CRONOGRAMA DE EJECUCION DE OBRA : PABELLON DE IDIOMAS 1ERA ETAPA DIAGRAMA DIAGRAMA DE GANTT (TIEMPO (TIEM PO DE EJECUCION EJECUCI ON = 210 DÍAS DÍAS CALENDARIOS) 1° MES FASE
ACTIVIDAD OBRAS PROVISIONALES CASETA P/GUARDIANIA Y/O DEPOSITO DE MAT. CER CERCO PROV PROVIS ISIO IONA NALL CO CON ARP ARPIL ILLE LER RA Y RO ROLLIZ LLIZOS OS DE EUC EUCALI ALI INSTALACION PROVISIONAL DE ENERGIA ELECTRICA INSTALACION PROVISIONAL DE AGUA CARTELDE OBRA TRABAJOS PRELIMINARES TRA TRAZO Y REP REPLA LAN NTEO TEO DU DURAN RANTE EL PROC ROCESO ESO CON CONSSTRU TRUCTIV CTIVO O MOVIMIENTO DE TIERRAS T IERRAS EXCAVA EXCAVACIO CION N MASIVA MASIVA A MAQUIN MAQUINAA EN TERREN TERRENO O NORMAL NORMAL"C" "C"/RE /RE ELIMI ELIMINA NACI CION ON DE DESM DESMON ONTE TE,PR ,PROV OV.DE .DELL MOV. MOV.EN EN TERR TERREN ENO O NO DEMOLICION DE ALBAÑILERIA DEMOLICION DE VEREDAS RELLENO CON MATERIAL PROPIO SELECCIONADO RELLENO Y APISONADO CON MATERIAL SELECCIONADO PERFILADO E=0.15 M CONCRETO SIMPLE SOLADO PARA LOSA DE FUNDACION ME MEZCAL 1:12 CONCRETO 1:10 +30% P.G. PARA CIMIENTOS CORRIDOS ENC ENCOFR OFRADO ADO PA PARA CIME CIMEN NTAC TACION IONES REN RENDIMI DIMIEENTO NTO=15 =15 M2 M2/DIA /DIA CONCRETO 1:8+25% P.M. PARA SOBRECIMIENTOS ENCOFRADO Y DESENCOF. SO SOBRECIMIE MIENTO DE DE 0. 0.30 A 0.60 MT MT OBRAS DE CONCRETO ARMADO VIGAS DE CIMENTACION Y PLATEA DE CIMENTACION CONC CONCRE RETO TO EN VIGA VIGASS PLAT PLATEA EA DE CIMEN CIMENTA TACI CION ON F'C= C = 210 210 KG/C KG/C ENC ENCOFR OFRADO ADO Y DES DESENC ENCOFR OFRADO ADO VIG VIGAA Y PLA PLATE TEAA DE DE CIM CIMEN ENTA TA ACERO EN VIGA Y PLATEA DE CIMENTACION GRADO 60 TECNOPORT EN JUNTAS 2" MUROS DE CONTENCION REFORZADO CONCRETO EN MURO DE CONTENCION F 'C= 210 KG/CM2 ENCOFRADO Y DE DESENCOFRADO EN EN MU MURO DE DE CO CONTENCION ION ACERO EN MURO DE CONTENCION GRADO 60 TECNOPORT EN JUNTAS 2" COLUMNAS
S CONCRETO EN COLUMNAS F'C=210 KG/CM2 ENCOFRADO Y DESENCOFRADO NORMAL EN COLU A ACERO GRADO 60 EN COLUMNAS COLUMNAS R COLUMNAS DE AMARRE U CONCRETO EN COLUMNAS DE AMARRE F'C=175 KG/CM2 T ENC ENCOFR OFRADO ADO Y DES DESENC ENCOFR OFRADO ADO NOR NORMA MALL EN EN CO COLUMN LUMNAS AS DE A C ACERO GRADO 60 EN COLUMNAS DE AMARRE U TECNOPORT EN JUNTAS 2" EN COLUMNAS R VIGAS T VIGAS PRINCIPALES Y SECUNDARIAS S CONCRETO EN VIGAS F'C=210 KG/CM2 E ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS
ACERO GRADO 60 EN VIGAS VIGAS DE AMARRE CONCRETO EN VIGAS DE AM AMARRE F'C=210 KG/CM2 ENC ENCOFR OFRADO ADO Y DES DESENC ENCOFR OFRADO ADO NORMA ORMALL EN VIG VIGAS DE AMA AMAR ACERO GRADO 60 EN VIGAS DE AMARRE VIGAS DE ESCALERA CONCRETO EN VIGAS DE ES ESCALERA F'C=210 KG/CM2 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS ACERO GRADO 60 EN VIGAS VIGAS CHATAS CONCRETO EN VIGAS CHATAS F'C=210 KG/CM2 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS ACERO GRADO 60 EN VIGAS VIGAS DE BORDE CONCRETO EN VIGAS DE BORDE F'C=210 KG/CM2 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS ACERO GRADO 60 EN VIGAS LOSAS ALIGERADAS CONCRETO EN LOSAS ALIGERADAS F'C=210 KG/CM2 ENC ENCOFR OFRADO ADO Y DES DESEN ENC COFR OFRADO ADO NOR NORMA MALL EN EN LOS LOSAS AS ALI ALIG GERA ERA ACERO GRADO 60 EN LOSAS ALIGERADAS BLOQ BLOQUE UE HUEC HUECO/ O/CO CONC NCRE RETO TO 20X1 20X15X 5X30 30 CM PARA PARA TECH TECHO O ALI ALIGE GE LOSAS MACISAS CONCRETO EN LOSAS SOLIDAS F' F'C=210 KG KG/CM2 UNSAAC ENC ENCOFR OFRADO ADO Y DES DESENC ENCOFR OFRADO ADO NORMA ORMALL DE LOS LOSAS MAC MACIZAS IZAS ACERO GRADO 60 EN LOSAS MACIZAS ESCALERAS CONCRETO EN ESCALERAS F'C=210 KG/CM2 ENCOFRADO Y DESENCOFRADO NORMAL EN ESCALERAS ACERO GRADO 60 EN ESCALERAS PLACAS CONC CONCR RETO ETO EN EN MUR MURO OS TAB TABIQ IQUE UESS Y PLA PLACA CASS F'C F'C== 21 210 KG KG/CM2 /CM2 ENCO ENCOFR FRAD ADO O Y DESE DESENC NCOF OFRA RADO DO MURO MUROSS TABI TABIQU QUES ES Y PLAC PLACAS AS ACERO GRADO 60 EN MUROS TABIQUES Y PLACAS
MUROS Y TABIQUES MURO SOGA LA LADRILLO DE DE ARCILLA C/ C/M 1:4 X 1.5CM. MURO CABEZA LADRILLO DE ARCILLA C/ C/M 1:5 X 1.5CM. MURO MURO SOGA SOGA LADR LADRIL ILLO LO DE ARCI ARCILL LLAA C/M C/M 1:4 1:4 X 1.5C 1.5CM M PARA PARA M MUROS DE COSTILLA LADRILLO CORRIENTE REVOQUES ENLUCIDOS Y CIELO RASOS TAR TARRAJE RAJEO O DEL TIPO TIPO RAYAD AYADO O O PRIMA RIMAR RIO EN INTE INTER RIOR IORES C/ C/ TARRAJEO DE DEL TIPO RAYADO O PR PRIMARIO EN EXTERIORES TARRAJEO EN INTERIORES ACABADO CON CEMENTO-ARENA TARRAJEO EN EXTERIORES CON CEMENTO-ARENA TAR TARRAJE RAJEO O DE SUP SUPEERF.V RF.VIG IGAS AS PER PERAALTAD LTADAS AS--INDE INDEPPEND END.( .(EN EN EX EX TARR TARRAJ AJEO EO DE SUPE SUPERF RF.. VIG VIGAS AS PERA PERALT LTAD ADAS AS-I -IND NDEP EPEN END. D.(E (EN N IN IN TARRAJEO CO COLUMNAS EX EXTERIOR C/ C/MORTERO 1: 1:5 X 1. 1.5CM. TARRAJEO DE COLUMNAS INTERIORES INDEPENDIENTES TARRAJEO DE PLACAS EN EXTERIORES C:M 1:5 E=2cm TARRAJEO DE PLACAS INTERIORES C: C:M 1:5 E=2cm TARRAJEO DE MUROS REFORZADOS C:M 1:5 E=2cm TARRAJEO DE MURETES EN BARANDAS Y ESCALERAS C:M 1:5 TARRAJEO FINO PARA REVESTIMIENTO DE FONDO Y CARAS L TARRAJEO FINO PARA PIZARRAS UNSAAC
PTO S/ 2,237.40 2,11 2,118. 8.00 00 250.00 250.00 399.25 3,71 3,715. 5.46 46 19,250. 19,250.18 18 45,59 45,593.6 3.600 1,105.77 2,385.08 22,283.37 6,061.75 2,801.87
4° MES
SEMANA 3° SEMANA 4° SEMANA 1° SEMANA 2° SE
5° MES
3° SE SEMANA
4° SE SEMANA
1° SEMANA
2° SE SEMANA
1° SEMANA
2° SE SEMANA
7° MES
3° SE SEMANA
4° SE SEMANA
1° SEMANA
2°S 2°SEMAN MANA
3°S 3°SEMAN MANA
8° MES 4°SEMANA
1° SE SEMANA ANA
2°S 2°SEMAN MANA
2,237.40 2,118.00 250.00 250.00 399.25
250.00 399.25
3,715.46
3,715.46
19,250.18 45,593.60 1,105.77 2,385.08 22,283.37 6,061.75 2,801.87
19,250.18 45,593.60 1,105.77 2,385.08 22,283.37 6,061.75 2,801.87
7,289.88 1,488.34 1,083.31 823.31 706.20
7,289.88 1,488.34 1,083.31 823.31 706.20
129,716.94 23,487.96 202,280.65 1,031.21
129,716.94 23,487.96 101,140.33
101,140.33 1,031.21
17,729.15 13,872.59 15,940.71 1,828.02
17,729.15 13,872.59 15,940.71 1,828.02
27,038.17
40,557.26 22,665.67 211,499.10
13,519.09
15,110.45
7,555.22
140,999.40
70,499.70
600.84
2,403.37 1,723.16 2,733.50 2,329.45
1,802.53
430.79
68,086.57 43,107.32 79,313.86
1,292.37
683.37
2,050.12
776.48
1,552.96
34,043.28
68,086.57 43,107.32 79,313.86
34,043.28
21,553.66
21,553.66
39,656.93
3 9, 65 6 . 93
1,616.56 1,34 1,342. 2.67 67 1,811.71
808.28
1,616.56 1,342.67 1,811.71
808.28
671.34
671.34 905.85
473.21 347.53 550.79
905.85
473.21 347.53 550.79
473.21 347.53 550.79
1,019.90 467.81 1,942.63
509.95
1,019.90 467.81 1,942.63
509.95
233.90
233.90
971.32
971.32
1,404.94 1,821.96 2,677.56
1,404.94 1,821.96 2,677.56
1,404.94 1,821.96 2,677.56
27,234.38
54,468.76 41,177.67 28,059.78 30,512.22
27,234.38
20,588.84
20,588.84
14,029.89
14,029.89 15,256.11
4,394.60 2,37 2,379. 9.15 15 5,437.02
15,256.11
2,197.30
4,394.60 2,379.15 5,437.02
2,197.30
1,189.57
1,189.57
2,718.51
11,132.37 10,757.20 21,797.57 40,7 40,7660.27 0.27 27,4 27,476 76.6 .644 62,074.35
4°S 4°SEMAN MANA
250.00
2,403.37 1,72 1,723. 3.16 16 2,733.50 2,329.45
54,468.76 41,1 41,1777.67 7.67 28,059.78 30,5 30,512 12.2 .222
6° MES
3°S 3°SEMAN MANA
2,118.00
17,729.15 13,87 ,872.59 .59 15,940.71 1,828.02 40,557.26 22,665.67 211,499.10
3° MES
2,237.40
7,289.88 1,488.34 1,08 1,083. 3.31 31 823.31 706.20 .20 129,7 129,716 16.94 .94 23,4 23,4887.96 7.96 202,280.65 1,031.21
2° MES
1° SEMANA SEMANA 2°SE °SEMAN MANA 3°SE °SEMANA 4°SE °SEMAN MANA 1° SE SEMANA 2° SEMANA 3° SEMANA 4°SEM 4°SEMA ANA 1° SEMA SEMANA NA 2°SEMANA
L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D
2,718.51
11,132.37 10,757.20 21,797.57
11,132.37 10,757.20 21,797.57
20,380.14
40,760.27 27,476.64 62,074.35
20,380.14 13,738.32
13,738.32
31,037.18
31,037.18
1,356,054.13
2,829.69 19,622.46 666. 666.14 14 393.74 747. 747.72 72 525.28 8,139.27 3,363.21 4,38 4,388. 8.92 92 10,6 10,637 37.6 .633 1,776.65 4,936.61 2,912.46 10,992.74 3,618.55 762.78 2,178.94 860.03
1,414.84
2,829.69 19,622.46 666.14 393.74
1,414.84
9,811.23
9,811.23 333.07
333.07
196.87
196.87
37 3. 86
37 3 . 86
262.64
262.64
4,069.63
4,069.63 1,681.61
1,681.61 2,194.46
2,194.46
5,318.81
5,318.81
888.32
888.32 2,468.30
2,468.30
1,456.23
1,456.23 5,496.37
5,496.37
1,809.28
1,809.28 381.39
381.39
726.31 430.01
1,452.62 430.01
747.72 525.28 8,139.27 3,363.21 4,388.92 10,637.63 1,776.65 4,936.61 2,912.46 10,992.74 3,618.55 762.78 2,178.94 860.03
1° MES ACTIVIDAD
PTO S/
A L
2° MES
3° MES
4° MES
SEMANA 1° SEM SEMA ANA 2°SEM 2°SEMA ANA 3°SEM °SEMA ANA 4°SE °SEMAN MANA 1° SEM SEMA ANA 2°SE 2°SEMA MANA NA 3°SE °SEMANA 4°SE °SEMANA 1° SEM SEMANA 2°SE °SEMANA 3°SE °SEMANA 4°SE °SEMANA 1° SEM SEMANA 2° SE
5° MES
3° SE SEMANA
4° SE SEMANA
1° SEMANA
2° SE SEMANA
6° MES
3° SE SEMANA
4°SEMANA
1° SEMAN EMANA A
2°SE 2°SEMA MAN NA
7° MES
3° SE SEMANA
4° SE SEMANA
1° SE SEMANA
2° SE SEMANA
8° MES
3° SE SEMANA
4°SE °SEMAN MANA
1° SE SEMAN MANA
2°SEMANA
L MM J V S D L M M J V S D L M MJ V S D L M M J V S D L M MJ V S D L M M J V S D L M M J V S D L MM J V S D L M M J V S D L MM J V S D L M M J V S D L M MJ V S D L M M J V S D L M M J V S D L MM J V S D L M M J V S D L M MJ V S D L M M J V S D L M MJ V S D L M M J V S D L M M J V S D L MM J V S D L M M J V S D L M MJ V S D L M M J V S D L M M J V S D L MM J V S D L M M J V S D L M MJ V S D L M M J V S D
VESTIDURA DE DERRAMES 4,699.33 BRUÑAS DE 1/2" 1,452.12 CIELORRAS CIELORRASOS OS EN INTERIOR INTERIOR CON MEZCLA MEZCLA DE CEMENTOCEMENTO-ARE ARE 16,077.19 16,077.19 PISOS Y PAVIMENTOS CONTRAPISO DE 48 MM. 19,119.24 FALSO PISO 4" INCLUYE ENRROCADO 29,026.53 PISO DE TERRAZO CON ESTRIAS DE ALUMINIO 22,708.97 PISO CERAMICO 0.30X0.30 SERIE ORIGENES 1,693.40 P I S O CE C E R A M I C O SU S U P E R F O R T E AL A L T O TR T R A N S I T O 0. 0 . 3 0 X 0 . 3 0 16,457.70 A VEREDAS DE DE CO CONCRETOFC=140 KG KG/CM /CM2 E=10CM CO CON EM EMPED 892.31 .31 R SARDINELES FC=175 KG/CM2 DE 15*30 M 546.20 U TAPAJUNTAS METALICO 421.17 T CONTRAZOCALOS C CONTRAZOCALO DE TERRAZO E=1CM, H=0.15m 3,586.50 E CONTRAZOCALO DE CERAMICO H=0.15m COLOR 4,231.47 T I ZOCALOS ZOCALO DE CERAMICO 20X30 cm 2,329.44 U LISTELOS DE 7.5 X 20 cm 1,247.01 QCARPINTERIA DE MADERA R PUERT UERTAA DE MEL MELAMIN AMINAA CON BOR BORDES DES DE DE MADE MADER RA CED CEDR RO (1 (1 H 6,5 6,543.6 43.699 A PUERTA PUERTA DE MELAMI MELAMINA NA CON BORDES BORDES DE MADER MADERAA CEDRO CEDRO Y JA 10,14 10,140.1 0.122 CLOS CLOSET ETSS EMPO EMPOTR TRAD ADOS OS CON CON MELAM MELAMIN INAA DE18 DE18MM MM CORR CORRED EDIZ IZO O 2,13 2,138. 8.94 94 CLOSETS- ESTANTE EMPOTRADOS CON MELAMINA DE18MM 1,809.48 MAMPARA DE MELAMINA CON MARCOS DE CEDRO Y VIDRIOS 5,147.48 BARA BARAND NDAA DE MADE MADERA RA D=3" D=3" CON CON TUBO TUBO ELEC ELECTR TROS OSOL OLDA DADO DO 1 1/ 1,58 1,588. 8.22 22 PASAMANO DE MADERA D=3" CON TUBO ELECTROSOLDADO ELECTROSOLDAD O 1 1,002.80 1,002. 80 SEPARADORES DE DE UR URINA INARIOS IOS CO CON ME MELAMINA INA INC INC IN INSTALACI 124.08 .08 TAPAJUNTAS DE MADERA CEDRO DE 10" X 1/2" 33.54 CARPINTERIA METALICA SEPARA SEPARADOR DORES ES DE BAÑO BAÑO CON MELAMI MELAMINA NA CON FIERRO FIERRO CUADR CUADR 2,091. 2,091.68 68 PUERTAS EN SEPARADORES DE BAÑO CON MELAMINA 469.30 PUERTA METALICA DE INSPECCION A DUCTOS 195.84 PIZARRA ACRILICA 7,292.00 REJA METALICA DE PROTECCION VENTANAS ICL. PINT. ANTICO 8,750.28 CERRAJERIA BISA ISAGRA CAPUCHINA INA BRONCEADA DE 3 1/2" /2" X 3 1/2" /2" UNSAAC 980.10 .10 CERRADURA PARA PUERTAS DE VIDRIO O CRITAL 210.00 CERRADURA PTA.BAÑO TIPO PERILLAS UNSAAC 782.88 CERRADURA PARA PUERTA PRINCIPAL UNSAAC 167.22 CIERRAPUERTAS CIERRAPUERTAS FRENO HIDRAULICO PUERTAS VIDRIO 2,730.00 PICAPORTES DE FIERRO REDONDO DE 4" 222.32 VIDRIOS, CRISTALES Y SIMILARES VENTANA VIDRIO CRUDO COLOR GRISS 6mm CON PERFILES D 2,621.59 VENTANA VIDRIO CRUDO COLOR GRISS 8mm CON PERFILES D 597.19 PUERTA DE VIDRIO CRUDO COLOR BRONCE 10mm CON TUBO 6,006.97 VIDRIOS 6mm 340.06 VITROVENT 1,913.98 VIDRIO CATEDRAL INCOLORO 47.02 ESPE SPEJO BIS BISELAD ELADO O CORR CORRID IDO O ICL ICL. ARM ARMASON ASON DE MADER ADERAA Y SUJ 487.7 87.733 PINTURA PINTURA LATEX EN MUROS INTERIORES UNSAAC 14,127.89 PINTURALATEX EN DERRAMES 939.00 PINTURA ESMALTE EN PIZARRAS COLOR VERDE 280.71 APARATOS Y ACCESORIOS SANITARIOS 283,623.51 INODORO BLANCO CON GR GRIFERIA Y ACCESORIOS UNSAAC 1,379.00 LAVAT AVATOR ORIO IOSS TIP TIPO O OVA OVALI LIN N BLA BLANC NCO O INC INC. MES MESAA DE CON CONCRET CRETO O 1,4 1,400.0 00.000 LAVATORIOS TIPO MALIBU BLANCO C/P 70.00 URINARIOS DE LOZA DE PICO BLANCO UNSAAC 218.79 GRIFERIA DE URINARIOS UNSAAC 120.00 GRIFERIA DE LAVATORIOS UNSAAC 522.00 COLOCACION DE APARATOS SANITARIOS UNSAAC 619.68 GABINETE CONTRAINCENDIOS 1,100.29 RED DE CONEXION A TANQUE E INSTALACION PROVISIONAL AL EDIFICIO SISTEMA DE ALIMENTACION TUBERIA DE 3" PVC-SAP 864.05 TEE PVC-SAP 3" * 3/4" 19.92 CODO PVC SAP 3" 53.44 TUBERIA PVC SAP C-10 R 3/4" 622.69 CODO PVC-SAP3/4" 36.64 SISTEMAS DE CONDUCCIÓN AGUA POTABLE POTABLE A T. ELEVADO Y CONTRAINCENDIO TUBERIA DE AGUA PVC. DE 2"(50MM).INSTALACION.INC.PRUEB 2"(50MM).INSTALACION.INC.PRUEB 108.70 CODO PVC SAP 2" 26.58 CODO PVC SAP 2"X45° 13.65 SISTEMA DE CONTRAINCENDIO TUBE TUBERI RIAA FIER FIERRO RO GALV GALVAN ANIZ IZAD ADO O 2 " INSTA INSTAL. L.IN INC. C.PR PRUE UEBA BA HIDR HIDR.. 1,23 1,236. 6.38 38 CODO PVC SAP 2" 93.03 SISTEMA DE AGUA Y DESAGUE SISTEMA DE AGUA FRIA SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/2" 1,897.50 SISTEMA DE DESAGUE Y VENTILACION SALIDA DE DESAGÜE DE 2" 2,232.00 SALIDA DE DESAGÜE DE 4" 1,764.37 PROV ROVISIO ISION N E INST INSTAL ALAC ACIO ION N TU TUBERI BERIAA PVC PVC-SAL -SAL D=4 D=4" + PRUEB RUEB.H .HII 344.0 44.033 PROV ROVISIO ISION N E INST INSTAL ALAC ACIO ION N TU TUBERI BERIAA PVC PVC-SAL -SAL D=3 D=3" + PRUEB RUEB.H .HII 212.2 12.266 PROVISIO ISION N E INS INSTALACION ION TU TUBERIA PVC-SAL D= D=2" + PRUEB.HI .HI 86.13 .13 REGISTRO DE BRONCE CROMADO DE 4" 49.71 REGISTRO DE BRONCE CROMADO DE 3" 81.80 10.53 S REGISTRO DE BRONCE 2" SUMIDERO DE BRONCE 2" 60.18 A I CODO PVC SAL 4"X45° 65.46 147.84 R CODO PVC SAL 3"X45° 40.32 A YEE DE P.V.C. SAL SP,RAMAL CON REDUCCION DE 4"-3" 84.30 T YEE PVC SAL 4" I TEE PVC-SAL 3"* 2" 145.20 N COLECTOR DE AGUAS SERVIDAS A TRAZO Y REPLANTEO 162.30 S EXCAVACION DE TERRENO P/TUB COLECTOR AGUAS SERVIDA 4,939.19 2,358.03 S ELIMINACION DE EXCESO DE CORTE CON VOLQUETE, CARGUI 7,091.48 E RPEERLLFEILNAODOCOEN=M0.A15TEMRIAL PROPIO SELECCIONADO 127.73 N DEMOLICION DE VEREDAS 46.20 ODEMOLICION DE PAVIMENTO ASFALTICO DE 2" 98.22 I 56.82 C TUBERIA PVC SAL3" TUBERIA PVC SAL4" 38.88
783.22
1,566.44
1,174.83
4,699.33 1,452.12 16,077.19
1,174.83
726.06
726.06
8,038.60
8,038.60
19,119.24 29,026.53 22,708.97 1,693.40 16,457.70 892.31 546.20 421.17
19,119.24 29,026.53 11,354.49
11,354.49 1,693.40 16,457.70
892.31 546.20 421.17
3,586.50 4,231.47
3,586.50 4,231.47
1,164.72
2,329.44 1,247.01
1,164.72
623.51
623.51
6,543.69 10,140.12 2,138.94 1,809.48 5,147.48 1,588.22 1,002.80 124.08 33.54
6,543.69 10,140.12 2,138.94 1,809.48 5,147.48 1,588.22 1,002.80 124.08 33.54
2,091.68 469.30 195.84 7,292.00 8,750.28
2,091.68 469.30 195.84 7,292.00 8,750.28
980.10 210.00 782.88 167.22 2,730.00 222.32
980.10 210.00 782.88 167.22 2,730.00 222.32
2,621.59 597.19 6,006.97 340.06 1,913.98 47.02 487.73
14,127.89 939.00 280.71
1,379.00 1,400.00 70.00 218.79 120.00 522.00 619.68 1,100.29
19.92 53.44 622.69 36.64
26.58 13.65
1,236.38 93.03
1,236.38 93.03
1,897.50
1,897.50
1,116.00 882.19
1,116.00 882.19
172.01
172.01
106.13
106.13
43.07
43.07 49.71 81.80 10.53 60.18
65.46 147.84 40.32 84.30 145.20
2,358.03 7,091.48 127.73 46.20 98.22 56.82 38.88
1,379.00 1,400.00 70.00 218.79 120.00 522.00 619.68 1,100.29
108.70 26.58 13.65
108.70
4,939.19
14,127.89 939.00 280.71
864.05 19.92 53.44 622.69 36.64
864.05
162.30
2,621.59 597.19 6,006.97 340.06 1,913.98 47.02 487.73
2,232.00 1,764.37 344.03 212.26 86.13 49.71 81.80 10.53 60.18 65.46 147.84 40.32 84.30 145.20 162.30 4,939.19 2,358.03 7,091.48 127.73 46.20 98.22 56.82 38.88
A T S N I
1° MES ACTIVIDAD TUBERIA PVC SAL 6" TUBERIA PVC SAL10" CAJA DE REGISTRO DE DESAGUE C/TAPA Cº 10"X20" CAJA DE REGISTRO DE DESAGUE C/TAPA Cº 18"X24" CAJA DE REGISTRO DE DESAGUE C/TAPA Cº 28"X28" BUZO BUZON N TIPO TIPO I TER TERR. R.NO NORM RMAL AL E.D. E.D. C/CA C/CARG RG.+ .+VO VOLQ LQ.H .HAS ASTA TA 3.00 3.00M M SOPORTE METALICO T/ABRAZADERA P/TUB. DE DIAMETRO 3"SISTEMA DEDESAGUE DE AGUAS PLUVIALES TUBERIA PVC SAL3" TUBERIA PVC SAL4" ACCE ACCESO SORI RIO OS DE FIJA IJACIO CION DE RECU RECUBR BRIM IMIE IENT NTO O DE MONTAN NTANTE TE TAR TARRAJE AJEO DE DE RE RECUBR CUBRIM IMIE IENT NTO O DE DE MO MONTAN NTANTE TESS C:M 1:5 E=1 E=1.5 CODO PVC SAL 4"X45° CODO PVC SAL 3"X45° TEE PVC SAL 4" TEE PVC-SAL 3" SISTEMA COLECTOR DE AGUAS DE PLUVIALES TRAZO Y REPLANTEO EXCAVACION DE TERRENO P/TUB COLECTOR AGUAS SERVIDA ELIMINACION DE EXCESO DE CORTE CON VOLQUETE, CARGUI RELLENO CON MATERIAL PROPIO SELECCIONADO PERFILADO E=0.15 M TUBERIA PVC SAL3" TUBERIA PVC SAL4" TUBERIA PVC SAL 6" TUBERIA PVC SAL10" CAJA DE REGISTRO DE DESAGUE C/TAPA Cº 10"X20" CAJA DE REGISTRO DE DESAGUE C/TAPA Cº 12"X24" CAJA DE REGISTRO DE DESAGUE C/TAPA Cº 18"X24" CAJA DE REGISTRO DE DESAGUE C/TAPA Cº 24"X24" CAJA DE REGISTRO DE DESAGUE C/TAPA Cº 28"X28" BUZO BUZON N TIPO TIPO I TER TERR. R.NO NORM RMAL AL E.D. E.D. C/CA C/CARG RG.+ .+VO VOLQ LQ.H .HAS ASTA TA 2.00 2.00M M BUZO BUZON N TIPO TIPO I TER TERR. R.NO NORM RMAL AL E.D. E.D. C/CA C/CARG RG.+ .+VO VOLQ LQ.H .HAS ASTA TA 3.00 3.00M M SALIDA DE DESAGÜE DE 3" INSTALACIONES ELECTRICAS
PTO S/
2° MES
3° MES
4° MES
1° SEMANA 2°S 2°SEMA EMANA 3°S 3°SEMA EMANA 4°S 4°SEMA EMANA 1° SEMA EMANA 2°SEMANA 3° SEMANA 4° SEMANA 1° 1 ° SEMANA 2° 2 ° SEMANA 3°SEM 3°SEMA ANA 4°SEM 4°SEMA ANA 1° SEMANA SEMANA
2°SEMANA
3° SE SEMANA
5° MES 4° SE SEMANA
1° SEMANA
2° SE SEMANA
3° SE SEMANA
6° MES 4° SE SEMANA
1° SEMAN EMANA A
2°S 2°SEMAN EMANA A
3° SE SEMANA
7° MES 4° SE SEMANA
1° SEMANA
2° SE SEMANA
3° SE SEMANA
8° MES 4° SE SEMANA
1° SEMANA
2° SE SEMANA
L MM J V S D L M M J V S D L M M J V S D L MM J V S D L M M J V S D L M M J V S D L MM J V S D L M M J V S D L M M J V S D L MM J V S D L M M J V S D L M M J V S D L MM J V S D L M M J V S D L M M J V S D L MM J V S D L M M J V S D L M M J V S D L MM J V S D L M M J V S D L M M J V S D L MM J V S D L M M J V S D L M M J V S D L MM J V S D L M M J V S D L M M J V S D L MM J V S D L M M J V S D L M M J V S D
1,342.05 3,691.74 172.32 144.01 526.94 4,88 4,881. 1.72 72 522.99
1,342.05 3,691.74 172.32 144.01 526.94 4,881.72 522.99
1,342.05 3,691.74 172.32 144.01 526.94 4,881.72 522.99
56.82 38.88 557.1 57.166 1,9 1,924.9 24.911 10.91 24.64 15.17 10.42
56.82 38.88 557.16 1,924.91 10.91 24.64 15.17 10.42
56.82 38.88 ##### 1,924.91 10.91 24.64 15.17 10.42
239.17 3,974.06 1,459.35 5,705.79 231.54 44.60 378.43 1,369.51 5,856.89 258.48 121.20 144.01 579.39 263.47 1,03 1,030. 0.20 20 1,22 1,220. 0.43 43 149.40
239.17 3,974.06 1,459.35 5,705.79 231.54 44.60 378.43 1,369.51 5,856.89 258.48 121.20 144.01 579.39 263.47 1,030.20 1,220.43 149.40
239.17 3,974.06 1,459.35 5,705.79 231.54 44.60 378.43 1,369.51 5,856.89 258.48 121.20 144.01 579.39 263.47 1,030.20 1,220.43 149.40
67,591.92
LINEA DE ALIMENTACION PRINCIPAL Y A TABLEROS D E DISTRIBUCION
TUBERIAS PVC SAP (ELECTRICAS) D=2" TUBERIAS PVC SAP (ELECTRICAS) D=3" - ALIMENTACION CABLE ELECTRICO NYY 3 X 70 MM2. CABLE ELECTRICO NYY 3 X 6 MM2. CABLE NYY 3 X 10 MM2 - ALIMENTACION CABLE ELECTRICO NYY 3X25 MM2. A TABL. DIST. CABLE ELECTRICO NY NYY 1X16 MM2 A TABL. DISTRIB. CABLE ELECTRICO NYY 3X16 MM2. A TABL. DISTRIB. TUBERIAS PVC SAP (ELECTRICAS) D=2" TUBERIAS PVC SAP (ELECTRICAS) D=3" EXCAVACION PARA POZO DE TIERRA POZO POZO-C -CON ONEX EXIO ION N A TIE TIERR RRAA EN SIST SISTEM EMAA C/EQ C/EQ.B .BOM OMBE BEO, O,AL ALUM UMB, B, EXCAVACION RELLENO CON MAT FILTRANTE RELLENO COMPACTADO A MANO LADRILLO DE ARCILLA CORRIENTE TABLERO DE DISTRIBUCION CAJA METALICA CON PUERTA Y C INTERRUPTORES TERMOMAGNETICOS S SISTEMA DE DISTRIBUCION SALIDA DE TOMACORRIENTE CO CON PUESTA TIERRA A SALIDA DE TOMACORRIENTE TRIFASICO CON PUESTA TIERRA C SALIDA PARA TOMACORRIENTES MONOFASICO EN PISO I SALIDAA PARA PARA TOMA TOMACO CORR RRIE IENT NTES ES MONO MONOFA FASI SICO CO EN PISO PISO sin sin ca R SALID T SALIDA PARA TOMACORRIENTE AH=1.80 m SALIDAA PARA PARA TOMA TOMACO CORR RRIE IENT NTEE BIPO BIPOLA LAR R DOBL DOBLEE CON CON PVC PVC sin sin c C SALID W 4.0mmUNSAAC E SSAALLIIDDAA DDEE TTEECCHHOO TTW 4.0mmUNSAAC sin cableado ni acces. L SALIDA DE PARED (BRAQUETES) CON PVC E SALI SALIDA DA DE PARE PARED D (BR (BRAQ AQUE UETE TES) S) CON CON PVC PVC sin cab cable lead adoo ni ni acc acces es.. S CAJA DEPASO F°G° 200X200X30 MM. INC. TAPA E LUMINARIAS N LAMPARA FLUORESCENTE SIMPLE ADOSADA A PARED LAMPARA FLUORESCENTE SIMPLE ADOSADA A CIELO RASO O I LAMP LAMPAR ARAA FLU FLUOR ORES ESCE CENT NTEE DOB DOBLE LE CON CON RE REJIL JILLA ADOS ADOSAD ADAA A CI CI C LUMINA INARIA CEILIN ILING G LIG LIGTTH CL CLR 30 304 DE DE 60 60 W O EQ EQUIVA IVALENTE 1 *50 W O EQUIVALENTE A LUMINARIA WALL SPOTLIGTH 1* 3 *50 W O EQUIVALENTE L LUMINARIA WALL SPOTLIGTH 3* A REFLEXTOR LAMPARA HALOGENA DE 150 W PIPISO T LAMPARA VAPOR DE SODIO DE 150W CON POSTE DE C°A° S LAMPARA INCANDECENTE DE 50w FOTOCELULAS RELOJ N I INSTALACIONES ESPECIALES INTERNET SALIDA PARA RED INFORMATICA CAJA DE PASO METALICA DE 100X100X50 MM. INC. TA TAPA INTE TUBERIAS PVC SAP (ELECTRICAS) D=1 1/2" TV CABLE SALIDA PARA TELEVISION - CABLE CAJA DE PASO METALICA DE 100X100X50 MM. INC. TA TAPA TV-C TUBERIAS PVC SAP (ELECTRICAS) D=2" TELEFONO DIRECTO E INTERNO SALIDA PARA TELEFONIA INTERNA TUBERIAS PVC SAP (ELECTRICAS) D=1" TUBERIAS PVC SAP (ELECTRICAS) D=2" CAJA DE PASO METALICA ICA DE 400 400X250X50 MM. INC INC. TAPA TELE LUZ DE EMERGENCIA SALIDA IDA DE DE PA PARED (B (BRAQUETES) CO CON PV PVC PA PARA EM EMERGENCIA TUBE TUBERI RIAAS PVC SAP SAP (ELEC ELECTR TRIC ICAAS) D=1 D=1 1/2 1/2" PARA PARA EMER EMERGE GENC NCIA IA CAJA DEPASO F°G° 200X200X30 MM. INC INC. TAPA EMERGENCIA ALARMA CONTRAINCENDIO SALIDA PARA ALARMA CONTRAINCENDIO INC. SISTEMA TUBE TUBERI RIAAS PVC SAP SAP (ELEC ELECTR TRIC ICAAS) D=1 D=1 1/2 1/2" PARA PARA EMER EMERGE GENC NCIA IA
636.23 2,004.62 2,562.00 258.45 1,036.21 1,334.34 718.62 790.16 1,168.16 2,373.61 101.75 1,82 1,829. 9.88 88 138.03 45.30 107.94 239.20 1,154.79 2,406.83
636.23 2,004.62 2,562.00 258.45 1,036.21 1,334.34 718.62 790.16 1,168.16 2,373.61 101.75 1,829.88 138.03 45.30 107.94 239.20 1,154.79 2,406.83
636.23 2,004.62 2,562.00 258.45 1,036.21 1,334.34 718.62 790.16 1,168.16 2,373.61 101.75 1,829.88 138.03 45.30 107.94 239.20 1,154.79 2,406.83
4,327.68 3,760.00 455.40 274. 274.20 20 60.72 109. 109.68 68 3,817.80 3,887.84 1,271.51 1,10 1,106. 6.84 84 159.00
2,163.84
4,327.68 3,760.00 455.40 274.20 60.72 109.68 3,817.80 3,887.84 1,271.51 1,106.84 159.00
2,163.84
1,880.00
1,880.00
227.70
227.70
137.10
137.10
30.36
30.36
54.84
54.84
1,908.90
1,908.90
1,943.92
1,943.92
635.76
635.76
553.42
553.42
79.50
79.50
684.00 205.20 3,2 3,242.4 42.400 1,93 ,937.60 .60 574.20 477.60 636.80 1,356.80 59.40 111.53
684.00 205.20 3,242.40 1,937.60 574.20 477.60 636.80 1,356.80 59.40 #####
2,519.20 37.20 608.61
1,259.60
464.52 43.40 774.11
18.60 304.30
232.26
21.70
387.06
387.06
33.48
63.09
178.56
178.56
31.93
31.93
73.93
73.93
351.12
239.04 147.9 47.900
66.96 126.17 357.12 63.86
33.48
63.09
147.85 .85 702.2 02.244 159.00 .00
464.52 43.40 774.11
232.26
21.70
66.96 126.17 357.12 63.86 .86
2,519.20 37.20 608.61
1,259.60
18.60 304.30
147.85 702.24 159.00
351.12
79.50
79.50
#####
#####
73.95
73.95
239.04 147.90 1,761,149.06
53,879.50 1,761,149.06
188,638.56
451,121.07
395,825.12
230,491.88
295,038.43
118,624.78
58,728.14
684.00 205.20 3,242.40 1,937.60 574.20 477.60 636.80 1,356.80 59.40 111.53
22,681.07
1,761,149.06
FASE
ACTIVIDAD
Duración (días)
OBRAS PROVISIONALES CERCO PROVISIONAL CON ARPILLERA Y ROLLIZOS DE EU INSTALACION PROVISIONAL DE AGUA INSTALACION PROVISIONAL DE ENERGIA ELECTRICA CARTELDE OBRA ENCOFRADO Y DESENCOFRADO PARA PROTECCION DE D
0.50 0.50 1.00 1.00 1.00
TRABAJOS PRELIMINARES TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUC
4.00
OBRAS DE CONCRETO ARMADO COLUMNAS CONCRETO EN COLUMNAS F'C=210 KG/CM2 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS ACERO GRADO 60 EN COLUMNAS TECNOPORT EN JUNTAS 2" EN COLUMNAS
4.00 16.00 12.00 2.00
COLUMNAS DE AMARRE CONCRETO EN COLUMNAS DE AMARRE F'C=175 KG/CM2 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS ACERO GRADO 60 EN COLUMNAS DE AMARRE
4.00 4.00 4.00
VIGAS
S A R U T C U R T S E
CONCRETO EN VIGAS F'C=210 KG/CM2 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS ACERO GRADO 60 EN VIGAS
4.00 40.00 25.00
VIGAS DE AMARRE CONCRETO EN VIGAS DE AMARRE F'C=210 KG/CM2 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS DE A ACERO GRADO 60 EN VIGAS DE AMARRE
4.00 4.00 4.00
PLACAS CONCRETO EN PLACAS F'C= 210 KG/CM2 ENCOFRADO Y DESENCOFRADO EN PLACAS ACERO GRADO 60 EN PLACAS
2.00 4.00 4.00
LOSAS ALIGERADAS CONCRETO EN LOSAS ALIGERADAS F'C=210 KG/CM2 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIG ACERO GRADO 60 EN LOSAS ALIGERADAS BLOQUE HUECO/CONCRETO 15X20X30 CM PARA TECHO A
5.00 27.00 20.00 7.00
LOSAS SOLIDAS PLEGADAS CONCRETO EN LOSAS SOLIDAS PLEGADAS F'C=210 KG/CM ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS SOLI ACERO GRADO 60 EN LOSAS SOLIDAS PLEGADAS
4.00 4.00 4.00
ESCALERAS CONCRETO EN ESCALERAS F'C=210 KG/CM2 ENCOFRADO Y DESENCOFRADO NORMAL EN ESCALERAS ACERO GRADO 60 EN ESCALERAS
1.00 3.00 2.00
RAMPA CONCRETO EN RAMPAS F'C=210 KG/CM2 ENCOFRADO Y DESENCOFRADO EN RAMPAS ACERO GRADO 60 EN RAMPAS
2.00 6.00 6.00
PARAPETOS CONCRETO EN PARAPETO F'C= 210 KG/CM2 ENCOFRADO Y DESENCOFRADO ENPARAPETO ACERO ENPARAPETO GRADO 60 MUROS Y TABIQUES DE ALBAÑILERIA
A R U T C E T I U Q R A
2.00 8.00 4.00
MURO DE BLOQUE HUECO DE CONCRETO e=15 cm, mezcla 1:5 MURO DE BLOQUE HUECO DE CONCRETO e=30 cm, mezcla 1:5 REVOQUES, ENLUCIDOS Y MOLDURAS
12.00 30.00
TARRAJEO DEL TIPO RAYADO O PRIMARIO C/MORTERO 1: TARRAJEO FINO unsaac TARRAJEO FROTACHADO CON CEMENTO-ARENA UNSAAC TARRAJEO DE COLUMNAS C:M 1:5 E=2cm TARRAJEO DE VIGAS PERALTADAS TARRAJEO DE PLACAS INT. C:M 1:5 E=2cm TARRAJEO DE ESCALERAS C:A 1:5 TARRAJEO DE PARAPETOS EN RAMPAS Y ESCALERASC:M VESTIDURA DE DERRAMES BRUÑAS TARRAJEO FINO EN CIELORRASOS CON MEZCLA DE CEME TARRAJEO FROTACHADO EN CIELORRASOS CON MEZCLA PISOS Y PAVIMENTOS CONTRAPISO DE 48 MM. PISO DE TERRAZO CON ESTRIAS DE ALUMINIO E= 2.50 cm PISO DE PARQUET HUAYACAN 6 X 30 CM VETEADO PISO CERAMICO 0.30X0.30 PISO CERAMICO VITRIFICADO ALTO TRANSITO ANTIDESLI REVESTIMIENTO DE GRADAS CON TERRAZO ICL. CANTON TAPAJUNTAS METALICO CONTRAZOCALOS
6.00 42.00 30.00 42.00 48.00 3.00 20.00 27.00 24.00 24.00 54.00 24.00
CONTRAZOCALO DE TERRAZO C/PERFILES DE ALUMINIO CONTRAZOCALO DE MADERA AGUANO DE 4" x 3/4" C/RODON DE 3/4" CONTRAZOCALO DE MADERA AGUANO DE 6" x 3/4" C/RODON DE 3/4" CONTRAZOCALO CERAMICO ZOCALOS ZOCALO DE CERAMICO DE 30x30cm. LISTELO TIPO CINTILLO DE 0.015x0.30m. CUBIERTAS COBERTURA DE TEJAS SOBRE TIJERALES DE MADERA Y CORREAS COBERTURA DE POLICARBONATO SOBRE ESTRUCT METALICA MURO LADRILLO SOGA TARRAJEO DE PARAPETOS DE TECHO TARRAJEO CON IMPERMEABILIZANTE EN CANALES DE TECHO CANALETA DE LATON SUMIDERO DE BRONCE DE 6" CARPINTERIA DE MADERA PUERTA DE MELAMINA CON BORDES DE MADERA AGUANO e=45mm.
48.00 12.00 2.00 1.00
ASIENTOS DE MADERA SOBRE TUBO DE 2" Y PERFILES DE CARPINTERIA METALICA PUERTA DE VIDRIO CRUDO 8mm CON BORDES DE TUBO D SEPARADORES METALICOS DE BAÑO e= 2.50MM SEPARADORES DE URINARIOS METALICO e= 6MM INC INS BARANDAS METALICAS DE TUBO 2" CON FIERRO LISO DE 5 TUBO DECORATIVO DE FIERRO DE 4" PINTADO DE COLOR ANCLADO CON ANGULAR ESTRIADO DE 1 1/2" X 1 1/2" X 1/ PLATAFORMAS DE DESCANSO TIPO CANASTILLA ESCALERA DE GATO METALICA PIZARRA ACRILICA CERRAJERIA CERRADURA TIPO PERILLAS TIPO FORTE CERRADURA DE POMO PARA PUERTAS DE VIDRIO O CRIT CERRADURA PARA PISO EN PUERTAS DE VIDRIO SIMILAR BISAGRA CAPUCHINA ALUMINIZADA DE 4" X 4" UNSAAC CERROJO DE FIERRO REDONDO DE 5/8" X 0.60 M. CERROJO DE FIERRO REDONDO DE 5/8" X 0.35 M. PICAPORTES DE FIERRO REDONDO DE 4" VIDRIOS, CRISTALES Y SIMILARES VENTANA VIDRIO CRUDO TRASLUCIDO 8mm INCL ACCESO VENTANA VIDRIO PAVONADO 8mm INCL ACCESORIOS VIDRIOS PAVONADO DE 8mm EN PUERTAS VIDRIO CRUDO 8mm TRASLUCIDO EN PUERTAS MAMPARA DE VIDRIO CRUDO 8mm C/TUBO ELECTROSOLD PUERTA DE VIDRIO CRUDO 8mm ESPEJO BISELADO CON MARCO DE ALUMINIO PINTURA
24.00 54.00 60.00 12.00 10.00 11.00 12.00
18.00 2.00 14.00 5.00 9.00 14.00 6.00 2.00 2.00 12.00 12.00 6.00 6.00 6.00 12.00 12.00 12.00 1.00 5.00 2.00 12.00 12.00 12.00 12.00 1.00 1.00 1.00 8.00 1.00
1.00 1.00 10.00 3.00 3.00
1° MES LU MA MI JU VI 1 2 3 4 5
SA DO LU MA 6 7 8 9
MI 10
JU 11
VI 12
SA 13
DO 14
LU 15
MA 16
MI 17
2° MES JU 18
VI 19
SA 20
DO 21
LU 22
MA 23
MI 24
JU 25
VI 26
SA 27
DO 28
LU 29
MA 30
MI JU VI 1 2 3
SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
3° MES VI 24
SA 25
DO 26
LU 27
MA 28
MI 29
JU 30
VI 31
SA DO LU MA MI JU VI 1 2 3 4 5 6 7
SA DO 8 9
LU 10
MA 11
MI 12
JU 13
VI 14
SA 15
DO 16
LU 17
MA 18
MI 19
JU 20
VI SA 21 22
DO 23
LU 24
MA 25
MI 26
JU 27
VI 28
SA 29
DO LU MA 30 1 2
PINTURA LATEX EN MUROS INTERIORES UNSAAC PINTURALATEX EN MUROS EXTERIORES PINTURA VINILICA EN COLUMNAS , VIGAS Y/O PLACAS PINTURA VINILICA EN ESCALERAS, RAMPAS Y PARAPETOS PINTURA LATEX EN CIELORRASOS UNSAAC PINTURALATEX EN DERRAMES
S A I R A T I N A S S E N O I C A L A T S N I
S A C I R T C E L E S E N O I C A L A T S N I
S E R O I R E T X E S A R
APARATOS Y ACCESORIOS SANITARIOS INODORO BLANCO CON ACCESORIOS LAVATORIOS TIPO OVALIN BLANCO SOBRE MESA DE CONCRETO URINARIOS DE LOZA DE PICO BLANCO GRIFERIA DE URINARIOS UNSAAC GRIFERIA DE LAVATORIOS UNSAAC COLOCACION DE APARATOS SANITARIOS PAPELERA DE LOSA Y BARRA PLASTICA, COLOR BLANCO GABINETE CONTRAINCENDIOS SISTEMA DE AGUA FRIA Y CONTRA INCENDIO REDES DE DISTRIBUCION DE AGUA FRIA Y CONTRAINCENDIO TUBERIA DE AGUA PVC. DE 2"(50MM).INSTALACION.INC.PRUEBA HIDR VALVULA DE COMPUERTA 1 1/2" REDUCCION PVC SAP DE 2" A 1 1/2" REDUCCION PVC SAP DE 1 1/2" A 3/4" TEE PVC-SAP 1 1/2" CODO PVC SAP 2" CODO PVC-SAP 1 1/2" TUBERIA DE AGUA PVC. DE 2"(50MM) ISIST CONTRAINCENDIO TEE PVC-SAP 2"* 2" SISTEMA DE AGUA FRIA SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 3/4" SISTEMA DE DESAGUE Y VENTILACION REDES DE DISTRIBUCION DE DESAGUE Y VENTILACION SALIDA DE DESAGÜE DE 2" SALIDA DE DESAGÜE DE 4" PROVISION E INSTALACION TUBERIA PVC-SAL D=4" + PRUEB.HIDR PROVISION E INSTALACION TUBERIA PVC-SAL D=2" + PRUEB.HIDR TEE PVC SAL 4" TEE PVC SAL 2" CODO DE PVC SAL SP DE 4" SOMBRERO PARA VENTILACION DE P.V.C. DE 2" REGISTRO DE BRONCE CROMADO DE 4" REGISTROS DE BRONCE DE 2" SUMIDERO DE BRONCE 2" SISTEMA DE AGUAS PLUVIALES RED DE DISTRIBUCION DE AGUAS PLUVIALES SALIDA SUMIDERO REJILLA 0.10m x 0.10m EN TECHO SALIDA DE DESAGÜE DE 4" TUBERIA PVC SAL4" CONCRETO EN FALSA COLUMNA F'C=140 KG/CM2 RECUBRIMIENTO DE ENCOFRADO EN COLUMNAS RECUBRIMIENTO DE MONTANTES TARRAJEO DE RECUBRIMIENTO DE MONTANTES C:M 1:5 E=1.5cm CONFORMACIÓN DE FONDOS EN CANALES DE TECHO CODO PVC SAL 4" TEE PVC SAL 4" EQUIPO HIDRONEUMATICO DE 120 GLN DE 20-40 LB DE PRESION ELECTROBOMBA DE 1.5 HP
30.00 24.00 30.00 24.00 21.00 3.00 6.00 6.00 6.00 4.00 1.00 1.00 1.00 1.00 1.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 1.00 4.00 1.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 14.00 1.00 1.00 1.00 4.00 5.00 6.00
INSTALACIONES ELECTRICAS LINEA DE ALIMENTACION TUBERIAS PVC SAP (ELECTRICAS) D=3/4" CABLE ELECTRICO TW AWG NO. 12 CABLE ELECTRICO TW AWG-MCM NO. 14 -2.5 MM2. EXCAVACION POZO-CONEXION A TIERRA EN SISTEMA C/EQ.BOMBEO,ALUMB,TOMACORR TABLERO DE DISTRIBUCION CAJA METALICA CON PUERTA Y CERRADURA PARA 8TERMOMAGNETICOS TIPO ENGRAMPE INTERRUPTOR TERMOMAGNETICO 2X20A SISTEMA DE DISTRIBUCION SALIDA DE TOMACORRIENTE TRIFASICO CON PUESTA TIERRA SALIDA DE TECHO TW 4.0mmUNSAAC CAJA DEPASO F°G° 200X200X30 MM. INC. TAPA CAJA DE PASO CUADRADO CAJA DE PASO CIRCULAR LUMINARIAS LAMPARA FLUORESCENTE DOBLE PARA EMPOTRAR DE 40W LAMPARA FLUORESCENTE DOBLE CON REJILLA ADOSADA A CIELORASO LAMPARA FLUORESCENTE CIRCULAR PARA DOSAR CON DIFUSOR LAMPARA FLUORESCENTE DOBLE PARA ADOSAR 40W LAMPARA HALOGENA FLOOD LIGTH DE 150 W O EQUIVALENTE REFLEXTOR LAMPARA HALOGENA DE 75 W CIELO RASO LAMPARA VAPOR DE SODIO DE 150W CON POSTE DE C°A° INSTALACIONES ESPECIALES INTERNET SALIDA PARA RED INFORMATICA CAJA DE PASO METALICA DE 100X100X50 MM. INC. TAPA INTERNET TELECONFERENCIAS SALIDA PARA TELECONFERENCIAS CAJA DE PASO METALICA DE 100X100X50 MM. INC. TAPA TV-CABLE ALARMA CONTRAINCENDIO SALIDA PARA ALARMA CONTRAINCENDIO INC. SISTEMA CAJA DE PASO CUADRADO PARLANTES SALIDA DE PARLANTES CAJA DE PASO CUADRADO OBRAS PRELIMINARES TRAZO Y REPLANTEO DURANTE UNSAAC REUBICACION DE ESTRUCTURAS DE CONCRETO ELIMINACION DE ARBOLES REUBICACION DE POSTES DE LUZ MOVIMIENTO DE TIERRAS EXCAVACION MASIVA A MAQUINA CORTE Y EXCAVACION MANUAL DEMOLICION ESTRUCTURA DE CONCRETO PICADO DE MURO DE CONCRETO (JARDINERA) REMOSION DE PAVIMENTO- VEREDAS PICADO DE PAVIMENTO PARA NUEVO VACIADO RELLENO CON MATERIAL PROPIO SELECCIONADO ELIMINACION DE DESMONTE, COMPACTADO Y APISONADO CON MAT. SELECCIONADO PERFILADO E=0.15 M CONCRETO SIMPLE MURO-SARDINEL FC=140 KG/CM2 DE 0.30*1.20 M SARDINELES FC=175 KG/CM2 DE H= 15 E=30 M SARDINELES FC=175 KG/CM2 DE 15*10 M MURO DE C° C° REVESTIDO CON LAJA GRADA DE CONCRETO 175 KG/CM2 BANCAS DE CONCRETO CICLOPEO TARRAJEADAS MURO DE CONTENCION C° C° TIPO BANCA REVESTIDO CUNETAS REVESTIDAS EVAC. PLUVIAL OBRAS DE ARTE CONCRETO ARMADO MURO DE CONTENCION CONCRETO ARMADO TIPO 1 H=2.50 MURO DE CONTENCION CONCRETO ARMADO TIPO2 H=1.20 TAPA DE CANAL CONCRETO ARMADO ANCHO=0.70M
B O
RAMPA TAPA DE CANAL CONCRETO ARMADO BANCAS MADERA C/SOPORTE DE C° A° INCL PINTADO REJILLA FIERRO ANGULAR 3/4" Y FIERRO DE 1/2" PAVIMENTO Y VEREDAS ASENTADO DE BLOCK GRASS DE CONCRETO PISO SEMIRIGIDO BLOQUES DE CONCRETO S/ CAMA ARENA PISO DE TERRAZO CON ESTRIAS DE ALUMINIO PAVIMENTO/VEREDAS DE C° FC=175 KG/CM2 REPOSICION DE PISOS CONCRETO E=2" C:A 1:2 UNSAAC BRUÑAS JARDINES NIVELACION CON TIERRA AGRICOLA Y ARENA SEMBRADOD E GRASS PLANTACION DE ARBOLES VARIOS LAMPARA VAPOR DE SODIO DE 150W CON POSTE DE C°A° LIMPIEZA DE OBRA UNSAAC
4° MES MI JU VI 3 4 5
5° MES
6° MES
SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
1° MES FASE
ACTIVIDAD
TOTAL
LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU 1
OBRAS PROVISIONALES CERCO PROVISIONAL CON ARPILLERA Y ROLLIZOS DE EUCALIPTO
0.50
INSTALACION PROVISIONAL DE AGUA
0.50
INSTALACION PROVISIONAL DE ENERGIA ELECTRICA
1.00
CARTELDE OBRA
1.00
ENCOFRADO Y DESENCOFRADO PARA PROTECCION DE DUCTOS PASILLO
1.00
TRABAJOS PRELIMINARES TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO
4.00
OBRAS DE CONCRETO ARMADO COLUMNAS CONCRETO EN COLUMNAS F'C=210 KG/CM2
4.00
ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS
16.00
ACERO GRADO 60 EN COLUMNAS
12.00
TECNOPORT EN JUNTAS 2" EN COLUMNAS
2.00
COLUMNAS DE AMARRE CONCRETO EN COLUMNAS DE AMARRE F'C=175 KG/CM2
4.00
ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS DE AMARRE
4.00
ACERO GRADO 60 EN COLUMNAS DE AMARRE
4.00
VIGAS
S A R U T C U R T S E
CONCRETO EN VIGAS F'C=210 KG/CM2
4.00
ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS
40.00
ACERO GRADO 60 EN VIGAS
25.00
VIGAS DE AMARRE CONCRETO EN VIGAS DE AMARRE F'C=210 KG/CM2
4.00
ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS DE AM ARRE
4.00
ACERO GRADO 60 EN VIGAS DE AMARRE
4.00
PLACAS CONCRETO EN PLACAS F'C= 210 KG/CM2
2.00
ENCOFRADO Y DESENCOFRADO EN PLACAS
4.00
ACERO GRADO 60 EN PLACAS
4.00
LOSAS ALIGERADAS CONCRETO EN LOSAS ALIGERADAS F'C=210 KG/CM2
5.00
ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGERADAS
27.00
ACERO GRADO 60 EN LOSAS ALIGERADAS
20.00
BLOQUE HUECO/CONCRETO 15X20X30 CM PARA TECHO ALIGERADO
7.00
2
3
4
5
6
7
8
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1
2
3
4
5
6
7
8
9 10 11 12 13
LOSAS SOLIDAS PLEGADAS CONCRETO EN LOSAS SOLIDAS PLEGADAS F'C=210 KG/CM2
4.00
ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS SOLIDAS PLEGADAS
4.00
ACERO GRADO 60 EN LOSAS SOLIDAS PLEGADAS
4.00
ESCALERAS CONCRETO EN ESCALERAS F'C=210 KG/CM2
1.00
ENCOFRADO Y DESENCOFRADO NORMAL EN ESCALERAS
3.00
ACERO GRADO 60 EN ESCALERAS
2.00
RAMPA CONCRETO EN RAMPAS F'C=210 KG/CM2
2.00
ENCOFRADO Y DESENCOFRADO EN RAMPAS
6.00
ACERO GRADO 60 EN RAMPAS
6.00
PARAPETOS CONCRETO EN PARAPETO F'C= 210 KG/CM2
2.00
ENCOFRADO Y DESENCOFRADO ENPARAPETO
8.00
ACERO ENPARAPETO GRADO 60
4.00
MUROS Y TABIQUES DE ALBAÑILERIA
MURO DE BLOQUE HUECO DE CONCRETO e=15 cm, mezcla 1:5
12.00
MURO DE BLOQUE HUECO DE CONCRETO e=30 cm, mezcla 1:5
30.00
REVOQUES, ENLUCIDOS Y MOLDURAS TARRAJEO DEL TIPO RAYADO O PRIMARIO C/MORTERO 1:5 UNSAAC
6.00
TARRAJEO FINO unsaac
42.00
TARRAJEO FROTACHADO CON CEMENTO-ARENA UNSAAC
30.00
TARRAJEO DE COLUMNAS C:M 1:5 E=2cm
42.00
TARRAJEO DE VIGAS PERALTADAS
48.00
TARRAJEO DE PLACAS INT. C:M 1:5 E=2cm
3.00
TARRAJEO DE ESCALERAS C:A 1:5
20.00
TARRAJEO DE PARAPETOS EN RAMPAS Y ESCALERASC:M 1:5 E=2cm
27.00
VESTIDURA DE DERRAMES
24.00
BRUÑAS
24.00
TARRAJEO FINO EN CIELORRASOS CON MEZCLA DE CEMENTO-ARENA UNSAAC
54.00
TARRAJEO FROTACHADO EN CIELORRASOS CON MEZCLA DE CEMENTO-ARENA U
24.00
PISOS Y PAVIMENTOS CONTRAPISO DE 48 MM.
24.00
PISO DE TERRAZO CON ESTRIAS DE ALUMINIO E= 2.50 cm
54.00
PISO DE PARQUET HUAYACAN 6 X 30 CM VETEADO
60.00
PISO CERAMICO 0.30X0.30
12.00
PISO CERAMICO VITRIFICADO ALTO TRANSITO ANTIDESLIZANTE DE 0.30X0.30
10.00
REVESTIMIENTO DE GRADAS CON TERRAZO ICL. CANTONERA ALUMINIO
11.00
TAPAJUNTAS METALICO
12.00
CONTRAZOCALOS
CONTRAZOCALO DE TERRAZO C/PERFILES DE ALUMINIO
48.00
CONTRAZOCALO DE MADERA AGUANO DE 4" x 3/4" C/RODON DE 3/4"
12.00
CONTRAZOCALO DE MADERA AGUANO DE 6" x 3/4" C/RODON DE 3/4"
2.00
CONTRAZOCALO CERAMICO
1.00
ZOCALOS
ZOCALO DE CERAMICO DE 30x30cm.
18.00
LISTELO TIPO CINTILLO DE 0.015x0.30m.
2.00
CUBIERTAS
COBERTURA DE TEJAS SOBRE TIJERALES DE MADERA Y CORREAS
A R COBERTURA DE POLICARBONATO SOBRE ESTRUCT METALICA U MURO LADRILLO SOGA T TARRAJEO DE PARAPETOS DE TECHO C TARRAJEO CON IMPERMEABILIZANTE EN CANALES DE TECHO E CANALETA DE LATON T I U SUMIDERO DE BRONCE DE 6" Q CARPINTERIA DE MADERA R PUERTA DE MELAMINA CON BORDES DE MADERA AGUANO e=45mm. A ASIENTOS DE MADERA SOBRE TUBO DE 2" Y PERFILES DE FIERRO 8mm
14.00 5.00 9.00 14.00 6.00 2.00 2.00 12.00 12.00
CARPINTERIA METALICA PUERTA DE VIDRIO CRUDO 8mm CON BORDES DE TUBO DE ACERO
6.00
SEPARADORES METALICOS DE BAÑO e= 2.50MM
6.00
SEPARADORES DE URINARIOS METALICO e= 6MM INC INSTALACION Y PINTURA
6.00
BARANDAS METALICAS DE TUBO 2" CON FIERRO LISO DE 5/8" SEGUN DISEÑO
12.00
TUBO DECORATIVO DE FIERRO DE 4" PINTADO DE COLOR ALUMINIO 110
12.00
ANCLADO CON ANGULAR ESTRIADO DE 1 1/2" X 1 1/2" X 1/8" EN GRADAS
12.00
PLATAFORMAS DE DESCANSO TIPO CANASTILLA
1.00
ESCALERA DE GATO METALICA
5.00
PIZARRA ACRILICA
2.00
CERRAJERIA CERRADURA TIPO PERILLAS TIPO FORTE
12.00
CERRADURA DE POMO PARA PUERTAS DE VIDRIO O CRITAL
12.00
CERRADURA PARA PISO EN PUERTAS DE VIDRIO SIMILAR A CISA
12.00
BISAGRA CAPUCHINA ALUMINIZADA DE 4" X 4" UNSAAC
12.00
CERROJO DE FIERRO REDONDO DE 5/8" X 0.60 M.
1.00
CERROJO DE FIERRO REDONDO DE 5/8" X 0.35 M.
1.00
PICAPORTES DE FIERRO REDONDO DE 4"
1.00
VIDRIOS, CRISTALES Y SIMILARES VENTANA VIDRIO CRUDO TRASLUCIDO 8mm INCL ACCESORIOS
8.00
VENTANA VIDRIO PAVONADO 8mm I NCL ACCESORIOS
1.00
VIDRIOS PAVONADO DE 8mm EN PUERTAS
1.00
VIDRIO CRUDO 8mm TRASLUCIDO EN PUERTAS
1.00
MAMPARA DE VIDRIO CRUDO 8mm C/TUBO ELECTROSOLDADO DE 2" X 1"
10.00
PUERTA DE VIDRIO CRUDO 8mm
3.00
ESPEJO BISELADO CON MARCO DE ALUMINIO
3.00
PINTURA PINTURA LATEX EN MUROS INTERIORES UNSAAC
30.00
PINTURALATEX EN MUROS EXTERIORES
24.00
PINTURA VINILICA EN COLUMNAS , VIGAS Y/O PLACAS
30.00
PINTURA VINILICA EN ESCALERAS, RAMPAS Y PARAPETOS
24.00
PINTURA LATEX EN CIELORRASOS UNSAAC
21.00
PINTURALATEX EN DERRAMES
3.00
APARATOS Y ACCESORIOS SANITARIOS
INODORO BLANCO CON ACCESORIOS
6.00
LAVATORIOS TIPO OVALIN BLANCO SOBRE MESA DE CONCRETO
6.00
URINARIOS DE LOZA DE PICO BLANCO
6.00
GRIFERIA DE URINARIOS UNSAAC
4.00
GRIFERIA DE LAVATORIOS UNSAAC
1.00
COLOCACION DE APARATOS SANITARIOS
1.00
PAPELERA DE LOSA Y BARRA PLASTICA, COLOR BLANCO
1.00
GABINETE CONTRAINCENDIOS
1.00
SISTEMA DE AGUA FRIA Y CONTRA INCENDIO REDES DE DISTRIBUCION DE AGUA FRIA Y CONTRAINCENDIO
TUBERIA DE AGUA PVC. DE 2"(50MM).INSTALACION.INC.PRUEBA HIDR
1.00
VALVULA DE COMPUERTA 1 1/2"
2.00
REDUCCION PVC SAP DE 2" A 1 1/2"
2.00
REDUCCION PVC SAP DE 1 1/2" A 3/4"
S A I R A T I N
TEE PVC-SAP 1 1/2"
2.00
CODO PVC SAP 2"
2.00
CODO PVC-SAP 1 1/2"
2.00
TUBERIA DE AGUA PVC. DE 2"(50MM) ISIST CONTRAINCENDIO
2.00
TEE PVC-SAP 2"* 2"
2.00
SISTEMA DE AGUA FRIA
SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 3/4"
1.00
A S S E N O I C A L A T S N I
SISTEMA DE DESAGUE Y VENTILACION REDES DE DISTRIBUCION DE DESAGUE Y VENTILACION
SALIDA DE DESAGÜE DE 2"
4.00
SALIDA DE DESAGÜE DE 4"
1.00
PROVISION E INSTALACION TUBERIA PVC-SAL D=4" + PRUEB.HIDR PROVISION E INSTALACION TUBERIA PVC-SAL D=2" + PRUEB.HIDR
2.00
TEE PVC SAL 4"
2.00
TEE PVC SAL 2"
2.00
CODO DE PVC SAL SP DE 4"
2.00
SOMBRERO PARA VENTILACION DE P.V.C. DE 2"
2.00
REGISTRO DE BRONCE CROMADO DE 4"
2.00
REGISTROS DE BRONCE DE 2"
2.00
SUMIDERO DE BRONCE 2"
2.00
SISTEMA DE AGUAS PLUVIALES RED DE DISTRIBUCION DE AGUAS PLUVIALES
SALIDA SUMIDERO REJILLA 0.10m x 0.10m EN TECHO
14.00
SALIDA DE DESAGÜE DE 4" TUBERIA PVC SAL4"
1.00
CONCRETO EN FALSA COLUMNA F'C=140 KG/CM2 RECUBRIMIENTO DE MONTANTES
1.00
ENCOFRADO EN COLUMNAS RECUBRIMIENTO DE MONTANTES
1.00
TARRAJEO DE RECUBRIMIENTO DE MONTANTES C:M 1:5 E=1.5cm
4.00
CONFORMACIÓN DE FONDOS EN CANALES DE TECHO CODO PVC SAL 4"
5.00
TEE PVC SAL 4"
6.00
EQUIPO
HIDRONEUMATICO DE 120 GLN DE 20-40 LB DE PRESION ELECTROBOMBA DE 1.5 HP INSTALACIONES ELECTRICAS LINEA DE ALIMENTACION
TUBERIAS PVC SAP (ELECTRICAS) D=3/4" CABLE ELECTRICO TW AWG NO. 12 CABLE ELECTRICO TW AWG-MCM NO. 14 -2.5 MM2. EXCAVACION POZO-CONEXION A TIERRA EN SISTEMA C/EQ.BOMBEO,ALUMB,TOMACORR TABLERO DE DISTRIBUCION CAJA METALICA CON PUERTA Y CERRADURA PARA 8TERMOMAGNETICOS TIPO ENGRAMPE INTERRUPTOR TERMOMAGNETICO 2X20A
S
SISTEMA DE DISTRIBUCION
A C I R T C E L E S E N O I C A L A T S N I
SALIDA DE TOMACORRIENTE TRIFASICO CON PUESTA TIERRA SALIDA DE TECHO TW 4.0mmUNSAAC CAJA DEPASO F°G° 200X200X30 MM. INC. TAPA CAJA DE PASO CUADRADO CAJA DE PASO CIRCULAR LUMINARIAS
LAMPARA FLUORESCENTE DOBLE PARA EMPOTRAR DE 40W LAMPARA FLUORESCENTE DOBLE CON REJILLA ADOSADA A CIELORASO LAMPARA FLUORESCENTE CIRCULAR PARA DOSAR CON DIFUSOR LAMPARA FLUORESCENTE DOBLE PARA ADOSAR 40W LAMPARA HALOGENA FLOOD LIGTH DE 150 W O EQUIVALENTE REFLEXTOR LAMPARA HALOGENA DE 75 W CIELO RASO LAMPARA VAPOR DE SODIO DE 150W CON POSTE DE C°A° INSTALACIONES ESPECIALES INTERNET
SALIDA PARA RED INFORMATICA CAJA DE PASO METALICA DE 100X100X50 MM. INC. TAPA INTERNET TELECONFERENCIAS
SALIDA PARA TELECONFERENCIAS CAJA DE PASO METALICA DE 100X100X50 MM. INC. TAPA TV-CABLE ALARMA CONTRAINCENDIO
SALIDA PARA ALARMA CONTRAINCENDIO INC. SISTEMA CAJA DE PASO CUADRADO PARLANTES SALIDA DE PARLANTES
OBRAS PRELIMINARES TRAZO Y REPLANTEO DURANTE UNSAAC REUBICACION DE ESTRUCTURAS DE CONCRETO
2° MES
3° MES
4° MES
MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1
2
3
4
5
6
7
8
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1
2
3
4
5
6
7
8
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
5° MES JU VI SA DO LU MA MI JU VI SA DO LU MA MI 1
2
3
4
5
6
7
8
9 10 11 12 13 14