 11 Earthing P: Yes / No Earthing S: Yes / No Ip = 10 - 100000 A Is = 10 - 100000 A Ith = 0.1 - 0.5 Ir URL = 0.5 - 5.0 SBRT = 0.2 - 2.0 SBRL = 1.00 - 2.00 Ir Slope = 0.4 - 1.0 Trip Id> = 5.00-40.00 I2 Block= 0.1 - 0.3 I5 Block = 0.1 - 0.3
A28 221661/02/B - OCT 2007/28 of 4 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Setting
Remark
ON 0.25 0 0.5
I REF> pickup value Time delay Slope of characteristic 0
Transformer vector gp.
Yes Yes 437 1750 0.2 0.5 0.25 1 1 5 0.3 0.3
Threshold current Unbiased region limit Slightly biased threshold Slightly biased region limit Third region slope Upper Id threshold for trip 2nd harmonic threshold 5th harmonic threshold
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
Mott MacDonald CTJV
A-3: 33/6.6 kV and 6.6/0.415 kV transformer relay setting schedule S. Switch No Board ID .
Voltage Feeder Name (kV)
Device Type / Device CT ratio Setting range Manufacturer Duty
Setting
Remark
Schedule for 6.6 kV switch board SB-27204
51
50 2500
50N
51N
51G 400/1
REF 542 +
1 SB-27204
6.6
I> = 0.05-40 Curve = NI, EI, VI, DT k = 0.05 - 1.5 t>DT = 0.02 to 300s
0.85 NI 0.07
I>> = 0.05-40 t>> = 0.02 to 300s I0>> = 0.05 - 40 k = 0.05 - 1.5
1.6 0.015 0.05 0.05 (NI)
I0>> = 0.05-40 Curve = NI, EI, VI, DT k = 0.05 - 1.5 t0>>DT = 0.04 to 300s
0.05 DT 0.72
I0> = 0.05-40 Curve = NI, EI, VI, DT k = 0.05 - 1.5 t0>DT = 0.04 to 300s
27
U< = 0.1 - 1.2 Un t< = 40 - 30,000 ms
87
VG = 0 - 11 Earthing P: Yes / No Earthing S: Yes / No Ip = 10 - 100000 A Is = 10 - 100000 A Ith = 0.1 - 0.5 Ir URL = 0.5 - 5.0 SBRT = 0.2 - 2.0 SBRL = 1.00 - 2.00 Ir Slope = 0.4 - 1.0 Trip Id> = 5.00-40.00 I2 Block= 0.1 - 0.3 I5 Block = 0.1 - 0.3
0.25 DT 1.02 0.7 70
PT 6.6/0.11
Incoming A/B TR-27204 A/B 20000 kVA
87L
Solkor-N (33 kV side)
600/1
11 Transformer vector gp. No Yes 437
Id> = 0.1 - 2.5 In BS1 = 20 - 150 % BS2 = 30 - 150 % Ibreak = 0.5 - 20.0 In td> 0.0 - 10 s CT Ratio Cor = 0.50 - 1.0 Internal Trip = ON, OFF OFF External Trip = ON, OFF ON Delay Ex. Trip = 0.0 - 10s
A29 221661/02/B - OCT 2007/29 of 1 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
2092
0.1 Threshold current 0.5 Unbiased region limit 0.2 Slightly biased threshold 1 Slightly biased region limit 0.5 Third region slope 9 Upper Id threshold for trip 0.3 2nd harmonic threshold 0.3 5th harmonic threshold 0.2 Differential current 20 1st Bias slope 150 2nd Bias slope 1 Bias break point 0.05 Differential delay 1 CT raio correction
0 External trip delay
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
S. Switch No Board ID .
Voltage Feeder Name (kV)
Device Type / Device CT ratio Setting range Manufacturer Duty
2500 2 SB-27204
6.6
Bus Coupler
Mott MacDonald CTJV
REF 542 +
PT 6.6/ 3 /
51
25
0.110/ 3
6.6
DTR27305A/B 1000 kVA
REF 542 +
150/1
I> = 0.05-40 Curve = NI, EI, VI, DT k = 0.05 - 1.5
51
6.6
TR-27303A/B 1600 kVA
REF 542 +
200/1
6.6
SB-27205A/B
REF 542 +
500/1
15 Time delay 0.65 NI 0.2
200A
I0> = 0.05-40 Curve = NI, EI, VI, DT t0>DT = 0.04 to 300s I> = 0.05-40
0.35 DT 0.12
0.85 NI
0.19
50
I>>> = 0.05-40 t>>> = 0.015 to 300s
51N
I0> = 0.05-40 Curve = NI, EI, VI, DT t0>DT = 0.04 to 300s
DT
I> = 0.05-40 Curve = NI, EI, VI, DT k = 0.05 - 1.5
NI
51
5 SB-27204
0.07
0.05 Delta voltage 10 Delta phase
I> = 0.05-40 Curve = NI, EI, VI, DT k = 0.05 - 1.5
Curve = NI, EI, VI, DT k = 0.05 - 1.5 4 SB-27204
NI
V = 0.02 - 0.4 Un Phase = 5 - 50 Deg.
Fuse ABB-CEF
51N
50
I>>> = 0.05-40 t>>> = 0.015 to 300s
51N
I0> = 0.05-40 Curve = NI, EI, VI, DT t0>DT = 0.04 to 300s
Remark 0.85
TD = 0.2 - 1000s 51
3 SB-27204
Setting
20 0.015 0.25 0.12 2.35 0.05 11.75 0.015 0.25 DT
A30 221661/02/B - OCT 2007/30 of 2 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
0.42
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
S. Switch No Board ID .
Voltage Feeder Name (kV)
Mott MacDonald CTJV
Device Type / Device CT ratio Setting range Manufacturer Duty
Schedule for 11 kV switch b oard SB-27603 51 I> = 0.05-40 Curve = NI, EI, VI, DT k = 0.05 - 1.5 t>DT = 0.02 to 300s 50 REM 543
700/1
51N
51G REF542+
REM 543 SB-27603 1 To SB27606
11
Incoming TR-27603 to TR-27606 25000 kVA
400/1
I0>> = 0.05-40 Curve = NI, EI, VI, DT k = 0.05 - 1.5 t0>>DT = 0.04 to 300s I0> = 0.05-40 Curve = NI, EI, VI, DT k = 0.05 - 1.5 t0>DT = 0.04 to 300s
27
U< = 0.1 - 1.2 Un t< = 40 - 30,000 ms
87
VG = 0 - 11 Earthing P: Yes / No Earthing S: Yes / No Ip = 10 - 100000 A Is = 10 - 100000 A Ith = 0.1 - 0.5 Ir URL = 0.5 - 5.0 SBRT = 0.2 - 2.0 SBRL = 1.00 - 2.00 Ir Slope = 0.4 - 1.0 Trip Id> = 5.00-40.00 I2 Block= 0.1 - 0.3 I5 Block = 0.1 - 0.3
Remark
1.55 From 11 kV, 9500 kW Motor relay 0.78
EI
Used for 51LR 4.75 2 0.15 DT 0.12 0.25 DT 0.72 0.7 From 11 kV, 9500 kW 70 Motor relay
PT 6.6/0.11
REF542+
87L
Solkor-N (33 kV side)
I>> = 0.05-40 t>> = 0.02 to 300s I>>> = 0.05-40 Op. mode I>>>
Setting
600/1
11 Transformer vector gp. No Yes 437 1312 0.1 Threshold current 0.5 Unbiased region limit 0.2 Slightly biased threshold 1 Slightly biased region limit 0.5 Third region slope 9 Upper Id threshold for trip 0.3 2nd harmonic threshold 0.3 5th harmonic threshold
Id> = 0.1 - 2.5 In BS1 = 20 - 150 % BS2 = 30 - 150 % Ibreak = 0.5 - 20.0 In td> 0.0 - 10 s
0.2 Differential current 20 1st Bias slope 150 2nd Bias slope 1 Bias break point 0.05 Differential delay
CT Ratio Cor = 0.50 - 1.0 Internal Trip = ON, OFF External Trip = ON, OFF
1 CT raio correction OFF ON
Delay Ex. Trip = 0.0 - 10s
A31 221661/02/B - OCT 2007/31 of 3 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
0 External trip delay
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
S. Switch No Board ID .
Voltage Feeder Name (kV)
Mott MacDonald CTJV
Device Type / Device CT ratio Setting range Manufacturer Duty
Setting
Remark
Schedule for 0.415 kV switch boards
51
2500/1 1
TR-27303A/B SB-27303 0.415 TR-27301A/B SB-27301 1600 kVA
I> = 0.05-40 Curve = NI, EI, VI, DT
NI
k = 0.05 - 1.5
0.09
50
I>> = 0.05-40 t>> = 0.02 to 300s
4 For ATS 0.02 operation
27
U< = 0.1 - 1.2 Un t< = 40 - 30,000 ms
REF 542 +
51G 10/1
51
I0> = 0.05-40 Curve = NI, EI, VI, DT t0>DT = 0.04 to 300s
50
I>> = 0.05-40 t>> = 0.02 to 300s
27
U< = 0.1 - 1.2 Un t< = 40 - 30,000 ms
1600/1
0.7 70 0.25 DT 0.52
I> = 0.05-40 Curve = NI, EI, VI, DT k = 0.05 - 1.5
LDBDTR27302, 27302, 27305, 2 27305, 0.415 27306, 27306, 27307 A/B 27307 A/B 1000 kVA
1.05
0.95 NI 0.09 6.2 For ATS 0.02 operation
REF 542 +
51G 10/1
I0> = 0.05-40 Curve = NI, EI, VI, DT t0>DT = 0.04 to 300s
0.7 70
0.25 DT
A32 221661/02/B - OCT 2007/32 of 4 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
0.52
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
Mott MacDonald CTJV
A-4: MV motor relay setting schedule Following functional blocks are used for the motor protection using REM 543
Relay REM 543
Protection Duty 51(I>) 50 (I>>>) 51N(I0>)
Non directinal over current low set Non directinal over current inst. Non directinal earth fault low set
Functional block name NOC3Low NOC3Inst NEF1Low
27(U<) 27 (U<<)
Undervoltage low set Undervoltage high set
UV3LOW UV3High
59 (U>)
Overvoltage low set
OV3Low
49
Thermal overload
TOL3Dev
46
Negative phase sequence
NPS3Low
66
Start-up supervision
MotStart
37 (I<)
Under current
NUC3St1
51LR
Lock rotor protection
NOC3High
47
Three-phase phase sequence
PSV3ST1
87M
Motor differential
Diff6G
Function name
A33 221661/02/B - OCT 2007/33 of 5 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
S. Switch No Board ID .
Voltage Feeder Name (kV)
Device Type
CT ratio
PT ratio
Mott MacDonald CTJV
Device Setting range Duty
Setting
Schedule for 6.6 kV switch board SB-27201
1
SB-27201 SB-27204
6.6
27-PM7102 LNG Loading REM 543 pump 589 kW
100/1
27
U< = 0.1 - 1.2 Un t< = 0.1 - 300 s Operation Mode = 0,1,2
59
U> = 0.10 - 1.60 Un t> = 0.05 - 300 s Operation Mode = 0,1,2,3
1.15 5 1
49
Ist = 0.1-10.00 In Tst = 0.1 - 120.0 s NC-st = 1-3 Device Type = 0-6 Trip Temp. = 80-120 % Alarm Temp. = 40-100% Reset Temp. = 40-100% Am Temp.= -50-100 Deg C TC-cooling = 1.0-10.0 TC-Heating = 1-999 min ST-CS = 0.0-999.0 min LT-CS = 0.0-999.0 min p = 0.0 - 1.0 S-TR =50-350 Deg C Tmax S = 0.0-350 Deg C ST-CR = 0.0-999.0 min LT-CR = 0.0-999.0 min p = 0.0 - 1.0 R-TR =50-350 Deg C Tmax R = 0.0-350 Deg C
3.6 1 3 3 120 90 60 50 6 30 14 69 0.5 70 155 4 69 0.25 80 200
46
Operation Mode = 0-2 I2> = 0.01 - 0.5 In K = 5.0 - 100.0 Start Delay = 0.1 - 60 s Tmin = 0.1 - 120 s Tmax =500 - 10000 s T cooling = 5 - 10000 s
66
Operation Mode = 0 - 2 Ist = 1.0 - 10.0 In Tst = 0.3 - 250 s Time limit = 1.0 - 500.0s Countdwn Rate = 2.0-250 s/h Stall time = 2.0 - 120.0s
1 3.6 1.1 2 3
37
Op. mode Op. criteria I< = 0.1 - 0.99 In t< = 0.1 - 600.0 s I< Block t< blocking
2 0 0.1 300
6.6/0.1 1
51
I> = 0.10 - 5.0 Op. mode I> k = 0.05 - 1.0
Fuse ABB - CEF 7.2 kV 51N I0> = 1 - 100% Curve = NI, EI, VI, DT t0>DT = 0.05 to 300s 51LR I>> = 0.05-40 t>> = 0.05 to 300s
A34 221661/02/B - OCT 2007/34 of 6 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
0.7 0.5 1
2 0.05 5 1 7 3600 1800
Disable 0 1.35 EI 0.74 160 A
65 DT 0.12 2.7 0.5
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies S. Switch No Board ID .
Voltage Feeder Name (kV)
Device Type
CT ratio
PT ratio
Mott MacDonald CTJV
Device Setting range Duty
Setting
Schedule for 6.6 kV switch board SB-27603 27 U< = 0.1 - 1.2 Un t< = 0.1 - 300 s Operation Mode = 0,1,2
1
SB-27603 SB-27606
11
27-KM7101 Motor 9500 kW
REM 543
0.7 0.5 1
59
U> = 0.10 - 1.60 Un t> = 0.05 - 300 s Operation Mode = 0,1,2,3
1.15 5 1
49
Ist = 0.1-10.00 In Tst = 0.1 - 120.0 s NC-st = 1-3 Device Type = 0-6 Trip Temp. = 80-120 % Alarm Temp. = 40-100% Reset Temp. = 40-100% Am Temp.= -50-100 Deg C TC-cooling = 1.0-10.0 TC-Heating = 1-999 min ST-CS = 0.0-999.0 min LT-CS = 0.0-999.0 min p = 0.0 - 1.0 S-TR =50-350 Deg C Tmax S = 0.0-350 Deg C ST-CR = 0.0-999.0 min LT-CR = 0.0-999.0 min p = 0.0 - 1.0 R-TR =50-350 Deg C Tmax R = 0.0-350 Deg C
3.7 10 3 3 120 90 60 50 6 20 14 69 0.5 90 155 4 69 0.25 100 200
46
Operation Mode = 0-2 I2> = 0.01 - 0.5 In K = 5.0 - 100.0 Start Delay = 0.1 - 60 s Tmin = 0.1 - 120 s Tmax =500 - 10000 s T cooling = 5 - 10000 s
66
Operation Mode = 0 - 2 Ist = 1.0 - 10.0 In Tst = 0.3 - 250 s Time limit = 1.0 - 500.0s Countdwn Rate = 2.0-250 s/h Stall time = 2.0 - 120.0s
47
Operation Mode = 0 - 7 U2> = 0.01 - 1.00 t2> = 0.04 - 60.00 s
5 0.05 1
87
Id> = 5 - 50% TP1 = 0.0 - 1.0 In Starting ratio = 10 - 50% TP2 = 1.0 - 3.0 In Id>> = 5 - 30 In
10.0 0.5 50 1.5 5
51
I> = 0.10 - 5.0 Op. mode I> k = 0.05 - 1.0
700/1 11/0.11
2 0.05 8 1 7 3600 1800 1 3.7 11 40 30
1.55 2 (EI) 0.78
51LR I>> = 0.05-40 t>> = 0.05 to 300s Op. mode I>> 50 I>>> = 0.05-40 Op. mode I>>> 51N I0> = 1 - 100% Curve = NI, EI, VI, DT t0>DT = 0.05 to 300s
A35 221661/02/B - OCT 2007/35 of 7 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
2.8 0.5 1 4.75 2 15 1 (DT) 0.12
Electrical System Studies for QGX-CLP Development Project Relay Co-ordination Studies
Mott MacDonald CTJV
Appendix - B: TCC for relay co-ordination The TCC of the over current (O/C) and motor protections are arranges as follows
S.No.
Relay location
CT ratio
Reference location voltage
Switch Board number
1
DTR-27305
150/1
6.6 kV
SB-27204
2
TR-27303
200/1
6.6 kV
SB-27204
3
MR-27PM7104A
100/1
6.6 kV
SB-27205
4
MR-27KM7101C
700/1
11 kV
SB-27603
5
TR-27204
600/1
33 kV
SB-27101
6
TR-27201
400/1
33 kV
SB-27101
B1 221661/02/B - OCT 2007/1 of 1 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Mott MacDonald Relay Co-ordination Studies
CTJV
S.No.
Relay location
CT ratio
Reference location voltage
Switch Board number
1
DTR-27305
150/1
6.6 kV
SB-27204
B2 221661/02/B - OCT 2007/2 of 1 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Mott MacDonald Relay Co-ordination Studies
CTJV
S.No.
Relay location
CT ratio
Reference location voltage
Switch Board number
2
TR-27303
200/1
6.6 kV
SB-27204
B3 221661/02/B - OCT 2007/3 of 2 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Mott MacDonald Relay Co-ordination Studies
CTJV
S.No.
Relay location
CT ratio
Reference location voltage
Switch Board number
3
MR-27PM7104A
100/1
6.6 kV
SB-27205
B4 221661/02/B - OCT 2007/4 of 3 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Mott MacDonald Relay Co-ordination Studies
CTJV
S.No.
Relay location
CT ratio
Reference location voltage
Switch Board number
4
MR-27KM7101C
700/1
11 kV
SB-27603
Settings of relay at the outgoing RMU feeders from switchboard SB-27104/5, is set equal to the relay settings of the 33kV feeder TR-27601 from the switchboard SB-29103 of the QGX system. The time margin with the upstream relay will not be available when the SB-27601 and SB-27602 are supplied either from the QGX system or CLP system; due to the tight relay co-ordination at the 33kV and upstream relays.
B5 221661/02/B - OCT 2007/5 of 4 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP
Electrical System Studies for QGX-CLP Development Project Mott MacDonald Relay Co-ordination Studies
CTJV
S.No.
Relay location
CT ratio
Reference location voltage
Switch Board number
5
TR-27204
600/1
33 kV
SB-27101
B6 221661/02/B - OCT 2007/6 of 5 P:\Glasgow\PSB\EEG\3Jobs\221661 QGX\CLP Studies\Report\221661A - QGX-CLP - Relay Coordination-Rev1.doc/CLP