Check List for use by Bu ilding Construction Supervisors
FEDERAL DEMOCRATIC REPUBLIC OF ETHIOPIA MINISTRY OF WORKS AND URBAN DEVELOPMENT
CHECK – LIST
FOR USE BY BUILDING CONSTRUCTION SUPERVISORS
Ministry of Works and Urban Development Addis Ababa, Ethiopia 2001
Ministry of Works and Urban Development
1
2
Check List for use by Bu ilding Construction Supervisors
FOREWORD The Proclamation to define the powers and duties of the Federal and Regional Executive organs of the Federal Democratic republic of Ethiopia No. 4/1995 empowers the Ministry of Works & Urban Development to prepare the Country's Building Code, issue Standards and Guidelines for design and construction works, registration of professionals and consultants and follow up and supervise the implementation of same. In exercising these powers and in discharging of its responsibilities, the Ministry is issuing a series of Building Code Standards, Manuals and Guidelines of general application. The purpose of these documents i s to serve s erve as nationally recognized documents, documents, the application of which is deemed to ensure compliance of constructions with the minimum requirements for design, procurement procedures, construction and quality of materials set down by the Ministry. The major benefits to be gained in applying these documents are the harmonization of professional practice and the ensuring of appropriate levels of safety, health and economy with due consideration of the objective conditions and needs of the country. As the documents are technical documents which, by their very nature, require periodic updating, revised editions will be issued by the Ministry from time t o time as appropriate. The Ministry welcomes comments and suggestions on all aspect of the documents. All feedback received will be carefully reviewed by professional experts in the field with a view to possible incorporation of amendments in the future editions.
Haile Assegide Minister Ministry of Works and Urban Development 2001
Ministry of Works and Urban Development
2
Check List for use by Bu ilding Construction Supervisors
FOREWORD The Proclamation to define the powers and duties of the Federal and Regional Executive organs of the Federal Democratic republic of Ethiopia No. 4/1995 empowers the Ministry of Works & Urban Development to prepare the Country's Building Code, issue Standards and Guidelines for design and construction works, registration of professionals and consultants and follow up and supervise the implementation of same. In exercising these powers and in discharging of its responsibilities, the Ministry is issuing a series of Building Code Standards, Manuals and Guidelines of general application. The purpose of these documents i s to serve s erve as nationally recognized documents, documents, the application of which is deemed to ensure compliance of constructions with the minimum requirements for design, procurement procedures, construction and quality of materials set down by the Ministry. The major benefits to be gained in applying these documents are the harmonization of professional practice and the ensuring of appropriate levels of safety, health and economy with due consideration of the objective conditions and needs of the country. As the documents are technical documents which, by their very nature, require periodic updating, revised editions will be issued by the Ministry from time t o time as appropriate. The Ministry welcomes comments and suggestions on all aspect of the documents. All feedback received will be carefully reviewed by professional experts in the field with a view to possible incorporation of amendments in the future editions.
Haile Assegide Minister Ministry of Works and Urban Development 2001
Ministry of Works and Urban Development
3
Check List for use by Bu ilding Construction Supervisors
PREFACE This check-list for site supervisors is issued by the Ministry of Works and Urban Development for use by Employers, Consultants and Contractors in order to ensure a uniform system of supervision of building construction projects and as a result ensure a safe and durable construction. It is to be of use mainly when construction works are carried out by contractors and can in some ways be of use for construction carried out by direct labour. In this check-list the responsibilities, liabilities and limitations of the supervisor are briefly mentioned. The steps to be followed in checking building construction works are expressed in general terms. Details of construction are specified in the drawings, technical specifications and in the general and special provisions of the contract. The duty of the site supervisor is to ensure that the construction works are executed in accordance with the contract requirements. Therefore in the application of this check-list the details specified in the contract document always precede before the application and use of it. There are also tables and forms in this check-list that help as records of the incidences affecting the work and as references. In addition the standard technical specification is used as reference on the preparation of this checklist.
Ministry of Works and Urban Development
Check List for use by Bu ilding Construction Supervisors
ACKNOWLEDGEMENT
In July 2000, the Ministry of Works and Urban Development invited National Consulting firms to compete for the preparation of codes and manuals. One of these, is the present Tessema
" ______________________" ______________________"
Demisse Consulting Architects and Engineers was awarded the
contract for the preparation of this document, and prepared prepared it in association with professionals. The working group of the document was: Damtew Wolde, __________________, __________________,
who drafted the document; and Beyene Wolde Gabriel, B.Sc. (Eng.),
who reviewed the document with comments and suggestions. The document is based based on " _______________________ ________________________ _ " prepared prepared by the World Bank for use of its browses. After presentation to the MoWUD, the document was commented on by professionals of the Ministry and other invited institutions and individuals. MoWUD wishes to acknowledge the contributions made by the Consulting Office and the associated professionals involved in its preparation and to thank all those who made comments. Our thanks also to ________________ ________________ for use of their document. document.
Ministry of Works and Urban Development
4
5
Check List for use by Bu ilding Construction Supervisors
TABLE OF CONTENTS PAGE
1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. 24. 25. 26. 27. 28. 29. 30. 31 32. 33. 34. 35. 36. 37. 38. 39. 40.
FORWARD ……………………………………………………………………… PREFACE ............................................................................................................. ACKNOWLEDGEMENT ..................................................................................... INVESTIGATION & PREPARATION OF SITE ................................................. SETTING OUT ...................................................................................................... EXCAVATION & EARTHWORK ....................................................................... FOUNDATION TRENCH & PIT EXCAVATION................................................ FOUNDATION IN STONE MASONRY .............................................................. BACK FILLING...................................................................................................... HARD CORE ......................................................................................................... CONCRETE ........................................................................................................... PRESTRESSED CONCRETE .............................................................................. FORM WORK........................................................................................................ STEEL REINFORCEMENT ................................................................................. MORTAR .............................................................................................................. STONE MASONRY ............................................................................................. HOLLOW CONCRETE BLOCK WALL ............................................................. WALLS WITH BRICKS........................................................................................ WOODEN WALLS............................................................................................... PLASTER AND POINTING................................................................................. STRUCTURAL STEEL WORK........................................................................... PAVIOR (TILES PAVIOR) .................................................................................. WALL TILES........................................................................................................ P. V. C. TILES....................................................................................................... ROOFING AND CLADDING .............................................................................. GUTTERS AND DOWN PIPES........................................................................... CARPENTRY AND JOINERY ............................................................................ CEILING ............................................................................................................... PAINTING............................................................................................................. GLAZING.............................................................................................................. WATER WELL..................................................................................................... WATER SUPPLY LINES..................................................................................... PLUMBING AND SANITARY INSTALLATIONS............................................ SEWER SYSTEM................................................................................................. SEPTIC TANK & SOAK AWAY PIT.................................................................. ELECTRICAL INSTALLATIONS ....................................................................... RETAINING WALLS........................................................................................... SITE WORK.......................................................................................................... ROAD AND FOOTPATHS .................................................................................. DRAIN CHANNELS & CULVERTS................................................................... FENCING AND GATE......................................................................................... PREPARATION OF PAYMENT CERTIFICATES............................................. INFORMATION IN CONSTRUCTION PROCEDURES ...................................
Ministry of Works and Urban Development
1 2 3 6 6 6 7 8 8 9 9 13 14 16 17 17 18 19 20 20 20 22 22 22 23 24 24 25 25 26 26 26 26 27 28 28 29 30 30 31 31 32 32
6
Check List for use by Bu ilding Construction Supervisors
TABLE OF CONTENTS
TABLES & FORMS
1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. 24. 25. 26. 27. 28.
PAGE
TABLE 8.5.3a. STANDARD CONCRETE MIX …………………………….. TABLE 8.5.3b. STANDARD CONCRETE MIX .............................................. HANDING OVER THE CONSTRUCTION SITE ............................................. ACQUISITION OF DOCUMENTS .................................................................... FOR MATERIAL TESTING .............................................................................. EVALUATION OF TEST RESULTS .................................................................. SOIL IDENTIFICATION AND ACCEPTANCE OF EXCAVATION FOUNDATION DEPTHS ................................................... SITE DIARY ........................................................................................................ MONTHLY REPORT ......................................................................................... QUARTERLY REPORT .................................................................................... WORK ORDER ................................................................................................... PAYMENT CERTIFICATE ................................................................................ SITE HANDOVER INSPECTION CERTIFICATE ............................................ SITE PREPARATION INSPECTION CERTIFICATE....................................... FOUNDATION EXCAVATION INSPECTION................................................. EARTHWORKS INSPECTION CERTIFICATE................................................ MATERIAL QUALITY EVALUATION CERTIFICATE .................................. CONCRETE WORK INSPECTION CERTIFICATE ......................................... MASONRY WORK INSPECTION CERTIFICATE .......................................... STRUCTURAL STEEL WORK INSPECTION.................................................. STRUCTURAL TIMBER WORK INSPECTION............................................... CARPENTRY & JOINERY WORK INSPECTION ........................................... ROOFING & CLADDING WORK INSPECTION ............................................. FINISHING WORK INSPECTION CERTIFICATE........................................... SITE WORK INSPECTION CERTIFICATE...................................................... MINUTES OF INSPECTION FOR TEMPORARY ACCEPTANCE ................ TEMPORARY ACCEPTANCE ........................................................................ FINAL ACCEPTANCE ......................................................................................
39 40 41 46 51 52 55 56 57 58 59 60 61 62 63 64 65 66 68 70 72 75
APPENDIX 1 : GUIDELINE ON CONTROL OF CONSTRUCTION PROJECTS ..............................................
79
APPENDIX 2 : LIST OF MAJOR DUTIES AND RESPONSIBILITIES OF A RESIDENT ENGINEER (SUPERVISOR ) ................................................
84
Ministry of Works and Urban Development
33 34 35 36 37 38
Check List for use by Bu ilding Construction Supervisors
1.
INVESTIGATION AND PREPARATION OF SITE
CHECK:
1.1
The site visually if underground utilities cross it.
1.2
The site on maps showing the location of underground structures and utilities to avoid breaking them during construction.
1.3
The site plan and layout of buildings and sewer system specially concerning levels and soil condition. If changes are necessary submit a writ ten report to the designer.
1.4
The area to be cleared off and take measurements.
1.5
The trees and bushes within the foundation to be cut and rooted up as given in the standard technical specification.
1.6
Permission is obtained from local authorities to cut down trees outside the foundation areas.
1.7
Boarder lines are agreed with local municipality and corner stones placed.
1.8
The connection points for water and electricity are agreed upon with local authorities.
1.9
All necessary temporary drains are constructed to keep the site free of water.
2.
SETTING OUT
CHECK:
2.1
The setting out is done correctly with proper measuring tape and accurate levelling instrument.
2.2
All measurements to confirm the accuracy and correct locations of working areas are properly stated out.
2.3
The elevation reference point in accordance with the survey map, and confirm.
2.4
All bottom of trenches and floor levels are according to the elevations shown on the drawings.
3.
EXCAVATION AND EARTHWORK
3.1
Check all top soil is excavated separately.
3.2
Decide the place to pile up the suitable excavated material and check it is 2 meters outside the building perimeter.
3.3
Decide the place for the cart away which is not necessary for backfilling or terracing.
Ministry of Works and Urban Development
7
Check List for use by Bu ilding Construction Supervisors
CHECK:
3.4
For sites where blasting is proposed, the explosives are used in the quantities and manner recommended by the manufacturers. Check a written consent is obtained on each occasion the contractor wished to use explosives.
3.5
All excavations are carried out to the lines, levels, widths and depths shown on the drawings.
3.6
Any discrepancies in levels, dispositions etc. are reported to the engineer prior to proceeding with the works.
3.7
All necessary temporary drains and culverts are constructed to keep the site free of water.
3.8
Slopes to embankments, cuttings, shoulders, ditches etc.; are trimmed to the dimensions and inclinations shown on drawings.
3.9
Cut for roads is carried out until a level of suitable material is allowed.
3.10 Excavations are suitably trimmed and levelled before any concrete or masonry work is placed. 3.11 In locations where the soil is subject to softening during excavation, a bottom layer of soil removed immediately before the placing of concrete, in accordance with the standard technical specification. 4.
FOUNDATION TRENCH AND PIT EXCAVATION
CHECK:
4.1
The foundation drawings to correspond with the conditions on the site, if not prepare a written report and submit to the designer immediately.
4.2
The foundation depth, width, line and levels to correspond the drawings.
4.3
The excavation or foundation is executed 25cm. wider on each side than the thickness of the foundation wall as given in the standard technical specification.
4.4
The trench and pits to be clean from grass, bushes and pieces of wood.
4.5
The trench and pits to be kept free of water by pumping or other means.
4.6
The foundation engineer has accepted the excavated foundation depths by filling form No. 005.
4.7
The foundation excavation is suitably trimmed and levelled before concrete or masonry work in placed.
Ministry of Works and Urban Development
8
Check List for use by Bu ilding Construction Supervisors
4.8
In the event of over excavation, without approval the area to be filled with selected excavation or borrowed material or class 5 concrete in accordance with the standard technical specification.
4.9
The faces of excavation is retained with sheeting, tim-bearing, strutting and shoring to protect workmen and prevent damage where necessary.
5.
FOUNDATION IN STONE MASONRY
CHECK:
5.1
The trench to be clean from grass, bushes and pieces of wood.
5.2
The stone is of the type given on specifications.
5.3
The stone to be hard, sound, free from cracks and decay and not weathered.
5.4
The stone is freshly quarried from an approved quarry.
5.5
The stone not to be round surfaced.
5.6
The stone masonry execution is with specified mortar and with well filled joints.
5.7
The stone masonry during execution is kept free from solid and other kind of dirt.
5.8
The length of stone does not exceed three times its height.
5.9
The mix of lean concrete to correspond the specification.
5.10 The mix proportion of mortar is correct. 6.
BACKFILLING
CHECK:
6.1
All internal back filling is done with approved material, if possible with material excavated on the site.
6.2
All external backfilling around foundation walls and behind retaining walls shall be done with approved selected materials, if possible with material excavated on the site which is capable of being compacted and form a stable filling.
6.3
all organic materials, such as pieces of wood, roots, bushes and black cotton soil are removed from all backfill material.
6.4
All ground trenches and places where backfilling shall be executed are clean from grass, bushes and pieces of wood.
Ministry of Works and Urban Development
9
Check List for use by Bu ilding Construction Supervisors
6.5
Where pipes and electrical cables are in connection with the backfilling, the work shall be executed very carefully, so they do not break or get damaged.
6.6
All backfilling to be in layers and compacted to 95% of maximum dry density in accordance with the standard technical specification.
6.7
Each layer to be well rammed and consolidated with the addition of water as necessary to achieve the required compaction.
6.8
The maximum layer of fill for one time compaction does not exceed 20cm. thickness in accordance with the standard technical specification.
6.9
Depressions or voids that are crated during trimming of slopes to embankments, cuttings, shoulders, ditches etc.; are filled with suitable material and to approved compaction.
6.10 Any material which after repeated compaction does not fulfil the requirements is removed and replaced. 7.
HARD CORE
CHECK:
7.1
Stone for hardcore is sound and approved quality.
7.2
All stones in the hardcore are of approximately equal and recommended size.
7.3
All hardcore is well rammed and consolidated with the top surface blinded with crushed aggregate of 20mm. thickness in accordance with the standard technical specification.
7.4
The thickness of the hardcore satisfies the specification or design.
7.5
the placing of stones to result in minimum voids.
8.
CONCRETE
CHECK:
8.1
All ingredients cement, aggregates and water are of the type and quality specified.
8.2
Cement is fresh, not older than six months and is delivered to the site in the manufacturer's original sealed bags.
8.3
Cement is stored in a dry and well ventilated store, on a wooden floor raised minimum 20cm. above the ground.
8.4
Cement is stocked separately.
8.5
The cement has markings showing the type and date of consignment pinned to it and check it is used in the order of its arrival.
Ministry of Works and Urban Development
10
11
Check List for use by Bu ilding Construction Supervisors
8.6
Cement more than six months old after production is tested to satisfy the specified requirements.
8.7
Sand or fine aggregate to be clean river or pits sand of approved quality and consist of hard, dense, durable uncoated rock fragments.
8.8
Sand to be clear of impurities like dust, mica and organic matter.
8.9
Rejected samples of aggregates are removed from the site within 24 hours.
8.10 Coarse aggregate to be crushed basaltic stone or gravel of approved quality. 8.11 Coarse aggregate to be hard, dense, durable non-porous and uncoated rock fragments. 8.12 Coarse aggregate to be free from impurities like clay, soft thin elongated or laminated pieces and shall be free from alkali and organic matter. 8.13 The gradation of coarse aggregate to comply with the standard technical specification. 8.14 Before any coarse aggregate is delivered to the site, the quality is approved at the quarry by the designer. 8.15 Aggregates are stored on clear hard surface to prevent contamination by soil. 8.16 Different grades are stocked independently. 8.17 Water used for mixing concrete is clean and free from injurious amounts of oil, acids, alkalies, organic materials. 8.18 Water is not taken from sea or tidal rivers to be used for structural concrete. If possible water shall be piped or otherwise stored in an enclosed container free from contamination. 8.19 If there are any doubts about the quality of the water a sample shall be sent to the designer or engineer for testing. °
8.20 If the temperature of the water exceeds 60 c it is first mixed with the aggregate before the cement is added. 8.21 The concrete is mixed to a uniform colour and consistency prior to placing. 8.22 Hand mixing is not allowed but if unavoidable shall be used only for class II concrete and shall under no circumstance be allowed for concrete of class C-200 and higher. 8.23 Concrete is mixed in an approved mechanical batch mixer machine, the mixer is thoroughly cleaned from hardened concrete and other kind of dirt before use. 8.24 Mixer which has been out of use for more than 20 minutes is thoroughly washed before any fresh concrete is mixed as specified in the standard technical specification.
Ministry of Works and Urban Development
12
Check List for use by Bu ilding Construction Supervisors
8.25 The mixer drum is tight to avoid loss of mortar. The values must not leak mixing water. 8.26 The specified mixing time is carefully adhere to but in no case shall the mixing discontinue for less than 2 minutes after adding water as specified in the standard technical specification. 8.27 The batch capacity. The contractor must not be allowed to exceed the rated capacity of the mixer. 8.28 The materials enter the drum rapidly. 8.29 The whole of the mixed batch is removed before materials for fresh batch enter the mixer. 8.30 Mixed concrete is not modified by the addition of extra water or cement, in order to facilitate handling or any other purpose. 8.31 Before any casting starts at the site, test cubes of side dimension 15x15x15 or cylinders of diameter 15cm and length 30cm of wood or steel are made ready. 8.32 All reinforcement and form work are properly placed prior to any concreting and the mix approved and also check from No. 004 is filled a nd approved by the designer. 8.33 For any one structure samples are made at the same time from the same batch and the date clearly marked on each cube. 3
8.34 Test cubes are made when directed but not less than one set of nine cubes for each 100m 3 of concrete placed, or if the rate of placing is less than 100m then each 10 days or every floor for multi-storey structures in a ccordance with the standard technical specifications. 8.35 Three cubes of each set are tested at 3 and 7 or 7 and 14 days and the third at 28 days all in accordance with the code of practice. 8.36 In the absence of approved design mix that the standard mixes in Tables 8.5.3a and table 8.5.3b or the mix design given in the standard technical specification are followed. 8.37 Before any casting starts the consistency of fresh concrete must be measured using the slump test, from the same batch for test cubes. 8.38 Concrete is son transported as rapidly as practicable and placed such that contamination, segregation or loss of constituent materials does not occur. 8.39 All placing of concrete starts from one end and continue in the same direction without any break. 8.40 Concrete is deposited as near as practicable and no concrete is dropped from a height exceeding 2 meters as specified on the standard technical specification. 8.41 When chutings is used the inclination of the chute shall be such as to allow the concrete to flow without the use of water in excess of the specified volume for mix and without
Ministry of Works and Urban Development
Check List for use by Bu ilding Construction Supervisors
segregation or loss of the ingredients. Details of any proposed chuting plant must be approved before the plant is delivered. 8.42 The vibration is carefully done, and continues until a dense homogeneous mass is produced and surface is fairly smooth. 8.43 Concrete is not over vibrated so that the consistency of the concrete is maintained and separation of materials is caused. 8.44 If construction joints are necessary they are approved by the designer. 8.45 When concrete casting continues on a construction joint, the joint is clean from foreign matter. 8.46 When concrete casting continues on a construction joint, the surface of the joint is roughened and aggregate is exposed without being damaged. 8.47 The roughened surface of the construction joint is wetted with thin layer of mortar prior to concreting. 8.48 After casting is completed and for 7 days thereafter, that the concrete is kept damp (cured) to minimize loss of moisture from the concrete. 8.49 Whenever testing of a material is required fill the requisition from No.005 and for the evaluation of test result fill form No.006 and get the approval of the engineer or designer when the result is submitted. 8.50 Inspection prior to concreting: CHECK:
The rigidity of the scaffolding and shuttering The leak-tightness of joints between form work elements Conformity of the dimensions of the form work with the (drawings) The cleanliness of the form work The surface conditions of the reinforcement The position and size of reinforcement The rigidity of the reinforcement securing systems, and the quality of the joints between bars. − Cover to reinforcement is correct. − Class of concrete, mix design and water cement ratio.
− − − − − − −
8.51
Pre cast concrete is cast under sheds and remain in the moulds for 3 days and further 7 days after removal from the moulds. Then removed from the sheds and stocked in the open for at least 7 days to season.
8.52
Random load testing is made on the pre cast units and the damaged ones immediately replaced.
Ministry of Works and Urban Development
13
Check List for use by Bu ilding Construction Supervisors
8.53 Pre cast units and hoisted and placed in proper position in such a way as to avoid over stressing or damaging the units nor causing damage to previously erected structure. 8.54 If any doubt about the quality of, aggregate, cement, reinforcement and water arises sample are sent for testing. 9.
PRESTRESSED CONCRETE
CHECK:
9.1
All pre stressing components are stored in clean dry conditions.
9.2
All pre stressing components are clean and free from loose rust at the time of fixing in position and subsequent concreting.
9.3
All pre stressing tendons are not welded within the length to be tensioned.
9.4
All pre stressing tendons (cables) are not twisted and individual wires or strands are identifiable at each member.
9.5
All ducts and tendons are respectively sealed and protected until the tendon is threaded through and the stressing operations are commenced.
9.6
All anchor cones, blocks and plates are positioned and maintained during concreting such that the center line of the duct passes axially through the anchorage assembly.
9.7
All bearing surface of the anchorages are clean prior to concreting and tensioning.
9.8
The tendons immediately and during stressing do not exceed the strength specified.
9.9
Stressing is from both ends unless required or agreed by the engineer.
9.10
The tendons are anchored only if the pre stressing is applied to the satisfaction of the engineer.
9.11
The jack pressure is released in such a way as to avoid shock to the anchorage or tendons.
9.12
If the pull-in of the tendons at completion of anchoring is greater than that agreed by the engineer, the load shall be released slowly and tensioning carried out afresh.
9.13
Sufficient test cubes are taken and specified transfer strength is attained.
9.14
The tendons are not cropped or cut prior to 3 days after grouting.
9.15
Full records of all tensioning operations including the measured extensions, pressure guage or load all readings and the amount of pull-in at each anchorage, are kept.
Ministry of Works and Urban Development
14
Check List for use by Bu ilding Construction Supervisors
9.16
All ducts are thoroughly cleaned by compressed air or method specified prior to grouting.
9.17
all anchorages are sealed before grouting.
9.18
The ducts are completely filled with grout.
9.19
The filled ducts are protected to the satisfaction of the engineer that they are not subjected to shock or vibration for one day.
9.20
Full records of grouting including the date each duct was grouted is kept.
9.21
The grout mixer produces a grout of colloidal and uniform consistency.
9.22
The grout is mixed for a minimum of two minutes unless otherwise specified.
9.23
No admixtures like chloride or nitrates are used. But if other admixtures may be used a written permission must be submitted from the engineer and check it is applied strictly with the manufacturer's instructions.
9.24
The gout consists only of ordinary port land cement and water unless otherwise specified.
9.25
Pre stressed members are lifted or supported only at the points specified and handled and placed without impact.
9.26
Beams are prevented from moving laterally during the placing of the in situ concrete.
9.27
The engineer informed in advance of the date of commencement of manufacture and the dates when tensioning of tendons, casting of members and transfer of stress will be undertaken for the first time for each type of beam.
9.28
All pre stressed concrete construction comply the standard technical specification.
10.
FORM WORK
CHECK :
10.1
Form work is so constructed that it can be stripped from the hardened concrete easily without hammering or without such shock or vibration in order to protect the concrete or reduce labour cost.
10.2
The bracing of the form work. The form work must be strong enough to carry the load until the concrete is strong enough to carry itself and hardened sufficiently.
10.3
The inside surface of form works shall, except for permanent form works, or unless otherwise agreed by the engineer, are coated with a release agent.
Ministry of Works and Urban Development
15
16
Check List for use by Bu ilding Construction Supervisors
10.4
Release agents do not come into contact with the reinforcement and anchorages, and should not be visible on the finished works.
10.5
Wooden form works for unexposed concrete surface, are executed of sawed boards with sharp edges and of the same thickness.
10.6
Wooden form works for exposed concrete surface are generally of tongued and grooved boards of the same thickness and free from knots, holes, cracks and splits.
10.7
Form work lumber shall be kept under shed and in varying thickness and width and shall be constantly aerated and under weight to prevent it from decay.
10.8
Before any concreting starts, the form work has the right dimensions and is level and straight.
10.9
Before any concreting starts, all forms are thoroughly cleaned out and free from holes and dirt.
10.10
The top level of the form work is at the same level as the top of the finished concrete.
10.11
All form work is removed without any damage to the concrete during the striking.
10.12
After removal of the form work remedial treatment to surfaces of the hardened concrete is carried out immediately without delay and period of removal is as follows: for vertical form work to columns, walls and beams for soffit form work to slab for props to slabs for soffit form work to beams for props to beams in accordance with the standard technical specification.
- 16 hrs. - 21 days - 14 days - 21 days - 14 days
10.13
Where intended to re-use form work it is thoroughly cleaned and made good to the satisfaction of the engineer.
10.14
Stripping of form work not to be done until concrete is set i.e. should ring under a hammer blow. In no circumstances shall form work be struck until the concrete attains a cube strength of at least twice the stress to which it may be subjected at the time of striking.
10.15
All form work construction and quality comply the standard technical specification.
Ministry of Works and Urban Development
Check List for use by Bu ilding Construction Supervisors
11.
17
STEEL REINFORCEMENT
CHECK:
11.1
Steel reinforcement is stored in clean condition. It should be free from loose rust.
11.2
All reinforcement bars are of the specified quality and in accordance with the standard technical specification.
11.3
Given in the design in cases where certificates for ultimate tensile strength, yield stress, elongation and cold bend tests are not i ssued by the manufacturers.
11.4
The dimension, length and shape of the reinforcement bars is according to the drawings and specifications.
11.5
Bending of reinforcement bars is done with adequate bending tools. But heat is strictly not allowed for bending of reinforcement bars.
11.6
All bars with cracks or splits at the bend are not used for construction.
11.7
All mild steels have their ends booked, and the bending radius meets the specification.
11.8
All reinforcement bars are clean and free from loose rust, grease, oil, or tar and other kind of dirt.
11.9
The reinforcement bars are placed in position according to the drawings, and firmly bound together with mild steel wire, diameter 1 .6mm in accordance with the standard technical specification.
11.10
Before any casting of concrete starts, that pre cast concrete blocks or spacers or metal chairs are prepared and all reinforcement bars are placed on them.
11.11
These blocks or spacers do not turn over when concrete is casted.
11.12
The thickness of concrete cover is according to the requirements of the drawings and specifications.
11.13
And approve the placing of the reinforcement and form work condition before any concrete is casted.
11.14
The reinforcement in structures are not welded unless permitted by the designer.
11.15
All reinforcement quality and work comply the standard technical specification.
Ministry of Works and Urban Development
Check List for use by Bu ilding Construction Supervisors
12.
MORTAR
CHECK:
12.1
All mortar is if possible mixed in an approved mechanical batch miser. If not possible it could be mixed by hand until its color and consistancy are uniform.
12.2
Lime for mortar is freshly burnt limestone. Lime shall be delivered to the site in large lumps, slaked, run to putty and mature for not less than two weeks before use.
12.3
If hydraulic lime is used, it is stored in the same manner as described for cement.
12.4
Cement used in mortar is port land cement and of quality as described for concrete works.
12.5
Sand for mortar is of quality as described for concrete works.
12.6
Water is of quality described for concrete works.
12.7
Cement mortar consists of cement and sand as specified. If not given in the specification, check that cement mortar consists of one part cement to three parts of sand (1:3) measured by volume.
12.8
Compo mortar consists of cement, lime and sand as specified. If not specified, check that the compo mortar is composed of one part cement two parts of lime and nine parts of sand (1 :2:9) measured by volume.
12.9
Cement mortar is used within 30 minutes of the duration of cement.
13.
STONE MASONARY WALL
CHECK:
13.1
Stone is of type given on specification.
13.2
The stone in hard, sound, free from cracks and decay and not weathered.
13.3
The stone is freshly quarried from an approved quarry.
13.4
The stone masonry execution is with specified mortar and with well finished joints.
13.5
All mortar for stone masonry bedding and jointing is 20mm thick.
13.6
Stone masonry during execution is kept free from solid and other kind of dirt.
13.7
Stone walling is carried up with no portion more than 1000mm above adjacent wall at any one time.
13.8
The wall is in plumb within 3m.
Ministry of Works and Urban Development
18
19
Check List for use by Bu ilding Construction Supervisors
2
13.9
Sample panel of wall not less than 1m in area including joint pointing as specified is prepared and approved.
13.10
The type size and pattern of laying is as detailed on drawing.
13.11
All stone masonry walling comply with the standard technical specification.
14.
HOLLOW CONCRETE BLOCK WALL
CHECK:
14.1
The hollow concrete blocks are free from laminations, cracks and other defects that would impair the proper setting, strength or permanence of the construction.
14.2
The hollow concrete blocks are well compacted, properly cured and uniform colour and texture.
14.3
The hollow concrete blocks manufactured on the site above the quality of cement and aggregate as described for concrete works.
14.4
All blocks are manufactured in an approved special hollow block machine and under shed.
14.5
Before any manufacturing in big scale starts on the site, test samples are made, cured and sent for testing and test results are approved by the designer.
14.6
For curing of hollow blocks, that they are kept moist, at least for seven days after casting.
14.7
That the blocks are properly dried under shade for at least 14 days before they are used for construction.
14.8
Damaged or blocks with defects in the walls are replaced with good ones at the expenses of the contractor.
14.9
Hollow blocks and the walls are kept free from soil and other kind of dirt during execution.
14.10
All joints vertical and horizontal are well filled with specified mortar.
14.11
Walling is carried up with no portion more than 1000mm. above adjacent wall at any one time.
14.12
Partition walls are well bonded to elevations walls.
14.13
That the joints and the walls are in plumb within 3m.
14.14
If the wall in designated as load bearing by the designer and special care in taken for the execution of the work.
Ministry of Works and Urban Development
20
Check List for use by Bu ilding Construction Supervisors
14.15
A minimum of 6 blocks per 1000 pcs. for site manufactured blocks are tested.
14.16
The thickness of the joints do not exceed 15mm.
14.17
The compo mortar is used only above ground level.
14.18
The drawings carefully before any wall construction if extra reinforcement or expansion joints are prescribed.
14.19
The minimum compressive strength class A, class B and class C, hollow concrete blocks in as follows according to the standard technical specification. CLASS
AVERAGE OF 6 BLOCKS
Class A Class B Class C
INDIVIDUAL BLOCKS
48kg/cm2 2 35kg/cm 2 20kg/cm
38 kg/cm2 2 32 kg/cm 2 18kg/cm
14.20 All hollow concrete block walling comply with the standard technical specification. 15. WALLS WITH BRICKS CHECK:
15.1
Bricks are not dumped on site but stocked in regular tires as they are unloaded.
15.2
Bricks to be used for different situations are stocked separately on a clean place.
15.3
Bricks are soaked in water for a minimum period of one hour before use.
15.4
Sample panels of not less than 1m for each type of brick.
15.5
All brick works are laid in good English bond even and true to line plumb within 3m, level and all joints accurately kept.
15.6
All joints vertical and horizontal are well filled with specified mortar.
15.7
The thickness of the joints do not exceed 10mm.
15.8
All bricks of the same dimensions are only used in the same wall.
15.9
Brick samples are taken at random from the load approved also manufacturers test certificate submitted.
15.10
All brick walling comply with the standard technical specification.
2
Ministry of Works and Urban Development
Check List for use by Bu ilding Construction Supervisors
16.
WOODEN WALLS
CHECK:
16.1
The quality and dimensions of wood are according to specifications and drawings.
16.2
All wood for wall are well seasoned, fee from major knots, worms, splits and bends.
16.3
All wood for construction are stored free from the ground and well protected against rain.
16.4
All wood if specified are treated with anti-termite liquid.
16.5
Dimension, placing and number of nails in according to drawings. Unless indicated on the drawing no wood structure shall be joined.
16.6
The wall is plumb and level.
17.
PLASTER AND POINTING
CHECK:
17.1
The cement plaster and compo plaster quality mixture, thickness and type of surface are according to the specification and drawing.
17.2
That cement plaster is used where water effect is expected such as in toilets, laundries and external walls while compo-mortar is used in all cases unless otherwise specified.
17.3
Before any plaster is applied, the wall is thoroughly cleaned from dirt and dust.
17.4
all plaster in mixed in a mechanical mixer of approved type if possible.
17.5
The wall, depending on the material is kept wet for some time before any plaster applied. It's not enough to sprinkle water just before plastering.
17.6
All pointing if prescribed in done with cement mortar.
17.7
All pointing in plumb and level.
17.8
All plastering and pointing comply with the standard technical specification.
18.
STRUCTURAL STEEL WORK
CHECK:
18.1
The shape and size of structural steel members comply with the requirements of the specification and the manufacturers standards.
18.2
Size location, elevation and plumbing of another bolts.
Ministry of Works and Urban Development
21
Check List for use by Bu ilding Construction Supervisors
18.3
Condition and capacity of welding equipment.
18.4
Conformity of electrodes to specifications and correct usage.
18.5
Production and assembly of steel in carried out in accordance with the detail drawings and specifications.
18.6
Steel before and after fabrication is straight and free from twist or other damages.
18.7
Cutting is done by shearing, cropping, sawing or machine flame cutting.
18.8
Cutting by hand operated flame in approved.
18.9
Sheared or cropped edges are dressed to a neat machine work and are prepared for welding finish.
18.10
Welded sections are inspected and approved prior to priming.
18.11
The maximum gap for butt welded section in less that 3mm.
18.12
Each weld in continuous, sound and without interruption and free of creaters.
18.13
Slag in taken away immediately after welding and the weld cleared with metal brush.
18.14
All ends of rectangular, square and circular sections (DHS, CHS) are sealed by welding to prevent ingress of moisture.
18.15
The steel structure is securely bolted to plates, channels or angle cleates during erection.
18.16
Direct bolting to sides of steel hollow sections in not carried on.
18.17
Holes for fixing electrical fittings, partitions etc. … are correctly positioned.
18.18
All structural steel is protected from chemical solutions.
18.19
All structural steel ready to erect is prevented from water or dirt accumulated against any of the surfaces.
18.20
All steel which will have concrete cast against them are clean and free from loose rust at the time of concreting.
18.21
all structural steel work comply with the standard technical specification.
Ministry of Works and Urban Development
22
Check List for use by Bu ilding Construction Supervisors
19.
PAVIOR (TILES PAVIOR)
CHECK:
19.1
Before any paving starts, the mass concrete is completely free from standing water.
19.2
Cement tiles conform with the standards.
19.3
In the mass concrete surface immediately before the bedding is laid, a slurry of cement and water is brushed, unless specified.
19.4
The bedding in of cement mortar, one part cement to four parts sand (1 :4), and the slump in 2-5cm and over.
19.5
the bedding thickness is 2-3cm.
19.6
The tiles are gently knocked down into the bedding so the mortar will be forced up in the joints approximately 5mm.
19.7
When the bedding is hard enough usually after one day the joints which shall be 2-4mm wide are filled with cement mortar.
19.8
Expansion joints are executed as indicated on drawings.
19.9
The complete floor under construction is protected for the first 14 days and kept wet and is protected against damage.
20.
WALL TILES
CHECK:-
20.1
Wall tiles are soaked in clean water before laying and taken out just before use.
20.2
Tiles are bedded with straight joints in cement and sand (1 :3) and grouted in white cement.
20.3
The work when completed is cleaned properly before approval.
20.4
Only tiles free from defects are used for the construction.
21.
P.V.C. TILES
CHECK:
21.1
P.V.C. tiles are laid on floor screeds with approved glue and in accordance with manufacturer's instruction.
21.2 21.3
Only tiles free from defects are used for the construction. Damaged tiles are replaced with good ones at the contractor's expense.
Ministry of Works and Urban Development
23
Check List for use by Bu ilding Construction Supervisors
22.
ROOFING AND CLADDING
CHECK:
22.1
Asbestos cement sheets are free from visible defects.
22.2
The surface of asbestos cement sheet is of uniform texture and smooth on one side.
22.3
The edges of asbestos cement sheets are square, straight and clean.
22.4
Asbestos cement sheet unless otherwise specified is 6mm thick when used for roofing.
22.5
Asbestos cement accessories match the pitch of the sheets.
22.6
Galvanized plain and corrugated sheets comply the manufacturer's specifications.
22.7
Steel hock bolts and nuts are zinc coated, the size and use of which shall be as per manufacturer's instruction.
22.8
Fixing of roofing and flashing is made fully water tight and performed to the standard of best workmanship.
22.9
Chiseler diamond edges and convex bend nails made of mild steel round wires are used to fix galvanized steel sheet roofing and flashing to timber members.
22.10 Steel hock bolts and nuts are used to fix galvanized steel sheets and asbestos roofing to steel and wooden truss members and purlins. 22.11 Fixing holes are drilled in crown of corrugation of roofing sheets. 22.12 Holes are 5mm larger in diameter than bolts or screws. 22.13 Holes are 40mm far from edges of sheet. 22.14 Sheets are laid with laps not less than 150mm. 22.16 Upper laps of sheets are constructed away from prevailing wind. 22.17 No person other than workmen in roofing have access to roof area. 22.18 All roofing work comply with the standard technical specification.
23.
GUTTERS AND DOWN PIPES
CHECK: 23.1 Gutters and down pipes are formed with the specified guage galvanized mild steel flat sheet from suitable lengths and to shapes s hown on the drawings.
Ministry of Works and Urban Development
24
Check List for use by Bu ilding Construction Supervisors
23.2
Gutter hangers hangers and down pipe supports are 2.25mm anti-rust painted painted flat sheet spaced at 1 meter center maximum unless otherwise specified.
23.3
Joints of gutter are lapped 15cm and welded.
23.4
Jointer of gutter gutter after welding treated with three three coats coats of of zinc paint. paint.
24.
CARPENTRY AND JOINERY
CHECK:
24.1
Timber for carpentry and joinery joinery is as specified and of best best quality. quality.
24.2
Timber is reasonably reasonably straight grained and obtained from an approved sources.
24.3
And inspect the timber as as it arrives, an timber timber not approved is removed removed forthwith. forthwith.
24.4
Timber is open open stacked for as long long as possible before before use.
24.5
Timber and assembled wood work are protected from rain and sun.
24.6
Timber and assembled wood work are stored stored in such away as to prevent prevent attack by termites, insects or decayed fungi.
24.7
Timber ready ready for use in free from live borer, beetle or other insect insect attack.
24.8
All measures to eradicate insect attack of timber are approved.
24.9
Timer in seasoned to moisture content content of not more that 20% for Carpentary Carpentary and 12% 12% for joinery.
24.10 All timber surface exposed by cutting are treated with three coats of approved preservations. 24.11 All pressure impregnated timber is treated with preservative preservative chemicals at a pressure pressure of not less than 10 atmospheres and in accordance with the chemical manufacturers instruction. 24.12 Fixed joinery is completely protected from damage until the completion of the construction. 24.13 Profile of sections is not modified from those shown on drawings without without approval. 24.14 Right type of of door is fixed in the right right place and that the doors awing in accordance accordance to the drawings. 24.15 Door frames and window frames are fixed straight and in plumb.
Ministry of Works and Urban Development
25
Check List for use by Bu ilding Construction Supervisors
24.16 Hinges, locks, latches and handles are of approved approved type and properly fixed. 24.17 Window panels are are of the right thickness and properly fixed. 24.18 All carpentry and joinery to comply with the standard standard technical specification. specification. 25.
CEILING
CHECK:
25.1
Material and dimensions are according to the specifications and the drawings.
25.2
Before any mounting, painting of parts in connection with the ceiling such such as steel guides guides and walls, is completed.
25.3
The ceiling in cleaned cleaned and well fixed when when the work is completed. completed.
26.
PAINTING
CHECK:
26.1
The kind of paints in according to the specifications and designer's designer's instructions.
26.2
The painting is done according to the manufacturer's manufacturer's instructions. instructions.
26.3
The paint is not diluted unless specified by the manufacturer.
26.4
All surface surface to be painted is clean clean from from dust and dirt.
26.5
All surface to be painted is absolutely dry and free free from defects before painting. painting.
26.6
All brushes brushes and tins used for painting are clean and and free free from from old old paint.
26.7
The room is closed until the paint dries.
26.8
All electrical appliances, iron iron and brass works works are removed before painting and properly properly re-fixed after painting.
27.
GLAZING
CHECK:
27.1
Frames are fixed straight and in plumb.
27.2
The type and thickness thickness of glass is according to the specifications and drawings.
27.3
The application and proper ness of putty.
Ministry of Works and Urban Development
26
Check List for use by Bu ilding Construction Supervisors
28.
WATER WELL
CHECK:
28.1
The water well is dug according to the specifications and drawings, drawings, if possible dug during the dry season.
28.2
If septic septic tanks, soak away pits and dry latrines are situated nearby nearby and and inform the designer designer to change the position of the wall.
28.3
The water is tested and approved after the digging digging is completed. completed.
28.4
The masonry work is not started before the test result is known and and approved.
29.
WATER SUPPLY LINES
CHECK:
29.1
The dimensions dimensions and types, tubes valves valves and water tower tower is according to the specifications and drawings.
29.2
All valves, unless otherwise specified is buried in the ground to a minimum depth of 30cm.
29.3
All valves are placed according to the drawings.
29.4
Inspect and approve approve the supply supply line before before any back filling starts. starts.
30.
PLUMBING AND SANITARY INSTALLATIONS
CHECK:
30.1
Dimensions and types of pipes, tubes, valves and sanitary ware is according to the specification and drawings.
30.2
All pipes pipes and tubes to be installed in the floor are placed in position.
30.3 30.4
All joints before mass concrete in east. Pipes and tubes tubes are placed in the board board core with minimum 10cm covering covering layer layer of sand or in channels of floors as indicated on the drawings.
30.5
All sanitary ware is properly properly fixed in its correct correct position.
30.6
All connection between sanitary ware and sewer system system is done with the prescribed syphon.
30.7 30.8
All exposed exposed pipes pipes and tubes are well cleaned cleaned and painted as specified. specified. All sanitary work comply with the standard technical specification.
Ministry of Works and Urban Development
27
Check List for use by Bu ilding Construction Supervisors
31.
SEWER SYSTEM
CHECK:
31.1
Dimensions and types of pipes pipes and inspection pits is according according to the specifications and the drawings.
31.2
The excavation measurements of the sewer lines is according to the drawings.
31.3
The excavation is done in straight lines between between the manholes.
31.4
All trenches before pipes are laid.
31.5
Unless otherwise specified, the pipes are laid on a sand bed with a minimum thickness of 10cm and in an absolutely straight line with an even slope of minimum 1 :100 and covering soil layer is minimum 50cm.
31.6
The joining of concrete concrete to pipes is always done with cement mortar, mortar, the joint completely completely filled all around.
31.7
Joining of of asbestos cement pipes is done according to the manufacturer's instruction.
31.8
Inspection pit is according to the drawing before back filling.
31.9
All pipes connected to the inspection pit come approximately on the same level level and check channel formed in concrete at the bottom of the pit.
31.10 Back fill soil is of good quality, free free from stones stones and it is not top soil. 31.11 Back filling is in layers of minimum 20cm, if vibrating or roller machine is used the thickness of the layer can be 40cm unless otherwise specified. 31.12 Each layer of back fill is well rammed and consolidated consolidated with the addition of water water if necessary. 31.13 The correct position of the water water and sewer systems systems and prepare a sketch sketch on the site plan to send to the designer for preparing drawings showing their correct positions as built on site. 31.14 Measure the correct correct lengths of all trenches, of all tubes and and pipes. 32.
SEPTIC TANK AND SOAK AWAY PIT
CHECK:
32.1
Dimension and type of of septic tank tank and soak away pit is according according to the specifications specifications and drawings.
Ministry of Works and Urban Development
28
Check List for use by Bu ilding Construction Supervisors
32.2
The position of septic tank and soak away pit if situated nearby water wells, and inform the designer for the change of the positions.
32.3
Level of overflow pipes between different chambers and inlet and outlet pipes are according to the drawings.
32.4
all plastering in and out, is with cement plaster with thickness and mixture according to specifications and drawings.
32.5
All water proofing is done according to specifications and drawings.
33.
ELECTRICAL INSTALLATIONS
CHECK:
33.1
The electrical installation is approved by EELPA or the designated professional.
33.2
Materials to be used for the installation strictly follow the specifications and the drawings.
33.3
The electrical subcontractor has a valid certificate issued by EELPA before he starts his work and his foreman is competent.
33.4
The conduits are free from defects and cover the wires all the way.
33.5
All switches and outlets are properly fixed according to the drawings.
33.6
The connections of wires are always done in junction boxes.
33.7
All external cables are placed with a minimum 10cm depth in concrete or asbestos cement pipes and 40cm depth in the ground, unless otherwise specified.
33.8
The excavation is in a straight line between the inspection pits.
33.9
The inspection pits are constructed every 30cm unless otherwise specified.
33.10 All trenches before pipes are laid. 33.11 The pipes are laid on a minimum 10cm thick sand bed unless otherwise specified. 33.12 The joining of asbestos cement pipes is done with cement mortar, the joint completely filled around. 33.13 The joining of asbestos cement pipes is done according to the manufacturer's instructions. 33.14 The inspection pits, pipes and joints before back filling. 33.15 The back fill soil is of good quality, free from stones and it is not top soil.
Ministry of Works and Urban Development
29
Check List for use by Bu ilding Construction Supervisors
33.16 The back filling is in layers of minimum 20cm if vibrating or rolled machine is used the thickness of the layer can be 40cm unless otherwise specified. 33.17 Each layer of back fill is well rammed and consolidated with the addition of water if necessary. 33.18 All underground cable joining are done in special water-tight junction box approved by EELPA or designated professional. 33.19 All junction boxes used are placed in the inspection pits. 33.20 Measure the correct lengths of all trenches and cables. 33.21 The correct position of external cables and pits and prepare a sketch on the site plan to send to the designer for preparing drawings showing their correct positions as built on site. 33.22 All electrical installation comply with the standard technical specification. 34.
RETAINING WALLS
CHECK:
34.1
The trench to be free from loose soil, roots and pieces of wood before construction.
34.2
The depth and width of trench to correspond with the drawing.
34.3
All stones are of good and approved quality.
34.4
All stones and the wall are kept free from soil and other kind of dirt during execution.
34.5
No borrow pits are to be opened in the vicinity.
34.6
If expansion joints are executed as on the drawings.
34.7
The mix proportion of mortar.
34.8
All retaining wall construction comply with the standard technical specification.
35.
SITE WORK
CHECK:
35.1
The clearing of buildings is up to 2 meters from elevation walls on all sides, and check thin limit is approved by the designer.
35.2
The clearing for roads, footpaths and parking areas is up to 1 meter from their boundaries and check this limit is approved by the designer.
Ministry of Works and Urban Development
30
Check List for use by Bu ilding Construction Supervisors
35.3
All roots are taken out within the building area, under roads footpaths and parking lots and transported away from the site.
35.4
The place for the down trees and check they are within the building site.
35.5
All top soil is excavated separately.
35.6
And decide the place to pile up the excavated to soil and check it is 2 meters outside the building perimeter.
35.7
And decide the place for the cart away which is not necessary for back filling or terracing.
35.8
All back filling and terracing is done in layers not exceeding 20cm and if vibrating or roller machine is used the thickness must be 40cm.
35.9
Each layer of back filling and terracing is well rammed and consolidated.
35.10 Back filling and terracing is not with top soil. 35.11 All site work comply with the standard technical specification. 36.
ROADS AND FOOTPATHS
CHECK:
36.1
Excavation for roads footpaths is executed to bottom of footpaths is executed to bottom of hard core.
36.2
Back filling for roads and foot paths is done with non expansive selected material.
36.3
All back filling is done in layers not exceeding 20cm and if vibrating or roller machine is used the thickness must be 40cm.
36.4
Each layer of back filling is well rammed and consolidated with addition of water if necessary.
36.5
Before back filling starts the ground is free from top soil, grass, bushes, roots and pieces of wood.
36.6
Stone for hard core is of approved quality.
36.7
All stones in the hard core are of approximately equal size.
36.8
The hard core is well rammed, consolidated and the top tightened with crushed stones or gravel.
36.9
The thickness of hard core is not less than specified.
Ministry of Works and Urban Development
31
Check List for use by Bu ilding Construction Supervisors
36.10 The hard cores as well as the top surface is executed with a minimum slope of 1 :100 towards the sides. 36.11 The top surface is executed with material on the specification or drawings. 37.
DRAIN CHANNELS AND CULVERTS
CHECK:
37.1
Drain channels are according to the measurements on the drawings.
37.2
Drain channels to have a minimum slope of 1 :200, unless otherwise specified.
37.3
Stone channels to be on a bed hard-core or well compacted gravel with joints and pointing in cement mortar (1 :3).
37.4
Channels of half-concrete pipes are on a well compacted layer of fine aggregate with a thickness not less than 10cm.
37.5
Half-concrete pipes are laid in and joined with cement mortar (1 :3).
37.6
Stone channels and culverts are constructed according to the drawings and specifications.
37.7
All pipes are laid so that each one is in contact with the bed throughout the length of its
38.
FENCING AND GATE
CHECK:
38.1
The type of fence and gate are according to the specifications and drawings.
38.2
The foundations of fence and gate is according to the specifications and drawings.
39.
PREPARATION OF PAYMENT CERTIFICATE
39.1
Payment certificate should be prepared on official formats.
39.2
Payment certificates should be prepared in sufficient copies as needed.
39.3
Payment certificates should be signed by : a. the supervisor b. consultant, if there is contract provision for such supervision c. the contractor d. the investor The supervisor shall check payment against: a. arithmetic error b. contract prices c. contract quantities d. contract time
39.4
Ministry of Works and Urban Development
32
Check List for use by Bu ilding Construction Supervisors
e. f. g. h. i.
actual measurement sheets variation orders supplementary agreements validity of performance bond progress reports
40.
INFORMATION ON CONSTRUCTION PROCEDURES
40.1
Check a site book is kept for any construction work and the following information is included: − dates on which excavation, concreting, stripping of form work, back filling, site work has taken place. − acceptance of materials an components − results of tests and measurements − type of cement and aggregate − inspection and measurement reports of t he positioning of reinforcement. − important instruction received. − description of any incidents.
Ministry of Works and Urban Development
33
Check List for use by Building Construction Supervisors
28
Table 8.5.3a Standard Mixes for Ordinary Structural Concrete per 50kg Bags of Cement (ESCP 2 : Part 1: 1983)
Concrete Work
C5
C15
C20
C25
C30
Nominal max. size of Aggregate (mm) Workability Limits to slump that may be expected (mm) Total Aggregate (kg) Fine Aggregate (%) 3 Vol. of finished concrete (m ) Total Aggregate (kg) Fine Aggregate (%) 3 Vol. of finished concrete (m ) Total Aggregate (kg) Fine Aggregate (%) 3 Vol. of finished concrete (m ) Total Aggregate (kg) Fine Aggregate (%) 3 Vol. of finished concrete (m )
Total Aggregate (kg) Fine Aggregate (%) 3 Vol. of finished concrete (m )
40
20
14
10
Medium
High
Medium
High
Medium
High
Medium
High
30-60 640 30-45 0.312 370 30-45 0.200 350 30-35 0.165 265 30-35 0.147
60-120 550 30-45 0.275 330 30-45 0.183 270 30-40 0.155 240 30-40 0.137
20-50 540 35-50 0.277 320 35-50 0.178 280 30-40 0.156 240 30-40 0.137
50-100 480 35-50 0.252 280 35-50 0.160 250 35-45 0.143 215 35-45 0.127
10-30
30-60
10-25
25-50
-
-
-
-
-
-
-
-
255 35-45 0.146 220 35-45 0.130
220 40-50 0.130 195 40-50 0.118
240 40-50 0.137 210 40-50 0.124
200 45-55 0.121 175 45-55 0.110
235 30-35 0.134
215 30-40 0.127
210 30-40 0.124
190 35-45 0.115
195 35-45 0.115
170 40-50 0.106
180 40-50 0.109
150 45-55 0.097
NOTE: To get volumes of fine and coarse aggregates as follows: 1. Calculate the weights of fine and coarse aggregates by using percentages within the given ranges. 2. Calculate the volume of fine aggregate in it, by dividing the weight in kg. 3. Calculate the volume of coarse aggregates in it by dividing the weight in kg. By 1.25.
Ministry of Works and Urban Development
Check List for use by Building Construction Supervisors
29
Table 8.5.3b Standard Concrete Per 50kg. Bag of Cement (ESCP 2 : Part 1: 1983)
Concrete Grade C5
C15
C20
C25
C50
Nominal Max. Size of Agg. (mm) Work Ability Limits to Slump that may be expected (mm) Sand Coarse Agg. Water (Litres) Sand Coarse Agg. Water (Litres) Sand Coarse Agg. Water (Litres) Sand Coarse Agg. Water (Litres) Sand Coarse Agg. Water (Litres)
40 Medium 30-60 5A 7A 48 3A 4A 30 3C 4C 25 2A 3A 23 2B 3B 20
20 High 60-100 6C 7C 48 3B 4B 30 2A 3A 25 2B 3B 23 2C 3C 20
Medium 20-50 6C 7C 48 3B 4B 30 2B 4b 25 2B 3B 23 2C 3C 20
High 50-100 4A 5 48 2B 4B 30 2C 4C 25 2C 3C 23 2B 2B 20
Check List for use by Building Construction Supervisors
29
Table 8.5.3b Standard Concrete Per 50kg. Bag of Cement (ESCP 2 : Part 1: 1983)
Concrete Grade C5
C15
C20
C25
C50
Nominal Max. Size of Agg. (mm) Work Ability Limits to Slump that may be expected (mm) Sand Coarse Agg. Water (Litres) Sand Coarse Agg. Water (Litres) Sand Coarse Agg. Water (Litres) Sand Coarse Agg. Water (Litres) Sand Coarse Agg. Water (Litres)
40 Medium 30-60 5A 7A 48 3A 4A 30 3C 4C 25 2A 3A 23 2B 3B 20
20 High 60-100 6C 7C 48 3B 4B 30 2A 3A 25 2B 3B 23 2C 3C 20
Medium 20-50 6C 7C 48 3B 4B 30 2B 4b 25 2B 3B 23 2C 3C 20
High 50-100 4A 5 48 2B 4B 30 2C 4C 25 2C 3C 23 2B 2B 20
Standard Box Sizes (Sizes in cms)
A - 40x50x20 B - 40x50x18 C - 40x50x16
Ministry of Works and Urban Development
Check List for use by B uilding Construction Supervisors
MINISTRY OF WORKS AND URBAN DEVELOPMENT HANDING OVER THE CONSTRUCTION SITE This _________________________________ date of ___________ 19____ the work for the construction of the _______________________________________________ has been officially handed over to the contractor: MR/ATO ____________________________________________________________________ The Contractor, therefore, acknowledges the taking over of the site and immediately the work with all its explanation clearly defined in the specification and drawings (sketches).
30
30
Check List for use by B uilding Construction Supervisors
MINISTRY OF WORKS AND URBAN DEVELOPMENT HANDING OVER THE CONSTRUCTION SITE This _________________________________ date of ___________ 19____ the work for the construction of the _______________________________________________ has been officially handed over to the contractor: MR/ATO ____________________________________________________________________ The Contractor, therefore, acknowledges the taking over of the site and immediately the work with all its explanation clearly defined in the specification and drawings (sketches). The Contractor, hereinafter, shall be responsible for the damages that occur as a result of his fault, carelessness or negligence in connection with untimely commencement of the work. The Contractor, in addition, acknowledges the completion of the said work shall count as from the date mentioned above and comply with the terms and conditions of the Contract to the Contract to the satisfaction of the Client. IN WITNESS HEREOF THIS DOCUMENT HAS BEEN SIGNED BY ALL PRESENCE IN SIX COPIES
OF
WHICH
THE
CLIENT
HAS
ONE,
THE
SUPERVISOR
ONE,
CONTRACTOR ONE, AND THE BUILDING DESIGN ENTERPRISE THREE.
_____________________________
___________________________
FOR THE CLIENT (EMPLOYER)
THE CONTRACTOR
WITNESS
1. _____________________
1. ___________________
2. _____________________
2. ___________________
3. _____________________
3. ___________________
Ministry of Works and Urban Development
THE
31
Check List for use by B uilding Construction Supervisors
MINISTRY OF WORKS AND URBAN DEVELOPMENT ACQUISITION OF DOCUMENTS PROJECT
:
___________________________________________________
SITE
:
___________________________________________________
EMPLOYER
:
___________________________________________________
CONTRACTOR
:
___________________________________________________
SUPERVISOR
:
___________________________________________________
This is to acknowledge that I have received the following set of documents concerning the project. 1.
CONTRACT DOCUMENT NO.
________________________________________
2.
ARCHITECT DRAWINGS NO.
________________________________________
3.
STRUCTURAL DRAWINGS NO. ________________________________________
4.
ELECTRICAL DRAWINGS NO. ________________________________________
5.
SANITARY DRAWINGS NO.
_________________________________________
6.
BILL OF QUANTITIES
_________________________________________
7.
OTHERS NO.
_________________________________________
DOCUMENT HANDED OVER BY
_________________________________
DOCUMENT RECEIVED BY
________________________________ DATE: ______________________________
Ministry of Works and Urban Development
Check List for use by B uilding Construction Supervisors
MINISTRY OF WORKS AND URBAN DEVELOPMENT REQUISITION FOR MATERIAL TESTING PROJECT
:
____________________________________________________
SITE
:
____________________________________________________
EMPLOYER
:
____________________________________________________
CONTRACTOR
:
____________________________________________________
SUPERVISOR
:
____________________________________________________
REQUIRED TEST
TEST REQUESTED BY
_____________________________________________________ SUPERVISOR
APPROVED BY
_____________________________________________________ CONSULTANT OR DESIGNER
DATE _____________________
Ministry of Works and Urban Development
32
33
Check List for use by B uilding Construction Supervisors
MINISTRY OF WORKS AND URBAN DEVELOPMENT EVALUATION OF TEST RESULT
Contract No. ________________ PROJECT
:
___________________________________________________
SITE
:
___________________________________________________
EMPLOYER
:
___________________________________________________
CONTRACTOR
:
___________________________________________________
SUPERVISOR
:
___________________________________________________
TESTING LAB ________________________________
TEST NO. ___________________
DATE OF TESTING __________________________________________________________ KIND OF MATERIAL TESTED _________________________________________________ ____________________________________________________________________________ SPECIFIED QUALITY ________________________________________________________ ____________________________________________________________________________ TEST RESULT _______________________________________________________________ ____________________________________________________________________________ RECOMMENDATION OF DESIGNER ___________________________________________ ____________________________________________________________________________ ____________________________________________________________________________
MATERIAL ACCEPTED
MATERIAL REJECTED
APPROVED BY : _____________________________________________ CONSULTANT OR DESIGNER C.C To Site Supervisor To Contractor To Employer
Ministry of Works and Urban Development
34
Check List for use by B uilding Construction Supervisors
MINISTRY OF WORKS AND URBAN DEVELOPMENT SOIL IDENTIFICATION AND ACCEPTANCE OF EXCAVATED FOUNDATION DEPTHS
PROJECT
:
_____________________________________________________
SITE
:
_____________________________________________________
EMPLOYER
:
_____________________________________________________
CONTRACTOR
:
_____________________________________________________
SUPERVISOR
:
_____________________________________________________
SOIL TEST REPORT NO. ___________________________ DATE _____________________ Specified Soil Type Test Report
Actual Soil Condition
Specified Depth in Test Report
Recommended Foundation Depth
Remark
RECOMMENDATION OF FOUNDATION ENGINEER ___________________________________________________ ____________________________________________________________________________ INSTRUCTION PASSED TO THE CONTRACTOR
____________________________________________________
_____________________________________________________________________________ ACKNOWLEDGEMENT OF SUPERVISOR _______________________________________ _____________________________________________________________________________
Ministry of Works and Urban Development
35
Check List for use by B uilding Construction Supervisors
MINISTRY OF WORKS AND URBAN DEVELOPMENT SITE DIARY Report No. _____ Date __________ : ____________________________________________________________ Project Site : ____________________________________________________________ : ____________________________________________________________ Employer Contractor : ____________________________________________________________ : ____________________________________________________________ Consultant Site Supervisor : ____________________________________________________________
1. Weather Conditions : Fine _________ Good ________ Bad _______ Lost Hrs. _______ 2. Staff on Site : Project Eng. ________________ Civ. Eng. _______________ Bld. Eng. _______________ Technician _______________ Eng. Aide _______________
Secretary ______________ Clerk _________________ Purchaser ______________ Cashier ________________ Dresser ________________
Driver ____________ Guard ____________ Messenger _________ Cleaner ___________ Others ____________
3. Labour Force Gen. Forman _______________ Gen. Operator _______________ Forman ____________________ Operator ___________________ Mechanic __________________ Welder ____________________
Mason ________________ Carpenter ______________ Barbender ______________ Plumber ________________ Electrician ______________ Helper _________________
Plasterer __________ Painter __________ Chiselled __________ Glazier ___________ Labourer _________ Others ____________
4. Work in progress: __________________________________________________________ ________________________________________________________________________ 5. Materials on Site : _________________________________________________________ ________________________________________________________________________ 6. Equipment on Site : ________________________________________________________ ________________________________________________________________________ 7. Given Instruction __________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ 8. Difficulties and Shortages: __________________________________________________ _________________________________________________________________________ _________________________________________________________________________ 9. Remarks : ________________________________________________________________ ________________________________________________________________________ ________________________________________________________________________
Ministry of Works and Urban Development
Check List for use by Building Construction Supervisors
36
MINISTRY OF WORKS AND URBAN DEVELOPMENT INSPECTION AND PROGRESS REPORT Monthly Report No. ___________________ Month ______________________________ Date _______________________________ Cont. No. ___________________________ Project Title Location Employer Contractor Consultant
: __________________________________ : __________________________________ : __________________________________ : __________________________________ : __________________________________
Region ___________________
1. Date of signing of contract ____________________________ Contract Time _____________________ Commencement Date _________________________________ Completion Date ___________________ Contract amount Birr _________________________________ Elapsed Time ______________________ Amount earned Birr __________________________________ 2. Stage Construction : Variation and values on certificates.
No.
1 2 3 4
Type of Work
Value Out of Total Work
Variation Order No.
Value of (Total)
Total Executed in %
Value of Work Executed This To Date Month
Value of Certificate This Month
To Date
Excavation & Earth works Stone Masonary Works Concrete in foundation Concrete in superstruc.
Ministry of Works and Urban Development
Check List for use by Building Construction Supervisors
No.
5 6 7 8 9 10 11 12 13 14 15 16
Type of Work
Wall Roofing Metal works Carpentry & Joinery Plastering & Screeding Flooring & Screeding Glazing Painting Sanitary Installation Electrical Installation Site Work Others
Value Out of Total Work
37
Variation Order No.
Value of (Total)
Total Executed in %
Value of Work Executed This To Date Month
Value of Certificate This Month
To Date
Check List for use by Building Construction Supervisors
No.
5 6 7 8 9 10 11 12 13 14 15 16
Type of Work
Value Out of Total Work
37
Variation Order No.
Value of (Total)
Total Executed in %
Value of Work Executed This To Date Month
Value of Certificate This Month
To Date
Wall Roofing Metal works Carpentry & Joinery Plastering & Screeding Flooring & Screeding Glazing Painting Sanitary Installation Electrical Installation Site Work Others
REMARK: _________________________________________________________________________________________________________________
Ministry of Works and Urban Development
38
Check List for use by Bu ilding Construction Supervisors
3. Difficulties encountered during the month under review: Major Difficulties By Type
Yes/No
Material shortage Equipment shortage Cash shortage Manpower shortage Weather condition Design Drawing Supervision Others If yes, define type of Material, Equipment, also identify source of cash shortage and profession of
38
Check List for use by Bu ilding Construction Supervisors
3. Difficulties encountered during the month under review: Major Difficulties By Type
Yes/No
Material shortage Equipment shortage Cash shortage Manpower shortage Weather condition Design Drawing Supervision Others If yes, define type of Material, Equipment, also identify source of cash shortage and profession of manpower.
4. Instruction given during the month under review. Instruction
Date
Reference
Design change Quantity variation Suspension Material change Rectification Others REMARKS: ___________________________________________________________________
___________________________________________________________________ ___________________________________________________________________ ___________________________________________________________________ ___________________________________________________________________
Ministry of Works and Urban Development
39
Check List for use by Bu ilding Construction Supervisors
5.
Evaluations (Mark: Poor, Fair, Good, Excellent) a) Quality of work _____________________________ b) Quality of materials __________________________ c) Performance
− Progress ____________________________________________________ − Delivery of materials __________________________________________ − Mobilization of manpower ______________________________________ − Equipment availability _________________________________________ REMARKS: _____________________________________________________________
_____________________________________________________________ _____________________________________________________________ _____________________________________________________________ 6.
Variation Approved (State types and quantities) _____________________________________________________________________ _____________________________________________________________________ _____________________________________________________________________ _____________________________________________________________________
7.
Claims filled (Reasons and duration) _____________________________________________________________________ _____________________________________________________________________ _____________________________________________________________________
8.
Status of Certifications approved Month Previous Month Current Month Difference
Ministry of Works and Urban Development
% Executed
% Time Elapsed
40
Check List for use by Bu ilding Construction Supervisors
General Remarks and Actions to be taken:
_____________________________ Supervisor
___________________________ Supervision Office
_______ ______________________ Date
___________________________ Date
Ministry of Works and Urban Development
Check List for use by Building Construction Supervisors
41
MINISTRY OF WORKS AND URBAN DEVELOPMENT Quarterly Construction Inspection and Progress Report Monthly Report No. ________________ Month ______up to Month __________ Date _____________________________ Cont. No. _________________________ Project Title : _________________________________ : _________________________________ Location Employer : _________________________________ Contractor : _________________________________ Consultant : _________________________________ 1. Date of signing of contract __________________ Commencement Date ______________________ Contract amount Birr ______________________
Region : ____________________
Contract Time _______________ Completion Date _____________ Elapsed Time ________________
2. Stage of construction: Variation and values of certificates.
No.
1 2 3 4 5 6
Type of Work
Value Out of Total Work
Variation Order No.
Value of (Total)
Total Executed in %
Value of Work Executed This Month
To Date
Value of Certificate This Month
To Date
Excavation & Earth works Stone Masonary Works Concrete in foundation Concrete in super structure Wall Roofing
Ministry of Works and Urban Development
Check List for use by Building Construction Supervisors
No.
7 8 9 10 11 12 13 14 15 16
Type of Work
42
Value Out of Total Work
Variation Order No.
Value of (Total)
Total Executed in %
Value of Work Executed This Month
To Date
Value of Certificate This Month
To Date
Metal Works Carpentary & Joinery Plastering & Pointing Flooring & Screeding Glazing Painting Sanitary Installation Electrical Installation Site work Others
REMARKS: ____________________________________________________________________________________________________________ ____________________________________________________________________________________________________________ ____________________________________________________________________________________________________________ ____________________________________________________________________________________________________________
Check List for use by Building Construction Supervisors
No.
7 8 9 10 11 12 13 14 15 16
Type of Work
42
Value Out of Total Work
Variation Order No.
Value of (Total)
Total Executed in %
Value of Work Executed This Month
To Date
Value of Certificate This Month
To Date
Metal Works Carpentary & Joinery Plastering & Pointing Flooring & Screeding Glazing Painting Sanitary Installation Electrical Installation Site work Others
REMARKS: ____________________________________________________________________________________________________________ ____________________________________________________________________________________________________________ ____________________________________________________________________________________________________________ ____________________________________________________________________________________________________________ ____________________________________________________________________________________________________________
Ministry of Works and Urban Development
Check List for use by Building Construction Supervisors
3. Difficulties encountered during the month under review: Major Difficulties By Type
Yes/No
Material shortage Equipment shortage Cash shortage Manpower shortage Weather condition Design Drawing Supervision Others If yes, define type of Material, Equipment, also identify source of cash shortage and profession
Check List for use by Building Construction Supervisors
3. Difficulties encountered during the month under review: Major Difficulties By Type
Yes/No
Material shortage Equipment shortage Cash shortage Manpower shortage Weather condition Design Drawing Supervision Others If yes, define type of Material, Equipment, also identify source of cash shortage and profession of manpower.
4. Instruction given during the month under review. Instruction
Date
Reference
Design change Quantity variation Suspension Material change Rectification Others REMARKS: ________________________________________________________________
________________________________________________________________ ________________________________________________________________ ________________________________________________________________ ________________________________________________________________
Ministry of Works and Urban Development
44
Check List for use by Building Construction Supervisors
5.
Evaluations (Mark: Poor, Fair, Good, Excellent) a)
Quality of work _____________________________
b)
Quality of materials __________________________
c)
Performance
−
Progress ___________________________________________
−
Delivery of materials _________________________________
−
Mobilization of manpower _____________________________
−
Equipment availability ________________________________
REMARKS: ______________________________________________________
_______________________________________________________ _______________________________________________________ 6.
Variation Approved (State types and quantities) _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ ______________________________________________________________
7.
Claims filled (Reasons and duration) _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
8.
Status of Certifications approved Month
% Executed
% Time Elapsed
Previous Month Current Month Difference
Ministry of Works and Urban Development
44
45
Check List for use by Building Construction Supervisors
General Remarks and Actions to be taken
________________________ Supervisor
_______________________ Supervision Office
___________________________ Date
________________________ Date
Ministry of Works and Urban Development
45
46
Check List for use by Building Construction Supervisors
MINISTRY OF WORKS AND URBAN DEVELOPMENT WORK ORDER
Project ___________________________________________________________ Employer ________________________________________________________ Contractor ________________________________________________________ Consultant Or Designer ______________________________________________ Work Order No. __________ Date ____________________ I, We ______________________________________________________________ ___________________________________________________________________ have recommended and instructed the following. ____________________________________________ _____________________________________________ _____________________________________________ _____________________________________________ _____________________________________________ _____________________________________________ _____________________________________________ _____________________________________________ _____________________________________________ _____________________________________________ _____________________________________________ _____________________________________________
SKETCH (Sketched and enclosed drawings should be detailed enough to work out quantities.)
______________________ Consultant or designer
_______________________ Contractor
_______________________ Site Supervisor
C.C: Employer
Ministry of Works and Urban Development
46
Check List for use by Building Construction Supervisors
47
PAYMENT CERTIFICATE ON EXCEL
Ministry of Works and Urban Development
47
48
Check List for use by Building Construction Supervisors
MINISTRY OF WORKS AND URBAN DEVELOPMENT
Site Hand over Inspection Certificate Certificate No. 001
Project : ____________________ Employer : ____________________ Contractor : ____________________ Consultant: ____________________
1. Site
2. Obstruction
3. References :
Location : __________________ Contract No . ________________
-
Surface Soil Surface water Surface slope Adjacent construction Accessibility
- – – – – –
Trees and bushes water supply lines Sewer /drainage lines Electricity lines Telephone lines Road/railway lines Over ground structures Under ground structures Others
– – – – – –
Bench marks/levels _____________________ _____________________ Corner stones Boarder lines _____________________ Water supply connection points _____________________ Electricity connection points _____________________ Sewer/drainage connection points _____________________
_____________________ _____________________ _____________________ _____________________ _____________________ _____________________ _____________________ _____________________ _____________________ _____________________ _____________________ _____________________ _____________________ _____________________
4. Additional Items/Comments :
Following an inspection of the site as per the above listed items the contractor is here by advised to take over the site and proceed with the subsequent Mobilization and site preparation works.
Supervisor : Name __________________ Contractor : Name_________________ Sig. __________________ Sig._________________ Date __________________ Date_________________
Ministry of Works and Urban Development
48
49
Check List for use by Building Construction Supervisors
MINISTRY OF WORKS & URBAN DEVELOPMENT
Site Preparation Inspection Certificate – For Item Location __________________ Certificate No. 002
Project : ________________ Employer : ________________ Contractor : ________________ Consultant: ________________
1. Layout:
– Buildings : – Sewer lines – Area to be cleared off : – Others:
2. Levels
– – – – –
Reference Bench mark(s) : Bottom of Basement Floor(s) : Bottom of Ground Floor(s) : Site Works Other cleared off area :
Location : _________________ Contract No . _______________
________________________ ________________________ ________________________ ________________________ ________________________ ________________________ ________________________ ________________________ ________________________
3. Additional Items/Comments :
Following an inspection of the layout and levels of all buildings, site works, etc. as per the above listed items permission to proceed with the subsequent Excavation/Earth works is hereby Granted/Refused to the contractor.
Supervisor : Name ___________________ Contractor : Name _________________ Sig. ___________________ Sig. _________________ Date ___________________ Date _________________
Ministry of Works and Urban Development
49
50
Check List for use by Building Construction Supervisors
MINISTRY OF WORKS & URBAN DEVELOPMENT
Foundation Excavation Inspection Certificate – For Item Location __________ Certificate No. 003
Project : _________________ Employer : _________________ Contractor : _________________ Consultant: _________________ 1. 2. 3. 4. 5. 6. 7. 8.
9. 10.
Location : __________________ Contract No . ________________
Foundation Layout Width of Excavation Depth of Excavation Method of Excavation Type of Excavation material (s) compared to soil report Foundation levels Type of soil at foundation level Foundation Pits & Trenches Free from – Ground water – Roots and bushes – Backfill or made ground Sides of Pits & Trenches – Safe from damage – Protected with sheeting, strutting & shoring Additional Items/Comments.
____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________
Following an inspection of the layout, width, depth and levels of Foundation Excavations as per the above listed items permission to proceed with the subsequent foundation works is hereby Granted/Refused to the contractor.
Supervisor : Name ________________ Sig. ________________ Date ________________
Ministry of Works and Urban Development
Contractor : Name ___________________ Sig . ___________________ Date ___________________
50
51
Check List for use by Building Construction Supervisors
MINISTRY OF WORKS & URBAN DEVELOPMENT Earthworks Inspection Certificate – For Item Location
_________________
Certificate No. 004
Project : ___________________ Employer :___________________ Contractor : ___________________ Consultant: ___________________
Location : __________________ Contract No ._________________
1. Excavation :-
– Location of Excavation – Method of Excavation – Type of Excavated material (s) : Top – – – –
soil, roots, Thickness of Excavated materials : Slopes & Levels of Excavated Surfaces Necessary Temporary drains provided : No Damage to adjacent areas
____________________________ ____________________________ ____________________________ ____________________________ ____________________________ ____________________________ ____________________________
2. Placement of Excavated Materials :-
– –
Top soil, roots & others to be carted away Materials used for backfilling/terracing
____________________________ ____________________________
3. Filling :-
– Cleanliness of areas to filled – Quality of fill material (s) – Thickness of layers – Type & weight of rollers
___________________________ ___________________________ ___________________________ ___________________________
4. Degree of Compaction :-
– – – – – –
Optimum moisture content Maximum Dry Density Field Dry Density Comparison of Degree of Compaction Specified No. of passes of rollers Correctness of Compaction
5. Protection of Filled areas from Vehicles prior to placement of upper pavement layer
__________________________ __________________________ __________________________ __________________________ __________________________ __________________________ __________________________
6. Additional Items/Comments Following an inspection of the quality of Earthworks as per the above listed items permission to proceed with the subsequent construction/ _____________________/ work is hereby Granted/Refused to the Contractor. Supervisor : Name ______________________ Sig. ______________________ Date ______________________
Ministry of Works and Urban Development
Contractor : Name ____________________ Sig. ____________________ Date ____________________
51
52
Check List for use by Building Construction Supervisors
MINISTRY OF WORKS & URBAN DEVELOPMENT
Material Quality Evaluation Certificate – For Item Location _______________ Certificate No. 005
Project : ______________________ Employer :______________________ Contractor :______________________ Consultant: ______________________ 1. 2. 3. 4. 5.
Testing Laboratory Test No . Date of Testing Kind of Material Tested Required Tests
6. Required/specified qualities 7. Test results 8. Recommendation of supervisor : Material 9. Additional Items/Comments
Location : _____________________ Contract No. ___________________
_____________________________ _____________________________ _____________________________ _____________________________ _____________________________ _____________________________ _____________________________ _____________________________ _____________________________ _____________________________ _____________________________ _____________________________ Accepted / Rejected
Following an evaluation of the submitted ____________ test results as per the above listed items permission to use the material is hereby Granted/Refused to the contractor.
Supervisor : Name _________________ Sig. _________________ Date _________________
Approved by : Name _________________ Sig . _________________ Date _________________
Acknowledged by Contractor : Name _________________ Sig. _________________ Date _________________
Ministry of Works and Urban Development
52
53
Check List for use by Building Construction Supervisors
MINISTRY OF WORKS & URBAN DEVELOPMENT Concrete Work Inspection Certificate – For Item Location : ________________ Certificate No. 006
Project : _______________________ Employer : _____________________ Contractor : _____________________ Consultant: _____________________ 1. 2. 3. 4. 5. 6.
7. 8. 9. 10.
11.
12.
13. 14. 15.
Location : _____________________ Contract No . ___________________
Quality & Age of Cement Quality of Sand/Fine Aggregate Quality of Coarse Aggregate Quality of Water Type of Mixing Hand Mixing – Mechanical Mixing – Mechanical Batch Mixing – Approved Concrete mix : Proportion of Cement : : Sand : Coarse Aggregate Water Cement – Workability/Slump – Flexural Strength – Concrete Test Cubes Required/Not Required – Concrete Placement Pouring Height – No Segregation – Concrete Vibration Not under/over Vibrated – Construction Joints Location Approved – Roughened – Vandexed – Cleaned & Free from Water – Form Work Adequately Braced – Grout-tight – Correct dimension & levels – Cleaned & Oiled – Steel Reinforcement Correct Grade – Correct Sizes – Correct Places – Tolerance – – Concrete Cover/Clearance Correctly bent – Lap Lengths – Clean Steel – Stability of fixed Steel – Correct Welds – Starters Location – Props Built in Items Additional Items/Comments
____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________
Following an inspection of the quality of concrete work as per the above listed items permission to pout concrete is hereby Granted/Refused to the Contractor.
Supervisor : Name ___________________ Sig. ___________________ Date ___________________
Ministry of Works and Urban Development
Contractor : Name ____________________ Sig . ____________________ Date ____________________
53
54
Check List for use by Building Construction Supervisors
MINISTRY OF WORKS & URBAN DEVELOPMENT Masonry work Inspection Certificate – For Item Location ______________ Certificate No. 007
Project : _____________________ Employer : _____________________ Contractor : _____________________ Consultant: _____________________
Location : __________________ Contract No . ________________
1. 2. 3. 4. 5. 6. 7.
Type of Masonry (Stone / HCB / Brick) ____________________________________ Hardness, Soundness & Size of Stone ____________________________________ Manufacturing & Curing of H . C . B . ____________________________________ Cleanliness of Masonry _________________________________________________ Storing of H . C . B . & Bricks __________________________________________ Strength of H . C . B . & Bricks________________________________________ Quality of Mortar Ingredients / Cement, Lime, Sand, Water/ __________________ _________________________________________________________________ 8. Mix proportion of Mortar _______________________________________________ 9. Upper/Lower levels of wall ______________________________________________ 10. Uprightness/Straightness of wall surfaces __________________________________ 11. Correctness of wall corner angles _________________________________________ 12. Masonry bedding/Jointing thickness _______________________________________ 13. Quality of Joint pointing ________________________________________________ 14. Type, size and pattern of masonry laying ___________________________________ 15. Additional Items/Comments Following an inspection of the quality of Masonry Work as per the above listed items permission to proceed with the subsequent construction /_________/work is hereby Granted/Refused to the Contractor.
Supervisor : Name __________________ Sig. __________________ Date __________________
Ministry of Works and Urban Development
Contractor : Name __________________ Sig . __________________ Date __________________
54
55
Check List for use by Building Construction Supervisors
MINISTRY OF WORKS & URBAN DEVELOPMENT Structural Steel Work Inspection Certificate – For Item Location _______________ Certificate No. 008
Project : _______________________ Employer : _______________________ Contractor : _______________________ Consultant: _______________________ 1. Component 2. Steel Members
Quality Shape/Size Straightness Free from :: Twist : Dust/Dirt/Water : Loose Rust : Other Damages 3. Quality/Size of – Plates – Bolts/Nuts – Electrodes 4. Shape/Pattern of Steel Work 5. Condition/Capacity of welding equipment 6. Weld – Type (Fillet, Butt) – Run continuous – Sound – No porosity – Correct Finishing – Slag Chipped – Seal complete 7. Anchor Bolts – Correct Location " Elevation – " Plumbing – 8. Position, Size of Holes for : – Electrical Fittings – Partition – Others 9. Erection – Correctly slung " Lifted – " – Positioned " Bolted/Welded – 10. Painting – Rust Removed – Primed – No. of Coats Applied 11. Additional Items / Comments :
– – – –
Location : ______________________ Contract No . _____________________
_______________________________ _______________________________ _______________________________ _______________________________ _______________________________ _______________________________ _______________________________ _______________________________ _______________________________ _______________________________ _______________________________ _______________________________ _______________________________ _______________________________ _______________________________ _______________________________ _______________________________ _______________________________ _______________________________ _______________________________ _______________________________ _______________________________ _______________________________ _______________________________ _______________________________ _______________________________ _______________________________ _______________________________ _______________________________ _______________________________ _______________________________ _______________________________ _______________________________
Following an inspection of the quality of steel work as per the above listed items permission to proceed with the subsequent construction/ ____________________/work is Granted/Refused to the Contractor.
Supervisor : Name _____________________ Sig. _____________________ Date _____________________
Ministry of Works and Urban Development
Contractor : Name _________________ sig . __________________ Date __________________
55
56
Check List for use by Building Construction Supervisors
MINISTRY OF WORKS & URBAN DEVELOPMENT
Structural timber work Inspection Certificate – For Item Location _______ Certificate No. 009
Project : _____________________ Employer : _____________________ Contractor : _____________________ Consultant: _____________________
1. Component 2. Timber Members : –
3. 4. 5.
6. 7. 8. 9. 10. 11.
Quality – Shape/Size – Free from : Decay : Insects attack : Other damages Type Quality of Timber Treatment Storage protection of Timber Quality / Size of – Nail – Bolts/Nuts – Glue – Other joinery Shape/Pattern of Timber work Quality of Fabrication Quality/location of Joinery Quality of Erection Straightness/Deflection of Timber work Additional Items/Comments:
Location : ___________ Contract No . ________
________________________ ________________________ ________________________ ________________________ ________________________ ________________________ ________________________ ________________________ ________________________ ________________________ ________________________ ________________________ ________________________ ________________________ ________________________ ________________________ ________________________ ________________________
following an inspection of the quality of Timber work as per the above listed items permission to proceed with the subsequent construction/ ______/ work is Granted/Refused to the Contractor.
Supervisor : Name ___________________ Contractor : Name _________________ Sig. ___________________ Sig . _________________ Date ___________________ Date _________________
Ministry of Works and Urban Development
56
57
Check List for use by Building Construction Supervisors
MINISTRY OF WORKS & URBAN DEVELOPMENT Carpentry & Joinery work Inspection Certificate – For Item Location ___________ Certificate No. 0010
Project : ________________________ Employer : ________________________ Contractor : ________________________ Consultant: ________________________
Location : _____________ Contract No . ___________
1. Ceiling Work
– – – – –
Quality/Size of ceiling Material Fixing of ceiling material Type, colour, quality of ceiling painting Quality, procedure of ceiling painting Cleanliness of ceiling
______________________________ ______________________________ ______________________________ ______________________________ ______________________________
2. Doors & Windows
– – – – – –
Location of Door/Windows Quality of Door/Windows materials Type of Doors/Windows Direction of Door/Window swings Straightness & plumbing of Door/Window frames Quality/fixture of Door & Windows : : : :
–
Hinges Locks Latches Handles
Protection of Fixed Joinery from damage
______________________________ ______________________________ ______________________________ ______________________________ ______________________________ ______________________________ ______________________________ ______________________________ ______________________________ ______________________________
3. Additional Items/Comments Following an inspection of the quality of carpentry, Joinery & Glazing work as per the above listed items permission to proceed with the subsequent construction /____________/ work is Granted/refused to the contractor. Supervisor : Name ___________________ Sig. ___________________ Date ___________________
Ministry of Works and Urban Development
Contractor : Name _______________ Sig . _______________ Date _______________
57
58
Check List for use by Building Construction Supervisors
MINISTRY OF WORKS & URBAN DEVELOPMENT Roofing & Cladding Work Inspection Certificate – For Item Location ________ Certificate No. 0011 : ______________________ Project Employer : ______________________ Contractor : ______________________ Consultant: ______________________
Location : _________________ Contract No . _______________
1. Roofing work
– Type/Quality of roof sheet
_________________________
– Thickness of roof sheet
_________________________
– Size/coating of steel hook bolts/nuts
_________________________
– Lapping of sheets : End laps length
_________________________ _________________________ _________________________
Quality of roof fixing/flashing
_________________________
: Side laps length : Direction
–
2. Gutters & Down Pipes :
–
Quality, Size, thickness, coating of : Gutter : Down pipe
–
Quality, Size, thickness, spacing coating of : Gutter hangers __________________________ : Down pipe supports __________________________
–
Lapping of Down pipes
__________________________
–
Quality coating of Gutter joints welding
__________________________
__________________________ __________________________
3. Additional Items/Comment : Following an inspection of the quality of Roofing and cladding work as per the above listed items permission to proceed with the subsequent construction /_______________/ work is Granted/Refused to the Contractor. Supervisor : Name ________________ Sig. ________________ Date ________________
Ministry of Works and Urban Development
Contractor : Name _________________ Sig . _________________ Date _________________
58
59
Check List for use by Building Construction Supervisors
MINISTRY OF WORKS & URBAN DEVELOPMENT Finishing work
Inspection Certificate
– For Item Location ______________ Certificate No. 0012
: __________________ Project Employer : __________________ Contractor : __________________ Consultant: __________________
Location : ________________ Contract No . _____________
1. Plastering Work
– Location of plastering – Quality of plaster :
: Material (cement, lime, sand, water) : Mix proportion – Type of Mechanical Mixer used – Elapsed time of plaster paste – Cleanliness of wall – Wetting of wall prior to plastering – Thickness of plaster – Plumbing & levering of plaster
________________________ ________________________ ________________________ ________________________ ________________________ ________________________ ________________________ ________________________ ________________________
2. Wall Tiling Work
– – – – – – – –
Location of Tiling Readiness of Wall surface Quality of Tile bedding : : Material (cement, sand, water) : Mix proportion Quality of Tile Soaking of Tile before laying Straightness of Tile Joints Grouting of Tile in white cement Cleanliness of Wall Tile
________________________ ________________________ ________________________ ________________________ ________________________ ________________________ ________________________ ________________________ ________________________
3. Floor Tile Work
– Location of Tiling – Readiness of concrete slab surface – Quality of Tile bedding – – – – –
: Material (cement, sand, water) : Mix proportion Quality of Glue for P . V. C. Tile Quality of Tile Straightness of Tile Joints Setting/wetting Time of Floor Tile Cleanliness of Floor Tile
________________________ ________________________ ________________________ ________________________ ________________________ ________________________ ________________________ ________________________ ________________________
4. Glazing work
– – – –
Quality & thickness of glass panes Quality & proper application of Putty Readiness of frame Cleanliness of glass
Ministry of Works and Urban Development
_________________________ _________________________ _________________________ _________________________
59
60
Check List for use by Building Construction Supervisors
– Quality of window panels fixing
_________________________
5. Painting work
– – – – –
Kind & Quality of paint Cleanliness of wall & brushes prior to painting Removal of Electrical Appliances prior to painting Number of coats applied Drying of painted walls & ceilings
________________________ ________________________ ________________________ ________________________ ________________________
6. Additional Items/Comments: Following an inspection of the quality of Finishing work as per the above listed items permission to proceed with the subsequent construction/_____________________/ work is Grant/ Refused to the Contractor.
Supervisor : Name _____________________ Sig. _____________________ Date _____________________
Ministry of Works and Urban Development
Contractor : Name _________________ Sig . _________________ Date _________________
60
61
Check List for use by Building Construction Supervisors
MINISTRY OF WORKS & URBAN DEVELOPMENT Site woks Inspection Certificate
–
For Item Location ___________________ Certificate No. 0013
Project : __________________ Employer : __________________ Contractor : __________________ Consultant: __________________
Location : ____________ Contract No . __________
1. Paved Areas (Roads, parking lots, Foot paths)
– – – – – – –
–
Location of Excavation ______________________ Slopes and Levels of Excavation Surfaces ______________________ Excavation surface free from Top soil Roots and Loose or Softened soil. ______________________ Quality and Degree of Compaction of Fill Material ______________________ Quality and Size of Hard core stone material ______________________ Thickness, placing, ramming and blinding of Hard core layer ______________________ Quality, thickness and degree of compaction of : ______________________ – sub base layer ______________________ – base course layer ______________________ – surface course layer Slopes and Levels or Tope surface layer ______________________
2. Drain Channels and Culverts
– – – – – – –
Location of Channels & Culverts Sizes, Levels & Slopes of Channels And Culverts Type and Quality of Channel's Lining Type, Thickness & Compation of Channels Lining – Bedding Jointing & Pointing of Channel's Lining Quality of Mortar ingredients (cement, sand, water) Mix proportion of Mortar
____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________
3. Retaining Wall
– – – – – – – –
Position, Width and Depth of Foundation Trench Cleanliness of Trench Bottom (roots, loose soil, etc.) Type, Hardness, Soundness, Size and Surface Cleanliness of Stone Quality of Mortar ingredients (cement, sand, water) Mix proportion of Mortar Location and construction of Weep Holes Location & construction of Expansion Joints Correctness of Batter slope
Ministry of Works and Urban Development
____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________ ____________________
61
62
Check List for use by Building Construction Supervisors
4. Fencing & Gate
–
Locating of Fencing & Gate
_____________________
–
Width & Depth of Fence & Gate Foundation Trench/pit
_____________________
–
Cleanliness of Trench or Pit Bottom
_____________________
–
Quality of Fence & Gate Materials (stone, HCB, Steel, etc.)
_____________________
–
Quality of Mortar, if used (ingredients, mix proportion)
_____________________
–
Quality of Concrete if used (ingredients, mix proportion, strength, work ability)
_____________________
–
Quality of Foundation works
_____________________
–
Quality of Work above ground level
_____________________
5. Additional Items/Comments Following an inspection of the site works as per the above listed items permission to proceed with the subsequent work is hereby Granted/Refused to the Contractor.
Supervisor : Name ____________________ Sig. ____________________ Date ____________________
Ministry of Works and Urban Development
Contractor : Name ____________________ Sig . ____________________ Date ____________________
62
63
Check List for use by Building Construction Supervisors
MINUTES
Subject
:
Inspection for Temporary(Provisional) Acceptance
Project and Location _________________________________________________ _________________________________________________ Client ______________________________________________________________ Consultant __________________________ Contractor ______________________ Mooting hold at ______________________ Time __________________________ Date of Inspection ____________________
Present
were
Represented from
1. ______________________________
_______________________________
2. ______________________________
_______________________________
3. ______________________________
_______________________________
4. ______________________________
_______________________________
5. ______________________________
_______________________________
6. ______________________________
_______________________________
7. ______________________________
_______________________________
8. ______________________________
_______________________________
In order to determine the satisfactory completion of the ______________________, the above representatives proceeded with the Inspection and made the following observations.
I ______________________________________ Outline of remarks and/or changes noticed.
_____________________________________________________________________ _____________________________________________________________________ _____________________________________________________________________
Ministry of Works and Urban Development
63
Check List for use by Building Construction Supervisors
64
_____________________________________________________________________ _____________________________________________________________________ _____________________________________________________________________ _____________________________________________________________________ _____________________________________________________________________ _____________________________________________________________________ _____________________________________________________________________ _____________________________________________________________________ _____________________________________________________________________ _____________________________________________________________________ _____________________________________________________________________ _____________________________________________________________________ _____________________________________________________________________ _____________________________________________________________________
We the above representatives hereby our respective signatures witness that:
1.
The Construction of this ___________________________________________ in accordance with plans & specifications.
2.
Outlines of remarks given above is based on our observations and is to be notified as per plan and specification.
3.
Promotion of the provisional acceptance is affected as of ______________________________________________________________.
C.C. __________________________ __________________________ __________________________ __________________________
Ministry of Works and Urban Development
64
65
Check List for use by Building Construction Supervisors
MINISTRY OF WORKS AND URBAN DEVELOPMENT TEMPORARY(PROVISIONAL) ACCEPTANCE
Project
: _______________________________________________
Location
: _______________________________________________
Employer
: _______________________________________________
Contractor : _______________________________________________
Contract :
No.
Date
Amount Eth. B
Basis
A. Main Contract
________
________
_________
_________
B. Suppl. Agreement
________
________
_________
_________
C. Variation Order No. 1
________
________
_________
_________
D.
"
"
"
2
________
________
_________
_________
E.
"
"
"
3
________
________
_________
_________
F.
"
"
"
4
________
________
_________
_________
This _____________ day of __________ 19 ____ by the order of our respect Department and after due notification to all concerned parties, we the undersigned: 1. __________________________ Representing the _________________________ 2. __________________________
"
" _________________________
3. __________________________
"
" _________________________
4. __________________________
"
" _________________________
5. __________________________
"
" _________________________
6. __________________________
"
" _________________________
7. __________________________
"
" _________________________
Have examined: a) Contracts, Drawings and Specifications: b) _________________________________________________________________ c) _________________________________________________________________ and have proceeded with the ascertainment of the completion and Temporary Acceptance of the above project on the bases of the following information: A. Date when the contractor took possession of site ___________________________ B. Agreed length of completion time ______________ Calendar days (working days)
Ministry of Works and Urban Development
65
Check List for use by Building Construction Supervisors
66
C. Commencing date ___________________________________________________ D. Completion date according to contract : _________________________________ E. Actual completion Date : ______________________________________________ F. Total Number of delay ________________________________________________ G. Number of justified days of delay _______________________________________ H. Number of Unjustified days of delay _____________________________________ I. Penalty of ________day Eth. Birr ______________ per day Eth. Birr ___________
ACCOUNT
Total value of work executed and/or material supplied _______________________________
DEDUCTIONS
1. Previous payments _____________________________ 2. Penality ______________________________________ 3. Rebate _______________________________________ 4. _____________________________________________
Total deductions ____________________________ Total amount due to the contractor ______________ Retention money __________% of the total value of work expected payable on the final acceptance __________________________________________ Net Sum Payable to the Contractor ______________ Performance Bond : ________________________________ REMARKS: _________________________________________________________ _________________________________________________________ _________________________________________________________ _________________________________________________________
Ministry of Works and Urban Development
66
67
Check List for use by Building Construction Supervisors
Conclusion:
The date for final acceptance will be _______________________________________ After thorough investigation of the works in all its parts excepting invisible latent defects, we declare that it was executed in accordance with the Drawings and the Specifications in an acceptable manner.
We witness thereof, we have written and signed this temporary acceptance of which one copy is to be issued to the contractor for all practical purposes after due approval.
__________________________
_____________________
Construction Supervisor
Contractor
ATTENDING PARTIES
1. ____________________
2. ________________
3. _________________
4. ____________________
5. ________________
6. _________________
Date ______________________
MINISTRY OF WORKS AND URBAN DEVELOPMENT
Ministry of Works and Urban Development
67
68
Check List for use by Building Construction Supervisors
FINAL ACCEPTANCE
Project Location Employer Contractor
: : : :
_______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________
Contracts
A. Main Contract B. Supp. Agreement C. Variation Order No. 1 D. " " " 2 E. " " " 3 F. " " " 4
No.
Date
________ ________ ________ ________ ________ ________
________ ________ ________ ________ ________ ________
Amount (Birr)
_________ _________ _________ _________ _________ _________
Basis
_________ _________ _________ _________ _________ _________
This _____________ day of __________ 19 ____ by verbal/written order No. _____________ dated _____________ 19 ____ from ________________ we the undersigned: 1. __________________________ Representing the _________________________ 2. __________________________ " " _________________________ 3. __________________________ " " _________________________ 4. __________________________ " " _________________________ 5. __________________________ " " _________________________ Have examined : a) Contracts, Specifications and Drawings; b) The Final Certificate of Measurement and the Report of the Temporary Acceptance; c) _________________________________________________________________ d) _________________________________________________________________ and have proceeded with the ascertainment of good execution and final acceptance of the project, on the bases of the following facts : a. Date of Temporary Acceptance ______________________ b. Date of Final Acceptance___________________________ c. Remarks made during the provisional Acceptance of the works : 1. __________________________________________________________________ 2. __________________________________________________________________ 3. __________________________________________________________________
FINAL EXAMINATION OF THE WORKS:
Ministry of Works and Urban Development
68
69
Check List for use by Building Construction Supervisors
A. Signes of visible defects: The general examination of the works as well as random checks and test made of the different parts of the project have shown: __________________________________________________________________ __________________________________________________________________ __
B. New facts: Since the provisional Acceptance of the works, the following facts have occured:
1. ___________________________________________________________________ 2. ___________________________________________________________________ 3. ___________________________________________________________________ 4. ___________________________________________________________________
C. New Orders:
New orders have been given by us to the
Contractor
on __________ 19___ in view of making good any eventual defects, in the works, specially with regard to the following parts : 1. __________________________________________________________________ 2. __________________________________________________________________ 3. __________________________________________________________________ 4. __________________________________________________________________ D. General remarks: The comparison of the Report of the provisional Acceptance of the works with the present condition of the entire project, the contract and other justificative document has brought up the following remarks: 1. 2. 3. 4.
___________________________________________________________________ ___________________________________________________________________ ___________________________________________________________________ ___________________________________________________________________
ACCOUNT:
Ministry of Works and Urban Development
69
70
Check List for use by Building Construction Supervisors
A. Total Value of the work executed and material supplied ________________________
Eth. Birr
B. D E D U C T I O N S
1. Payments made until Temporary Acceptance ____________________ 2. Payments made after Temporary Acceptance ____________________ 3. Various Deductions : a.________________________ b. _______________________
Total deduction sum due to the contractor. ______________________________
CONCLUSION
Therefore, we do hereby declare that the work has been executed in the principle of good workmanship, and have accepted the project definitely on behalf of ________________________________________________________________
____________________ Owner
Date _______________
____________________ Construction Supervisor
__________________ Contractor
______
Ministry of Works and Urban Development
70
Check List for use by Building Construction Supervisors
71
ACT OF RENOUNCMENT
I, we the undersigned ___________________________________________________ contractor, holder of the construction agreement of ___________________________ hereby declare that the sum of Eth. ________________________________________ ____________________________________________________________________ represents the final balance of all accounts related to the above mentioned works, and that after payment of this sum to us, we renounce formally and for ever to the benefit resulting from any action we might have brought against the ___________________ in connection with the agreement in cause. Any action or claim or reservation that we may take in the future shall be deemed as legally covered by the present Act of Renouncement. Done at ______________________ on ____________________
_____________________
Ministry of Works and Urban Development
71
Check List for use by Building Construction Supervisors
72
APPENDIX 1
GUIDELINE ON CONTROL OF CONSTRUCTION PROJECTS
Ministry of Works and Urban Development
72
Check List for use by Building Construction Supervisors
73
APPENDIX 1 : GUIDELINE ON CONTROL OF CONSTRUCTION PROJECTS
1.
Pre-mobilization Stage
1.1
2.
3.
Pursuant to the signing of the Agreement, the Consultant shall ensure that the Contractor submits the following programs in 3 copies: a.
Project's works schedule
b.
Material Delivery Schedule
c.
On-site availability program for major Equipment
d.
Project Cash-flow (inclusive of proposed utilization of advance fund from the Contract, (if any is involved)
e.
Proposed Project's Organization Chart (inclusive of description of qualifications or supervisory and administrative staff)
1.2
The Employer, consultant and Contractor shall jointly discuss and amend the programs submitted if necessary. The program as amended by all three shall be signed by all three.
1.3
Copies of the adjusted program shall be retained by the Employer, Supervisor and Contractor.
Post Mobilization Stage
2.1
The Consultant shall require to submit Quarterly Work Schedules for following quarters in appreciation of progresses attained during proceeding quarters. These quarterly Work Programs need to be accompanied by related delivery schedules for materials and major equipment.
2.2
The Employer, consultant and contractor shall discuss the quarterly schedules submitted and sign them subsequent to making necessary adjustments to them.
2.3
Copies of adjusted schedule shall be retained by the Employer, Supervisor and contractor.
Site Control
3.1
The consultant shall ensure to be present on site to check and approve that the contractor's performance is generally in accordance to the conditions of contract and will require to make such visits to site as the consultant shall consider necessary to satisfy himself that the works are executed generally according to the contract and otherwise in accordance with good engineering practice. The consultant's site inspection and
Ministry of Works and Urban Development
73
Check List for use by Building Construction Supervisors
74
approval shall be particularly required in respect of (but limited to) the following construction stages: a.
Clearing off site
b.
Levelling and layout of foundation works
c.
Checking of foundation depth
d.
Material quality of : -
e.
sand aggregates water concrete block, bricks, stone limes steel, etc.
Concrete works: - mixes - form works - reinforcement bars
f.
Masonry work at: - foundation level - above ground level - elevation walls
g.
Roofing works: - fabrication and erection of steel and wooden trusses
h.
Finishing works
i.
Submitting progress reports to the investor at least once in a month.
j.
Giving all necessary instructions to the contractor provided that the consultant shall not without the prior approval of the investor give any instructions which in the opinion of the consultant are likely to increase substantially (more than 10%) the cost of the works unless it is not in the circumstances practicable for the consultant to obtain such prior approval.
k.
Issuing certificates for payment to the contractor.
Ministry of Works and Urban Development
74
Check List for use by Building Construction Supervisors
4.
Checking of payment certificates.
m.
Performing any services which the consultant may be required to carry cut under any contract for the execution of the works, including where appropriate the supervision of any specified tests and of the commissioning of the works, provided that the consultant may decline to perform any services specified in a contract the terms of which have not initially been approved by the consultant.
n.
Delivering to the investor on the completion of the works such records and manufacturer's manuals as are reasonably necessary to enable to the investor to operate and maintain the works.
o.
Deciding any dispute or difference arising between the Employer and the contractor and submitted to the consultant for his decision, provided that this service shall not extend to advising the investor following the taking of any step in or towards any arbitration or litigation in connection with the works.
Quarterly Progress Evaluation Meetings
4.1
5.
l.
75
A joint evaluation meeting is to be conducted quarterly in the presence of the following: a.
Employer's representative
b.
Consultant's representative
c.
Contractor
d.
Project site supervisor (if any)
4.2
Official minutes of such meetings shall be recorded, signed and distributed to each participant. Subsequent findings shall be reported back at the next quarterly meeting.
4.3
When deemed necessary evaluation meetings can be called for on monthly or bi-monthly bases.
Provisional Acceptance
The consultant shall conduct inspection and reporting of provisional acceptance of the project. 6.
Final Acceptance
The consultant shall conduct inspection and reporting of final acceptance of project.
Ministry of Works and Urban Development
75
Check List for use by Building Construction Supervisors
76
APPENDIX 2 LIST OF MAJOR DUTIES AND RESPONSIBILITIES OF A RESIDENT ENGINEER (SUPERVISOR )
Ministry of Works and Urban Development
76
Check List for use by Building Construction Supervisors
77
APPENDIX 2 : LIST OF MAJOR DUTIES AND RESPONSIBILITIES OF A RESIDENT ENGINEER (SUPERVISOR) 1.
Maintains, for the duration of contract period, singed copies of contract agreement, technical specifications, bill of quantities, drawings and other referenced standards.
2.
Familiarizes himself with and understands fully the details in the contract documents which include the technical specifications, the general provisions, the special provisions, and any other referenced standards.
3.
Reviews the plans and specifications and other pertinent documents that would be furnished to him for accuracy and completeness.
4.
Evaluates and approves project’s work schedule, material delivery schedule, on-site availability program for major equipment, project cash-flow and proposed project’s organization chart prepared by the contractor to ensure that it is practical and provides for effective and efficient utilization of resources.
5.
Inspects and approves work methods and quality of all materials used in the work for conformity with the contract specifications.
6.
Reviews regularly construction progress schedule to ensure that reasonable close conformity of pre-determined work schedule, plans and specifications are attained and alerting the contractor of possible delays and consequences.
7.
Verifies all measurements and quantity computations.
8.
Arranges periodic and regular site meetings with the designer of the project, the contractor and the project owner.
9.
Consulting with the designer, schedules for testing of materials and submits to him detail field observations on material characteristics with indications on tests required.
10.
Considers and evaluates suggestions and recommendations which may be submitted by the contractor or the project owner and reports them with recommendations to the designer.
11.
Advises the project owner on the need for special inspection or testing other than those referred to in the contract documents.
12.
Keeps a site book and records in it, for the duration of the project such as the following and any other matter relevant to the works: 12.1
Sequence of operations and their accomplishment dates;
12.2
Conditions and qualities of construction works;
Ministry of Works and Urban Development
77
Check List for use by Building Construction Supervisors
12.3
Variations made on the work and subsequent changes in cost;
12.4
Register of Minutes of Meetings;
12.5
Names of the responsible technical staff for the construction of the projects;
12.6
Change in the technical staff;
12.7
Incidences affecting the progress of the construction works;
12.8
Performance errors or faulty workmanship by the contractor or errors in the design and the solution to rectify the same;
12.9
The results of inspections performed by designers and project owner as the case may be;
78
12.10 The date of receipt on site by the contractor of any part of designs or modifications and the persons who delivered them; 12.11 Materials received that do not comply with the contract specifications; 12.12 Delays in operations and their causes; 12.13 Site instructions given to the contractor; 12.14 Comments and clarifications in all matters affecting the execution of the works; 12.15 And all other matters related to the construction works that have caused delays and extra expenses or that have helped for the efficient operations; 12.16 The designer also records in the site book any observations be made and clarifications he gave on the construction works; 12.17 All recordings shall be in Amharic or English and shall be dated and signed. 13.
Keeps a dairy or logbook recording daily activities, occurrences, etc. in accordance with the appropriate forms.
14.
Submits construction monthly, quarterly and annual progress reports to the project owner.
15.
Rejects any work or materials that fail to conform to the contract specifications after the same are thoroughly assessed, and informing the designer of such an action in advance.
Ministry of Works and Urban Development
78
Check List for use by Building Construction Supervisors
79
16.
Suspends that portion of work where in his opinion there is an imminent danger to the safety of the workers, provided, however, such suspension shall obtain the approval of the designer or the consultant.
17.
Examines any proposal submitted by the contractor and advises the project owner and the consultant regarding the same.
18.
Conducts inspection and prepares certificates of completion.
19.
Conducts inspection and prepares certificates of final acceptance of the project.
20.
Accepts works executed and materials delivered on site in conformity with the contract drawings, provisions and technical specifications.
21.
Performs all other duties that may be delegated to him in writing by the consultant.
22.
Performs his duties with a professional standards of conduct, ethical behaviour, integrity and honesty.
Ministry of Works and Urban Development
79