Almohileb Productivity Rates
Home
Almohileb Productivity Rates
generalFull description...
Author:
tharazain
5 downloads
225 Views
207KB Size
Report
DOWNLOAD .PDF
Recommend Documents
Productivity Rates
Standard Productivity Rates - UAEFull description
Productivity Rates
jFull description
Productivity Rates
Productivity Rates
Productivity Rates
Productivity RatesFull description
Productivity Rates-Downloaded From Planning Planet
downloadedFull description
Rates
Full description
Mep Productivity Rates: S.N0 Activity Productivity norms Qty Units Electrical/Elv
MEP Productivity RatesFull description
Rates Radionic
Descripción completa
Productivity Index
fsfsFull description
Reaction Rates
Full description
Radionics Rates
These are workouts Based on the principle of Magneto Geometrical Application.
Qui Rates
Descripción: qUIRATES
Production Rates
Man power production ratesFull description
Productivity Techniques
Full description
Productivity Planner
Productivity Planner
Productivity Rate
hbhbDescrição completa
green productivity
green productivityFull description
Construction Productivity
constructionFull description
Productivity Rate
hbhbFull description
Productivity Planner
Productivity PlannerFull description
Productivity Rate
Productivity RateFull description
Productivity Questionnaire
Productivity Quotes
Quotes about productivity
Productivity Rate
Details in productivityFull description
AL-MOHILEB GROUP Almohileb For Contracting
PLANNING & CONTROL DEPT.
PRODUCTIVITY RATES 1- SITE WORK Excavation
Activity
No.
M. P ( Gangs)
Equipments
Unite
Rate
1
Soft Soil (Hand Tools)
1H
Hand Tool s
M3/Day
3
2
Hard Soil (Hand Tools)
1H
Hand Tool s
M3/Day
1
3
Soft Soil
-
Shovel
M3/Hr
40
4
Hard Soil
-
Shovel
M3/Hr
25
5
Soft Soil
-
JCB
M3/Hr
20
6
Hard Soil
-
J.C.B.
M3/Hr
10
-
Shovel
M3/Hr
30
1H
Ro ll ll er er Co Co mp mp.
M2/Day
100
-
Shovel
M2/Hr
100
1H
Rolle oll err Comp Comprr.
M2/Da /Day
200
Backfilling 1
Filling in foundation, plinth
2
Level, Compaction
3
Spreading 250mm layer
4
Compaction 250mm layer
Cement Tiles 1
Laying Tiles
1 M +1 H
M2/Day
45
2
Tiles on curved lines
1 M +1 H
M2/Day
30
M2/Da /Day
200
Interlock Paving 1
Compaction / Levelling
2H
2
Spreading Sand and Brushing
2H
M2/Day
200
3
Laying Tiles
1M+1H
M2/Day
60
1H
R.M/Day
10
Rolle oll err Comp Comprr.
Precast KerbStone 1
Excavation & Blinding for Kerbstone
2
Laying Kerbs
1M+1H
R.M/Day
35
3
Karb stone on curved lines
1M+1H
R.M/Day
20
2 - CONCRETE CONCRETE FORMWORK " Shuttering " 1
Shutt. of Blinding
1C+1H
M2/Day
20
2
Shutt. of Raft & Isolate Footing
1C+1H
M2/Day
15
Shutt. of Column Necks
1C+1H
M2/Day
6
3
Shutt. of Wall
1C+1H
M2/Day
14
4
Shutt. of Column
1C+1H
M2/Day
10
5
Shutt. O Connectionf Beam
1C+1H
M2/Day
12
6
Shutt. of Floor Slab
2C+1H
M2/Day
20
7
Shutt. of Lintel
1C+1H
M2/Day
8
8
Shutt. of Parapet
1C+1H
M2/Day
12
9
Expansion Joints / Ground Slab
1C+1H
L.M/Day
70
10
Shutt. of Beam & Column for H
1C+1H
M2/Day
8
11
Shutt. of Staircase
1C+1H
M2/Day
12
12
De-shuttering De-shuttering Works (Cleaning & Arrangement Arrangement )
≥
4m
40% more than Shuttering Works
REINFORCEMENT " Cut & Bend & Fix " 1
Reinf. of Raft & Isolate Footing
1 SF + 1 H
KG/Day
500
2
Reinf. of Wall
1 SF + 1 H
KG/Day
400
Reinf. of Column
1 SF + 1 H
KG/Day
350
3
4
Reinf. ofConnection Beam
1 SF + 1 H
KG/Day
300
5
Reinf. of Floor Slab (Solid & Hollow Block )
1 SF + 1 H
KG/Day
400
6
Reinf. of Lintel
1 SF + 1 H
KG/Day
200
7
Reinf. of Parapet
1 SF + 1 H
KG/Day
300
8
Reinf. of Staircase
1 SF + 1 H
KG/Day
300
CASTING CONCRETE "Readymix" 1
Cast. Blinding 15cm, 10cm
1C+3H
Pump
FOR ALL CASTING DAY
2
Cast. Of Col. & Wall & Staircase
2C+3H
Pump
FOR ALL CASTING DAY
3
Cast. Of Slab and Beams
2C+4H
Pump
FOR ALL CASTING DAY
4
Cast. of Lintel & Parapet
1C+2H
Pump
FOR ALL CASTING DAY
3 - MASONRY BLOCK WORK 1
Solid Block
2M+1H
Nos./Day
200
2
Hollow Block
2M+1H
Nos./Day
250
4- PLASTER Internal Plaster 1
Ceiling Plaster
1M+1H
M2/Day
10
2
Wall Plaster up to 3m Height
1M+1H
M2/Day
20
3
Wall Plaster 3m to 6m Height
1M+2H
M2/Day
17
4
Fixing of Plaster Mesh
1C+1H
Rm/Day
90
5
Fixing of Corner Beed
1M+1H
Rm/Day
30
Wall Plaster up to 3m Height
1M+1H
M2/Day
20
2
Wall Plaster 3m to 6m Height
1M+2H
M2/Day
18
3
Wall Plaster above 6m Height
1M+2H
M2/Day
15
External Plaster 1
5- TILING Mosaic 1
Floor Mosaic Tiles
1M+1H
M2/Day
15
2
Mosaic Skirting
1M+1H
Rm/Day
40
Fixing of Ceramic Wall Tiles (Glur Type)
1M+1H
M2/Day
10
2
Grouting of Ceramic Wall Tiles
1M+1H
M2/Day
30
3
Fixing of Ceramic Floor Tiles 20x20cm
1M+1H
M2/Day
12
4
Fixing of Ceramic Floor Tiles 30x30cm
1M+1H
M2/Day
15
5
Fixing of Ceramic Floor Tiles 50x50cm
1M+1H
M2/Day
20
6
Grouting of Ceramic Floor Tiles
1M+1H
M2/Day
40
7
Ceramic Skirting
1M+1H
Rm/Day
30
Marble & Stone Wall (Mec. Fixing )
1M+1H
M2/Day
8
2
Marble & Stone Floor
1M+1H
M2/Day
15
3
Marble Skirting
1M+1H
Rm/Day
30
4
Marble Steps (Riser & Treads)
1M+1H
Rm/Day
10
1 FM + 1 H
M2/Day
30
1P
M2/Day/C oat
150
Ceramic 1
Marble & Stone 1
5- False Ceiling 1
False Ceiling - Suspended Type (Tiles&Board&Alu.)
6- Painting Normal Paint 1
Primer
2 3 4
Stucco (Putty) Emulsion Paint Oil Paint
1P
M2/Day/C oat M2/Day/C oat M2/Day/C oat
1P 1P
NOTS : One Day is considered as 8 working hours C=Carpenter; M=Mason; P=Painter; SF=Steel Fixer
Prepared By : Eng/ Mohammed Farag
40 50 30
* * * *
×
Report "Almohileb Productivity Rates"
Your name
Email
Reason
-Select Reason-
Pornographic
Defamatory
Illegal/Unlawful
Spam
Other Terms Of Service Violation
File a copyright complaint
Description
×
Sign In
Email
Password
Remember me
Forgot password?
Sign In
Our partners will collect data and use cookies for ad personalization and measurement.
Learn how we and our ad partner Google, collect and use data
.
Agree & close