Corus Construction & Industrial
Composite steel highway bridges
Contents
Contents Acknowledgement of author
This guide is an update of a publication originally
Advantages of steel bridges
prepared by A.C.G. Hayward. Corus gratefully acknowledges the work of Mr Hayward and the
1
Design standards
2
Conceptual design
contribution made by D.C. Iles, The Steel Construction Institute, during this update.
2.1 Spans and component lengths 2.2 Cross sections 2.3 Intermediate supports 2.4 Bracings 2.5 Steel grades 2.6 Further guidance 3
Initial sizes and overall unit weight 3.1 Introduction 3.2 Use of charts
4
3.2.1
Plate girder flange sizes
3.2.2
Plate girder web sizes
3.2.3
Overall unit weight
3.2.4
Universal beams
3.2.5
List of symbols
Worked examples – use of charts 4.1 Continuous plate girder bridge 4.2 Simply supported universal beam bridge
5 6
References Figures Figure 4 – Simply supported bridges Figure 5 – Continuous bridges – span girders Figure 6 – Continuous bridges – pier girders Figure 7 – Girder spacing factors Figure 8 – Overall unit weights – plate girder bridges Figure 9 – Universal beams – elastic stress analysis Figure 10 – Universal beams – plastic stress analysis
1. Left: Waterside Bridge Newburgh, Scotland 2. Right: A1(M) Yorkshire, England
2
Composite steel highway bridges
Advantages of steel bridges
Composite steel highway bridges The Author
Alan Hayward was continuously involved with the
Alan C. G. Hayward FREng CEng FICE FIStructE
development of bridge codes including BS 5400 and
Alan Hayward was a founding Partner of bridge
Eurocodes and has been National Technical Contact for
specialists Cass Hayward & Partners of Chepstow who
the composite bridge code EC4-2. He contributes to the
design and evolve construction methodology for all
education of engineers by lecturing at Universities on
types of bridges, particularly steel highway, railway,
behalf of industry, and has written numerous papers on
footbridges, movable bridges and Roll-On/Roll-Off
steel bridge construction. He was a long-standing
linkspans in the UK and overseas. He remains active in
member of the Steel Bridge Group who disseminate best
the firm as a Consultant.
practice through their published Guidance Notes.
Advantages of steel bridges Feature
Leading to
Advantages
Low weight of superstructure.
Fewer piles and smaller sizes of pile caps/foundations. Typical 30 – 50% reduction over concrete decks. Composite bridges 6.0 – 8.0kN/m2 typical.
Cheaper foundations.
Light units for erection.
Erection by smaller cranes. Delivery of long pieces. Launch erection with light equipment (skates or rollers).
Cheaper site costs.
Simple site joints.
Bolted joints: easy to form larger pieces from small transported components taken to remote sites.
Flexible site planning.
Maximum pre-fabrication in factory.
Quality control in good factory conditions avoiding outdoor site affected by weather and difficult access.
More reliable product.
Predictable maintenance costs.
Commuted painting costs can be calculated. If easy repainting is made possible by access and good design then no other maintenance necessary.
Total life cost known.
Low construction depth.
Depth/span ratio 1/20 to 1/30 typically. Lower depth achieved with half-through girders.
Slender appearance. Reduces costs of earthworks in approaches.
Self supporting during construction.
Falsework eliminated. Slab formwork and falsework also avoided using permanent formwork.
Falsework costs eliminated. Significant if more than 8m above ground.
Continuous and integral spans.
Continuity easy with bolted or welded joints. Most expansion joints eliminated. Number of bearings reduced. Compliance with BD57.
Better appearance. Improved durability. Improved running surface.
Adaptable details.
Pleasing appearance taking advantage of curves and colour.
Aesthetic gain.
Re-usable product.
Demountable structures and recyclable components which reduce manufacturing energy input.
Sustainable product.
Composite steel highway bridges
3
1. M4/M25 Poyle Interchange
1. Design standards The current bridge code BS 5400 (Ref. 1) was conceived in 1967. Its ten parts cover the more common structural media. The 1980 conference in Cardiff introduced the Code relating to steel and made use of research carried out since 1970.
(ii)
Design clauses are easier to use than previous Codes.
(iii) Workmanship requirements, including tolerances, are rationalised. (iv) Longitudinal web stiffeners to girders are rarely needed.
Part 3 (Design of Steel Bridges) is compatible with the workmanship standards and tolerances defined in Part
Use of the plastic modulus is permitted for stress
6, drawn up jointly with industry.
analysis of compact sections and where the slenderness is controlled by sufficient restraints, the effects of
The Code uses limit state principles. The ultimate
shrinkage and differential temperature can be neglected.
limit state (ULS) and serviceability limit state (SLS) must be satisfied.
For ‘compact’ sections, the entire load can also be assumed to act on the composite section even if the
In practice the ULS generally governs, exceptions being
steelwork is unpropped, provided that SLS checks
the checking at SLS for slip of HSFG bolts and the
are made.
design of shear connectors. While most rolled universal beams, columns and BS 5400 encourages the use of steel for a number
channels will be compact, plate girders will often be
of reasons:
non-compact and must be stressed elastically. (See also Section 3.2.4.)
(i)
Plastic stress analysis option offers the use of lighter members and extends the span range of
For structural analysis, elastic methods are utilised
rolled sections.
using gross sections (i.e. not allowing for shear lag or effective width).
4
Composite steel highway bridges
Redistribution of moments arising from the formation of
For example:
plastic hinges is not permitted, but redistribution due to cracking of concrete over intermediate supports may be
(i)
assumed using Part 5.
Do not locate welded attachments close to or on flange edges (class 'G').
(ii)
Re-entrant corners should be radiused.
Combined bending and shear is dealt with using
(iii) Use HSFG bolts for permanent bolted connections.
interaction formulae. This is sometimes critical at
(iv) Restrict doubler flange ends to areas of low stress
intermediate supports.
(class 'G'). (v)
The Code contains no specific limits on slenderness of members or proportion of plate panels. Longitudinal web
Avoid single sided partial penetration butt welded joints which are subject to tensile stress.
(vi) Avoid welded cruciform joints, which are subject to
stiffeners are usually only necessary for very deep
significant tensile stresses. An example is when
girders or those with curved soffits.
using integral crossheads (see Figs. 1B & 1F) where fillet welds should be used in preference to
For rolled sections the full shear yield stress can
full penetration butt welds. If butt welds are
generally be used without the need for intermediate
necessary, the use of steel with through-thickness
stiffeners. Bearing stiffeners are virtually mandatory at
quality (Z-grades to BS EN 10164 – Ref 14) may be
supports, together with lateral bracing or a system of
considered in view of the strains which will be
bracing to maintain verticality.
caused during welding.
Fatigue is checked to Part 10, although for highway bridges this rarely demands a reduction in working stresses provided good detailing practice is used.
Composite steel highway bridges
5
1. This page: A69 Haltwhistle Viaduct (Photo courtesy of Cleveland Bridge (UK) Ltd.) Northumberland, England 2. Right: Festival Park Flyover Stoke, England 3. Far right: Simon De Montford Bridge Evesham, England
Conceptual design
2. Conceptual design 2.1 Spans and component lengths
Curved bridges
Spans are usually fixed by site restrictions and
Curved bridges in plan may be formed using straight
clearances. Where freedom exists, budget costing –
fabricated girders, with direction changes introduced at
including foundations – is desirable to determine the
each site splice. However, steel girders can be curved in
economic span. A range of 25m to 50m is likely.
plan which simplifies the cantilever formwork and
Where deep piled foundations are needed, cost will
permits the use of standard systems. An example is the
encourage the use of longer spans, thus keeping
A69 Haltwhistle Viaduct (radius 540m)
foundations to a minimum. Skew and plan tapered bridges may also be built in Multiple spans
steel. Ideally, plan layout should be as simple as
Multiple spans of approximately 24m suit universal
possible (Ref. Documents in Section 2.6).
beams, this being the longest readily available length and because continuous spans are convenient and economic.
Integral bridges
Site splices may be bolted with HSFG bolts or welded
The Highways Agency requires consideration of integral
near points of contraflexure. The length of end spans
bridge forms for spans up to 60m with the objective of
should ideally be about 0.8 of the penultimate span.
improved durability by elimination of bridge deck movement joints (Ref. 4 & 5). Girders may then be
Continuous spans
required to develop a degree of continuity with
The optimum for using plate or box girders for
substructures at end supports such that axial forces and
continuous spans is about 45m, because 27m long
reverse moment effects need to be considered in the
‘span girders’ can be spliced with ‘pier girders’ of a
design of the composite deck. Design principles remain
single plate 18m long. For longer spans, more shop or
the same but girder sizes and bracing provision may be
site splices are needed. Component lengths for shop
influenced. Further guidance is available from the Steel
fabrication should be the maximum possible consistent
Construction Institute (Ref. 8, 9, 10 & 10a).
with delivery and site restrictions to reduce the amount of on-site assembly. The maximum length for road
2.2 Cross sections
delivery without restrictions is normally 27.4m although
Deck type construction
longer lengths can readily be transported by
Deck type construction is common and is suitable for
arrangement. A minimum number of shop butt welds
highway bridges as shown in Fig. 1. A span-to-girder
should be used consistent with plate sizes available. The
depth ratio of 20 is economic although 30 or more can
decision whether to introduce thickness changes within
be achieved. A half-through bridge (‘U’ frame) can be
a fabricated length should take account of the cost of
appropriate in cases of severely limited depth, such as
butt welds compared with the potential for material
where approach lengths are restricted. Footbridges and
saving (Ref. Documents in Section 2.6).
rail under-bridges are common examples.
Composite steel highway bridges
7
Conceptual design
Where permanent formwork is envisaged, the slab
Box girders
should be made sufficiently thick to accommodate the
Where spans exceed 100m box girders are likely to be
details taking account of reinforcement cover and
more economic than plate girders with which flange sizes
practical tolerances (Ref. 7). When using composite part
would be excessive. Other reasons for using box girders
depth planks such as Omnia then a minimum thickness
include aesthetics (where justifiable), aerodynamic
of 250mm may be needed.
stability, severe plan curvature, the need for single column supports or very limited depth. Other than in the cases
Universal beams and plate girders
noted, box girders – being heavier than plate girders – are
Universal beams may be appropriate for bridges up to
more expensive because although less flange material
25m span and above when continuous, or when use can
may be demanded due to inherent torsional properties,
be made of the plastic modulus. For spans above 22m,
this is usually more than offset by the amount of internal
plate girders, especially if continuous, can be economic
stiffening and extra costs for workmanship. Fabrication
because lighter sections can be inserted in mid-span
costs are higher because the assembly/welding
regions. Costs per tonne of painted and erected
processes take longer and more shop space is needed.
universal beams were traditionally lower but, more
However, erection work is often reduced because box
recently, automated fabrication and less expensive plate
girders require little or no external bracing.
material has allowed economic supply of plate girders for the shorter spans.
Multiple box girders have in the past proved to be economic for spans of around 50m in particular
A girder spacing of 3.0m to 3.5m is usual with a deck
situations. Using narrow cross sections eliminates the
slab of about 250mm thick (see Figs. 1A and 1B). Edge
need for longitudinal stiffeners (see Fig. 1F). An example
cantilevers should not exceed half the beam spacing
of which is the M25/M4 Poyle Interchange.
and to simplify falsework should, where possible be less than 1.5m. Shorter cantilevers are usually necessary
For box girders, consideration of the safety of personnel in
with a locally thickened slab where very high
confined spaces is essential during fabrication, erection and
containment parapets are specified, e.g. over rail tracks.
for maintenance. Detailing must recognise the need to avoid
An even number of girders achieves better optimisation
internal welding as far as possible and to allow sufficient
of material (ordering) and allows bracing in pairs. For
ventilation and openings for access and recovery in
wide girder spacings, the slab may be haunched, but
emergency situations.
use of standardised permanent formwork is unlikely to be possible and construction depth is increased (see
Open-topped trapezoidal and rectangular shaped box
Fig. 1C). Where spans exceed 40m, twin plate girders
girders have been used efficiently, but provisions are
with a central stringer have been used on some single
needed to preserve stability during erection, for example the
carriageway decks up to about 13m wide (see Fig. 1D).
Forrest Way Bridge, Warrington.
Twin girders and cross beams (often referred to as ladder decks) have proved economic for a wide range of
Plate girder flanges
spans (Ref. 10b). They can be used for single
Plate girder flanges should be as wide as possible but
carriageway decks (see Fig. 1E) and for wider decks
consistent with outstand limitations in BS 5400 (i.e. 12t in
supporting more lanes.
compression if fully stressed and up to the 20t robustness
8
Composite steel highway bridges
Conceptual design
limit), to give the best achievable stability during erection
Intermediate bracings require to be spaced at about
and to reduce the number of bracings. For practical
20 x top flange width and need to be adequate to
reasons a desirable minimum width is about 400mm to
prevent lateral torsional buckling. Bracing is necessary
accommodate detailing for certain types of permanent
at supports if only to prevent overturning during
formwork, especially precast concrete. A maximum flange
erection. At abutments this can be a channel trimmer
thickness of 63mm is recommended to avoid heavy welds,
composite with the slab and supporting its free end. Over
minimise pre-heating requirements and also limit the
piers a channel section can be used between each pair
reduction in design yield strength. Limiting the thickness
of girders of up to about 1.2m deep. For deeper girders
also has benefits in terms of notch toughness specification.
triangulated angle bracings are usual (see Fig. 1B).
2.3 Intermediate supports
Intermediate lateral bracings are usually necessary in
Piers can take the form of reinforced concrete, leaf,
hogging regions with a maximum spacing of about
column or portal. Steel columns are also used. For
12 x bottom flange width. If the bridge is curved they
example, tubular steel columns (concrete filled
should be close to the site splices where curvature
composite), were used in the M5 Almondsbury
induces torsion. Bracings may be of a triangulated form
Interchange and deserve consideration. Leaf piers or
or of single channel sections between each pair of
multiple columns supporting every girder are convenient
girders of up to 1.2m deep (see Fig. 1A). Alternatively,
but where fewer columns are demanded for aesthetic
bracings can take the form of inverted 'U' frames, but
reasons, integral steel crossheads provide a solution. The
for spans exceeding around 35m it may be necessary to
popularity of these crossheads has recently increased
interconnect all the girders by bracings during erection
following earlier examples on M25 bridges including
so that transverse flexure from wind is adequately
Brook Street Viaduct, Mar Dyke Viaduct and South
shared. Although plan bracing systems are uneconomic
Mimms Interchange Bridges (see Figs. 1B and 1F). They
and should be avoided, they may be required for spans
were extensively used for the Second Severn crossing
exceeding 55m for temporary stability, especially if
approach roads and for the new Thelwall Viaduct.
launch erection is used (Ref. Documents in Section 2.6).
It should, however, be recognised that the introduction
Use may be made of bracings in distributing live loads
of these additional members is only likely to be
between girders. This may offer reduced flange sizes
economic where the use of fewer supports is essential.
under HB loading but the uniformity of current loading to
Costs can increase especially if column spacing is not
BD37 across the carriageway (HB + 2 lanes HA + 0.6 HA
arranged to allow balanced erection and temporary
other lanes) tends to discourage this. An optimum design
trestles become necessary. Care is also needed detailing
is likely to include bracings only between pairs of girders,
cruciform welded joints at the crosshead/main girder
such discontinuous bracings attracting minimal effects
connection (Ref. Section 1 (vi)).
under deck loading except in cases of heavy skew or curvature where a different system may be appropriate.
2.4 Bracings
Bracings should be included in the global analysis to
For most universal beam or plate girder bridges, lateral
check for possible overload or fatigue effects.
bracings are needed for erection stability and during deck concreting.
1. Far Left: Nene Bridge Peterborough, England 2. Left: Forrest Way Bridge Warrington, England 3. Right: M20 Road Bridge Folkstone, England
Composite steel highway bridges
9
Conceptual design
DECK WIDTH W
230 TO 1A Multiple U.B. (N=4)
250 mm D
2.5 TO 3.5
230 TO 1B Multiple P.G. (N=4)
250 mm D 1.0 TO 1.75 TYPICAL
300 TO 350 mm 1C Twin P.G. Haunch Slab (N=2) D
1.0 TO 3.3
4.0 TO 5.5 AT MID-SPAN
AT PIER
Figures 1A – 1F Typical deck type cross-sections
1. Left: Humber Road Bridge Immingham, England 2. Right: Thelwall Viaduct M6, Warrington, England
10 Composite steel highway bridges
Conceptual design
230 TO 320 mm 1D Twin P.G. & Stringer (N=2) D
6.0 TO 7.0
1.0 TO 3.3
230 TO 1E Twin P.G. & Cross Girders (N=2)
250 mm
D
3.0 TO 3.5 c/c
>7.0
230 TO 1F Multiple Box (N=6)
250 mm
D
0.9 TO 1.2
2.5 TO 3.5 AT MID-SPAN
AT PIER
Composite steel highway bridges 11
2.5 Steel grades
temperatures to be determined from isotherms of
BS EN 10025-2: 2004 Grade S355 steels (Ref. 12) are
minimum and maximum shade air temperature for a
usual for bridges as they offer a lower cost-to-strength
particular site location. Limiting thicknesses for steel
ratio than Grade S275. BS 5400 requires all steel parts to
parts are prescribed in BS 5400: Part 3, as implemented
achieve a specified notch toughness, depending upon
by BD13 (Ref. 3), as appropriate to these effective bridge
design minimum temperature, stress level and
temperatures, and the other factors mentioned above.
construction features (e.g. welding details). Subgrades J2 and K2 will be most common.
Weathering steel To eliminate the need for painting, weathering steels to
Composite bridge decks are specifically categorised in
BS EN 10025-5: 2004 (Ref. 13) should be considered.
the composite version of BS 5400: Part 2 (implemented
Although it can be shown that the commuted costs of
by BD37), to allow a range of effective bridge
repainting are less than 1% of the initial bridge cost, weathering steel bridges can be more economical on a
1. Above: Findhorn Viaduct Inverness, Scotland 2. Left: Westgate Bridge Gloucester, England 3. Right: Slochd Beag Bridge Inverness, Scotland
12 Composite steel highway bridges
first cost basis and are particularly useful in eliminating
design standard BD 7 (Ref. 6) and Corus Publication
maintenance where access is difficult – over a railway,
‘Weathering steel bridges’ (Ref. 11).
for example.
2.6 Further guidance Weathering steel is not suitable at or near the coast, (i.e.
Particularly relevant information for initial (and detailed)
within about 2km from the sea) due to the chloride laden
design is included within two publications:
environment or in areas of severe pollution. • BCSA Publication No. 34/02 ‘Steel Bridges’ The Highways Agency requires sacrificial thickness to be added to all exposed surfaces for possible long term corrosion (1.5mm per face in a severe marine or industrial
Alan Hayward, Neil Sadler and Derek Tordoff, 2002. • SCI-P-185, Steel Bridge Group: Guidance notes on Best Practice in Steel Bridge Construction.
environment, 1mm in mild environments and 0.5mm inside box girders) and detailed guidance is given in
Composite steel highway bridges 13
Initial sizes and overall unit weight
3. Initial sizes and overall unit weight
(viii) Steelwork is unpropped and therefore not acting compositely under its own weight and that of the concrete slab. The steel is however composite for all superimposed loads after the concrete has cured.
3.1 Introduction
(ix)
due to buckling criteria.
area (A f) web thickness (t w) and overall unit weight of steelwork (kg/m2) for typical composite bridge cross
Sufficient transverse bracings are included such that bending stresses are not significantly reduced
Charts are given to provide initial estimates of flange (x)
Top flanges in sagging regions are dictated by the maximum stress during concreting allowing for
sections as shown in Fig. 1.
formwork and live load – to BS 5975 (Ref. 15). Continuous or simply supported span plate girders and
Continuous bridge mid-span regions are concreted
simply supported universal beams are included. The
in turn followed by portions over the piers.
charts were derived from approximate BS 5400 designs
(xi)
HA loading (BD37).
distribution and to achieve correlation with modern bridges. The charts take account of the latest highway
Live loading HA (assuming 3.5m wide lanes), or alternatively 45 units of HB loading with co-existent
using simplifying assumptions for loads, transverse
(xii) Continuous spans are approximately equal.
loading requirements in BD37.
3.2 Use of charts It is emphasised that the sizes obtained do not represent final designs, which must always be executed to take
3.2.1 Plate girder flange sizes
account of all factors, such as bridge configuration and
Flange areas (Af in m2) are read against the span L.
loading. Adjustments will need to be made to take account of the likely effects of end continuity if integral
(a)
For simply supported bridges – (refer Fig. 4)
construction is intended.
(b)
For continuous bridges – Size of span girder (refer Fig. 5)
The charts are based on the following assumptions: (i) (ii) (iii)
Deck slab 250mm average thickness (6.25kN/m2).
Figures 4, 5 and 6 are applicable to an average girder
Superimposed dead loads equivalent to 100mm of
spacing ‘s’ of 3.5m. Fig. 7 gives a girder spacing factor
surfacing (2.40 kN/m2).
K af which is multiplied by the flange areas, obtained
Permanent formwork weight 0.50 kN/m of slab
above, to give values appropriate to the actual average
soffit area.
girder spacing.
2
(iv)
Steel grade S355.
(v)
Span to depth ratios L/D of 20 & 30.
(vi)
Size of pier girder (refer Fig. 6)
i.e. Top Flange A ft = A ft (Figs. 4, 5 or 6) x K af (Fig. 7)
Plate girder webs have vertical stiffeners at approx. 2.0m centres where such stiffening is required.
i.e. Bottom Flange A fb = A fb (Figs. 4, 5 or 6) x K af ( Fig. 7)
(vii) Elastic stress analysis is used for plate girders. If however the plastic modulus is used for compact
Two different span-to-depth ratios, L/D = 20 and L/D =
cross sections, then economies may be possible.
30, are included for either HB or alternatively HA loading. Values for intermediate L/D ratios can be read by interpolation.
14 Composite steel highway bridges
Initial sizes and overall unit weight
The charts also show actual flange sizes using
depth (L/D) ratio for each span based upon the average
400mm x 15mm to 1000mm x 75mm.
girder depth (D) within that span.
Flange area of pier girders of continuous unequal spans
For box girder bridges a rough estimate may be
can be estimated by taking the greater of the two
obtained assuming that N = 2 x number of box girders in
adjacent spans.
the cross section (see Fig. 1F where N = 2 x 3 = 6).
End spans of continuous bridges may be estimated
For continuous bridges the end spans should be assumed
using L = 1.25 x actual span.
as 1.25 x actual span, following which the mean span for use in Fig. 8 may be determined as follows:
3.2.2 Plate girder web sizes Web thicknesses are similarly obtained using Figs. 4, 5 and 6 applicable to 's' = 3.5m. Adjustment for the actual
4
Mean span L =
L14 + L24...Ln4 n
average girder spacing 's' is obtainable from Fig. 7 using girder spacing factor k tw. i.e. Web thickness t w = t w (Figs. 4, 5 or 6) x k tw (Fig. 7). The thickness obtained may be regarded as reasonably typical. However, designers may prefer to opt for thicker webs to reduce the number of web stiffeners.
3.2.3 Overall unit weight Overall unit weight (kg/m2 of gross deck area) for plate girders is read against the span L from Fig. 8 for simply supported or continuous bridges with L/D ratios of 20 or 30, under HB or alternatively HA loading and applicable to ‘s’ = 3.5m. Adjustment for average girder spacing 's' other than 3.5m is obtainable from Fig. 7 using girder spacing factor k w. i.e. Unit weight kg/m2 = kg/m2 (Fig. 8) x k w (Fig. 7). The unit weight provides an approximate first estimate of steelwork tonnage allowing for all stiffeners and bracings. For continuous bridges with variable depth, Fig. 8 may be used to provide a rough guide, assuming a span-to-
where n = number of spans.
3.2.4 Universal beams An indication of beam size for simply supported spans may be obtained from Figs. 9 and 10 for elastic or plastic stress analysis respectively. BS 5400 permits the use of either option, provided that the cross section is ‘compact’; this condition being satisfied for all sections shown in Fig. 10. Sufficient ductility is also required. It is apparent that plastic stress analysis can achieve significant economy in extending the span range of universal beams. In practice, a serviceability stress check (SLS) must be made including the effects of shear lag. There is advantage also in using the plastic design option for continuous spans but some universal beams may need to be classed as 'non-compact', requiring elastic analysis in hogging regions because the web depth between the (elastic) neutral axis and its compressive edge may exceed 28t w, depending upon the amount of longitudinal slab reinforcement. An overall unit weight for universal beam bridges may be estimated at the conceptual stage by adding an allowance of approximately 8% to the weight of the main beams to allow for any bracings and stiffeners etc. Figs. 9 and 10 refer to mass per metre of universal beams.
1. Left: Milton Bridge Lesmahagow, Scotland 2. Right: Fossdyke Bridge (Photo courtesy of Cleveland Bridge (UK) Ltd.) Lincoln, England
Composite steel highway bridges 15
Initial sizes and overall unit weight
Reference figures 9 & 10
Universal beam size
Actual depth (mm)
3.2.5 List of symbols
Serial size (mm)
Mass per metre (kg/m)
914 x 419
388
921.0
343
911.8
289
926.6
253
253
918.4
HA
224
224
910.4
HB
388 343 289
914 x 305
201 226
838 x 292
201
903.0
226
850.9
194
194
840.7
176
176
834.9
197
769.8
173
762.2
197
762 x 267
173 147 170
686 x 254
152
147
754.0
170
692.9
152
687.5
Af
Flange area (m2)
A fb
Bottom flange area (m2)
A ft
Top flange area (m 2)
D
Girder or beam overall depth excluding slab or finishes (m) Standard highway loading defined in BD37 Abnormal highway loading defined in BD37, 45 units assumed
K af
Girder spacing factor for flange area
K tw
Girder spacing factor for web thickness
Kw
Girder spacing factor for unit weight
L
Span centre to centre of bearings (taken as 1.25 x span for end span of continuous bridges)
kg/m
2
Unit weight of steelwork in bridge expressed as: total steelwork weight (kg) W x overall bridge length
s
Average girder spacing defined as W/N (m)
tw
Web thickness (mm)
W
Overall deck width including parapets (m)
140
140
683.5
125
125
677.9
238
635.8
n
Number of spans
179
179
620.2
N
Number of girders (refer to Section 3.2.3 for
149
149
612.4
140
617.2
125
125
612.2
113
113
607.6
101
101
602.6
238
140
610 x 305
610 x 229
Table 1 (with reference to sizes in Figs. 9 and 10)
Table 1 above defines the referencing system for the serial sizes in Figs. 9 and 10, which is based on the mass per metre of universal beams. Larger sizes are available (e.g. 1016), but are unlikely to be economic compared to fabricated plate girders.
16 Composite steel highway bridges
box girders) Notes (i) Where relevant, symbols correspond with BS 5400 Part 3. (ii) Units where relevant are shown in parentheses.
Worked examples – use of charts
4. Worked examples – use of charts 4.1 Continuous plate girder bridge
Flange and web sizes
A composite highway bridge has 3 continuous spans –
Girder spacing factors: for 'S' = 3.0m
A, B and C of 24, 40 and 32m.
From Fig. 7: K af = 0.87, Kaf = 0.85*, K tw = 0.95
Overall deck width is 12m and it carries 45 units of HB
(*top flange span girders only).
loading (as shown in figure 2). There are 4 plate girders in the cross section of 1.75m depth. Estimate the main girder sizes and the total weight of structural steel. Average girder spacing 's' = W/N =12m/4 No. = 3.0m
W = 12m
D = 1.75m
Span girder
Pier girder
24m Span A
Span girder
40m Span B
Pier girder
Span girder
32m Span C
Figure 2 Worked example
1. Left: Trent Viaduct Newark, England 2. Right: A69 Haltwhistle Viaduct (Photo courtesy of Cleveland Bridge (UK) Ltd.) Northumberland, England
Composite steel highway bridges 17
Worked examples – use of charts
Span A: 24m
Pier girders
This is an end span so take L = 1.25 x 24m = 30m
Take L as the greater of the two adjacent spans, i.e.
Therefore L/D = 30m/1.75m = 17, so assume L/D = 20
assume L = 40m at both supports, hence, L/D = 40m/1.75m = 22.9
Top flange A ft
= A ft (from Fig. 5) x K af = 0.006 x 0.85 = 0.0051m2
Top flange A ft
= A ft (from Fig. 6) x K af = 0.017 x 0.87 = 0.015m2
400 x 15 top flange
400 x 40 top flange Bottom flange A fb
= A fb(from Fig. 5) x K af Bottom flange A fb
= 0.014 x 0.87 = 0.012m2
= A fb(from Fig. 6) x K af = 0.033 x 0.87 = 0.029m2
500 x 25 bottom flange
500 x 60 bottom flange Web t w
= t w (from Fig. 5) x K tw Web t w
= 10 x 0.95 = 9.5mm
= t w (from Fig. 6) x K tw = 16.8 x 0.95 = 16mm
Use 10mm web
Therefore use 18mm web
Span B: 40m Span girder
Steel tonnage
L/D = 40m/1.75m = 22.9
Girder spacing for end span A:
Top flange A ft
= A ft (from Fig. 5) x K af = 0.009 x 0.85 = 0.0077m
2
= 3.0m L = 1.25 x 24m = 30m
for centre span B:
L = 40m
for end span C:
L = 1.25 x 32m = 40m
400 x 20 top flange Therefore mean span Bottom flange A fb
= A fb (from Fig. 5) x K af
4
L14 + L24...Ln4
= 0.020 x 0.87 = 0.017m2
n
500 x 35 bottom flange 4
Web t w
= t w (from Fig. 5) x K tw = 10 x 0.95 = 9.5mm
304 + 404 + 404 = 37.5m 3
Use 10mm web L/D = 37.5m/1.75m = 21
Span C: 32m
= kg/m2 (from Fig. 8) x Kw (from Fig. 7)
This is an end span so take L = 1.25 x 32m = 40m
= 145kg/m2 x 1.04 = 151kg/m2
therefore sizes as 40m span. Hence, steel weight = 151 kg/m2/1000 x (24m + 40m + 32m) x 12m wide = 174 tonnes
18 Composite steel highway bridges
Worked examples – use of charts
4.2 Simply supported universal beam bridge A composite bridge has a simply supported span of 24m. (as shown in figure 3). Overall deck width is 9.6m and it carries HA loading only. Estimate the beam size and total weight of structural steel assuming there are 4 beams in the cross section.
W = 9.6m
24m
Figure 3 Worked example
(a) For an elastic stress analysis refer to Fig. 9
(b) For a plastic stress analysis refer to Fig. 10
For 4 beams
For 'S' = 2.4m. Use 289
'S' = 9.6m/4No. = 2.4m. Use 388
i.e. 914 x 305 x 289kg/m universal beam
i.e. 914 x 419 x 388kg/m Universal Beam Total weight approx. (289kg/m /1000) x 4No. x 24m x 1.08
Total weight approx. (388kg/m/1000) x 4No. x 24m x 1.08
= 30 tonnes (i.e. 130kg/m 2) (the 1.08 factor allows for 8% bracing + stiffener Thus, plastic stress analysis offers a significant
allowance)
reduction in beam size but SLS checks must be made. 2
= 40.2 tonnes (i.e. 174kg/m )
1. Left: A9 Bridge Pitlochry, Scotland 2. Right: A1(M) Yorkshire, England
Composite steel highway bridges 19
References
5. References 1. BS5400, Steel, Concrete and Composite Bridges. British Standards Institution. Design Manual for Roads and Bridges (DMRB): 2. DMRB 1.3 BD37 Loads for Highway Bridges. 3. DMRB 1.3 BD13 Codes of Practice for Design of Steel Bridges. 4. DMRB 1.3 BD & BA 57 Design for Durability. 5. DMRB 1.3 BA 42 Design of Integral Bridges. 6. DMRB 2.3 BD7 Weathering Steel for Highway Structures. 7. DMRB 2.3 BA36 The Use of Permanent Formwork. Steel Construction Institute Publications 8. P163: Integral Steel Bridges – Design Guidance. 9. P180: Integral Steel Bridges – Design of a Single Span Bridge. 10. P250: Integral Steel Bridges – Design of a Multi Span Bridge. 10a. P340: Technical Report on Integral Steel Bridges. 10b. P339: Design Guide for Ladder Deck Bridges. 11. Corus Publication – Weathering steel bridges. Material Standards (EN) 12. BS EN 10025-2 – Non-alloy structural steels. 13. BS EN 10025-5 – Structural Steels with improved atmospheric corrosion resistance. 14. BS EN 10164 – Steel products with improved deformation properties perpendicular to the surface of the product. Other Standards (BS) 15. BS 5975 Code of Practice for Falsework.
BS 5400
Title
Part
DMRB
MCDHW
Document*
Document**
1
General Statement
BD15
–
2
Specification for Loads
BD37
–
3
Code of Practice for Design of Steel Bridges
BD13
–
4
Code of Practice for Design of Concrete Bridges
BD 24
–
5
Code of Practice for Design of Composite Bridges
BD16
–
6
Specification for Materials & Workmanship, Steel
–
Volume 1 Series 1800
7
Specification for Materials & Workmanship, Concrete, Reinforcement & Prestressing Tendons
–
Recommendations for Materials & Workmanship, Concrete, Reinforcement & Prestressing Tendons
–
9
Bridge Bearings
BD20
–
10
Code of Practice for Fatigue
BD9
–
8
Volume 1 Series 1700 Volume 2 Series NG1700
* Design Manual for Roads and Bridges published by the Stationery Office for the Overseeing Organisations. ** Manual of Contract Document for Highway Work published by the Stationery Office for the Overseeing Organisations.
20 Composite steel highway bridges
45
50
55
75
60
50
45
35
25
30
35
25
30
35
40
45
55
50
40
60
55
45
40
65
70
75
600 x
60
65
70
75
650 x
75 70 65 60 55 50 45 40 35 30 25 20
500 x
Flange size (mm)
50
55
60
65
70
800 x
65
70
75
1000 x
S = 3.5m
400 x 75 70 65 60 55 50 45 40 35 30 25 20 15 0
0.01
0.02
0.03
0.04
0.05
0.06
0.07
(m2)
Af
20
25
30
Figure 4: Simply supported bridges – flange (at mid-span) and web (at support)
6. Figures
35
Afb
40
Afb
Afb
Span (m)
45
Aft
50
Afb
HA
HB
HA
55
/HB
tw
tw
HB HA/
HB HA
Aft
60
30
30
30
D
30
L/
20
20
20
20
10
11
12
13
14
15
tw (mm)
Figures
Composite steel highway bridges 21
22 Composite steel highway bridges
70
65
65
60
25
30
35
40
45
50
25
30
35
40
45
50
55
60
75
70
55
600 x
650 x
75 70 65 60 55 50 45 40 35 30 25 20
500 x
400 x 75 70 65 60 55 50 45 40 35 30 25 20 15
Flange size (mm)
S = 3.5m
0
0.01
0.02
0.03
0.04
Af (m2)
0
25
30
Figure 5: Continuous bridges – flange and web sizes of span girders
35
Aft
40 Span (m)
Aft
tw
HA/HB
Afb HA/HB
Afb
45
tw
HA
Afb
50
Afb
HA
HB
HB
55
D
60
30
30
30
L/
30
20 20
20
20
10
11
12
13
14
15
tw (mm)
Figures
45
50
55
60
1000 x
35
40
45
50
55
60
65
70
75
800 x
25
30
35
40
45
50
25
30
35
40
45
50
55
60
65
55
70
70
65
75
75
60
600 x
650 x
75 70 65 60 55 50 45 40 35 30 25 20
500 x
Flange size (mm)
S = 3.5
400 x 75 70 65 60 55 50 45 40 35 30 25 20 15 0
0.01
0.02
0.03
0.04
0.05
Af (m2)
20
25
Figure 6: Continuous bridges – flange and web sizes of pier girders
30
35
Span (m)
40
HA/HB
B HA/H
H
B A/H
45
HB HA/
Afb
50
Aft
Aft
Afb
55
tw
tw
L / 30 D
60
30
30
20
20
20
10
11
12
13
14
15
16
17
18
19
20
21
tw (mm)
Figures
Composite steel highway bridges 23
0.4
0.5
0.6
0.7
0.8
0.9
1.0
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
1
Kw
3
4
5 Haunch slab
Girder spacing - S (m)
Girders & slab
2
on
Stringer
6
ly Ka f
2.0
f Ka
p To
d mi ge Fla n
24 Composite steel highway bridges -sp an
Figure 7: Girder spacing factors
7
8
Cross girders
L=60
L=40
Ktw
Figures
Ka f
Kt
w
Kaf, Ktw, Kw
Kg/m2
80
100
120
140
160
180
200
220
240
260
280
300
320
340
360
380
20
m
s
ea
400
rs
al b
Un ive
25
30
35
HB
40 Span (m)
45
HA
50
HA
HB
55
HB
HA
HA
HB
60
30
30
30 L / D
20 20
20
20
Simply supported Continuous
Figure 8: Overall unit weights – plate girder bridges (S = 3.5)
Figures
Composite steel highway bridges 25
26 Composite steel highway bridges
7 19
1 20
17
12
13
14
15
28 9
17
17
6
3
1
79
14
2.2
4 19
2.3
38
2.4
4/2
2.5
19
2.6
8
2.7
/23
2.8
2.9
3.0
3.1
3.2
3.3
3.4
3.5
22 4 16
17
34
Beam spacing - S (m)
Figure 9: Universal beams – elastic stress analysis
18
28 9 Span (m)
19
20
21
22
23
24
HB
HA
25
Figures
8 38
3 34
8 38
3
3 25
6 22
253
224
201
6
173
7
28 26
27
HA
HB
29
Figures
25
8 38
3
23
24
34
8 38
3
21
34
9
22
28
3
6
22
1
20
4
19
6 22
38
7/2
19 4
22
16
1
20
6
17
3
17 38
15
4/2
19
79 0/1
197 176
12
2.2
2.5
2.6
2.7
3.1
125 113 101
125 2.8
3.2
3.3
3.4
3.5
0)
(61
140
2.3
86)
2.9
1
3.0
2
15
7
/14
14 40/
13
7 14
2
15
9(6
179
) 86 0(6 14 9 14 0) (61 140
2.4
173 170
14
17
Beam spacing - S (m)
Figure 10: Universal beams – plastic stress analysis
4 22
17
18
2
53
Span (m)
9
19
28
20
25
Composite steel highway bridges 27
www.corusgroup.com Care has been taken to ensure that this information is accurate, but Corus Group plc, including its subsidiaries, does not accept responsibility or liability for errors or information which is found to be misleading. Copyright 2005 Corus Designed and produced by Orchard Corporate Ltd.
Corus Construction & Industrial Technical Sales & Marketing PO Box 1 Brigg Road Scunthorpe North Lincolnshire DN16 1BP T +44 (0) 1724 405060 F +44 (0) 1724 404224 E
[email protected] www.corusconstruction.com English language version
CC&I:CD:3000:UK:04/2005/r